Академический Документы
Профессиональный Документы
Культура Документы
Submitted To:
Assistant Prof. Sugato Mukherjee
Submitted By:
Shivani Jaiswal
B.B.A.LL.B (Hons.) VII Semester
MATS University
1
ACKNOWLEDGEMENT
I express my sincere gratitude to Asst. Prof. Sugato Mukherjee, MATS Law School,
Raipur, and owe my foremost regards to him for giving me an opportunity to carry out this
project work under his guidance. This work would not have been possible without his invaluable
support and thought provoking comments.
I would also like to thank my batch mates who directly or indirectly helped me in making
this project.
DISCLAIMER
This project report is authored by student of 4th year under the five year BBA.LL.B (H) Program
in MATS Law School, Raipur. The report is purely academic in nature and shall not be treated as
a legal or business advice. The views expressed in this report are personal to the student and do
not reflect the view of law school or any of its staff or personnel. All the copyrights relating to
this work are vested in the author; the same shall not be exploited without their express
permission.
Shivani Jaiswal
4th Year, MATS Law school, Raipur
RESEARCH METHODOLOGY
I have adopted the mode of primary research source where I have refereed some books of
Industrial law to take information about this project report. So I have taken materials, references
and guide from books
I have also adopted the Doctrinal Research Methodology where the sources of the project are
solely based upon the materials collected from the websites and books. Certain other resources
for our project are several Articles collected from various journals and magazines as well as
several other commentaries and digests written and published by several eminent scholars who
have excelled in various fields of the managerial fraternity nationally and internationally.
OBJECTIVES OF RESEARCH:
The objectives of research are
To understand the concept of industrial adjudication in India under the Industrial Dispute
Act,1947
To understand the concept of industrial adjudication in USA
Further the researcher highlight the comparative analysis of industrial adjudication
between USA and India
TABLE OF CONTENT
INTRODUCTION........................................................................................................... 6
THREE METHOD FOR SETTLEMENT OF DISPUTE.........................................................7
ADJUDICATION PROCESS IN INDIA.............................................................................. 9
A COMPARISON OF INDIA AND THE UNITED STATES.................................................18
CONCLUSION AND SUGGESTION..............................................................................21
REFRENCES.............................................................................................................. 22
INTRODUCTION
The Industrial Disputes Act, 1947, reflects this very concern of the State and thus justifying a
strong need for the intervention of the State in modern industrial disputes. State intervention in
industrial relations is essentially a modern development. With the emergence of the concept of
welfare state, new ideas of social philosophy, national economy and social justice sprang up with
result that industrial relation no longer remains the concern of labour and management alone.
The concern of state in matters relating to labour is a product of its obligations to protect the
interest of industrial community, while at the same time fostering economic growth in almost all
countries. The state has assumed powers to regulate labour relations in some degree or the other.
In some, it has taken the form of laying down bare rules or observance by employers and
workers; in others, the rules cover a wider area of the rules. So far as our country is concerned,
State intervention in labour matters can be traced back to the enactment of the Employers and
Workmens Disputes Act 1860 which provided for the speedy disposal of the dispute relating to
the wages of workmen engaged in railways, canals and other public works by Magistrates. In
1947, the Government of India passed the Industrial Disputes Act under which machinery for the
preventions and settlement of the disputes was outlined. The Act as amended in 1956 has set up
machinery for settlement of disputes. The act provides the three methods for settlement of
industrial disputes are as follows Conciliation, Arbitration and Adjudication.
Conciliation
In simple sense, conciliation means reconciliation of differences between persons. Conciliation
refers to the process by which representatives of workers and employers are brought together
before a third party with a view to resolve the dispute persuading them to arrive at an agreement
by mutual discussion between them. The alternative name which is used for conciliation is
mediation. The third party may be one individual or a group of people.
In view of its objective to settle disputes as quickly as possible, conciliation is characterized
by the following features:
i.
ii.
The conciliator or mediator tries to remove the difference between the parties.
