Академический Документы
Профессиональный Документы
Культура Документы
ABSTRACT
Various methods exist to connect a pipeline end to a platform or a
subsea structure. Normally, a separate spool or jumper is used, but a
direct tie-in is advantageous if this can be used. Different ways of direct
subsea tie-ins exist, however the main challenges with these methods
are relatively large forces on the connection and large pipeline stresses
close to the connection point.
This paper shows how application of residual curvature near the end of
the pipeline can be utilized for direct tie-in of pipelines to subsea
structures. This is done by solving the existing direct tie-in challenges
with large forces on the connection and large pipeline stresses close to
the connection point.
Tie-in forces will be illustrated for the main variables affecting the
pipeline tie-in point such as: soil friction, residual curvature parameters,
tie-in and operational loads, various tie-in systems and their
requirements. Effect on lay initiation and lay down will be outlined.
KEY WORDS:
residual; curvature.
BACKGROUND
The reel-lay method is frequently used for installation of smaller
diameter offshore pipelines. The installation process involves onshore
fabrication of pipe sections, loading of the pipe onto the reel ship
(spooling on), and finally unreeling during the offshore installation.
The pipeline is normally plastically bent on the reel and over the
aligner, due to which the pipeline runs through a straightener system
before leaving the reel ship, ref. Fig. 1. The straightening scheme is
normally a three point bending system, and the position setting of the
system is hydraulically adjustable, and can be quickly altered as
required, e.g. by change in the pipeline outer diameter.
The quick, hydraulic adjustment of the straightener system can be
utilized to create sections with residual curvature in the pipeline. This
method was patented by Statoil in 2002 in Norway, Denmark, UK and
USA. The intention is that these residual curvature sections provide
axial flexibility in the pipeline similar to an expansion loop, either to
accommodate compressive or tensile forces.
Recent work performed by Statoil and IKM Ocean Design have also
proven that the axial flexibility achieved by the residual curvature
method, can be utilized for other purposes also:
1)
2)
Risk issues
Comparative costs
Type of service, design loads
and design life
Pipe material
Water depth and
hydrodynamic loads
Pipeline end expansion
Field layout and pipeline
routing
Tie-in area congestion
Size of equipment/tools and
access requirements
Method of metrology
Tolerances
Equipment capacities, quality
and track record
Protection requirements
No. tie-ins to be performed, as
well no. different type tieins/sizes etc, standardization
Fishing activity at the location
Seabed condition
Installation method, schedule
and lay direction
Pigging requirements
Market situation
Vessel limitations
Region of the world where the
project takes place
Development and long term
strategic plans
National and operator
requirements
Hyperbaric welding
Above water weld
Bolted flange connectors
Mechanical clamp connectors
more vulnerable than rigid pipe solutions, and thus have a reduced lifetime compared to a rigid solution. In addition, flow assurance issues
could also be a concern for flexible. A typical flexible tail tie-in layout
is shown in Figure 4.
Figure 5: First End Direct Tie-in: Pull-in to J-tube and Lay Away
Direct tie-in subsea, connect and lay away: This is a simple
alternative for tie-in, but is normally for first end tie-ins. Due to the
expansion forces being transferred directly into the subsea structure or
riser, this method is relying on a robust tie-in structure or that
expansion forces are absorbed in an adjacent pipeline section, e.g. by an
anchor or a curve in the pipeline route.
Deflect to connect, see Figure 6: This direct tie-in method involves
laying the pipeline down at a predetermined target, angle and distance
relative to the structure/connection point.
Notes:
The same axial and lateral flexibility utilized for direct tie-in, will be
even more efficient when it comes to absorbing and controlling
expansion forces/movements caused by pressure and temperature loads
during the operating condition. In fact, pipeline expansion effects can
be seen to neutralize the tie-in forces remaining in the system.
Figure 10: First End Direct Tie-in using The Residual Curvature
Method Typical Initiation Overview.
