Академический Документы
Профессиональный Документы
Культура Документы
This Specification covers the repair of steel pipelines as used in Company onshore oil and gas
operations.
In this Section, reference is also made to Standard Construction Specification Sections S-1, S2, S-3, S-4, S-10, S-20, S-2 1, S-23, S-24, S-25, S-29, S-34 and S-35.
-1-
INDEX
Page
4
26.1
26.2
26.3
26.4
MATERIALS
26.4.1
26.4.2
26.4.3
26.4.4
26.4.5
5
5
6
6
6
26.5
26.6
26.7
EQUIPMENT
26.5.1
26.5.2
26.5.3
26.5.4
supply
Suitability for Duty
Temporary Power Supplies
Temporary Lighting
26.9
6
6
7
7
7
SITE PREPARATION
7
8
26.8.1
26.8.2
26.8.3
26.8.4
26.8.5
26.8.6
26.8.7
26.8.8
26.8.9
8
9
9
9
9
9
9
10
10
10
26.9.1 General
26.9.2 Collection and Disposal of Line Fill and Spillage
10
11
-2-
26.9.3
26.9.4
26.9.5
26.9.6
26.9.7
26.9.8
11
11
12
12
12
26.10
13
13
13
14
14
14
14
26.11
26.12
15
26.12.1
26.12.2
26.12.3
26.12.4
26.12.5
15
15
16
16
16
General
Boats, Barges and Equipment
Preliminaries and Company Representatives
Cleaning the Line
Repair Procedure
-3-
13
26.1
26.2
Tie-in welding
Radiography and testing
Pipeline repair operations will be stringently controlled by the Company. The Contractor shall
prepare detailed work procedures and submit them in writing to the Company for
approval/amendment in sufficient time (as directed) before the work is due to start.
26.3
26.4
MATERIALS
26.4.1
26.4.2
thus supplied by the Contractor shall strictly conform to the relevant Standards and
Specifications as directed by the Company. The cost of all such materials shall he included in
the Contract Price.
26.4.3
26.4.4
26.4.5
Storage of Materials
The Contractor shall be responsible for the proper storage, protection and security of all
materials and equipment as stipulated in Standard Construction Specification S-1 (General
Requirements) and will be liable for the replacement costs of any materials or equipment lost
or damaged.
All materials and equipment received shall be stored well clear of the ground on timber skids
or pallets and shall be properly protected from the weather. All machined items such as bolt
threads or the contact faces of flanges, shall be greased (if not otherwise protected) to prevent
corrosion.
26.5
EQUIPMENT
26.5.1
Supply
Unless otherwise stated in the Contract Documents, the Contractor will be required to provide
all tools and equipment necessary for the correct execution of the repair Works. Where the use
of special tools and/or equipment supplied on loan by the Company is agreed, the Contractor
shall give a full week's notice to the Company Representative of the days on which the
tools/equipment are actually required.
26.5.2
unsuitable, worn or unserviceable, shall be replaced by the Contractor at his own expense. All
lifting equipment must be covered by a valid inspection/test certificate in accordance with Part
4 of Specification S-35 (Contractor Safety).
26.5.3
26.5.4
Temporary Lighting
The Contractor shall supply all necessary temporary lighting and shall ensure that flame proof
enclosure are provided for temporary lighting systems in hazardous areas and that all
associated power generating equipment is located in a non-hazardous area.
26.6
26.6.1
Preliminary Checks
The Contractor shall first verify that all planned repair work operations are entirely possible
with respect to location, accessibility, size, pressure and
temperature ratings, material
suitability or any other relevant factors and shall take account of all such matters in his detailed
work procedure.
26.6.2
26.7
SITE PREPARATION
26.7.1
Area Clearance
All preliminary work necessary on the pipeline right-of-way, access roads and storage areas
shall be carried out in accordance with the relevant parts of the following Standard
Construction Specifications:S-2 (Right of Way and Access Roads)
-7-
Excavations
In the case of underground pipelines, the contractor shall perform all excavations necessary for
access to the pipe(s) to be repaired. The width and depth of the trench excavation for any pipe
shall be sufficient to properly conduct the work but in any case shall be at least 50 cms wider
than the outside diameter of the existing pipeline. Extra excavations and bellholes shall be
carried out as necessary so as to provide ample working space for cutting and jointing or the
installation of any valve or fitting.