He/she persuades the parties to think over the matter with a problem-solving
iii.
iv.
own viewpoint.
The conciliator may change his approach from case to case as he/she finds fit
depending on other factors.
Arbitration:
Arbitration is a process in which the conflicting parties agree to refer their dispute to a neutral
third party known as Arbitrator. Arbitration differs from conciliation in the sense that in
arbitration the arbitrator gives his judgment on a dispute while in conciliation, the conciliator
disputing parties to reach at a decision.
The arbitrator does not enjoy any judicial powers. The arbitrator listens to the view points of the
conflicting parties and then gives his decision which is binding on all the parties. The judgment
on the dispute is sent to the government. The government publishes the judgment within 30 days
of its submission and the same becomes enforceable after 30 days of its publication. In India,
there are two types of arbitration: Voluntary and Compulsory.
Adjudication:
7
The ultimate legal remedy for the settlement of an unresolved dispute is its reference to adjudication by the government. The government can refer the dispute to adjudication with or without the
consent of the disputing parties. When the dispute is referred to adjudication with the consent of
the disputing parties, it is called voluntary adjudication. When the government herself refers the
dispute to adjudication without consulting the concerned parties, it is known as compulsory
adjudication.
The difference between arbitration and adjudication is that in the case of arbitration the
parties to the dispute agree to refer the dispute for the decision of the arbitrator. In the case of
adjudication, the dispute is referred for adjudication by the Government. In the case of arbitration
the parties to the dispute can choose the arbitrators. In the case of adjudication the Presiding
Officer of the Labour Court/Industrial Tribunal are appointed by the Government.
The preamble to the Industrial Disputes Act, 1947 mentions that this Act makes provision for the
investigation and settlement of Industrial Disputes and certain other purposes. The preamble of
the act provides for the settlement of industrial disputes through a three tier system of Labour
Courts, Industrial Tribunals and National Tribunals 1, which comes under this adjudication
process. The Labour Court/Industrial Tribunal gets the jurisdiction to decide an industrial only if
the Government makes a reference of that dispute to it. The proceedings before the Labour
Court/Industrial Tribunal are called adjudication proceedings.
LABOUR COURT:
Labour Court2 is one of the adjudication authorities set up by the appropriate Government
by notifying in the official Gazette, may constitute Labour Court for adjudication of the
industrial disputes. The labour court consists of one independent person who is the presiding
officer or has been a judge of a High Court, or has been a district judge or additional district
judge for not less than 3 years, or has been a presiding officer of a labour court for not less than 5
years. The labour court deals with the matters specified in the second schedule of the Industrial
Disputes Act, 1947, which includes the matter as follows:
1. The property or legality of an employer to pass an order under the standing orders.
2. The application and interpretation of standing orders.
3. Discharge or dismissal of workers including reinstatement or grant of relief to workmen
wrongfully dismissed.
4. Withdrawal of any statutory concession or privilege.
5. Illegality or otherwise of a strike or lockout.
1 A critical analysis on efficacy of mechanism to industrial disputes resolution in India by M.J.Arputharaj* and R.
Gayatri.
The Central Government may also appoint two assessors to advise the National Tribunal. The
Presiding Officers of Labour Courts, Tribunals or National Tribunals should be independent
persons, below the age of 65 years and with no interest in the industry whose dispute be heard.
12
13
Names and addresses of the parties to the contract, including addresses where documents
may be served.
The Act sets out eight features of a compliant adjudication scheme;
If a construction contract does not contain a compliant procedure, then the terms of the statutory
Scheme for Construction Contracts (a piece of subordinate legislation) cut in by way of statutory
implication.
