Академический Документы
Профессиональный Документы
Культура Документы
and Development
A propose
design for
sewer network
KBTC
Yivitesh Sookun
National Diploma in Civil Engineering, Cohort
06 Full-Time
Page 2
and
research
development
and
of
studies
projects
for
relating
the
to
wastewater sector.
Promoting the treatment and reuse wastewater.
Ensure the generation of sufficient resources from tariff to
finance the operation, maintenance and depreciation cost of
wastewater
system,
sewerage
and
sewage
treatment
installations.
Previous works and projects
The National Sewerage Master Plan (NSMP) was accomplished in the
year 1993. The principal aim of this National Sewerage Master Plan
was to provide public sewerage coverage mainly in the urban areas
about 50% of the population by 2010 and 80% by the year 2020. The
NSMP goal is to target 100% connection to the sewerage system by
2030.
Since 1994 the Government has started implementing the master plan
(NSMP) and has been financing the following projects:
Louis, lower Beau Bassin and Coromandel also including the industrial
waste of Plaine Lauzan, la Tour Koenig and Pailles.
Facts and figures on public sewer system in Mauritius
The percentage connection to public sewer
In 2010, about 29% number of people were connected to the sewer
system and the remaining 71% uses on site wastewater disposal
system.
Page 5
Gallons used
3 gallons per flush
6 gallons per day
Total = 3x6 = 18 gallons
10 minutes of shower
2 gallons per day
Total = 10x2 = 20 gallons
Hygiene (brushing teeth,
washing face, etc) 2.5
gallons per day
8 glasses of water
1 gallon per day
Page 6
Secondary treatment
Generally, a level of treatment that removes 85% of Biological Oxygen
Demand [BOD] and suspended solids via biological or chemical
treatment processes. Secondary treatment reclaimed water usually has
a BOD of <20 milligrams per liter (mg/L) and suspended solids of <30
mg/L, but this may increase to >100 mg/L due to algal solids in lagoon
systems.
Tertiary treatment
The treatment reclaimed water beyond the secondary biological stage.
This normally implies the removal of a high percentage of suspended
solids and/or nutrients, followed by disinfection. It may include
processes such as coagulation, flocculation and filtration.
Wastewater treatment process
Page 8
Category of reuse
Urban reuse (unrestricted)
Other
Agricultural
Food crops
Environment enhancement
Industrial reuse
Example of application
Landscape irrigation of
parks, playground, school
yards, golf course
Fire protection,
Construction
and
more
rational
allocation
of
freshwater
Page 10
is
increasing
and
it
is
generated
from
domestic,
Mm
Mm
in 2033.
Divide the total area into logical sub areas as needed, and
develop design flow rates for each section in the system
Hydraulic design
Designing a sanitary sewer generally involves estimation of waste flow
rate for the design data and also evaluation of the local condition
which may affect the hydraulic equation of the system. The selection of
hydraulic design equation is wide as various formulas are available for
the design of a sanitary sewer. Due to the simplicity and accuracy of
Manning equation, it is mostly used by designers to design sanitary
sewer.
Manning equation
Page 15
Where,
V=
1
n
2 /3
1/ 2
Page 16
Uniform flow
Page 18
V=
R2 /3
S 1/ 2
Hydraulic radius, R =
Area of liquid =
Area of liquid
Wetted perimeter
(m)
d2
4
Where,
n= Manning coefficient
S = Slope of energy line
When the value of V (mean velocity) is obtained, using the continuity
equation to find the discharge in pipe.
Continuity
Equation=
Where,
Q = V.A
Q = Discharge,
Volume flow rate in pipe
V = Mean velocity
A = Cross sectional area of flow
Page 19
(Section of a pipe)
Where,
Gradient
Fall
Distance
1. Fall in a pipe may be defined as the vertical amount by which the
pipe drops over a distance
2. The distance can be between sections of pipe or between to
manholes.
Page 20
Gradient =
Where,
Ground elevation at MH 1Ground elevationat MH 2
MH 1: Manhole 1
Distance between MH 1MH 2
MH 2: Manhole 2
The above formula can be rearranged to find fall if the gradient is
already available
Fall = Gradient x
Distance
Page 21
Page 22
Page 23
Back-sight
1.824
1.640
H.I
R.L
101.824
100.000
1.580
101.884
100.244
A to B
14.018
1.535
1.670
101.749
100.214
B to C
50.200
1.793
1.610
101.932
100.139
C to D
59.400
1.649
1.650
101.931
100.282
D to E
17.750
100.237
E to F
12.600
Fore-sight
1.694
Distance
(m)
Page 24
Where,
H.I: Height of Instrument
R.L: Reduced Level
Page 25
Page 26
Page 27
These
typse
of
pipes
are
manufactured using mixed of asbestos
fibers, silica and cement.
