Академический Документы
Профессиональный Документы
Культура Документы
About DMRC
Progress/achievements so far
Status of Phase III
Operational Highlights
About DMRC
3
Phase III
6
STATUS OF PHASE-III
Further expansion by 136 kms. 110 km (50 km U/G) in
Delhi & 26 km in Haryana (14 km) Line-6 Badarpur to
YMCA Chowk, Faridabad & (12 km) Mundka to
Bahadurgarh.
The contracts are in place and the work is in progress.
STATUS OF PHASE-III
Operational Highlights
OPERATION HIGHLIGHTS
DMRC is having 142 Stations and 190 Km in operation. This is
including high speed Airport Express line having 6 stations
and 23 km section.
About 2800 train trips a day with 208 train sets (1100
Coaches) on 6 lines.
Each train used to consist of 4 coaches. With the increase in
commuters, the trains are progressively being lengthened to
6 coaches and finally to 8 coaches. We have already near
about 100 six car sets.
Average Ridership more than 2.3 million passengers per
10
day. (meaning about 1,00,000 vehicles off the road)
10
OPERATION HIGHLIGHTS
Frequency during peak hours 2 m 40 sec on 2 out of 6 lines
(on other lines 3 to 5 mts).
DMRC has around 7,000 employees, besides contract staff.
Op. Ratio 62%
Fare : From
8/- to
30/-. The system is making an
operational profit from Day-1.
DMRC is able to service and pay back the loans despite no
subsidy from the Government and the Fare Structure being
lowest in the world except Kolkata.
11
OPERATION HIGHLIGHTS
20% of DMRCs revenue is from Non-operational sources
mainly real estate development and advertisements.
The system is fully Barrier Free for Physically challenged.
The trains operate from 6 AM to 11 PM.
DMRC has introduced feeder bus short loop services to help
the commuters.
Punctuality measured with a least count of 60 sec and the
punctuality percentage has been above 99%.
12
12
DELHI GATE
KARKAR DUMA
PREET VIHAR
NIRMAN VIHAR
JAMA MASJID
LAXMI NAGAR
LAL QUILA
YAMUNA BANK
DWARKA
DABRI MOR
DHAULA KUAN
DHSRATH PURI
DELHI AEROCITY
ASHRAM
SRINIVASPURI
PALAM
GOLF COURSE
BOTANICAL GARDEN
BOTANICAL GARDEN
DWARKA SEC 21
KALINDI KUNJ
PHASEI
PHASEII
PhaseIII
Total
=
=
=
=
65.1Km
125.0 Km
136.0 Km
326.0 Km
From the reliability point of view Power supply at 220 kV, 132
kV or 66 kV level is taken from the Grid Sub Stations of
DTL/UPPCL/HVPN.
At the RSS it is stepped down to 25 kV to feed the OHE with
single phase traction transformers and 33 kV with 3 phase
auxiliary transformers to feed the auxiliary requirements. Both
are with 100% standby capacity.
33 kV is distributed through duplicate ring feeders along the
corridor and at every station it is stepped down to 400 volts
(3 phase supply) through dry type transformers. This
substation is termed as Auxiliary Substation (ASS) in our
system. This is distributed in the station to meet the power
supply requirements of the stations.