Hub capacity is often seen to be a governing factor for pipeline tie-ins
using diverless systems. Since hubs on subsea templates typically could
be elevated 2.5 m above the seabed floor, vertical alignment between
pipeline end and the hub is a key parameter. In order to compensate for
this, the hub can typically be tilted slightly downwards, say 3, 5 or 7.
However, further vertical alignment will in many cases be needed. This
has on several projects been solved by introducing rock supports or
adjustable mechanical supports in the adjacent free span.
After the pipeline is pulled down and safely landed in the tie-in
porch/landing frame, the pipeline is ready for the final stroke-in and
finally the clamp connector is made up and the seal can be tested.
Most major tie-in vendors have modern and efficient systems that are
applicable for this method. The latest generation tie-in systems are
compact, modular and simpler compared to the previous generation
tools that also included winch pull-in capability. The basis for all the
new tie-in systems is a stroke and connect functionality. As discussed
by Olsen (2013), the new generation tie-in systems HCCS, HCS and
UCON, are based on landing the termination head into the porch,
letting the ROV stroke the hubs together by the temporary stroking tool
and engage the connector. Also other tie-in systems are available, that
will provide the same functionality as the three mentioned above. Some
minor modifications to the structure or equipment may be required,
however these are considered small.
Detailed routing and pipeline rotation design is required in order to
ensure that the subsea layout has space for the lateral displacements
that the method requires. If two or more pipelines, cables etc are
approaching the subsea structure along a common corridor, they should
have sufficient separation in order to allow displacements and/or
rotations in the opposite direction.
Second end tie-in: Even though the proposed method is considered
more suitable for a first end tie-in, it is also considered relevant and
suitable for a second end tie-in as well. Hence, the solution may be
utilized generally on a project without having different solutions at first
and second end tie-in points.
One feasible approach to a second end tie-in, is to install and lay down
the pipeline end with a heading passing slightly on the outside of the
subsea structure to be tied into with sufficient clearance, see Figure 11.
Notes:
Figure 11: Second End Tie-in using The Residual Curvature Method
Laydown Position, Ready for Lift, Shift & Docking Operation.
The target box axial tolerance is a crucial parameter for second end tieins and minimizing tolerances is important. The pre-bent section in
combination with the wire tensioning system or buoyancy, provides the
possibility to retract the pipeline end considerably. However, in the
event that the pipeline end is installed outside of the planned target box,
the pipeline end may have to be recovered to surface for length
adjustment (as on any other project).
After lay down of the pipeline end, the position of the end relative to
the tie-in point and the 3D perimeter of the structure should be checked
and evaluated. Following the relative pipeline end position, the wire
tensioning system can be tensioned up in order to retract the pipeline
end in order to create sufficient access for the lateral lift, shift and
handling towards the tie-in porch on the subsea structure. The lift and
shift operation should be performed with the vessel crane supported by
ROV visuals, winches, required installation aids etc. After landing the
termination head directly into the porch, the stroking and engagement
of the connector can be made in accordance with the specifics of the
selected tie-in system.
Note:
Figure 12: Second End Direct Tie-in using The Residual Curvature
Method Final Make-up of Clamp Connector.
General Rotation Control: Achieving approximately 90 pipeline roll of
the residual curvature section during installation is advantageous for a
safe and robust design, because then the pipeline has a lateral deflection
and the residual curvature section is in contact with the seabed. If the
pipeline does not roll the residual curvature section may be free
spanning as well as being exposed to hydrodynamic loads, trawl loads
etc. Pipeline roll has been assessed analytically in Appendix A, and it is
seen that the pipeline will roll approximately 90 during installation.
This was also the experience from the Skuld project in 2012 (Endal and
Egeli, 2014). The additional weight when waterfilling the pipeline will
be an eccentric load that will encourage the pipeline to rotate until
contact with the seabed. Hence, the pipeline will want to rotate
towards 90.
