Вы находитесь на странице: 1из 394

This softawre is based on Standard Data book for analysis of Rates for Road and Bridge Works

This Software runs on Microsoft Excel


INPUT- Input the usage rates of Plant & Machinery, labour and material as applicable
SUMMARY - In this sheet summary of all the rates analysized is presented
ANALYSIS- The analysis has been presented in 16 nos. of spread sheets
Worksheet- 1 : CHAPTER-1 CARRIAGE OF MATERIALS
Worksheet- 2 : CHAPTER-2 SITE CLEARANCE
Worksheet- 3 : CHAPTER-3 EARTH WORK, EROSION CONTROL AND DRAINAGE
Worksheet- 4 : CHAPTER-4 SUB-BASES, BASES (NON- BITUMINOUS) AND
SHOULDERS
Worksheet- 5 : CHAPTER-5 BASES AND SURFACE COURSES (BITUMINOUS)
Worksheet- 6 : CHAPTER-6 CEMENT CONCRETE PAVEMENTS
Worksheet- 7 : CHAPTER-7 GEOSYNTHETICS AND REINFORCED EARTH
Worksheet- 8 : CHAPTER-8 TRAFFIC SIGNS, MARKINGS & OTHER ROAD
APPURTENANCES
Worksheet- 9 : CHAPTER-9 PIPE CULVERTS
Worksheet- 10 : CHAPTER-10 MAINTENANCE OF ROADS
Worksheet- 11 : CHAPTER-11 HORTICULTURE
Worksheet- 12 : CHAPTER-12 FOUNDATIONS
Worksheet- 13 : CHAPTER-13 SUB-STRUCTURE
Worksheet- 14 : CHAPTER-14 SUPER-STRUCTURE
Worksheet- 15 : CHAPTER-15 RIVER TRAINING AND PROTECTION WORKS
Worksheet- 16 : CHAPTER-16 REPAIR AND REHABILITATION

(A) Usage Rates of Plant and Machinery


Sl. No.

Description of Machine

Activity

Output of
Machine

Output

Unit

Rate

P&M-001

Air Compressor

General Purpose

capacity in cfm

170/250

hour

300

P&M-002

Batching and Mixing Plant (a) 30 cum capacity

Concrete Mixing

cum/hour

20

hour

2094

P&M-003

Batching and Mixing Plant (b) 15 - 20 cum capacity Concrete Mixing

cum/hour

13

hour

1745

P&M-004

Bitumen Pressure Distributor

Applying bitumen tack coat

sqm/hour

1750

hour

1006

P&M-005

Bitumen Boiler oil fired

Bitumen Spraying

capacity in litre

1500

hour

186

P&M-006

Concrete Paver Finisher with 40 HP Motor

Paving of concrete surface

cum / hour

20

hour

2690

P&M-007

Concrete Pump of 45 & 30 cum capacity

Pumping of concrete

cum / hour

33 / 22

hour

240

P&M-008

Concrete Bucket

For Pouring concrete

capacity in cum

hour

15

P&M-009

Concrete Mixer (a) 0.4/0.28 cum

Concrete Mixing

cum/hour

2.5

hour

218

P&M-010

Concrete Mixer (b) 1 cum

Concrete Mixing

cum/hour

7.5

hour

218

P&M-011

Crane (a) 80 tonnes

Lifting Purpose

hour

1200

P&M-012

Cranes b) 35 tonnes

Lifting Purpose

hour

800

P&M-013

Cranes c) 3 tonnes

Lifting Purpose

hour

334

P&M-014

Dozer D - 80 - A 12

Spreading /Cutting / Clearing

cum/hour

300/ 150/250

hour

3490

P&M-015

Dozer D - 50 - A 15

Spreading /Cutting / Clearing

cum/hour

200/ 120/150

hour

2069

P&M-016

Emulsion Pressure Distributor

Applying emulsion tack coat

sqm/hour

1750

hour

750

P&M-017

Front End loader 1 cum bucket capacity

Soil loading / Aggregate loading

cum/hour

60 /25

hour

756

P&M-018

Generator (a) 125 KVA

Genration of electric Energy

KVA

100

hour

654

P&M-019

Generator( b) 63 KVA

Genration of electric Energy

KVA

50

hour

349

P&M-020

GSB Plant 50 cum

Producing GSB

cum/hour

40

hour

974

P&M-021

Hotmix Plant - 120 TPH capacity

DBM/BM/SDC/ Premix

cum/hour

40

hour

15906

P&M-022

Hotmix Plant - 100 TPH capacity

DBM/BM/SDC/ Premix

cum/hour

30

hour

12360

P&M-023

Hotmix Plant - 60 to 90 TPH capacity

DBM/BM/SDC/ Premix

cum/hour

25

hour

10256

P&M-024

Hotmix Plant - 40 to 60 TPH capacity

DBM/BM/SDC/ Premix

cum/hour

17

hour

7339

P&M-025

Hydraulic Chip Spreader

Surface Dressing

sqm/hour

1500

hour

2472

P&M-026

Hydraulic Excavator of 1 cum bucket

Soil Ordinary/Soil Marshy / Soil Unsuitable

cum/hour

60 /60 /60

hour

1222

P&M-027

Integrated Stone Crusher 100THP

Crushing of Spalls

TPH

100

hour

8130

P&M-028

Integrated Stone Crusher 200 HP

Crushing of Spalls

TPH

200

hour

17103

P&M-029

Kerb Casting Machine

Kerb Making

291

P&M-030

Mastic Cooker

Mastic Wearing coat

P&M-031

Mechanical Broom Hydraulic

P&M-032
P&M-033

Rm/hour

80

hour

capacity in tonne

hour

58

Surface Cleaning

sqm/hour

1250

hour

334

Motor Grader 3.35 mtr blade

Clearing /Spreading /GSB /WBM

cum/hour

200/200/50/50

hour

2247

Mobile slurry seal equipment

Mixing and laying slurry seal

sqm/hour

2700

hour

945

P&M-034

Paver Finisher Hydrostatic with sensor control 100


TPH

Paving of DBM/ BM/SDC/ Premix

cum/hour

40

hour

2509

P&M-035

Paver Finisher Mechanical 100 TPH

Paving of WMM /Paving of DLC

cum/hour

40/30

hour

915

P&M-036

Piling Rig with Bantonite Pump

0.75 m dia to 1.2 m dia Boring attachment

Rm/hour

2 to 3

hour

5126

P&M-037

Pneumatic Road Roller

Rolling of Asphalt Surface

cum/hour

25

hour

1166

P&M-038

Pneumatic Sinking Plant

Pneumatic Sinking of wells

cum/hour

1.5 to 2.00

hour

3912

P&M-039

Pot Hole Repair Machine

Repair of potholes

cum/hour

hour

851

P&M-040

Prestressing Jack with Pump & access

Stressing of steel wires/stands

hour

121

P&M-041

Ripper

Scarifying

60

hour

26

P&M-042

Rotavator

Scarifying

cum/hour

25

hour

16

P&M-043

Road marking machine

Road marking

Sqm/hour

100

hour

87

P&M-044

Smooth Wheeled Roller 8 tonne

Soil Compaction /BM Compaction

cum/hour

70/25

hour

432

P&M-045

Tandem Road Roller

Rolling of Aspalt Surface

cum/hour

30

hour

1073

P&M-046

Tipper - 5 cum

Transportation of soil, GSB, WMM, Hotmix


etc.

Capacity in cum

5.5

km

227

P&M-047

Tipper - 5 cum

Transportation of soil, GSB, WMM, Hotmix


etc.

Capacity in cum

5.5

tonne.km

Tipper - 5 cum

Transportation of soil, GSB, WMM, Hotmix


etc.

Capacity in cum

5.5

hour

291

P&M-048

cum/hour

Page 1 of 394

P&M-049

Transit Mixer 4.0/4.5 cum

Transportation of Concrete Mix to site

cum/hour

4.5

hour

873

P&M-050

Transit Mixer 4/4.5 cum

Transportation of Concrete Mix to site

cum/hour

4.5

tonne.km

input

P&M-051

Transit Mixer 3.0 cum

Transportation of Concrete Mix to site

cum/hour

hour

800

P&M-052

Transit Mixer 3.0 cum

Transportation of Concrete Mix to site

cum/hour

tonne.km

input

P&M-053

Tractor

Pulling

capacity in HP

50

hour

340

P&M-054

Tractor with Rotevator

Rate of Tractor + Rotevator

hour

356

P&M-055

Tractor with Ripper

Rate of Tractor 6+ Ripper

hour

366

P&M-056

Truck 5.5 cum per 10 tonnes

Material Transport

capacity/cum

4.5

km

21

P&M-057

Truck 5.5 cum per 10 tonnes

Material Transport

capacity/cum

4.5

hour

291

P&M-058

Truck 5.5 cum per 10 tonnes

Material Transport

capacity/cum

4.5

tonne.km

P&M-059

Vibratory Roller 8 tonne

Earth or soil / GSB / WBM

cum/hour

100/60/60

hour

1446

P&M-060

Water Tanker

Water Transport

capacity in KL

hour

233

P&M-061

Water Tanker

Water Transport

capacity in KL

km

23

P&M-062

Wet Mix Plant 60 TPH

Wet Mix

cum/hour

25

hour

1130

Sl. No.

Description of Machine

Unit

Rate

P&M-063

Air compressor with pneumatic chisel attachment for cutting hard clay.

hour

300

P&M-064

Batch type cold mixing plant 100-120 TPH capacity producing an average output of 75 tonne per hour

hour

input

P&M-065

Belt conveyor system

hour

input

P&M-066

Boat to carry atleast 20 persons

hour

input

P&M-067

Cement concrete batch mix plant @ 175 cum per hour (effective output)

hour

input

P&M-068

Cement concrete batch mix plant @ 75 cum per hour

hour

input

P&M-069

Cold milling machine @ 20 cum per hour

hour

input

P&M-070

Crane 5 tonne capacity

hour

334

P&M-071

Crane 10 tonne capacity

hour

input

P&M-072

Crane 15 tonne capacity

hour

input

P&M-073

Crane 20 tonne capacity

hour

input

P&M-074

Crane 40 T capacity

hour

800

P&M-075

Crane with grab 0.75 cum capacity

hour

349

P&M-076

Compressor with guniting equipment along with accessories

hour

300

P&M-077

Drum mix plant for cold mixes of appropriate capacity but not less than 75 tonnes/hour.

hour

input

P&M-078

Epoxy Injection gun

hour

input

P&M-079

Generator 33 KVA

hour

349

P&M-080

Generator 100 KVA

hour

654

P&M-081

Generator 250 KVA

hour

700

P&M-082

Induction, deinduction and erection of plant and equipment including all components and accessories for pneumatic method of well sinking.

hour

input

P&M-083

Joint Cutting Machine with 2-3 blades (for rigid pavement)

hour

input

P&M-084

Jack for Lifting 40 tonne lifting capacity.

day

input

P&M-085

Piling rig Including double acting pile driving hammer (Hydraulic rig)

hrs

input

P&M-086

Plate compactor

hour

input

P&M-087

Snow blower equipment 140 HP @ 600 cum per hour

hour

input

P&M-088

Texturing machine (for rigid pavement)

hour

input

P&M-089

Truck Trailor 30 tonne capacity

hour

input

P&M-090

Truck Trailor 30 tonne capacity

t.km

input

P&M-091

Tunnel Boring machine

hour

input

P&M-092

Vibrating Pile driving hammer complete with power unit and accessories.

hour

input

P&M-093

Wet Mix Plant 100 TPH

hour

1130

P&M-094

Wet Mix Plant 75 TPH

hour

1130

Page 2 of 394

(B) Labour
Sl. No.

Description of Labour

Unit

Rate

L-01

Blacksmith (IInd class)

day

450

L-02

Blacksmith (Ist class)/ Welder/ Plumber/ Electrician

day

500

L-03

Blaster (Stone cutter)

day

396

L-04

Carpenter I Class

day

500

L-05

Chiseller (Head Mazdoor)

day

400

L-06

Driller (Jumper)

day

400

L-07

Diver

day

471

L-08

Fitter

day

456

L-09

Mali

day

377

L-10

Mason (IInd class)

day

471

L-11

Mason (Ist class)

day

500

L-12

Mate / Supervisor

day

673

L-13

Mazdoor

day

377

L-14

Mazdoor/Dresser (Semi Skilled)

day

377

L-15

Mazdoor/Dresser/Sinker (Skilled)

day

408

L-16

Medical Officer

day

852

L-17

Operator(grouting)

day

450

L-18

Painter I class

day

396

L-19

Para medical personnel

day

852

Unit

Rate

(C) Materials
Sl. No.

Description

M-001

Stone Boulder of size 150 mm and below at Cruser Plant

cum

210

M-002

Supply of quarried stone 150 - 200 mm size for Hand Broken at site

cum

240

M-003

Boulder with minimum size of 300 mm for Pitching at Site

cum

240

M-004

Coarse sand at Mixing Plant

cum

2400

M-005

Coarse sand at Site

cum

2400

M-006

Fine sand at Site

cum

616

M-007

Moorum at Site

cum

450

M-008

Gravel/Quarry spall at Site

Cum

175

M-009

Granular Material or hard murrum for GSB works at Site

Cum

190

Page 3 of 394

M-010

Granular Material or hard murrum for GSB works at Mixing Plant

Cum

190

M-011

Fly ash conforming to IS: 3812 ( Part II & I) atHMP Plant / Batching Plant / Crushing Plant

Cum

Nil

M-012

Filter media/Filter Material as per Table 300-3 (MoRT&H Specification)

Cum

725

Unit

Rate at Plant
(HMP/Batching
)

Rate at Site

Description
M-013

Close graded Granular sub-base Material 53 mm to 9.5 mm

cum

input

655.20

M-014

Close graded Granular sub-base Material 37.5 mm to 9.5 mm

cum

input

923

M-015

Close graded Granular sub-base Material 26.5 mm to 9.5 mm

cum

input

923

M-016

Close graded Granular sub-base Material 9.5 mm to 4.75 mm

cum

input

692.6

M-017

Close graded Granular sub-base Material 9.5 mm to 2.36 mm

cum

input

692.6

M-018

Close graded Granular sub-base Material 4.75mm to 2.36 mm

cum

input

137

M-019

Close graded Granular sub-base Material 4.75mm to 75 micron mm

input

137

M-020

Close graded Granular sub-base Material 2.36 mm

cum

input

137

M-021

Stone crusher dust finer than 3mm with not more than 10% passing 0.075 sieve.

cum

input

137

M-022

Coarse graded Granular sub-base Material 2.36 mm & below

cum

input

137

M-023

Coarse graded Granular sub-base Material 4.75mm to 75 micron mm

input

137

M-024

Coarse graded Granular sub-base Material 4.75 mm to 2.36 mm

cum

input

137

M-025

Coarse graded Granular sub-base Material 9.5 mm to 4.75 mm

cum

input

137

M-026

Coarse graded Granular sub-base Material 26.5 mm to 4.75 mm

cum

input

511.4

M-027

Coarse graded Granular sub-base Material 26.5 mm to 9.5 mm

cum

input

713

M-028

Coarse graded Granular sub-base Material 37.5 mm to 9.5 mm

cum

input

713

M-029

Coarse graded Granular sub-base Material 53 mm to 26 .5mm

cum

input

713

M-030

Aggregates below 5.6 mm

cum

input

1507

Aggregates 22.4 mm to 2.36 mm - Wet Mix Macadam

cum

input

653

Aggregates 22.4 mm to 2.36 mm - Bituminous Penetration Macadam

cum

input

678.6

Aggregates 22.4 mm to 2.36 mm - Built up Spray Grout

cum

input

757.7

M-032

Aggregates 22.4 mm to 5.6 mm

cum

input

137

M-033

Aggregates 45 mm to 2.8 mm

cum

input

912.95

Aggregates 45 mm to 22.4 mm - Wet Mix Macadam

cum

input

863.55

Aggregates 45 mm to 22.4 mm - Crusher Run Macadam Base

cum

input

713

M-035

Aggregates 53 mm to 2.8 mm

cum

input

900.55

M-036

Aggregates 53 mm to 22.4 mm

cum

input

793.5

M-037

Aggregates 63 mm to 2.8 mm

cum

input

1010.7

M-038

Aggregates 63 mm to 45 mm

cum

input

599.2

M-039

Aggregates 90 mm to 45 mm

cum

input

581.1

Aggregates 10 mm to 5 mm - Bituminous Macadam

cum

input

700

Aggregates 10 mm to 5 mm - Dense graded Bituminous Macadam

cum

input

2314

Aggregates 10 mm to 5 mm - Semi Dense Bituminous Macadam Concrete

cum

input

700

M-031

M-034

M-040

Aggregates 10 mm to 5 mm - Bituminous Concrete

cum

input

1063

M-041

Aggregates 11.2 mm to 0.09 mm

cum

input

1749.1

M-042

Aggregates 13.2 mm to 0.09 mm

cum

input

1375.2

M-043

Aggregates 13.2 mm to 5.6 mm

cum

input

941.2

Aggregates 13.2 mm to 10 mm - Semi Dense Bituminous Macadam Concrete

cum

input

989.2

Aggregates 13.2 mm to 10 mm - Bituminous Concrete

cum

input

1063

Aggregates 20 mm to 10 mm

cum

input

1025.4

Aggregates 25 mm to 10 mm - Bituminous Macadam

cum

input

965.75

Aggregates 25 mm to 10 mm - Dense graded Bituminous Macadam

cum

input

928

M-047

Aggregates 19 mm to 6 mm

cum

input

input

M-048

Aggregates 37.5 mm to 19 mm

cum

input

input

Aggregates 37.5 mm to 25 mm - Bituminous Macadam

cum

input

713

Aggregates 37.5mm to 25 mm - Dense graded Bituminous Macadam

cum

input

711

M-044
M-045
M-046

M-049

Page 4 of 394

M-050

Aggregates 6 mm nominal size

cum

input

700

M-051

Aggregates 10 mm nominal size

cum

input

1063

M-052

Aggregates 13.2/12.5 mm nominal size

cum

input

928

M-053

Aggregates 20 mm nominal size

cum

input

942

M-054

Aggregates 25 mm nominal size

cum

input

767

M-055

Aggregates 40 mm nominal size

cum

input

659

Unit

Rate

Sl. No.

