Академический Документы
Профессиональный Документы
Культура Документы
26,Bologna, Italy
I. INTRODUCTION
T "
vo.In
P*
The real power delivered to the load at the receiving end bus R
of the transmission line is
P, =-v,
cos q
z, 1+ (z, / z , y + 2(z, / Z , ) C O S ( 8 -
ZR
q ) z , (I)
/ z , = 1.
gets
PO
(5)
(6)
Bus 1
0"s 6
BUS 5
BUS 2
Fig. 4 shows that the voltage stability index LsR for branch
where
& and
k
L,,,,
....
ql
.....
multiplied by a weight
O20
'
,
35
45
55
65
75
85
95
105
PI, = max(z:,)
V. SIMULATION RESULTS
The proposed method was tested for small test to large realistic
power systems and showed to be able to correctly identify the
most critical contingencies. Some simulation results are
included here to show some important characteristics of the
method.
Table 1 shows some results for the IEEE 30 bus system [71.
The first 10 most critical contingencies ranked according to
the proposed method are compared to the ones obtained by a
detailed analysis. The detailed analysis consists of obtaining
the post-contingency maximum loading point through
successive load flow solutions by increasing both load and
generation. Load power factors were kept constant.
100%
Table I1 shows that the capture ratio for the IEEE 30 bus
system is very good, providing encouraging results.
TABLE U
TABLE I
CONTINGENCY RANKLNG FOR T EIEEE - 30 BUS SYSTEM
Tables I11 and IV show some results for a 904 bus, 1283
branch system corresponding to a reduced version of the
Southwest USA. Table I11 shows the rankings (expected and
obtained by the proposed method), while Table IV shows the
capture ratios.
TABLE Ul
RANKWGFOR THE 904 BUS SYSTEM
TABLE Iv
CAFTLlrtE RATIOS FOR THE 904 BUS SYSIEM
VIII. BIOGRAPHIES
Mririo de ALmeida e Albuquerque was born in N i t d i , Brasil, on November
11,1956. He obtained the BS degree from the Federal University from Ria de
Janeiro in 1980. He is with Fumas Csntais El6uicas. Brazil, where he is
responsible for supervising the operation of part of the southeast area of the
brazilian power system. He is pursuing his MS degree at the State University
of Campinas (UNICAMP).
VI. CONCLUSIONS
The objective of this paper was to propose a contingency
ranking procedure for selecting the most critical contingencies
for voltage stability. Additionally, the ranking process should
take the smallest extra computational effort possible with
respect to the current screeening practices (for MW overload
and voltage violation analyses). In other words, only one load
flow iteration should be computed for each contingency. This
constitutes an important constraint if compared to other
selection procedures proposed in the literature. Results have
shown that a second iteration is necessary in case of reactive
power generation limit violations at generation buses.
Therefore, the conventional contingency selection procedure
was preserved with mild modifications. The proposed
procedure requires in average less than two load flow
iterations per contingency. A very simple, easy to understand,
and easy to compute voltage stability proximity index was
used. This index was incorporated into a performance index
for ranking the contingencies. Results showed that the
proposed method can correctly identify the critical
contingencies for voltage stability.
VII. REFERENCES
B. Ston, 0. Alsq. and A.]. Monticelli, Security analysis and
optimization, Proceedings of the IEEE, ~01.75,n.12, pp.1623-1644,
1987.