Академический Документы
Профессиональный Документы
Культура Документы
Conclusion
The Government has failed to provide a coherent or compelling Business Case for Capital Metro Stage 1.
While riddled with inconsistencies, its most important failing is to ignore the substantial cost of capital which,
when included, drops the claimed benefit-cost ratio to well below unity to 0.81 at the most optimistic. The
Government claim that the project is cost-effective cannot be sustained.
All Canberra taxpayers should be made aware of the gross failings of the Business Case and of how the
Government has apparently ignored them in deciding in October to proceed with the project.
M.R. Flint
Principal Consultant, Acquisition and Logistics Services
25 November 2014
The Author: Max Flint has specialised for many years in providing logistics services for defence-related major
capital project acquisitions, including life-cycle costing. He is well qualified in this field, having extensive
experience as a logistician in the RAAF, the Department of Defence and as a consultant, as well as possessing a
diploma in electrical engineering from RMIT and a Master of Science (Logistics Management) with Distinction
from USAF Institute of Technology.
In the preparation of this critique, the author has not received funds from any external source nor prepared
it on behalf of any other entity.
File.6e1941fd-6578-45c1-9e77-08be38216852
Copyright of Acquisition & Logistics Services
1
Printed: 25-Nov-14
The Government has failed to provide a coherent or compelling Business Case for Capital Metro Stage 1. Its
most important deficiency is to ignore the substantial cost of capital which, when included, drops the claimed
benefit-cost ratio to well below unity to 0.81 at the most optimistic. The Government claim that the project is
cost-effective cannot be sustained.
All Canberra taxpayers should be made aware of the gross failings of the Business Case and of how the
Government has apparently ignored them in deciding in October to proceed with the project.
File.6e1941fd-6578-45c1-9e77-08be38216852
Copyright of Acquisition & Logistics Services
1
Printed: 25-Nov-14
File.6e1941fd-6578-45c1-9e77-08be38216852
Copyright of Acquisition & Logistics Services
2
Printed: 25-Nov-14
[1]
2014 prices
Loan ($M)
Assumed Interest Rates
6%
7%
8%
$M
$M
$M
447
533
623
206
287
372
95
111
127
398
499
301
599
361
478
783
9%
$M
715
Actual BDV 20 Year Interest
[2]
Net BDV 20 Year Interest
[3]
459
3 year BDV capital carrying cost
143
602
Total Capital Cost (risk free)
722
Total Capital Cost (+ 20% risk )
[4]
Notes:
1. BDV (Base Date Value)= values discounted at the assumed escalation rate of 3.16%
2. Actual BDV of interest component.
3. Net BDV interest is $783 less BDV of principal component of annual repayments.
4. Risk is +20% (reduced from 50% because $783 includes $173m contingency).
The whole document has a major problem with how escalation, inflation and discounting are applied. While it
is acceptable practice to use validly produced Present Values (PV) of quantified benefits and costs to establish a
benefit-cost ratio for comparison of options (using a cost of capital or an Internal Rate of Return figure), it is an
erroneous practice to use these discounted costs as the true costs of a project in Base Date Values (BDV). This
point is illustrated in Table 2 below. A net result is that the Business Case seriously underestimates the project
costs.
Table 2- Bank Loan Example Base Date Values
Bank Loan example
Data
In
Principal
Interest Rate
Inflation rate
Years
Outputs
Abbrev
Value
$P
%Ipa
%Infpa
Y
50,000
7.00%
2.75%
5
Total
at Base Year
5
Date
1
2
3
4
4.10
PV of a $ pa
PV$pa
(1-(1+%Ipa)^(-y))/%Ipa
12,195
Repayment pa
$Rpa
$P/PV$pa
60,973 12,195 12,195 12,195 12,195
8,695
PV Repayments @ 7%
PV$P@%Ipa
Same as $Principal
50,000 11,397 10,651
9,954
9,303
PV Repayments @ 2.75
PV$P@%Infpa $Rpa/(1+%Infpa)^y
56,248 11,868 11,551 11,241 10,941
10,648
Base Date Value interest paid PV$Int
Actual cost of loan
6,248
Notes:
1. PVs discounted at full interest (discount) rate are not what has to be paid. They are used only for comparison of investments.