Description

M-056

AC pipe 100 mm dia

M-057

Acrylic polymer bonding coat

metre

55

litre

457

M-058
M-059

Alluminium Paint

litre

195

Aluminium alloy plate 2mm Thick

sqm

926

M-060

Aluminium alloy/galvanised steel

tonne

57960

M-061

Aluminium sheeting fixed with encapsulated lens type reflective sheeting including 2% towards lettering, cost of angle iron, cost of drilling holes,
nuts, bolts etc.and signs as applicable

sqm

input

M-062

Aluminium studs 100 x 100 mm fitted with lense reflectors

nos

input

M-063

Barbed wire

kg

49.68

M-064

Bearing (Cost of parts)

nos

input

M-065

Bearing (Cast steel rocker bearing assembly of 250 tonne )

nos

input

M-066

Bearing (Elastomeric bearing assembly consisting of 7 internal layers of elastomer bonded to 6 nos. internal reinforcing steel laminates by the
process of vulcanisation,)

nos

input

M-067

Bearing (Forged steel roller bearing of 250 tonne

nos

input

M-068

Bearing (Pot type bearing assembly consisting of a metal piston supported by a disc, PTFE pads providing sliding surfaces against stainless steel
mating together with cast steel assemblies/fabricated structural steel assemblies duly painted with all components

nos

input

M-069

Bearing (PTFE sliding plate bearing assembly of 80 tonnes )

nos

input

M-070

Bearing (Supply of sliding plate bearing of 80 tonne)

nos

input

M-071

Bentonite

kg

6.35

M-072

Binding wire

kg

87

M-073

Bitumen ( Cationic Emulsion )

tonne

34975

M-074

Bitumen (60-70 grade)

tonne

41320

M-075

Bitumen (80-100 grade )

tonne

40367

M-076

Bitumen (Cutback )

tonne

40367

M-077

Bitumen (emulsion)

tonne

34975

M-078

Bitumen (modified graded)

tonne

42677

M-079

Brick

each

3.8

M-080

C.I.shoes for the pile

M-081

kg

53

Cement

tonne

5940

M-082

Cold twisted bars (HYSD Bars)

tonne

52100

M-083

Coller for joints 300 mm dia

nos

input

M-084

Compressible Fibre Board(20mm thick)

sqm

603

M-085

Connectors/ Staples

each

M-086

Copper Plate(12m long x 250mmwide)

M-087

Corrosion resistant Structural steel

M-088

Corrugated sheet, 3 mm thick, "Thrie" beam section railing

M-089
M-090
M-091

kg

522

tonne

input

kg

53.4

Credit for excavated rock found suitable for use

cum

391

Curing compound

liter

727

Delineators from ISI certified firm as per the standard drawing given in IRC - 79

each

input

M-092

Earth Cost or compensation for earth taken from private land

cum

137

M-093

Elastomeric slab seal expansion joint assembly manufactured by using chloroprene, elastomer for elastomeric slab unit conforming to clause
915.1 of IRC: 83 (part II),

metre

input

M-094

Electric Detonators @ 1 detonator for 1/2 gelatin stick of 125 gms each

100 nos

1100

M-095

Epoxy compound with accessories for preparing epoxy mortar

kg

input

M-096

Epoxy mortar

kg

input

M-097

Epoxy primer

kg

input

M-098

Epoxy resin-hardner mix for prime coat

kg

input

M-099

Flag of red color cloth 600 x 600 mm

each

input

M-100

Flowering Plants

each

input

Page 5 of 394

M-101

Galvanised MS flat clamp

nos

input

M-102

Galvanised steel wire crates of mesh size 100 mm x 100 mm woven with 4mm dia. GI wire in rolls of required size.

sqm

input

M-103

Galvanised structural steel plate 200 mm wide, 6 mm thick, 24 m long

kg

input

M-104

Gelatin 80%

kg

74.08

M-105

Geo grids

sqm

404

M-106

Geomembrane

sqm

input

M-107

Geonets

sqm

input

M-108

Geotextile

sqm

79

M-109

Geotextile filter fabric

sqm

input

M-110

GI bolt 10 mm Dia

nos

input

M-111

Grouting pump with agitator

hour

input

M-112

Grass (Doob)

kg

input

M-113

Grass (Fine)

kg

input

M-114

HDPE pipes 75mm dia

metre

input

M-115

HDPE pipes 90mm dia

metre

input

M-116

Hedge plants

each

input

M-117

Helical pipes 600mm diameter

metre

input

M-118

Hot applied thermoplastic compound

M-119

HTS strand

M-120

Joint Sealant Compound

M-121
M-122

litre

137

tonne

input

kg

input

Jute netting, open weave, 2.5 cm square opening for seeding and Mulching

sqm

input

LDO for steam curing

litre

input

M-123

M.S. Clamps

nos

input

M-124

M.S. Clamps

kg

55

M-125

M.S.shoes @ 35 Kg per pile of 15 m

kg

53

M-126

Mild Steel bars

tonne

37100

M-127

Modular strip/box seal expansion joint including anchorage catering to a horizontal movement beyond 70 mm and upto 140mm assembly
comprising of edge beams, central beam,2 modules chloroprene seal, anchorage elements, support and control system, all steel sections
protected against corrosion and installed by the manufacturer or his authorised representative

metre

input

M-128

Modular strip/box seal expansion joint catering to a horizontal movement beyond 140mm and upto 210mm box/box seal joint assembly
containing 3 modules/cells and comprising of edge beams, two central beams, chloroprene seal, anchorage elements, support and control
system, all steel sections protected against corrosion and installed by the manufacturer or his authorised representative

metre

input

M-129

Nipples 12mm

nos

15

M-130

Nuts and bolts

kg

81

M-131

Paint

litre

211

M-132

Pavement Marking Paint

litre

211

M-133

Paving Fabric

sqm

input

M-134

Perforated geosynthetic pipe 150 mm dia

metre

input

M-135

Perforated pipe of cement concrete, internal dia 100 mm

metre

54

M-136

Pesticide

kg

463

M-137

Pipes 200 mm dia, 2.5 m long for drainage

metre

input

M-138

Plastic sheath, 1.25 mm thick for dowel bars

sqm

input

M-139

Plastic tubes 50 cm dia, 1.2 m high

nos

input

M-140

Polymer braids

metre

input

M-141

Pre moulded Joint filler,25 mm thick for expansion joint.

sqm

992

M-142

Pre-coated stone chips of 13.2 mm nominal size

cum

input

M-143

Preformed continuous chloroprene elastomer or closed cell foam sealing element with high tear strength, vulcanised in a single operation for the
full length of a joint to ensure water tightness.

metre

input

M-144

Pre-moulded asphalt filler board

sqm

input

M-145

Pre-packed cement based polymer concrete of strength 45 Mpa at 28 days

kg

input

M-146

Primer

kg

input

M-147

Quick setting compound

kg

input

M-148

Random Rubble Stone

cum

391

M-149

RCC Pipe NP 4 heavy duty non presure pipe 1000 mm dia

metre

input

M-150

RCC Pipe NP 4 heavy duty non presure pipe 1200 mm dia

metre

input

M-151

RCC Pipe NP 4 heavy duty non presure pipe 300 mm dia

metre

input

Page 6 of 394

M-152

Reflectorising glass beads

kg

61

M-153

Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. (Copper Strips)

metre

input

M-154

Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. (Galvanised carbon steel strips)

metre

input

M-155

Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. (Glass reinforced polymer/fibre reinforced polymer/polymeric strips)

metre

input

M-156

Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. (Stainless steel strips)

metre

input

M-157

Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. Aluminium strips)

metre

input

M-158

Rivets

each

0.65

M-159

Sand bags (Cost of sand and Empty cement bag)

nos

22

M-160

Sapling 2 m high 25 mm dia

each

input

M-161

Scrap tyres of size 900 x 20

nos

input

M-162

Seeds

kg

input

M-163

Selected earth

cum

137

M-164

Separation Membrane of impermeable plastic sheeting 125 micron thick

sqm

input

M-165

Sheathing duct

metre

input

M-166

Shrubs

each

input

M-167

Sludge / Farm yard manure @ 0.18 cum per 100 sqm at site of work for turfing

cum

input

M-168

Sodium vapour lamp

each

input

M-169

Square Rubble Coursed Stone

cum

753

M-170

Steel circular hollow pole of standard specification for street lighting to mount light at 5 m height above deck level

each

input

M-171

Steel circular hollow pole of standard specification for street lighting to mount light at 9 m height above road level

each

input

M-172

Steel drum 300 mm dia 1.2 m high/empty bitumen drum

nos

238

M-173

Steel helmet and cushion block on top of pile head during driving.

kg

input

M-174

Steel pipe 25 mm external dia as per

IS:1239

metre

66

M-175

Steel pipe 50 mm external dia as per

IS:1239

metre

245

M-176

Steel wire rope 20 mm

kg

input

M-177

Steel wire rope 40 mm

kg

input

M-178

Strip seal expansion join

metre

input

M-179

Structural Steel

tonne

44100

M-180

Super plastisizer admixture IS marked as per 9103-1999

kg

input

M-181

Synthetic Geogrids as per clause 3102.8 and approved design and specifications.

sqm

404

M-182

Through and bond stone

each

14

M-183

Tie rods 20mm diameter

nos

input

M-184

Tiles size 300 x 300 mm and 25 mm thick

each

input

M-185

Timber

cum

input

M-186

Traffic cones with 150 mm reflective sleeve

nos

input

M-187

Tube anchorage set complete with bearing plate, permanent wedges etc

nos

input

M-188

Filler Material (quarry dust)

tonne

72

Unstaked lime

tonne

3200

M-189

Water

KL

13

M-190

Water based cement paint

litre

input

M-191

Welded steel wire fabric

kg

input

M-192

Wire mesh 50mm x 50mm size of 3mm wire

kg

52

M-193

Wooden ballies 2" Dia for bracing

each

input

M-194

Wooden ballies 8" Dia and 9 m long

each

337

M-195

Wooden packing

cum

input

M-196

Wooden staff for fastening of flag 25 mm dia, one m long

each

Page 7 of 394

Overheads for Road Works

10%

Contractors profit for Road Works

10%

Overheads for Bridge Works

20%

for input of Overheads or Contractors profit please type in collum C as like below

Overheads for Bridge Works (Rehabilitation)

30%

Type symble of apostrope(') then input value then one space then symble of
percentage (%) for example '08 %

Contractors profit for Bridge Works

10%

Lead from Mixing Plant to working site

1 km

Lead for E/W borow area to site

1 km

Lead for fly ash from source to site

1 km

Page 8 of 394

Items No.

Summary of Rates calculated and used for analysis of rates of other items

Unit

Rate

per cm height
per letter

0.60
76.00

Item 8.3

Printing new letter and figures of any shade (ii) English Roman

Item 8.8

Painting Two Coats on New Concrete Surfaces

sqm

Item 8.9

Painting angle iron post two coats

sqm

68.00

Item 12.6 (B)

Cement mortor 1:2 (Excluding OH & CP)

cum

6,598.00

Item 12.6 (A)

Cement mortor 1:3 (Excluding OH & CP)

cum

5,916.00

Item 12.6 (D)

Cement mortor 1:6 (Excluding OH & CP)

cum

4,957.00

Item 12.7 (A )

Course Rubble masonary in cement mortor 1:3 (including OH & CP)

cum

5,568.00

Item 12.7 (Addl) B)

Random Rubble masonary in cement mortor 1:6 (including OH & CP)

cum

4,523.00

Item 12.8 (A)

PCC Grade M15 including OH & CP for Open Foundation by Mixer

cum

5,820.00

Item 12.8 (A)

PCC Grade M15 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer

cum

4,240.00

Item 12.8 (B) PCC

PCC Grade M20 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer

cum

4,710.00

Item 12.8 (C)

RCC Grade M20 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer

cum

4,853.00

RCC Grade M20 including OH & CP for Open Foundation by Batching Plant

cum

#VALUE!

Item 12.8 (C)

RCC Grade M20 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Batching Plant

cum

#VALUE!

Item 12.8 (D)

PCC Grade M25 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer

cum

5,038.00

Item 12.8 (D)

PCC Grade M25 including OH & CP for Open Foundation by Batching Plant

cum

#VALUE!

Item 12.8 (D)

PCC Grade M25 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Batching Plant

cum

#VALUE!

Item 12.8 (E)

RCC Grade M25 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer

cum

5,186.00

Item 12.8 (E)

RCC Grade M25 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Batching Plant

cum

#VALUE!

Item 12.8 (F)

PCC Grade M30 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer

cum

5,074.00

Item 12.8 (F)

PCC Grade M30 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Batching Plant

cum

#VALUE!

Item 12.8 (G)

RCC Grade M30 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer

cum

5,206.00

Item 12.8 (G)

RCC Grade M30 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Batching Plant

cum

#VALUE!

Item 12.8 (H)

RCC Grade M35 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer

cum

5,297.00

Item 12.8 (H)

RCC Grade M35 including OH & CP for Open Foundation by Batching Plant

cum

#VALUE!

Item 12.8 (H)

RCC Grade M35 excluding OH & CP for Open Foundation by Batching Plant

cum

#VALUE!

Item 12.8 (H)

Item 12.8 (C) RCC

RCC Grade M35 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Batching Plant

cum

#VALUE!

Item 12.11 (C) i

PCC Grade M20 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material & Mechinery by Mixer

cum

#VALUE!

Item 12.11 (C) i

PCC Grade M20 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material & Mechinery by
Batching Plant

cum

#VALUE!

Item 12.11 (C) ii

PCC Grade M25 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material & Mechinery by Mixer

cum

#VALUE!

Item 12.11 (C) ii

PCC Grade M25 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material & Mechinery by
Batching Plant

cum

#VALUE!

Item 12.11 (C) iii

PCC Grade M30 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material & Mechinery by Mixer

cum

#VALUE!

Item 12.11 (C) iii

PCC Grade M30 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material & Mechinery by
Batching Plant

cum

#VALUE!

Item 12.11 (C) iv

PCC Grade M35 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material & Mechinery by Mixer

cum

#VALUE!

Item 12.11 (C) iv

PCC Grade M35 including OH & CP for Well Foundation (Bottom Plug) by Batching Plant

cum

#VALUE!

Item 12.11 (C) iv

PCC Grade M35 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material & Mechinery by
Batching Plant

cum

#VALUE!

Item 12.11 (F) iv

PCC Grade M35 including OH & CP for Well Foundation (Well Cap) by Batching Plant

cum

#VALUE!

Item No. 3.13

Excavation for Structures (Manual Means)

cum

391.00

Item No. 3.13

Excavation for Structures (Mechenical Meanse)

cum

43.00

Item 14.1(A)

RCC Grade M20 for super-structure including OH & CP by Batching Plant

cum

#VALUE!

Item 14.1(B)

RCC Grade M20 for super-structure including OH & CP by Batching Plant

cum

#VALUE!

Item 14.1(E)

RCC Grade M20 for super-structure including OH & CP by Batching Plant

cum

#VALUE!

Item 14.1(C)

RCC Grade M30 for super-structure including formwork and excluding OH & CP by Batching Plant

cum

#VALUE!

Item 14.1(C)

RCC Grade M30 for super-structure excluding formwork and excluding OH & CP by Batching Plant

cum

#VALUE!

Item 14.2 A

Supplying ,fitting and placing HYSD bar reinforcement in super-structure exncluding OH & CP

tonne

60,214.00

Item 13.6

Supplying, fitting and placing HYSD including OH & CP for sub-structure

tonne

77,756.00

Item 5.17

Fog Seal

sqm

36.00

Item 5.21 Case-I

Crack Prevention courses. Case-I Stress Absorbing Membrane (SAM) crack width less than 6 mm

sqm

58.00

Item 5.21 Case-II

Crack Prevention courses. Case-II Stress Absorbing Membrane (SAM) with crack width 6 mm to 9 mm

sqm

73.00

Item 5.21 Case-IV

Crack Prevention courses. Case-III Stress Absorbing Membrane (SAM) crack width above 9 mm and cracked area
above 50 %

sqm

96.00

Item 5.21 Case-IV

Crack Prevention courses. Case-IV Bitumen Impregnated Geotextile

sqm

161.00

Item 5.15 Case-I

Slurry Seal Case-I 5 mm thickness

sqm

73.00

Item 5.15 Case-II

Slurry Seal Case-II 3 mm thickness

sqm

49.00

Page 9 of 394

Item 5.15 Case-III

Slurry Seal Case III 1.5 mm thickness

sqm

24.00

Item 5.9 Case-I

Surface Dressing Case-I 19 mm nominal chipping size

sqm

82.00

Item 5.9 Case-II

Surface Dressing Case-II 13 mm nominal size chipping

sqm

67.00

Page 10 of 394

Sr No

Ref. to
MoRTH
Spec.

