Вы находитесь на странице: 1из 80

Specification Report to accompany the Estimate

1.Providing CC roads in SC Colony of Kanthetivaripodu in V.V. Meraka in E.G.Dt. 2.


Providing CC road to Choppallavari Group SC Colony in Malikipuram Village in E.G.Dt
Providing CC Road to SC Colony at Kandikatlavari Group in Lakkavaram Village,
Malikipuram Mandal, E.G.Dt.
Estimate Amount : Rs. 100.00

The work "1.Providing CC roads in SC Colony of Kanthetivaripodu in V.V. Merak


E.G.Dt. 2. Providing CC road to Choppallavari Group SC Colony in Malikipuram Village in E.G
3. Providing CC Road to SC Colony at Kandikatlavari Group in Lakkavaram Village, Malikipu
Mandal, E.G.Dt." is sanctioned vide G.O.Rt.No. 183, Dt. 01.04.2016 of T R&B (R.I) under S
for the year 2015-16. In this connection, the estimate for this work is prepared with
provisions as stated below.
Construction of CC roads is proposed in the internal roads of the SC Colonies.
commercial vehicular traffic on these internal roads is very less. Hence, construction o
Pavement is proposed with a nominal crust of 100mm GSB + 100 mm thick VCC (1:4:8
150mm thick VCC M35. The minimum cross section of 0.900M width of drain was proposed
a length of 129.00m on one side of the road in Kathetivaripodu SC Colony and 350M lengt
one side of the road in Choppallavari Group SC Colony. The CC drains are not require
Kanthetivari Group in Lakkavaram Village.

With the explained provisions, the internal roads in SC Colonies are prepared
these provisions are adopted as per the actual requirement based on the road condition to
extent of absolute necessity.

Provisions:For CC Roads:1)
2)
3)
4)
5)
6)

Providing
Providing
Providing
Providing
Providing
Providing

and laying GSB 100mm thick in widening portion.


VCC 1:4:8 below CC pavement.
M35 grade concrete for CC pavement
uncoated mild steel for contraction and expansion joints
and fixing 25.4 mm Mastic pad in expansion joints
earthen shoulders

For CC Drains:1)
2)
3)
4)
5)
6)
7)

Earthwork excavation for CC Drains


Sand filling in foundations for CC pavement and CC drains
Providing VCC 1:4:8 below CC pavement and CC drains
VCC M15 for CC Drain bed and body walls
Providing VRCC M20 grade concrete for CC Drain cover blocks
Providing HYSD for Reinforcement for VRCC drain cover slabs
Plastering in CM (1:5) 12 mm thick

1)
2)
3)
4)
5)
6)
7)
8)

LS provisions:Provision towards VAT @ 5%


Provision for price adjustment
Provision for QC charges
Provision towards insurance charges
Provision towards NAC
Provision for Seigniorage Charges.
Provision for Avagahana sadassu
Provision for Saw cutting, seperation membrane etc.

9)
10)

Provision for Shifting of Electrical poles


Provision for Unforeseen items and rounding of

The estimate is prepared with 2015-2016 commom SSR for all Enginee
Department and datas as per MoRT&H standard data book duly adopting over head charge
6% and contractors profit at 10% as per G.O.Ms No 141, T(R&B) Dept, dated 27.07.20
Provision for VAT is shown separately as PART "B" in the estimate as per G.O.Ms No 141, T(R
Dept., Dt 27.07.2006 The work will be carriedout as per relevant clauses of IRC & MO
specifications.
Asst Executive Engineer (R&B),
R&B Section, Malikipuram

Executive Engineer (R&B),


R&B Division, Amalapuram

Deputy Executive Engineer (R&


R&B Sub-division, Razole

Superintending Engineer (R&B


R&B Circle, Kakinada

tion Report to accompany the Estimate


C Colony of Kanthetivaripodu in V.V. Meraka in E.G.Dt. 2.
llavari Group SC Colony in Malikipuram Village in E.G.Dt. 3.
Colony at Kandikatlavari Group in Lakkavaram Village,
Malikipuram Mandal, E.G.Dt.
Lakhs

ng CC roads in SC Colony of Kanthetivaripodu in V.V. Meraka in


Choppallavari Group SC Colony in Malikipuram Village in E.G.Dt.
ony at Kandikatlavari Group in Lakkavaram Village, Malikipuram
vide G.O.Rt.No. 183, Dt. 01.04.2016 of T R&B (R.I) under SCSP
connection, the estimate for this work is prepared with the

roads is proposed in the internal roads of the SC Colonies. The


n these internal roads is very less. Hence, construction of CC
nominal crust of 100mm GSB + 100 mm thick VCC (1:4:8) +
nimum cross section of 0.900M width of drain was proposed for
de of the road in Kathetivaripodu SC Colony and 350M length on
pallavari Group SC Colony. The CC drains are not required in
am Village.

d provisions, the internal roads in SC Colonies are prepared and


s per the actual requirement based on the road condition to the

GSB 100mm thick in widening portion.


below CC pavement.
e concrete for CC pavement
mild steel for contraction and expansion joints
25.4 mm Mastic pad in expansion joints
houlders

ations for CC pavement and CC drains


below CC pavement and CC drains
in bed and body walls
grade concrete for CC Drain cover blocks

5) 12 mm thick

s prepared with 2015-2016 commom SSR for all Engineering


MoRT&H standard data book duly adopting over head charges @
10% as per G.O.Ms No 141, T(R&B) Dept, dated 27.07.2006.
rately as PART "B" in the estimate as per G.O.Ms No 141, T(R&B)
k will be carriedout as per relevant clauses of IRC & MORTH

Deputy Executive Engineer (R&B),


R&B Sub-division, Razole

Superintending Engineer (R&B),


R&B Circle, Kakinada

GENERAL ABSTRACT
Name of the 1.Providing CC roads in SC Colony of Kanthetivaripodu in V.V.
Work ::
Meraka in E.G.Dt. 2. Providing CC road to Choppallavari
Group SC Colony in Malikipuram Village in E.G.Dt. 3.
Providing CC Road to SC Colony at Kandikatlavari Group in
Lakkavaram Village, Malikipuram Mandal, E.G.Dt.
Sl.
No.

Item Description

Part - A
Cost of CC road work

Cost of CC drains work

Amount
65,14,441

Sub-Total (A)

,25,41,141
---------------90,55,582

Part-B
VAT @ 5%

4,52,779

Seigniorage Charges

1,61,586

Provisions for Price Adjustment @ 1.5%

1,50,000

Provisions Towards Quality control Charges @ 0.5%

Provisions Towards Insurance charges @ 0.385%

Provisions Towards NAC @ 0.1%

Provision for Avagahana Sadassulu

46,100
,34,864
,9,056
2,500

10 Provision for Saw cutting, seperation membrane etc.

40,000

11 Provision for Shifting of Electrical Poles

40,000

12 Provisions towards Unforeseen items and rounding of

7,534
---------------Sub-Total (B)
9,44,419
---------------------GRAND TOTAL (A)+(B) Excess percentage
1,00,00,000

Asst. Executive Engineer (R&B),


(R&B) Section : Malikipuram

Dy. Executive Engineer (R&B),


(R&B) Sub Division : Razole

Executive Engineer (R&B),

Superintending Engineer (R&B),

(R&B) Division : Amalapuram

(R&B) Circle : Kakinada

DETAILED CUM ABSTRACT ESTIMATE FOR ROAD WORK

Name of work :
1.Providing CC roads in SC Colony of Kanthetivaripodu in V.V. Meraka in E.G.Dt. 2.
Providing CC road to Choppallavari Group SC Colony in Malikipuram Village in E.G.Dt. 3
Providing CC Road to SC Colony at Kandikatlavari Group in Lakkavaram Village,
Malikipuram Mandal, E.G.Dt.
(CC Road Work)
S.
No.
1

DESCRIPTION

NO

Contents

Rate

Per

Construction of Granular sub-base by providing


HBG
material confirming to Grading - III of MoRT&H Table 4002 including cost, seigniorage charges and conveyance of
all materials to work site and spreading in uniform layers
with motor grader or by approved means, on prepared
surface mixing by mix in place method with Rotavator /
approved means at OMC and compacting with vibratory
roller to achieve the desired density etc., complete for
finished item of work as per MoRT&H Specification 401
(4th revision) and as directed by the Engineer-in-charge. (
Payment will be made based on levels for finished item of
work ).
Kanthetivaripodu in VV Meraka
180
1x1
3.75 0.10
129
1x1
3.75 0.10
Choppallavari Group SC Colony in Malikipuram Village
350
1x1
3.75 0.10
Kandikatlavari Group, Lakkavaram Village
300
1x1
3.75 0.10
or

67.50
48.38
131.25
112.50
359.63
360.00 2245.00 cum
cum

Providing Vibrated Cement Concrete (1:4:8) mix using


40mm size
HBG crushed stone aggregate and fine
aggregate conforming to table 1000-2 of MoRT&H
including cost, seigniorage conveyance of all materials to
site and labour charges, centering, machine mixing,
laying,
Vibrating, curing etc., including all other
incidental and operational charges of all T&P
etc.,
complete for finished item of work as per MoRT&H
specification 1500,1700, 2100 (4th Revision) and as
directed by the Engineer-in-Charge for base coarse below
CC Pavement.
Kanthetivaripodu in VV Meraka
180
1x1
3.75 0.10
129
1x1
3.75 0.10
Choppallavari Group SC Colony in Malikipuram Village
350
1x1
3.75 0.10
Kandikatlavari Group, Lakkavaram Village
300
1x1
3.75 0.10
or

67.50
48.38
131.25
112.50
359.63
360.00 4415.00 cum
cum

S.
No.
3

DESCRIPTION

NO

Contents

Rate

Per

Vibrated cement concrete M 35 grade using 20mm &


10mm HBG crushed stone aggregate (Coarse aggregate
conforming to table 1000-1 and fine aggregate
conforming to table 1000-2) including cost, seigniorage
conveyance of all materials to site and labour charges,
centering, machine mixing, laying, vibrating, curing etc.,
including all other incidental and operational charges of
all T&P etc., complete for finished item of work as per
MoRT&H specification 1500, 1700, 2100 & 2702 (4th
Revision) and as directed by the Engineer-in-Charge for
C.C Pavement. (including Vacuum dewatered flooring
service, Saw cutting and filling joints with sealing
compound)
Kanthetivaripodu in VV Meraka
180
1x1
3.75 0.15
129
1x1
3.75 0.15
Choppallavari Group SC Colony in Malikipuram Village
350
1x1
3.75 0.15
Kandikatlavari Group, Lakkavaram Village
300
1x1
3.75 0.15
or

101.25
72.56
196.88
168.75
539.44
540.00 6825.00 cum
cum

Providing Uncoated Mild Steel bars ( Fe-250 ) of diferent


diameters, wrought and put up bars of all diameters
including cost and conveyance of steel to site and all
labour charges for fabrication of reinforcement including
cutting, bending, binding rods, tying grills, placing them
in position etc., complete including cost and conveyance
of binding wire and all handling charges and operational
charges etc., and including over lapping welding if
required etc., complete for all R.C.C items for finished
item of work as per standard drawings, as per the
directions of the Engineer-in-Charge and as per MoRT&H
specification 1600 &2200 (4th revision)
and as per
I.S.1786 of 1985 .for dowel bars
Kanthetivaripodu in VV Meraka
0.50
1x4
3.85
-0.50
1x3
3.85
-Choppallavari Group SC Colony in Malikipuram Village
0.50
1x8
3.85
-Kandikatlavari Group, Lakkavaram Village
0.50
1x7
3.85
-kg/m
or

Providing 25.4 mm mastic pads for Longitudinal joints,


Transversal expansion joints and Construction joints of
approved quality including cost, conveyance and placing
in position, etc., complete as directed by the Engineer-incharge.
Kanthetivaripodu in VV Meraka

7.70
5.78
15.40
28.88
57.75
0.06
MT

###

MT

S.
No.

DESCRIPTION

NO

3.75
4
0.15
3.75
3
0.15
Choppallavari Group SC Colony in Malikipuram Village
3.75
8
0.15
Kandikatlavari Group, Lakkavaram Village
3.75
3
0.15
or

Contents

Rate

Per

2.25
1.69
4.50
1.69
10.13
11.00 991.00 sqm
sqm

Forming shoulders with borrowed useful selected earth


having MDD of not less than 1.75 gms/CC from outside
road boundary by mechnical means with a lead of 17
kms. and lifts including pre-watering of soil at borrow
area, removal of top soil, excavation of soils at borrowed
area, conveyance of soil, depositing the soils on the
embankment, spreading soils, breaking clods, sectioning,
grading and consolidation with vibratory road roller @
OMC to meet requirement of table 300-2 of MORT&H
including all hire and operational charges of T&P and
complete for finished item of work as per MORT&H
specification 305 (4th revision)
Kanthetivaripodu in VV Meraka
180
1x2
1.00 0.25
129
1x1
1.00 0.25
Choppallavari Group SC Colony in Malikipuram Village
350
1x1
1.00 0.25
Kandikatlavari Group, Lakkavaram Village
300
1x2
1.00 0.25
or

90.00
32.25
87.50
150.00
359.75
360.00 1160.00 cum
cum

Asst. Executive Engineer (R&B),


(R&B) Section : Malikipuram

Dy. Executive Engineer (R&B),


(R&B) Sub Division : Razole

Executive Engineer (R&B),


(R&B) Division : Amalapuram

Superintending Engineer (R&B),


(R&B) Circle : Kakinada

STRACT ESTIMATE FOR ROAD WORK

ny of Kanthetivaripodu in V.V. Meraka in E.G.Dt. 2.


Group SC Colony in Malikipuram Village in E.G.Dt. 3.
y at Kandikatlavari Group in Lakkavaram Village,
ipuram Mandal, E.G.Dt.
(CC Road Work)
Amount

808200

1589400

Amount

3685500

2840

Amount

10901

417600

7E+006

Dy. Executive Engineer (R&B),


(R&B) Sub Division : Razole

Superintending Engineer (R&B),


(R&B) Circle : Kakinada

DETAILED CUM ABSTRACT ESTIMATE


Name of the work: 1.Providing CC roads in SC Colony of Kanthetivaripodu in V.V. Meraka
in E.G.Dt. 2. Providing CC road to Choppallavari Group SC Colony in
Malikipuram Village in E.G.Dt. 3. Providing CC Road to SC Colony at
Kandikatlavari Group in Lakkavaram Village, Malikipuram Mandal,
E.G.Dt.
(CC Drains Work)
Sl.
No.
1
1

Description of item

No

Quantit
y

Rate
/Per

Amount

Earthwork excavation in soils upto SDR by mechanical means for


foundations of structures as per drawing and technical
specification including setting out, construction of shoring and
bracing, removal of stumps and other deleterious matter, dressing
sides of bottom, back filling the excavation earth to the extent
required etc., complete including seignioarge charges for finished
item of work as per MoRT&H specification 304(4th Revision) and
as directed by the Engineer-in-Charge
Kanthetivaripodu in VV Meraka
( 1 x

0.900
129
Choppallavari Group SC Colony in Malikipuram Village
( 1 x 1 )
0.900
350
Total length of drain 479.00

110.30

0.950

299.25

or say

409.55
410.00
Cum

93.00
1 /Cum

38,130

Sand filling in foundation including cost, seignoirage and


conveyence of all materials to site and watering, tamping etc.,
complete for finshed item of work as per MoRT&H specification 304
(4th Revision) and as directed by the Engineer - in - Charge.
Kanthetivaripodu in VV Meraka
( 1 x 1 ) 129.00 0.900
Choppallavari Group SC Colony in Malikipuram Village
( 1 x 1 ) 350.00 0.900

0.950

0.100

11.61

0.100

31.50

or say

43.11
43.11 1153.00
Cum 1 /Cum

Providing Vibrated Cement Concrete (1:4:8) mix using 40mm size


HBG crushed stone aggregate and fine aggregate conforming to
table 1000-2 of MoRT&H including cost, seigniorage conveyance of
all materials to site and labour charges, centering, machine
mixing, laying, Vibrating, curing etc., including all other incidental
and operational charges of all T&P etc., complete for finished item
of work as per MoRT&H specification 1500,1700, 2100 (4th
Revision) and as directed by the Engineer-in-Charge for below base
coarse of CC Drains.
Kanthetivaripodu in VV Meraka
( 1 x 1 ) 129.00 0.900
Choppallavari Group SC Colony in Malikipuram Village
( 1 x 1 ) 350.00 0.900

0.100

11.61

0.100

31.50
43.11

49,706

Sl.
No.

