Академический Документы
Профессиональный Документы
Культура Документы
5. Liaison with the engineer/supervisor in-charge of the electrode handling process for stocks,
discrepancy happened if any, damages in electrode if any etc.
6. Maintain the mother oven and portable oven in good condition
7. Calibration of ovens before due dates and maintain a valid calibration certificate.
8. Replenish the electrodes in the ovens as per work load and in communication with welding
engineer.
9. Electrode mix if happened to be brought to the knowledge of welding engineer.
10. If power has gone during baking re-baking to be done in consultation with the
engineer/supervisor in charge for electrode handling process.
What is baking of an electrode?
The coating of the electrode is having the tendency to absorb moisture. Baking is the process of
removing moisture from the electrodes, with the help of heat, thereby reducing the level of
dissolved H2 in the weld metal which is prone to make delayed cracking in the weld metal.
How baking is done?
Baking is done with the help of ovens. These ovens are fitted with electrical resistant heating coils
which will generate heat upon giving electrical current. The heat in the coils are controlled by
temperature controllers. The temperature required is set in the temperature controllers. It
automatically controls the temperature in the oven.
What is the difference between mother oven, holding oven and portable oven (Heated
Electrode Quiver)?
Mother oven is the oven in which fresh electrodes are put which are taken from the original
electrode packets.
Holding oven is the oven in which the electrodes are put to maintain the holding temperature.
Portable oven is the oven which are used to carry the electrodes, transferred from the holding oven,
to the job location, where it is electrically connected and holding temperature is maintained.
Electrode Issue Process:
Electrode as per requirement at site/job location are assessed by welding engineer. Welding
engineer will raise the requisition to issue the electrodes through electrode issue slip.
The welding assistant (Helper to the welder) will take the electrode issue slip to the electrode store
and handover the slip to the electrode issuer (electrode store keeper). The welding assistant will
take the electrode bits of the previously issued electrodes along with the electrode issue slip and
that also will be handed over to the electrode issuer.
The electrode issuer cross check the signature of the welding engineer with the specimen signature
list of welding engineers available with him. He will also cross check the welder details
(qualification to use the requested electrode) with the qualified welder list available with him. He
will issue the electrodes as per requirement in the electrode issue slip.
If the electrode is of low hydrogen type, electrodes are taken in a portable oven by the welding
assistant, if else the welding assistant will take it as a loosely tied bundle
What is the expiry date of an electrode?
There is no expiry date for an electrode. Before using the electrodes/before placing the electrodes in
an oven ensure that the electrodes are in good condition.
If you have doubt about the quality of electrodes, take some electrodes and do a test weld. If the
electrode is giving a good weld then the electrode can be used
Oven validation Process
A sticker will be pasted on the oven with the signature of the validating person. A register will be
maintained with the details of validation.
VALIDATION STICKER
Duration of oven validation: Duration will be fixed based on the usability, chances of abnormalities
of machines etc. Normally mother oven and holding oven are validated once in 6 months. Portable
ovens are validated once in 3 months. But it is advisable to validate the mother oven and holding
oven once in 3 months and portable oven in every month.
What is the time period that an electrode can be kept at atmospheric temperature after electrodes are
taking out from hermetically sealed containers or from baking or storage ovens?
As per AWS D1.1, Clause 5.3.2.2 and Table 5.1, approved atmospheric time periods are as per the
below table.
.
HANDLING OF GTAW FILLER WIRES
For GTAW welding, filler wires are used. Color coding of filler wires are done for easily
identifying them.
Refer the above chart, if you see the filler wire with yellow colour on on one end, you can easily
identify from the chart that it is ER70 S2.
1T
2T
3T
4T
5T
Colour
Code
Violet
Green
Yellow
Grey
Red
Width
(mm)
Vertical
Straight Lift
Choked
Lift
Basket
Basket
450
Basket
900
25/30/50
56/60
75/90
100/120
125/150
1
1
2
3
4
5
X 0.8
0.8
1.6
2.4
3.2
4
X2
2
4
6
8
10
X 1.8
1.8
3.6
5.4
7.2
9
X 1.4
1.4
2.8
4.2
5.6
7
6T
8T
10T
12T
15T
16T
18T
20T
Brown
Blue
Orange
Orange
Orange
Orange
Orange
Orange
150/180
200/240
250/300
300
300
300
300
300
6
8
10
12
15
16
18
20
4.8
6.4
8
9.6
12
12.8
14.4
16
12
16
20
24
30
32
36
40
10.8
14.4
18
21.6
27
28.8
32.4
36
8.4
11.2
14
16.8
21
22.4
25.2
28
The other easiest way of identifying the tonnage of the belt is by counting the black stitches along
the width of the belt.
Eg:
5 stitches indicates 5T
3 stitches indicates 3T
1.
a.
b.
2.
a.
b.
c.
d.
3.
a.
b.
INSPECTION
Before using of the belt for any lifting purpose the following are to be inspected
Whether the correct belt is used?
Check the load to be lifted.
