Академический Документы
Профессиональный Документы
Культура Документы
Date:
XX/xx/2XXX
Analyst: MPG
Approval:
Job: Investment
casting
Page ___ of
____
Summary of Activities
Activity
(symbols)
Count
Operations (,
O)
Inspections (, I)
Moves (, M)
Delays (, D)
Part No:
Time
Storages (, S)
Se
q.
1
2
3
4
5
6
7
8
9
10
11
12
13
Activity description
Injection molding of wax
patterns
Allow patterns to cool
Move patterns to assembly
work area
Assemble patterns to sprue
for pattern tree
Move pattern tree to
refractory room
Coat pattern tree with
refractory material
Coat tree with refractory
multiple times
Move tree to furnace room
Invert pattern tree and heat
to melt wax
Reheat tree to remove
contaminants
Position mold upright, pour
molten metal
Allow time for cooling and
solidification
Move tree and casting to
Sym
bol
O
D
M
O
M
O
O
M
O
O
O
D
M
Tim
e
Distan
ce
Analysis notes
Distan
ces
14
finishing room
Break mold and separate
sprue from casting
1.
Change the casting process from investment casting to die casting, which is a much
simpler process consisting of fewer steps. Functional requirements of the part may
argue against this recommendation.
2.
Set up all processing steps in one room to eliminate moves between separate rooms.
3.
In addition to all steps being carried out in one room, could a work cell be designed to
provide a more sequential work flow between operations.
4.
Where are the inspections? No inspection operations are listed among the investment
casting steps. For a rather complex sequence, inspections should be included to make
sure that further processing is not performed using defective patterns or molds.
tools, a milling machine and a drill press. From the machine shop, the
parts travel to the finishing department for painting and baking (to
cure the paint). From the finishing department, the parts are moved
back to the machine shop, where additional milling is accomplished to
provide two machined metal surfaces that will mate with other
components in the final product. The parts are then moved to the
shipping and receiving department for shipment to the customer. (a)
Develop the flow process chart .
Solution :
Flow Process Chart
Date: XX/xx/2XXX
Analyst: MPG
Job: Forged machinery part
Approval:
Part No:
Seq
.
1
2
3
4
5
6
7
Activity description
Unloading of pallet load at S&R Dept
Inspection of billets
Move billets to warehouse
Move billets into storage at warehouse
Storage at warehouse, awaiting order
(Forklift dispatch from factory to warehouse
(Forklift waits at warehouse
Pallet of billets retrieved from storage
Forklift transports billets back to forge shop
Summary of Activities
Activity (symbols)
Count
Operations ( , O)
Inspections
(, I)
12
Delays (, D)
11
Storages (, S)
O
I
M
M
S
M
D
M
M
Dis
Distances
Moves (, M)
Sym
Time
2885 ft
Analysis notes
500 ft
100 ft
500 ft
100 ft
500 ft
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
D
M
O
D
M
D
O
D
M
D
O
D
M
D
O
M
O
D
M
D
O
D
M
100 ft
200 ft
100 ft
200 ft
60 ft
200 ft
325 ft
2- the workplace were redesigned using a work holding fixture, and the worker
were trained to use both hands simultaneously to perform the task
Solution:
Left hand
Pick up board, put in workholder
Time
Right hand
0.08 min
Cum. time
0.08 min
0.04 min
Close workholder
0.12 min
0.05 min
0.17 min
0.10 min
0.27 min
0.03 min
Open workholder
0.30 min
0.07 min
0.37 min
The cycle time is reduced from 0.62 min to 0.37 min, which is a 40% reduction in cycle
time.
Worker time
Machine
time
0.13 min.
(idle)
0.23 min.
(idle)
0.12 min.
(idle)
(idle)
0.75 min.
0.10 min.
(idle)
0.15 min.
(idle)
Totals
0.73 min.
0.75 min.
(B)
Time
Machine 1
Time
Cum.
time
0.13
0.13
0.23
0.36
0.12
0.48
Machine cycle
0.75
1.23
0.10
1.33
0.15
1.48
Time
0.10
0.10
0.12
0.22
0.51
Machine 1
Machine cycle
Time
0.75
Cum.
time
0.97
Summary: The cycle time for the revised cycle is 0.97 min, a 35% reduction
from the original cycle time of 1.48 min.
Relationship Chart :
Quantities per
day
Sequence
25
M-D-G
10
T-F
50
D-M-D-G-F
25
M-T-F
15
M-G
T-G-F
(b) Activity-relationship
chart
From\
To
75
25
15
50
75
T
G
F
35
55
E
-
Quantities per
day
Sequence
20
A-B-D
13
B-E-A
10
E-C
30
D-A-B-D
25
A-C-E-B
18
C-B-E-D-A
Solution: (a) From-to chart and (b) activity-relationship chart. To determine the
closeness ratings in (b), the following divisions were used: A = number of trips 50;
E = number of trips = 35 to 49; I = number of trips = 20 to 34; O = number of
trips = 1 to 19, and U = zero trips.
(a) From-to chart
From\
To
50
25
18
48
13
(b) Activity-relationship
chart
D
E
A
50
-
31
25
25
10
18
D
-
O
-
Quantities per
day
Sequence
40
M-D-F-A
50
T-G-F
20
T-D-F
60
G-F-A
70
M-D-M-GF
30
T-M-F-A
10
M-T-G
11
0
10
70
30
70
20
60
30
G
F
A
60
-
T
18
0
-
G
13
0
E
-