JAIHIND PROJECTS LIMITED.

PROCEDURE FOR FORM WORK


PROJECT: NTPC JHANORE GAS PIPELINE PROJECT

PROCEDURE
FOR
FORM WORK
PROJECT

:PAGUTHAN-NTPCJHANORE PIPELINE
PROJECT.

DOCUMENT NO

: JPL/GSPL/PNJPL/WP/C02

CLIENT

: GUJARAT STATE PETRONET LTD.

CONSULTANT

:DORSCH CONSULT (INDIA)PVT.LTD.

TPIA

: BAXCOUNSCEL INSPECTION
BUREAU PVT. LTD.

CONTRACTOR

: JAIHIND PROJECTS LIMITED.

JPL
PREPARED BY

BIBPL

DCIL

GSPL

REVIEWED BY

CHECKED &
APPROVED BY

APPROVED

NAME
DESIGNATION
SIGNATURE
DATE

FROM WORK

DOCUMENT No.
JPL/GSPL/PNJPL/WP/C02

REV.
0

Page No. 1 of 7

BY

JAIHIND PROJECTS LIMITED.


PROCEDURE FOR FORM WORK
PROJECT: NTPC JHANORE GAS PIPELINE PROJECT

INDEX
SR.NO.

DESCRIPTION

PAGE NO

Purpose

03

Reference

03

Scope

03

Material

3-4

Method

Tolerance

Documentation

For JPL
Name:
Sign:
Date:

For BIBPL

For DCIL / GSPL


Name:
Sign:
Date:

Name:
Sign:
Date:
FROM WORK

DOCUMENT No.
JPL/GSPL/PNJPL/WP/C02

REV.
0

Page No. 2 of 7

JAIHIND PROJECTS LIMITED.


PROCEDURE FOR FORM WORK
PROJECT: NTPC JHANORE GAS PIPELINE PROJECT

1.

PURPOSE
The purpose of this procedure is to prepared guidelines / method of
completing formwork as per specification and good workmanship.

2.

REFERENCE
GSPL Specification. 1019 162 204

3.

SCOPE
This procedure covers fixing and removing of formwork with necessary
supports system including checking and removal and checking of
formwork.
MATERIAL
Only GSPL approved steel shuttering plate, Ply board, clamps, jacks
Acrow spans, Scaffolding pipes, nails, bellies, planks, battens, shuttering
oil of approved quality.
METHOD
Before erection of formwork, all the plates will be cleaned to remove any
concrete/nails or any other foreign material.

4.

5.
5.1
5.2

Approved shuttering oil shall be applied as release agent before


reinforcement steel is placed.

5.3

Depending upon types of formwork required (i.e. Rough / wrought / Lined


at particular location) accordingly formwork will be made to the exact
dimensions with the allowable tolerances to meet the requirements of
design and surface finish.

5.4

When chamfers are to be formed, the fillets shall be cut accurately to


correct size so as to provide smooth and continuous chamfer.

5.5

For heavy concrete sections like beam / slab etc. proper size timber / steel
at required spacing shall be provided to take the design loads / pressure.

5.6

All the spacing members shall have proper bearing at supports.

5.7

Proper staging will be provided in order to place formwork at locations and


to facilitate de shuttering.

5.8

After placing of formwork, line, level, plumb and dimensions will be


checked and kept within the permissible limits.

FROM WORK

DOCUMENT No.
JPL/GSPL/PNJPL/WP/C02

REV.
0

Page No. 3 of 7

JAIHIND PROJECTS LIMITED.


PROCEDURE FOR FORM WORK
PROJECT: NTPC JHANORE GAS PIPELINE PROJECT

5.9

The Joints in the form work shall be sufficiently tight to prevent any
leakage of slurry or mortar.

5.10

Polythene sheet / Bitumen paper of approved makes shall be used for


prevention of leakage through joints.

5.11

In case of formwork for columns, one side shall be left open and built up in
sections progressively as placing of concrete is continued.

5.12

In structures having floors, proper prop supports are given.

5.13

Casting of concrete will start after the inspection.

5.14

The necessary safe access to inspect the formworks has to be provided.

5.15

Formwork components shall be removed is such a manner that no


vibrating damage shall be done to the structure.

5.16

After removal of formwork, material will be cleaned immediately and


stocked properly for reuse.

6.0

TOLERANCE
The tolerances on the shapes, lines and dimensions shown in the drawing
shall be within the limits given below.