1.1

Note
1.4

Description

Unit

Loading and unloading of stone boulder / stone


aggregates / sand / kanker / moorum.
Placing tipper at loading point, loading with front end loader,
dumping, turning for return trip, excluding time for haulage
and return trip
Unit : cum
Taking output = 5.5 cum
Time required for
i) Positioning of tipper at loading point
ii) Loading by front end loader 1 cum bucket capacity
@ 25 cum per hour
iii) Maneuvering, reversing, dumping and turning for
return
iv) Waiting time, unforeseen contingencies etc
Total
a) Machinery
Tipper 5.5 tonnes capacity
Front end-loader 1 cum bucket capacity @ 25
cum/hour
b) Overheads @ 0.1 on (a)
c) Contractors profit @ 0.1 on (a+b)
Cost for 5.5 cum = a+b+c
Rate per cum = (a+b+c)/ 5.5
Unloading will be by tipping.
Cost of Haulage Excluding Loading and Unloading

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

1 Min
13 Min
2 Min
4 Min
20 Min
hour
hour

0.330
0.330

291.00
756.00

96.03
249.48

P&M-048
P&M-017

34.55
38.01
418.07
76.01
76.00

say

Haulage of materials by tipper excluding cost of loading,


unloading and stacking.
Unit : t.km
Taking output 10 tonnes load and lead 10 km = 100 t.km
1.4(I)

Case I

Surfaced Road
Speed with load : 25 km / hour.
Speed while Returning empty : 35 km / hour.
a) Machinery.
i) Tipper 10 tonne capacity
Time taken for onward haulage with load
Time taken for empty return trip.
b) Overheads @ 0.1 on (a)
c) Contractors profit @ 0.1 on (a+b)
cost for 100 t km = a+b+c
Rate per t.km = (a+b+c)/100

hour
hour

0.400
0.290

291.00
291.00

116.40
84.39
20.08
22.09
242.96
2.43
2.40

P&M-048
P&M-048

291.00
291.00

145.50
96.03
24.15
26.57

P&M-048
P&M-048

say
1.4(II)

Case II

Unsurfaced Gravelled Road


Speed with load : 20 km / hour
Speed for empty return trip : 30 km / hour
a)Machinery
Tipper 10 tonnes capacity
Time taken for onward hanlage with load
Time taken for empty return trip
b) Overheads @ 0.1 on (a)
c) Contractors profit @ 0.1 on (a+b)

Page 11 of 394

hour
hour

0.500
0.330

Cost for 100 t .km = a+b+c


Rate per t.Km = (a+b+c)/100

292.25
2.92
2.90

say
1.4(III)

Case III

Katcha Track and Track in river bed / nallah bed and


choe bed.
Speed with load : 10 km / hour
Speed while returning empty : 15 km / hour
a) Machinery
I) Tipper 10 tonnes capacity
Time taken for onward haulage
Time taken for empty return trip
b) Overheads @ 0.1 on (a)
c) Contractors profit @ 0.1 on (a+b)
Cost for 100 t .km = a+b+c
Rate per t.Km = (a+b+c)/100

hour
hour

1.000
0.670

291.00
291.00

say
1.5

291.00
194.97
48.60
53.46
588.02
5.88
5.90

P&M-048
P&M-048

Hand Broken Stone Aggregates 63 mm nominal size


Supply of quarried stone, hand breaking into coarse
aggregate 63 mm nominal size (passing 80 mm and retained
on 50 mm sieve) and stacking as directed
Unit : cum
Taking output = 1 cum
a)

b)

Labour
Mate

day

0.060

673.00

40.38

L-12

Mazdoor

day

1.500

377.00

565.50

L-13

cum

1.100

240.00

264.00

M-002

Material
Supply of quarried stone 150 - 200 mm size

c)

Overheads @ 0.1 on (a+b)

86.99

d)

Contractors profit @ 0.1 on (a+b+c)

95.69

Rate per cum = a+b+c+d

1052.55
say

1.6

1053.00

Crushing of stone aggregates 13.2 mm nominal size.


Crushing of stone boulders of 150 mm size in an integrated
stone crushing unit of 200 tonnes per hour capacity
comprising of primary and secondary crushing units, belt
conveyor and vibrating screens to obtain stone aggregates
of 13 mm nominal size.
Unit : cum
Taking Output = 600 cum at crusher location.
a) Labour
Mate
Mazdoor Skilled
Mazdoor including breaking of any oversize boulder.
b) Material
Stone Boulder of size 150 mm and below
c) Machinery
Integrated stone crusher of 200 TPH including belt
conveyor and vibrating screens
Front end loader 1 cum bucket capacity
Tipper 5.5 cum capacity
d) Overheads @ 0.1 on (a+b+c)

Page 12 of 394

day
day
day

0.760
2.000
17.000

673.00
377.00
377.00

511.48
754.00
6409.00

L-12
L-14
L-13

cum

800.000

210.00

168000.00

M-001

Hour

6.000

17103.00

102618.00

P&M-028

Hour
Hour

20.000
20.000

756.00
291.00

15120.00
5820.00
29923.25

P&M-017
P&M-048

e) Contractors profit @ 0.1 on (a+b+c+d)


Cost for 600 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)*0.95/600

32915.57
362071.30
573.28
573.00

say
Note

1. 800 cum of stone boulders are needed to get 600 cum of


stone chips of size 13.2 mm.
2. 95% of above cost will be attributed to the production of
600 cum of stone chips of 13.2 mm size and balance 5% to
the production of stone dust which comes out as a byproduct.
3. The integrated stone crusher includes primary and
secondary crushing units.

1.7

Crushing of stone aggregates 20 mm nominal size


Crushing of stone boulders of 150 mm size in an integrated
stone crushing unit of 200 tonnes per hour capacity
comprising of primary and secondary crushing units, belt
conveyor and vibrating screens to obtain stone aggregates
of 20 mm nominal size.
Unit : cum
Taking Output = 670 cum at crusher location.
a) Labour
Mate
Mazdoor Skilled
Mazdoor including breaking of any size boulder.
b) Material
Stone Boulder of size 150 mm and below
c) Machinery
Integrated stone crusher of 200 TPH including belt
conveyor and vibrating screens
Front end loader 1 cum bucket capacity
Tipper 5.5 cum capacity
d) Overheads @ 0.1 on (a+b+c)
e) Contractors profit @ 0.1 on (a+b+c+d)
Cost for 670 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)*0.90/670

day
day
day

0.760
2.000
17.000

673.00
377.00
377.00

511.48
754.00
6409.00

cum

800.000

210.00

168000.00

M-001

Hour

6.000

17103.00

102618.00

P&M-028

Hour
Hour

20.000
20.000

756.00
291.00

15120.00
5820.00
29923.25
32915.57
362071.30
486.36
486.00

P&M-017
P&M-048

say
Note

1. 800 cum of stone boulders are needed to get 600 cum of


stone chips of size 20 and 40 mm.
2. 90% of above cost will be attributed to the production of
670 cum of stone aggregates of 20mm size and balance
10% will be for smaller size aggregates and stone dust
which comes out as a by-product.
3. The integrated stone crusher includes primary and
secondary crushing units.

1.8

Crushing of stone aggregates 40 mm nominal size


Crushing of stone boulders of 150 mm size in an integrated
stone crushing unit of 200 tonnes per hour capacity
comprising of primary and secondary crushing units, belt
conveyor and vibrating screens to obtain stone aggregates
of 40 mm nominal size.
Unit : cum
Taking Output = 750 cum at crusher location.
a) Labour

Page 13 of 394

L-12
L-14
L-13

Mate
Mazdoor Skilled
Mazdoor
b) Material
Stone Boulder of size 150 mm and below
c) Machinery
Integrated stone crusher of 200 TPH including belt
conveyor and vibrating screens
Front end loader 1 cum bucket capacity
Tipper 5.5 cum capacity
d) Overheads @ 0.1 on (a+b+c)
e) Contractors profit @ 0.1 on (a+b+c+d)
Cost for 750 cum = (a+b+c+d+e)x0.85
Rate per cum = (a+b+c+d+e)x0.85/750

day
day
day

0.760
2.000
17.000

673.00
377.00
377.00

511.48
754.00
6409.00

cum

800.000

210.00

168000.00

M-001

Hour

6.000

17103.00

102618.00

P&M-028

Hour
Hour

20.000
20.000

756.00
291.00

15120.00
5820.00
29923.25
32915.57
307760.61
410.35
410.00

P&M-017
P&M-048

say
Note

5.9

510

L-12
L-14
L-13

1. 800 cum of stone boulders are needed to get 600 cum of


stone chips of size 13.2 mm.
2. 85% of above cost will be attributed to the production of
750 cum of stone aggregates of 40mm size and balance
15% will be for smaller size aggregates and stone dust
which comes out as a by-product.
3. The integrated stone crusher includes primary and
secondary crushing units.
Surface Dressing
Providing and laying surface dressing as wearing course in
single coat using crushed stone aggregates of specified size
on a layer of bituminous binder laid on prepared surface and
rolling with 8-10 tonne smooth wheeled steel roller
Unit = sqm
Taking output = 9000 sqm
Case -1:-19 mm nominal chipping size
a) Labour

b)

c)

Mate

day

0.440

673.00

296.12

L-12

Mazdoor

day

9.000

377.00

3393.00

L-13

Mazdoor skilled

day

2.000

408.00

816.00

L-15

Mechanical broom @ 1250 sqm per hour

hour

7.200

334.00

2404.80

P&M-031

Air compressor 250 cfm

hour

7.200

300.00

2160.00

P&M-001

Hydraulic self propelled chip spreader @ 1500 sqm per


hour
Tipper 10 tonne capacity for carriage of stone chips
from stockpile on road side to chip spreader
Front end loader 1 cum bucket capacity

hour

6.000

2472.00

14832.00

P&M-025

hour

6.000

291.00

1746.00

P&M-048

hour

6.000

756.00

4536.00

P&M-017

Bitumen pressure distributor

hour

6.000

1006.00

6036.00

P&M-004

Smooth wheeled roller 8-10 tonne weight

hour

6.000

432.00

2592.00

P&M-044

tonne

10.800

41320.00

446256.00

M-074

cum

135.000

942.00

127170.00

M-053

Machinery

Material
Bitumen@ 1.20 kg per sqm

d)

Crushed stone chipping,19 mm nominal size @ 0.015


cum per sqm
Overheads @ 0.1 on (a+b+c)

e)

Contractors profit @ 0.1 on (a+b+c+d)

Page 14 of 394

61223.79
67346.17

Cost for 9000 sqm= a+b+c+d+e

740807.88

Rate per sqm = (a+b+c+d+e)/9000

82.31
say

82.00

Case - II13 mm nominal size chipping


a) Labour

b)

c)

Mate

day

0.440

673.00

296.12

L-12

Mazdoor

day

9.000

377.00

3393.00

L-13

Mazdoor skilled

day

2.000

408.00

816.00

L-15

Mechanical broom @ 1250 sqm per hour

hour

7.200

334.00

2404.80

P&M-031

Air compressor 250 cfm

hour

7.200

300.00

2160.00

P&M-001

Hydraulic self propelled chip spreader @ 1500 sqm per


hour
Tipper 10 tonne capacity for carriage of stone chips
from stockpile on road side to chip spreader
Front end loader 1 cum bucket capacity

hour

6.000

2472.00

14832.00

P&M-025

hour

6.000

291.00

1746.00

P&M-048

hour

6.000

756.00

4536.00

P&M-017

Bitumen pressure distributor @ 1750 sqm per hour

hour

6.000

1006.00

6036.00

P&M-004

Vibratory roller 8-10 tonne weight

hour

6.000

1446.00

8676.00

P&M-059

tonne

9.000

41320.00

371880.00

M-074

cum

90.000

928.00

83520.00

M-052

Machinery

Material
Bitumen@ 1.00 kg per sqm

d)

Crushed stone chipping,13 mm nominal size @ 0.01


cum per sqm
Overheads @ 0.1 on (a+b+c)

e)

Contractors profit @ 0.1 on (a+b+c+d)

50029.59
55032.55

Cost for 9000 sqm= a+b+c+d+e

605358.06

Rate per sqm = (a+b+c+d+e)/9000

67.26
say

Note

5.15

516

67.00

1.Where the proposed aggregate fails to pass the stripping


test, an approved adhesion agent may be added to the
binder as per clause 510.2.4. Alternatively, chips may be
pre-coated as per clause 510.2.5
2.Input for the second coat, where required, will be the
same as per the Ist coat mentioned above
Slurry Seal
Providing andlaying slurry seal consisting of a mixture of fine
aggregates, portland cement filler, bituminous emulsion
and water on a road surface including cleaning of surface,
mixing of slurry seal in a suitable mobile plant, laying and
compacting to provide even riding surface

Case I

5 mm thickness
Unit = sqm
Taking output = 16000 sqm (80 cum)
Taking density of 2.2 tonnes per cum, weight of mix =
264 tonnes
weight of mix = 176 tonnes
a) Labour

b)

Mate

day

0.240

673.00

161.52

L-12

Mazdoor

day

6.000

377.00

2262.00

L-13

Machinery

Page 15 of 394

c)

Mechanical broom

hour

6.000

334.00

2004.00

P&M-031

Air compressor 250 cfm

hour

6.000

300.00

1800.00

P&M-001

Mobile slurry seal equipment

hour

6.000

945.00

5670.00

P&M-033

Front end loader 1 cum bucket capacity

hour

6.000

756.00

4536.00

P&M-017

Tipper 5.5 cum capacity for carriage of aggregate from


stockpile on road side to slurry equipment,bitumen
emulsion and filler.
Pneumatic tyred roller with individual wheel load not
exceeding 1.5 tonnes
Water tanker6 KL capacity

hour

6.000

291.00

1746.00

P&M-048

hour

6.000

1166.00

6996.00

P&M-037

hour

2.000

233.00

466.00

P&M-060

tonne

19.360

34975.00

677116.00

M-077

cum

102.080

2400.00

244992.00

M-005

tonne

3.520

3200.00

11264.00

M-188

KL

12.000

13.00

156.00

M-189

Material
Residual Binder @ 11 % of mix 80 x 2.2 x 0.11
Fine aggregate 4.75 mm and below 87 % of total
mix,80 x 2.2 x 0.87 = 153.12 tonnes. Taking
density1.5,= 153.12/1.5 = 102.08 cum
Filler @ 2 % of total mix = 80 x 2.2 x 0.02
Cost of water

d)

Overheads @ 0.1 on (a+b+c)

e)

Contractors profit @ 0.1 on (a+b+c+d)

95916.95
105508.65

Cost for 16000 sqm= a+b+c+d+e

1160595.12

Rate per sqm = (a+b+c+d+e)/16000

72.54
say

Case II

73.00

3 mm thickness
Unit = sqm
Taking output = 20000 sqm (60 cum)
a) Labour

b)

c)

Mate

day

0.200

673.00

134.60

L-12

Mazdoor

day

5.000

377.00

1885.00

L-13

Mechanical broom

hour

6.000

334.00

2004.00

P&M-031

Air compressor 250 cfm

hour

6.000

300.00

1800.00

P&M-001

Mobile slurry seal equipment

hour

6.000

945.00

5670.00

P&M-033

Front end loader 1 cum bucket capacity

hour

6.000

756.00

4536.00

P&M-017

Tipper 5.5 cum capacity for carriage of aggregate from


stockpile on road side to slurry equipment,bitumen
emulsion and filler
Water tanker6 KL capacity

hour

6.000

291.00

1746.00

P&M-048

hour

2.000

233.00

466.00

P&M-060

tonne

17.160

34975.00

600171.00

M-077

cum

74.800

2400.00

179520.00

M-005

tonne

2.640

3200.00

8448.00

M-188

KL

12.000

13.00

156.00

M-189

Machinery

Material
Residual Binder @ 13 % of mix = 60 x 2.2 x 0.13
Fine aggregate 3 mm and below 85 % of total mix, 60x
2.2 x 0.85 = 112.2 tonnes. Taking density 1.5,
Filler @ 2 % of total mix =60x 2.2 x 0.02
Cost of water

d)

Overheads @ 0.1 on (a+b+c)

80653.66

e)

Contractors profit @ 0.1 on (a+b+c+d)

88719.03

Cost for 30000 sqm= a+b+c+d+e

975909.29

Rate per sqm = (a+b+c+d+e)/20000

48.80
say

Page 16 of 394

49.00

Case III

1.5 mm thickness
Unit = sqm
Taking output = 24000 sqm (36 cum)
a) Labour

b)

c)

Mate

day

0.200

673.00

134.60

L-12

Mazdoor

day

5.000

377.00

1885.00

L-13

Mechanical broom

hour

6.000

334.00

2004.00

P&M-031

Air compressor 250 cfm

hour

6.000

300.00

1800.00

P&M-001

Mobile slurry seal equipment

hour

6.000

945.00

5670.00

P&M-033

Front end loader 1 cum bucket capacity

hour

6.000

756.00

4536.00

P&M-017

Tipper 5.5 cum capacity for carriage of aggregate from


stockpile on road side to slurry equipment,bitumen
emulsion and filler.
Water tanker6 KL capacity

hour

6.000

291.00

1746.00

P&M-048

hour

2.000

233.00

466.00

P&M-060

tonne

12.670

34975.00

443133.25

M-077

cum

43.300

137.00

5932.10

M-022

tonne

1.580

3200.00

5056.00

M-188

KL

12.000

13.00

156.00

M-189

Machinery

Material
Residual Binder @ 16 % of mix, 36 x 2.2 x 0.16
Fine aggregate 2.36 mm and below,82 % of total
mix,36x 2.2 x 0.82 = 64.94 tonnes. Taking density 1.5
Filler @ 2 % of total mix = 36x 2.2 x 0.02
Cost of water

d)

Overheads @ 0.1 on (a+b+c)

47251.90

e)

Contractors profit @ 0.1 on (a+b+c+d)

51977.08

Cost for 24000 sqm= a+b+c+d+e

571747.93

Rate per sqm = (a+b+c+d+e)/24000

23.82
say

5.17

Note

1.Tack coat, if required to be provided, before laying slurry


seal may be measured and paid separately

518

Fog Spray

24.00

Providing and applying low viscosity bitumen emulsion for


sealing cracks less than 3 mm wide or incipient fretting or
disintegration in an existing bituminous surfacing.
Unit = sqm
Taking output = 10500 sqm
a) Labour

b)

c)

Mate

day

0.120

673.00

80.76

L-12

Mazdoor

day

3.000

377.00

1131.00

L-13

Mechanical broom @ 1250 sqm per hour

hour

6.000

334.00

2004.00

P&M-031

Air compressor 250 cfm

hour

6.000

300.00

1800.00

P&M-001

Bitumen emulsion pressure distributor @ 1750 sqm per


hour
Material

tonne

6.000

1006.00

6036.00

P&M-004

Bitumenemulsion @ 0.75 kg per sqm

tonne

7.880

34975.00

275603.00

Machinery

d)

Overheads @ 0.1 on (a+b+c)

28665.48

e)

Contractors profit @ 0.1 on (a+b+c+d)

31532.02

Page 17 of 394

M-077

Cost for 10500 sqm= a+b+c+d+e

346852.26

Rate per sqm = (a+b+c+d+e)/10500

33.03
say

33.00

1.In case it is decided by the engineer to blind the fog spray,


the following may be added
a) Labour

c)

