Академический Документы
Профессиональный Документы
Культура Документы
349-358
ABSTRACT: Deep tunnels present unique geological problems that are exceptionally challenging for the design of tunnelling machines capable
of excavating in such conditions. Traversing faulted and disturbed ground at significant depth requires that tunnelling procedures be able to cope
with a huge range of difficult geological conditions. Investigating, evaluating and assessing anticipated geology ahead of tunnelling, and dealing
with encountered difficult ground conditions requires that better understanding be gained of the interaction between complex geology and stress
conditions when mining at these significant depths. Extremes of ground conditions present major contrasts to tunnelling, so much so that they
often demand use of flexible rock engineering solutions in order for the tunnel to progress. This need to adopt flexible solutions is often seen as
being at variance with the constraints imposed by the rigidity of design elements incorporated into the fabrication of a typical TBM. In this paper
extremes of experience are cited from tunnelling in the Himalayas at the Nathpa Jhakri Scheme (Figure 1) where a variety of difficult ground
conditions had to be traversed, ranging from rock-burst-prone rhyolitic units with hydrothermal water inrushes through to coping with squeezing,
very soft, soil-like fault zone infills.
RÉSUMÉ: Les tunnels profonds présentent les problèmes géologiques uniques qui sont exceptionnellement provocants pour la conception des
machines de perçage d'un tunnel capables de l'excavation en de telles conditions. Traverser la terre censurée et dérangée à la profondeur
significative exige que le tunne l procédures de ling puisse faire face à une gamme énorme des conditions géologiques difficiles. L'investigation,
l'évaluation et l'évaluation de la géologie prévue en avant du perçage d'un tunnel, et traiter dans des conditions au sol difficiles produites exige
qu'une meilleure compréhension soit gagnée de l'interaction entre la géologie et les états complexes d'effort en extrayant à ces profondeurs
significatives. Les xtremes de E du commandant actuel de conditions au sol contraste au perçage d'un tunnel, tellement de sorte qu'ils exigent
souvent l'utilisation des solutions flexibles de technologie de roche dans l'ord heu pour que le tunnel progresse. Ce besoin d'adopter les solutions
flexibles est souvent vu en tant qu'étant en désaccord avec les contraintes imposées par la rigidité des éléments de conception incorporés à la
fabrication d'un TBM typique. En cela des extrémités de papier de l'expérience sont citées du perçage d'un tunnel en Himalaya à l'arrangement
de Nathpa Jhakri (Figures 1) où une variété de conditions au sol difficiles a dû être traversée, s'étendant à partir des unités rhyolitiques roche-
éclater-enclines avec les inrushes hydrothermiques de l'eau à travers à faire face au serrage, très doux, sol-comme des remplissages de zone
faillée.
1.0 INTRODUCTION
Page 1 of 10
(decimetre-scale) convergence to be dealt with. In zones of upper reaches of the River Sutluj in the state of Himachal Pradesh,
significant closure it is still possible for such machines to become (HP) almost on the Chinese border. The project has been
trapped. In fact, because of the length of the latest state-of-the-art implemented by Satluj Vidyut Nigam Limited (SJVN), a
telescoping double shield machines, it might be argued that the risk Government of India company, formerly known as the Nathpa
of problems occurring due to squeeze and/or closure may actually Jhakri Power Corporation. The total project cost, which was in
be compounded by the use of such machines as against more excess of US$1.2 billion, was one third funded by the World Bank.
open-structured TBM’s, which have a lower rock contact area. Aecon Constructors, through its wholly owned subsidiary, the
Foundation Company of Canada, was Managing Party of one of
the joint ventures constructing the project, responsible for
undertaking two of the main civil work contracts, totalling $620M.
These construction contracts included the Main Dam, the Intakes,
the Desilting Chambers (Figure 3) and approximately 16km of the
Headrace Tunnel. Throughout the ten years of execution of the
joint venture’s contract works execution, Golder Associates
provided geotechnical and geological engineering advice.