Check whether the belt is of correct tonnage.
Whether the belt is having any damage?
Check for any wear and tear.
Check the eye of the belt for any cut in the belt.
Check whether any damage to the stitching in the belt.
Belts wetted with water, oil etc should not be used.
Whether it is properly hooked with the material to be lifted?
Sharp edges in contact with the belt to be avoided.
Belt to be positioned considering the Center of gravity of the material to be lifted.
There are many ways to record the LHS. The most popularly used method is maintaining the
records in a Microsoft Excel Format. There are other softwares available like Parascadd (
www.parascadd.com). Some organisations will use in-house developed software's.
Why MSExcel became a popular platform for maintaining LHS?
1. A software programming crew is not required.
2. The process of entering and managing rows and columns is a simple process.
3. People can be trained easily on the software.
4. With a single licence for a system, it can be used by any number of persons.
5. Filtering option makes it easy for searching conditions of the entered data.
For starting the LHS the person should be familiarize with,
1. A line numbering system - for starting the column heading in LHS.
2. The data's in the isometric drawings.
3. The joint numbering system
4. The reports generated for a joint.
A isometric line number system is given below.
2" - P - 334143 - A1A - IH
What you can understand from this?
2" - P - 334143 - A1A - IH :
The red coloured 2" is the main line size of that line.
2" - P - 334143 - A1A - IH
The red coloured "P" represents this is a process line. Some times this contains the fluid handled by
that line. For example: DW - Drinking Water, PW - Process Water, HO - Hot Oil etc.
2" - P - 334143 - A1A - IH
The red coloured "334143" is line number. This may contain other information like, the area where
the pipe comes is "334" and the number of the line is "143" etc.
e) Check whether proper lighting is available night near each and every joint that you are offering.
3) Backlog of PWHT report entry against Weld Visual report entry.
Controlling Parameter: It should not be greater than the average of PWHT (in number of joints)
that can be done in two days time by your PWHT agency.
Points to Check and control if gone outside the limit
a) Check whether proper offering (in nos of joints) is getting to your PWHT agency from your
area engineers.
b) Check your PWHT agency is doing joints which are being offered.
c) Check whether your PWHT agency is having experienced technicians (experienced technicians
will do more joints - speed will be more) .
d) Check whether you are providing proper number of riggers and scaffolding for your pwht
agency in time (Speak with your PWHT technicians.)
e) Check whether proper number of coils (in gauge, numbers), cables (compensating and power
cable in sufficient length and qty), ceramic wool (the inventory of wool should be monitored
regularly), binding wire etc. are available with your PWHT agency.
f) Check whether shift of works are properly overlapped - of your PWHT agency. When a shift
starts, the shift technicians along with helpers should execute the PWHT of the joints- made ready
in previous shift- as well as prepare the joints (coil wrapping, wool wrapping, connection etc.) for
next shift.
g) Under stand the thump rule (a general rule based on the commonly available machines) is , to
one PID, 3 numbers of coils can be connected and these three coils can be monitored using three
recorders. So it should be ensured that with each PID machine 3 recorders should be available.
With each recorder 6 numbers(there are mcahines with 12 thermocouple also) of thermocouples can
be connected. So as per the number of thermocouples for each joint, the number of joints that can
be done (PWHT) can be calculated. When calculating keep in mind that 6 themocouple in one
recorder but one recorder to one coil only. that is if size is big for example 30" joint (3
themocouples) and one coil is used to wrap it, then one coil - one recorder but to this recorder only
3 termocouples will be connected (balance 3 thermocouple points in this recorder will be free - not
connected)
4) Backlog of DPT report entry against Weld Visual report entry and/or PWHT/RT entry.
Controlling Parameter: It should not be greater than the average of DPT (in number of joints) that
can be done in two days time by your NDTagency/In house level-1 technicians.
Points to Check and control if gone outside the limit
a) Check whether proper offering (in nos of joints) is getting to your ND agency from your area
engineers.
b) Check your NDT agency is doing joints which are being offerred.
c) Check whether your NDT agency is having experienced technicians (experienced technicians
will do more joints - speed will be more) .
d) Check whether you are providing proper number of riggers and scaffolding for your NDT
agency in time (Speak with your NDT technicians.)
d) Check whether your mechnical sub contractor is attending repairs as instructed by your area
engineer.
5) Repair status
a) Make a rule that, if a joint is found of having defects, that welder (who welded the defective
joint) should not weld further before attending the repairs.
6) PMI status
a) Check PMI report progress against total scope
b) Check the time period over which you have to do the job and plan for PMI machine and
operator. One day of 8hrs duty time, one operator- one PMI machine can check a maximum of
250Spots on an average.
7) Ferrite/Hardness checking status
a) Check Ferrite report progress against total scope
b) Check the time period over which you have to do the job and plan for Ferrite/Hardness checking
machine and operator. One day of 8hrs duty time, one operator- one machine can check a maximum
of 300 Spots on an average.