Description of item

No

6
or say

Rate
/Per

7
8
43.11 4415.00
Cum 1 /Cum

Amount
9
1,90,331

Vibrated cement concrete M 15 Grade Concrete using 40mm ,


20mm and 10mm size HBG crushed stone aggregate (Coarse
aggregate conforming to table 1000-1 and fine aggregate
conforming to table 1000-2) including cost,seignorage and
conveyance of all materials to site and all labour charges for
machine mixing,laying in position, Compacting , Vibrating and
curing including all other incidental and all other operational
charges of T&P required etc., complete as per MoRT&H
Specification 1500,1700, 2100 (4th Revision) base course for
below CC Drains.
Kanthetivaripodu in VV Meraka
( 1 x 1 ) 129.00 0.900
Choppallavari Group SC Colony in Malikipuram Village
( 1 x 1 ) 350.00 0.900

Quantit
y

0.200

23.22

0.200

63.00

or say

86.22
86.22 5405.00
Cum 1 /Cum

4,66,019

Vibrated cement concrete M 15 Grade Concrete using 40mm ,


20mm and 10mm size HBG crushed stone aggregate (Coarse
aggregate conforming to table 1000-1 and fine aggregate
conforming to table 1000-2) including cost,seignorage and
conveyance of all materials to site and all labour charges for
machine mixing, laying in position,Compacting, Vibrating and
curing including all other incidental and all other operational
charges of T&P required etc., complete as per MoRT&H
Specification 1500,1700, 2200 (4th Revision) for CC Drains body
walls.
Kanthetivaripodu in VV Meraka
(0.3+0.
2)/2
Choppallavari Group SC Colony in Malikipuram Village
(0.3+0.
( 1 x 2 ) 350.00
2)/2
( 1 x

) 129.00

0.600

38.70

0.600

105.00

or say
6

143.70
143.70 5946.00
Cum 1 /Cum

Vibrated reinforced cement concrete M 20 grade using 20mm &


10mm
HBG crushed stone aggregate (Coarse aggregate
conforming to table 1000-1 and fine aggregate conforming to table
1000-2) including cost, seigniorage conveyance of all materials to
site and labour charges, centering, machine mixing, laying,
vibrating, curing etc., including other incidental hire and
operational charges of all T&P as per approved drawings and as
directed during execution but excluding cost of steel and its
fabrication charges for finished item as per MoRT&H specification
1500,1600,1700 & 2200 (4th revision ) and as directed by the
Engineer-in-Charge for Cover slabs over side drains
Kanthetivaripodu in VV Meraka
Cover Blocks
( 1 x 258 ) 0.50
0.900
Choppallavari Group SC Colony in Malikipuram Village

0.200

23.22

8,54,440

Sl.
No.

Description of item

No

Quantit
y

Rate
/Per

Amount

( 1 x 700 )

0.50

0.900

0.200

Cover Blocks

or say
7

5,46,882

Providing HYSD bars ( Fe-415 ) of diferent diameters, wrought and


put up bars of all diameters including cost and conveyance of steel
to site and all labour charges for fabrication of reinforcement
including cutting, bending, binding rods, tying grills, placing them
in position etc., complete including cost and conveyance of
binding wire and all handling charges and operational charges etc.,
and including over lapping welding if required etc., complete for all
R.C.C items for finished item of work as per standard drawings, as
per the directions of the Engineer-in-Charge and as per MoRT&H
specification 1600 &2200 (4th revision) and as per I.S.1786 of
1985 for Sub structure of R.C.C items.
Over drain Cover slabs###

63.00
86.22
87.00 6286.00
Cum 1 /Cum

87.00

75.000
Kgs

/1 cum
or say

6525.00
Kgs
6.50 44734.00
Mt
1 /Mt

2,90,771

Plastering in CM (1:5) 12 mm thick including cost and conveyance


of all materials, seigniorage charges, labour charges, curing etc
complete for finished item of work as directed by the Engineer -inCharge
L = 0.20+0.2+0.61+0.3+0.61+0.2+0.20 = 2.32
Kanthetivaripodu in VV Meraka
Cover Blocks
( 1 x
0.00
Cover Blocks
( 1 x

) 129.00

2.320

--

299.28

) 350.00

2.320

--

812.00

or say

1,111.28
### 943.00
Sqm 10/ Sqm
TOTAL

Asst. Executive Engineer (R&B),


(R&B) Section : Malikipuram

Dy. Executive Engineer (R&B),


(R&B) Sub Division : Razole

Executive Engineer (R&B),


(R&B) Division : Amalapuram

Superintending Engineer (R&B),


(R&B) Circle : Kakinada

1,04,862
###

LEAD CALCULATION FOR VARIOUS MATERIALS UPTO CENTER OF THE WORKING STRETCH
Name of the work: 1.Providing CC roads in SC Colony of Kanthetivaripodu in V.V. Meraka in E.G.Dt. 2.
Providing CC road to Choppallavari Group SC Colony in Malikipuram Village in E.G.Dt. 3.
Providing CC Road to SC Colony at Kandikatlavari Group in Lakkavaram Village,
Malikipuram Mandal, E.G.Dt. -:oOo:-

Kanthetivaripodu in VV Meraka
Reach proposed in the present estimate:
Centre KM of the Working Reach =
=
A) For HBG metal:
HBG metal from Katheru quarry
a) Cart track length =
b) Metalled road length:
From km 906 / 400
to
944 / 805
From km
61 / 425
to
31 / 735
From km 120 / 350
to
115 / 550
From km
0 / 000
to
2 / 600
From km
0 / 000
to
5 / 650
From km
0 / 000
to
0 / 735
From km
0 / 000
to
0 / 758
0.155
Working K.M.
K.M.
c) Total lead
B) For gravel:
Gravel from Kadium Quarry
a) Cart track length =
b) Metalled road length:
Quarry at Kadium Quarry
From km
55 / 600
to
60
From km 918 / 200
to
944
From km
61 / 425
to
31
From km 120 / 350
to
115
From km
0 / 000
to
2
From km
0 / 000
to
5
From km
0 / 000
to
0
From km
0 / 000
to
0
0.155
Working K.M.
K.M.
c) Total lead

km

to

309

0.309 kms
0.155 kms

2.200 kms

0.155 K.M.

of
of
of
of
of
of
of

NH 16
NH 16 to RP road
NH 216
S M road
CBM Road
CBM road to NREGS Building
NREGS Building to Kanthetivaripodu

=
=
=
=
=
=
=
=
=
Or say:

/
/
/
/
/
/
/
/

200
805
735
550
600
650
735
758

of
of
of
of
of
of
of
of

Kakinada - Rajahmundry Road


NH 16
NH 16 to RP road
NH 216
S M road
CBM Road
CBM road to NREGS Building
NREGS Building to Kanthetivaripodu

C) For Sand :
Sand Quarry at River Godavari at P. Gannavaram
River Bed to Panchayat Road
Panchayat Road
From km
49 / 072
to
61 / 425 of Rajavaram - Podalada Road
From km 120 / 350
to
115 / 550 of NH 216
From km
0 / 000
to
2 / 600 of S M road
From km
0 / 000
to
5 / 650 of CBM Road
From km
0 / 000
to
0 / 735 of CBM road to NREGS Building
From km
0 / 000
to
0 / 758 of NREGS Building to Kanthetivaripodu
0.155
Working K.M.
K.M.
c) Total lead

Asst. Executive Engineer (R&B),


R&B Section : Malikipuram

Deputy Executive Engineer (R&B),


R&B Sub-division : Razole

Superintending Engineer (R&B),


(R&B) Circle : Kakinada

38.405
29.690
4.800
2.600
5.650
0.735
0.758
0.155
84.993

kms
kms
kms
kms
kms
kms
kms
kms
kms
kms

0.000 kms

=
=
=
=
=
=
=
=
=
=
Or say:

4.600
26.605
29.690
4.800
2.600
5.650
0.735
0.758
0.155
75.593

kms
kms
kms
kms
kms
kms
kms
kms
kms
kms
kms

=
=
=
=
=
=
=
=
=
=
Or say:

0.110
0.200
12.353
4.800
2.600
5.650
0.735
0.758
0.155
27.361

kms
kms
kms
kms
kms
kms
kms
kms
kms
kms
kms

Executive Engineer (R&B),


R&B Division : Amalapuram

LEAD CALCULATION FOR VARIOUS MATERIALS UPTO CENTER OF THE WORKING STRETCH
Name of the work: 1.Providing CC roads in SC Colony of Kanthetivaripodu in V.V. Meraka in E.G.Dt. 2.
Providing CC road to Choppallavari Group SC Colony in Malikipuram Village in E.G.Dt.
3. Providing CC Road to SC Colony at Kandikatlavari Group in Lakkavaram Village,
Malikipuram Mandal, E.G.Dt.
-:oOo:-

Choppallavari Group SC Colony in Malikipuram Village


Reach proposed in the present estimate:
Centre KM of the Working Reach =
=
A) For HBG metal:
HBG metal from Katheru quarry
a) Cart track length =
b) Metalled road length:
From km 906 / 400
to
944
From km
61 / 425
to
31
From km 123 / 935
to
115
From km
81 / 600
to
86
0.175
Working K.M.
K.M.
c) Total lead

B) For Gravel:
Gravel from Kadium Quarry
a) Cart track length =
b) Metalled road length:
Quarry at Kadium Quarry
From km
55 / 600
to
60
From km 918 / 200
to
944
From km
61 / 425
to
31
From km 123 / 935
to
115
From km
81 / 600
to
86
0.175
Working K.M.
K.M.
c) Total lead

/
/
/
/

805
735
760
980

km

/ 000 to

0.350 kms
0.175 kms

2.200 kms

0.175 K.M.

of
of
of
of

NH 16
NH 16 to RP road
NH 216
KANF Road

=
=
=
=
=
=
Or say:

/
/
/
/
/

200
805
735
760
980

of
of
of
of
of

Kakinada - Rajahmundry Road


NH 16
NH 16 to RP road
NH 216
KANF Road

C) For Sand :
Sand Quarry at River Godavari at P. Gannavaram
River Bed to Panchayat Road
Panchayat Road
From km
49 / 072
to
61 / 425 of Rajavaram - Podalada Road
From km 123 / 935
to
115 / 760 of NH 216
From km
81 / 600
to
86 / 980 of KANF Road
0.175
Working K.M.
K.M.
Total lead

Asst. Executive Engineer (R&B),


R&B Section : Malikipuram

350

Deputy Executive Engineer (R&B),


R&B Sub-division : Razole

Superintending Engineer (R&B),


(R&B) Circle : Kakinada

38.405
29.690
8.175
5.380
0.175
84.025

kms
kms
kms
kms
kms
kms
kms

0.000 kms

=
=
=
=
=
=
=
Or say:

4.600
26.605
29.690
8.175
5.380
0.175
74.625

kms
kms
kms
kms
kms
kms
kms
kms

=
=
=
=
=
=
=
Or say:

0.110
0.200
12.353
8.175
5.380
0.175
26.393

kms
kms
kms
kms
kms
kms
kms
kms

Executive Engineer (R&B),


R&B Division : Amalapuram

LEAD CALCULATION FOR VARIOUS MATERIALS UPTO CENTER OF THE WORKING STRETCH
Name of the work: 1.Providing CC roads in SC Colony of Kanthetivaripodu in V.V. Meraka in E.G.Dt. 2.
Providing CC road to Choppallavari Group SC Colony in Malikipuram Village in E.G.Dt. 3.
Providing CC Road to SC Colony at Kandikatlavari Group in Lakkavaram Village,
Malikipuram Mandal, E.G.Dt. -:oOo:-

Kandikatlavari Group, Lakkavaram Village


Reach proposed in the present estimate:
Centre KM of the Working Reach =
=
A) For HBG metal:
HBG metal from Katheru quarry
a) Cart track length =
b) Metalled road length:
From km 906 / 400
to
944 / 805
From km
61 / 425
to
31 / 735
From km 120 / 350
to
115 / 550
From km
0 / 000
to
2 / 600
From km
0 / 000
to
4 / 517
0.150
Working K.M.
K.M.
c) Total lead
B) For gravel:
Gravel from Kadium Quarry
a) Cart track length =
b) Metalled road length:
Quarry at Kadium Quarry
From km
55 / 600
to
60
From km 918 / 200
to
944
From km
61 / 425
to
31
From km 120 / 350
to
115
From km
0 / 000
to
2
From km
0 / 000
to
4
0.150
Working K.M.
K.M.
c) Total lead

km

to

300

0.300 kms
0.150 kms

2.200 kms

0.150 K.M.

of
of
of
of
of

NH 16
NH 16 to RP road
NH 216
S M road
CBM Road

=
=
=
=
=
=
=
Or say:

/
/
/
/
/
/

200
805
735
550
600
517

of
of
of
of
of
of

Kakinada - Rajahmundry Road


NH 16 to RP road
NH 16 to RP road
NH 216
S M road
CBM Road

C) For Sand :
Sand Quarry at River Godavari at P. Gannavaram
River Bed to Panchayat Road
Panchayat Road
From km
49 / 072
to
61 / 425 of Rajavaram - Podalada Road
From km 120 / 350
to
115 / 550 of NH 216
From km
0 / 000
to
2 / 600 of S M road
From km
0 / 000
to
4 / 517 of CBM Road
0.150
Working K.M.
K.M.
c) Total lead

Asst. Executive Engineer (R&B),


R&B Section : Malikipuram

Deputy Executive Engineer (R&B),


R&B Sub-division : Razole

Superintending Engineer (R&B),


(R&B) Circle : Kakinada

38.405
29.690
4.800
2.600
4.517
0.150
82.362

kms
kms
kms
kms
kms
kms
kms
kms

0.000 kms

=
=
=
=
=
=
=
=
Or say:

4.600
26.605
29.690
4.800
2.600
4.517
0.150
72.962

kms
kms
kms
kms
kms
kms
kms
kms
kms

=
=
=
=
=
=
=
=
Or say:

0.110
0.200
12.353
4.800
2.600
4.517
0.150
24.730

kms
kms
kms
kms
kms
kms
kms
kms
kms

Executive Engineer (R&B),


R&B Division : Amalapuram

WEIGHTED AVERAGE LEAD CALCULATIONS

Sl.
No.

Road Name

Road
Length
in kms

HBG
Lead
in kms

Gravel

Weighted
Average

Lead
in kms

Sand

Weighted
Average

Lead
in kms

Weighted
Average

Kanthetivaripodu in VV Meraka

0.309

84.993

26.263

75.593

23.358

27.361

8.454

Choppallavari Group SC Colony in


Malikipuram Village

0.350

84.025

29.409

74.625

26.119

26.393

9.238

Kandikatlavari Group, Lakkavaram


Village

0.300

82.362

24.709

72.962

21.889

24.730

7.419

Weighted Average Lead

83.817
84.000

or say

Asst. Executive Engineer (R&B),


R&B Section : Malikipuram

Deputy Executive Engineer (R&B),


R&B Sub-division : Razole

Superintending Engineer (R&B),


(R&B) Circle : Kakinada

74.417
74.000

Executive Engineer (R&B),


R&B Division : Amalapuram

26.185
26.000

ROAD METAL RATES

Sl.
No

Description of Metal

Source of
Supply

Lead
Conveyanc
in
e
Kms

Initial
cost

Machine
Blasting crushin
charges
g
charges

Seigniorag
e charges

NAME OF WORK ::- 1.Providing CC roads in SC Colony of Kanthetivaripodu in V.V. Meraka in E.G.Dt. 2. Providing CC
road to Choppallavari Group SC Colony in Malikipuram Village in E.G.Dt. 3. Providing CC Road to
SC Colony at Kandikatlavari Group in Lakkavaram Village, Malikipuram Mandal, E.G.Dt.
Deduct
13.615% CP &
Toal Cost
OH charges
per Cum
from
conveyance

A) FOR ROAD WORKS


1

60 to 63 mm IRC and MoRTH HBG metal

Katheru

84

948.90

419.00

70.00

--

--

-113.71

1324.19

50 to 55 mm IRC and MoRTH HBG metal

-- do --

84

948.90

456.00

70.00

--

--

-113.71

1361.19

40 to 45 mm IRC and MoRTH HBG metal

-- do --

84

948.90

588.00

70.00

--

--

-113.71

1493.19

50 to 55 mm IRC and MoRTH HBG M/C metal

-- do --

84

948.90

456.00

70.00

114.00

--

-113.71

1475.19

40 to 45 mm IRC and MoRTH HBG M/C metal

-- do --

84

948.90

588.00

70.00

147.00

--

-113.71

1640.19

25 to 27 mm IRC and MoRTH HBG M/C metal

-- do --

84

948.90

944.00

70.00

236.00

--

-113.71

2085.19

19 to 22 mm IRC and MoRTH HBG M/C metal

-- do --

84

948.90

984.00

70.00

246.00

--

-113.71

2135.19

12 to 14 mm IRC and MoRTH HBG M/C metal


9.5 to 11.20 mm IRC and MoRTH HBG M/C
metal
5 to 7 mm IRC and MoRTH HBG M/C metal