Figure 4 : HRT Layout and Geology from Desilting Complex to Wadhal Adit
Page 2 of 10
generating units of 250 MW each set within a 225m long, 49m high Now complete, the HRT is fully concrete lined, with nominal lining
and 20m span underground powerhouse, allowing full utilization of thicknesses varying from 300 mm to 500 mm, dependent on rock
the approximately 425 m head created by the scheme. quality and cover. It was constructed in four different segments,
named after local communities, from upstream to downstream, the
Numerous technical papers describing various aspects of the Nathpa, Sholding, Nugalsari and Wadhal sections, ie., extending
scheme have already been published elsewhere, (eg., Kumar and from left to right across Figure 4. Because of concerns regarding
Dhawan, 1999, Dasgupta et al, 1999, Hoek, 1999, 2000; Bagde, the competence of the ground, and the possibility of encountering
2000, Mahajan, 2000). This paper does not discuss the overall geothermal water sources and high stress zones, and also
scheme in any detail, rather it concentrates on examining the rock because of perceived poor previous TBM utilization elsewhere in
conditions encountered during excavation of the section of the mountainous terrain, all of the tunnelling contacts for the HRT were
Headrace Tunnel driven by the Continental-Foundation Joint tendered for Drill and Blast drivage, with none of the joint venture
Venture (CFJV) along the alignment configuration shown on Figure contactors electing to propose an alternative TBM bid. As a
4. While not unique, some of the conditions encountered on this consequence, each of the access and main tunnel drives were
drive are exceptional and amongst the most difficult that are likely driven drill and blast, with face production drilling undertaken with,
to have to be dealt with when driving long tunnels beneath high for the CFJV section, sixteen two-boom electric/hydraulic jumbo
3
mountainous terrain anywhere. Over the 16,042 m long stretch of drills working from 7 headings to complete more than 3 million m
the HRT from Stn. 0+00 at the junction point at the Link Tunnels of rock excavation for the tunnel. Most of the alignment was
just downstream of the Desilting Chambers (Figure 3) to the excavated by the heading and bench method. However because of
Wadhal Adit junction, at the extreme right hand side of Figure 4, the many difficulties encountered due to adverse geological
not only is the geology variable and complex, with numerable conditions, some reaches of the CFJV section of the HRT were
faults, some of which gave rise to major convergence issues (ref. advanced by multiple drifting methods (Figure 5) while other
Figure 5), but the rock cover varies from a minimum of about 90m sections of the alignment further along the HRT, also in difficult
beneath one of the heavily faulted river crossings to a maximum of ground, were constructed with umbrella forepoling methods as
about 1,500m adjacent to the zone of spectacular rock cliffs shown illustrated on Figure 6 (after Hoek, 2000).
on Figure 1, where high stress face spalling and sidewall slabbing
conditions were encountered.
Sta 11615.00
Sta 14204.00
Sta 13615.50
Sta 11602.00
Sta 13125.00
Sta 13599.75
Sta 14192.00
Sta 13438.00
Sta 13133.00
Sta 12690.00
Sta 13425.00
Sta 12702.00
Sta 16062.00
Sta 9687.00
2462.25
2446.50
1858.00
2624.00
2929.00
2637.00
1870.00
2937.00
1928.00
3360.00
3372.00
1925.00
A B C D E F
Page 3 of 10
3.1 Back-Analysis Insights
Two of the extremes of tunnel wall stability behaviour encountered
along the HRT are briefly examined to illustrate some common,
and important inter-relationships that frequently exist between rock
mass characteristics and overburden cover in controlling the
severity of encountered problem conditions. The first back-
analysis case involves a zone of significant closure and squeezing
in the Nugalsari Section of the HRT associated with mining through
a completely granulated quartz-mica mylonite fault zone.
Figure 7 lists the locations of the most adverse faulted zones in the
Wadhal and Nugalsari sections, with Figures 8 and 9 showing
some examples of the ground conditions encountered whilst
traversing through these faults. As is evident from Figure 8, where
a major mudflow developed into the tunnel from one of the faults,
water also complicated dealing with the most adverse of these
zones. In general the inflows associated with the worst faults were
relatively small (typically less than 300 gpm (20 l/sec)). By contrast,
in some of the more blocky and brittle, faulted areas, where
extreme ground condition problems were not encountered, heavy
groundwater inflows, of up to 2000 gpm (150 l/sec) occurred
(including in some cases, hot >50°C water). In such zones,
progress rates were significantly affected, with advance often
reduced to well less than one metre per day.