Sizes available 10-100 cm internal
diameter and length up to 4m.
It can be easily assemble with the
help of couplings
known as ring tie coupling.
Glass fiber
reinforced plastic
pipes
Page 30
Base ring
Sizes available
900mm x 600mm
1050mm x 300mm
Page 31
A propose
Diam
Wall Lengt
eter( Thick h(m)
sewer
network
design for KBTC
mm)
ness
(mm)
x 600mm
110
3.2 1050mm
6
150
4.1 1200mm
6
x 150mm
200
4.2 1200mm
6
x 300mm
250
6.2
6
1200mm x 600mm
315
7.7
6
1200mm
1500mm
1800mm
2400mm
x
x
x
x
900mm
600mm
600mm
600mm
x
x
x
x
110mm
150mm
250mm
150mm
Page 32
110mm to 400mm
450mm x 750mm x
150mm
375mm x 900mm x
350mm
UPVC Gully Trap
Sizes available
Outlet 110mm
Outlet 150mm
Design stage
100.244100.000
14.018
= 57.5
Page 33
R= Hydraulic radius =
0.15
=0.0375
4
S= Slope = (1/60)
n= Manning roughness coefficient= 0.013
Replacing all value appropriately, the value obtain for velocity is 1.1
m/s.
For the discharge in the pipe, I will apply the continuity equation.
Discharge, Q=AV
D2
A=
4
A= 0.0176
m2
V= 1.1m/s
Q= 0.0176 x 1.1 = 0.01936
m3 /s
From conversion
1cubic metre = 1000 litres
Q= 0.01936 x 1000 = 19.4 L/s
From stand pipe to point B
I will use the manning equation to determine the velocity.
Page 34
R = Hydraulic radius=
4
D
=
D
4
2
0.2
=0.05
4
1
60
S = Slope =
A=
4
A= 0.0314
V= 1.3m/s
Q= 0.0314 x 1.3 = 0.04082
m3 /s
From conversion
1cubic metre = 1000 litres
Q= 0.04082 x 1000 = 40.8 L/s
Consider point B to C
The data obtained after I carried out survey are as follows:
Ground level at point A= 100.244m and at point C= 100.214m
The distance between A and B is 50.200m
1. Determine the actual ground slope between A and B
Ground slope =
100.244100.214
50.200
= 1633.3
Page 35
From
Manning
Equation,
1 3 2
= n.R .S
.Equation (1)
D2
4
D
=
D
4
2
R = Hydraulic radius=
S = Slope =
0.2
=0.05
4
1
80 = 0.0125
m 2 (0.031 m2 )
m3 /s
From conversion
1cubic metre = 1000 litres
Q= 0.0372 x 1000 = 37.2 L/s
Hence, the pipe B to C has a capacity of 37.2 L/s.
Point
B to C
Pipe diameter
(mm)
200
Velocity (m/s)
Page1.2
36
Capacity (L/s)
37.2
Consider points C to D
I will apply the same method to determine the velocity and capacity of
sewer pipe UPVC 200mm.
Ground slope =
100139100.214
1
=
59.400
792
The actual slope of ground is not enough steep to be use for the
design. I will choose a slope of (1/80) to proceed with the design.
From manning equation, I will determine the value of V m/s (velocity).
2
D
0.2
4
D
=0.05
=
R = Hydraulic radius=
4
D
4 =
2
S = Slope =
1
80 = 0.0125
Page 37
m /s
From conversion
1cubic metre = 1000 litres
Q= 0.0372 x 1000 = 37.2 L/s
Hence, the pipe B to C has a capacity of 37.2 L/s.
Consider points C to D
I
Pipe diameter
Velocity (m/s)
Capacity (L/s)
(mm)
B to C
200
1.2
37.2
will apply the same method to determine the velocity and capacity of sewer
Point
100139100.214
1
=
59.400
792
The actual slope of ground is not enough steep to be use for the
design. I will choose a slope of (1/80) to proceed with the design.
From manning equation, I will determine the value of V m/s (velocity).
2
D
0.2
4
D
=0.05
=
R = Hydraulic radius=
=
4
D
4
2
S = Slope =
1
80 = 0.0125
m3 /s
From conversion
Page 38
Pipe diameter
(mm)
200
Velocity (m/s)
Capacity (L/s)
1.2
37.2
Consider point D to E
Ground slope =
100.282100.237
1
=
12.600
280
The actual slope of ground is not enough steep to be use for the
design. I will choose a slope of (1/100) to proceed with the design.
From manning equation, I will determine the value of V m/s (velocity).
