ConstructionProjectBidReview
*Includesclarificationsrequestedat
30MAR16FACCOMMeeting(italicized)
FacilitiesCommitteeMeeting
March30,2016
(Updated March 31,2016)
AGENDA
FacilitiesImprovementsUpdate
NewtownMiddleSchoolBidReview/Recommendations
HollandMiddleSchoolBidReview/Recommendations
CapitalImprovementsProjectUpdate
(20APR16FACCOMAgendaItems)
FinalAccountingofNOCConstruction
2016SummerProjectsBidReview/Recommendations
HollandESToiletRoomFloorTileRepairs
AramarkCustodialFees1,3,and5YearProposal
PublicComments
Facilities
Improvements
Update
NewtownMiddleSchool
SitePlanSketch
NewtownMS 1stFloorPlanSketch
NewtownMS 2ndFloorPlanSketch
NewtownMiddleSchool
ConstructionProjectBidReview
BidsopenedMarch1&3,2016
Goodcompetition Minimum4bidsforeachofthemajor
contracts
Projectunderbudgetandonschedule
LEEDGold,sustainable,energyefficientbuilding
Valueaddedalternatesincorporatedfordurabilityand
maintainability
Ontracktoreceive$2MinACEGrantFunds
OntracktoreceivePDEreimbursement
NewtownMiddleSchoolProject
BidResults
NewtownMiddleSchoolProject
Budget vs.BidResults
Budget
ConstructionCosts
$49,704,672
FinancingCosts
$1,148,673
Contingencyforunforeseens
$2,274,562
Fees,Permits,Testing,etc.
$5,054,403
FF&E
$400,000
ProjectBudgetwithoutACEGrant $58,582,310
LEEDGoldACEGrantachievablethough
projectdesignandconstruction
$2,000,000
TotalProjectCost,ExcludingFinancing $55,433,637
Actual
$46,298,250
$917,899
$2,191,275
$4,713,027
$1,700,000
$55,820,451
$2,000,000
$52,902,552
BidAlternatesReview
RecommendedAlternates
RecommendedAlternates
Engineeredstonefillforbuildingpad
$320,000
Constructionactivitiescancontinuefollowingstormevents.Clean,compactedfillbeneathbuildingslab.
AlternateGarlandroofw/25yr.warranty
$288,000
Upgradedroofwithadditional5yearwarranty;LEEDcompliance
AlternatebuildingmonitoringsystemcontrolsandHVACequipment
BMScontrolsandequipmentbyJCIinlieuofTrane/Siemens
Solarroofpanels
Offset3%ofbuilding'selectricuse,teachingtool
Extendedwarranty(allprimes)
Increaseperiodfrom1yearto2yearsvalueasthereiscomplexequipmentandBMS
Installsodinlieuofgrassinselectareas
Eliminatesearthfromenteringthebuildingandestablisheslawnatbuildingfrontwherefoottrafficismostanticipated
Upgradelockerdoors
$(110,000)
$198,000
$102,000
$58,000
$2,800
Durabilityandextendedlifeoflockers
Outdoorcafeteriaseating
$83,000
Additionaloutdoorseatingforstudents;programrequirementthatwillprovideforopportunitiesforthestudents
MillandOverlayGreenLane
Roadisdeterioratedandwilllikelycontinuetodosoduringconstruction
Sanitarylinereplacement(required)
RequiredinordertoobtaintheproperapprovalsfortheProject
Lightningprotectionsystem
$87,000
$32,000
$99,000
Protectionforthebuildingandexpensiverooftopequipment
TotalAlternates
$1,159,800
BidAlternatesReview
AlternatesNotRecommended
AlternatesNotBeingRecommended
DeleteFour(4)Classrooms
BasebidincludesDistrictrequirementfor7Learningteams
AlternateFloorFinishes
Lessdurable/lesserqualityfloorfinisheswithashorterlifecycle
AlternateLightFixtures
Addedcostwithlittlevalue
TotalAlternatesNotBeingRecommended
$(391,000)
Varies
$19,900
$(371,100)
GeneralConstructionBids
MechanicalConstructionBids
ElectricalConstructionBids
PlumbingConstructionBids
EnvironmentalAbatementConstructionBids
NewtownMiddleSchoolProject
Budget vs.BidResults
Budget
ConstructionCosts
$49,704,672
FinancingCosts
$1,148,673
Contingencyforunforeseens
$2,274,562
Fees,Permits,Testing,etc.
