Академический Документы
Профессиональный Документы
Культура Документы
Structural Engineering
1. Introduction
The structural engineering profession plays an
important role in design of offshore platforms for
production of hydrocarbons oil & gas. Rapid
developments have taken place the last fifty
years since the first fixed offshore platform was
installed in more than 30meters (100ft) water
depth in the Gulf of Mexico. Today more than
9,000 fixed platforms have been installed world
wide in water-depths up to 400m (Bullwinckle
Jacket in Gulf of Mexico) and has reached
installation weight of more than 650,000 metric
tones (Troll A GBS in the North Sea). Floating
production
platforms
are
taking
field
developments into deeper waters with several
installations in more than 2000m water depth
(Gulf of Mexico). In South-East Asia the first
deep water TLP platform was installed at West
Seno field in Indonesia in 1,000m water depth,
while the first deep water platform in Malaysian
waters is planned for installation in 2007, in
water depth of 1,330m (Kikeh Spar).
Synopsis
The main purpose of Offshore Platforms is to
support facilities required for Oil & Gas Drilling,
Production and Export. This paper provides an
introduction to Offshore Structural Engineering
through references to both fixed and floating
platform concepts, main design requirements
and the way temporary phases, marine
environment and soil conditions at site affect
design.
Modern platform structural design is based on
detailed knowledge of design procedures,
international codes and standards reflecting the
latest developments within research and
experience. This in addition to classical theories,
extensive use of sophisticated computer
programs and creativity as frontiers are
continuously moved. Unique challenges for
offshore platforms are mainly from:
Designing to resist forces from natural
phenomena (waves, current, hydrostatic
pressure, wind and earthquake), corrosion
caused by the marine environment,
Designing for fatigue caused by the cyclic
nature of wind and waves for a duration of
25 to 50 years,
Designing the topside (offshore plant) within
extremely confined spaces,
Designing to maximize completion at
construction site and to minimize offshore
construction work,
Designing for temporary phases
(construction, loading out, sea transport and
offshore installation).
Notations
1) FPSO
2)
3)
4)
5)
6)
GBS
LMU
MT
MODU
SSCV
7) TLP
2. Platform Types
Fixed platforms are mainly found for relative
shallow waters, with installations up to around
400m water depth for jackets, 300m for GBS
and 600m for Compliant Towers (see below for
description of GBS and Compliant Towers).
Floating platforms are utilized when water depth
is
rendering
fixed
platform
concepts
uneconomical
or
technically
unfeasible.
Maximum water depth possible with present
technologies is around 3000m for floating
platforms.
Semi-submersible production platforms (Figure3) are moored to the seabed using platform
inertia and catenary mooring lines (or slack
mooring) to restrict extreme lateral motions
during a storm. The hull form is derived from a
traditional drilling semi. By taking advantage of
being a stationary platform, a ring pontoon
configuration can be utilized to accommodate
higher deck loading. Most commonly four or six
columns are connecting the pontoons to the
deck structure. Due to large heave motions, the
key factor is the seabed well completion (wet
tree) driving up costs, compared to on-platform
well completion (dry tree).
4. Design Loads
For offshore platforms, it is essential to
estimate, report and monitor platform weight
(mass) with high accuracy throughout design
and construction process, as operations during
temporary phases and in-service conditions are
usually sensitive even to small changes in
weight and centre of gravity. Particularly for
topside structures weighing is usually required
prior to load out using jacks and load cells that
can provide weighing inaccuracy less than 1%.
Thorough weight estimation and reporting will
typically achieve weights within 3% of the actual
weighing results.
3. Design Criteria
For a specific platform project, structural design
has to comply with specific offshore structural
design procedures (codes), local governmental
regulations
and
developer
(owner)
specifications.
Design
procedures
are
necessary to provide acceptable standard of
safety by defining minimum requirements for the
structural design during pre-service phases
(construction, load out, sea transportation and
installation), in-service and during eventual
removal. These procedures will also serve as
guidelines and technical reference documents in
contractual matters.
(d)
Permanent ballast.
6. Foundation design
Essential for foundation design is availability of
reliable and site-specific soil investigation data
that consider type and size of platform,
foundation method, uniformity of soil, type of soil
deposits and seabed conditions. The soil
investigation must also consider requirements
applicable for temporary stability during platform
installation.
pile sleeves connected to the jacket legs at seafloor level. The underwater sleeves can be
grouped in clusters around the jacket legs either
as vertically sleeves or as inclined sleeves. The
latter arrangement will provide a stiffer
foundation due to increased base at the bottom
of the piles at the cost of added steel weight and
more complicated pile driving.
7. Fabrication
The main goal with onshore fabrication of
offshore platforms is to complete as much work
as possible on land under conditions that are far
more productive, produce higher quality and
involve less risk than offshore works. Some of
the principles that are followed to reduce
offshore work are (a) Fabricate as large
components as possible, (b) Simplification and
reduction of number of Offshore (Hook-up)
interfaces.
While skidding can achieve speed of typical 510meters/hour, much faster operation can be
achieved using self-propelled trailers with the
speed limited by barge ballast capacity (Figure10). Trailers also provide load control as
hydraulic jacks as each axle are changing
stroke to keep loading constant during the entire
8
8.2 Transportation
9. Offshore Installation
Offshore installation phase is critical due to the
marine operational costs and risks involved.
Lifting is the most common method for smaller
and medium size platform topsides and
substructures. Crane vessels can be of monohull type with a single crane or a semi
submersible crane vessel (SSCV) equipped with
two cranes. For practical purposes, SSCV
utilizing tandem lifts are currently limited to only
two vessels world-wide capable to lift
approximately 11,000MT as proven for topside
structures in the North sea. For lifts in this
range, sling diameter is around 350-400mm with
safe braking loads of around 2,500MT, and
arranged as double-double slings connected to
pad ears using pins and sheaves. Design load
for a single pad ear can typically be around
7,000MT. A number of jackets in the North Sea
in the range of 7,000MT have been directly lifted
and upended (when required) using SSCV.
Direct lifting is beneficial for structural weight as
additional buoyancy tanks are not required,
which is often the case if the jacket must be
upended while floating in the water. Mobilization
costs are a major hindrance for the large SSCV
to be considered for instance in Asia and AsiaPacific region where the currently operating liftvessels are having maximum capacity of
approximately 3,000MT.
For relative shallow water depths, a selfinstalled platform or jack-up platform can take
away the requirement for a heavy lift vessel.
The platform can be transported on a barge or
towed to the site, and installed by lowering
platform legs down to seabed. The legs can be
supported using spud-cans or large tanks that
can be flooded and act as gravity foundation.
10
References
[1]
American
Petroleum
Institute
Recommended Practice (2A-WSD) for Planning,
Designing, and Constructing Fixed Offshore
Platforms Working Stress Design.
[2] ISO 19 902 Petroleum and Natural gas
Industries Fixed Steel Offshore Structures.
[3] NORSOK Standard N-001 Structural
Design.
[4] NORSOK Standard N-003 Actions and
Action Effects.
[5] NORSOK Standard N-004 Design of Steel
Structures.
[6] Edited by A. Almar-Naess, Tapir, Fatigue
Handbook, Offshore Steel Structures, 1985.
[7] N. P. D. Barltrop and A. J.Adams, Dynamics
of fixed marine structures, ButterworthHeinemann Ltd, The Marine Technology
Directorate Ltd 1991.
[8] Det Norske Veritas Rules for Planning and
Execution of Marine Operations.
11