Mate

day

0.160

673.00

107.68

L-12

Mazdoor for precoating of grit

day

4.000

377.00

1508.00

L-13

cum

26.250

137.00

3596.25

M-024

tonne

0.790

34975.00

27630.25

M-077

Material
Crushed stone grit 3 mm size @ 3.75 kg per sqm
Bitumenemulsion for precoating grit @ 2 % of
grit,39.38 x 0.02

32842.18
3.13
say
5.21

522
Case - I

3.00

Crack Prevention Courses


Stress Absorbing Membrane (SAM) crack width less
than 6 mm
Providing and laying of a stress absorbing membrane over a
cracked road surface, with crack width below 6 mm after
cleaning with a mechanical broom, using modified binder
complying with clause 521, sprayed at the rate of 9 kg per
10 sqm and spreading 5.6 mm crushed stone aggregates @
0.11 cum per 10 sqm with hydraulic chip spreader,
sweeping the surface for uniform spread of aggregates and
surface finished to conform to clause 902.
Unit = sqm
Taking output = 10500 sqm
a) Labour

b)

c)

Mate

day

0.240

673.00

161.52

L-12

Mazdoor

day

6.000

377.00

2262.00

L-13

Mechanical broom @ 1250 sqm per hour

hour

6.000

334.00

2004.00

P&M-031

Air compressor 250 cfm

hour

6.000

300.00

1800.00

P&M-001

Bitumen pressure distributor @ 1750 sqm per hour

hour

6.000

1006.00

6036.00

P&M-004

Hydraulic Chip spreader

hour

6.000

2472.00

14832.00

P&M-025

Smooth wheeled road roller 8-10 tonne

hour

6.000

432.00

2592.00

P&M-044

tonne

9.450

42677.00

403297.65

M-078

cum

105.000

700.00

73500.00

M-050

Machinery

Material
Modified binder
Crushed stone aggregates 5.6 mm size

d)

Overheads @ 0.1 on (a+b+c)

50648.52

e)

Contractors profit @ 0.1 on (a+b+c+d)

55713.37

Cost for 10500 sqm= a+b+c+d+e

612847.06

Rate per sqm = (a+b+c+d+e)/10500

58.37
say

Page 18 of 394

58.00

Case - II

Stress Absorbing Membrane (SAM) with crack width 6


mm to 9 mm
Providing and laying of a stress absorbing membrane over a
cracked road surface, with crack width 6 to 9 mm after
cleaning with a mechanical broom, using modified binder
complying with clause 521, sprayed at the rate of 11 kg per
10 sqm and spreading 11.2 mm crushed stone aggregates
@ 0.12 cum per 10 sqm, sweeping the surface for uniform
spread of aggregates and surface finished to conform to
clause 902.
Unit = sqm
Taking output = 10500 sqm
a) Labour

b)

c)

Mate

day

0.240

673.00

161.52

L-12

Mazdoor

day

6.000

377.00

2262.00

L-13

Mechanical broom @ 1250 sqm per hour

hour

6.000

334.00

2004.00

P&M-031

Air compressor 250 cfem capacity

hour

6.000

300.00

1800.00

P&M-001

Bitumen pressure distributor @ 1750 sqm per hour

hour

6.000

1006.00

6036.00

P&M-004

Hydraulic Chip spreader

hour

6.000

2472.00

14832.00

P&M-025

Smooth wheeled road roller 8-10 tonne

hour

6.000

432.00

2592.00

P&M-044

tonne

11.550

42677.00

492919.35

M-078

cum

105.000

1063.00

111615.00

M-051

Machinery

Material
Modified binder
Crushed stone chipping 11.2 mm size

d)

Overheads @ 0.1 on (a+b+c)

63422.19

e)

Contractors profit @ 0.1 on (a+b+c+d)

69764.41

Cost for 10500 sqm= a+b+c+d+e

767408.46

Rate per sqm = (a+b+c+d+e)/10500

73.09
say

Case III

73.00

Stress Absorbing Membrane (SAM) crack width above 9


mm and cracked area above 50 %
Providing and laying a single coatn of a stress absorbing
membrane over a cracked road surface, with crack width
above 9 mm and cracked area above 50 % after cleaning
with a mechanical broom, using modified binder complying
with clause 521, sprayed at the rate of 15 kg per 10 sqm
and spreading 11.2 mm crushed stone aggregates @ 0.12
cum per 10 sqm, sweeping the surface for uniform spread
of aggregates and surface finished to conform to clause 902.
Unit = sqm
Taking output = 10500 sqm
a) Labour

b)

Mate

day

0.240

673.00

161.52

L-12

Mazdoor

day

6.000

377.00

2262.00

L-13

Mazdoor skilled

day

2.000

408.00

816.00

L-15

Mechanical broom @ 1250 sqm per hour

hour

6.000

334.00

2004.00

P&M-031

Air compressor 250 cfem capacity

hour

6.000

300.00

1800.00

P&M-001

Machinery

Page 19 of 394

c)

Bitumen pressure distributor @ 1750 sqm per hour

hour

6.000

1006.00

6036.00

P&M-004

Hydraulic Chip spreader

hour

6.000

2472.00

14832.00

P&M-025

Smooth wheeled road roller 8-10 tonne

hour

6.000

432.00

2592.00

P&M-044

tonne

15.750

42677.00

672162.75

M-078

cum

126.000

1063.00

133938.00

M-051

Material
Modified binder
Crushed stone aggregates 11.2 mm size

d)

Overheads @ 0.1 on (a+b+c)

83660.43

e)

Contractors profit @ 0.1 on (a+b+c+d)

92026.47

Cost for 10500 sqm= a+b+c+d+e

1012291.17

Rate per sqm = (a+b+c+d+e)/10500

96.41
say

Case IV

96.00

Case - IV : Bitumen Impregnated Geotextile


Providing and laying a bitumen impregnated geotextile layer
after cleaning the road surface, geotextile conforming to
requirements of clause 704.3, laid over a tack coat with 1.05
kg per sqm of paving grade bitumen 80 - 100 penetration
and constructed to the requirement of clause 704.4.5
Unit = sqm
Taking output = 3500 sqm
a) Labour

b)

Mate

day

0.560

673.00

376.88

L-12

Mazdoor

day

12.000

377.00

4524.00

L-13

Mazdoor skilled

day

2.000

408.00

816.00

L-15

Mechanical broom @ 1250 sqm per hour

hour

2.800

334.00

935.20

P&M-031

Air compressor 250 cfem capacity

hour

2.800

300.00

840.00

P&M-001

tonne

2.000

1006.00

2012.00

P&M-004

hour

2.000

1166.00

2332.00

P&M-037

tonne

3.680

40367.00

148550.56

M-075

sqm

3850.000

79.00

304150.00

M-108

Machinery

Bitumen pressure distributor @ 1750 sqm per hour


Pneumatic roller
c)

Material
Paving grade bitumen of 80 - 100 penetration @ 1.05
kg per sqm
Geotextile including 10 % for overlaps

d)

Overheads @ 0.1 on (a+b+c)

46453.66

e)

Contractors profit @ 0.1 on (a+b+c+d)

51099.03

Cost for 10500 sqm= a+b+c+d+e

562089.33

Rate per sqm = (a+b+c+d+e)/3500

160.60
say

NOTE

8.3

801

As bitumen overlay construction shallfollow closely the fabric


placement on the same day, an output of 3500 sqm only
has been considered for the analysis which will cover a
length of 500 m, of 7 m widecarriagway. This can be
conveniently overlaid by a bitumenious course in a day
Printing new letter and figures of any shade
Printing new letter and figures of any shade with synthetic
enamel paint black or any other approved colour to give an
even shade
ii) English and Roman

Page 20 of 394

161.00

Hyphens and the like not to be measured and paid for


Detail for 100 letters of 16 cm height. i.e.1600 cm
Unit = per cm height per letter
a) Labour
Mate

day

0.07

673

47.11

Painter Ist class

day

1.25

396

495.00

Mazdoor

day

0.50

377

188.50

Litre

0.50

211

105.50

b) Material
Paint
c) Overheads @ 0.1 on (a+b)

83.61

d) Contractors profit @ 0.1 on (a+b+c)

91.97

Cost for 1600 cm = a+b+c+d

1011.69

Rate per cm height per letter = (a+b+c +d)/1600


8.8

803

0.63
say

0.60

Painting Two Coats on New Concrete Surfaces


Painting two coats after filling the surface with synthetic
enamel paint in all shades on new plastered concrete
surfaces
Unit = sqm
Taking output = 40 sqm
a) Labour
Mate

day

0.12

673

80.76

Painter

day

2.00

396

792.00

Mazdoor

day

1.00

377

377.00

Litre

6.00

211

1266.00

b) Material
Paint conforming to requirement of clause 803.3.
Add for scaffolding @ 1% of labour cost where required

12.66

c) Overheads @ 0.1 on (a+b)

252.84

d) Contractors profit @ 0.1 on (a+b+c)

278.13

Cost for 40 sqm = a+b+c+d

3059.39

Rate per sqm = (a+b+c+d)/40


8.9

803

76.48
say

76.00

Painting on Steel Surfaces


Providing and applying two coats of ready mix paint of
approved brand on steel surface after through cleaning of
surface to give an even shade
Unit = sqm
Taking output = 10 sqm
a) Labour
Mate

day

0.03

673

20.19

Painter

day

0.45

396

178.20

Mazdoor

day

0.25

377

94.25

Litre

1.25

211

263.75

b) Material
Paint ready mixed approved brand.
Add @ 1% on cost of material for scaffolding
c) Overheads @ 0.1 on (a+b)

2.64
55.90

Page 21 of 394

d) Contractors profit @ 0.1 on (a+b+c)

61.49

Cost for 10 sqm = a+b+c+d

676.42

Rate per sqm = (a+b+c+d)/10


12.6

67.64

SubCement mortar1:3 (1cement :3 sand)


analysis
(A)
Unit = 1 cum
Taking output = 1 cum
a) Materials
Cement
Sand
b) Labour
Mate
Mazdoor
Total Material and Labour = (a+b)
SubCement mortar1:2 (1cement :2 sand)
analysis
(B)
Unit = 1 cum
Taking output = 1 cum
a) Materials
Cement
Sand
b) Labour
Mate
Mazdoor
Total Material and Labour = (a+b)

12.7

Cement mortar1:6 (1cement :6 sand)


Subanalysis
(D)
Unit = 1 cum
Taking output = 1 cum
a) Materials
Cement
Sand
b) Labour
Mate
Mazdoor
Total Material and Labour = (a+b)
1400
Stone masonry work in cement mortar 1:3 in foundation
complete as drawing and Technical Specification

(A)

say

68.00

MT
cum

0.51
1.05

5940.00
2400.00

3029.40
2520.00

day
day

0.04
0.90

673.00
377.00

26.92
339.30
5916.00

MT
cum

0.67
0.93

5940.00
2400.00

3991.68
2240.00

day
day

0.04
0.90

673.00
377.00

26.92
339.30
6598.00

MT
cum

0.29
1.20

5940.00
2400.00

1710.72
2880.00

day
day

0.04
0.90

673.00
377.00

26.92
339.30
4957.00

cum
each

5.50
35.00

753.00
14.00

4141.50
490.00

M-169
M-182

cum

1.50

5916.00

8874.00

Item 12.6
(A)

Unit = cum
Taking output = 5 cum
Square Rubble Coursed Rubble Masonry (first sort)
a)

Material
Stone
Through and bond stone
(35no.x0.24mx0.24mx0.39m = 0.79 cu.m)
Cement mortar 1:3 (Rate as in Item 12.6 A subanalysis)

Page 22 of 394

b)

Labour
Mate
Mason
Mazdoor
c) Overhead charges @ 0.2 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Cost for 5 cum = a+b+c+d
Rate per cum (a+b+c+d)/5
1405.3

12.7 (Add)

1400

1405.3

B) Random Rubble Masonry


( coursed/uncoursed )
Unit = cum
Taking output = 5 cum
a) Material
Stone
Through and bond stone
(35nos.x0.24mx0.24mx0.39m = 0.79 cu.m)
Cement mortar 1:3 (Rate as in item 12.6 A)
b) Labour
Mate
Mason
Mazdoor
c) Overheads @ 0.2 on (a+b)
d) Contractors profit @ 0.1 on (a+b+c)
Cost for 5 cum = a+b+c+d
Rate per cum (a+b+c+d)/5

day
day
day

0.66
7.50
9.00

673.00
500.00
377.00

say

444.18
3750.00
3393.00
4218.54
2531.12
27842.34
5568.47
5568.00

cum
Nos

5.50
35.00

391.00
14.00

2150.50
490.00

cum

1.55

5916.00

9169.80

day
day
day

0.62
6.00
9.00

673.00
500.00
377.00

say

417.26
3000.00
3393.00
3724.11
2234.47
24579.14
4915.83
4916.00

The labour already considered in cement mortar has been


taken into account while proposing labour for masonry
works.
Stone masonry work in cement mortar 1:6 in foundation
complete as drawing and Technical Specification
Unit = cum
Taking output = 5 cum
B) Random Rubble Masonry
( coursed/uncoursed )
Unit = cum
Taking output = 5 cum
a) Material
Stone
Through and bond stone
(35nos.x0.24mx0.24mx0.39m = 0.79 cu.m)
Cement mortar 1:3 (Rate as in item 13.6 D)
b) Labour
Mate
Mason
Mazdoor
c) Overheads @ 0.2 on (a+b)
d) Contractors profit @ 0.1 on (a+b+c)
Cost for 5 cum = a+b+c+d
Rate per cum (a+b+c+d)/5

cum
Nos

5.50
35.00

391.00
14.00

2150.50
490.00

cum

1.55

4957.00

7683.35

day
day
day

0.62
6.00
9.00

673.00
500.00
377.00

417.26
3000.00
3393.00
3426.82
2056.09
22617.03
4523.41
4523.00

say
@

The labour already considered in cement mortar has been


taken into account while proposing labour for masonry
works.

Page 23 of 394

L-12
L-11
L-13

12.8

1500, 1700 Plain/Reinforced cement concrete in open foundation


& 2100 complete as per drawing and technical specifications
A

PCC Grade M15


Unit = cum
Taking output = 15 cum
a) Material
Cement
Coarse sand
40 mm Aggregate
20 mm Aggregate
10 mm Aggregate
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum)
Generator 63 KVA
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)
d) Formwork @ 4% on cost of concrete i.e.cost of material,
labour and machinery
e) Overheads @ 0.2 on (a+b+c+d)
f) Contractors profit @ 0.1 on (a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f
Rate per cum (a+b+c+d+e+f)/15

4.13
6.75
8.10
4.05
1.35

5940.00
2400.00
659.00
942.00
1063.00

24532.20
16200.00
5337.90
3815.10
1435.05

day
day
day

0.86
1.50
20.00

673.00
500.00
377.00

578.78
750.00
7540.00

hour
hour

6.00
6.00
4,240.00

218.00
349.00

1308.00
2094.00
2543.64

say

13226.93
7936.16
87297.77
5819.85
5820.00

Note

12.8

12.8

Nedle Vibrator is an item of minor T & P which is already


included in overhead charges. Hence not added in rate
analysis of cement concrete works.
B
PCC Grade M20
Unit : cum
Taking output = 15 cum
a) Material
Cement
Coarse sand
40 mm Aggregate
20 mm Aggregate
10 mm Aggregate
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum)
Generator 33 KVA
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)
C
RCC Grade M20
Unit = cum
Case I Using concrete mixer
Taking output = 15 cum
a) Material
Cement
Coarse sand
20 mm Aggregate

MT
cum
cum
cum
cum

Page 24 of 394

MT
cum
cum
cum
cum

5.16
6.75
5.40
5.40
2.70

5940.00
2400.00
659.00
942.00
1063.00

30650.40
16200.00
3558.60
5086.80
2870.10

day
day
day

0.86
1.50
20.00

673.00
500.00
377.00

578.78
750.00
7540.00

hour
hour

6.00
6.00
4,710.00

218.00
349.00

1308.00
2094.00

MT
cum
cum

5.21
6.75
8.10

5940.00
2400.00
942.00

30947.40
16200.00
7630.20

10 mm Aggregate
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum)
Generator 33 KVA
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)
Case II With Batching Plant, Transit Mixer and Conrete Pump
Unit : cum
Taking Output = 120 cum
a) Material
Cement
Coarse Sand
20 mm Aggregate
10 mm Aggregate
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader 1 cum capacity
Transit Mixer 4 cum capacity for lead upto 1 km.
Lead beyond 1 km, L-lead in km
Concrete Pump
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)
d) Formwork @ 4% on cost of concrete i.e.cost of material,
labour and machinery
e) Overheads @ 0.2 on (a+b+c+d)
f) Contractors profit @ 0.1 on (a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f
Rate per cum = ( a+b+c+d+e+f )/120
12.8

PCC Grade M25


Unit = cum
Case I Using concrete Mixer
Taking output = 15 cum
a) Material
Cement
Coarse sand
40 mm Aggregate
20 mm Aggregate
10 mm Aggregate
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum)
Generator 33 KVA
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)

cum

5.40

1063.00

5740.20

day
day
day

0.86
1.50
20.00

673.00
500.00
377.00

578.78
750.00
7540.00

hour
hour

6.00
6.00
4,853.00

218.00
349.00

1308.00
2094.00

MT
cum
cum
cum

41.66
54.00
64.80
43.20

5940.00
2400.00
942.00
1063.00

247460.40
129600.00
61041.60
45921.60

day
day
day

0.84
3.00
18.00

673.00
500.00
377.00

565.32
1500.00
6786.00

hour
hour
hour
hour
T-km
hour

6.00
6.00
6.00
15.00
300L
6
#VALUE!