An alternative to control the direction of rotation is to attach a clamp at
either end of the prebent section with a cantilever arm with attached
buoyancy to the arm. The arm can then be fixed at 3 or 9 oclock
depending on which direction the rotation should take place. The
clamp/arm arrangement could also be extended to have a second
function including compressing the prebent curve. Then, buoyancy can
be attached in the middle with a wire extended to each clamp arm.
Careful assessment of influencing factors should be accounted for
during design in order to ensure that the residual curvature section
rotates as planned into the horizontal plane. Additional installation aids
such as the possibility to pull the section down via a return sheave or a
subsea winch etc should be considered. However, as was experienced
on the Skuld project, the residual curvature sections rotated as planned
(Endal and Egeli, 2014).
Case
C
Figure 13: SIMLA FE model for Residual Curvature / Direct tie-in
analyses (exaggerated lateral scale)
A typical 12 pipeline case in the North Sea is considered for the study
cases.
Main data for the example pipeline analysed in this paper are given in
Table 1.
Value
DNV SML 450
323.9 mm
15.9 mm
40 mm PP
130 barg @ +30 m
Design temperature
Submerged weight (empty/waterfilled)
50 C (max)
29.3/98.1 kg/m
Gas
480/430 kNm
Water Depth
Friction Coefficient (axial/lateral)
Residual Lay Tension
300 m
Description
Base Case with 70 m @ 0.26% residual curvature section, 15
m transitions on either side of the curved section, waterfilled
pipe and no buoyancy (Wsub =98.1 kg/m) , 1500 m model
length and 100 m straight section towards tie-in point, 1.5 m
stroke.
As Case A, but with 68.8 kg/m buoyancy from tie-in point
until end of residual curvature section, Wsub=29.3 kg/m (i.e.
the same effective submerged pipe weight as in empty
condition).
As Base Case, but where the wire tensioning system is
compressed 1.2 m prior to pipeline termination head docks
into the tie-in porch. After docking, the 1.2 m wire retraction is
gradually released prior to stroke-in. This is followed by
applying pressure and 1.0 m feed-in from the pipeline side
(operational condition).
As Case B, but with 40 m instead of 70 m long residual
curvature section, 1.5 m stroke.
As Case B, but with wire tensioning system attached, reducing
the wire length 10 m in order to see what tensile forces are
required for the wire.
As Case A and B, plus rotating the termination head up to 5
about the vertical axis in order to simulate the bending
moments for correction of misalignment.
0.6
40 kN
Effect of friction/buoyancy
The possibility to retract the pipeline end for a second end tiein and/or generally for handling and disconnection.
Alternatively, the pipeline will have high residual capacity for other
type of loads, eg. trawl loads.
Case A
As seen above in Figure 14, the force is 400 kN for 0.5 m stroking and
consequently too high for the applicable tie-in tools. Hence, it is
concluded that the considered 12 pipeline case cannot be tied in
directly in waterfilled condition without the assistance of installation
aids.
Case B
Case B is as Case A, but with 68.8 kg/m buoyancy applied after
pipeline water-filling along the residual curvature section and transition
lengths. As seen in Figure 14, the force needed to stroke 0.5 m is 185
kN, i.e well within the capacity of available tie-in tools.
Case C
This case is as Case A, except that a wire tensioning system is used to
compress the prebent curve by 1.2 m in the sagbend during laydown
prior to the pipeline end docks into the tie-in porch. Hence, a large the
deflected shape is large. After docking, the pipeline is flooded and wire
is gradually released prior to stroke-in. The release of the wire causes
the pipeline to push back towards the tie-in point and thus reduce the
stroking force, see Figure 14. After stroking 0.5 m, the pipeline is filled
with gas, pressurized and subsequently given a 1 m pipeline feed-in.