The Contractor shall install all necessary timbering for shoring the sides of the excavations in a
safe manner so as to prevent earth slips and falls and shall also ensure that all excavations are
kept free of water.
The topsoil shall be segregated from the main fill or subsoil during excavation work and shall
be subsequently replaced last after the backfill operation.
Blasting with dynamite or any other explosive will not be permitted and the Contractor shall
conduct all excavation work in such a manner as to protect all persons and property (including
the pipeline and adjacent underground services) from injury and damage.
Mechanical excavators may only be used (with the prior approval of the Company
Representative) when the exact locations of the pipeline and all adjacent pipelines and other
underground services have been clearly established. Mechanical excavation shall not be
permitted within 1 metre (above or to either side) of any pipeline; water conduit or sewer;
power or telecommunications cable or any other service. In all such proximities, only hand
excavation will he permitted.
All additional hand excavation, whether incurred by these restrictions or otherwise, shall be
done at no additional cost to the Company.
All excavated material shall be deposited in neat tidy rows or heaps, well away from the edges
of excavations and shall be placed in such a manner that it does not impede the escape of
personnel from the working area in the event of danger or an emergency. The contractor shall
remove the excavated material from the work site (and return it as required for backfill) if the
Company Representative considers it necessary for safety reasons or for improving the
efficiency of the work in hand.
26.8
26.8.1
length shall be set down in a slightly skewed position so as to make both ends easily accessible
for visual inspection).
Pipes shall not be placed directly on the ground and wrapped pipes shall be set down on well
padded timbers provided by the Contractor. Valves and fittings shall also be kept well clear ,of
the ground surface by timber skids.
26.8.2
26.8.3
26.8.4
26.8.5
26.8.6
Pressure Testing
-9-
All pressure testing operations (including pre-cleaning, pigging, pre-installation tests on subassemblies and final integrity tests) shall be carried out in accordance with Standard
Construction Specification S-29 (Pressure Testing).
The Contractor shall submit a detailed test programme and schedule of operations to the
Company for approval/amendment in sufficient time (as directed) before the work is due to
start.
The Contractor shall determine the locations of any leakages or any faulty or suspect pipe
material, valves and fittings during pressure testing.
26.8.7
26.8.8
26.8.9
Lowering-In
The repaired or renewed sections of pipeline shall be handled and lowered into the trench in
strict accordance with Part 5 of Standard Specification S-25 (Pipeline Construction).
-10-
Prior to lowering in any section of pipeline or fittings, the Contractor shall ensure the removal
of all stones, rocks and hard objects from the bottom of the trench excavation, which shall then
be prepared in accordance with Part 5 of Standard Specification S-25.
The prepared trench or pipe ditch must be inspected and approved by the Company
Representative before any repaired pipeline/fitting is lowered in.
26.9
26.9.1
General
All procedures for pipeline repair shall be submitted for approval to the Company as detailed in
Clause 26.2 herein.
Prior to starting any repair operations on a pipeline in service, the necessary safety procedures
shall be carefully established and official Permits-to-Work obtained from the Company
Representative as detailed in Clause 26.3 herein. On no account shall any work commence
until the Contractor has given formal acknowledgment of receipt of the official Permits-toWork and his understanding and acceptance of the various conditions and procedures laid
down therein.
26.9.2
26.9.3
26.9.4
-11-
The pipe wrapping at each repair location shall be carefully removed and the surface of the
pipe in the vicinity of intended welding operations thoroughly cleaned of all coating, paint, rust
and dirt deposits by wi re brushing to bright metal.
Prior to any hot tapping operations, the pipe shall be prepared and inspected in accordance with
the Standard Construction Specification S-34, with checks for corrosion damage and
laminations being applied to the standards detailed therein. Hot tapping shall proceed only
after the Company Representative has inspected and approved the examination and test results.
If the area thus inspected and tested is found to be unsuitable, the Contractor shall strip and
prepare other locations as directed by the Company Representative.
Pipeline repair work shall proceed only after the Company Representative has inspected the
section which is to be, repaired or replaced and has given formal instructions for the repair
works to proceed.
26.9.5
26.9.6
26.9.7
26.9.8
(b)
Inspection
All tie-in welds shall be subjected to 100% radiographic inspection. This shall be carried out
in accordance with Standard Specifications S-21 and S-20 (Radiographic Inspection and NDT).