2. Once investment decision is made, the Base Date Value (BDV) is what has to be paid.
3. The BDV of the loan is the sum of repayments discounted at the assumed inflation rate.
4. Repayments are made in arrears, at end of each year.
Abbrev
Formula
For a reason not understood, several of the tables in the Business Case discount the basic estimate of $610
million, over 3 years, to a lower figure, at various discount rates. Why, when it itself is an estimate
escalated up from some earlier estimate? What Base Dates are used in the Business Case and what are the
dates of various estimates?
Throughout the Business Case, estimates are given predominantly for 23 years (3 years construction plus
20 year operating period, while ignoring the costs of years 21-30 of operations.
The capital cost estimate (Tables 1, 15, 17, 38, 41, 43 and 44) all give a basic estimate of capital
investment of $610 million (2014 prices), to which is added the $173 million, P75 risk allowance
(contingency). It is clear from these tables that the cost of capital is not included in the $783 million. It
is noted, however, that the figure includes a profit component of $59 million, being 8% on cost. This is a
very small profit margin given that it must account for the cost of capital to the firm/consortium, an
allowance for risk in addition to the transferred risk included in the contingency, plus a normal profit
margin. The basic capital cost of the project has not changed significantly from the 2011 estimate of
$614 m, in spite of three years of project definition. This result tests credibility of the Business Case
estimate.
The Business Case claims a Benefit Cost Ratio (BCR) (discounted) of 1.2 (Table page 17, Tables 18 and
29). However, the equation ignores the cost of capital investment, the minimum estimated at $398
File.6e1941fd-6578-45c1-9e77-08be38216852
Copyright of Acquisition & Logistics Services
3
Printed: 25-Nov-14
406
222
54
129
381
198
985
Including
$Cost Capital
Value
[8]
Notes $m PV
4
3
[1] [2]
406
222
54
129
381
198
985
619
0
204
823
[0]
Value
$m PV
2
Tab 43 figures
& $Cost Capital
Value
[9]
$m PV
5
406
222
54
129
381
198
985
[10]
507
398
269
1174
0.64
0.67
0.81
0.84
Estimates in the Business Case for operating and maintenance costs (Tables 16, 22 and 42) bear no
resemblance to those in the revised, independent assessment of the 30 year Operations and Maintenance
costs yet the Present Values of the two assessments almost agree at about $23m-$24m per annum. Nor
are the bases of estimates explained in the Business Case. Both assessments agree on a 20 % contingency
as being appropriate.
The graph for Capex distribution Profile (Figure 23) is recognised as an @Risk output, but the Business
Case does not give any detail of the risk profiles of each component of the capital cost modelled. The
components are presumed to be those comprising the Public Sector Comparator (PSC) point estimate of
$610m plus Transferable Risk ($81m) and Retained Risk ($68m) for a Mean (P50 of $759m). The graph
gives a P75 figure of $783m, which is only 3% higher than the Mean. This is an extremely small
increment. The Case offers no idea of what inputs and respective risk profiles were input to the model
but the assumed risk profile of each component cost must have been very small. Even taking the
transferred and retained risks into account, the P75 figure using the base estimate of $610m is only 28%
above the Mean. This is far too conservative for the capital investment, especially given that the risk on
O&M costs is assumed at a reasonable 20%. The revised independent study assumes a risk of plus 20 per
cent on the point estimates (down from the +50% on the $610 million in the initial, independent
assessment).
The Business Case gives the cost of the Capital Metro Agency during the three-year construction period
at $45m. However, it neglects to include the cost of the Agency during the three years prior to the
construction phase. The independent assessment estimated the cost of the Agency at $60m for the six
years.
The Business Case identifies several costs excluded from a PPP contract that will need to be met by the
ACT Government but does not attempt to quantify them. These have been included in the revised,
independent cost estimates at a nominal (not justified) $60 million for six years of CMA project office
costs, plus an additional $60 million for project costs outside the scope of the PPP contract, eg
File.6e1941fd-6578-45c1-9e77-08be38216852
Copyright of Acquisition & Logistics Services
4
Printed: 25-Nov-14
The Business Case cites (8.3.5.3, page 122) participants recommended the ACT Government provide
an affordability signal to the market during the RFP stage.. This content of the Business Case
contradicts the ACT Governments oft-stated position that release of such information would prejudice
tendering. The independent assessments refute the Governments position as a self-servicing fallacy.
