Академический Документы
Профессиональный Документы
Культура Документы
1.
2.
Q- If you are to select any one of the following for control, which
one you will select?
General Specification
Special Specification
Bill of Quantities (B.O.Q.)
Drawing
A-
3.
4.
Ferdinand C Bacus
Q- If in cut section the 20 cm. material are okey but below it the
soil has natural compaction of 90% and the contractor are
asking for a payment, are you going to pay?
A-
6.
7.
Q- What Back Slopes you would adopt in the rocky area and
sandy area?
A-
10
9.
Q- Supposing there are many activities going on that day, and same
day request for next day activities was submitted by the
contractor, what will be the flow of those request and such
request be acted?
A-
8.
No
Ferdinand C Bacus
Beginning of project
End of project
Cost of project
Percentage of progress
percentage of progress
Equipment list of contractor & his staff
List of consultant
Approval certificate for materials like steel and
cement.
Deduction are Insurance which is 2%
11
Q- What is C.P.M.?
A-
Ferdinand C Bacus
Only one.
17. Q- If the contractor submit his schedule or program for work. How
will you deal with it?
A-
Ferdinand C Bacus