IQI (Penetrameter) Selection in Industrial Radiography Testing
Now how will you measure that the radiography film is having minimum 2% sensitivity. We have
to use the 'instrument' called IQI or Penetrameter.
IQI is a set of standard wires having standard diameter.(Hole type IQI is also used. In that case it will
be standard thickness plates with standard diameter holes).
The IQI is placed on a radiography film while doing the radiography. The image will be caught in
the film. If the wire having 0.16mm diameter is visible in the radiography film, then we can say that
the film is having a sensitivity of this 2%.
The IQI that is commonly used is of ASTM and DIN standards.
Below table (Table 233 T-233.2 in ASME BPVC Sec V) is the set of ASTM wire type IQI with its
wire diameters.
Now to our above example, select the set of IQI to be used. How this is done?
What is the minimum size of wire to be shown in our radiography film in our example?
It
is
Select
the
of
set
of
wire
0.16mm.
having
0.16mm
dia
wire.
It is in 'set A' in the above table and the wire is having a identity number of 4. So use this set at the
time of taking radiography and if that wire is visible (3 wires minimum will be visible that is wire of
thickness 0.16mm, 0.2mm and 0.25mm will be visible) in the film, then that radiography film is said
to be of having 2% sensitivity.
Example
2:
Radiography to be done on a plate with thickness of 32mm with a minimum sensitivity of 2%.
Now
the
2%
of
32
that
is
32
2/100=0.64mm
Select the set having a wire of 0.64mm thickness from the table given above. It is set B and wire
identity
number
is
10.
If in the radiography film of the above 32mm thickness plate, the wire with identity number 10 is
visible, we can say that the radiography film is having 2% sensitivity.
We have taken the radiography of a 60mm thickness plate and in the radiography film used set C and
the wire with identity number up to 12 is visible (5 wires will be visible in this radiography film).
What is the sensitivity?
Find
the
From
diameter
of
the
the
wire
table,
having
identity
it
number
is
12.
1.02mm.
Sensitivity =Diameter of the smallest IQI wire visible x 100 / Thickness of the plate radiographed.
So
in
the
above
case,
Sensitivity
1.02
100
60
1.7%
So the sensitivity is higher than that is required and the radiography film is acceptable from sensitivity
point
ofview.
Now there is no need for this type of extensive calculations for sensitivity. ASME BPVC Section 5
specifies the wire identity number that shall be minimum visible while taking radiography of material
with minimum thickness range as in the below table.
Please note an interesting fact in this. Up to and including 6.4 mm thickness the IQI identity number
that
shall
be
visible
is
for
source
side
and
for
film
side.
The other important point to note in the IQI selection is that the IQI shall be made up of the same
material as that of the material to be radiographed or the IQI shall be of a radiographically similar
material.
.
DHRUVA (Indias largest neuclear reactor),now supplies radioactive substances but limited for
medical and other research applications.
SPEC-2T
Another important news related to radiography camera is that M/s.Source Production & Equipment
Company Inc. (SPEC) the manufacturer of SPEC-2T camera is stopping the production of SPEC2T as per the information given in their website www.spec150.com. From April 30, 2015 onwards
they stopped the supply of the spare parts for that camera also.
How we check, whether the face preparation for a pipe joint is correct or not?.
That is the face width will be the same as thickness, including 2.5 to 3 mm gap. This is a thumb rule
only.
How is the lifting capacity(in ton) of a steel rope be identified from its diameter?
6 x d2, Where d is the diameter in inches, the result you will get will be in ton.
eg: 1" diameter rope = 6 x 12 =6MT capacity
Oxygen and Acetylene Cylinders
Acetylene becomes unstable above 15PSI, so we can see a red area marked on the regulators used
with acetylene cylinder.
Oxygen hose - Green Colour; Acetylene hose - Red Colour
One litre of acetone will absorb 250litres of acetylene at a pressure of 10 bar.
Acetylene is less dense than air.
DIGITAL THERMOMETER
The instrument is used to measure,
1. Temperature of welding viz, interpass temperature
2. Temperature verification during PWHT
CLAMP METER
Measuring current and voltage during welding (Production welding, welding for procedure
qualification and welding for welder performance qualification)
The bevel protractor can be used for measuring,
1. Angle of bevel.
2. Miscellaneous other angles of such as fabricated branches etc.
The Vernier caliper can be used for measuring,
1. Dimensions of rods, shafts, pipes etc
2. Difference in heights, Hi-Lo condition from outside etc can also be accurately measured by the
same.
The weld gauge can be used for measuring,
1. Weld thickness of fillet.
2. Reinforcement thickness of a butt weld.
3. Depth of undercut.
4. Depth of pit due to corrosion/indentations on material
.
HI-LO Welding gauge is used for measuring the,
1. Offset in fit-up.
2. Ovality of a joint at a location.
3. Internal misalignment.
4. Height of reinforcement in the weld.
5. Fillet weld leg length
DIGITAL SURFACE PROFILE GAUGE (Painting)
1. Measuring the surface roughness.
Surface roughness of the desired profile for the paint to be applied can be judged by this instrument.