-- do --

84

948.90

780.00

70.00

195.00

--

-113.71

1880.19

-- do --

84

948.90

656.00

70.00

164.00

--

-113.71

1725.19

-- do --

84

948.90

504.00

70.00

126.00

--

-113.71

1535.19

10 2.36 to 5 mm IRC and MoRTH HBG M/C metal

-- do --

84

948.90

308.00

70.00

77.00

--

-113.71

1290.19

11 HBG Stone chips 2.36mm and below

-- do --

84

948.90

350.00

--

--

--

-113.71

1185.19

Kadiyam

74

845.90

103.00

--

--

--

-101.37

847.53

13 40 mm SS-5 HBG M/C metal

Katheru

84

948.90

620.00

70.00

155.00

--

-113.71

1680.19

14 25 mm SS-5 HBG M/C metal

-- do --

84

948.90

994.00

70.00

248.50

--

-113.71

2147.69

15 20 mm SS-5 HBG M/C metal

-- do --

84

948.90

1036.00

70.00

259.00

--

-113.71

2200.19

16 12 mm SS-5 HBG M/C metal

-- do --

84

948.90

822.00

70.00

205.50

--

-113.71

1932.69

17 10 mm SS-5 HBG M/C metal

-- do --

84

948.90

692.00

70.00

173.00

--

-113.71

1770.19

18 6 mm SS-5 HBG M/C metal

-- do --

84

948.90

532.00

70.00

133.00

--

-113.71

1570.19

8
9

12 Gravel
B) FOR C.D. WORKS

Description of Metal

Source of
Supply

Initial
cost

Machine
Blasting crushin
charges
g
charges

Seigniorag
e charges

Sl.
No

Lead
Conveyanc
in
e
Kms

Deduct
13.615% CP &
Toal Cost
OH charges
per Cum
from
conveyance

19 Sand for Concrete

Gannavaram

26

343.10

610.00

--

--

--

-41.12

911.98

20 Sand for Filling

Gannavaram

26

343.10

450.00

--

--

--

-41.12

751.98

21 Sand for Plastering

Gannavaram

26

343.10

677.00

--

--

--

-41.12

978.98

22 HYSD Steel

34000.00

23 6mm Mild Steel

36000.00

24 Mild Steel

38000.00

25 Cement

5920.00

Asst. Executive Engineer (R&B),


(R&B) Section : Malikipuram

Dy. Executive Engineer (R&B),


(R&B) Sub Division : Razole

Superintending Engineer (R&B),


(R&B) Circle : Kakinada

Executive Engineer (R&B),


(R&B) Division : Amalapuram

DATA
Name of Work ::- 1.Providing CC roads in SC Colony of Kanthetivaripodu in V.V.
Meraka in E.G.Dt. 2. Providing CC road to Choppallavari Group SC
Colony in Malikipuram Village in E.G.Dt. 3. Providing CC Road to
SC Colony at Kandikatlavari Group in Lakkavaram Village,
Malikipuram Mandal, E.G.Dt.
Quantity
Description of Item
Rate
per
Amount
1 Construction of Granular sub-base by providing HBG material confirming to Grading - III of
MoRT&H Table 400-2 including cost, seigniorage charges and conveyance of all materials to
work site and spreading in uniform layers with motor grader or by approved means, on
prepared surface mixing by mix in place method with Rotavator / approved means at OMC
and compacting with vibratory roller to achieve the desired density etc., complete for finished
item of work as per MoRT&H Specification
401 (4 th revision) and as directed by the
Engineer-in-charge. ( Payment will be made based on levels for finished item of work ).
Unit = cum
Taking output = 300 cum
Page 95 of MoRT&H SDB
(A) Labour
0.40 day
Mate
375.00
2.00 day
Mazdoor skilled
388.50
8.00 day
Mazdoor unskilled
320.00
Total
(B) Machinery
6.00 hr
Motor grader 3.35M Blade @50 cum/Hr
3220.00
12.00 hr
Tractor with Rotavator
425.00
6.00 hr
Vibratory roller 8T
2609.10
3.00 hr
Water tanker 6 KL
630.00
Total
(C) Material
Coarse graded Granular sub-base
material as per Table 400-2 of MORT&H

day
day
day

hr
hr
hr
hr

150.00
777.00
2560.00
3487.00
19320.00
5100.00
15654.60
1890.00
41964.60

1516.86

Cum

386799.30

255.00 cum

9.5mm to 4.75mm @ 66%


(Av. rate of 9.5-11.2mm , 5-7mm & 2.36 5mm HBG M/C metal)

129.00 cum

2.36mm and below @34%


(Rate of 2.36mm & below HBG metal)

1185.19

Cum

152889.51

Total
(D) Over head charges @ 4.615% (10%-VAT)
Add for Over head charges @ 4.615% on (A)+(B)+( C)
4.615 %
(E) Total of (A) + (B)+( C)+(D)
(F) Add Contractors Profit at 10% on (E)
Cost per 300 cum (E) + (F)
Rate per 1 cum
Rate to be adopted

539688.81
27004.23
###
61214.46
###
2244.53
2245.00
1 Cum

Quantity
Description of Item
Rate
per
Amount
2 Providing Vibrated Cement Concrete (1:4:8) mix using 40mm size HBG crushed stone
aggregate and fine aggregate conforming to table 1000-2 of MoRT&H including cost,
seigniorage conveyance of all materials to site and labour charges, centering, machine
mixing, laying, Vibrating, curing etc., including all other incidental and operational charges of
all T&P etc., complete for finished item of work as per MoRT&H specification 1500,1700,
2100 (4th Revision) and as directed by the Engineer-in-Charge for base coarse below CC
Pavement.
Unit = cum
Taking output = 15 cum
(A) Labour
0.64 nos
Mate
day
240.00
375.00
1.00 nos
Mason
day
388.50
388.50
15.00 nos
Mazdoor
day
4800.00
320.00
Total
5428.50
(B) Material
13.50 cum
1680.19 cum
22682.57
Cost of 40mm SS-5 HBG M/C metal
6.75
cum
Sand at site
911.98
cum
6155.87
2.43
MT
Cement at site
5920.00
MT
14385.60
Total
43224.04
Machinery
6.00
hr
Concrete mixer 0.4/0.28 cum
456.20
hr
2737.20
6.00
hr
Generator set 35 KVA
816.80
hr
4900.80
2.00
hr
Water tanker 6 KL
630.00
hr
1260.00
Total
8898.00
(D)
4.615
(E)
(F)

Over head charges @ 4.615% (10%-VAT)


Add for Over head charges @ 5% on (A)+(B)+( C)
%
Total of (A) + (B)+( C)+(D)
Add Contractors Profit at 10% on (E)
Cost per 15 cum (E) + (F)
Rate for 1 cum
Rate to be adopted

2655.96
60206.50
6020.65
66227.15
4415.14
4415.00
1 Cum

3 Vibrated cement concrete M 35 grade using 20mm & 10mm HBG crushed stone aggregate
(Coarse aggregate conforming to table 1000-1 and fine aggregate conforming to table 10002) including cost, seigniorage conveyance of all materials to site and labour charges,
centering, machine mixing, laying, vibrating, curing etc., including all other incidental and
operational charges of all T&P etc., complete for finished item of work as per MoRT&H
specification 1500, 1700, 2100 & 2702 (4th Revision) and as directed by the Engineer-inCharge for C.C Pavement.
Unit = cum
Page 345,346 of MoRT&H SDB
Taking output = 15 cum
(A)
0.86
1.50
20.00

(B)
8.10
5.40
6.75
6.33

Labour
nos
Mate
nos
Mason
nos
Mazdoor
Total
Material
cum
Cost of 20mm SS-5 HBG M/C metal
cum
Cost of 10mm SS-5 HBG M/C metal
cum
Sand at site
MT
Cement at site

375.00
388.50
320.00

day
day
day

322.50
582.75
6400.00
7305.25

2200.19
1770.19
911.98
5920.00

cum
cum
cum
MT

17821.54
9559.03
6155.87
37473.6

Quantity

Description of Item
Total
Machinery
6.00 hr
Concrete mixer 0.4/0.28 cum
6.00 hr
Generator set 35 KVA
(D) Form work
3.50 %
Form work @ 3.50% on (A)+(B)+( C)

(E)
4.615
(F)
(G)

Rate

per

456.20
816.80

hr
hr

85953.29

Cum

Over head charges @ 4.615% (10%-VAT)


Add for Over head charges @ 5% on (A)+(B)+( C)+(D)
%
Total of (A) + (B)+( C)+(D)+(E)
Add Contractors Profit at 10% on (F)
Cost per 15 cum (F)+(G)
Rate for 1 cum
Rate to be adopted

Amount
71010.04
2737.20
4900.80
7638.00
3008.37
4105.58
93067.24
9306.72
###
6824.93
6825.00
1 Cum

4 Providing Uncoated Mild Steel bars ( Fe-250 ) of diferent diameters, wrought and put up bars
of all diameters including cost and conveyance of steel to site and all labour charges for
fabrication of reinforcement including cutting, bending, binding rods, tying grills, placing
them in position etc., complete including cost and conveyance of binding wire and all
handling charges and operational charges etc., and including over lapping welding if required
etc., complete for all R.C.C items for finished item of work as per standard drawings, as per
the directions of the Engineer-in-Charge and as per MoRT&H specification 1600 &2200 (4 th
revision) and as per I.S.1786 of 1985 .
Unit = MT
Page 460 of MoRT&H SDB
Taking output = 1 MT
(A)
0.28
1.50
5.50

Labour
nos
Mate
nos
Black smith
nos
Mazdoor
Total
(B) Material
1.05 MT
Mild steel bars including overlaps
6.00 Kg
Binding wire
Total
(C)
4.615
(D)
(E)

375.00
375.00
320.00

day
day
day

105.00
562.50
1760.00
2427.50

38000.00
36000.00

MT
MT

39900.00
216.00
40116.00

Over head charges @ 5% (10%-VAT)


Add for Over head charges @ 4.615% on (A)+(B)
%
Total of (A) + (B)+( C)
Add Contractors Profit at 10% on (D)
Rate for 1 MT
Rate to be adopted

1963.38
44506.88
4450.69
48957.57
48958.00
1 MT

5 Providing 25.4 mm mastic pads for Longitudinal joints, Transversal expansion joints and
Construction joints of approved quality including cost, conveyance and placing in position,
etc., complete as directed by the Engineer-in-charge.
1.00 sqm

item no. 1001 of ssr 2014-15


Rate to be adopted

991.00

1 SQM

991.00
991.00
1 SQM

Quantity

Description of Item

Rate

per

Amount

6 Sawing of Concrete Pavement using a self propelled walk behind, petro/electric powered saw
of suitable capacity to give a finished groove of 4mm width and 1/4 to 1/3 depth in the cured
concrete in the longitudinal and transverse directions along predetermined lines. The rate is
inclusive of the cost of consumables such as diamond blade. Masons engaged for the
marking is also deemed to be included in the rate and pouring of Polysulphide Sealent to the
full depth of groove. The rate is inclusive of the cleaning of the groove after the sawing to
remove cementatious particles adn cement washings to give a clean dry surface and surface
preparation of the sides of the groove to accommodate the sealent material etc., to give a
neat finished look including cost of sealent, hire and operational charges of Generator of
Adequate capacity and other T&P and labour charges for all operations etc. complete.
60.00
1 RM
7 Forming shoulders with borrowed useful selected earth having MDD of not less than 1.75
gms/CC from outside road boundary by mechnical means with a lead of 17 kms. and lifts
including pre-watering of soil at borrow area, removal of top soil, excavation of soils at
borrowed area, conveyance of soil, depositing the soils on the embankment, spreading soils,
breaking clods, sectioning, grading and consolidation with vibratory road roller @ OMC to
meet requirement of table 300-2 of MORT&H including all hire and operational charges of T&P
and complete for finished item of work as per MORT&H specification 305 (4th revision)
Unit : Cum
Taking out put = 100 Cum
(A) Labour
0.04 day
1.00 day

74
Lead for selected earth
Page 68, 69 of MoRT&H SDB

Mate
Mazdoor unskilled

Km.

375.00
320.00

day
day

15.00
320.00
335.00

13.00

cum

1300.00

7.22

t.km

85484.80

(B) Machinery
100.00 cum
11840.00 t.km
(160 x L)
hr
hr
4.00 hr
1.00 hr

Rate as per G.O. Ms No 10, Dt 26/7/2005


Tipper (for 74 Km = 160 x 74 = 11840)

Add 10% of cost of carriage to cover cost


of loading and unloading
Dozer 80 HP for spreading @ 200 cum
per hour
Motor
Graders for Grading @ 100 cum
per
hour
Water tanker 6 KL
Vibratory roller 8T

(C) Seigniorage charges


100.00 Cum
Seigniorage charges

8548.48
2540.90
3220.00
630.00
2609.10

hr
hr
hr
hr

0.00

cum

(D) Over head charges @ 4.615% (10%-VAT) on (A) + (B)+( C)


(E) Total of (A) + (B)+( C)+(D)
(F) Add Contractors Profit at 10% on (E)
Cost per 100 cum (E) + (F)
Rate per Cum
Rate per 1 cum

0.00
0.00
2520.00
2609.10
100462.38
0.00
4651.80
###
10544.92
###
1159.94
1160.00
1 Cum

8 Supply and fixing cap to reinforcement with PVC Pipe of 25.40mm dia as per technical
specifications and as directed by the Engineer-in-charge.

Quantity
1.00 RM

Description of Item
PVC Pipe 25.40mm dia (item no. 55 ELEC 1.2.4 of SSR 2015-16)
Rate to be adopted

Rate

per

Amount
31.80

31.80

1 RM
32.00
1 RM

DRAIN DATA
Quantity

Description of Item

Rate

per

Amount

1 Providing Vibrated Cement Concrete (1:4:8) mix using 40mm size HBG crushed stone
aggregate and fine aggregate conforming to table 1000-2 of MoRT&H including cost,
seigniorage conveyance of all materials to site and labour charges, centering, machine
mixing, laying, Vibrating, curing etc., including all other incidental and operational charges
of all T&P etc., complete for finished item of work as per MoRT&H specification 1500,1700,
2100 (4th Revision) and as directed by the Engineer-in-Charge for base coarse below CC
Pavement.
Unit = cum
Taking output = 15 cum
(A) Labour
0.64 nos
Mate
day
240.00
375.00
1.00 nos
Mason
day
388.50
388.50
15.00 nos
Mazdoor
day
4800.00
320.00
Total
5428.50
(B) Material
13.50 cum
1680.19
cum 22682.57
Cost of 40mm SS-5 HBG M/C metal
6.75
cum
Sand at site
911.98
cum
6155.87
2.43
MT
Cement at site
5920.00
MT
14385.60
Total
43224.04
Machinery
6.00
hr
Concrete mixer 0.4/0.28 cum
456.20
hr
2737.20
6.00
hr
Generator set 35 KVA
816.80
hr
4900.80
2.00
hr
Water tanker 6 KL
630.00
hr
1260.00
Total
8898.00
(D)
4.615
(E)
(F)

Over head charges @ 4.615% (10%-VAT)


Add for Over head charges @ 5% on (A)+(B)+( C)
%
Total of (A) + (B)+( C)+(D)
Add Contractors Profit at 10% on (E)
Cost per 15 cum (E) + (F)
Rate for 1 cum
Rate to be adopted

2655.96
###
6020.65
###
4415.14
4415.00
1 Cum

2 Earthwork excavation in soils upto SDR by mechanical means for foundations of structures
as per drawing and technical specification including setting out, construction of shoring
and bracing, removal of stumps and other deleterious matter, dressing sides of bottom,
back filling the excavation earth to the extent required etc., complete including
seignioarge charges for finished item of work as per MoRT&H specification 304(4 th Revision)
and as directed by the Engineer-in-Charge
Unit : Cum
Taking out put = 240 Cum
(A) Labour

Page 323 of MoRT&H SDB

0.32 day

Mate

375.00

day

8.00 day

Mazdoor unskilled

320.00

day

2791.00

cum

16746.00

0.00

cum

0.00

(B) Machinery
6.00 Hr
Hydraulic excavator 1.0 cum bucket
capacity
(C) Seigniorage charges
240.00 Cum
Seigniorage charges