6.1

Deviations from specified dimensions


of cross section of column and beams

6 mm

Deviations from dimensions of footings


1) Dimensions in plan

+ 12 mm
-12mm to +50mm

6.2

2) Eccentricity

3) Thickness
7.0

0.02 times the width


of the footing in the
directions
of
deviations but not
more than 50mm.
+
0.05
times
specified thickness

DOCUMENTATION

FROM WORK

DOCUMENT No.
JPL/GSPL/PNJPL/WP/C02

REV.
0

Page No. 4 of 7

JAIHIND PROJECTS LIMITED.


PROCEDURE FOR FORM WORK
PROJECT: NTPC JHANORE GAS PIPELINE PROJECT

8.0

Inspection Test Plan:

JPL/GSPL/PNJPL/WP/ITP/C02

Inspection Report

JPL/GSPL/PNJPL/WP/IR/C02

Health Safety:
1. PPE is a must in this activity
2. While walking on the reinforcement bars slippage may occur.
3. Safety

Note:
In case of any conflict between the requirements of this procedure and
that of the above referred specifications the requirements of the latter shall
govern, until and unless specific intention in meant.

For JPL
Name:
Sign:
Date:

For BIBPL

For DCIL / GSPL


Name:
Sign:
Date:

Name:
Sign:
Date:

FROM WORK

DOCUMENT No.
JPL/GSPL/PNJPL/WP/C02

REV.
0

Page No. 5 of 7

JAIHIND PROJECTS LIMITED.


PROCEDURE FOR FORM WORK
PROJECT: NTPC JHANORE GAS PIPELINE PROJECT

INSPECTION TEST PLAN


Owner

: GUJARAT STATE PETRONET LTD.

Format: JPL/GSPL/PNJPL/WP/IR/C02

Consultant

: DORSCH CONSULT ( INDIA) PVT. LTD.

Revision : 0.0

TPIA

: BAXCOUNSCEL INSPECTION BUREAU PVT. LTD.

Contractor

: JAIHIND PROJECT LIMITED.

Project

Date:

: PAGUTHAN NTPC JHANORE PIPELINE PROJECT.


JPL/GSPL/PNJPL/WP/ITP/C02

Sr.
No

Frequency of
inspection
/Testing

Activity Description

Inspection Category

Remarks

BAX(TPIA)

DCIL/
GSPL

RI

RI

RI

JPL

Check layout lines and levels

Check preparation of formwork with


proper support and staging

For Every
Layout
Each
Formwork

Checking of formwork as tolerance

Each Structure

W/RI

Each formwork

RI

Each formwork

RM

RM

Each formwork

RM

RM

Each formwork

RM

4
5
6
7

Check embedment, inserts, anchor


bolts and pipe/POCKET
Check for electrical conduits, pipes
etc.
Check for Joints / openings to avoid
any leakage
Check for removal of form work and
staging

Post pour inspection / Tolerances

Each Structure

RM

Safety

Each Formwork

For JPL
Name:
Sign:
Date:

For BIBPL

RM
W/RM
W

For DCIL / GSPL


Name:
Sign:
Date:

Name:
Sign:
Date:
Legend: P Perform
RI Random Inspection
W Witness
INSPECTION REPORT FORM WORK
FROM WORK

DOCUMENT No.
JPL/GSPL/PNJPL/WP/C02

REV.
0

Page No. 6 of 7

JAIHIND PROJECTS LIMITED.


PROCEDURE FOR FORM WORK
PROJECT: NTPC JHANORE GAS PIPELINE PROJECT

Owner

: GUJARAT STATE PETRONET LTD.

Format: JPL/GSPL/PNJPL/WP/IR/C02

Consultant

: DORSCH CONSULT ( INDIA) PVT. LTD.

Revision : 0.0

TPIA

: BAXCOUNSCEL INSPECTION BUREAU PVT. LTD.

Contractor

: JAIHIND PROJECT LIMITED.

Project

Date:

: PAGUTHAN NTPC JHANORE PIPELINE PROJECT.

Inspection date:

Location:

Structure:
OBSERVATION

SR. NO

DESCRIPTION

REMARKS
Yes/ok

Check layout lines and levels

Check preparation of formwork with


proper support and staging

Checking of formwork as tolerance

Check embedment, inserts, anchor bolts


and pipe

Check for electrical conduits, pipes etc.

6
7

No

N/A

Check for Joints / openings to avoid any


leakage
Check for removal of form work and
staging

Post pour inspection / Tolerances

Safety

For JPL

For BIBPL

For DCIL / GSPL

Name:

Name:

Name:

Sign:

Sign:

Sign:

Date:

Date:

Date:

FROM WORK

DOCUMENT No.
JPL/GSPL/PNJPL/WP/C02

REV.
0

Page No. 7 of 7