Академический Документы
Профессиональный Документы
Культура Документы
PipeLine
h Railway Jacking
1 | h CC-GRP Culverts DN 3000 Jacked Under Railway, Cikowice, PL
3 | h Jacking Pipes Installed under a Railroad, Ettelbruck, LU
4 | h Jacking Pipes Premiere in Hong Kong
5 | h Pipes Jacked at Port Cape Lambert, AUS
6 | XXL h GRP Jacking Pipes replace Concrete Railway Culvert, PL
7 | Interview with Kimberly Paggioli h GRP Pipe: Jack Of All Trains
8 | Trenchless Project on the Rails with h GRP Pipes, Budapest, HU
8 | Auger Boring Small Diameter h GRP Pipe Beneath Dutch Railway, NL
9 | Croatias Most Challenging Project Realized with h Pipes
10 | Russian Railways Authorize h Products
11 | h GRP Jacking Pipes Under Railway Track in Tinec, CZ
12 | Polish Railway Project on the Fast Track with h, Chiechanw, PL
Year of construction
2014
Construction time
2 months
Total length of pipeline
136 m in total,
4 parallel lines of
34 m each
HOBAS Poland supplied the required pipes with an external diameter of 3000 mm for the
realization of the culverts. The pipes smooth inner surface ensures that flood water which
flows through them and usually contains various impurities does not lead to siltation.
HOBAS Pipes also made it much easier to resume jacking works after an installation
interruption due to heavy rain: The water causes the sandy soil to become slightly
compacted and adhesive, and the thrust force required to restart works after the interruption is usually quite high. Thanks to the smooth outer surface, the necessary
forces would be comparably lower and a restart quite easy.
Diameter
De 3000
Pressure class
PN 1
Stiffness class
SN 40000, SN 64000
Application
Culvert beneath railway
for flood protection
Installation method
Trenchless installation /
pipe jacking
Before the start of the jacking works, the rail tracks were equipped with special
beams that transferred the load from the trains evenly to the rails in case of any
ground movements. The structure of the pipes, on the other hand, was strong
enough that even in the course of their installation the vibration induced by
passing trains was not felt inside. The jacking machinery was secured against
sliding on the sandy and slippery soil and positioned in a way to install the
pipes with a slight slope, so that the water would eventually flow in the right
direction. Once a culvert had been jacked through the embankment, its ends
were specially prepared: One side was bevelled from the top, while on the
uninhabited side of the embankment the culverts were equipped with special
flaps, which prevent the backflow of water to the village.
Client
PKP (Polskie Linie
Kolejowe) S.A.
The construction of culverts in Cikowice took around two months. The project is
in successful operation and the client satisfied with the HOBAS Solution.
Fmd: hobas.poland@hobas.com
Year of construction
2009
Construction time
3 days
Total length of pipeline
40 m
Diameter
Not only the installation method but also material selection calls for careful consideration. Electric rail systems create electromagnetic fields during
operation, which can lead to corrosion in materials such as steel or cast
iron. In addition, leakage current could flow to the metal components in
the pipes. Risks that have to be avoided at all costs.
De 1720
Wall Thickness 68 mm
Stiffness class
SN 64000
Application
Protection Pipe
Client
SIDEN
Contractors
Kuhn, K-Boringen
Special Features
Jacking under a railroad
line, fast installation,
low weight, small out-
In February 2009, HOBAS Pipes (De 1720) were jacked under the railroad
at a depth of 3 m. After installation, the pipeline was filled with a
25 cm thick layer of concrete to facilitate future maintenance work on the third party lines inside it. Once
construction had been completed, the client and
contractor alike were impressed by the rapid
installation rate and very pleased with the
pipes low weight and small outside
diameter, which meant that the jacking pits were much smaller than
anticipated. Quality from HOBAS
solutions for all situations!
Fmd:
hobas.france@hobas.com
side diameter
In December 2013, HOBAS Pipes De 1026 SN 320000 were jacked in the Chinese metropolis
Hong Kong underneath a railway track as protection for power lines.