In respect of costs in excess of affordability (9.9.2), two optional strategies are offered, neither of which
would provide a suitable compromise for most Canberran taxpayers and voters. Other more acceptable
options would be to either to cancel the project, or to defer the project until after the next ACT election
when the current Government can test its claimed mandate for the project.
Revised, independent assessment
After release of the Business Case, its detailed study has led to revision of the following assumptions that have
been incorporated in a revision of the initial independent assessment:
The assumed cost of capital has been revised down from 9% to 7% per annum.
The Base Date Value (BDV) has been calculated for the total capital investment cost (including cost of
capital) over 20 years at an assumed average escalation rate of 3.16% pa; ie the BDV of the sum of the
annual repayments over 20 years, has been discounted to the Base Date year of 2014 at the assumed
escalation rate. The 3.16% is an equally weighted average of the assumed wage and material indexes
(0.5*3.75% + 0.5*2.27%) 1. Although the assumed inflation rate of 2.75% is included in nominal
discount rates used in the Case, it is not appropriate as an escalation factor for costs.
Given that the basic P75 estimate of $783 million, includes $173 million of contingency (28%), the
maximum risk of capital investment has been reduced from 50 % to 20 %.
Consequently, the revised independent assessment is summarised at Table 4 below. The expected annual
repayment of loan and interest (availability payment) will be between $85 million and $102 million over 20
years and the overall cost over 30 years is now estimated at from $1,890 million to $2,280 million including a
residual, annual operating subsidy of from $18.9 million to $23.7 million (all values in 2014 prices). Revised,
estimated taxpayer liabilities per Canberra household are given in Table 5 below. Note that these revised
estimates are considered rock-bottom estimates. Given the history of cost blow-outs on other major projects in
the ACT (the dam, the gaol, Gungahlin extension and probably the Majura parkway), final costs could well be
much higher.
File.6e1941fd-6578-45c1-9e77-08be38216852
Copyright of Acquisition & Logistics Services
5
Printed: 25-Nov-14
[1]
Total Cost
30 Years
$m
[2]
[3]
30
1,890
2,280
10
1,701
2,043
189
237
[4]
120
[5]
1,269
1,549
33
50
[6]
[7]
312
374
156
187
na
Notes:
1.
2.
3.
4.
5.
6.
7.
Conclusion
While the total cost estimate has been revised down from a range of $2,138 million to $3,064 million to a
probable range of $1,890 million to $2,280 million, the net, annual O&M subsidy has risen moderately to a
range of $19 million to $24 million, excluding the assumed value of benefits that may not be realised for many
years if ever.
The Business Case gives the 30 year value of benefits at $984 million against an estimate of $823 million in
costs (2014 prices), claiming a BCR of 1.2. However, when the ignored cost of capital of a minimum of $398
million is added (could be as high as $602 million), the best BCR drops to about 0.81 and possibly as low as
0.61.
M.R. Flint
Principal Consultant, Acquisition and Logistics Services
Canberra, ACT
25 November 2014
Max Flint has specialised for many years in providing logistics services for defence-related major capital
project acquisitions, including life-cycle costing. He is well qualified in this field, having extensive
experience as a logistician in the RAAF, the Department of Defence and as a consultant, as well as
possessing a diploma in electrical engineering from RMIT and a Master of Science (Logistics Management)
with Distinction from USAF Institute of Technology.
File.6e1941fd-6578-45c1-9e77-08be38216852
Copyright of Acquisition & Logistics Services
6
Printed: 25-Nov-14
Reference
Pri
Subject
Query/Comment
1.2, 1.3
Full Business
Case
Table 1
Capital cost
estimate(P75),$m
nominal
It is clear that the $610 estimate does not include the cost of capital.
Includes Contractors overhead and profit of 8% on cost (most probably too
low).