120.00
2560.00
2680.00

Quantity

Description of Item

Rate

per

Amount
896.51
###
2032.25
###
93.14
93.00
1 Cum

(D) Over head charges @ 4.615% (10%-VAT) on (A) + (B)+( C)


(E) Total of (A) + (B)+( C)+(D)
(F) Add Contractors Profit at 10% on (E)
Cost per 240 cum (E)+(F)
Rate for 1 cum
Rate to be adopted

3 Vibrated cement concrete M 15 Grade Concrete using 40mm , 20mm and 10mm size HBG
crushed stone aggregate (Coarse aggregate conforming to table 1000-1 and fine
aggregate conforming to table 1000-2) including cost,seignorage and conveyance of all
materials to site and all labour charges for machine mixing,laying in position, Compacting ,
Vibrating and curing including all other incidental and all other operational charges of T&P
required etc., complete as per MoRT&H Specification 1500,1700, 2100 (4 th Revision) for
base course below CC drains
Unit = cum
Page 335,500 of MoRT&H SDB
Taking output = 15 cum
(A)
0.86
1.50
20.00
(B)
8.10
4.05
1.35
6.75
4.13

6.00
6.00

Labour
nos
Mate
nos
Mason
nos
Mazdoor
Total
Material
cum
Cost of 40mm SS-5 HBG
cum
Cost of 20mm SS-5 HBG
cum
Cost of 10mm SS-5 HBG
cum
Sand at site
MT
Cement at site
Total
Machinery
hr
Concrete mixer 0.4/0.28
hr
Generator set 35 KVA

M/C metal
M/C metal
M/C metal

cum

(D) Form work


0.00 %
Form work @ 4% on (A)+(B)+( C)
(E)
4.615
(F)
(G)

375.00
388.50
320.00

day
day
day

322.50
582.75
6400.00
7305.25

1680.19
2200.19
1770.19
911.98
5920.00

cum
cum
cum
cum
MT

13609.54
8910.77
2389.76
6155.87
24449.60
55515.54

456.20
816.80

hr
hr

70458.79

Cum

Over head charges @ 4.6155% (10%-VAT)


Add for Over head charges @ 5% on (A)+(B)+( C)+(D)
%
Total of (A) + (B)+( C)+(D)+(E)
Add Contractors Profit at 10% on (F)
Cost per 15 cum (F)+(G)
Rate for 1 cum
Rate to be adopted

2737.20
4900.80
7638.00
0.00
3251.67
###
7371.05
###
5405.43
5405.00
1 Cum

4 Vibrated cement concrete M 15 Grade Concrete using 40mm , 20mm and 10mm size HBG
crushed stone aggregate (Coarse aggregate conforming to table 1000-1 and fine
aggregate conforming to table 1000-2) including cost,seignorage and conveyance of all
materials to site and all labour charges for machine mixing, laying in position,Compacting,
Vibrating and curing including all other incidental and all other operational charges of T&P
required etc., complete as per MoRT&H Specification 1500,1700, 2200 (4 th Revision) for
Drain body Walls

Quantity

Description of Item

Rate

per

Amount

375.00
388.50
320.00

day
day
day

322.50
582.75
6400.00
7305.25

1680.19
2200.19
1770.19
911.98
5920.00

cum
cum
cum
cum
MT

13609.54
8910.77
2389.76
6155.87
24449.60
55515.54

456.20
816.80

hr
hr

70458.79

Cum

Unit = cum
Page 335,455 of MoRT&H SDB
Taking output = 15 cum
(A)
0.86
1.50
20.00
(B)
8.10
4.05
1.35
6.75
4.13

6.00
6.00

Labour
nos
Mate
nos
Mason
nos
Mazdoor
Total
Material
cum
Cost of 40mm SS-5 HBG
cum
Cost of 20mm SS-5 HBG
cum
Cost of 10mm SS-5 HBG
cum
Sand at site
MT
Cement at site
Total
Machinery
hr
Concrete mixer 0.4/0.28
hr
Generator set 35 KVA

M/C metal
M/C metal
M/C metal

cum

(D) Form work


10.00 %
Form work @ 10% on (A)+(B)+( C)
(E)
4.615
(F)
(G)

Over head charges @ 4.615% (10%-VAT)


Add for Over head charges @ 5% on (A)+(B)+( C)+(D)
%
Total of (A) + (B)+( C)+(D)+(E)
Add Contractors Profit at 10% on (F)
Cost per 15 cum (F)+(G)
Rate for 1 cum
Rate to be adopted

2737.20
4900.80
7638.00
7045.88
3576.84
###
8108.15
###
5945.98
5946.00
1 Cum

5 Vibrated reinforced cement concrete M 20 grade using 20mm & 10mm HBG crushed
stone aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate
conforming to table 1000-2) including cost, seigniorage conveyance of all materials to site
and labour charges, centering, machine mixing, laying, vibrating, curing etc., including
other incidental hire and operational charges of all T&P as per approved drawings and as
directed during execution but excluding cost of steel and its fabrication charges for
finished item as per MoRT&H specification 1500,1600,1700 & 2200 (4 th revision ) and as
directed by the Engineer-in-Charge for Cover slabs over Side drains
Unit = cum
Page 472,457 of MoRT&H SDB
Taking output = 15 cum
(A)
0.86
1.50
20.00
(B)
8.10
5.40
6.75
5.12

Labour
nos
Mate
nos
Mason
nos
Mazdoor
Total
Material
cum
Cost of 20mm SS-5 HBG M/C metal
cum
Cost of 10mm SS-5 HBG M/C metal
cum
Sand at site
MT
Cement at site
Total
Machinery

375.00
388.50
320.00

day
day
day

322.50
582.75
6400.00
7305.25

2200.19
1770.19
911.98
5920.00

cum

17821.54
9559.03
6155.87
30310.40
63846.84

cum
MT

Quantity

Description of Item

6.00 hr
6.00 hr

Concrete mixer 0.4/0.28 cum


Generator set 35 KVA
Total
(D) Form work
4.00 %
Form work @ 10% on (A)+(B)+( C)
(E)
4.615
(F)
(G)

Rate

per

Amount

456.20
816.80

hr
hr

2737.20
4900.80
7638.00

78790.09

Cum

3151.60

Over head charges @ 4.615% (10%-VAT)


Add for Over head charges @ 5% on (A)+(B)+( C)+(D)
%
Total of (A) + (B)+( C)+(D)+(E)
Add Contractors Profit at 10% on (F)
Cost per 15 cum (F)+(G)
Rate for 1 cum
Rate to be adopted

3781.61
###
8572.33
###
6286.38
6286.00
1 Cum

6 Providing HYSD bars ( Fe-415 ) of diferent diameters, wrought and put up bars of all
diameters including cost and conveyance of steel to site and all labour charges for
fabrication of reinforcement including cutting, bending, binding rods, tying grills, placing
them in position etc., complete including cost and conveyance of binding wire and all
handling charges and operational charges etc., and including over lapping welding if
required etc., complete for all R.C.C items for finished item of work as per standard
drawings, as per the directions of the Engineer-in-Charge and as per MoRT&H specification
1600 &2200 (4th revision) and as per I.S.1786 of 1985 for Sub structure of R.C.C items.
Unit = MT
Page 459,460 of MoRT&H SDB
Taking output = 1 MT
(A) Labour
0.34 nos
Mate
day
127.50
375.00
2.00 nos
Black smith
day
750.00
375.00
6.50 nos
Mazdoor
day
2080.00
320.00
Total
2957.50
(B) Material
1.05 MT
HYSD bars including overlaps
34000.00
MT
35700.00
6.00 Kg
Binding wire
36000.00
MT
216.00
Total
35916.00
(C)
4.615
(D)
(E)

Over head charges @ 4.615% (10%-VAT)


Add for Over head charges @ 5% on (A)+(B)
%
Total of (A) + (B)+( C)
Add Contractors Profit at 10% on (D)
Rate for 1 MT (D)+(E)
Rate to be adopted

1794.01
###
4066.75
44734.26
###
1 MT

7 Sand filling in foundation including cost, seignoirage and conveyence of all materials to
site and watering, tamping etc., complete for finshed item of work as per MoRT&H
specification 304 (4th Revision) and as directed by the Engineer - in - Charge.
Unit = cum
Taking output = 1 cum
(A) Labour
0.01 day
Mate
0.30 day
Mazdoor
(B) Material
1.20 Cum
Sand for filling

Page 422 of MoRT&H SDB

375.00
320.00

day
day

751.98

cum

3.75
96.00
99.75
902.38

Quantity
(C)
4.615
(D)
(E)

Description of Item

Rate

per

Over head charges @ 4.615% (10%-VAT)


Add for Over head charges @ 5% on (A)+(B)
%
Total of (A) + (B)+( C)
Add Contractors Profit at 10% on (D)
Cost per 1 cum (D)+(E)

Amount
46.25
1048.38
104.84
1153.22
1153.00

Or say

1 cum
8 Plastering in CM (1:5) 12 mm thick including cost and conveyance of all materials,
seigniorage charges, labour charges, curing etc complete for finished item of work as
directed by the Engineer -in-Charge
Unit = 10 sqm
Taking output = 10 sqm

Page 452 & 333 of MoRT&H SDB

(A) Labour
0.04
0.50
0.50

day
day
day

Mate
Mason
Mazdoor

375.00
388.50
320.00

(B) Material
0.144 Cum
Cement Mortar (1:5)
3124.69
(C) Over head charges @ 4.615% (10%-VAT)
Add for Over head charges @ 5% on (A)+ 819.21
4.615 %
(D) Total of (A) + (B)+( C)
(E) Add Contractors Profit at 10% on (D)
Cost per 10 sqm (D)+(E)
Or say

day
day
day

15.00
194.25
160.00
369.25

Cum

449.96
37.81
857.02
85.70
942.72
943.00
1 Sqm

0.303
1.05

MT
cum

0.04
0.90

day
day

Sub-Analysis
Cement Mortar (1:5)
(a) Material
Cement
5920.00
Sand for Mortar
978.98
(b) Labour
Mate
Mazdoor
Rate per cum

375.00
320.00

MT
cum

1793.76
1027.93
2821.69
15.00
288.00
303.00
3124.69

Asst. Executive Engineer (R&B),


(R&B) Section : Malikipuram

Dy. Executive Engineer (R&B),


(R&B) Sub Division : Razole

Executive Engineer (R&B),


(R&B) Division : Amalapuram

Superintending Engineer (R&B),


(R&B) Circle : Kakinada

Name of Work :

1.Providing CC roads in SC Colony of Kanthetivaripodu in V.V. Meraka in E.G.Dt. 2.


Providing CC road to Choppallavari Group SC Colony in Malikipuram Village in E.G.Dt. 3.
Providing CC Road to SC Colony at Kandikatlavari Group in Lakkavaram Village,
Malikipuram Mandal, E.G.Dt.

Sl.
No.

Short description of Item

Unit

Theoritical
requirement of
Seignorage charges
Material per Unit as
per Cum.
per Data (in Cum.)
Gravel
Gravel
Metal Sand
Metal Sand
/
/
Earth
Earth

Seignor-age
charges per
Unit

Statement showing the Seigniorage charges

Quantity

Amount of
Seigniorage

Sand filling

1 Cum.

0.00

1.000

--

75.00

50.00

--

50.00

43.11

2,155.50

V.C.C. (1:4:8) for bed concrete 1 Cum.

0.90

0.450

--

75.00

50.00

--

90.00

43.11

3,879.90

V.C.C. M15 for base course

1 Cum.

0.90

0.450

--

75.00

50.00

--

90.00

86.22

7,759.80

V.C.C. M20 for body walls

1 Cum.

0.90

0.450

--

75.00

50.00

--

90.00

143.70

12,933.00

V.C.C. M20 for cover blocks

1 Cum.

0.90

0.450

--

75.00

50.00

--

90.00

87.00

7,830.00

12 mm plastering

1 Cum.

--

0.012

--

50.00

--

0.60

GSB

1 Cum.

1.28

--

--

75.00

50.00

--

96.00

360.00

34,560.00

V.C.C. (1:4:8) for base course

1 Cum.

0.90

0.450

--

75.00

50.00

--

90.00

360.00

32,400.00

VRCC M35

1 Cum.

0.90

0.450

--

75.00

50.00

--

90.00

540.00

48,600.00

construction of
earthenshoulders

1 Cum.

--

--

1.00

--

--

30.00

30.00

10

1112.00

360.00

667.20

10,800.00

Total Rs. 161,585.40


or say

Asst. Executive Engineer (R&B),

Dy. Executive Engineer (R&B),

161,586.00

Executive Engineer (R&B), Superintending Engineer (R&B),

Short description of Item

(R&B) Section : Malikipuram

Seignor-age
charges per
Unit

Sl.
No.

Theoritical
requirement of
Seignorage charges
Material per Unit as
per Cum.
Unit
per Data (in Cum.)
Gravel
Gravel
Metal Sand
/
Metal Sand
/
Earth
Earth
(R&B) Sub Division : Razole
(R&B) Division : Amalapuram

Quantity

Amount of
Seigniorage

(R&B) Circle : Kakinada

CERTIFICATE
Name of Work: 1.Providing CC roads in SC Colony of Kanthetivaripodu in
V.V. Meraka in E.G.Dt. 2. Providing CC road to Choppallavari
Group SC Colony in Malikipuram Village in E.G.Dt. 3.
Providing CC Road to SC Colony at Kandikatlavari Group in
Lakkavaram Village, Malikipuram Mandal, E.G.Dt.

1)

Certified that I have personally inspected the above road on


and the provisions made in the estimate for the above work are adequate and
essential.

2)

Certified that the leads provided in the R.M.R of the estimate are shortest and there is
sufficient yield of good quality material from the quarries proposed in the estimate.

3)

Certified that all the distances in the quarry map are correct.

4)

Certified that the quarries provided are the nearest.

5)

Certified that the routes shown in the quarry map are the
transportation of the materials.

6)

Certified that all the materials can be easily quarried.

7)

Certified that the description of all materials mentioned are correct to the best of my
knowledge.

8)

Certified that the selected earth is proposed from Kadiyam quarry nearest from the
workspot .

9)

Certified that no land acquisition is required for the proposed work and the lands
available are free from encumbrance encroachments and utilization.

10)
11)

shortest for the

Certified that the C.B.R. Value of Proposed internal C.C.Roads in SC Colonies is about
5.00%
Construction of CC road is proposed in the internal roads of the SC/ST Colonies and as
such there is no commercial vehicular traffic on these internal roads. Hence,
construction of CC Pavement is proposed with a nominal crust of 100mm GSB + 100
mm thick VCC (1:4:8) + 150mm thick VCC M35.

Asst. Executive Engineer (R&B),


(R&B) Section : Malikipuram

Dy. Executive Engineer (R&B),


(R&B) Sub Division : Razole

Executive Engineer (R&B),


(R&B) Division : Amalapuram

Superintending Engineer (R&B),


(R&B) Circle : Kakinada

LEAD CHARGES (SSR 2015-16)

loading
unloading
stacking
0.25
0.5
1
2
3
4
5
6
7

Earth/Gravel/
Metal
Sand
51.40
102.80
15.70
15.70
xx
xx
xx
xx
xx
xx
31.00
29.90
43.40
41.90
57.90
57.90
70.30
70.30
82.70
82.70
95.10
95.10
107.50
107.50

8
9
10

119.90
132.30
144.70

119.90
132.30
144.70

11

157.10

157.10

12

169.50

169.50

13
14
15
16
17
18
19

181.90
194.30
206.70
219.10
231.50
243.90
256.30

181.90
194.30
206.70
219.10
231.50
243.90
256.30

20

268.70

268.70

21

281.10

281.10

22
23
24
25
26
27

293.50
305.90
318.30
330.70
343.10
355.50

293.50
305.90
318.30
330.70
343.10
355.50

Cost of Materials, Labour


SSR 2015-16
Material Rates
60 to 63 mm IRC & MoRTH HBG metal
50 to 55 mm IRC & MoRTH HBG metal
40 to 45 mm IRC & MoRTH HBG metal
Roughstone 300mm (HBG)for revetment
Roughstone 225mm (HBG)for revetment
SS Revetment work 225mm
SS Revetment work 300mm
SS Revetment work 450mm
Laterite for Revetment 225mm
Laterite for Revetment 300mm
Jeddy stone above 450mm to 600mm
Quarry spall(Field picked metal)
Av. Of rate 25mm & 40mm
150 mm soling stone HBG metal
40 to 45 mm IRC & MoRTH HBG M/C metal

419.00
456.00
588.00
172.00
177.00
144.00
164.00
156.00
136.00
159.00
206.00
49.50
95.00
588.00

As per SSR of PR Dept.