Figure 10 – Disruption to Primary Rib Support
associated with benching towards Major Fault
Figure 9 – Rock Conditions and Strain Analysis Approach for Figure 11 - Strain Based Ground Behaviour
Wadhal RD 2630 Fault Zone Classification (after Hoek and Marinos, 2000)
Page 4 of 10
back-analysis assessments were completed using both numerical formulations utilized the Kirsch solution to rapidly determine
modelling methods and the semi-empirical approach suggested by induced stress conditions along the tunnel alignment so as to help
Hoek and Marinos (2000). As shown on Figure 9, which determine zones where stress : rockmass strength ratios might be
summarizes the intersected fault zone geology through this critical adverse. This formed an initial basis for assessing whether such
area, quite a number of poor rock areas existed in this section of zones would occur in areas where the rock would be hard and
the HRT where adverse conditions might occur. competent, where stress slabbing and spalling might prevail, or
where the rock would be weak and deformable, where potential
The effects of such zones on tunnelling behaviour can be broadly squeezing could be the issue of most concern.
assessed using the Hoek-Marinos closure prediction method,
allowing credible back-analysis of the possible magnitude of Subsequent enhancements to these initial approaches have now
convergence, in this case with σcm/po ~ 0.06 and ε >60%, (ref. incorporated quantitative algorithms and other empirical guidelines
Figures 9 and 11) extreme squeezing conditions are suggested from amongst others Singh, et al, 1992, 1995, Barton, et al., 1977;
(ref. descriptive strain zones A-E, as listed on Figure 11). Grimstad and Barton, 1995, Carter, 1990 and Kirsten, 1988. These
refinements have been generally targeted towards developing a
As is also evident from Figure 9, the RD 2630 fault is located
amidst an area of moderate quality rock mass where no adverse
conditions would normally be expected (and none were
encountered) and where there is no significant change in
overburden cover crossing the faulted areas. However, back-
analysis of the fault zone area, for the assessed rock mass quality
(Q ~ 0.05 with RQD = 20%, ie., equivalent RMR = 17)) indicates
that severe swelling was entirely feasible even though the
overburden cover was less than 650 m.
These back-analysis observations led to the initial development of This then allows a first order ranking to be carried out to define any
a series of parametric analyses being carried out to attempt to potential impacts that might be sufficiently adverse as to negate the
better pre-define likely problem zones that could be encountered in choice of that alignment.
the remaining tunnelling; with the aim of determining this well
ahead of actually excavating into potential problem areas. Early
Page 5 of 10
A matrix tabulation, such as Table 1 allows each of the major types develop where soft deformable rocks exist, or faults have to be
of geotechnical tunnelling risks to be quantified and ranked with traversed, particularly if adverse water inflow conditions occur.
respect to each other. Here a simple qualitative scale is presented
reflecting assessed comparative tunnelling difficulty for each of the
hazards; with squeezing conditions considered to create problems
more than double the severity of those associated with slabbing;
which, in turn, are ranked as being more of a nuisance than
significant groundwater inflows, while moderate groundwater
inflows, which can usually be handling by active pumping systems
at the tunnel face are ranked as of somewhat more importance,
than zones of thin cover (on the assumption that in such zones,
other geotechnical issues will be important).
Page 6 of 10
Taking the SRF criteria established by Kirsten and modifying them While calculating SRF values for each tunnel sector helps provide
still further to incorporate key aspects of a more recent a reasonable indicator for zoning the tunnels and establishing the
knowledgebase of information compiled by Grimstad and Barton potential lengths where problematic conditions might occur, and is
(1995), spalling and squeezing conditions can be usefully related to thus of great value for the sort of ranking requirements needed at a
the Q-system SRF parameter. In this context, as a means to apply preliminary level of study, it is tunnel size independent when
the above general approach to delineating the extent of potentially considered solely in terms of a rock strength to overburden stress
troublesome zones along each of any alignments under study, in ratio (σcmass/σv). Similarly Singh’s (1992) σCMass /σ(V>350Q) approach,
both competent rock zones and in association with faults etc., is also tunnel size independent, as this merely relates squeezing
appropriate SRF values can be computed using Kirsten’s (1988) likelihood to the minimum overburden cover at which squeezing
⅓
polynomial expressions, namely: may occur [viz., H > 350 Q (m), for a rock mass with strength
⅓
defined as σC.MASS = 7 γ Q (MPa)]. Applying these relationships,
For fractured competent rock; which are based on collected case records from Himalayan
0.346 1.322 1.413 tunnelling (principally from the Indian subcontinent), nevertheless
SRF = 0.244k (H/σC) + 0.176 (σC/H) ,
provides a good second backup for checking inferred conditions
where k is the principal field stress ratio, H the cover
where the SRF method suggests squeezing potential.
depth (m) and σC is the uniaxial compressive strength
of the intact rock (MPa).