It Includes escalation by $65m from an initial estimate of $545m to $610m. But
why? Was this not a new estimate made in 2014?
This is stated to be a new estimate, not one updated from 2011, or is it? If an
updated estimate, the escalation rate is 3.8%pa over 3 years.
Contingency (P75) of 28% [most likely too low].
The estimate has not changed much from 2011, in spite of three years of
additional project definition. Amazing!
Table 2
and notes
Comparison Total
cost ($m NPC) of
PSC and PPP
Proxy
1.6.3 and
table p17
3.1.1
Table 4
3.1.2.3
3.1.2.6
3.1.2.8
3.1.3.2
4.2.2.2
Figure 12
Table 11
Problem 3
4.3.2
4.3.2.1
5 Key
messages
& 5.1.2
current capital
delivery cost
estimate is in
order of earlier
$614m
Table 15
[also Table
1]
Capital delivery
cost estimates
($m, nominal,
P75)
housing in
Australia
Patronage
Some imply additional costs outside contract scope but which should be
included in the project cost.
These imply additional costs outside contract scope but which should be
included in the project cost.
Yes but seating for only 85. A lot of commuting standing up, hanging onto a
strap to be done.
Independent modelling shows travel time more likely to be from 30-35 minutes.
File.6e1941fd-6578-45c1-9e77-08be38216852
Copyright of Acquisition & Logistics Services
A-1
Printed: 25-Nov-14
Opex
benchmarking
Figure 21,
p83
Figure 22
Table 16
Discount rate of
5.52%; escalation
rate of 2.75%
Comparison of
cost estimates
Operating,
maintenance and
life-cycle costs
($m nominal)
There does not seem to be a need for Figure 22, which serves only to confuse.
There has been no basis offered for the estimates or why operations costs are
so much higher than maintenance costs.
Costs are for 30 years but later tables use only the 20 year totals.
These estimates for each of operating costs and maintenance costs bear no
resemblance to those in the independent assessment of the 30 year O&L costs
yet the PVs of the two assessments almost agree at about $23m-$24m per
annum.
Both assessments agree on a 20 % contingency.
The figures in this table do not agree with those in Table 22, although
estimates in the latter are in real $m they agree with those in Table 38 which
are nominal estimates.
Error: The yearly totals do not even add up correctly.
The following table give Table 16 totals (not actually in Table 16) and the
different, apparent discount rates used in other tables, as an example of
inconsistent use of discount rates.
O&M
Component
Op Cost
Mnt Cost
LCC
Total O&M
Risk
Total $Nominal
5.1.8
Capital Metro
Agency costs
Figure 23
Capex distribution
Profile ($m
nominal)
1.66
BDVs
Discounted @
BDV esc Rate
BDV Total (Y)
BDV $pa (Y)
Less Risk
Tables 22&23
Discounted @
PV nominal Rate
PV Total (Y)
PV $pa (Y)
Less Risk
665
Table 43
204
Table 43
Discounted @
PV nominal Rate
PV Total (Y)
PV $pa (Y)
Less Risk
Table 44
Discounted @
PV nominal Rate
PV Total (Y)
PV $pa (Y)
Less Risk
445
Table 43
269
Table 44
205
3.16%
657
22
665
1.12
204
10
12.34%
230
8
625
1.09
269
13
8.67%
327
11
625
1.12
205
10
12.27%
231
8
This paragraph gives the cost of the CMA during the three-year construction
period at $45m. However, it neglects to include the cost of the Agency during
the three years prior to the construction phase.
The independent assessment estimated the cost of the Agency at $60m for the
six years.
This has to be considered an error in the Business Case.
While a project cost, it should not be included in the contract cost estimate.
The graph for the PSC Capex distribution Profile is recognised as an @Risk
output.
The components are presumed to be those comprising the PSC point estimate
of $610m plus Transferable Risk ($81m) and Retained Risk ($68m) for a Mean
(P50 of $759m).
The graph gives a P75 figure of $783m, which is only 3% higher than the
Mean. This is a very small increment. The Case offers no idea of what
inputs and respective risk profiles were input to the model but the assumed risk
profile of each component cost must have been very small.
