Вы находитесь на странице: 1из 6

INSURANCE SLIP NO

CONTRACTORS ALL RISKS INSURANCE


Insured

a) Principal
b) Contractor

: PETRONAS REFINERY AND PETROCHEMICAL


CORPORATION SDN BHD
: UNIJAYA INDUSTRI SDN BHD

Project

RENOVATION AND REFURBISHMENT WORKS FOR ADDITIONAL OFFICE


FLOORS ON LEVEL 52, 54 & 55 AT VISTA TOWER, THE INTERMARK
FOR PETRONAS REFINERY AND PETROCHEMICAL CORPORATION SDN
BHD
CONTRACT NO.: PRPC/TC3/001/2013

Period of Insurance

12 WEEKS (DATE TBA) WITH 12 MONTHS DEFECTS LIABILITY PERIOD

Location of Risk

As above

Coverage

Standard Lonpac Form


(excluding Designers Risk)

Section 1

Material Damage

To indemnify the Insured against any sudden and unforeseen physical


loss or damage to the construction works from any cause other than
those specifically excluded.
Section 2

Third Party Liability

To indemnify the Insured against any sums which the Insured shall
become legally liable to pay as damages consequent upon:
a. accidental bodily injury or illness to third parties
b. accidental loss of or damage to property belonging to third
parties
occurring in direct connection with the construction works and
happening on or in the immediate vicinity of the site during the
period of insurance.
The Insurer will in addition indemnify the Insured against:
a.

all costs and expenses of litigation


recovered by any claimant from the Insured, and
b.
all legal cost and expenses incurred
with the written consent of the Insurer.
Subject always to the Limit of Liability under Section 2.

1
PETRONAS REFINERY AND PETROCHEMICAL CORPORATION SDN BHD UNIJAYA INDUSTRI SDN BHD
01112013

CONTRACTORS ALL RISKS INSURANCE


Subject Matter

Section 1

1
2

Total Contract Value


Materials or Items supplied by
Principal(s)
Construction Plant and Machinery
Removal of Debris
Professional Fees
Principals Existing Property or
Property Belonging To or Held in Care,
Custody or Control By the Insured

3
4
5
6

Material Damage
the

Total Sum Insured


Section 2

RM
RM

1,859,157.00
-

RM
RM
RM
RM

RM 1,859,157.00

Third Party Liability

Limit of Indemnity 1) RM 2,000,000.00


2) Unlimited
Premium Rate

0.125 % on Third Party Liability Limit

Total Premium

Gross Premium
6% Service Tax
Stamp Duty
Total Premium Due

Deductibles

Section 1 : Material Damage

Any One Accident


Any One Period

RM 2,500.00
RM
150.00
RM
10.00
RM 2,660.00

AOG/ Collapse/Subsidence/Upheaval/
Landslide/Landslip/Inundation

RM 7,500.00

Min eel/10% of
loss whichever
is higher

Theft .

RM 10,000.00

Min eel/10% of
loss whichever
is higher

Principals Existing Property

RM

eel

Others .

RM

5,000.00

eel

Section 2 : Third Party Liability


TPPD

RM 5,000.00

Min eel/10% of
loss whichever
is higher

VRWS/Underground Services

RM 10,000.00

Min eel/10% of
loss whichever
is higher

2
PETRONAS REFINERY AND PETROCHEMICAL CORPORATION SDN BHD UNIJAYA INDUSTRI SDN BHD
01112013

CONTRACTORS ALL RISKS INSURANCE


Additional Clauses

(1)

CAR 001

Cover for loss or damage due to Strike, Riot and Civil


Commotion (SRCC) (Limit of RM500,000.00)

(2)

CAR 004

Extended Maintenance Cover

(3)

CAR 006

Cover of Extra Charges for Overtime, Night-work, Work


On Public Holidays, Express Freight
(Limit 10% of loss and max. RM 35,000.00 eel & in agg.)

(4)

CAR 012

Property in Off-site Storage


(Limit RM 50,000.00 per location)

(5)

CAR 022

Special Conditions Concerning Safety Measures with Respect to


Precipitation, Flood and Inundation

(6)

CAR 025

Inland Transit (Limit RM 35,000.00 per carrying)

(7)

CAR 029

Special Conditions for laying water supply and sewer pipes

(8)

CAR 033

Special
conditions
concerning
Piling,
Foundation
and
Retaining Wall Works

(9)

CAR 040

Cover for Removal of Debris Endorsement


(Limit 10% of loss / max RM 50,000.00 on eel & in agg.)

(10)

CAR 041

Cover for Professional Fees Endorsement


( Limit 10% of loss / max RM 35,000.00 on eel & in agg.)