2094.00
654.00
756.00
873.00
input
240.00

12564.00
3924.00
4536.00
13095.00
#VALUE! L= 1
1440.00
#VALUE!

say

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

Page 25 of 394

MT
cum
cum
cum
cum

5.99
6.75
5.40
5.40
2.70

5940.00
2400.00
659.00
942.00
1063.00

35580.60
16200.00
3558.60
5086.80
2870.10

day
day
day

0.86
1.50
20.00

673.00
500.00
377.00

578.78
750.00
7540.00

hour
hour

6.00
6.00
5,038.00

218.00
349.00

1308.00
2094.00

Case II

With Batching Plant, Transit Mixer and Conrete Pump

Unit : cum
Taking Output = 120 cum
a) Material
Cement
Coarse sand
40 mm Aggregate
20 mm Aggregate
10 mm Aggregate
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader 1 cum capacity
Transit Mixer 4 cum capacity for lead upto 1 km.
Transit Mixer 4 cum capacity lead beyond
1 Km, L - lead in Kilometer
Concrete Pump
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)
d) Formwork @ 3.75% of cost of concrete i.e.cost of
material, labour and machinery
e) Overheads @ 0.2 on (a+b+c+d)
f) Contractors profit @ 0.1 on (a+b+c+d+e)
cost of 120 cum = a+b+c+d+e+f
Rate per cum (a+b+c+d+e+f)/120
12.8

RCC Grade M25


Unit = cum
Case I Using concrete Mixer
Taking output = 15 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum)
Generator 33 KVA
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)
Case II With Batching Plant, Transit Mixer and Conrete Pump

MT
cum
cum
cum
cum

47.95
54.00
43.20
43.20
21.60

5940.00
2400.00
659.00
942.00
1063.00

284823.00
129600.00
28468.80
40694.40
22960.80

day
day
day

0.84
3.00
18.00

673.00
500.00
377.00

565.32
1500.00
6786.00

hour
hour
hour
hour
T-Km

6.00
6.00
6.00
15.00
300L

2094.00
654.00
756.00
873.00
input

hour

6
#VALUE!

240.00

12564.00
3924.00
4536.00
13095.00
#VALUE! L= 1
1440.00
#VALUE!

say

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

Unit : cum
Taking Output = 120 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate

Page 26 of 394

MT
cum
cum
cum

6.05
6.75
8.10
5.40

5940.00
2400.00
942.00
1063.00

35937.00
16200.00
7630.20
5740.20

day
day
day

0.86
1.50
20.00

673.00
500.00
377.00

578.78
750.00
7540.00

hour
hour

6.00
6.00
5,186.00

218.00
349.00

1308.00
2094.00

MT
cum
cum
cum

48.38
54.00
64.80
43.20

5940.00
2400.00
942.00
1063.00

287377.20
129600.00
61041.60
45921.60

12.8

12.8

Admixer
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader 1 cum capacity 1 cum
Transit Mixer 4 cum capacity for lead upto 1 km.
Transit Mixer 4 cum capacity lead beyond
1 Km, L - lead in Kilometer
Concrete Pump
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)
F
PCC Grade M30
Unit = cum
Case I Using Concrete Mixer
Taking output = 15 cum
a) Material
Cement
Coarse sand
40 mm Aggregate
20 mm Aggregate
10 mm Aggregate
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum)
Generator 33 KVA
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)
Case II Using Batching Plant, Transit Mixer and Conrete Pump
Unit : cum
Taking Output = 120 cum
a) Material
Cement
Coarse sand
40 mm Aggregate
20 mm Aggregate
10 mm Aggregate
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader 1 cum capacity
Transit Mixer 4 cum capacity for lead upto 1 km.
Transit Mixer 4 cum capacity lead beyond
1 Km, L - lead in Kilometer
Concrete Pump
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)
G
RCC Grade M30

Page 27 of 394

Kg

193.52

input

#VALUE!

day
day
day

0.84
3.00
18.00

673.00
500.00
377.00

565.32
1500.00
6786.00

hour
hour
hour
hour
T-Km

6.00
6.00
6.00
15.00
300L

2094.00
654.00
756.00
873.00
input

hour

6.00
#VALUE!

240.00

1440.00

MT
cum
cum
cum
cum

6.08
6.75
5.40
5.40
2.70

5940.00
2400.00
659.00
942.00
1063.00

36115.20
16200.00
3558.60
5086.80
2870.10

day
day
day

0.86
1.50
20.00

673.00
500.00
377.00

578.78
750.00
7540.00

hour
hour

6.00
6.00
5,074.00

218.00
349.00

1308.00
2094.00

MT
cum
cum
cum
cum

48.60
54.00
43.20
43.20
21.60

5940.00
2400.00
659.00
942.00
1063.00

288684.00
129600.00
28468.80
40694.40
22960.80

day
day
day

0.84
3.00
18.00

673.00
500.00
377.00

565.32
1500.00
6786.00

hour
hour
hour
hour
T-Km

6.00
6.00
6.00
15.00
300L

2094.00
654.00
756.00
873.00
input

hour

6.00
#VALUE!

240.00

12564.00
3924.00
4536.00
13095.00
#VALUE! L= 1

12564.00
3924.00
4536.00
13095.00
#VALUE! L= 1
1440.00

Case I

Using Concrete Mixer


Unit = cum
Taking output = 15 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum)
Generator 33 KVA
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)
Case II
Using Batching Plant, Transit Mixer and Conrete Pump

12.8

Unit = cum
Taking output = 120 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader 1 cum capacity
Transit Mixer 4 cum capacity for lead upto 1 km.
Transit Mixer 4 cum capacity lead beyond
1 Km, L - lead in Kilometer
Concrete Pump
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)
H
RCC Grade M35
Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum)
Generator 33 KVA
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)

Page 28 of 394

MT
cum
cum
cum

6.10
6.75
8.10
5.40

5940.00
2400.00
942.00
1063.00

36234.00
16200.00
7630.20
5740.20

day
day
day

0.86
1.50
20.00

673.00
500.00
377.00

578.78
750.00
7540.00

hour
hour

6.00
6.00
5,206.00

218.00
349.00

1308.00
2094.00

MT
cum
cum
cum

48.80
54.00
64.80
43.20

5940.00
2400.00
942.00
1063.00

289872.00
129600.00
61041.60
45921.60

day
day
day

0.84
3.00
18.00

673.00
500.00
377.00

565.32
1500.00
6786.00

hour
hour
hour
hour
T-Km

6.00
6.00
6.00
15.00
300L

2094.00
654.00
756.00
873.00
input

hour

6.00
#VALUE!

240.00

1440.00

MT
cum
cum
cum

6.33
6.75
8.10
5.40

5940.00
2400.00
942.00
1063.00

37600.20
16200.00
7630.20
5740.20

day
day
day

0.86
1.50
20.00

673.00
500.00
377.00

578.78
750.00
7540.00

hour
hour

6.00
6.00
5,297.00

218.00
349.00

1308.00
2094.00

12564.00
3924.00
4536.00
13095.00
#VALUE! L= 1

Case II

Using Batching Plant, Transit Mixer and Conrete Pump

Unit ; cum
Taking Output = 120 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
Admixer
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader 1 cum capacity
Transit Mixer 4 cum capacity for lead upto 1 km.
Transit Mixer 4 cum capacity lead beyond
1 Km, L - lead in Kilometer
Concrete Pump
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)
d) Formwork @ 3% on cost of concrete i.e.cost of material,
labour and machinery
e) Overheads @ 0.2 on (a+b+c+d)
f) Contractors profit @ 0.1 on (a+b+c+d+e)
cost of 120 cum = a+b+c+d+e+f
Rate per cum (a+b+c+d+e+f)/120

MT
cum
cum
cum
Kg

50.64
54.00
64.80
43.20
202.56

5940.00
2400.00
942.00
1063.00
input

300801.60
129600.00
61041.60
45921.60
#VALUE!

day
day
day

0.84
3.00
18.00

673.00
500.00
377.00

565.32
1500.00
6786.00

hour
hour
hour
hour
T-Km

6.00
6.00
6.00
15.00
300L

2094.00
654.00
756.00
873.00
input

hour

6.00
#VALUE!

240.00

12.11

1440.00
#VALUE!

say
Note:

12564.00
3924.00
4536.00
13095.00
#VALUE! L= 1

Rate per cum (a+b+c+d)/120 Excluding OH & CP


Where ever concrete is carried out using batching plant,
transit mixer, concrete pump, admixers @ 0.4% of weight of
cement may be added for achieving desired slump of
concrete.

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

1200, 1500 Plain/Reinforced cement concrete, in well foundation


& 1700 complete as per drawing and technical specification

C
Case I
(i)

Bottom Plug
Concrete to be placed using tremie pipe
Using Concrete Mixer
PCC Grade M20
Unit = cum
Taking output = 15 cum
a) Material
Cement
Coarse sand
40 mm Aggregate
20 mm Aggregate
10 mm Aggregate
Admixer
b) Labour
Mate
Mason

Page 29 of 394

MT
cum
cum
cum
cum
Kg

5.55
6.75
5.40
5.40
2.70
18.60

5940.00
2400.00
659.00
942.00
1063.00
input

32967.00
16200.00
3558.60
5086.80
2870.10
#VALUE!

day
day

0.90
1.50

673.00
500.00

605.70
750.00

Mazdoor
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum)
Generator 33 KVA
Light Crane 3 tonnes capacity for handling tremie pipe
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)
10% extra cement may be added where under water
concreting is involved.
Case II Using Batching Plant, Transit Mixer and Crane/concrete
pump
Unit ; cum
Taking Output = 120 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
Admixer
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader 1 cum capacity
Transit Mixer 4 cum capacity for lead upto 1 km.
Transit Mixer 4 cum capacity, lead beyond 1 Km, L lead in Kilometer
Concrete Pump
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)

day

20.00

377.00

7540.00

hour
hour
hour

6.00
6.00
6.00

218.00
349.00
334.00

1308.00
2094.00
2004.00

#VALUE!

Note

(ii)

MT
cum
cum
cum
Kg

44.40
54.00
64.80
43.20
148.80

5940.00
2400.00
942.00
1063.00
input

263736.00
129600.00
61041.60
45921.60
#VALUE!

day
day
day

0.88
3.00
18.00

673.00
500.00
377.00

592.24
1500.00
6786.00

hour
hour
hour
hour
T-Km

6.00
6.00
6.00
15.00
300L

2094.00
654.00
756.00
873.00
input

hour

6.00
#VALUE!

240.00

1440.00

MT
cum
cum
cum
cum
Kg

5.99
6.75
5.40
5.40
2.70
21.60

5940.00
2400.00
659.00
942.00
1063.00
input

35580.60
16200.00
3558.60
5086.80
2870.10
#VALUE!

day
day
day

0.90
1.50
20.00

673.00
500.00
377.00

605.70
750.00
7540.00

hour
hour
hour

6.00
6.00
6.00

218.00
349.00
334.00

1308.00
2094.00
2004.00

12564.00
3924.00
4536.00
13095.00
#VALUE! L= 1

PCC Grade M25

Case I

Using Concrete Mixer


Unit = cum
Taking output = 15 cum
a) Material
Cement
Coarse sand
40 mm Aggregate
20 mm Aggregate
10 mm Aggregate
Admixer
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum)
Generator 33 KVA
Light Crane of 3 tonnes capacity for handling tremie
pipe
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)

Page 30 of 394

#VALUE!

Case II

Using Batching Plant, Transit Mixer and Crane/concrete


pump
Unit = cum
Taking output = 120 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
Admixer
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader 1 cum capacity
Transit Mixer 4 cum capacity for lead upto 1 km.
Transit Mixer 4 cum capacity, lead beyond 1 Km, L lead in Kilometer
Concrete Pump
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)

PCC Grade M30


Using Concrete Mixer
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement
Coarse sand
40 mm Aggregate
20 mm Aggregate
10 mm Aggregate
Admixer
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum)
Generator 33 KVA
Light Crane of 3 tonnes capacity for handling tremie
pipe
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)
Case II Using Batching Plant, Transit Mixer and Crane/concrete
pump
Unit = cum
Taking output = 120 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
Admixer
b) Labour

MT
cum
cum
cum
Kg

47.88
54.00
64.80
43.20
172.80

5940.00
2400.00
942.00
1063.00
input

284407.20
129600.00
61041.60
45921.60
#VALUE!

day
day
day

0.88
3.00
18.00

673.00
500.00
377.00

592.24
1500.00
6786.00

hour
hour
hour
hour
T-Km

6.00
6.00
6.00
15.00
300L

2094.00
654.00
756.00
873.00
input

hour

6.00
#VALUE!

240.00

1440.00

MT
cum
cum
cum
cum
Kg

6.08
6.75
5.40
5.40
2.70
21.60

5940.00
2400.00
659.00
942.00
1063.00
input

36115.20
16200.00
3558.60
5086.80
2870.10
#VALUE!

day
day
day

0.90
1.50
20.00

673.00
500.00
377.00

605.70
750.00
7540.00

hour
hour
hour

6.00
6.00
6.00

218.00
349.00
334.00

1308.00
2094.00
2004.00

5940.00
2400.00
942.00
1063.00
input

288921.60
129600.00
61041.60
45921.60
#VALUE!

12564.00
3924.00
4536.00
13095.00
#VALUE! L= 1

(iii)
Case I

Page 31 of 394

#VALUE!

MT
cum
cum
cum
Kg

48.64
54.00
64.80
43.20
172.80

Mate
Mason
Mazdoor
c) Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader 1 cum capacity
Transit Mixer 4 cum capacity for lead upto 1 km.
Transit Mixer 4 cum capacity, lead beyond 1 Km, L lead in Kilometer
Concrete Pump
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)
(iv)
PCC Grade M35
Using Concrete Mixer
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement
Coarse sand
40 mm Aggregate
20 mm Aggregate
10 mm Aggregate
Admixer
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum)
Generator 33 KVA
Light Crane of 3 tonnes capacity for handling tremie
pipe
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)
Case II Using Batching Plant, Transit Mixer and Crane/concrete
pump
Unit = cum
Taking output = 120 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
Admixer
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader 1 cum capacity
Transit Mixer 4 cum capacity for lead upto 1 km.
Transit Mixer 4 cum capacity, lead beyond 1 Km, L lead in Kilometer
Concrete Pump

day
day
day

0.88
3.00
18.00

673.00
500.00
377.00

592.24
1500.00
6786.00

hour
hour
hour
hour
T-Km

6.00
6.00
6.00
15.00
300L

2094.00
654.00
756.00
873.00
input

hour

6.00
#VALUE!

240.00

1440.00

MT
cum
cum
cum
cum
Kg

6.29
6.75
5.40
5.40
2.70
21.60

5940.00
2400.00
659.00
942.00
1063.00
input

37362.60
16200.00
3558.60
5086.80
2870.10
#VALUE!

day
day
day

0.90
1.50
20.00

673.00
500.00
377.00

605.70
750.00
7540.00

hour
hour
hour

6.00
6.00
6.00

218.00
349.00
334.00

1308.00
2094.00
2004.00

12564.00
3924.00
4536.00
13095.00
#VALUE! L= 1

Case I

Page 32 of 394

#VALUE!

MT
cum
cum
cum
Kg

50.28
54.00
64.80
43.20
172.80

5940.00
2400.00
942.00
1063.00
input

298663.20
129600.00
61041.60
45921.60
#VALUE!

day
day
day

0.88
3.00
18.00

673.00
500.00
377.00

592.24
1500.00
6786.00

hour
hour
hour
hour
T-Km

6.00
6.00
6.00
15.00
300L

2094.00
654.00
756.00
873.00
input

hour

6.00

240.00

12564.00
3924.00
4536.00
13095.00
#VALUE! L= 1
1440.00

Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)


Add 5% of cost of material and labour towards cost of
forming sump, protective bunds, chiselling and making
arrangements for under water concreteing with tremie pipe..

#VALUE!
#VALUE!

d) Overheads @ 0.2 on (a+b+c)


e) Contractors profit @ 0.1 on (a+b+c+d)
cost of 120 cum = a+b+c+d+e
Rate per cum (a+b+c+d+e)/120
F
iv)
Case II

Say

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

Well cap
RCC Grade M35
Using Batching Plant, Transit Mixer and Conrete Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader(capacity 1 cum)
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity for lead upto 1 km.
Lead beyond 1 Km, L - lead in Kilometer
Concrete Pump
Formwork @ 3% of (a+b+c)
d) Overheads @ 0.2 on (a+b+c)
e) Contractors profit @ 0.1 on (a+b+c+d)
cost of 120 cum = a+b+c+d+e
Rate per cum (a+b+c+d+e)/120

MT
cum
cum
cum

50.64
54.00
64.80
43.20

5940.00
2400.00
942.00
1063.00

300801.60
129600.00
61041.60
45921.60

day
day
day

0.84
3.00
18.00

673.00
500.00
377.00

565.32
1500.00
6786.00

hour
hour
hour

6.00
6.00
6.00

2094.00
654.00
756.00

12564.00
3924.00
4536.00

hour
T-Km
hour

15.00
300L
6.00

873.00
input
240.00

Say

3.13

Note

Where ever concrete is carried out using batching plant,


transit mixer, concrete pump, admixers @ 0.4% of weight of
cement may be added for achieving desired slump of
concrete.

304

Excavation for Structures


Earth work in excavation of foundation of structures as per
drawing and technical specification, including setting out,
construction of shoring and bracing, removal of stumps and
other deleterious matter, dressing of sides and bottom,
backfilling the excavation earth to the extent required and
utilising the remaning earth locally for road work.
I) Ordinary soil
Unit = cum
Taking output = 10 cum

Manual Means

Page 33 of 394

13095.00
#VALUE! L= 1
1440.00
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

(i) Depth upto 3 m


a) Labour
Mate

day

0.320

673.00

215.36

L-12

Mazdoor

day

8.000

377.00

3016.00

L-13

b) Overheads @ 0.1 on (a)

323.14

c) Contractors profit @ 0.1 on (a+b)

355.45

Cost for 10 cum = a+b+c

3909.95

Rate per cum = (a+b+c)/10

390.99
say

Note

391.00

Cost of dewatering may be added where required upto 10 %


of labour cost Assessment for dewatering shall be made as
per site conditions..
Mechanical Means
(i) Depth upto 3 m
Unit = cum
Taking output = 300 cum
a) Labour
Mate

day

0.32

673

215.36

Mazdoor

day

8.00

377

3016.00

hour

6.00

1222

7332.00

b) Machinery
Hydraulic excavator 1.0 cum bucket capacity
c) Overheads @ 0.1 on (a+b)

1056.34

d) Contractors profit @ 0.1 on (a+b+c)

1161.97

Cost for 300 cum = a+b+c+d

12781.67

Rate per cum = (a+b+c+d)/300

13.6

42.61

Note

Cost of dewatering upto 5% of (a+b) may be added, where


required. Assessment for dewatering shall be made as per
site conditions..

