Академический Документы
Профессиональный Документы
Культура Документы
3. attemp to equalize surface emperature of walls, floors and windoes with room
temperature.
Simply ricing air temperature doesnot achieved sufficient warmth within the
hime. It is necessary to attempt to equalize the surface temperature of walls
and other sorrounding to the room and reduce the temperature between
thermal sensation and the room temperature by insulating the house.
Even whem the room is heted, it is not comfortable if occupants feel warm
around the upper area of the room but their feet are cold.
Reinforcing the insulation performance of floor (i.e installing insulation and air
leakage prevention)increase the floor surface temperature and reduce the
vertical temperature gradient and temperature irregulalrity within the house.
5. Increasing solar shading heat from roof to reduce heat in upper floor rooms.
Reinforcing roof and ceiling insulation prevents solar radiation heat received on
the room from entering the house and reduces the heat in the upper floor rooms
However, a roof cavity (at least 30 mm) is requires if the roof is insulated and
attic ventilation is required if the ceiling is insulated.
4.1.3 Steps for examining insulation building envelope planning and setting target
levels
2. Confirming lifestyle orientation and other condition and setting target level
1) desired thermal environment
that insulation materials are properly and firmly installed the required area inside
the building envelope.
b. Blown in insulation
This is atype of loose fill insulation that is blown into the ceiling, roof, walls and
other component. Example of material include glass wool, rock wool and cellulose
fiber. It is generally easy to install especially for ceiling insulation, but it has
slightly lower performance than batt insulation.
c. Board insulation
This insulation material is often used in the exterior insulation methods for
floor insulation and on the outside of the building frame. This type of material
include plastic foam insulation material, such as extrude polystyrene foam,
expanded polystyrene foam, rigid urethane foam, polyethylene foam and
phenolic foam as well as glass wool and rock wool. Generally it has higher
insulation performance than batt insulation when comparing materials with
the same thickness.
On the other hand, this material is less susceptible to moisture problem. it is
also need to be used with a fire resistant exterior finish when install on the
exterior side of the frame as it is prone to fire and UV damage.
4) Installing insulation
a. installation should with no gap between it and the surrounding frame
b. when installing insulation with integral vapor barrier , sealed batt
insulation has large tabs is recommended
c. it is recommended the minimum thickness of separate vapor barrier film is
0.1 mm
d. it is recommended the minimum thickness of integral vapor barrier film is
0.05 mm
e. Vapor barrier film for residential use is JIS A 6930
2. Foundation installation
Insulation should be installed on the exterior, interior or both sides of the
foundation
Insulation material should be low water absorption such as plastic board
insulation
Make sure to prevent gaps by installing airtight gasket between upper
surface of foundation and groundsill.
Use decay and termite resistant wood for floor framing and slab on grade
foundation for moisture control of the ground can eliminate the need for
chemical preservatives in the crawl space.
5. Ceiling Insulation
Insulation on the ceiling is prone to gaps at the connection between the ceiling
and exterior walls, junction with partition walls, area around ceiling hangers,
between insulation materials, around ceiling seamlessly with the wall to prevent
a gap. Install insulation over the entire ceiling seamlessly with the wall to prevent
a gap
When using batt insulation over standard ceiling sheathing, lay insulation in
parallel to the ceiling joist seats and install without gaps by making slits in the
ceiling hanger. For moisture control, apply a separate vapor barrier film or use
special plasterboard backed with a vapor barrier (Figure 40).
When using insulation with an integral vapor barrier, insert insulation between
the ceiling joists and sample the overlaid tabs of the vapor barrier at the bottom
surface of the ceiling joist. If insulation thickness of at least 150mm is required,
use two layers of insulation and lay the top layer in parallel to the ceiling joists
seats then place the bottom layer between the ceiling joists under the ceiling
joist seats and fasten the tabs.
If a suspended ceiling construction method adopted, used integral vapor barrier.
(Figure 42)
If a blown insulation adopted, it is recommended to install sheathing board so the
ceiling insulation not blocking the attic ventilation. (Figure 43)
7. Roof insulation
In order to prevent internal condensation and promote heat removal in
summer, it is recommended to install a ventilated cavity with a thickness at
least 30mm on the exterior of the insulation.
1) Selecting windows
When designing and installing windows, it is necessary to consider
construction area, solar radiation level, sunshine hours, direction of the
house, insulation performance and cost of windows.
In addition, the purpose and view of room, thermal environment, light
environment and cross ventilation performance should also be in the
consideration before installing a window.