Construction time
6 nights / 15 hours
Diameter
De 1026
Pressure class
PN 1
Stiffness class
SN 320000
Application
Protection pipes for
power lines
Client
MTR Corporation
Limited
Planner
Hong Kongs Mass Transit Railway (MTR) includes more than 200 km of rail. With an
average of 2.45 million passengers per day, it is one of the worlds most profitable rapid
transit railway systems. Its operating company, the MTR Corporation, is currently extending the network in the vicinity of Hung Hom railway station in the urban area
of Kowloon. Since the space around the existing rail track was very limited, the
construction company had to remove parts of the adjacent slope over a length of
400 m and relocate the existing power transmission lines. With the new planned
route crossing beneath the double-track, the project managers sought for the least
invasive and most sustainable solution. They found what they were looking for
in HOBAS Pipe Systems: HOBAS CC-GRP Pipes with an outer diameter of
De 1026 mm and a stiffness class of SN 320000 were jacked over a length of
12 meters in 2.3 m depth beneath the double-track as protection pipes for the
power lines. Thanks to the non-conductive material and high load capacity,
HOBAS Pipes are ideally suited for the given conditions.
The installation was challenging in several respects. Due to the limited working
space on the tracks ballast bed, the starting pit had to be kept quite narrow
(4 x 4.5 m) and the pipes could not be stored on site but had to be rolled to the
jacking pit one after the other on temporary tracks over 50 m distance. As the
railway track is in operation 19 hours a day from 5:30 to 00:30 a.m., the client allowed the jacking works to be conducted at nighttime between 1:30 and 4:00 a.m.
only. The contractor had to work very efficiently to achieve each nights installation
goal within these 2.5 hours. With their smooth outer surface and quick and easy
coupling system, HOBAS Pipes increased the installation efficiency significantly.
Non-conductive
features, high load
capacity, smooth outer
surface, easy coupling
system
Year of construction
2012
Construction time
6 months
In the 1950s, it was discovered that the Pilbara area is home to one of the worlds largest iron ore
deposits. Since then it has been an integral contributor to the Australian economy with the help of
mining companies such as Rio Tinto. With most of the ore being exported today, a rail infrastructure and large ports have been built to accommodate the ore transportation. One of the largest
of these ports is Rio Tintos Cape Lambert. Trains travel in from Rio Tinto mines throughout the
region, carrying around 80 million tonnes of iron ore per year into Cape Lambert for processing
and ship loading.
Cape Lambert is currently undergoing an upgrade, which will see its capacity more than double
by mid 2015. At the projects completion, an estimated 200 million tonnes of iron ore will be
exported per year from this port. An integral part of the upgrade project was the extension of
the Sams Creek drainage lines, which run under the existing rail lines allowing the release of
stormwater during the wet season. The rail lines needed to stay in constant operation throughout
the construction works in order to ensure the continual loading of ships. Stopping the productivity
was not an option, making trenchless installation the only choice.
The designer of the new drainage culvert Sinclair Knight Merz planned two rows of
2100 mm internal diameter pipes with approximately 100 meters length each.
HOBAS Jacking Pipes with an outside diameter of 2250 mm and a stiffness
of SN 32000 were specified for this purpose. With the soil being hard and
rocky, the initially calculated jacking force added up to 7850 kN. Thanks
to the smooth outer surface of HOBAS Jacking Pipes, the actually applied jacking forces were much lower than expected. The substantially
smaller outside diameter as compared to an alternative concrete
pipe had the additional benefit of allowing increased ground cover
beneath the rail line, reducing both risk and installation time. Furthermore, the lead-time for HOBAS was substantially shorter than that
of locally supplied concrete pipe, and given the tight timeframe for
the project, HOBAS proved to be the best solution.