Some better account of tunnel size and relative degree of severity
…and…
of damage can however be made if the tangential stress to wall-
For weak, disturbed and faulted zones;
-0.329 rock strength ratio (σθ / σcmass) is derived for each segment of any
SRF = 1.809 Q
alignment under study by examining the alignment with reference
to cover depth and Q/RMR values for that particular tunnel
segment. This method, which was formalized by Alber, 1988 for
determining Factors of Safety (defined as σCM / σθMax ) for zoning
rock conditions that might present difficulties for TBM applications,
simply compares rock mass strength at the tunnel periphery to the
induced tangential stress, as estimated from the Kirsch solution.
For the crown the maximum tangential stress is given by σθCrown =
σv(3k - 1), where k, the horizontal to vertical stress ratio for the
various proposed alignments would be estimated as k ~ 2.0
typically for near-surface excavations, conservatively ranging down
to k ~ 0.8 potentially for the deeper, highest cover zones (ie., under
the centres and margins of the main mountain ridges), where
vertical stresses might dominate; suggesting that sidewall
conditions might be more critical, for which the Kirsch solution can
be rewritten as: σθSidewall = σv(3 - k).
Page 7 of 10
the various faults and major structure zones so that an appreciation This procedure, although not totally rigorous, does allow some
can be gained of the likelihood of encountering water, on perhaps a rapid appraisal to be made of the extent of potentially problematic
three point scale – high, moderate and low potential inflow. Length crown cover conditions for any given rock quality. The extents of
estimates can then be prepared of the perceivable extent of major zones of thin cover can thus be readily identified by this method
and/or moderate level inflows for each alignment, with the and then summed for each alignment, providing another key
summations then incorporated into the ranking matrix as another parameter for inclusion as a line item within an overall hazard
key component for optimization study. ranking matrix aimed at assessing all the tunnels under study.
Figure 15 – Typical Tabulation for Stress State, Spalling or Squeezing Conditions, Water Inflows and Low Cover Zones
Page 8 of 10
extent of the potential problems for each alignment in this example
tabulation the total summation of “at risk” lengths for each category
have been summed to give a length value in kilometres. On Figure
14, these have then been ranked and colour coded on the following
scale … 0 – 0.1km = low risk, yellow; 0.1 - 0.5km = moderate risk,
orange; and >0.5km = high risk, red.
Page 9 of 10
7.0 REFERENCES
Grimstad, E and Barton, N. (1993) Updating the Q-System for
NMT. Proc. Int. Symp. On Sprayed Concrete, Fragernes.
Alber, M. (1988) Design of High Speed TBM Drives. Proc.
Canadian Tunnelling; pp.181 - 187. (From selected papers from Grimstad, E and Barton, N. (1995) Rock Mass Classification and
th
the 15 Can. Tunnelling Conference, Vancouver) the Use of NMT in India. Proc. Int. Conf. On Design and
Construction of Underground Structures, New Delhi, India.
Bagde, M.N., (2000) Finite element analysis of underground
caverns of Nathpa Jhakri Hydel Project. Proc. Int.Conf. Tunnelling Hoek, E (1999) Putting numbers to geology—an engineer's
Asia ‘2000 544 pp viewpoint. Q. Jnl Eng. Geol. & Hydrogeol. vol. 32, no. 1, pp. 1-
19(19)
Barton, N., Lien, R. and Lunde, J. (1974). Engineering
Classification of Rock Masses for the Design of Tunnel Support, Hoek, E., (2000) Big Tunnels in Bad Rock, The Terzaghi lecture –
Rock Mechanics. Vol.6, pp.183-236. presented at the ASCE Civil Engineering Conf., Seattle, Oct 18-21,
2000
Barton, N. (1976). Recent Experiences with the Q-system of
Tunnel Support Design. Proc. Hoek E and Brown E.T. (1988) The Hoek-Brown failure criterion - a
Symp. on Exploration for Rock Engineering, Johannesburg, 1988 update. Proc.15th Canadian Rock Mech. Symp. (ed. J.H.
pp.lO7-l17. Curran), Toronto: Civil EngineeringDept., University of Toronto, pp.