Figure 18 shows the deflected shapes for various steps in the process.
the as-laid & docked & prior to wire release step. Releasing the wire,
causes the effective force to drop to almost zero at the prebent section,
while the 0.5 m stroke increases the tensile force at the tie-in point. As
the pipeline is de-watered and filled with gas (reduced submerged
weight compared to a waterfilled pipe), the pipeline shape becomes
more relaxed and the tensile forces reduces again. Pressure and pipeline
feed-in causes the pipeline effective force to go into compression.
Figure 23 shows the pipeline end retraction and the associated wire
force as a function of shortening the wire length in Figure 11. This
shows that using small tensile loads can easily retract the pipeline end
by several meters. For instance, a load of 100 kN can retract the
pipeline end 3.5 m.
Figure 21: Forces Acting on Tie-in Point During Tie-in & Operation
for Cases B & C
Case D
This case is as Case B except for a 40 m residual curvature section
length. As shown in Figure 14, the stroke-in force is slightly higher
than for Case B, however still feasible for the applicable tie-in tools.
The displaced shape configurations for different stroke-ins are shown in
Figure 22. Due to the residual curvature section being 40 m instead of
70 m, also the lateral displacement prior to stroke-in is slightly reduced
compared to Case B.
The maximum bending moment utilization for 0.5 m stroke length is
0.74 for this case.
Figure 24: Bending Moment Utilization vs Pipeline End Retraction
using the Wire Tensioning System
ACKNOWLEDGEMENTS
The authors wish to thank the managements of Statoil and IKM Ocean
Design for permitting publication of this paper.
REFERENCES
Berge, JO, Repair of subsea pipelines by a remote welding system,
Presented at the Offshore Pipeline Technology (OPT) conference,
Amsterdam, February 2015.
Corbetta, G and Cox, DS, Deepwater Tie-ins of Rigid Lines: Horizontal
Spools or Vertical Jumpers, Presented at the Offshore Europe
Conference, Society of Petroleum Engineers, Aberdeen, Scotland, 7-9
Sept 1999.
DNV OS-F101, Submarine Pipeline Systems, 2013.
Figure 25: Lateral Displacement vs Pipeline End Retraction using the
Wire Tensioning System
Case F
As concluded above under General Results, alignment of the pipe end
can easily be done within the capacity of the applicable tie-in systems.
CONCLUSIONS
Endal, G and Egeli, H (2014). Reel-lay method to control global pipeline buckling under operating loads 2014 OPT Conf, Amsterdam.
This paper has shown that residual curvature sections created during
reel-lay installation enables direct tie-in of pipelines at both first and
second end tie-ins.
The traditional direct tie-in challenges with large forces on the
connection and large pipeline stresses close to the connection point are
solved. Tie-in forces and alignment moments are found to be well
within the capacity of existing stroke and connect tie-in systems. In
addition, efficient methods to control rotation and lay tolerances have
been identified.
The residual curvature method is seen to be effective for both tie-in and
operational loads. Forces in both conditions can be more or less
neutralized.
Residual curvature sections can be effectively installed, as documented
by Endal and Egeli (2014). A cost comparison between the new direct
tie-in method and a conventional spool installation and tie-in indicates a
cost saving potential of MUSD 1.8 per pipeline end in favor of the new
technique, ref. Appendix B.
Other benefits of the new direct tie-in method are:
Figure A1: Total work to bend and twist a 12 pipeline from surface to
seabed (300m water depth), at various lengths on the section with
residual curvature (0.2% local residual strain).
Qty
Unit
Cost
Cost
Price
DTI
Spool
(MUSD) (MUSD) (MUSD)
0.1
-
0.1
0.1
0.1
0.1
0.4
0.1
0.16
0.4
0.65
0.65
0.4
-
0.65
1.3
0.1
0.06
0.06
0.1
0.001
0.25
0.12
0.7
0.05
0.25
0.1
0.3
0.1
0.3
-
0.03
0.1
0.025
0.1
0.1
0.1
-
0.2
0.05
0.1
0.1
5
0.1
0.25
0.25
0.2
-
0.1
0.5
0.1
0.3
2.6
4.4