Section
1600 &
2200

Supplying, fitting and placing HYSD bar reinforcement in


sub-structure complete as per drawing and technical
specifications
Output : MT
Taking output = 1 MT
a) Material
HYSD bars including 5% overlaps and wastage
Binding wire
b) Labour for cutting, bending, shifting to site, tying and
placing in position
Mate
Blacksmith
Mazdoor
c) Overheads @ 0.2 on (a+b)
d) Contractors profit @ 0.1 on (a+b+c)
Rate for per MT (a+b+c+d)

say

43.00

MT
kg

1.05
6.00

52100.00
87.00

54705.00
522.00

day
day
day

0.34
2.00
6.50

673.00
500.00
377.00

228.82
1000.00
2450.50
11781.26
7068.76
77756.34
77756.00

say
14.1

1500
&1600
1700

Furnishing and Placing Reinforced/Prestressed cement


concrete in super-structure as per drawing and
Technical Specification

Page 34 of 394

A
Case II

RCC Grade M20


Using Batching Plant, Transit Mixer and Concrete Pump

Unit = cum
Taking output = 120 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto 1 Km
Lead beyond 1 Km, L - lead in Kilometer
Concrete Pump
Basic Cost of Labour, Material & Mechinery (a+b+c) for 120 cum
(i)
(p)

B
Case II

MT
cum
cum
cum

40.92
54.00
64.80
43.20

5940.00
2400.00
942.00
1063.00

243064.80
129600.00
61041.60
45921.60

day
day
day

0.84
3.00
18.00

673.00
500.00
377.00

565.32
1500.00
6786.00

hour
hour
hour

6.00
6.00
6.00

2094.00
654.00
756.00

12564.00
3924.00
4536.00

hour
T-Km
hour

15.00
300L
6.00
#VALUE!

873.00
input
240.00

For solid slab super-structure, 20-30% of (a+b+c)


Height upto 5m
Basic Cost of Labour, Material & Mechinery (a+b+c) for 120
cum
d) Formwork and staging 20 % of (a+b+c)
e) Overheads @ 0.2 on (a+b+c+d)
f) Contractors profit @ 0.1 on (a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f
Rate per cum (a+b+c+d+e+f)/120

13095.00
#VALUE! L= 1
1440.00

#VALUE!
20.00

say

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

RCC Grade M25


Using Batching Plant, Transit Mixer and Concrete Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto 1 Km
Lead beyond 1 Km, L - lead in Kilometer

Page 35 of 394

MT
cum
cum
cum

47.95
54.20
64.80
43.20

5940.00
2400.00
942.00
1063.00

284823.00
130080.00
61041.60
45921.60

day
day
day

0.84
3.00
18.00

673.00
500.00
377.00

565.32
1500.00
6786.00

hour
hour
hour

6.00
6.00
6.00

2094.00
654.00
756.00

12564.00
3924.00
4536.00

hour
T-Km

15.00
300L

873.00
input

13095.00
#VALUE! L= 1

Concrete Pump
Basic Cost of Labour, Material & Mechinery (a+b+c) for 120 cum
For formwork and staging add the following:
(i)

For solid slab super-structure, 20-30% of (a+b+c)

(p)

Height upto 5m
Basic Cost of Labour, Material & Mechinery (a+b+c)
120 cum
d) Formwork and staging 20 % of (a+b+c)

C
Case II

6.00
#VALUE!

240.00

for

1440.00

#VALUE!
20.00

#VALUE!

e)

Overheads @ 0.2 on (a+b+c+d)

#VALUE!

f)

Contractors profit @ 0.1 on (a+b+c+d+e)

#VALUE!

Cost for 15 cum= a+b+c+d+e+f

#VALUE!

Rate per cum (a+b+c+d+e+f)/120

#VALUE!
say

#VALUE!

RCC Grade M 30
Using Batching Plant, Transit Mixer and Concrete Pump.

Unit = cum
Taking output = 120 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto 1 Km
Lead beyond 1 Km, L - lead in Kilometer
Concrete Pump
Basic Cost of Labour, Material & Mechinery (a+b+c) for 120 cum
For formwork and staging add the following:
(i)
(p)

hour

MT
cum
cum
cum

48.79
54.60
64.80
43.20

5940.00
2400.00
942.00
1063.00

289812.60
131040.00
61041.60
45921.60

day
day
day

0.88
3.00
19.00

673.00
500.00
377.00

592.24
1500.00
7163.00

hour
hour
hour

6.00
6.00
6.00

2094.00
654.00
756.00

12564.00
3924.00
4536.00

hour
T-Km
hour

15.00
300L
6.00
#VALUE!

873.00
input
240.00

For solid slab super-structure, 20-30% of (a+b+c)


Height upto 5m
Basic Cost of Labour, Material & Mechinery (a+b+c) for 120
cum
d) Formwork and staging 20 % of (a+b+c)
e) Overheads @ 0.2 on (a+b+c+d)
f) Contractors profit @ 0.1 on (a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f
Rate per cum (a+b+c+d+e+f)/120

#VALUE!
20.00

say
Rate per cum (a+b+c+d)/120 ( including formwork and excluding OH & CP)
Rate per cum (a+b+c+d)/120 ( excluding formwork and Excluding OH & CP)

Page 36 of 394

13095.00
#VALUE! L= 1
1440.00

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

E
Case 1

PSC Grade M-40


Using concret mixer.
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
Admixture @ 0.4% of cement
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum)
Generator 33 KVA
Basic Cost of Labour, Material & Mechinery (a+b+c) for 15 cum

Case II

MT
cum
cum
cum
kg

6.45
6.75
8.10
5.40
25.80

5940.00
2400.00
942.00
1063.00
input

38313.00
16200.00
7630.20
5740.20
#VALUE!

day
day
day

0.96
2.00
22.00

673.00
500.00
377.00

646.08
1000.00
8294.00

hour
hour

6.00
6.00
#VALUE!

218.00
349.00

1308.00
2094.00

MT
cum
cum
cum
kg
Kg

51.60
54.00
64.80
43.20
206.40
216.00

5940.00
2400.00
942.00
1063.00
input
input

306504.00
129600.00
61041.60
45921.60
#VALUE!
#VALUE!

day
day
day

0.94
3.50
20.00

673.00
500.00
377.00

632.62
1750.00
7540.00

hour
hour
hour

6.00
6.00
6.00

2094.00
654.00
756.00

12564.00
3924.00
4536.00

hour
T-Km
hour

15.00
300L
6.00
#VALUE!

873.00
input
240.00

Using Batching Plant, Transit Mixer and Concrete Pump

Unit = cum
Taking output = 120 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
Admixture @ 0.4% of cement
Admixer
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto 1 Km
Lead beyond 1 Km, L - lead in Kilometer
Concrete Pump
Basic Cost of Labour, Material & Mechinery (a+b+c) for 120 cum
For formwork and staging add the following:
(i)

For solid slab super-structure, 18-28% of (a+b+c)

(p)

Height upto 5m
Basic Cost of Labour, Material & Mechinery (a+b+c)
120 cum
d) Formwork and staging 18 % of (a+b+c)

for

13095.00
#VALUE! L= 1
1440.00

#VALUE!
18.00

#VALUE!

e)

Overheads @ 0.2 on (a+b+c+d)

#VALUE!

f)

Contractors profit @ 0.1 on (a+b+c+d+e)

#VALUE!

Cost for 15 cum= a+b+c+d+e+f

#VALUE!

Rate per cum (a+b+c+d+e+f)/120

#VALUE!

Page 37 of 394

Note

say

#VALUE!

1.Where ever concrete is carried out using batching plant,


transit mixer, concrete pump, admixers conforming IS: 9103
@ 0.4% of weight of cement may be added for achieving
desired slump of concrete.
2. Cement provided for various components of the super
structure is for estimating purpose only. Actual quantity of
cement will be as per approved mix design. Similarly, the
provision for coarse and fine aggregates is for estimating
purpose and the exact quantity shall be as per the mix
design.
3. The items like needle and surface vibrators are part of
minor T & P which is already covered under the overhead
charges. As such these items have not been added
seperately in the rate analysis.

14.2

1600

A) Supplying ,fitting and placing HYSD bar


reinforcement in super-structure complete as per
drawing and technical specifications
Unit = 1 MT
Taking output = 1 MT
a) Material
HYSD bars including 5% for laps and wastage
Binding wire
b) Labour for cutting, bending, tying and placing in position
Mate
Blacksmith
Mazdoor
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)

Page 38 of 394

MT
Kg

1.05
8.00

52100.00
87.00

54705.00
696.00

day
day
day

0.44
3.00
8.00
60214.00

673.00
500.00
377.00

296.12
1500.00
3016.00

Summary of Rate Analysis


Item No.

Unit

Descriptions

Rate

CHAPTER-1
CARRIAGE OF MATERIALS
1.1

Loading and unloading of stone boulder / stone aggregates / sand / kanker / moorum. (Placing tipper at loading point,
loading with front end loader, dumping, turning for return trip, excluding time for haulage and return trip)

1.2
1.3
1.4
(i)
(ii)
(iii)

cum

76.00

Loading and Unloading of Boulders by Manual Means

cum

127.00

Loading and Unloading of Cement or Steel by Manual Means and stacking.


Cost of Haulage Excluding Loading and Unloading

tonne

168.00

Unsurfaced Gravelled Road

tonne.km
tonne.km

2.40
2.90

Katcha Track and Track in river bed / nallah bed and choe bed.

tonne.km

5.90

Surfaced Road

1.5

Hand Broken Stone Aggregates 63 mm nominal size (Supply of quarried stone, hand breaking into coarse aggregate 63
mm nominal size (passing 80 mm and retained on 50 mm sieve) and stacking as directed)

cum

1053.00

1.6

Crushing of stone aggregates 13.2 mm nominal size. (Crushing of stone boulders of 150 mm size in an integrated stone
crushing unit of 200 tonnes per hour capacity comprising of primary and secondary crushing units, belt conveyor and
vibrating screens to obtain stone aggregates of 13 mm nominal size.)

cum

573.00

1.7

Crushing of stone aggregates 20 mm nominal size (Crushing of stone boulders of 150 mm size in an integrated stone
crushing unit of 200 tonnes per hour capacity comprising of primary and secondary crushing units, belt conveyor and
vibrating screens to obtain stone aggregates of 20 mm nominal size.)

cum

486.00

1.8

Crushing of stone aggregates 40 mm nominal size (Crushing of stone boulders of 150 mm size in an integrated stone
crushing unit of 200 tonnes per hour capacity comprising of primary and secondary crushing units, belt conveyor and
vibrating screens to obtain stone aggregates of 40 mm nominal size.)

cum

410.00

CHAPTER-2
SITE CLEARANCE
Cutting of Trees, including Cutting of Trunks, Branches and Removal (Cutting of trees, including cutting of trunks,
branches and removal of stumps, roots, stacking of serviceable material with all lifts and up to a lead of 1000 mtrs and earth
filling in the depression/pit.)

2.1
(i)

Girth from 300 mm to 600 mm

each

331.00

(ii)
(iii)

Girth from 600 mm to 900 mm


Girth from 900 mm to 1800 mm
Girth above 1800 mm

each
each

567.00
1142.00

each
hectare

2202.00
24437.00

hectare
hectare

73723.00
98571.00

hectare
hectare

44595.00
54224.00

(iv)
2.2

Clearing Grass and Removal of Rubbish

2.3

Clearing and Grubbing Road Land .(Clearing and grubbing road land including uprooting rank vegetation, grass, bushes,
shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees cut earlier and disposal of unserviceable
materials and stacking of serviceable material to be used or auctioned up to a lead of 1000 metres including removal and
disposal of top organic soil not exceeding 150 mm in thickness.)

(i)
A
B
(ii)
A
B

In area of thorny jungle


By Mechanical Means
In area of light jungle
In area of thorny jungle
Dismantling of Structures (Dismantling of existing structures like culverts, bridges, retaining walls and other structure
comprising of masonry, cement concrete, wood work, steel work, including T&P and scaffolding wherever necessary, sorting
the dismantled material, disposal of unserviceable material and stacking the serviceable material with all lifts and lead of
1000 metres)

2.4

(i)

Lime /Cement Concrete


By Manual Means

I
A
B
C
II
A
B
(ii)
A
B
C
D
(iii)

By Manual Means:In area of light jungle

Lime Concrete, cement concrete grade M-10 and below


Cement Concrete Grade M-15 & M-20
Prestressed / Reinforced cement concrete grade M-20 & above
By Mechanical Means for items No. 202( b) & ( c)
Cement Concrete Grade M-15 & M-20
Prestressed / Reinforced cement concrete grade M-20 & above
Dismantling Brick / Tile work
In lime mortar
In cement mortar
In mud mortar
Dry brick pitching or brick soling
Dismantling Stone Masonry

Page 39 of 394

cum
cum

480.00
578.00

cum

1585.00

cum
cum

479.00
865.00

cum
cum

284.00
382.00

cum
cum

245.00
226.00

Summary of Rate Analysis


Item No.

Unit

Descriptions

Rate

Rubble stone masonry in lime mortar

cum

323.00

Rubble stone masonry in cement mortar.

cum

382.00

Rubble Stone Masonry in mud mortar.

cum

284.00

Dry rubble masonry

cum

265.00

Dismantling stone pitching/ dry stone spalls.


Dismantling boulders laid in wire crates including opening of crates and stacking dismantled materials.

cum

245.00

cum

284.00

cum

735.00

Including dismembering
Excluding dismembering.

tonne
tonne

1976.00
1499.00

Extra over item No( V ) A and( V ) B for cutting rivets.

tonne

15.00

F
(iv)
(v)

Wood work wrought framed and fixed in frames of trusses upto a height of 5 m above plinth level
Steel work in all types of sections upto a height of 5 m above plinth level excluding cutting of rivet.
A
B
C

(vi)

Scraping of bricks dismantled from brick work including stacking.


A
B

(vii)

In lime/Cement mortar

1000
numbers

1711.00

In mud mortar

1000
numbers

611.00

cum

687.00

cum
sqm

145.00
21.00

Scraping of Stone from dismantled stone masonry


A
B

In cement and lime mortar


In Mud mortar

(viii)

Scarping plaster in lime or cement mortar from brick/ stone masonry

(ix)

Removing all type of hume pipes and stacking within a lead of 1000 metres including earthwork and dismantling of
masonry works.
A

Up to 600 mm dia

metre

253.00

B
C

Above 600 mm to 900 mm dia

metre
metre

344.00
588.00

cum
cum

889.00
625.00

Above 900 mm
Dismantling of Flexible Pavements (Dismantling of flexible pavements and disposal of dismantled materials up to a lead
of 1000 metres, stacking serviceable and unserviceable materials separately)

2.5
I
A
B
II
A

By Manual Means
Bituminous courses
Granular courses
By Mechanical Means

cum

309.00

2.6

Dismantling of Cement Concrete Pavement (Dismantling of cement concrete pavement by mechanical means using
pneumatic tools, breaking to pieces not exceeding 0.02 cum in volume and stock piling at designated locations and disposal
of dismantled materials up to a lead of 1000 metres, stacking serviceable and unserviceable materials separately)

cum

#VALUE!

2.7

Dismantling Guard Rails (Dismantling guard rails by manual means and disposal of dismantled material with all lifts and
up to a lead of 1000 metres, stacking serviceable materials and unserviceable materials separately.)

metre

94.00

2.8

Dismantling Kerb Stone (Dismantling kerb stone by manual means and disposal of dismantled material with all lifts and up
to a lead of 1000 metre)

metre

16.00

2.9

Dismantling Kerb Stone channel (Dismantling kerb stone channel by manual means and disposal of dismantled material
with all lifts and up to a lead of 1000 metre)

metre

24.00

2.10

Dismantling Kilometre Stone (Dismantling of kilometre stone including cutting of earth, foundation and disposal of
dismantled material with all lifts and lead upto 1000 m and back filling of pit.)
5th KM stone
Ordinary KM Stone

each
each

510.00
286.00

Hectometre Stone

A
B
C

Bituminous course

each

57.00

2.11

Dismantling of Fencing (Dismantling of barbed wire fencing/ wire mesh fencing including posts, foundation concrete, back
filling of pit by manual means including disposal of dismantled material with all lifts and up to a lead of 1000 metres, stacking
serviceable material and unserviceable material separately. )

metre

67.00

2.12

Dismantling of CI Water Pipe Line (Dismantling of CI water pipe line 600 mm dia including disposal with all lifts and lead
upto 1000 metres and stacking of serviceable material and unserviceable material separately under supervision of
concerned department)

metre

143.00

metre

170.00

each

226.00

2.13

2.14

Removal of Cement Concrete Pipe of Sewer Gutter (Removal of cement concrete pipe of sewer gutter 1500 mm dia
under the supervision of concerned department including disposal with all lifts and up to a lead of 1000 metres and stacking
of serviceable and unserviceable material separately but excluding earth excavation and dismantling of masonry works.)

Removal of Telephone / Electric Poles and Lines (Removal of telephone / Electric poles including excavation and
dismantling of foundation concrete and lines under the supervision of concerned department, disposal with all lifts and up to
a lead of 1000 metres and stacking the serviceable and unserviceable material separately)

Page 40 of 394

Summary of Rate Analysis


Item No.