$5,054,403
FF&E
$400,000
ProjectBudgetwithoutACEGrant $58,582,310
LEEDGoldACEGrantachievablethough
projectdesignandconstruction
$2,000,000
TotalProjectCost,ExcludingFinancing $55,433,637
Actual
$46,298,250
$917,899
$2,191,275
$4,713,027
$1,700,000
$55,820,451
$2,000,000
$52,902,552
NewtownMiddleSchoolProject
SummaryofSquareFootCosts
NewtownAchievements
Projectunderbudgetandonschedule
LEEDGold,sustainable,energyefficientbuilding
Valueaddedalternatesincorporatedfordurability
andmaintainability
NewtownMS
NextSteps
March31,2016:
Awardbidsandalternates
ApprovePlanConF,AttachmentC,PlanConG,andPlanConHdocuments
AwardConstructionTestingandConstructionWasteManagementContracts
May2016 Groundbreaking
June2016 Constructionbegins
June2018 Newbuildingcomplete
August2018 Studentsoccupynewschool
June2019 Demolitionandfieldscomplete
NewtownDiscussion
HollandMiddleSchool
SitePlanSketch
HollandMS 1stFloorPlanSketch
HollandMS 2ndFloorPlanSketch
HollandMiddleSchool
ConstructionProjectBidReview
BidsopenedMarch29,2016
Goodcompetition Minimum5 bidsforeachofthemajor
contracts
Projectunderbudgetandonschedule
LEEDGold,sustainable,energyefficientbuilding
Valueaddedalternatesincorporatedfordurabilityand
maintainability
Ontracktoreceive$2MinACEGrantFunds
OntracktoreceivePDEreimbursement
Holland MiddleSchoolProject
BidResults
Holland MiddleSchoolProject
Budgetvs.BidResults
Budget
ConstructionCosts
$43,488,168
FinancingCosts
$1,045,526
ReserveContingencyforunforeseens
$3,482,930
ReserveFees,Permits,Testing,etc.
$4,905,178
FF&E
$400,000
ProjectBudgetwithoutACEGrant $53,321,802
LEEDGoldACEGrantachievablethough
projectdesignandconstruction
$2,000,000
TotalProjectCost,ExcludingFinancing $50,276,276
Actual
$40,827,400
$785,077
$2,482,930
$4,905,178
$1,700,000
$50,700,585
$2,000,000
$47,915,508
BidAlternatesReview
RecommendedAlternates
RecommendedAlternates
AlternateGarlandroofw/25yr.warranty
$(50,000)
Upgradedroofwithadditional5yearwarranty;LEEDcompliance
AlternatebuildingmonitoringsystemcontrolsandHVACequipment
BMScontrolsandequipmentbyJCIinlieuofTrane/Siemens
Solarroofpanels
Offset7%ofbuilding'selectricuse,teachingtool
Engineeredstonefillforbuildingpad
$(115,000)
$450,000
$150,000
Constructionactivitiescancontinuefollowingstormevents.Clean,compactedfillbeneathbuildingslab.