Even taking the transferred and retained risks into account, the P75 figure
using the base estimate of $610m is only 28% above the Mean. This is far too
conservative for the capital investment, especially given that the risk on O&M
costs is assumed at a reasonable 20%.
Note: The author of this critique is an experienced cost risk analyst, including
use of @Risk and having developed cost-risk models validated by @Risk.
File.6e1941fd-6578-45c1-9e77-08be38216852
Copyright of Acquisition & Logistics Services
A-2
Printed: 25-Nov-14
6
Key
Messages
benefits to the
community of
around $3,587b
(nominal) over 30
years
6
Key
Messages
Table 18
.. an anticipated
BCR of 1.2
Cost Benefit
Analysis ($m PV)
top Page
90
Table 19
Economic benefits
are discounted at
7%, (in contrast
to PSC and PPP
Proxy discount
rates)
Economic
assumptions discount rate
Table 19
There is no definition offered for this term (or for any other for that matter), nor
how it is applied.
Table 19
Table 21
Summary of
operating,
maintenance and
life cycle costs
(real $m)
6.2.5.2,
para 3
O&M costs
Table 22
O&M costs
Error: The discount rate is given as a real rate of 7%, whereas the nominal
rate is 7%.
The nominal rate comprises the real rate and the assumed inflation rate
(2.75% ?).
This is one example of confusion caused by inconsistent and unexplained use
of different discount rates.
File.6e1941fd-6578-45c1-9e77-08be38216852
Copyright of Acquisition & Logistics Services
A-3
Printed: 25-Nov-14
Summary of
Project costs (real
$m)
Table 23
note under
6.2.8.2
financing
costs
Residual Values
Table 24
Summary
transport benefits
(total and PV $m)
Page 100
6.2.12.3
Table 29
Urban
densification
benefits
Additional tax
revenue
Cost Benefit
Analysis
7.0
Table 31
8.1.1
Table 36
PPP (Availability)
8.3.5.2, dot
point 3
8.3.5.3,
page 122,
dot points
3-5
9.1
Table 38
Raw cost
estimates
(nominal $m)
9.1.4
last para
Table 39
9.2.5
Timing
assumptions
Base date
Error: The table claims real $m but the totals are the same as nominal $m
figures. Another example of confusing terminology.
Why are capital expenditures being discounted over 3 years, given that the
basic $610m is an escalated figure?
What is the Base Date used in the Business Case?
While it is acceptable practice to use validly produced PV for quantified
benefits and costs to establish a Benefit-cost ratio and for comparison of
options, it is erroneous practice to use the discounted cost as the true cost of a
project once the option is selected (see text for detailed explanation).
What is the Base Date?
Cost of capital finally acknowledged, but is not estimated or included anywhere
in the Business Case.
Residual values are estimated within the transport benefits and are presented
as net residual benefits, being (presumed) residual benefits for years after the
30 year contract period less residual costs for the post-period.
This is an erroneous calculation that serves to inflate the overall benefits and
benefit-cost ratio.
total cost is presumed to mean nominal cost.
This table is quite strange. The ratio of Total to PV values should be much
the same but vary considerably.
Also, the table takes into account residual value of benefits [forever after the
30 year period]. This is not a valid inclusion, given that the cost side of
the equation stops at 30 years.
The Case covers claimed benefits of densification but not any of the
disadvantages, as if there were none. Yet, there are people who prefer not to
have such densification.
This claim is rather doubtful and open to challenge.
This table excludes the cost of capital investment. Therefore, a figure of 1.2 is
grossly in error and the ratio will be more like 0.81 at best.
Yet another example of presenting fully discounted PVs of costs as the true
cost of a project, which is patently in error (see text for detailed explanation).
Later in the Case, it assumes an average fare of only about $1. The current
Single trip, adult fare for ACTION is $4.50.
The Gold Coast tram has a flag-fall fare of $3.50.
The assumption of a $1.01 fare is for the tram is somewhat difficult to
understand.
Cost of capital acknowledged but is not estimated and is totally ignored in the
Business Case.
Who owns the infrastructure created by the project? The Case implies that the
Contractor does.
This paragraph, talking about preferences of operators and equity providers,
seem to be at odds with Federal Government guideline documents.