(11)

CAR 042

Cover for Plans and Documents Endorsement


(Limit RM 25,000.00 eel)

(12)

CAR 044

Cover for Public Authorities Reinstatement Endorsement


(Limit RM 10% of loss or max RM 50,000.00 eel)

(13)

CAR 047

Cover for Malicious Damage Endorsement

(14)

CAR 048

Cover for Goods/Materials kept in the open Endorsement


(Limit RM 35,000.00)

(15)

CAR 077

Automatic Reinstatement of Sum Insured following Loss Clause


(with additional premium)

(16)

CAR 083

Payment on Account Clause

(17)

CAR 084

Cessation of Works Clause (amended to 30 days)

(18)

CAR 085

Loss Notification Clause (30 days)

(19)

CAR 086

Weather Aggregate Clause (72 hours)

(20)

CAR 108

Special conditions
Endorsement

(21)

CAR 002

Cover for Cross Liability

(22)

CAR 015

Special Conditions concerning Underground Cables, Pipes and


Other Facilities

and

Exclusion

regarding

Dewatering

3
PETRONAS REFINERY AND PETROCHEMICAL CORPORATION SDN BHD UNIJAYA INDUSTRI SDN BHD
01112013

CONTRACTORS ALL RISKS INSURANCE


(23)

CAR 032

Vibration, Removal or Weakening of Support

(24)

CAR 134

Cover for Consultants as Third Parties Endorsement

(25)

CAR 135

Cover for Vehicles Licensed for Road use but used as Tools of Trade as
Site Endorsement

(26)

CAR 136

Cover for Plant Hired/Owned/Leased/Loaned Endorsement

(27)

CAR 132

Cover for third party liability during maintenance/defects liability


period

(28)

CAR 129

Terrorism Exclusion Endorsement

(29)

CAR 130

I.T Clarification Clause

WARRANTED NO CLAIM AS AT 01/11/2013

Remarks

Please advise the date of contract


Validity of Quotation

30 days

Lonpacs Participation

100% of 100% of risk

4
PETRONAS REFINERY AND PETROCHEMICAL CORPORATION SDN BHD UNIJAYA INDUSTRI SDN BHD
01112013

INSURANCE SLIP NO

WORKMENS COMPENSATION INSURANCE


Insured

a) Principal
b) Contractor

: PETRONAS REFINERY AND PETROCHEMICAL


CORPORATION SDN BHD
: UNIJAYA INDUSTRI SDN BHD

Project

RENOVATION AND REFURBISHMENT WORKS FOR ADDITIONAL OFFICE


FLOORS ON LEVEL 52, 54 & 55 AT VISTA TOWER, THE INTERMARK FOR
PETRONAS REFINERY AND PETROCHEMICAL CORPORATION SDN BHD
CONTRACT NO.: PRPC/TC3/001/2013

Period of Insurance

12 WEEKS (DATE TBA) WITH 12 MONTHS DEFECTS LIABILITY PERIOD

Location of Risk

As above

Coverage

To indemnify the Insured against their liability under the Workmens


Compensation Ordinance and at Common Law in respect of death or
bodily injury or illness to the insured employees arising out of and in the
course of employment in the above Project.
In addition, to pay all legal costs and expenses incurred with the Insurers
consent.

Territorial Limit

Malaysia

Subject Matter

On all employees of the Insured, contractor and sub-contractors involved


in the above Project

Total Sum Insured

RM 185,915.70 (Estimated Total Wages at 10% of Total Contract Value)

Premium Rate

0.25 % on Total Sum Insured

Total Premium

Gross Premium
6% Service Tax
Stamp Duty
Total Premium Due

Common Law
Liability Limit

RM 500,000.00

RM 464.79
RM
27.89
RM
10.00
RM 502.68

5
PETRONAS REFINERY AND PETROCHEMICAL CORPORATION SDN BHD UNIJAYA INDUSTRI SDN BHD
01112013

WORKMENS COMPENSATION INSURANCE


Additional Clauses :

Warranty 60 -

Inclusion of Sub-Contractor Employees

Warranty 76 -

Waiver of defence concerning Employees not


defined as Workmen

Warranty 77 -

Inclusion of Common Law liability to Employees


not defined as Workmen
Inclusion of Employees of Sub-contractors who
provide labour only

Warranty 194 Warranty 197 -

Waiver of defence Concerning the Contractor


not being a Workman within the said
Workmens Compensation Laws

Warranty 230 -

Inclusion of Principal Indemnity

Endt A

Inclusion of Indemnity to Officer or Agent of


the Employer in respect of personal injury or
disease sustained by Workmen

Endt B

Inclusion of legal liability of the Insured to


Workmen in the employment of SubContractors

Warranty 232 -

Premium Warranty (60 days)

Jurisdiction
Loss notification (30 days)
Terrorism Exclusion Clause
Remarks

WARRANTED NO CLAIM AS AT 01/11/2013

Lonpacs Participation

100% of 100% of risk

Validity of Quotation

30 days

6
PETRONAS REFINERY AND PETROCHEMICAL CORPORATION SDN BHD UNIJAYA INDUSTRI SDN BHD