Unit

Descriptions

Rate

CHAPTER-3
EARTH WORK, EROSION CONTROL AND DRAINAGE
3.1

Excavation in Soil by Manual Means. (Excavation for roadway in soil using manual means including loading in truck for
carrying of cut earth to embankment site with all lifts and lead upto1000 metres.)

cum

213.00

3.2

Excavation in ordinary rock by manual means (Excavation in ordinary rock using manual means including loading in a
truck and carrying of excavated material to embankment site with in all lifts and leads upto 1000 metres )

cum

314.00

3.3

Excavation in Soil with Dozer with lead upto 100 metres (Excavation for road way in soil by mechanical means including
cutting and pushing the earth to site of embankment upto a distance of 100 metres (average lead50 metres), including
trimming bottom and side slopes in accordance with requirements of lines, grades and cross sections.)

cum

146.00

3.4

Excavation in Ordinary Rock with Dozer with lead upto 100 metres (Excavation for roadway in ordinary rock by
deploying a dozer, 80 HP including cutting and pushing the cut earth to site of embankment upto a distance of 100 metres
( average lead 50 metres ), trimming bottom and side slopes in accordance with the requirements of lines, grades and cross
sections.)

cum

248.00

cum

33.00

3.6

Excavation in Soil using Hydraulic Excavator CK 90 and Tippers with disposal upto 1000 metres. (Excavation for
roadwork in soil with hydraulic excavator of0.9 cum bucket capacity including cutting and loading in tippers, trimming bottom
and side slopes, in accordance with requirements of lines, grades and cross sections, and transporting to the embankment
location within all lifts and lead upto 1000m)

cum

43.00

3.7

Excavation in Ordinary Rockusing Hydraulic ExcavatorCK-90 and Tippers with disposal upto 1000 metres.
(Excavation for roadway in ordinary rock with hydraulic excavator of 0.9 cum bucket capacity including cutting and loading in
tippers, transporting to embankment site within all lifts and lead upto 1000 m, trimming bottom and side slopes in
accordance with requirements of lines, grades and cross sections.)

cum

57.00

3.8

Excavation in Hard Rock (blasting prohibited) (Excavation for roadway in hard rock (blasting prohibited) with rock
breakers including breaking rock, loading in tippers and disposal within all lifts and lead upto 1000 metres, trimming bottom
and side slopes in accordance with requirements of lines, grades and cross sections.)
cum
cum

209.00
1131.00

3.9

Excavation in Hard Rock (controlled blasting) with disposal upto 1000 metres (Excavation for roadway in hard rock
with controlled blasting by drilling, blasting and breaking, trimming of bottom and side slopes in accordance with
requirements of lines, grades and cross sections, loading and disposal of cut road with in all lifts and leads upto 1000
metres )

cum

100.00

3.10

Excavation in Marshy Soil (Excavation for roadway in marshy soil with hydraulic excavator 0.9 cum bucket capacity
including cutting and loading in tippers and disposal with in all lifts and lead upto 1000 metres, trimming of bottom and side
slopes in accordance with requirements of lines, grades and cross sections.)

cum

49.00

3.11

Removal of Unserviceable Soil with Disposal upto 1000 metres (Removal of unserviceable soil including excavation,
loading and disposal upto 1000 metres lead but excluding replacement by suitable soil which shall be paid separately as per
clause 305.)

cum

43.00

3.12

Pre-splitting of Rock Excavation Slopes (Carrying out excavation in hard rock to achieve a specified slope of the rock
face by controlled use of explosives and blasting accessories in properly aligned and spaced drill holes, collection of the
excavated rock by a 80 HP dozer, loading in tipper by a front end loader and disposing of the material with all lifts and lead
upto 1000 m, all as specified in clause No. 303)

sqm

133.00

Excavation in Hard Rock (requiring blasting) with disposal upto 1000 metres (Excavation for roadway in hard rock
(requiring blasting) by drilling, blasting and breaking, trimming of bottom and side slopes in accordance with requirements
of lines, grades and cross sections, loading and disposal of cut road with in all lifts and leads upto 1000 metres )

3.5

A
B

Mechanised
Manual Method

Excavation for Structures (Earth work in excavation of foundation of structures as per drawing and technical specification,
including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides
and bottom, backfilling the excavation earth to the extent required and utilising the remaining earth locally for road work.)

3.13

(i)

Ordinary soil
A
B

Manual Means (Depth upto 3 m)


Mechanical Means (Depth upto 3 m)
Ordinary rock (not requiring blasting)

cum
cum

391.00
43.00

A
B

Manual Means (Depth upto 3 m)


Mechanical Means
Hard rock ( requiring blasting )

cum
cum

489.00
55.00

Manual Means
Hard rock ( blasting prohibited )

cum

725.00

Mechanical Means
Marshy soil
Manual means ( upto 3 m depth)

cum

607.00

cum

681.00

(ii)

(iii)
(iv)
(v)
A

Page 41 of 394

Summary of Rate Analysis


Item No.

Unit

Descriptions
B

Rate

cum

222.00

3.14

Scarifying Existing Granular Surface to a Depth of 50 mm by Manual Means (Scarifying the existing granular road
surface to a depth of 50 mm and disposal of scarified material within all lifts and leads upto 1000 metres. )

sqm

31.00

3.15

Scarifying existing bituminous surface to a depth of 50 mm by mechanical means (Scarifying the existing bituminous
road surface to a depth of 50 mm and disposal of scarified material with in all lifts and lead upto 1000 metres.)

sqm

4.00

Mechanical Means

3.16

Embankment Construction with Material Obtained from Borrow Pits (Construction of embankment with approved
material obtained from borrow pits with all lifts and leads, transporting to site, spreading, grading to required slope and
compacting to meet requirement of table 300-2)

cum

280.00

3.17

Construction of Embankment with Material Deposited from Roadway Cutting (Construction of embankment with
approved materials deposited at site from roadway cutting and excavation from drain and foundation of other structures
graded and compacted to meet requirement of table 300-2)

cum

83.00

3.18

Construction of Subgrade and Earthen Shoulders (Construction of subgrade and earthen shoulders with approved
material obtained from borrow pits with all lifts & leads, transporting to site, spreading, grading to required slope and
compacted to meet requirement of table No. 300-2)

cum

312.00

3.19

Compacting Original Ground


Compacting original ground supporting subgrade (Loosening of the ground upto a level of500 mm below the
subgrade level, watered, graded and compacted in layers to meet requirement of table 300-2 for subgrade construction.)

cum

61.00

:Compacting original ground supporting embankment

Case-I
Case-II

cum

30.00

3.20

Stripping and Storing Top Soil (Stripping, storing of top soil by road side at 15 m internal and re-application on
embankment slopes, cut slopes and other areas in localities where the available embankment material is not conducive to
plant growth)

cum

287.00

3.21

Stripping, storing and re-laying top soil from borrow areas in agriculture fields. (Stripping of top soil from borrow
areas located in agriculture fields, storing at a suitable place, spreading and re-laying after taking the borrow earth to
maintain fertility of the agricultural field, finishing it to the required levels and satisfaction of the farmer.)

cum

88.00

3.22

Turfing with Sods (Furnishing and laying of the live sods of perennial turf forming grass on embankment slope, verges or
other locations shown on the drawing or as directed by the engineer including preparation of ground, fetching of rods and
watering)

sqm

#VALUE!

3.23

Seeding and Mulching (Preparation of seed bed on previously laid top soil, furnishing and placing of seeds, fertilizer,
mulching material, applying bituminous emulsion at the rate of0.23 litres per sqm and laying and fixing jute netting, including
watering for 3 months all as per clause 308)

sqm

#VALUE!

3.24

Surface Drains in Soil (Construction of unlined surface drains of average cross sectional area 0.40 sqm in soil to specified
lines, grades, levels and dimensions to the requirement of clause 301 and 309. Excavated material to be used in
embankment within a lead of50 metres (average lead 25 metres))
metre

61.00

metre

98.00

metre

124.00

metre
metre

147.00

A
B

Surface Drains in Ordinary Rock (Construction of unlined surface drain of average cross sectional area 0.4 sqm in
ordinary rock to specified lines, grades, levels and dimensions as per approved design and to the requirement of clause 301
to 309. Excavated material to be used in embankment at site.)

3.25
A
B
3.26

3.27

Mechanical means
Manual Means

Mechanical Means
Manual Means
Surface Drains in Hard Rock (Rate per metre may be worked out based on quantity of hard rock as per design.)
Sub Surface Drains with Perforated Pipe (Construction of subsurface drain with perforated pipe of 100 mm internal
diameter of metal/ asbestos cement/ cement concrete/PVC, closely jointed, perforations ranging from 3 mm to 6 mm
depending upon size of material surrounding the pipe, with 150 mm bedding below the pipe and 300 mm cushion above the
pipe, cross section of excavation 450 x 550 mm. Excavated material to be utilised in roadway at site )

370.00

3.28

Aggregate Sub- Surface Drains (Construction of aggregate sub surface drain 300 mm x 450 mm with aggregates
conforming to table 300-4, excavated material to be utilised in roadway )

metre

188.00

3.29

Underground Drain at Edge of Pavement (Construction of an underground drain 1 m x 1 m (inside dimensions) lined with
RCC-20 cm thick and covered with RCC slab10 cm in thickness on urban roads)

metre

2467.00

3.30

Preparation and Surface Treatment of formation. (Preparation and surface treatment of formation by removing mud and
slurry, watering to the extent needed to maintain the desired moisture content, trimming to the required line, grade, profile
and rolling with 8-10 tonne smooth wheeled roller, complete as per clause 310.)

sqm

2.00

3.31

Construction of Rock fill Embankment (Construction of rock fill embankment with broken hard rock fragments of size not
exceeding 300 mm laid in layers not exceeding 500 mm thick including filling of surface voids with stone spalls, blinding top
layer with granular material, rolled with vibratory road roller, all complete as per clause 313)

cum

53.00

3.32

Excavation in Hill Area in Soil by Mechanical Means (Excavation in soil in hilly area by mechanical means including
cutting and trimming of side slopes and disposing of excavated earth with all lifts and lead upto 1000 metres)

cum

146.00

Page 42 of 394

Summary of Rate Analysis


Item No.

Descriptions

Unit

3.33

Excavation in Hilly Area in Ordinary Rock by Mechanical Means not Requiring Blasting. (Excavation in hilly area in
ordinary rock not requiring ballasting by mechanical means including cutting and trimming of slopes and disposal of cut
material with all lift and lead upto 1000 metres )

cum

224.00

cum

277.00

cum

108.00

3.34

Excavation in Hilly Areas in Hard Rock Requiring Blasting (Excavation in hilly areas in hard rock requiring blasting, by
mechanical means including trimming of slopes and disposal of cut material with all lifts and lead upto 1000 metres.)

3.35

Work in Urban Roads (The cost of earth work in urban roads inhabited area will be comparatively higher due to following
reasons:)

3.36

Embankment Construction with Fly ash/Pond ash available from coal or lignite burning Thermal Plants as waste
material. (Construction of embankment with fly ash conforming to table 1 of IRC: SP: 58 - 2001 obtained from coal or lignite
burning thermal power stations as waste material, spread and compacted in layer of 200mm thickness each at OMC, all as
specified in IRC: SP: 58-2001 and as per approved plans.)

Page 43 of 394

Rate

Summary of Rate Analysis


Item No.

Unit

Descriptions

Rate

CHAPTER-4
SUB-BASES, BASES ( NON- BITUMINOUS) AND SHOULDERS
4.1

Granular Sub-base with Close Graded Material (Table:- 400-1)


Plant Mix Method (Construction of granular sub-base by providing close graded Material, mixing in a mechanical mix plant
at OMC, carriage of mixed Material to work site, spreading in uniform layers with motor grader on prepared surface and
compacting with vibratory power roller to achieve the desired density, complete as per clause 401 )

A
(i)

for grading- I Material

cum

1019.00

(ii)
(iii)

for grading- II Material

cum
cum

1089.00
749.00

for grading-III Material


By Mix in Place Method (Construction of granular sub-base by providing close graded material, spreading in uniform layers
with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with vibratory
roller to achieve the desired density, complete as per clause 401)

B
(i)

for grading- I Material

cum

914.00

(ii)
(iii)

for grading- II Material

cum
cum

984.00
644.00

cum
cum

895.00
757.00

cum

322.00

cum
cum

328.00
368.00

cum

379.00

cum

679.00

for grading-III Material


Granular Sub-Base with Coarse Graded Material ( Table:- 400- 2) (Construction of granular sub-base by providing
coarse graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method
with rotavator at OMC, and compacting with vibratory roller to achieve the desired density, complete as per clause 401)

4.2

(i)
(ii)
(iii)

for grading- I Material


for grading- II Material
for grading-III Material
Lime Stabilisation for Improving Subgrade (Laying and spreading available soil in the subgrade on a prepared surface,
pulverising, mixing the spread soil in place with rotavator with 3 % slaked lime having minimum content of 70% of CaO,
grading with motor grader and compacting with the road roller at OMC to the desired density to form a layer of improved sub
grade)

4.3

A
B

By Mechanical Means
By Manual Means
Lime Treated Soil for Sub- Base (Providing, laying and spreading soil on a prepared sub grade, pulverising, mixing the
spread soil in place with rotavator with 3 % slaked lime with minimum content of 70% of CaO, grading with motor grader and
compacting with the road roller at OMC to achieve at least 98%of the max dry density to form a layer of sub base.)

4.4

4.5

Cement Treated Soil Sub Base/ Base (Providing, laying and spreading soil on a prepared sub grade, pulverising, adding
the designed quantity of cement to the spread soil, mixing in place with rotavator, grading with the motor grader and
compacting with the road roller at OMC to achieve the desired unconfined compressive strength and to form a layer of subbase/base.)

4.6

Cement Treated Crushed Rock or combination as per clause 403.2 and table 400.4in Sub base/ Base (Providing,
laying and spreading Material on a prepared sub grade, adding the designed quantity of cement to the spread Material,
mixing in place with rotavator, grading with the motor grader and compacting with the road roller at OMC to achieve the
desired unconfined compressive strength and to form a layer of sub-base/base.)

(i)

For Sub-Base course

cum

1596.00

(ii)

For Base course

cum

1216.00

sqm

1050.00

cum

3560.00

cum
cum

1411.00
1594.10

cum
cum

1434.00
1497.00

Making 50 mm x 50 mm Furrows (Making 50 mm x 50 mm furrows, 25mm deep, 450 to the center line of the road and at
one metre interval in the existing thin bituminous wearing coarse including sweeping and disposal of excavated material
within 1000 metres lead)

4.7

Inverted Choke (Construction of inverted choke by providing, laying, spreading and compacting screening B type/ coarse
sand of specified grade in uniform layer on a prepared surface with motor grader and compacting with power roller etc)

4.8

Water Bound Macadam (Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound
macadam specification including spreading in uniform thickness, hand packing, rolling with vibratory roller 8-10 tonnes in
stages to proper grade and camber, applying and brooming requisite type of screening/ binding Materials to fill up the
interstices of coarse aggregate, watering and compacting to the required density.)

4.9

A
(i)

By Manual Means
(a)
(b)

(ii)
(a)
(b)

Grading- I (Using Screening Crushable type such as Moorum or Gravel)


Using Screening Crushable type such as Moorum or Gravel
Using Screening Type-A (13.2mm Agg.)
Grading- II (Using Screening Crushable type such as Moorum or Gravel)
Using Screening Crushable type such as Moorum or Gravel
Using Screening Type-A (13.2mm Agg.)

Page 44 of 394

Summary of Rate Analysis


Item No.

Unit

Descriptions
(c)

(iii)

Using Screening Type-B (11.2mm Agg.)

Rate

cum

1626.00

Grading- III (Using Screening Crushable type such as Moorum or Gravel)


(a)

Using Screening Crushable type such as Moorum or Gravel

cum

1718.00

(b)

Using Screening Type-B (11.2mm Agg.)

cum

1911.00

cum
cum

1146.00
1329.44

By Mechanical Means:
Grading- I (Using Screening Crushable type such as Moorum or Gravel)

(i)
(a)
(b)
(ii)
(a)

Using Screening Crushable type such as Moorum or Gravel


Using Screening Type-A (13.2mm Agg.)
Grading- II (Using Screening Crushable type such as Moorum or Gravel)
Using Screening Crushable type such as Moorum or Gravel

cum

1169.00

cum
cum

1232.00
1361.00

Using Screening Crushable type such as Moorum or Gravel

cum

1453.00

Using Screening Type-B (11.2mm Agg.)

cum

1646.00

cum

249.00

sqm

25.00

4.12

Wet Mix Macadam (Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam
specification including premixing the Material with water at OMC in mechanical mix plant carriage of mixed Material by tipper
to site, laying in uniform layers with paver in sub- base / base course on well prepared surface and compacting with
vibratory roller to achieve the desired density.)

cum

1094.00

4.13

Construction of Median and Island with Soil Taken from Roadway Cutting (Construction of Median and Island above
road level with approved material deposited at site from roadway cutting and excavation for drain and foundation of other
structures, spread, graded and compacted as per clause 407)

cum

#VALUE!

4.14

Construction of Median and Island with Soil Taken from Borrow Areas (Construction of median and Island above road
level with approved material brought from borrow pits, spread, sloped and compacted as per clause 407)

cum

#VALUE!

sqm

#VALUE!

cum
cum

1343.00
1360.00

cum

1457.00

cum

922.00

cum

478.00

(b)
(c)
(iii)
(a)

Crushed Cement Concrete Sub-base / Base (Breaking and crushing of material obtained by breaking damaged cement
concrete slabs to size range not exceeding 75 mm as specified in table 400.7 transporting the aggregates obtained from
breaking of cement concrete slabs at a lead of L km., laying and compacting the same as sub base/ base course,
constructed as WBM to clause 404 except the use of screening or binding Material.)

4.10

Penetration Coat Over Top Layer of Crushed Cement Concrete Base (Spraying of bitumen over cleaned dry surface of
crushed cement concrete base at the rate of 25 kg per 10 sqm by a bitumen pressure distributor, spreading of key
aggregates at the rate of 0.13 cum per 10 sqm by a mechanical gritter and rolling the surface as per clause 506.3.8)

4.11

4.15

Construction of Shoulders (A. Earthen Shoulders)


Footpaths and Separators (Construction of footpath/separator by providing a 150 mm compacted granular sub base as
per clause 401 and 25 mm thick cement concrete grade M15, over laid with precast concrete tiles in cement mortar 1:3
including provision of all drainage arrangements but excluding kerb channel..)

4.16

Crusher Run Macadam Base (Providing crushed stone aggregate, depositing on a prepared surface by hauling vehicles,
spreading and mixing with a motor grader, watering and compacting with a vibratory roller to clause 410 to form a layer of
sub-base/Base)

4.17
A

(i)
(ii)

By Mix in Place Method

For 53 mm maximum size


For 45 mm maximum size
B

4.18

Using Screening Type-B (11.2mm Agg.)