Pg. No.17, Sl.53 (Roads)
Pg. No.17, Sl.52 (Roads)
Pg. No.16, Sl.51 (Roads)
Pg. No.13, Sl.9 (Roads)
Pg. No.13, Sl.8 (Roads)
Pg. No.13, Sl.2 (Roads)
Pg. No.13, Sl.3 (Roads)
Pg. No.13, Sl.4 (Roads)
Pg. No.13, Sl.6 (Roads)
Pg. No.13, Sl.7 (Roads)
Pg. No.13, Sl.5 (Roads)
(42+48)/2 Pg.18
Sl. No.84 & 85
Pg. No.18, Sl.79 (Roads)
Pg. No.16, Sl.51 (Roads)

25 to 27 mm IRC & MoRTH HBG M/C metal

944.00 Pg. No.16, Sl.50 (Roads)

19 to 22 mm IRC & MoRTH HBG M/C metal

984.00 Pg. No.16, Sl.49 (Roads)

12 to 14 mm IRC & MoRTH HBG M/C metal

780.00 Pg. No.16, Sl.48 (Roads)

9.5 to 11.20 mm IRC & MoRTH HBG M/C metal


5 to 7 mm IRC & MoRTH HBG M/C metal
2.36 to 5 mm IRC & MoRTH HBG M/C metal
HBG Stone chips 2.36mm and below
Gravel
40 mm SS-5 m/c HBG metal

656.00
504.00
308.00
350.00
103.00
620.00

25 mm SS-5 m/c HBG metal

994.00 Pg. No.15, Sl.29 (Roads)

20 mm SS-5 m/c HBG metal

1036.00 Pg. No.15, Sl.28 (Roads)

12 mm SS-5 m/c HBG metal

822.00 Pg. No.15, Sl.27 (Roads)

10 mm SS-5 m/c HBG metal


6 mm SS-5 m/c HBG metal
Sand for Concrete
Sand for Filling
HYSD Steel

692.00
532.00
610.00
460.00
41000.00

Pg. No.16, Sl.47 (Roads)


Pg. No.16, Sl.46 (Roads)
Pg. No.16, Sl.45 (Roads)
Pg. No.18, Sl.92 (Roads)
Pg. No.18, Sl.90 (Roads)
Pg. No.15, Sl.30 (Roads)

Pg. No.14, Sl.26 (Roads)


Pg. No.14, Sl.25 (Roads)
Pg. No.19, Sl.94 (Roads)
Pg. No.19, Sl.95 (Roads)

28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68

367.90
380.30
392.70
403.00
413.30
423.60
433.90
444.20
454.50
464.80
475.10
485.40
495.70
506.00
516.30
526.60
536.90
547.20
557.50
567.80
578.10
588.40
598.70
609.00
619.30
629.60
639.90
650.20
660.50
670.80
681.10
691.40
701.70
712.00
722.30
732.60
742.90
753.20
763.50
773.80
784.10

367.90
380.30
392.70
403.00
413.30
423.60
433.90
444.20
454.50
464.80
475.10
485.40
495.70
506.00
516.30
526.60
536.90
547.20
557.50
567.80
578.10
588.40
598.70
609.00
619.30
629.60
639.90
650.20
660.50
670.80
681.10
691.40
701.70
712.00
722.30
732.60
742.90
753.20
763.50
773.80
784.10

Mild Steel
Cement
Mild Steel 6mm
Blasting charges
Blasting charges
Blasting charges for rough stone
Seigniorage charges
Metal
Gravel/earth
Sand
Labour Rates
Mate
Mazdoor skilled (385 x 30% + 345 x 70%)
Mazdoor unskilled
Machinery Rates
Dozer 80 HP for spreading @ 200 cum per hour
Motor grader 3.35M Blade @50 cum/Hr
Hydralic excavator
Front end loader 1 cum capacity
Tipper 5 cum
Vibratory roller 8T
smooth wheeled roller 8 Ton
Water tanker 6 KL
Tractor
Tractor with Rotavator
Tractor with ripper attachment @ 60 cum per hour
Air compressor 250 cfm
Wet mix plant of 60 tonne hr. capacity
Mechanical broom @ 1250 sqm/hr.
Bitumen pressure distributor @1750 sqm/hr
Emulsion pressure distributor @1750 sqm/hr
Hot mix plant 40 to 60 TPH
Mechanical Paver finisher 100 TPH
Hydraulic self propelled chip spreader @ 1500 sqm/hr.
Finish rolling with 6-8 tonne smooth wheeled tandem roller.
Pneumatic road Roller
GSB Plant 50 Cum
Generator 250 KVA
Generator set 125 KVA
Generator set 35 KVA
Concrete mixer 0.4/0.28 cum

42500.00 As per the G.O.s


5920.00 October, 2014 GO RT
42500.00 No.869, dt.31.12.2014
70.00 Pg. No.19, Sl.95 (Roads)
xx
50.00
22.00 As per the G.O.s
40.00
375.00
388.50
320.00

Pg. No.10, Sl.71 (Roads)

2540.90
3220.00
2791.00
1650.00
909.70
2609.10
1101.00
630.00
415.00
425.00
425.00
538.20
1650.00
375.00
1500.00
860.00
19200.00
2250.00
2695.00
1650.00
1347.00
1257.00
1850.00
1320.00
816.80
456.20

Pg. No.25, Sl.1 (Roads)


Pg. No.25, Sl.3 (Roads)
Pg. No.25, Sl.4 (Roads)
Pg. No.25, Sl.5 (Roads)
Pg. No.25, Sl.6 (Roads)
Pg. No.25, Sl.7 (Roads)
Pg. No.25, Sl.8 (Roads)
Pg. No.25, Sl.10 (Roads)
Pg. No.25, Sl.11 (Roads)
Pg. No.25, Sl.12 (Roads)
Pg. No.25, Sl.13 (Roads)
Pg. No.25, Sl.14 (Roads)
Pg. No.26, Sl.15 (Roads)
Pg. No.26, Sl.16 (Roads)
Pg. No.26, Sl.17 (Roads)
Pg. No.26, Sl.18 (Roads)
Pg. No.26, Sl.22 (Roads)
Pg. No.26, Sl.24 (Roads)
Pg. No.26, Sl.25 (Roads)
Pg. No.26, Sl.26 (Roads)
Pg. No.26, Sl.27 (Roads)
Pg. No.26, Sl.30 (Roads)
Pg. No.27, Sl.43 (Roads)
Pg. No.27, Sl.43 (Roads)
Pg. No.28, Sl.43 (Roads)
Pg. No.27, Sl.38 (Roads)

Pg. No.10, Sl.73 (Roads)

69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
90
91
92
93
94
95
96
97
98
99
100
101
102
103
104
105
106
107
108
109
110

794.40
804.70
815.00
825.30
835.60
845.90
856.20
866.50
876.80
887.10
897.40
907.70
918.00
928.30
938.60
948.90
959.20
969.50
979.80
990.10
1000.40
1010.70
1021.00
1031.30
1041.60
1051.90
1062.20
1072.50
1083.00
1093.50
1104.00
1114.50
1125.00
1135.50
1146.00
1156.50
1167.00
1177.50
1188.00
1198.50
1209.00
1219.50

794.40
804.70
815.00
825.30
835.60
845.90
856.20
866.50
876.80
887.10
897.40
907.70
918.00
928.30
938.60
948.90
959.20
969.50
979.80
990.10
1000.40
1010.70
1021.00
1031.30
1041.60
1051.90
1062.20
1072.50
1083.00
1093.50
1104.00
1114.50
1125.00
1135.50
1146.00
1156.50
1167.00
1177.50
1188.00
1198.50
1209.00
1219.50

Tipper 5.50 cum capacity per 10 Tonnes per tkm


Tipper 5 cum capacity for Soil, GSB, WMM, Hot mix
Plate compactor/Power rammer

4.50
4.50
58.00

(As per SSR 2008-2009)


(As per SSR 2008-2009)
Pg. No.28, Sl.48 (Roads)

Sand for Mortar

677.00

Pg. No.19, Sl.93 (Roads)

Tipper 10Tonne capacity for carriage of stone


chips from stock pile on road side to chip
spreader

111
112
113
114
115
116
117
118
119
120
121
122
123
124
125
126
127
128
129
130
131
132
133
134
135
136
137
138
139
140
141
142
143
144
145
146
147
148
149
150

1230.00
1240.50
1251.00
1261.50
1272.00
1282.50
1293.00
1303.50
1314.00
1324.50
1335.00
1345.50
1356.00
1366.50
1377.00
1387.50
1398.00
1408.50
1419.00
1429.50
1440.00
1450.50
1461.00
1471.50
1482.00
1492.50
1503.00
1513.50
1524.00
1534.50
1545.00
1555.50
1566.00
1576.50
1587.00
1597.50
1608.00
1618.50
1629.00
1639.50

1230.00
1240.50
1251.00
1261.50
1272.00
1282.50
1293.00
1303.50
1314.00
1324.50
1335.00
1345.50
1356.00
1366.50
1377.00
1387.50
1398.00
1408.50
1419.00
1429.50
1440.00
1450.50
1461.00
1471.50
1482.00
1492.50
1503.00
1513.50
1524.00
1534.50
1545.00
1555.50
1566.00
1576.50
1587.00
1597.50
1608.00
1618.50
1629.00
1639.50

Pg. No.275, M-055 (Rs.845)

Pg. No.272, M-003

Pg. No.275, M-055 (Rs.845)


Pg. No.275, M-054 (Rs.1313)
Pg. No.275, M-053 (Rs.1365)
Pg. No.275, M-052 (Rs.1097)
Pg. No.274, M-051 (Rs.935)
Pg. No.274, M-050 (Rs.735)
Pg. No.273, M-024 (Rs.474)
Pg. No.261, Sl.No.67
Pg. No.272, M-008
Pg. No.275, M-055 (Rs.845)
Pg. No.275, M-054 (Rs.1313)
Pg. No.275, M-053 (Rs.1365)
Pg. No.275, M-052 (Rs.1097)
Pg. No.274, M-051 (Rs.935)
Pg. No.274, M-050 (Rs.735)
Pg. No.259, Sl. 27(a)
Pg. No.259, Sl. 27(b)

As per the G.O.s


October, 2014 GO RT
No.869, dt.31.12.2014
Pg. No.273

As per the G.O.s

Semi-skilled Mazdoor
Skilled 30% + Semi 70%
Un-skilled Mazdoor
Pg. No.288, Sl.No.8
Pg. No.289, Sl.No.52
Pg. No.289, Sl.No.54
Pg. No.290, Sl.No.62
Pg. No.289, Sl.No.50

Pg. No.288, Sl.No.2

Pg. No.289, Sl.No.24


Pg. No.289, Sl.No.18

ABOUT ESTIMATE
1

Name of the wor 1.Providing CC roads in SC Colony of Kanthetivaripodu in V.V. Meraka in E.G.Dt. 2.
Providing CC road to Choppallavari Group SC Colony in Malikipuram Village in
E.G.Dt. 3. Providing CC Road to SC Colony at Kandikatlavari Group in Lakkavaram
Village, Malikipuram Mandal, E.G.Dt.

Section

Asst. Executive Engineer (R&B),


(R&B) Section : Malikipuram

Sub - Division

Dy. Executive Engineer (R&B),


(R&B) Sub Division : Razole

Division

Executive Engineer (R&B),


(R&B) Division : Amalapuram

Circle

Superintending Engineer (R&B),


(R&B) Circle : Kakinada

ROADS & BUILDINGS DEPARTMENT


Name of the work:

1.Providing CC roads in SC Colony of Kanthetivaripodu


in V.V. Meraka in E.G.Dt. 2. Providing CC road to
Choppallavari Group SC Colony in Malikipuram Village
in E.G.Dt. 3. Providing CC Road to SC Colony at
Kandikatlavari Group in Lakkavaram Village,
Estimate Amount :
### Lakhs
Malikipuram Mandal, E.G.Dt.

R&B Section : Gannavaram


R&B Sub division : Kothapeta
R&B Division : Amalapuram
R&B Circle : Kakinada
Gannavaram Assembly Constituency
Amalapuram Parliamentary Constituency

Name of Work : 1.Providing CC roads in SC Colony of Kanthetivaripodu in V.V. Meraka in E.G.Dt.


2. Providing CC road to Choppallavari Group SC Colony in Malikipuram Village in
E.G.Dt. 3. Providing CC Road to SC Colony at Kandikatlavari Group in
Statement showing the Seigniorage charges

Short
SI
description of
No
Item

Unit

V.C.C. (1:4:8)
1 Cum.
for base course

2 VRCC M35

1 Cum.

construction of
3 earthenshoulde 1 Cum.
rs

Theoritical
requirement of
Seignorage
Material per Unit as charges per Cum. Seignorage
per Data (in Cum.)
Quantity
charges
Grave per Unit
Gravel Meta
Metal Sand
Sand
l/
/ Earth
l
Earth

0.90

0.45

--

75.00 50.00

--

90.00

360.00

0.90

0.45

--

75.00 50.00

--

90.00

540.00

--

--

1.00

30.00

30.00

360.00

--

--

Total Rs.
or say

Asst. Executive Engineer (R&B),


(R&B) Section : Malikipuram

Dy. Executive Engineer (R&B),


(R&B) Sub Division : Razole

Executive Engineer (R&B),


(R&B) Division : Amalapuram

Superintending Engineer (R&B),


(R&B) Circle : Kakinada

Meraka in E.G.Dt.
ikipuram Village in
roup in

Amount of
Seigniorage

32,400.00

48,600.00
10,800.00
91,800.00
91,800.00

neer (R&B),
: Amalapuram

COST OF BITUMEN / MT
Name of Work
1.Providing CC roads in SC Colony of Kanthetivaripodu in V.V.
Meraka in E.G.Dt. 2. Providing CC road to Choppallavari Group SC
Colony in Malikipuram Village in E.G.Dt. 3. Providing CC Road to SC
Colony at Kandikatlavari Group in Lakkavaram Village, Malikipuram
Mandal, E.G.Dt.
Ref ::- For Emulsion (Bulk) :- HINCOL Price List With Effect From Dt.1-02-2016
For Bulk Bitumen 80/100, 60/70:- HPCL Price List With Effect From Dt. 1-02-2016
Bulk 80/100 Gr.

Bulk 60/70 Gr.

Emulsion (Bulk)

Visakhapatnam Visakhapatnam Visakhapatnam


Basic Price

21,803.00

22,003.00

Excise Duty @ 14%

3,052.42
----------------24,855.42

3,080.42
----------------25,083.42

VAT @ 5%

1,242.77
----------------26,098.19

1,254.17
----------------26,337.59

762.00

762.00

26,860.19

27,099.59

Lead from
Visakhapatnam
254.00 Kms
Lead charges for Bulk @
1.50

per KM

Asst. Executive Engineer (R&B),


(R&B) Section : Malikipuram

Executive Engineer (R&B),


(R&B) Division : Amalapuram

Dy. Executive Engineer (R&B),


(R&B) Sub Division : Razole

Superintending Engineer (R&B),


(R&B) Circle : Kakinada

LEAD CALCULATION FOR VARIOUS MATERIALS UPTO CENTER OF THE WORKING STRETCH
Name of the wor 1.Providing CC roads in SC Colony of Kanthetivaripodu in V.V. Meraka
in E.G.Dt. 2. Providing CC road to Choppallavari Group SC Colony in
Malikipuram Village in E.G.Dt. 3. Providing CC Road to SC Colony at
Kandikatlavari Group in Lakkavaram Village, Malikipuram Mandal,
E.G.Dt.
-:oOo:Reach proposed in the present estimat
km 64 / 0 to 68 / 305
Center Km. of the working stretch
66.153
A) For HBG metal:
HBG metal from Katheru quarry
a) Cart track length =
b) Metalled road length:
From km 907 / 000
to
910 / 700 of NH -16
From km
0 / 000
to
3 / 100 of RK Road (V) Punyakshetram
Total metalled road length
Lead upto km
1 / 495
of Bye-Pass Road
Add for centre of working reach
c) Total lead

B) For gravel:
Gravel quarry at Kesavaram
a) Cart track length =
b) Metalled road length:
From km
0 / 000
to
14 / 600 of RK Road (V)Punyakshetram
Lead upto km 68 / 305
of Kakinada - Rajahmundry ro
Add for centre of working reach
Total metalled road length
c) Total lead

C) For Sand :
Sand from Kulla
a) Cart track length =
b) Metalled road length:
Lead upto km 68 / 305
of
Add for centre of working reach
c) Total lead

Kakinada - Rajahmundry ro

d) Lead charges for 9.000 kms lead ( including stacking charges)


D) For Bitumen & Emulsion :
a) Lead from ex-factoryVisakha
b) Metalled road length:
From km
/
to
/
From km 719 / 400
to
910 / 700
From km
0 / 000
to
3 / 100
Total metalled road length
Lead upto km 68 /
305 of RK Road
Add for centre of working reach
c) Total lead

Asst. Executive Engineer (R&B),


(R&B) Section : Malikipuram

4.305 kms

3.000 kms

=
=

3.700 kms
3.100 kms

6.800
9.800
=
2.153
= 11.953
Or say: 65.000
Rs. 753.20 /

d) Lead charges for65.000 kms lead ( including stacking charges)

d) Lead charges for56.000 kms lead ( including stacking charges)

kms
kms
kms
kms
kms
cum

1.700 kms

kms
kms
kms
kms
kms
kms
cum

0.700 kms

14.600
16.300
2.153
18.453
= 18.453
Or say: 56.000
Rs. 660.50 /

0.700
=
2.153
= 2.853
Or say:
9.000
Rs. 132.30 /

kms
kms
kms
kms
cum

of Refinery to V-V road (NH.5)


=
1.600 kms
of Vijayawada - Visakhapatnam road (NH.1 = 191.300 kms
of RK Road (V)Punyakshetram
=
3.100 kms
196.000 kms
(V)Punyakshetram
196.000 kms
=
2.153 kms
= 198.153 kms
Or say:
### kms

Dy. Executive Engineer (R&B),


(R&B) Sub Division : Razole
Superintending Engineer (R&B),
(R&B) Circle : Kakinada

Executive Engineer (R&B),


(R&B) Division : Amalapuram

GENERAL ABSTRACT
Sub-Work

Sl.
No.