This content of the Business Case contradicts the ACT Governments claim
that release of such information would prejudice tendering.
The independent assessment refuted the Governments position as a selfservicing fallacy.
The independent assessment is essentially a PPP Proxy and done for the
same reason.
This table needs review for accuracy and consistency with previous data.
Estimates are for the 20 year operational period only (see Tables 39 and
62). NPC of $507m from $610m is 6.4% over 3 years. 7% would give $503m.
But why is the $610m discounted when it was escalated over three years from
$507m?
The $610m does not include the cost of capital.
O&M costs $625m discounted over 20 Years to $269m, being a discount rate
of 8.7%. Where did this apparent rate come from?
Fully discounted costs are again being presented as Base Date project costs
when they are not.
Yet another example of mixing apples and oranges and cause of confusion.
CMA has made PSC and PPP discount rate assumptions, implying different
rates for the two methods. However, while paragraph 9.1.4 implies these are
used for PPP Proxy estimates, the Case does not show how or why for either
method.
Note that the Operational period is set at 20 years, and not 30 years.
First mention of a Base Date set at May 2016 (not 2014) but does not seem to
be applied consistently in the Business Case.
File.6e1941fd-6578-45c1-9e77-08be38216852
Copyright of Acquisition & Logistics Services
A-4
Printed: 25-Nov-14
Table 43
9.3
Table 44
Table 44,
Note 3
9.4, para 2
Table 45
Table 45
Note 1
NPC of availability
payments
9.7.1.1
Table 46
Potential
revenues ticket
sales;
Average fare
Table 46
and
Note 2
Potential
revenues ticket
sales;
Average fare
Later in the Case, it assumes an average fare of only about $1.01. The current
Single trip, adult fare for ACTION is $4.50.
The Gold Coast tram has a flag-fall fare of $3.50.
Although the average of the foregoing rates would be somewhat lower
because of concession fares and interchanges with bus fares, the assumption
of a $1.01 fare for the tram seems extremely low.
It is also difficult to understand, given that it goes against the Governments
case by significantly increasing the operating subsidy.
Estimated average fare is actually cited as $1.35, but reduced to $1.01.
Neither figure is explained.
Risk adjusted
PSC
Total Costs
PPP Proxy
discount rate
ACT
Government
option of making a
contribution equal
to 50% of project
debt
Total Cost ($m
NPC) of PSC and
PPP Proxy
This table again uses the basic cost of $610m, but why discounted at all? What
is the Base Date?
23 Year costs (3 construction + 20 O&M)
The $610m does not include the cost of capital.
Fully discounted costs are again being presented as true project costs when
they are not.
Total O&M Costs discounted from $625m to $269m over 20 Y, giving a
discount rate of 8.7% (where from?).
See also Comments on Table 44.
Why discounted at all? What is the Base Date?
This statement implies that the subsequent PPP Proxy estimates include
financing costs, but the Business Case excludes the cost of capital in
preceding tables.
The different discount rates used for the PPP Proxy calculation is neither given
nor explained.
The independent assessment discusses in some detail this probable course of
action and gave details of interest savings achieved.
File.6e1941fd-6578-45c1-9e77-08be38216852
Copyright of Acquisition & Logistics Services
A-5
Printed: 25-Nov-14
Other Costs
This paragraph discusses other costs that need to be added to the overall
project cost to the ACT taxpayers, in addition to the contract cost.
9.9.1
Affordability signal
9.9.2
Costs in excess of
affordability;
strategies that
could be adopted.
Table 62
Key Assumptions
Term
ownership of the project
[Table 36; p117 of
Business Case
total values
[Table 24 of Business
Case]
Annualisation and
extrapolation
[Table 19 Business Case]
Average Escalation Rate
Definition Query
Source
[otherwise by author]
File.6e1941fd-6578-45c1-9e77-08be38216852
Copyright of Acquisition & Logistics Services
[Table 19 of Business
Case]
Different to normally
accepted definition
A-6
Printed: 25-Nov-14
File.6e1941fd-6578-45c1-9e77-08be38216852
Copyright of Acquisition & Logistics Services
A-7
Printed: 25-Nov-14