31-38.
Barton, N.R. (1976). The Shear Strength of Rock and Rock Joints.
Intnl. J. Rock Mech. Min. Sci., Vol. 13, No. 10, pp. 1-24. Hoek E. and Brown E.T. 1980. Underground Excavations in Rock.
London: Institutionof Mining and Metallurgy
Barton, N., Lien, R. and Lunde, J. (1977) Estimating Support
Requirements for Underground Excavations, in Design methods in Hoek, E. and Marinos, P. (2000). Predicting Tunnel Squeezing.
th
Rock Mechanics. Proc. 16 US Sump. On Rock Mechanics, Tunnels and Tunnelling International, Part 1 – November 2000,
Minneapolis, USA, pp.163-177. Part 2 – December.
Carter, T.G., (1992) A New Approach to Surface Crown Pillar Kirsten, H.A.D., (1988) Discussion Contribution relating to the
Design. Proc. 16th Can. Rock Mechanics Symposium, Sudbury, Norwegian Geotechnical Institute Q System. In Rock Classification
pp. 75-83 Systems for Engineering Purposes. ASTM STP 984, ed. Kirkaldie,
L., Philadelphia, pp.86-88
Carter, T.G., (2000) An Update on the Scaled Span Concept for
Dimensioning Surface Crown Pillars for New or Abandoned Mine
Kumar, R and Dhawan, A. K., (1999). Geotechnical Investigations
Workings. Proc. 4th North American Rock Mechanics Conf.,
of Nathpa Jhakri Hydro Electric Project Proc. Workshop on Rock
Seattle, pp.465-472
Mechanics & Tunnelling Techniques, Shimla
Castro, L.A.M.; McCreath, D.R. & Kaiser, P.K. (1995). Rock Mass
Kumar, N., Varughese, A., Kapoor, V.K., Dhawan A.K. (2004) In
Strength Determination from Breakouts in Tunnels and Boreholes.
th Situ Stress Measurement and its Application for Hydro-Electric
8 ISRM Congress, Tokyo: 531-536.
Projects—An Indian Experience in The Himalayas , Paper 1b 02 —
Sinorock-2004 Symposium, Int. J. Rock Mech. Min. Sci. Vol. 41,
Dasgupta, B., R. Singh and V. M. Sharma. (1999) "Numerical
No. 3
Modelling of Desilting Chambers for Nathpa Jhakri Hydroelectric
Project," in Proceedings of the 9th ISRM Congress on Rock
Mahajan, S., (2000) Practical application of steel fibre reinforced
Mechanics. Paris, 1999, Vol. 1, pp. 359-360. Rotterdam: Balkema.
shotcrete in desilting chambers of Nathpa Jhakri Hydroelectric
Project Proc. Int.Conf. Tunnelling Asia ‘2000 544 pp
Duncan Fama, M. E. (1993) Numerical modeling of Yield Zones in
Weak Rocks. In Comprehensive Rock Engineering. (ed.
Singh, B., Jethwa, J.L., Dube, A.K and Singh, B (1992) Correlation
J.A.Hudson) Vol. 2 pp. 49-75, Pergamon, Oxford.
between Observed Support Pressure and Rock Mass Quality. J.
Tunnelling and Underground Space Technology, Vol 7, #1, pp 59-
Eberhardt, E. (2001) Numerical Modelling of Three-Dimension
74
Stress Rotation ahead of an Advancing Tunnel Face. Int. J. Rock
mech. Min. Sci. Vol 38, pp499-518
Singh, B., Jethwa, L.L and Dube, A.K (1995) A Classification
Fasching A. and Bofer, M. (1997) A Tunnel Under the Andes. System for Support Pressure in Tunnels and Caverns. J. Rock
Tunnels and Tunnelling International. April Edition pp.34-37 Mech and Tunnelling Technology, Vol 1, #1, pp.13-24
2005. Proc. Int. AFTES Congress, Tunnelling for a Sustainable Europe, Chambery, pp. 349-358 Page 10 of 10