Main Work: Widening and Strengthening of Kakinada Rajahmundry Road from KM 61/600 to 68/305 in East Godavari
District
Sub-Work (2): Widening and Strengthening of Kakinada Rajahmundry Road from KM 64/000 to 68/305 in East Godavari
District
Item Description
Amount

Part - A

Cost of Road work

Construction of CD works (Sub estimate)

Cost of Road Safety Interventions

Part - B

#REF!
25,41,141

Total

15,25,184
---------------#REF!

LS Provisions
5

Provisions for VAT @ 5.00% on Total

#REF!

Provisions for Seigniorage charges

L.S.

Asst. Executive Engineer (R&B),


(R&B) Section : Malikipuram

Dy. Executive Engineer (R&B),


(R&B) Sub-divn., : Rajahmundry

Executive Engineer (R&B),


(R&B) Division : Rajahumndry

Superintending Engineer (R&B),


(R&B) Circle : Kakinada

,91,800

DETAILED CUM ABSTRACT ESTIMATE


Name of work:-

Main Work: Widening and Strengthening of Kakinada Rajahmundry Road from KM 61/600 to 68/305 in East
Godavari District
Sub-Work (2): Widening and Strengthening of Kakinada Rajahmundry Road from KM 64/000 to 68/305 in East
Godavari District

Sub Work
Sl.
No.
1

Providing Road Safety Intervention

Description of Item

No

Qty.

Rate

Per

Amount
(in Rupees)
10

1 Supplying of hot applied thermoplastic road marking compound, 2.5mm thick


including reflectorising glass beads @ 250gms with Reflectorising Glass Beads on
Bituminous Surface at 250 gms per sqm area, thickness of 2.5mm is exclusive of
surface applied glass bead as per IRC: 35, the material should be of BERGER
Company/ BERGER Equivalent/ Equivalent brand and must comply with the
following: a) White index for the product should be in the range of 60-70 when
measured against standard reference. The applied panel 7/8 number must be
submitted for checking up the white index in the department lab. In case the
department approves the white index of any vendor, the department engineer may
carryout random checking of the applied products at site against the approved
panel. In case of any major deviation, beyond acceptance limit, department
reserve the right to cancel or reject the total supplied consignment of the said
material and will compell the vendor has to replace the full consignment by the
desired material as per approved panel at his own cost and additional demurrages
may be claimed due to loss of man days (as per the rules of the department). b)
Luminance factor of the material should be in the range of 80-85% at 45 degree
centigrade as per AASTHOM 249. c) Crack resistance: The applied panel cured for 7
days under ambient condition and then should be tested as per BS3262, Part-1,
1989 and should pass at the range of '0' degree centigrade to '-10' degree
centigrade D) Adhesion : Strong E) Softening point: 102 degree centigrade F) Dried
film finish : Smooth and uniform G) Night Vision: High as directed by the Engineerin-Charge and confirming to IS: 164-1961 (1st revision reaffirmed in 1986) and
clause conforming to IRC 35-1997
Centre Broken lines
In Km 64/0-68/305
Adjacent to divider
In Km 64/0-68/305
In Km 64/0-68/305
Zebra Crossings

3/7.5

4000

0.100

320.00

1
1

2
2

2500
2500

0.100
0.100

30

14

500.00
500.00
420.00
###

0.5

702

1 Sqm

2 Supplying & Fixing of Molded Shanks Raised Pavement Markers made of


polycarbonate and ABS moulded body and reflective panels with micro prismatic
lens capable of providing total internal reflection of the light entering the lens face
and shall support a load of 16000 kg tested in accordance to ASTM D 4280 Type H
and complying to Specifications of Category A of MORTH Circular No
RW/NH/33023/10-97 DO III Dt 11.06. 1997. The height, width and length shall not
exceed 50 mm, 100 mm and 100 mm and with minimum reflective area of 13
Sqcm on each side and the slope to the base shall be 35 +/- 5 degree. The strength
of detachment of the integrated cylindrical shanks, (of diameter not less than 19
+/- 2 mm and height not less than 30+/- 2 mm) from the body is to be a minimum
value of 700 Kgs. Fixing will be by drilling holes on the road for the twin shanks to
go inside, without nails and using epoxy resin based adhesive as per
manufacturers recommendation and complete as directed by the engineer.
In Km 64/0-68/305
2
275
0
(2060/7.5=275 nos)
In KM 66/060 to 68/305

250

250

1221480

Sl.
No.
1

Description of Item

No

Qty.

Rate

8
316.00
250.00

Per
9
Each

Amount
(in Rupees)
10
79000

Sl.
No.
1

Description of Item

No

Qty.

Rate

Per

Amount
(in Rupees)
10

3 Providing and fixing Village name board size 900x450 mm made out of Type IV of
ASTMD 4956-09 High Intensity Prismatic Prismatic Retro reflective sheeting and
confirming to IRC 67:2012 for full background of Green Colour & White Letters and
fixed over 3MM Alluminium Composite Material sheet having minimum 0.30 mm
thick Aluminium skin on both sides with back side painted grey colour and fixed
over back support frame of M.S angle 25x25x3mm all round and fixing with
35x35x4mm and mounted on a MS angle post of size 75x75x6mm with clear height
of not less than 2.1 m from the ground level to the bottom of the board. The
signpost should be painted with one coat of red oxide paint and 2 coats of
synthetic enamel paint Black and White colour with bands of 30cm of height. The
signpost shall be firmly fixed with MS base angle 35x35x4 mm in to the ground by
M-15 Concrete foundation of size 450x450x600mm including cost and conveyance
of all materials ,equipment, machinery and labour with all leads and lift, loading
charges necessary for satisfactory completion of the work as directed by Engineer
-in-Charge.
In km 64/0 to 68/305

2.00

5477.00

Each

10954

4 Supplying and installation of Hazard Markers/Delinators using M.S. angle of size


55x55x6mm and 120cm high above ground level painted with two coats of black &
white stripes of 15cm wide with first quality synthetic enamel paint over one coat
of appropriate primer of approved brand,colour, with 30cm x 90cm Type XI of
ASTMD 4956-09 wide angle cube cornered micro Prismatic
Retro reflective
sheeting of Yellow colour and confirming to IRC 67:2012 fixed over 3MM
Alluminium Composite Material having minimum 0.30 mm thick Aluminium skin on
both sides with standard supports consisting of alternately black and Yellow with
black stripes in screen printing sloping downward at an angle of 45 degrees
towards the side of the obstruction on which the traffic is to pass and buried into
the ground in a trench of size 30cm x 30cm and 50cm depth filled with CC M-20
including cost and conveyance of all materials, equipment, machinery and labour
with all leads and lifts, loading and un-loading charges necessary for successfull
completion of the work on any road in division as directed by Engineer-in-Charge
and conforming to IRC 67-2012 &MORT&H specification No.805 and approved
drawings etc., complete for finished item of work.
In Km.64/0-68/305)
At divider openings

10

20.00
20.00

4003.00

Each

80060

5 Providing fixing of Median Marker made of polycarbonate for impact resistance and
good weatherability. Polycarbonate used for molding the Median Marker shall have
a minimum Izod impact strength value of 600 J/m at room temperature. The impact
strength of the polycarbonate should not decrease to less than 70 % of its initial
value on being subjected to UV weathering as per ASTM G 155 for 1000 hours or
exposure to 2 years of natural weathering. The body of the median marker shall be
in the form of an isosceles trapezoidal structure of length 15 cm, height and width
of 10x10 cm. The Median Marker shall have fluorescent yellow retro-reflective
sheeting conforming to type XI specifications as per ASTM D4956. Area of reflective
sheeting should not be less than 70 cm2. Edge of retro-reflective sheeting shall be
concealed using a grill/ mesh/ similar mechanism to prevent vandalism and
sheeting pilferage. The logo of the manufacturer shall be embossed and printed in
contrasting color on both sides of median marker for distinct identification (even
from moving vehicles).
In Km.64/0-68/305)

145

290.00
290.00

461.00
Total

Asst. Executive Engineer (R&B),


(R&B) Section : South

Each
Rs.

133690
1,525,184

Dy. Executive Engineer (R&B),


(R&B) Sub-divn., : Rajahmundry

Sl.
No.
1

Description of Item

No

2
3
Executive Engineer (R&B),
(R&B) Division : Rajahumndry

Qty.

Rate

Per

Amount
(in Rupees)
10

Superintending Engineer (R&B),


(R&B) Circle : Kakinada

DETAILED-CUM-ABSTRACT ESTIMATE
me of the work:

Sl.
No
1

Description of item

No

Length

Breadth Depth
5

Quantity
7

Rate /
per
8

Part - A
1 Providing B.T. patchwork using 1.20 Cum of 40mm IRC size HBG metal to get compacted
quantity of 1 Cum precoated with bitumen 80/100 grade using a total quantity of 42 Kgs.
including tack coat, cost and conveyance of all materials and stacking the metal an
Km. 64 / 0 to 68 / 305
40.000
or say

40.000
40.000 Cum

#REF!
/Cum.

2 Earthwork excavation in soils upto SDR by mechanical means excluding trimming bottom and
side slopes in accordance with requirements of lines , grades and cross sections etc.,
excluding seignioarge charges for finished item of work for trench cutting a
Km. 64 / 0 to 66 / 060
( 1 x 2 ) 2060.00
2.975
0.550
or say

6741.350
6741.350
6750.000 Cum

19.30
/Cum.

3 Forming embankment with approved materials deposited at site from roadway cutting
including depositing the soils on the embankment, spreading soil, breaking clods, sectioning ,
grading and consolidation with 8 to 10 Tonnes Vibratory Road Roller @ OMC to m
Assuming 25% of excavated earth is useful for forming embankment .
1687.500
6750.000 x 25%
or say
1690.000 Cum

113.00
/Cum.

4 Construction of Granular sub-base by providing Coarse graded HBG material confirming to

Grading - III of MoRT&H Table 400-2 including cost, seigniorage charges and conveyance of all

materials to work site and spreading in uniform layers with motor grader
Km. 64 / 0

to 66 / 060

( 1 x

) 2060.00

2.975

0.300
or say

3677.100
3677.100
3680.000 Cum

2245.00

5 Providing, Laying, Spreading and compacting graded HBG crushed stone aggregate to Wet Mix

macadem specification including cost,seignorage of all materials and including premixing the

material with water at OMC in Mechanical mix plant carriage of mixed mat
Km. 64 / 0

to 66 / 060

( 1 x

) 2060.00

2.975

0.250
or say

3064.250
3064.250
3070.000 Cum

#REF!

6 Providing and applying Prime coat with bitumen Emulsion (Medium settting) (Bulk) using
Emulsion pressure distributor at the rate of 0.60 kgs per sqm on the prepared
bituminous/granular surface cleaned with mechanical broom for finished item of work as per
MoRT&H Specification 503 (4th revision) and as directed by the Engineer-in-Charge.
Km. 64 / 0

to 66 / 060

( 1 x

) 2060.00

2.975

12257.000

or say
7 Providing and applying tack coat with bitumen 80/100 (Bulk) using

12257.000
12260.000 Sqm

#REF!

Bitumen pressure

distributor at the rate of 0.20 kgs per sqm on the prepared bituminous/granular surface
cleaned with mechanical broom for
Before laying B.M. & B.C.
Km. 64 / 0 to 66 / 060
(
Km. 66 / 060to 66 / 600
(
Km. 68 / 0 to 68 / 305
(
Add for Bell mouths at Junctions

finished item of work as per MoRT&H Specification


1 x
1 x
1 x

2
2
1

) 2060.00
) 540.00
) 305.00

14.500
14.000
22.000

----

or say

59740.000
15120.000
6710.000
930.000
82500.000
82500.000 Sqm

#REF!

8 Providing and laying of 50mm thick Bituminous Macadam with hot mix plant producing an

average output of 37.5 tonnes per hour using hard blasted granite crushed aggregates of

Grading - II as per table 500-4 of MoRT&H specificaion 504 (4th Revision) pre
Km. 64 / 0 to 66 / 060
( 1 x 1 ) 2060.00
Km. 66 / 060to 66 / 600
( 1 x 1 ) 540.00
Add for Bell mouths at Junctions and Patch wo 2550.00

14.500
14.000

0.050
0.050
or say

1493.500
378.000
28.500
1900.000
1900.000 Cum

#REF!

9 Providing 30 mm thick compacted Bituminous Concrete by hot mix plant using hard blasted

granite crushed aggregates of Grading - 2 as per table 500-17 of specification 509 of MoRT&H

(4th Revision), premixed with bituminous binder 60/70 grade as per


Km. 64 / 0 to 66 / 060
( 1 x 1 ) 2060.00
14.500
Km. 66 / 060to 66 / 600
( 1 x 1 ) 540.00
14.000
Km. 68 / 0 to 68 / 305
( 1 x 1 ) 305.00
22.000
Add for Bell mouths at Junctions
2855.00

desi
0.030
0.030
0.030
or say

896.100
226.800
201.300
25.800
1350.000
1350.000 Cum

#REF!

10 Construction of earthen shoulders with selected earth with laboratory MDD not less than 17.5
KN / cum. obtained from approved source by mechanical means with all leads and lifts
including excavation of soils at borrowed area, conveyance of soil, depositin
Km. 64 / 0

to 66 / 060

( 1 x

) 1000.00

1.000

0.100
or say

200.000
200.000
200.000 Cum

1160.00

11 Vibrated cement concrete M 15 Grade Concrete using 40mm , 20mm and 10mm size HBG
crushed stone aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate
conforming to table 1000-2) including cost, and conveyance of all materials to site and all
labour charges , centering, machine mixing, laying in position, Compacting, Vibrating and
curing including all other incidental and all other operational charges of T&P required etc.,
complete as per MoRT&H Specification 1500,1700, 2200 (4th Revision) for Dividers .
Km. 64 / 0 to 66 / 060 Rectangl( 1 x ### )
Length after gaps
Trapizoid( 1 x ### )

1.25
0.250
0.450
1.25 (0.25+0.45)/20.275
or say

210.937
180.469
391.406
400.000
#REF!
400.000 Cum.

