Essilor Project
Remaining & Defected Construction Works List Ending 12 Oct 2013
Particular/Activities
Remarks
OS & Y valves with supervisory
switch (interface with Fire Alarm
control panel, Not yet installed for
Flow Metter Gate valves/ tested and
connected to the interface of fire
alarm control panel system.
Indicator/monitor of high/low level
of the fire water tank.
Level indicator at the fuel tank is not
installed. This should have interface
with the FACP.
The IM model for Gen. set is not yet
installed/ terminated/ tested and
connected to the interface of fire
alarm control panel system
(Run/off/Fault).
The smoke for ducting work are
installed not in accordance with
standards. It must be connect &
monitoring by FACP and output signal
shall be sent to AHU control panel
shut down in case of a fire.
The high pressure control for Jockey
& Diesel Fire Pump must be used
copper pipes not G.I as actual on site.
The control panel for jockey pump is
missing the alarm level for
underground fire tank & fuel oil.
Control panel for diesel pump shall
be made by 2 of SC(manual switch on
by hand & connect to 02 set of
battery ) instead of only one as
actual.
To install/provide heat insulation
for Diesel chimney (add more anchor
bolts to chimney flange/Gasket,
SleevesPlease refer to Technical
Catalogues for JU6H-UF(USA BUILD)
Engine series, the exhaust system
shall be positioned in such a way as
to prevent exhaust gases from reentering the pump room).
To extend & insulation the exhaust
chimney higher than the bus way &
cables & tray along the corridor to
avoid the heat of the chimney heating
the bus duct & power cable/ cable
tray.
Sleeves/ penetration thru the walls
need to be sealed by fire stopping
materials.
Steel rod and hanger support
painting & alignment adjustment.
Sprinkler heads/system at the pump
room is not yet installed.
Some zone of fire alarm are fault
Target Date
By
CTC
2
3
4
CTC
Issuance of commissioning
certificate
T&C
As-built document, O&M
Training & handover
Issuance of commissioning
certificate
ESS/CTC
Remarks
ACT
Target Date
CTC
ACT/CTC
By
ESS/CTC
ACT
1.1
Particular/Activities
Remarks
Target Date
By
Chiller system :
CTC
1.2
Chiller room
1.
2.
3.
1.3
4.
5.
CTC
CTC
6.
7.
8.
9.
10.
11.
12.
1.4
1.3
1.4
rectify/cover/sealed(waterproof).
4. Power cable along the corridor of utility
are installed out door type & no cover
protected. This is not acceptable. CTC
needs to urgent action.
5. Hanger/ support/ threaded rod, angel
bar, piping system are need to be
cleaned, Cold zinc rich galvanizing for
CWP,
6. To make & label the direction of the
piping system.
7. To install the tray/pan for collecting the
condensing water from the CHWP
8. Insulation for CHWP is not working
properly & need to rectify some which
were broken/damaged due to T&C.
9. Cladding for all CHWT inside the chiller
room and out door.
10. No sleeves for: CHWP, CWP penetration
thru the wall
11. Paint the steel rod and hanger support
also adjust the alignment.
12. Chiller control panel is delivered without
key. CTC need to provide it soon.
13. Functional testing & T&C form recorded
for Chiller, Pumps, CT, AHUs & FCUs are
not yet done by CTC.
1.5
1.6
As-built document
No progress
1.7
O&M
No progress
1.8
Issuance of
commissioning
certificate
D. Electrical System:
Item
Particular/Activities
Remarks
Need to replace cable tie for power
cables (not properly tied by special
cable tie the back with steel wire for
heavy power cables).
All cable tray/ trunlking without cover
& properly installed. Need to be
installed the cover for all
trunking(indoor & outdoor type)
Labelling & cleaning for distribution
boards/ panels.
Provide more reinforced anti-vibration
support for bus duct system in MSB &
Air compressor.
MSB & Sub main DB do not comply
with spec (Form 4 & 3).
T&C for MSB.
DB panel, the circuits are not label properly,
the circuits name need to be followed plan
layout
All breakers and components of the LV P/B
are not appropriately labelled
Target Date
By
Installation of incoming
undergrounds:
Outdoor landscapes lighting
As-built document
No progress
O&M
No progress
Issuance of commissioning
certificate
Particular/Activities
Remarks
Target Date
By
CCTV:
Installation of all equipments
for CCTV
Installation and termination of
CCTV cameras
As-built document
No progress
O&M
No progress
Issuance of commissioning
certificate
Particular/Activities
Installation of fuel fill point
cabinet, including fill alarm,
valve, gauge (GF)
As-built document, O&M
Training & handover
Remarks
Target Date
By
T&C
J. Others
1