Radiographs shall be S" Subject to the approval of the Company Representative and no attempt
at weld repair or the elimination of defects shall be undertaken without his discretionary
agreement.
26.9.9
Pressure Testing
Purging, filling, pigging and flushing operations and pressure testing of the pipeline after
repairs have been completed shall be carried out where called for in the Contract Works and as
directed by the Company Representative. Filling and pressure testing shall be carried out in
accordance with Standard Construction Specification S-29 (Pressure Testing). The required
test pressure will be advised by the Company and on no account shall the test pressure
specified for the particular section of pipeline be exceeded.
REMOVAL AND SALVAGE OF WELDED OR SCREWED LINE
26.10.1
General
The Contractor shall identify the pipeline section(s) to be taken up and removed, using
drawings and instructions provided by the Company Representative and (in the case of buried
lines) by using Pipeline metal detectors. and digging trial holes to definitely establish the
identity and Position of the line.
Before starting any work (including the digging of trial holes), the necessary safety procedures
must be carefully established with the Company Representative and official Permits-to- Work
issued by the Company. The Contractor shall also give formal acknowledgment of receipt of
each Permit, signifying his understanding and acceptance of the various conditions and
procedures laid down therein, before starting the work covered by the Permit.
26.10.2
-13-
The Contractor shall clear the pipeline right-of-way and carry out all necessary excavation
work in accordance with Clause 26.7 herein.
Note: The limitations on the usage and working proximity of mechanical excavators to the
line being removed (as stipulated in 26.7.2) may be varied by the prior direction or agreement
of the Company.
26.10.3
26.10.4
26.10.5
26.10.6
The Contractor shall take all possible care during handling and transportation to avoid
damaging the pipe and other salvaged materials. Particular care shall be taken in the case of
coated and wrapped pipes to avoid damaging the coating and wrapping. Only broad band
slings or properly shaped end-hooks shall be used for lifting these pipes and the bolsters of the
transporter trucks shall be well padded with soft material.
The pipes shall be neatly stacked to a limited height as directed by the Company
Representative, during transportation and at the storage yard. During transportation, the pipes
shall be adequately secured in such a manner as to prevent damage to the coating and
wrapping.
BACKFILL AND REINSTATEMENT
Prior to any backfilling on the repaired/replaced section(s) of any pipeline, all inspections and
tests as called for by this specification and other specifications referred to herein, shall have
been completed and accepted as satisfactory by the Company Representative.
Backfill and reinstatement shall be carried out in accordance with Standard Specification S-25
(Pipeline Construction). In particular, the attention of the Contractor is drawn to the whole of
Part 6 and Clauses 25.7.9 and 25.8.7 therein.
26.12
26.12.1
General
In marsh and swamp locations, different established working procedures, requiring specialised
equipment, will be used for pipeline repairs but the contractual responsibilities and formal
procedures as stipulated in Sections 26.1 to 26.6 herein shall still apply. The works shall also
be carried out in accordance with Part 8 of- Standard Specification S-25 (Pipeline Construction
Marsh and Swamp Areas).
26.12.2
duty winch
26.12.3
(e)
A water barge
(f)
(g)
(h)
26.12.4
26.12.5
Repair Procedure
The Contractor shall carry out excavation/dredging work in the vicinity of the pipeline as
necessary and then, using broad band slings, carefully lift the damaged section(s) with a crane,
taking care not to overstress the line at any point.
The leaking, damaged or suspect parts of the line shall then be replaced or repaired in
accordance with the procedures detailed under Specification Sections 26.8 and 26.9 herein. All
welds shall be subject to 100% radiographic examination.
After the tie-in welds have been satisfactorily completed, coating and wrapping the field joints
and all unprotected surfaces (and repairs to any damaged or suspect areas of the wrapping
protection) shall be carried out to the satisfaction of the Company Representative.
The repaired line section shall then be lowered back into the trench, refilled with water and
hydrostatically tested in accordance with Standard Construction Specification S-29 (Pressure
Testing). The required test pressure will be advised by the Company. The specified test
pressure shall be held for 24 hours. The test pressure shall never exceed 150 bars (2160 psig)
for lines of ANSI 600 lb rating.
-16-
After pressure testing has been satisfactorily completed the pipeline trench or slot shall be
backfilled in accordance with the instructions of the Company Representative.
-17-