12 Scarifying the existing B.T surface to a depth of 50 mm by Mechanical means and disposal of
scarified material with all leads and lifts upto 1000 Mtrs as per MoRT&H (4th Revision) Specn.
No.305.4.3
Km. 67 / ###
to 67 / 750
( 1 x 1 ) 100.000
16.000
1600.000
Km. 64 / 0 to 66 / 060
( 1 x 1 ) 2060.000
0.500
1030.000
2630.000
or say
2630.000 Sqm

7.60

13 Providing Vibrated Cement Concrete (1:4:8) mix using 40mm size HBG crushed stone
aggregate and fine aggregate conforming to table 1000-2 of MoRT&H including cost,
seigniorage conveyance of all materials to site and labour charges, centering, machine mixing,
laying, Vibrating, curing etc., including all other incidental and operational charges of all T&P
etc., complete for finished item of work as per MoRT&H specification 1500,1700, 2100 (4th
Revision) and as directed by the Engineer-in-Charge for base coarse below CC pavement
Km. 67 / ###
to 67 / 750

( 1 x

) 100.000
100.000

16.000

0.100
or say

160.000
160.000
160.000 Cum

4415.00

14 Vibrated cement concrete M 35 grade using 20mm & 10mm HBG crushed stone aggregate
(Coarse aggregate conforming to table 1000-1 and fine aggregate conforming to table 1000-2)
including cost, seigniorage conveyance of all materials to site and labour charges, centering,
machine mixing, laying, vibrating, curing etc., including all other incidental and operational
charges of all T&P etc., complete for finished item of work as per MoRT&H specification 1500,
1700, 2100 & 2702 (4th Revision) and as directed by the Engineer-in-Charge for C.C
Pavement.
Km. 67 / ###
to 67 / 750

( 1 x

) 100.000
100.000

16.000

0.250
or say

400.000
400.000
400.000 Cum

6825.00

15 Providing HYSD bars ( Fe-415 ) of diferent diameters, wrought and put up bars of all diameters
including cost and conveyance of steel to site and all labour charges for fabrication of
reinforcement including cutting, bending, binding rods, tying grills, placing them in position
etc., complete including cost and conveyance of binding wire and all handling charges and
operational charges etc., and including over lapping welding if required etc., complete for all
R.C.C items for finished item of work as per standard drawings, as per the directions of the
Engineer-in-Charge and as per MoRT&H specification 1600 &2200 (4th revision) and as per
I.S.1786 of 1985 for CC pavement.
providing 12mm with 500mm spacing
Km. 67 / ###
to 67 / 750
( 1 x 1 ) 200.000
0.500
0.890
89.000
Nos
Length each Kg/Rm
Kgs
89.000
or say

0.100 MT

16
16 Providing Uncoated Mild Steel bars ( Fe-250 ) of diferent diameters, wrought and put up bars
of all diameters including cost and conveyance of steel to site and all labour charges for
fabrication of reinforcement including cutting, bending, binding rods, tying grills, placing them
in position etc., complete including cost and conveyance of binding wire and all handling
charges and operational charges etc., and including over lapping welding if required etc.,
complete for all R.C.C items for finished item of work as per standard drawings, as per the
directions of the Engineer-in-Charge and as per MoRT&H specification 1600 &2200 (4th
revision) and as per I.S.1786 of 1985 .
Providing 25mm 100/4.5 = 22+1 joints
16/0.5=32*2=64Nos
Km. 67 / ###
to 67 / 750
( 1 x 23 )
0.500
3.850
2833.600
64
Joints
Nos
Length each Kg/Rm
Kgs

44576.00

6
or say

7
2833.600
2.900 MT

17 Providing, laying mastic pad of 25.4mm thick including cost , supply, cutting and all labor
charges,etc., complete
100/45= 2+1 = 3 joints
Km. 67 / ###
to 67 / 750
( 1 x 3 ) 16.00
0.200
9.600
Joints
Mts
9.600
or say
10.000 Sqm

8
48958.00

991.00

18 Supply and fixing cap to reinforcement with PVC Pipe of 25.40mm dia as per technical
specifications and as directed by the Engineer-in-charge.
100/45= 2+1 = 3 joints 16/0.5=32*2=64Nos
Km. 67 / ###
to 67 / 750
( 1 x 3 )
0.150
64
Joints
Nos
Length each

or say

28.800
28.800
29.000 Sqm

32.00

19 Providing Vaccum Dewatered Flooring Services including leveling the concrete to be followed
by placement of the bottom and top mats, operation of the Vaccum Machine to release the
excess free water in the Concrete, removal of the mat after completion of dewatering process,
conduction of the initial floating using power floater followed by finishing using power trowel of
adquate capacity. The rate is not inclusive of pin vibration of the concrete, placement of the
concrete and / or provision of the special toppings, but including hire and operational charges
of Generator of adequate capacity and other T&P and labour charges for all operations etc.
complete
Km. 67 / ###
to 67 / 750
( 1 x 1 ) 100.000
16.000
1600.000
1600.000 Cum.
Sqm
or say
1600.000

36.12

20 Sawing of Concrete Pavement using a self propelled walk behind, petro/electric powered saw of
suitable capacity to give a finished groove of 4mm width and 1/4 to 1/3 depth in the cured
concrete in the longitudinal and transverse directions along predetermined lines. The rate is
inclusive of the cost of consumables such as diamond blade. Masons engaged for the marking
is also deemed to be included in the rate and pouring of Polysulphide Sealent to the full depth
of groove. The rate is inclusive of the cleaning of the groove after the sawing to remove
cementatious particles adn cement washings to give a clean dry surface and surface
preparation of the sides of the groove to accommodate the sealent material etc., to give a neat
finished look including cost of sealent, hire and operational charges of Generator of Adequate
capacity and other T&P and labour charges for all operations etc. complete.
Length = 100mts
( 1 x1
) 100.000
100.000
Km. 67 / ###
to 67 / 750
( 1 x 23 ) 16.000
371.555
Joints
471.555
or say
480.000 RM

60.00

(R&B)
Division : Rajahumndry
21 Supply and fixing PVC pipe 110mm dia Prince/ Sudhakar make or equivalent quality PVC
/SWR
pipes & fittings ( as per ISI standards) 6kg/cm2
100/50 =2X2
Km. 67 / ###
to 67 / 750
( 1 x 4 )
16.000
64.000
64.000
or say
70.000 RM
218.33

22 Painting two coats after filling the surface with synthetic enamel paint in all shades on new
plastered concrete surfaces. Etc., complete for finished item of works as per MORTH Spn. No.
803 (4th Revision)
Km. 64 / 0

to 66 / 060

( 1 x

) 2060.000

1.086
or say

2237.160
2237.160
2240.000 Sqm

#REF!

SUB-TOTAL

Asst. Executive Engineer (R&B),


(R&B) Section : Malikipuram

Dy. Executive Engineer (R&B),


(R&B) Sub-divn., : Rajahmundry

Executive Engineer (R&B),

Superintending Engineer (R&B),

2
(R&B) Division : Rajahumndry

6
7
(R&B) Circle : Kakinada

Amount
9

#REF!

1,30,275

1,90,970

82,61,600

#REF!

#REF!

#REF!

#REF!

#REF!

2,32,000

#REF!

,19,988

7,06,400

27,30,000

,4,458

9
1,41,978

,9,910

,,928

,57,792

,28,800
: Rajahumndry

,15,283

#REF!

#REF!

DETAILS OF ROAD RENEWALS


Main Work: Widening and Strengthening of Kakinada Rajahmundry Road from KM 61/600 to 68/305 in East
Godavari District
Sub-Work (2): Widening and Strengthening of
Kakinada - Rajahmundry Road from KM 64/000 to
68/305 in East Godavari District

Name of
Work::

Type of Road:: Corenet State Highway

SI No

CHAINAGE IN KM

AVG. WIDTH
TYPE OF
YEAR OF
OF CARRIAGE
SURFACE RENEWALS
WAY in Meters

CONDITION
OF ROAD

61.600

67.000

7 to 14 M

BT

2009 - 10

FAIR

67.000

68.000

14 to 22 M

BT

20011 - 12

GOOD

68.000

68.305

22 M

BT

2009 - 10

FAIR

Assistant Executive Engineer


(R&B) South Section
Rajahmundry

Executive Engineer (R&B)


Rajahmundry

Deputy Executive Engineer


(R&B) Sub Division Rajahmundry

Superintending Engineer
(R&B) Circle Kakinada

DESIGN OF CRUST
Main Work: Widening and Strengthening of Kakinada - Rajahmundry Road from KM 61/600
to 68/305 in East Godavari District
Sub-Work (2): Widening and Strengthening of Kakinada - Rajahmundry Road from KM
64/000 to 68/305 in East Godavari District
The CVPD on Kakinada - Rajahmundry road =
5,150
For Four-lane single carriageway roads the design should be based on 40% of the CVPD
Total designed traffic for each direction = 2,575
Design traffic (N in msa) is finalised from
N=
A
n
r
F
D
N=
N=

365 x {(1+r)n - 1 }
r

xAxDxF

Initial traffic after construction in CVPD =


2,575
Design line in no. of years considered as 10 Years
Traffic growth rate in % (r = 7.5%)
Vehicle damage factor = 4.50
Distribution factor of commercial traffic over carriageway = 0.75
365 x {(1 + 7.5 / 100)10 - 1}
x 2060 x 0.75 x 4.50
7.50 / 100
387.00
0.075

x 6952.50

= 358,74,900 say
or say

35.87 msa

Say
35.00 Msa

21.00 msa

Requirement of Crust on widening portion where


the CBR of the embankment soil is 5% =

710 mm

Existing Crust (in mm)


S.No

Reach

Laterite
+Soling

WBM

BT

KM 61/600 to 68/305

450

75

100

Total
crust

Crust
required as
per design

Addl.
Crust
required

625

710

85

DETAILS OF CRUST PROPOSED


Existing C'way
Km.64/000 to
68/305

Widening portion
Km 64/000 to
66/060

1. G.S.B (mm)

---

300

2. WMM
3. BM

--50

250
50

4. BC
Total Crust

30
80

30
630

Item

Total Crust required - Crust provided =


710 - 630
80 mm
* Additional crust with (BC+BM) 80mm to be provided in Next 5 years
Asst. Executive Engineer (R&B),
(R&B) Section : South

Dy. Executive Engineer (R&B),


(R&B) Sub-divn., : Rajahmundry

Executive Engineer (R&B),

Superintending Engineer (R&B),

(R&B) Division : Rajahumndry

(R&B) Circle : Kakinada

TYPICAL CROSS SECTION


Name of the Project :

Main Work: Widening and Strengthening of Kakinada - Rajahmundry Road from KM 61/600 to 68/305 in East
Godavari District
Sub-Work (2): Widening and Strengthening of Kakinada - Rajahmundry Road from KM 64/000 to 68/305 in East
Godavari District

Berm
1.50
Mts.

Existing road
14 to 22 Mts.

Berm
1.50 Mts.

B.C. (30MM thick)

CC
Shoulders

2:1 Slope

B.M. (50 MM)

B.M. (50 MM)

CC
Shoulders

Existing Road

2:1 Slope

Cross Section from Km. 66/060 to 66/600 & 68/000 to 68/305

Asst. Executive Engineer (R&B),


(R&B) South Section,Rajahmundry

Dy. Executive Engineer (R&B),


(R&B) Sub-divn., : Rajahmundry

INDEX
EXISTING

PROPOSED
B.C. (30 MM)

Existing Crust - 550 MM


Executive Engineer (R&B),
(R&B) Division : Rajahumndry

Superintending Engineer (R&B),


(R&B) Circle : Kakinada

B.M. (50 MM)

TYPICAL CROSS SECTION


Name of the Project : Main Work: Widening and Strengthening of Kakinada - Rajahmundry Road from KM 61/600 to 68/305 in East Godavari
District
Sub-Work (2): Widening and Strengthening of Kakinada - Rajahmundry Road from KM 64/000 to 68/305 in East Godavari
District
Formation Width 18.00 MTs.
Berm
1.50
Mts.

Widening portion
3.975 to 2.975 Mts.

Existing road
7.00 to 9.00 Mts.

Widening portion
3.975 to 2.975 Mts.

Berm
1.50 Mts.

14.95 MTs.
B.C. (30MM thick)
Centre Dividers
B.M. (50 MM)
Earthen
Shoulders

2:1 Slope

W.M.M.
(250 MM)

G.S.B.
G.S.B.
(300 MM)
(150
MM)

B.M. (50 MM)


W.M.M.
(250 MM)

Existing Road

Earthen
Shoulders

G.S.B.
(300 MM)

2:1 Slope

Proposed Earth Work for embankment

Cross Section from Km. 64/000 to 66/060

Asst. Executive Engineer (R&B),


(R&B)South Section,Rajahmundry

INDEX

Dy. Executive Engineer (R&B),


(R&B) Sub-divn., : Rajahmundry

EXISTING

PROPOSED
B.C. (30 MM)
B.M. (50 MM)
W.M.M. (250 MM)

Executive Engineer (R&B),


(R&B) Division : Rajahumndry

Superintending Engineer (R&B),


(R&B) Circle : Kakinada

G.S.B. (300 MM)


Gravel shoulders
E/W

Name of Work ::
Main Work: Widening and Strengthening of Kakinada - Rajahmundry Road
from KM 61/600 to 68/305 in East Godavari District
Sub-Work (2): Widening and Strengthening of Kakinada - Rajahmundry Road
from KM 64/000 to 68/305 in East Godavari District
Sub Work ::
Providing CC Drains in Kakinada - Rajahmundry Road from KM 61/600 to
68/305 in East Godavari District.
1.40M
0.250M

0.90M

0.250M

1.20M

V.C.C. M-15

0.60M

V.C.C. M-15

0.20M

0.60M

VCC M-15 For Base cource


VCC ( 1:4:8) For below Base cource
Sand Cushion

0.20M
0.10M
0.10M

0.40M

1.40M
Typical Cross Section of CC Drain

Asst. Executive Engineer (R&B),


(R&B) Section : Malikipuram

Dy. Executive Engineer (R&B),


(R&B) Sub-divn., : Rajahmundry

Executive Engineer (R&B),


(R&B) Division : Rajahumndry

Superintending Engineer (R&B),


(R&B) Circle : Kakinada

Specification report to accompany the detailed estimate for the work of


Improvements to Alamuru to Kotipalli road from Km 0/000 to
3/500 in East Godavari District.

The road from Alamuru to Kotipalli from Km 0/000 to 23/300 is an


important Major District Road in East Godavari District. This road connects number of
important villages such as Alamuru, Jonnada, Tatapudi , Lankaagraharam,
Kapileswarapuram, Sriramapuram, Korumilli, Kulla, Mallavaram, Sundarapalli, & Kotipalli .
This road connects number of cross roads belonging to R&B and Panchayat Raj
departments.The road starts in km 164.80 of Vijayawada- Visakhapatnam road at
Jonnada(Alamuru),an important National Highway (NH-16) and connects at Kotipalli
village. As the road is on the canal bund of Godavari Left Bank (GLB), the Irrigation
authorities have taken up the flood bank works on this road. Now, the road is not in a
position to receive the present day traffic, as no improvements were taken up for the last
11 years (ie., since 2003-04). As there are many no. of bathing ghats all along the road
viz., Alamuru, Tatapudi, Lankaagraharam, Kapileswarapuram, Sriramapuram, Korumilli,
Kulla, Mallavaram, Sundarapalli, & Kotipalli . the connecting roads from Alamuru to
Kotipalli is to be improved for transportations of vehicles and movement of public and
pilgrims during the time of Godavari Pushkarams,2015. As the road is along the Godavari
Bund, a dwarf wall has to be constructed on right side of the road to retain the earthwork
formation done by the I&CAD officials. The existing WBM layer was warnout and gravel
exposed. The stretch of road from Km 0/0 to 3/500 is in very bad condition and at
present, not even a two wheeler is able to ply on this stretch of road. As the traffic and
movement of pilgrims and public will be high especially during the Godavari
Pushkarams,2015, the road stretch from Km 0/0 to 3/500 is to be improved to R&B
standards. Hence, an estimate is prepared with the following provisions to strengthen the
road from Km 0/0 to 3/500.
Administrative sanction accorded by Government vide GO Rt. No.826, T,R&B
Dept., dt.15.12.2014 for Rs.990.00 Lakhs, against which technical sanction accorded for the
this sub-work vide Engineer-in-Chief (R&B), Admn., State Roads, RSW & Buildings T.S. Memo
No.01 / KKD / PLAN / AK Road / EE / R / DEE-3 / AE, dt.20.12.2014 for Rs.200.00 Lakhs
permitted by the Government vide Govt. Memo No.9643 / R.III(2) / 2014-1, dt.17.12.2014
based on 2008-2009 commom SSR for all Engineering Department.

