02-APRIL-2016
Time
Waktu
Project
Proyek
Yamal LNG
Company
Perusahaan
Siemens
Work Location
Lokasi Kerja
PAB 030
Supervisor
Pengawas
Dani Ramdani
Task / Pekerjaan:
- Instalation Volt Meter Normaly Room & Essential Room
- Inter Loop Panel LV Switch Board 0,4kv Normaly Room & Essential Room
- Inter Loop Panel MV Switch Geard 6,6kv Normaly Room & Essential Room
- Inter Loop Panel MV Switch Geard 6,6kv Normaly Room & Essential Room
Put a cross sign (X) in the following column / Berilah tanda silang (X) pada kolom berikut ini:
Area of work involved /Daerah kerja yang terlibat:
1.
Multimeter
6.
2.
Electrical Handtools
7.
At height / Di ketinggian
3.
8.
4.
Power Supply
220VAC/110VDC
9.
5.
Precommissioning Work
Name
Nama
No
10.
Designation
Jabatan
AKBAR SYAWALUDIN
COMMISSIONING
ZAINAL ARIFIN
COMMISSIONING
SUCIPTO
COMMISSIONING
LAHMOT PAKPAHAN
COMMISSIONING
Pages(s): 1
Form: SIE-HSE-005-F11 Rev.01
KARISMA
COMMISSIONING
RONY THAMRIN
COMMISSIONING
PARLIN
COMMISSIONING
10
FERY BUDIANTO
COMMISSIONING
NATALIA KRISTIANTO
COMMISSIONING
11
M, OKI
COMMISSIONING
NANA SUBARNA
COMMISSIONING
12
SUTRISNO
COMMISSIONING
No/
No
Job Steps
Tahapan Pekerjaan
Visual inspection
Potential Hazards
Potensi Bahaya
Risk
Resiko
Mishandling of the
materials & tools
Mishandling of termination
KIT
Damage material
Control Measures
Tindakan Pengendalian
Completion Date
Tanggal
Pemenuhan
Electricity
Short Circuit
Electric Shock
Mishandling of equipment
Equipment damage
Pages(s): 2
Form: SIE-HSE-005-F11 Rev.01
Electricity
Short Circuit
Electric Shock
Mishandling of equipment
Equipment damage
Pages(s): 3
Form: SIE-HSE-005-F11 Rev.01