D2
0.2
4
D
=0.05
=
R = Hydraulic radius=
=
4
D
4
2
S = Slope =
1
100 = 0.01
m3 /s
From conversion
1cubic metre = 1000 litres
Q= 0.031 x 1000 = 31 L/s
Hence, the pipe B to C has a capacity of 31 L/s.
Point
D to E
Pipe diameter
(mm)
200
Velocity (m/s)
Capacity (L/s)
1.0
31
Page 39
Point E to F
Ground slope =
100.282100.237
12.600
= 280
The actual ground slope is (1/280), but for the design I will choose a
slope of (1/100).
Assume a sewer pipe of 150mm diameter connect to the gully trap
over a distance of 6m until the stand pipe.
From manning equation, I will determine the velocity in the sewer pipe
2
1
1 3 2
Apply manning formula: V = n . R . S
D2
4
D
=
D
4
2
R= Hydraulic radius =
0.15
=0.0375
4
S= Slope = (1/100)
n= Manning roughness coefficient= 0.013
Replacing all value appropriately, the value obtain for velocity is
0.86m/s.
For the discharge in the pipe, I will apply the continuity equation.
Discharge, Q=AV
D2
A= 4
A= 0.0176
m2
V= 0.86m/s
Q= 0.0176 x 0.86 = 0.01513
/s
Page 40
0.2
4
D
=0.05
=
R = Hydraulic radius=
=
4
D
4
2
S = Slope =
1
100
A=
4
A= 0.0314
m2
V= 1.04m/s
m
/s
From conversion
1cubic metre = 1000 litres
Q= 0.03265 x 1000 = 32.7 L/s
Velocity (m/s)
Capacity (L/s)
A to B
Pipe diameter
(mm)
150
1.1
19.4
A to B
200
1.3
40.8
Page 41
200
1.2
37.2
C to D
200
1.2
37.2
D to E
200
1.0
31.0
E to F
200
1.04
32.7
E to F
150
0.85
15.1
vertical
Horizontal
Vertical
7
Vertical= 0.1167m
The fall from gully trap to head of stand pipe is 0.1167m
Invert level of head stand pipe= 99.400-0.167= 99.283m
Distance from point B to foot of stand pipe is 7.018m and gradient is
(1/60)
Slope =
vertical
Horizontal
Page 42
Vertical
7.018 = 0.1170m
Vertical= 0.1170m
The fall from point B to foot of stand pipe is 0.1170m
Invert level at foot of stand pipe= 98.044-0.1170= 97.927m
Consider point B to C
Ground level= 100.244m, Gradient= (1/80), Pipe diameter= 200mm
Assume a cover of 2m
Invert level at point B= Ground level Cover Pipe diameter
Invert level at point B= 100.244 2 0.2 = 98.044m
Distance from point B to C is 50.200m and gradient is (1/80)
Slope =
1
80 =
vertical
Horizontal
Vertical
50.200 =
Vertical= 0.6275m
The fall at point C is 0.6275m
Invert level at point C= 98.044 0.6275 = 97.417m
Page 43
Consider point C to D
Invert level at point C= 97.417m, Distance from C to D= 59.400m,
Gradient= (1/80)
Slope =
1
80 =
vertical
Horizontal
Vertical
59.400 =
Vertical= 0.7425m
The fall at point D is 0.6275m
Invert level at point D= 97.417 0.6275 = 96.674m
Consider point D to E
Invert level at point D= 96.674m, Distance from D to E= 17.750m,
Gradient= (1/100)
Slope =
1
100 =
vertical
Horizontal
Vertical
17.750 =
Vertical= 0.1775m
The fall at point D is 0.1775m
Invert level at point E= 96.674 0.1775 = 96.496m
Page 44
Consider point E to F
At point F Gully trap= 600mm and Ground level= 100.237m
Invert level= 100.237-0.6= 99.637m
Distance between gully trap to head of stand pipe= 6m and gradient=
(1/100)
Slope =
1
100 =
vertical
Horizontal
Vertical
6
Vertical= 0.06m
The fall from gully trap to head of stand pipe is 0.06m
Invert level of head stand pipe= 99.637-0.06= 99.577m
Distance from point B to foot of stand pipe is 6.600m and gradient is
(1/100)
Slope =
1
100 =
vertical
Horizontal
Vertical
6.600 =
Vertical= 0.066m
The fall from point B to foot of stand pipe is 0.066m
Invert level at foot of stand pipe= 96.403 0.066 = 96.403m
Page 45
The table below shows the invert level and chainage of the
following points:
Point
Chainage (m)
99.400
0.000
98.004
14.018
97.417
64.218
96.674
123.618
96.496
141.368
99.637
153.968
Page 46
Discussion
Page 47
Page 48