PROCEDURE
FOR
FORM WORK
PROJECT
:PAGUTHAN-NTPCJHANORE PIPELINE
PROJECT.
DOCUMENT NO
: JPL/GSPL/PNJPL/WP/C02
CLIENT
CONSULTANT
TPIA
: BAXCOUNSCEL INSPECTION
BUREAU PVT. LTD.
CONTRACTOR
JPL
PREPARED BY
BIBPL
DCIL
GSPL
REVIEWED BY
CHECKED &
APPROVED BY
APPROVED
NAME
DESIGNATION
SIGNATURE
DATE
FROM WORK
DOCUMENT No.
JPL/GSPL/PNJPL/WP/C02
REV.
0
Page No. 1 of 7
BY
INDEX
SR.NO.
DESCRIPTION
PAGE NO
Purpose
03
Reference
03
Scope
03
Material
3-4
Method
Tolerance
Documentation
For JPL
Name:
Sign:
Date:
For BIBPL
Name:
Sign:
Date:
FROM WORK
DOCUMENT No.
JPL/GSPL/PNJPL/WP/C02
REV.
0
Page No. 2 of 7
1.
PURPOSE
The purpose of this procedure is to prepared guidelines / method of
completing formwork as per specification and good workmanship.
2.
REFERENCE
GSPL Specification. 1019 162 204
3.
SCOPE
This procedure covers fixing and removing of formwork with necessary
supports system including checking and removal and checking of
formwork.
MATERIAL
Only GSPL approved steel shuttering plate, Ply board, clamps, jacks
Acrow spans, Scaffolding pipes, nails, bellies, planks, battens, shuttering
oil of approved quality.
METHOD
Before erection of formwork, all the plates will be cleaned to remove any
concrete/nails or any other foreign material.
4.
5.
5.1
5.2
5.3
5.4
5.5
For heavy concrete sections like beam / slab etc. proper size timber / steel
at required spacing shall be provided to take the design loads / pressure.
5.6
5.7
5.8
FROM WORK
DOCUMENT No.
JPL/GSPL/PNJPL/WP/C02
REV.
0
Page No. 3 of 7
5.9
The Joints in the form work shall be sufficiently tight to prevent any
leakage of slurry or mortar.
5.10
5.11
In case of formwork for columns, one side shall be left open and built up in
sections progressively as placing of concrete is continued.
5.12
5.13
5.14
5.15
5.16
6.0
TOLERANCE
The tolerances on the shapes, lines and dimensions shown in the drawing
shall be within the limits given below.
6.1
6 mm
+ 12 mm
-12mm to +50mm
6.2
2) Eccentricity
3) Thickness
7.0
DOCUMENTATION
FROM WORK
DOCUMENT No.
JPL/GSPL/PNJPL/WP/C02
REV.
0
Page No. 4 of 7
8.0
JPL/GSPL/PNJPL/WP/ITP/C02
Inspection Report
JPL/GSPL/PNJPL/WP/IR/C02
Health Safety:
1. PPE is a must in this activity
2. While walking on the reinforcement bars slippage may occur.
3. Safety
Note:
In case of any conflict between the requirements of this procedure and
that of the above referred specifications the requirements of the latter shall
govern, until and unless specific intention in meant.
For JPL
Name:
Sign:
Date:
For BIBPL
Name:
Sign:
Date:
FROM WORK
DOCUMENT No.
JPL/GSPL/PNJPL/WP/C02
REV.
0
Page No. 5 of 7
Format: JPL/GSPL/PNJPL/WP/IR/C02
Consultant
Revision : 0.0
TPIA
Contractor
Project
Date:
Sr.
No
Frequency of
inspection
/Testing
Activity Description
Inspection Category
Remarks
BAX(TPIA)
DCIL/
GSPL
RI
RI
RI
JPL
For Every
Layout
Each
Formwork
Each Structure
W/RI
Each formwork
RI
Each formwork
RM
RM
Each formwork
RM
RM
Each formwork
RM
4
5
6
7
Each Structure
RM
Safety
Each Formwork
For JPL
Name:
Sign:
Date:
For BIBPL
RM
W/RM
W
Name:
Sign:
Date:
Legend: P Perform
RI Random Inspection
W Witness
INSPECTION REPORT FORM WORK
FROM WORK
DOCUMENT No.
JPL/GSPL/PNJPL/WP/C02
REV.
0
Page No. 6 of 7
Owner
Format: JPL/GSPL/PNJPL/WP/IR/C02
Consultant
Revision : 0.0
TPIA
Contractor
Project
Date:
Inspection date:
Location:
Structure:
OBSERVATION
SR. NO
DESCRIPTION
REMARKS
Yes/ok
6
7
No
N/A
Safety
For JPL
For BIBPL
Name:
Name:
Name:
Sign:
Sign:
Sign:
Date:
Date:
Date:
FROM WORK
DOCUMENT No.
JPL/GSPL/PNJPL/WP/C02
REV.
0
Page No. 7 of 7