The installation set a new record in terms of the largest diameter
HOBAS Jacking Pipe ever installed in Australia, and it paved the way for
similar projects in the ever-growing mining industry in Australia. The Rio
Tinto drainage system was also used as an opportunity for creating cultural
awareness: Local artists were invited to paint the HOBAS Pipes in the artistic
style of the traditional landowners. The imagery is supposed to bring good fortune to the land and HOBAS Pipes have become truly part of the local landscape.
Fmd: andy.holman@globalpipe.com.au
Contractor
NRW, Tunnel Boring
Australia
Advantages
Low jacking forces,
small inner/outer
diameter ratio
Since the concrete culvert crossing beneath the railway line E65 Warsaw - Gdynia in the polish
city Gdask could no longer handle high water levels from the nearby stream, it was decided to
replace it. For this purpose, HOBAS Pipes with an external diameter of 3600 mm were jacked
beneath the railway embankment.
Diameter
De 3600
Pressure class
PN 1
Stiffness class
SN 40000
Application
Railway Culvert
Client
The 2 x 1.2 m concrete culvert could no longer handle the nearby Krlewski streams
elevated water levels during periods of heavy rain, which occasionally flooded the surrounding area. There was no doubt it had to be replaced. The first respective plan involved
two parallel 2 x 2 m square concrete culverts, laid in open trench. It soon became clear
however that the design was unsuitable for the given circumstances and that a different
approach was necessary. In 2013, a new rehabilitation project was initiated that involved
the construction of a single circular. It was decided to install the new culvert by means
of jacking and to use HOBAS GRP Pipes with a diameter of De 3600 for this purpose.
The jacking works were carried out using a set of hydraulic jacks and a cutter head that
was specially designed for the project. Where the routes of the old and the new pipeline
intersected, the old culvert was demolished and removed. At the end of the installation
process, the annular space between the old and new structure was grouted with cement.
For safety reasons, the rail tracks had to be equipped with beams. In the case of any
ground movements caused by the jacking process, these beams would transfer the load
from the trains evenly to the rails.
The E65 is a main-line railway with trains passing every 3 minutes. Although the trains speed
was reduced to 30 km/h in this section because of the construction works, the trains could stay
in operation without interruptions thanks to trenchless installation. The contractors, PUT INTERCOR from Zawiercie and PROI2 from Katowice were highly satisfied with the
project result they have already installed HOBAS Pipe Systems several
times in the past and appreciate the products high quality.
Fmd: hobas.poland@hobas.com
The AREMA committees that evaluate products do a very thorough job and accept only the
highest performing products. The inclusion in
the Manual is therefore a great testimony to the
quality of our pipes.
Year of construction
2007
Total length of pipeline
30 m
Diameter
De 1720
Pressure class
The creek rdgrok, also known as Devils Ditch, leads rain water from the Buda
Moutains into the Danube in Budapest. While the creek flows freely in the upper part of
the mountains, it runs through a culvert midway down. In Hvsvlgyi street in Budapest,
this culvert passes underneath a streetcar track. When it needed to be replaced in 2007, the
contractor opted for trenchless installation with HOBAS Pipes to keep the impact on
the environment and traffic as low as possible and to benefit from the GRP materials excellent features. 30 meters of pipe De 1720, SN 32000 were jacked beneath
the rails the project was completed to the contractors utmost satisfaction.
PN 1
Stiffness class
SN 32000
Advantages
Low impact on environment and traffic, optimal
structural properties
Fmd: hobas.hungary@hobas.com
Year of construction
2011
Length of pipe
36 m
Diameter
De 220,
pipe wall thickness 20 mm
Installation method
Auger boring
Application
Protective pipe
Contractor
ProRail
Advantages
Quick installation due to
push-to-fit couplings, light
but sturdy material, flexibility in pipe design
Slavonia is a region in eastern Croatia and known as the countrys breadbasket. To ensure a successful harvest, a reliable irrigation system is
necessary and this is why 513 m HOBAS Pipes De 2047 have been
jacked as part of a large-scale irrigation project.
