Вы находитесь на странице: 1из 3

+

i .

COMMERCIAL ENGINE
BULLETIN

EXPORT CONTROLLED

Rolls-Royce

ENGINE - N2 SHAFTING REPLACEMENT


1.

PLANNING INFORMATION
A.

Effectivity
(1)

Engines
This Commercial Engine Bulletin (CEB) has effect on all Rolls-Royce M250-B17, -B17F,
-C20, and -C20R Series engines.

(2)
B.

Spares - Affected

Reason
The purpose of this CEB is to improve the misalignment capability of the N2 shafting with the
introduction of the following two new parts:
-Turbine Shaft to Pinion Gear Coupling (P/N M250-10415)
- Power Turbine Outer Shaft (P/N M250-1 0416)

C.

Description
At next overhaul, or repair activity where the power turbine outer shaft is removed, a new power
turbine outer shaft and turbine shaft to pinion gear coupling must be installed. These two parts
must be installed together and must NOT be installed in any combination with earlier part
numbers.

D.

Approval
Technical aspects are FAA approved.

E.

Compliance
Compliance Code 4: To be complied with the next time the affected module or component is at
an authorized repair/overhaul facility and the power turbine rotor is disassembled for any
reason.

F.

Interchangeability
All changes specified in this CEB must be incorporated simultaneously.
(1)

The new turbine shaft to pinion gear coupling (P/N M250-1 0415) and the new power
turbine outer shaft (P/N M250-1 0416) must always be used together.

NOTE:
(2)
G.

The turbine shaft to pinion gear coupling is now symmetrical with the identifiable
scallops on both ends and can be installed in either direction.

New P/Ns M250-10415 and M250-10416 must NOT be used in any combination with
earlier part numbers.

Material Availability
NEW P/N

NAME

QTY/ENG

M250-10415

Turbine Shaft to Pinion Gear Coupling

M250-1 0416

Power Turbine Outer Shaft

April14, 2014

M250-C20 Series
M250-C20R Series
M250-B17 Series
M250-B17F Series
COPYRIGHT 2014 Rolls-Royce Corporation

CEB-1414
CEB-72-41 02
TP CEB-1351
TP CEB-72-2099
Page 1 of 3

Rolls-Royce

EXPORT CONTROLLED

COMMERCIAL ENGINE BULLETIN


H.

Tooling
(1)

Fixture-pressure test, power turbine rotor (23006303-1 ).

I.

Weight and Balance - Not affected

J.

Electrical Load Data- Not affected

K.

References
(1)

Advance Engineering Memorandum (AEM), CW50001831 0132.

NOTE:

The document above is referenced for the internal use of Rolls-Royce only.

(2)

1OW2 Operation and Maintenance Manual, Turboshaft Models M250-C20, -C208, -C20F,
/
/
-C20J, -C20S, -C20W (OMM).

(3)

1OW3 Overhaul Manual, Turboshaft Models M250-C20 (OHM).

(4)

1OW4 Illustrated Parts Catalog, Turboshaft Models M250-C20, -C20B, -C20C, -C20F,
-C20'), -C20S, -C20''Jl (I PC).

(5)

11W2 Operation and Maintenance Manual, Turboprop Models M250-B17, -B17B, -B17C,
-B17D, -B17E (OMM).

(6)

11W3 Overhaul Manual, Turboprop Models M250-B17 (OHM).

(7)

11W4111ustrated Parts Catalog, Turboprop Models M250-B17, -B17B, -B17C, -B17D,


-B17E (IPC).

(8)

CSP 21007 Operation and Maintenance Manual, Turboshaft Models M250-C20R,


-C20R/1, -C20R/2, -C20R/4 (OMM).

(9)

CSP 21008 Operation and Maintenance Manual, Turboprop Models M250-B17F, -B17F/1,
-B17F/2 (OMM).

,..

(1 0) CSP 23007 Illustrated Parts Catalog, Turboshaft Models M250-C20R, -C20R/1, -C20R/2,
-C20R/4 (IPC).
(11) CSP 23008111ustrated Parts Catalog, Turboprop Models M250-B17F, -B17F/1, -B17F/2
(I PC).
(12) GTP 5232-3 Overhaul Manual, Turboshaft Models M250-C20R (OHM).
(13) GTP 5243-3 Overhaul Manual, Turboprop Models M250-B17F (OHM).

2.

L.

Other Publications - Not affected

M.

Prerequisites - None

ACCOMPLISHMENT INSTRUCTIONS

B.

Disassembly of the Power Turbine.


(1)

Remove the power turbine shaft to pinion gear coupling (Ref. OHM).

(2)

Remove the power turbine outer shaft (Ref. OHM).

Assembly of the Power Turbine.


(1)

Install the new power turbine outer shaft (M250-1 0416) (Ref. OHM).

(2)

Install the new power turbine shaft to pinion gear coupling (M250-1 0415) (Ref. OHM).

NOTE:
April 14, 2014

The new turbine shaft to pinion gear coupling is now symmetrical and can be installed
in either direction.
M250-C20 Series
M250-C20R Series
M250-B17 Series
M250-B17F Series
COPYRIGHT 2014 Rolls-Royce Corporation

CEB-1414
CEB- 72-41 02
TP CEB-1351
TP CEB-72-2099
Page 2 of 3

.l
f

Rolls-Royce

EXPORT CONTROLLED

COMMERCIAL ENGINE BULLETIN


(3)

Do the pressure test.


(a)

C.

A new detail for the power turbine rotor pressure test fixture (23006303-1) will be
needed to accommodate the reduced ID of the new power turbine outer shaft during
the pressure test called out in the overhaul manual.

Record compliance with this CEB in the applicable section of the engine logbook, engine
assembly (white pages), Part Ill, Modification Record and the Component Accessory Record
Card as applicable with the following:
M250-C20 Series
M250-C20R Series
M250-B17 Series
M250-B17F Series

D.
3.

CEB-1414
CEB-72-41 02
TP CEB-1351
TP CEB-72-2099

Basis for quantities is per engine assembly.

MATERIAL INFORMATION
A.

Configuration Chart

NEW P/N

QTY/
ENG

M250-10415

M250-10416

INSTRUCTIONS/ I
DISPOSITION .

OLD P/N

QTY/
ENG

Turbine Shaft to Pinion


Gear Coupling

6870832

1' 2

Power Turbine Outer Shaft

23037413

1' 2

NAME

INSTRUCTIONS/DISPOSITION NOTES:
1.

New Item.

2.

Remove and replace.

CUSTOMER SUPPORT
ROLLS-ROYCE

April14, 2014

M250-C20 Series
M250-C20R Series
M250-B17 Series
M250-B17F Series
COPYRIGHT 2014 Rolls-Royce Corporation

CEB-1414
CEB-72-41 02
TP CEB-1351
TP CEB-72-2099
Page 3 of 3

Вам также может понравиться