The eight compliance points are as follows:
1. The contract must enable a party to give notice at any time of his intention to refer a
dispute to adjudication;
2. The contract must provide a timetable with the object of securing the appointment of the
adjudicator and referral of the dispute to him within 7 days of such notice;
3. The contract must require the adjudicator to reach a decision within 28 days of referral or
such longer period as is agreed by the parties after the dispute has been referred;
4. The contract must allow the adjudicator to extend the period of 28 days by up to 14 days,
with the consent of the party by whom the dispute was referred;
5. The contract must impose a duty on the adjudicator to act impartially ;
6. The contract must enable the adjudicator to take the initiative in ascertaining the facts and
the law;
7. The contract shall provide that the decision of the adjudicator is binding until the dispute
is finally determined by legal proceedings, by arbitration (if the contract provides for
arbitration or the parties otherwise agree to arbitration) or by agreement;
8. The contract shall also provide that the adjudicator is not liable for anything done or
omitted in the discharge or purported discharge of his functions as adjudicator unless the
act or omission is in bad faith, and that any employee or agent of the adjudicator is
similarly protected from liability.
adjudicator in their contract. In many cases, the parties will agree on their adjudicator when a
dispute arises on a better the devil you know principle. In large cases, they will often choose a
construction specialist solicitor, but in smaller valuation cases, a quantity surveyor or other
construction professional is much more usual.
Following service of the Notice of Adjudication, the next step is to appoint an
adjudicator. The appointment of an adjudicator must be secured within seven days from service
of the Notice of Adjudication. The parties can agree on an individual to act as the adjudicator or,
if agreement cannot be reached, the party who referred the dispute to adjudication may make an
application to an Adjudicator Nominating Body (ANB). This is usually done by completing a
form and paying the required fee. On receipt of a request to nominate an adjudicator, the ANB
should communicate their selection to the party who referred the dispute to adjudication within
five days of the request. In the event that an ANB fails to do this the whole process must begin
again.
THE REFERRAL NOTICE
The referral notice must be served within seven days of service of the Notice of Adjudication.
This is the document that sets out in detail the case of the party who is referring the dispute to
adjudication and it should be accompanied by documentation in support of the claim together
with expert reports (if any) and witness statements. It is important to ensure that the referring
party is in a position to serve this notice - there have been instances where the ANB has
appointed an adjudicator 24 hours before the seven-day period expires, in which case the
adjudicator will need the notice within a day. A copy should be sent to the other party at the same
time.
TIMETABLE INVOLVED
The Construction Act sets out a tight timetable of within 28 days of service of the referral notice
for submission of a response and for the adjudicator's ultimate decision. However this may be
extended with the consent of the adjudicator. The rationale behind the process was to obtain
quick and cost effective results which are of a binding nature unless reviewed by litigation or
arbitration. This relies on timescales being tight.
15
16
The parties will be jointly and severally liable to pay the adjudicator a reasonable amount in
respect of fees for work reasonably undertaken and expenses reasonably incurred by him. This
means that both parties can be pursued for these fees, or that either party may be pursued for the
whole amount. The adjudicator may decide himself what sum is reasonable but, if there is any
dispute, an application can be made to the court for determination. This provision applies only to
adjudications which contain the required adjudication provisions set out in the Construction Act,
not to adjudications which rely on the provisions of the Scheme for Construction Contracts.
The Local Democracy, Economic Development and Construction Act provides that:
the parties may agree, in the construction contract, to confer power on the adjudicator to
allocate his fees and expenses between them - this agreement must be in writing;
if the parties agree, in the construction contract, to allocate liability for their own costs of
the adjudication that provision will be ineffective;
the parties are free to agree liability for their own costs of the adjudication after the notice
of intention to refer has been given - if they do so, this agreement must be in writing.
The Act does not address what will happen if a contract provision allocates liability for both the
parties' costs and the adjudicator's fees and expenses. It is arguable that in such a situation the
whole clause will be ineffective.
INTEREST
The adjudicator can only deal with interest on sums awarded if the contract contains a provision
dealing with interest, or alternatively if the parties agree.
17
Although labor laws in both the United States and India are derived primarily from British labor
legislation,6 there have been significant differences in the way the laws of the two countries have
evolved over time. American legislation has been largely influenced by the free enterprise
management philosophy, resulting in the fact that collective bargaining is not a compulsory but
an optional process. In the Indian situation, labor legislation was designed to prevent employeremployee conflicts from hindering rapid economic development."7In addition, the Indian
legislation is based on the assumption that labor unions are weak and will remain weak.