Installsodinlieuofgrassinselectareas
Eliminatesearthfromenteringthebuildingandestablisheslawnimmediately
Upgradelockerdoors
$22,000
$1,200
Durabilityandextendedlifeoflockers
Outdoorcafeteriaseating
$32,000
Additionaloutdoorseatingforstudents;programrequirementthatwillprovideforopportunitiesforstudents
DeleteWoodPanelingatLobbyArea
Moredurable,sustainablewallfinish,withaccessibilitytoutilitieslocatedinceiling
UseofSteelRailingSystematLearningStair
Moredurableandlesssusceptibletodamage/vandalism
CrosswalkatBuckRoad
$(191,000)
$(45,000)
$82,000
MustbeacceptedasthisisapartofLandDevelopmentrequirements
Lightningprotectionsystem
$75,800
Protectionforthebuildingandexpensiverooftopequipment
TotalAlternates
$412,000
BidAlternatesReview
AlternatesNotRecommended
AlternatesNotBeingRecommended
DeleteFour(4)Classrooms
BasebidincludesDistrictrequirementfor7Learningteams
AlternateFloorFinishes
Lessdurable/lesserqualityfloorfinisheswithashorterlifecycle
ReducetheSizeofFrontCanopy
Providesadryzoneforstudentdropoff,demarcationforcarstacking,anddefinestheschoolentry
RemoveTabletArmsfromMezzanineSeating/LGI
AreaservesLGIkeeptabletarmstoprovideadesksurfaceforstudents
SalvageExistingBleachersforAuxiliaryGym
$(416,300)
Varies
$(175,000)
$(7,400)
$(7,000)
Bleachersareover40yearsoldandattheendoftheirusefullife
AlternateAuditoriumSeating
Physicalsampleswereunavailableforseatingcanbereconsideredatalaterdate
TotalAlternatesNotBeingRecommended
$(14,000)
$(619,700)
GeneralConstructionBids
MechanicalConstructionBids
ElectricalConstructionBids
PlumbingConstructionBids
EnvironmentalAbatementConstructionBids
Holland MiddleSchoolProject
Budgetvs.BidResults
Budget
ConstructionCosts
$43,488,168
FinancingCosts
$1,045,526
ReserveContingencyforunforeseens
$3,482,930
ReserveFees,Permits,Testing,etc.
$4,905,178
FF&E
$400,000
ProjectBudgetwithoutACEGrant $53,321,802
LEEDGoldACEGrantachievablethough
projectdesignandconstruction
$2,000,000
TotalProjectCost,ExcludingFinancing $50,276,276
Actual
$40,827,400
$785,077
$2,482,930
$4,905,178
$1,700,000
$50,700,585
$2,000,000
$47,915,508
Holland MiddleSchoolProject
SummaryofSquareFootCosts
HollandAchievements
Projectunderbudgetandonschedule
LEEDGold,sustainable,energyefficientbuilding
Valueaddedalternatesincorporatedfordurability
andmaintainability
HollandMS
NextSteps
March31,2016:
Awardbidsandalternates
ApprovePlanConF,AttachmentC,PlanConG,andPlanConHdocuments
AwardConstructionTestingContract
May2016 Groundbreaking
June2016 Constructionbegins
June2016toAugust2018 Phasedcompletionofbuilding
renovationsandadditions
August2018 Studentsoccupyallnewareas
October2018 Finalsiteworkcomplete
HollandDiscussion
TotalProjectsComparison
Budgetvs.BidResults
NewtownMiddleSchool
ConstructionCosts
FinancingCosts
Contingencyforunforeseens
Fees,Permits,Testing,etc.
FF&E
ProjectBudgetwithoutACEGrant
LEEDGoldACEGrantachievablethough
projectdesignandconstruction
TotalProjectCost,ExcludingFinancing
HollandMiddleSchool
ConstructionCosts
FinancingCosts
ReserveContingencyforunforeseens
ReserveFees,Permits,Testing,etc.
FF&E
ProjectBudgetwithoutACEGrant
LEEDGoldACEGrantachievablethough
projectdesignandconstruction
TotalProjectCost,ExcludingFinancing
Budget
$49,704,672
$1,148,673
$2,274,562
$5,054,403
$400,000
$58,582,310
$2,000,000 $2,000,000
$55,433,637 $52,902,552
Budget
$43,488,168
$1,045,526
$3,482,930
$4,905,178
$400,000
$53,321,802
Actual
$40,827,400
$785,077
$2,482,930
$4,905,178
$1,700,000
$50,700,585
$2,000,000 $2,000,000
$50,276,276 $47,915,508
Budget
GRANDTOTAL:
Actual
$46,298,250
$917,899
$2,191,275
$4,713,027
$1,700,000
$55,820,451
Actual
$ 105,709,913 $ 100,818,060
Difference: $4,891,853
ContingencyAvailableforBothProjects: $4,674,205