The Government of A.P. vide G.O. Ms. No.2, T,R&B (R.I) Dept., dt.12.01.2015
issued orders for adoption of MoRT&H, Govt. of India specifications and Data for Road and
Bridge works in Roads & Buildings Department, with current SSRs

Scarifying the existing B.T surface to a depth of 50 mm by Mechanical means and


disposal of scarified material with all leads and lifts upto 1000 Mtrs as per MoRT&H (4th
Revision) Specn. No.305.4.3

HBG material confirming to Grading - I


of MoRT&H Table 400-2 including cost, seigniorage charges and conveyance of all
materials to work site and spreading in uniform layers with motor grader or by approved
3 Providing,
means, onLaying,
prepared
Spreading
surface mixing
and compacting
by mix ingraded
place method
HBG crushed
with Rotavator
stone aggregate
/ approved
to
Wet
Mix
including
cost roller
of all materials
premixing
means
at Macadam
OMC andspecification
compacting with
vibratory
to achieveand
the including
desired density
etc.,
the
material
water
at of
OMC
in Mechanical
mix plant
carriage of401
mixed
ti
complete
for with
finished
item
work
as per MoRT&H
Specification
(4thmaterial
revision)by
and
Providing
and
applying
prime
coat
with
bitumen
Emulsion
on
prepared
surface of
4 as directed by the Engineer-in-charge.
granular base including clearing of road surface and spraying primer at the rate of 0.60
2

Construction of Granular sub-base by providing

Kgs. / sqm using mechanical means as per MoRT&H Specification 502 (4th revision)
Providing
and applying tack coat with bitumen Emulsion (Medium setting) (Bulk) using
and as
Emulsion pressure distributor at the rate of 0.20 kgs per sqm on the prepared
bituminous/granular surface cleaned with mechanical broom for finished item of work
as per M

7
8
9

Providing and laying of 50mm thick Bituminous Macadam with hot mix plant
producing an average output of 37.5 tonnes per hour using hard blasted granite
crushed aggregates of Grading - II as per table 500-4 of MoRT&H specificaion 504 (4th
Providing
Revision) 25
premm thick compacted Semi-Dense Bituminous Concrete by hot mix plant
using hard blasted granite crushed aggregates of Grading -2 as per table 500-15 of
specification 508 of MoRT&H (4th Revision), premixed with bituminous binder 60/70
Forming
grade @ shoulders with barrowed useful selected earth having MDD of not less than
1.75 Gms/CC from out side road boundary by mechanical means ..
Earthwork excavation in soils upto SDR by mechanical means for foundations of
structures as per drawing and technical specification including setting out.

10 Providing Vibrated Cement Concrete (1:3:6) mix using 40mm size for base course below dwarf wall.
11 Vibrated cement concrete M 15 Grade Concrete using 40mm , 20mm and 10mm size
HBG crushed stone aggregate (Coarse aggregate conforming to table 1000-1 and fine
aggregate conforming to table 1000-2).. For Dwarf wall
L.S. Provisions for Price adjustment, VAT @ 5%, Quality Control Charges, Road Safety
12 Interventions, Shifting of utilities such Electrical lines, Water supply pipe lines, etc.,
Avagahana Sadassalu and for stationery , XEROX etc.& Unforeseen items.
RATES:
The estimate is prepared with 2014-2015 common SSR for all Engineering
Department and datas as per MoRT&H standard data book duly adopting over head charges
@ 5% and contractors profit at 10% as per G.O.Ms No 141, T(R&B) Dept, dated 27.07

Asst.Engineer (R&B),
Draksharama.

Dy. Executive Engineer (R&B), Executive Engineer (R&B),


Ramachandrapuram
(R&B) Division : Kakinada

Specification report to accompany the detailed estimate for the work of


Improvements to Alamuru to Kotipalli road from Km 0/000 to 17/000
East Godavari District.

in

Improvements to Alamuru to Kotipalli road from Km 3/500 to


7/000 in East Godavari District.

The road from Alamuru to Kotipalli from Km 0/000 to 23/300 is an important


Major District Road in East Godavari District. This road connects number of important
villages such as Alamuru, Jonnada, Tatapudi , Lankaagraharam, Kapileswarapuram,
Sriramapuram, Korumilli, Kulla, Mallavaram, Sundarapalli, & Kotipalli . This road connects
number of cross roads belonging to R&B and Panchayat Raj departments.The road starts
in km 164.80 of Vijayawada- Visakhapatnam road at Jonnada(Alamuru),an important
National Highway (NH-16) and connects at Kotipalli village. As the road is on the canal
bund of Godavari Left Bank (GLB), the Irrigation authorities have taken up the flood bank
works on this road. Now, the road is not in a position to receive the present day traffic, as
no improvements were taken up for the last 11 years (ie., since 2003-04). As there are
many no. of bathing ghats all along the road viz., Alamuru, Jonnada, Tatapudi ,
Lankaagraharam, Kapileswarapuram, Sriramapuram, Korumilli, Kulla, Mallavaram,
Sundarapalli & Kotipalli . the connecting roads from Alamuru to Kotipalli is to be improved
for transportations of vehicles and movement of public and pilgrims during the time of
Godavari Pushkarams,2015. As the road is along the Godavari Bund, a dwarf wall has to
be constructed on right side of the road to retain the earthwork formation done by the
I&CAD officials. The existing WBM layer was warnout and gravel exposed. The stretch of
road from Km 3/500 to 7/000 is in very bad condition and at present, not even a two
wheeler is able to ply on this stretch of road. As the traffic and movement of pilgrims and
public will be high especially during the Godavari Pushkarams,2015, the road stretch from
Km 3/500 to 7/000 is to be improved to R&B standards. Hence, an estimate is prepared
with the following provisions to strengthen the road from Km 3/500 to 7/000 .
Administrative sanction accorded by Government vide GO Rt. No.826,
T,R&B Dept., dt.15.12.2014 for Rs.975.00 Lakhs, against which technical sanction
accorded for the this sub-work vide Engineer-in-Chief (R&B), Admn., State Roads, RSW
& Buildings T.S. Memo No.10 / KKD / PLAN / AK Road / EE / R / DEE-3 / AE,
dt.20.12.2014 for Rs.200.00 Lakhs permitted by the Government vide Govt. Memo
No.9643 / R.III(2) / 2014-1, dt.17.12.2014 based on 2008-2009 commom SSR for all
Engineering Department.
The Government of A.P. vide G.O. Ms. No.2, T,R&B (R.I) Dept., dt.12.01.2015
orders issued for adoption of MoRT&H, Govt. of India specifications and Data for Road
and Bridge works in Roads & Buildings Department, with current SSRs. Accordingly
the estimate is recasted with current common SSR for the year 2014-15.
1

Scarifying the existing B.T surface to a depth of 50 mm by Mechanical means and


disposal of scarified material with all leads and lifts upto 1000 Mtrs as per MoRT&H (4th
Revision) Specn. No.305.4.3

HBG material confirming to Grading III of MoRT&H Table 400-2 including cost, seigniorage charges and conveyance of all
materials to work site and spreading in uniform layers with motor grader or by approved
3 Providing,
Spreading
and compacting
HBG crushed
stone aggregate
to
means, onLaying,
prepared
surface mixing
by mix ingraded
place method
with Rotavator
/ approved
Wet
Mix
including
cost roller
of all materials
premixing
means
at Macadam
OMC andspecification
compacting with
vibratory
to achieveand
the including
desired density
etc.,
the
material
water
at of
OMC
in Mechanical
mix plant
carriage of401
mixed
ti
complete
for with
finished
item
work
as per MoRT&H
Specification
(4thmaterial
revision)by
and
as directed by the Engineer-in-charge.
2

Construction of Granular sub-base by providing

4
5
6

7
8
9

Providing and applying prime coat with bitumen Emulsion on prepared surface of
granular base including clearing of road surface and spraying primer at the rate of 0.60
Kgs. / sqm using mechanical means as per MoRT&H Specification 502 (4th revision)
Providing
and applying tack coat with bitumen Emulsion (Medium setting) (Bulk) using
and as
Emulsion pressure distributor at the rate of 0.20 kgs per sqm on the prepared
bituminous/granular surface cleaned with mechanical broom for finished item of work
Providing
as per M and laying of 50mm thick Bituminous Macadam with hot mix plant
producing an average output of 37.5 tonnes per hour using hard blasted granite
crushed aggregates of Grading - II as per table 500-4 of MoRT&H specificaion 504 (4th
Providing
Revision) 25
premm thick compacted Semi-Dense Bituminous Concrete by hot mix plant
using hard blasted granite crushed aggregates of Grading -2 as per table 500-15 of
specification 508 of MoRT&H (4th Revision), premixed with bituminous binder 60/70
Forming
grade @ shoulders with barrowed useful selected earth having MDD of not less than
1.75 Gms/CC from out side road boundary by mechanical means .
Earthwork excavation in soils upto SDR

by mechanical means for foundations of

structures as per drawing and technical specification including setting out.

10 Providing Vibrated Cement Concrete (1:3:6) mix using 40mm size For base course
below Dwarf wall .
11 Vibrated cement concrete M 15 Grade Concrete using 40mm , 20mm and 10mm size
HBG crushed stone aggregate (Coarse aggregate conforming to table 1000-1 and fine
aggregate conforming to table 1000-2).. For Dwarf wall
L.S. Provisions for Price adjustment, VAT @ 5%, Quality Control Charges, Road Safety
12 Interventions, Shifting of utilities such Electrical lines, Water supply pipe lines, etc.,
Avagahana Sadassalu and for stationery , XEROX etc.& Unforeseen items.
RATES:
The estimate is prepared with 2008-2009 commom SSR for all Engineering
Department and datas as per MoRT&H standard data book duly adopting over head charges
@ 5% and contractors profit at 10% as per G.O.Ms No 141, T(R&B) Dept, dated 27.07.2006.
Provision for VAT is shown separately as PART "B" in the estimate as per G.O.Ms No 141,
T(R&B) Dept., Dt 27.07.2006 The work will be carriedout as per relevant clauses of IRC &
MORTH specifications.

Asst.Engineer (R&B),
Draksharama.

Dy. Executive Engineer (R&B), Executive Engineer (R&B),


Ramachandrapuram
(R&B) Division : Kakinada

Specification report to accompany the detailed estimate for the work of


Improvements to Alamuru to Kotipalli road from Km 17/000 to 23/300
and Kotipalli - Pillanka road from km 0/000 to 9/000 in East Godavari
District.
Improvements to Alamuru to Kotipalli road from Km 23/100 to
23/300 and Kotipalli to Pillanka road from km 0/000 to 2/900 in
East Godavari District.

The roads from 1)Alamuru to Kotipalli from Km 23/100 to 23/300(Proposed) (MDR)


2) Kotipalli to Pillanka road from Km 0/000 to 2/900 (Rural road)(Proposed) are important
roads in East Godavari District. These roads connect number of important villages
such as Kotipalli Kota,Rajaveru, Masakapalli, Brahamapuri . These roads also connect
number of cross roads belonging to R&B and Panchayat Raj departments. As the two
roads are on the canal bund of Godavari Left Bank (GLB), the Irrigation authorities have
taken up the flood bank works on these roads. Now, the roads are not in a position to
receive the present day traffic, as no improvements were taken up for the last 11 years
(ie., since 2003-04). As there are many no. of bathing ghats all along the road viz.,
Kotipalli,Kota , Rajaveru, Masakapalli, Brahamapuri the connecting roads from Alamuru Kotipalli road and Kotipalli to Pillanka are to be improved for transportation of vehicles
and movement of public and pilgrims during the time of Godavari Pushkarams,2015. As
the two roads are along the Godavari River Bund, a dwarf wall has to be constructed on
right side of the road to retain the earthwork formation dowel bank done by the I&CAD
officials. The existing roads are in very bad condition and at present, not even a two
wheeler is able to ply on this road. As the traffic and movement of pilgrims and public
will be high especially during the Godavari Pushkarams,2015, the roads are to be
improved to R&B standards. CC pavement is proposed in the village limits of Kotipalli
from Km 23/100 to 23/300, as there is recurring problem of inundation and frequent
damage of the road. Hence, an estimate is prepared with the following provisions to
Widen the road from 23/100 to 23/300 with C C Pavement and strengthen the B.T road
from Km 0/000 to 2/900 of Kotipalli - Pillanka road .
Administrative sanction accorded by Government vide GO Rt. No.826, T,R&B
Dept., dt.15.12.2014 for Rs.975.00 Lakhs, against which technical sanction accorded for
the this sub-work vide Engineer-in-Chief (R&B), Admn., State Roads, RSW & Buildings
T.S. Memo No.10 / KKD / PLAN / AK Road / EE / R / DEE-3 / AE, dt.20.12.2014 for
Rs.200.00 Lakhs permitted by the Government vide Govt. Memo No.9643 / R.III(2) /
2014-1, dt.17.12.2014 based on 2008-2009 commom SSR for all Engineering
Department.
The Government of A.P. vide G.O. Ms. No.2, T,R&B (R.I) Dept., dt.12.01.2015
orders issued for adoption of MoRT&H, Govt. of India specifications and Data for Road
and Bridge works in Roads & Buildings Department, with current SSRs. Accordingly the
estimate is recasted with current common SSR for the year 2014-15.
1 Scarifying the existing B.T surface to a depth of 50 mm by Mechanical means and
disposal of scarified material with all leads and lifts upto 1000 Mtrs as per MoRT&H (4th
Revision) Specn. No.305.4.3
2 Providing, Laying, Spreading and compacting graded HBG crushed stone aggregate to
Wet Mix macadem specification including cost of all materials and including premixing
the material with water at OMC in Mechanical mix plant carriage of mixed material by ti

3 Providing and applying prime coat with bitumen Emulsion on prepared surface of
granular base including clearing of road surface and spraying primer at the rate of 0.60
Kgs. / sqm using mechanical means as per MoRT&H Specification 502 (4th revision)
4 Providing
and applying tack coat with bitumen Emulsion (Medium setting) (Bulk) using
and as
Emulsion pressure distributor at the rate of 0.20 kgs per sqm on the prepared
bituminous/granular surface cleaned with mechanical broom for finished item of work
5 Providing
as per M and laying of 50mm thick Bituminous Macadam with hot mix plant
producing an average output of 37.5 tonnes per hour using hard blasted granite
crushed aggregates of Grading - II as per table 500-4 of MoRT&H specificaion 504 (4th
6 Providing
Revision) 25
premm thick compacted Semi-Dense Bituminous Concrete by hot mix plant
using hard blasted granite crushed aggregates of Grading -2 as per table 500-15 of
specification 508 of MoRT&H (4th Revision), premixed with bituminous binder 60/70
@
7 grade
Earthwork excavation in soils upto SDR by mechanical means as per MoRT&H specification
301(4th Revision) and as directed by the Engineer-in-Charge
8 Forming shoulders with barrowed useful selected earth having MDD of not less than 1.75 Gms/CC
from out side road boundary by mechanical means .
18 Construction of Earthen Shoulders on both sides to a depth of the crust.
19 Providing Vibrated Cement Concrete (1:3:6) mix using 40mm size below Dwarf wall
20 Vibrated cement concrete M 15 Grade Concrete using 40mm , 20mm and 10mm size
HBG crushed stone aggregate (Coarse aggregate conforming to table 1000-1 and fine
aggregate conforming to table 1000-2) including
21 L.S. Provisions for Price adjustment, VAT @ 5%, Quality Control Charges, Road Safety
Interventions, Shifting of utilities such Electrical lines, Water supply pipe lines, etc.,
Avagahana Sadassalu and for stationery , XEROX etc.& Unforeseen items.
RATES:
The estimate is prepared with 2008-2009 commom SSR for all Engineering
Department and datas as per MoRT&H standard data book duly adopting over head charges
@ 5% and contractors profit at 10% as per G.O.Ms No 141, T(R&B) Dept, dated 27.07.2006.
Provision for VAT is shown separately as PART "B" in the estimate as per G.O.Ms No 141,
T(R&B) Dept., Dt 27.07.2006 The work will be carriedout as per relevant clauses of IRC &
MORTH specifications.

Asst.Engineer (R&B),
Draksharama.

Dy. Executive Engineer (R&B), Executive Engineer (R&B),


Ramachandrapuram
(R&B) Division : Kakinada

Name of Work :

1.60 Kms

Main Work: Widening and Strengthening of Kakinada - Rajahmundry Road from KM 61/600 to 68/305 in
East Godavari District
Sub-Work (2): Widening and Strengthening of Kakinada - Rajahmundry Road from KM 64/000 to 68/305
in East Godavari District

Refinery

VIZAG
Km 719/4

Gravel Quarry

Km 16/910

1.70 Kms

Katheru Quarry

Km 14/600

Km 907/0

N
H
-1
6

R-K
Roa
d (v
) Pu
nyak
estr
a

3.00 Kms

Km
4

9/6
00

0.70 kM

Working Reach

Assistant Executive Engineer


(R&B) South Section, Rajahmundry

Km 61/60
0

Km 0/0

Km 64/00
0

Sand Ramp

Km
68/
305

Morampudi
Km 910/7
Km 3/100

Dy.Executive Engineer
(R&B) Sub-Dvn.,Rajahmundry

Superintending Engineer
(R&B) Circle, Kakainada

Executive Engineer
(R&B) Division, Rajahmundry

Superintending Engineer
(R&B) Circle, Kakainada

Вам также может понравиться