Transformers
25000
volts
33000
volts
33000
volts
To DMRC line
25000
volts
CONTRACT DEMAND
CONTRACT DEMAND & ENERGY CONSUMPTION SINCE 2006-07
S. No.
AS ON
1
2
3
4
5
6
31.03.2007
31.03.2008
31.03.2009
31.03.2010
31.03.2011
31.03.2012
CONTRACT DEMAND
in MVA
47
52
52
75.5
115
130
31.03.2013
138
193.6%
AS ON 01.08.2013
141
200%
% increase
10.6 %
10.6%
58.5%
144.6%
176.5%
ENERGY CONSUMPTION
% increase
AMOUNT PAID
in million
S.No
Financial Year
MU
2006-2007
189.52
2007-2008
199.61
10.5
514.80
2008-2009
220.14
16.15
707.20
2009-2010
254.49
34.33
832.29
2010-2011
422.73
123.05
1390.05
2011-2012
577.56
204.7
2139.24
2012-2013
596.69
214.84
3198.61
2013-14
upto Oct-13
410.33
271.17
2554.09
480.60
RSS IN PHASE I
LINE
Incoming
Voltage
RSS
LINE-1
KASHMERE GATE
220 kV
LINE-1
RITHALA
LINE-2
Rss in phase-1
66 kV
NEW DELHI
66 kV
LINE-3
DWARKA
66 kV
LINE-3
SUBHASH NAGAR
66 kV
LINE-3
INDRAPRASTHA
66 kV
TOTAL
6 SUBSTATIONS
RSS IN PHASE II
LINE
RSS
Incoming Voltage
LINE-2
JAHANGIRPURI,
CHHATARPUR
SUSHANT LOK (HCC)
66 kV
66 kV
66 kV
LINE-3
BOTANICAL GARDEN
132 kV
LINE-5
MUNDKA
66kV
LINE-6
SARITA VIHAR
PARK STREET (CTST)
66 kV
66 kV
66 kV
66 kV
TOTAL
8 SUBSTATIONS
RSS
Incoming
Voltage
STATUS
LINE -7 MUKUNDPUR
66 kV
DHAULA KUAN
66 kV
INA
66 kV
VINOD NAGAR 66 kV
YAMUNA VIHAR 66 kV
To be contd.
Contd.
LINE
LINE -8
TOTAL
RSS
Incoming
Voltage
STATUS
KALKAJI
66 kV
RKPURAM
66 kV
PALAM
66 kV
11 SUBSTATIONS
RSS
LINE-2
JAHANGIRPURI
(One Trafo of 131 MVA -220/66 kV)
LINE-3
BOTANICAL GARDEN
(2 nos 25 kV bays added)
Construction of below
Ground Substation
Contd
LAYOUT PLAN
ELEVATION
ELEVATION
Challenges faced
Challenges faced
Maintaining the clearances both in the vertical as well as
horizontal direction in the transformer bay was required.
Ventilation for the underground substation- Forced
ventilation system for the equipment rooms was adopted Three AHUs (2 Main + 1 Standby) have been provided
considering 15 Air changes per hour.
Water drainage system for this catchment area. The cables
trenches were designed with hangers at a height of 300 mm
from the bottom on which the cables were laid and the
bottom portion was used for draining the water to the water
tank with natural gravity towards the water collection tank.
To be contd
Contd
Contd
Contd
Contd
At bay level, the IEDs provide all bay level functions like
control (commands outputs), monitoring (status indications,
measured values).
The IEDs are directly connected to the switchgear avoiding
the need for additional interposing of transducers.
Each bay control IED is independent of the others and its
functioning is not affected by any fault occurring in any of the
other bay control units of the substation.
The data exchange among bay level IEDs, and between bay
level and substation level take place via dual fiber-optic inter
37
bay bus according to IEC 61850-8-1 protocol.
37
Station Level
Human Machine Interface enables local station control and
monitoring through the vendor software package compatible
with IEC 61850.
DMRC Substation bays are limited the bay bus arrangement
provides independent station-to-bay and bay-to-bay data
exchange.
Substation Configuration Language (SCL) facilitates
integration of the system by the users/operators and can be
used without detailed knowledge of real-time systems.
An authorization mechanism has been provided to prevent
system access to unauthorized users
OCC Level
IEC 61850 signals are converted to IEC 608705-101 signals through a software based
gateway for communication from the substation
to the OCC.
39
CLEARANCES
CONCLUSION
Thank You !!
DMRC Ltd.
Metro Bhawan,
Fire Brigade Lane,
Barakhamba Road,
New Delhi - 110 003.
49
49