Consequently, the legislation and collective bargaining framework that have evolved are
designed to protect labor.
From my point of view the comparison as follows:
1. In India, parties have to choose the three tier system one by one if the parties is not
satisfied with the decision of negotiation, the parties may agree to voluntary arbitration
and the commission will help the parties in choosing an arbitrator mutually concept able
to them. Further, when the parties to the dispute do not agree to arbitration, then party
refer the case for adjudication under section 7 of the Industrial Dispute Act, 1947. But in
the country of USA does not follow the three tier system, the party can refer their case
directly for adjudication under section 180 of HCGRA, which is similar to the concept of
arbitration because in USA party can choose their adjudicator itself.
2. In terms of definition, The Labour Court/Industrial Tribunal gets the jurisdiction to
decide an industrial only if the Government makes a reference of that dispute to it. The
proceedings before the Labour Court/Industrial Tribunal are called adjudication
proceedings. But the HGCRA does not define the term adjudication, but it is generally
understood to be a process in which third party will make a potentially binding decision
on the issue of dispute. That sounds similar to arbitration.
6 Id.; See Also D. Twomey, Labor Law & Legislation 4-6 (6th Ed. 1980).
7 E. Ramaswamy & U. Ramaswamy, Industry and Labor: An Introduction 195 (1981).
18
3.
When the parties to the dispute do not agree to arbitration, either party shall notify the
Industrial Relations Commission (IRC) with a copy to the appropriate Government of the
failure of negotiation where upon the IRC should adjudicate upon the disputes. 8 While in
USA, there is no need to notify to any commission with a copy of the failure of previous
decision. Here, the party directly choose the mechanism of adjudication by giving a
6. In USA, the contract must require the adjudicator to reach a decision within 28 days of
referral or such longer period as is agreed by the parties after the dispute has been
referred;
Further it allow the adjudicator to extend the period of 28 days by up to 14 days, with the
consent of the party by whom the dispute was referred.
7. If we look at the Indian perspective, the dispute resolution machinery has increasingly
failed to bring about the decision on time due to which cases are pending in the court and
party get frustrated with the case proceeding but the USA adjudication system complete
within a month like 30 or 50 days.
20
CONCLUSION
The following are few suggestions to make the settlement machinery more effective:
1. One average, around one-third of the disputes referred for conciliation failed. Of these,
about 60 to 90 per cent of cases were referred to adjudication. Only one per cent of the
cases were referred for arbitration. These underline the ineffectiveness of conciliation
machinery in settling industrial disputes. Thus, the existing machinery for the settlement
of industrial disputes, as provided under the Industrial Disputes Act, 1947, needs to be
strengthened. But in the same way adjudication has proved the most popular way of
settling industrial disputes in India. This is because adjudication is the last recourse for
disputing parties to settle their disputes.
2. One way to strengthen the adjudication machinery is to substitute it by setting up
Industrial Relations Commissions (IRCs), both at the Central and the State level, on the
lines suggested by the National Commission on Labour. The IRC should also be
empowered to oversee the working of the conciliation machinery.
3. The government should refrain from actively intervening in the matters of industrial
disputes unless it is must for her to intervene in the disputes.
4. As we have seen that in USA the parties has agree to choose their adjudicator if they want
because it has created a problems in practice, and has led to a couple of disadvantage to
the system as the it is not possible to provide a new adjudicator to number of parties due
to which the commercial interest of any Adjudicator Nominating Body is highly
increased, So the USA system should be changed.
But in India the parties do not have freedom to choose their adjudicator or officer,
the act itself provide the appointment and qualification of them as per their hierarchy for
the period not more than 5 or 3 years which is the best way of appointment.
21
REFRENCES
Labour and Industrial Laws by Professor P.K. Padhi, XLRI published by PHI learning
22