2011
Construction time
3 months
Total length of pipeline
513 m
Diameter
De 2047,
pipe wall thickness 65 mm
Pressure class
PN 1
Stiffness class
SN 32000
Application
Irrigation pipeline
Investor
Hrvatske Vode
Designer
Institut IGD d.d.,
Krimir Gali d.i.g.
Contractor
Aquaterm d.o.o. Karlovac
Advantages
Fmd: hobas.croatia@hobas.com
Only few pipe producers offer a broad range of technical solutions and are authorized to install their products beneath Russian rail tracks. In order to receive approval, the products
need to comply with the requirements and standards of the Russian Railways (RD),
one of the three largest rail companies worldwide. Safety is absolutely essential.
Pipe length
137 m
Diameter
De 1414 and 1638
Pressure class
PN 1
Stiffness class
SN 32000 and 40000
Application
Given the circumstances, the contractor decided for HOBAS Pipes De 1434
which should be jacked directly next to the old pipe beneath the railway track
by means of auger boring. It was planned to first dispose of the spoil with an
auger transporting it through a steel casing. Once the boring head had made
its way through to the receiving pit, HOBAS GRP Pipes were connected to the
steel casing in the thrust pit and driven to the receiving pit. Subsequently,
HOBAS Pipes De 1638 were installed in open trench. For the duration of the
construction works on the rail around the site, trains were slowed to 40 km/h.
Thanks to trenchless installation, the train traffic could be maintained.
HOBAS Products not only scored with their structural properties and corrosion
resistance (especially regarding stray currents) but also with a long service life and
easy installation. The construction works were completed in October 2012, after four
months only and to the complete satisfaction of everyone involved.
After this projects success, RD gave HOBAS Russia
the official authorization for using HOBAS Products
also in future projects that run beneath the
Russian railway.
Fmd: hobas.russia@hobas.com
Fmd: hobas.czech@hobas.com
Year of construction
Application
2010-2011
Sewer
Client
330 m
Glasspol Krom
Diameter
Contractor
De 427
Michlovsk
Pressure class
PN 1
Advantages
Stiffness class
SN 100000
Installation
Jacking
leak-tightness
Pressure class
PN 1
Stiffness class
SN 64000
SN 100000
Application
Stormwater,
animal passageways
Installation method
Microtunneling
Client
PKP Polskie Linie
Kolejowe S.A.
Contractor
Przedsibiorstwo
Przewiertowe MOTYL
Advantages
Quick installation,
The client, the Polish State Railways (PKP Polskie Linie Kolejowe S.A.), was already
familiar with HOBAS Products, which are technically approved by the Road and Bridge Research Institute (IBDiM) and the Polish Railway Institute (IK). The first HOBAS GRP Railway
Culvert, a DN 1300 section, had been installed under the E20 railway at Mienia in 2003. One
year later, the second followed at Ostrw Wielkopolski using a pipe with an external diameter
of 2047 mm. In 2005, a line De 1229 to 1434 in diameter had been installed under the railway
between Misk Mazowiecki and Terespol. Numerous further projects followed.
corrosion resistance
The engineering team from HOBAS worked closely with the design office in order to determine
adequate stiffnesses for the pipes, and the load capacity was calculated on the basis of the finite
element method (FEM). Highly experienced in directional drilling and similar jobs, the Polish
contractor Przedsibiorstwo Przewiertowe MOTYL made sure that microtunneling ran smoothly
and was completed successfully. In order to streamline the installation process and save on time,
the company ordered angular cut pipes and equipped these with precast headwalls from HOBAS
Poland. This way, the works were completed in a couple of days only.
Constantly scrutinizing and double checking the performance of pipes to provide clients with
optimal solutions, HOBAS decided to monitor the performance of the employed De 2047 pipes. To
this end, external experts in strength analysis were assigned to measure the pipes before and after
they were installed. After two years of operation they will be measured once again for final results.
Fmd: hobas.poland@hobas.com