Grading- III (Using Screening Crushable type such as Moorum or Gravel)

(b)

(i)
(ii)

Using Screening Type-A (13.2mm Agg.)

By Mixing Plant :

For 53 mm maximum size


For 45 mm maximum size
Lime, Fly ash stabalised soil sub-base (Construction of Sub-base using lime - fly ash admixture with granular soil,
free from organic matter/ deleterious material or clayey silts and low plasticity clays having PI between 5 and 20
and liquid limit less than 25 and commercial dry lime, slaked at site or pre-slaked with CaO content not less than
50%, fly ash to conform to gradation as per clause 4.3 of IRC: 88-1984, lime + fly ash content ranging between 10 to
30%, the minimum un-confined compressive strength and CBR value after 28 days curing and 4 days soaking to be
7.5kg/sq, cm and 25% respectively, all as specified in IRC: 88-1984. )

Page 45 of 394

Summary of Rate Analysis


Item No.

Unit

Descriptions

Rate

CHAPTER-5
BASES AND SURFACE COURSES (BITUMINOUS)
5.1

Prime coat (Providing and applying primer coat with bitumen emulsion on prepared surface of granular Base including
clearing of road surface and spraying primer at the rate of 0.60 kg/sqm using mechanical means.)

5.2

Tack coat
Providing and applying tack coat with bitumen emulsion using emulsion pressure distributor at the rate of 0.20
kg per sqm on the prepared bituminous/granular surface cleaned with mechanical broom.

sqm

27.00

sqm

10.00

cum
cum

6072.00
6115.00

Bituminous Macadam (Providing and laying bituminous macadam with 100-120 TPH hot mix plant producing an average
output of 75 tonnes per hour using crushed aggregates of specified grading premixed with bituminous binder, transported to
site, laid over a previously prepared surface with paver finisher to the required grade, level and alignment and rolled as per
clauses 501.6 and 501.7 to achieve the desired compaction)

5.3

(i)
(ii)

for Grading I ( 40 mm nominal size )


for GradingII(19 mm nominal size)
Bituminous Penetration Macadam (Construction of penetration macadam over prepared Base by providing a layer of
compacted crushed coarse aggregate using chips spreader with alternate applications of bituminous binder and key
aggregates and rolling with a smooth wheeled steel roller 8-10 tonne capacity to achieve the desired degree of compaction)

5.4

50 mm thick

sqm

338.00

75 mm thick

sqm

471.00

sqm

286.00

cum
cum

8107.00
8373.00

cum
cum

7831.00
8310.00

cum
cum

9019.00
9067.00

sqm
sqm

82.00
67.00

Built-Up-Spray Grout (Providing, laying and rolling of built-up-spray grout layer over prepared base consisting of a two
layer composite construction of compacted crushed coarse aggregates using motor grader for aggregates. key stone chips
spreader may be used with application of bituminous binder after each layer, and with key aggregates placed on top of the
second layer to serve as a Base conforming to the line, grades and cross-section specified, the compacted layer thickness
being 75 mm)

5.5

Dense Graded Bituminous Macadam (Providing and laying dense bituminous macadam with 100-120 TPH batch type
HMP producing an average output of 75 tonnes per hour using crushed aggregates of specified grading, premixed with
bituminous binder @ 4.0 to 4.5% by weight of total mix of mix and filler, transporting the hot mix to work site, laying with a
hydrostatic paver finisher with sensor control to the required grade, level and alignment, rolling with smooth wheeled,
vibratory and tandem rollers to achieve the desired compaction as per MoRTH specification clause No. 507 complete in all
respects.)

5.6

(i)
(ii)

for Grading I ( 40 mm nominal size )


for GradingII(19 mm nominal size)
Semi - Dense Bituminous Concrete (Providing and laying semi dense bituminous concrete with 100-120 TPH batch type
HMP producing an average output of 75 tonnes per hour using crushed aggregates of specified grading, premixed with
bituminous binder @ 4.5 to 5 % of mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher
with sensor control to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to
achieve the desired compaction as per MoRTH specification clause No. 508 complete in all respects)

5.7

(i)
(ii)

for Grading I ( 13 mm nominal size )


for GradingII(10 mm nominal size)
Bituminous Concrete (Providing and laying bituminous concrete with 100-120 TPH batch type hot mix plant producing an
average output of 75 tonnes per hour using crushed aggregates of specified grading, premixed with bituminous binder @
5.4 to 5.6 % of mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control
to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired
compaction as per MORTH specification clause No. 509 complete in all respects)

5.8

(i)
(ii)

for Grading-I ( 13 mm nominal size )


for Grading-II(10 mm nominal size)
Surface Dressing (Providing and laying surface dressing as wearing course in single coat using crushed stone aggregates
of specified size on a layer of bituminous binder laid on prepared surface and rolling with 8-10 tonne smooth wheeled steel
roller)

5.9
Case -1
Case - II

:-19 mm nominal chipping size


13 mm nominal size chipping
Open - Graded Premix Surfacing (Providing, laying and rolling of open - graded premix surfacing of 20 mm thickness
composed of 13.2 mm to 5.6 mm aggregates either using penetration grade bitumen or cut-back or emulsion to required
line, grade and level to serve as wearing course on a previously prepared base, including mixing in a suitable plant, laying
and rolling with a smooth wheeled roller 8-10 tonne capacity, finished to required level and grades.)

5.10

(i)

Case - I: Mechanical method using Penetration grade Bitumen and HMP of appropriate capacity not less than 75
tonnes/hour .

sqm

120.00

(ii)

Case - II: Open-Graded Premix Surfacing using cationic Bitumen Emulsion

sqm

138.00

Page 46 of 394

Summary of Rate Analysis


Item No.

Unit

Descriptions
Close Graded Premix Surfacing/Mixed Seal Surfacing (Mechanical means using HMP of appropriate capacity not
less than 75 tonnes/hour. Providing, laying and rolling of close-graded premix surfacing material of 20 mm
thickness composed of 11.2 mm to 0.09 mm (Type-a) or 13.2 mm to 0.09 mm (Type-b) aggregates using
penetration grade bitumen to the required line, grade and level to serve as wearing course on a previously
prepared base, including mixing in a suitable plant, laying and rolling with a Smooth wheeled roller 8-10 tonne
capacity, and finishing to required level and grade. )

5.11

Rate

sqm

182.00

Seal Coat (Providing and laying seal coat sealing the voids in a bituminous surface laid to the specified levels, grade and
cross fall using Type A and B seal coats)

5.12
(i)

Case - I : Type A

sqm

60.00

(ii)

Case - II : Type B (Providing and laying of premix sand seal coat with HMP of appropriate capacity not less than 75
tonnes/ hours using crushed stone chipping 6.7 mm size and penetration bitumen of suitable grade.)

sqm

45.00

Supply of Stone Aggregates for Pavement Courses (Supply of stone aggregates from approved sources confirming to
the physical requirement, specified in the respective specified clauses, including royalties, fees rents, collection,
transportation, stacking and testing and measured in cum as per clause 514.5 Competitive market rates to be ascertained.
Alternatively, rates for stone crushing given in chapter 1may be adopted, if found economical. In case for supply of
aggregates at site are not available, nearest crusher site may be ascertained. Loading and un-loading charges and cost of
carriage may be added to these rates to arrive at the cost at site.)

5.13

Mastic Asphalt (Providing and laying 25 mm thick mastic asphalt wearing course with paving grade bitumen meeting the
requirements given in table 500-29, prepared by using mastic cooker and laid to required level and slope after cleaning the
surface, including providing antiskid surface with bitumen precoated fine-grained hard stone chipping of 13.2 mm nominal
size at the rate of 0.005cum per 10 sqm and at an approximate spacing of 10 cm center to center in both directions,
pressed into surface when the temperature of surfaces not less than 1000C, protruding 1 mm to 4 mm over mastic surface,
all complete as per clause 515.)

5.14

cum

sqm

#VALUE!

sqm
sqm
sqm

65.00
38.00
24.00

cum

#VALUE!

sqm

33.00

sqm

3.00

cum

#VALUE!

cum
cum
cum

#VALUE!
#VALUE!
#VALUE!

cum

10374.00

Slurry Seal Providing and laying slurry seal consisting of a mixture of fine aggregates, portland cement filler, bituminous
emulsion and water on a road surface including cleaning of surface, mixing of slurry seal in a suitable mobile plant, laying
and compacting to provide even riding surface)

5.15
(i)
(ii)
(iii)

5 mm thickness
3 mm thickness
1.5 mm thickness
Recycling of Bituminous Pavement with Central Recycling Plant (Recycling pavement by cold milling of exiting
bituminous layers, planning the surface after cold milling, reclaiming excavated material to the extent of 30 % of the required
quantity, hauling and stock piling the reclaimed material near the central recycling plant after carrying out necessary checks
and evaluation, adding fresh material including rejuvenators as required, mixing in a hot mix plant, transporting and laying at
site and compacting to the required grade, level and thickness, all as specified in clause 517.)

5.16

5.17
added

Fog Spray
1.In case it is decided by the engineer to blind the fog spray, the following may be added
Bituminous Cold Mix ( Including Gravel Emulsion) (Providing, laying and rolling of bituminous cold mix on prepared base
consisting of a mixture of unheated mineral aggregate and emulsified or cutback bitumen, including mixing in a plant of
suitable type and capacity, transporting, laying, compacting and finishing to specified grades and levels.)

5.18
(i)
(ii)
(iii)
(iv)

Using bitumen emulsion and 9.5 mm or 13.2 mm nominal size aggregate


Using bitumen emulsion and 19 mm or 26.5 mm nominal size aggregate
Using cutback bitumen and 9.5 mm or 13.2 mm nominal size aggregate
Using cutback bitumen and 19 mm or 26.5 mm nominal size aggregate
Sand Asphalt Base Course (Providing, laying and rolling sand-asphalt base course composed of sand, mineral filler and
bituminous binder on a prepared sub-grade or sub-base to the lines, levels, grades and cross sections as per the drawings
including mixing in a plant of suitable type and capacity, transporting, laying, compacting and finishing.)

5.19

Modified Binder (Supply of modified binder produced by mixing bitumen with modifier such as natural rubber or crumb
rubber or any other polymer found compatible with bitumen and which allows properties given in clause 521.3 and IRC: SP:
53 blending of modifier with bitumen to be done either at the refinery or at the site plant capable of producing the modified
binder to be delivered in drums which shall be agitated in melted condition using suitable device before use to ensure
uniform dispersion.)

5.20

5.21

tonne

Crack Prevention Courses

(i)

Stress Absorbing Membrane (SAM) crack width less than 6 mm (Providing and laying of a stress absorbing
membrane over a cracked road surface, with crack width below 6 mm after cleaning with a mechanical broom, using
modified binder complying with clause 521, sprayed at the rate of 9 kg per 10 sqm and spreading 5.6 mm crushed stone
aggregates @ 0.11 cum per 10 sqm with hydraulic chip spreader, sweeping the surface for uniform spread of aggregates
and surface finished to conform to clause 902.)

Page 47 of 394

sqm

58.00

Summary of Rate Analysis


Item No.

Unit

Descriptions

(ii)

(iii)

(iv)

Stress Absorbing Membrane (SAM) with crack width 6 mm to 9 mm (Providing and laying of a stress absorbing
membrane over a cracked road surface, with crack width 6 to 9 mm after cleaning with a mechanical broom, using
modified binder complying with clause 521, sprayed at the rate of 11 kg per 10 sqm and spreading 11.2 mm crushed
stone aggregates @ 0.12 cum per 10 sqm, sweeping the surface for uniform spread of aggregates and surface finished
to conform to clause 902.)
Stress Absorbing Membrane (SAM) crack width above 9 mm and cracked area above 50 % (Providing and laying a
single coat of a stress absorbing membrane over a cracked road surface, with crack width above 9 mm and cracked area
above 50 % after cleaning with a mechanical broom, using modified binder complying with clause 521, sprayed at the
rate of 15 kg per 10 sqm and spreading 11.2 mm crushed stone aggregates @ 0.12 cum per 10 sqm, sweeping the
surface for uniform spread of aggregates and surface finished to conform to clause 902.)
Case - IV : Bitumen Impregnated Geotextile (Providing and laying a bitumen impregnated geotextile layer after
cleaning the road surface, geotextile conforming to requirements of clause 704.3, laid over a tack coat with 1.05 kg per
sqm of paving grade bitumen 80 - 100 penetration and constructed to the requirement of clause 704.4.5)

Rate

sqm

73.00

sqm

96.00

sqm

161.00

Recipe Cold Mix (Providing and laying of premix of crushed stone aggregates and emulsion binder, mixed in a batch type
cold mixing plant, laid over prepared surface, by paver finisher, rolled with a pneumatic tyred roller initially and finished with
a smooth steel wheel roller, all as per clause 519.3)

5.22
(i)

75 mm thickness

cum

#VALUE!

(ii)

40 mm thickness

cum

#VALUE!

(iii)

25 mm thickness

cum

#VALUE!

Page 48 of 394

Summary of Rate Analysis


Item No.

Unit

Descriptions

Rate

CHAPTER-6
CEMENT CONCRETE PAVEMENTS

6.1

Dry Lean Cement Concrete Sub- base (Construction of dry lean cement concrete Sub- base over a prepared sub-grade
with coarse and fine aggregate conforming to IS: 383, the size of coarse aggregate not exceeding 25 mm, aggregate
cement ratio not to exceed 15:1, aggregate gradation after blending to be as per table 600-1, cement content not to be less
than 150 kg/ cum, optimum moisture content to be determined during trial length construction, concrete strength not to be
less than 10 Mpa at 7 days, mixed in a batching plant, transported to site, laid with a paver with electronic sensor,
compacting with 8-10 tonnes vibratory roller, finishing and curing.)

cum

#VALUE!

cum

#VALUE!

cum

#VALUE!

cum

#VALUE!

cum

#VALUE!

7.1

Sub- Surface Drain with Geotextiles (Construction of sub surface drain 200 mm dia using geotextiles treated with carbon
black with physical properties as given in clause 702.2.3 formed in to a stable network and a planar geocomposite structure,
joints wrapped with geotextile to prevent ingress of soil, all as per clause 702 and approved drawings including excavation
and backfilling)

metre

#VALUE!

7.2

Narrow Filter Sub- Surface Drain (Construction of a narrow filter sub- surface drain consisting of porous or perforated pipe
laid in narrow trench surrounded by a geotextile filter fabric, with a minimum of 450 mm overlap of fabric and installed as per
clause 702.3 and 309.3.5 including excavation and backfilling)

metre

#VALUE!

sqm

#VALUE!

6.2

6.3

6.4

6.5

6.6

Cement Concrete Pavement (Construction of un-reinforced, dowel jointed, plain cement concrete pavement over a
prepared sub base with 43 grade cement @ 400 kg per cum, coarse and fine aggregate conforming to IS 383, maximum
size of coarse aggregate not exceeding 25 mm, mixed in a batching and mixing plant as per approved mix design,
transported to site, laid with a fixed form or slip form paver, spread, compacted and finished in a continuous operation
including provision of contraction, expansion, construction and longitudinal joints, joint filler, separation membrane, sealant
primer, joint sealant, debonding strip, dowel bar, tie rod, admixtures as approved, curing compound, finishing to lines and
grades as per drawing )
Rolled Cement Concrete Base (Construction of rolled cement concrete base course with coarse and fine aggregate
conforming to IS:383, the size of coarse aggregate not exceeding 25 mm with minimum, aggregate cement ratio15:1 and
minimum cement content of 200 kg/cum, aggregate gradation to be as per table 600-4 after blending, mixing in batching
plant at optimum moisture content, transporting to site, laying with a paver with electronic sensor, compacting with 8-10
tonnes smooth wheeled vibratory roller to achieve, the designed flexural strength, finishing and curing.)

Transition section between rigid and flexible pavement (Due to change in the properties of materials and type of
construction, a gradual changeover from rigid pavement to flexible pavement is desirable to avoid any damage at the butting
joint. After provision of an expansion joint in the cement concrete slab, the thickness of slab should be tapered to 10 cm
over a length of 3 m towards the flexible pavement. The deficiency of thickness caused due to tapering of the slab should be
made up by the asphaltic layers.)
Construction of Base/Sub-base of pavement with lean concrete - fly ash. (Construction of Base/sub-base using
cement, sand, fly ash and coarse aggregates proportioned as per table 4 of IRC: 74/1979 and with water content ratio,
slump and compressive strength as defined in the said table, mix prepared in a batching and mixing plant and compacted
with a vibratory roller 8-10 tonnes capacity within the time limit laid down vide clause 7.6.3 of IRC: 74-1979, construction
joints properly formed at the end of day's work, cured for 14 days, all as specified in IRC: 74-1979 and as per approved
plans.)
Cement - Fly ash concrete pavement. (Construction reinforced-reinforced, dowel jointed, plain cement concrete pavement
over a prepared sub base with 43 grade cement, coarse and fine aggregate conforming to IS 383, maximum size of coarse
aggregate not exceeding 25 mm, replacing cement by fly ash to the extent of 15% and sand by 10%, mixed in a batching
and mixing plant as per approved mix design, transported to site, laid with a fixed form or slip form paver, spread,
compacted and finished in a continuous operation including provision of contraction, expansion, construction and
longitudinal joints, joint filler, separation membrane, sealant primer, joint sealant, debonding strip, dowel bar, tie rod,
admixtures as approved, curing compound, finishing to lines and grades as per drawing )

CHAPTER-7
GEOSYNTHETICS AND REINFORCED EARTH

7.3

Laying Paving Fabric Beneath a Pavement Overlay (Providing and laying paving fabric with physical requirements as per
table 704-2 over a tack coat of paving grade Bitumen 80-100 penetration, laid at the rate of 1 kg per sqm over thoroughly
cleaned and repaired surface to provide a water resistant membrane and crack retarding layer. Paving fabric to be free of
wrinkling and folding and to be laid before cooling of tack coat, brooming and rolling of surface with pneumatic roller to
maximise paving fabric contact with pavement surface)

Page 49 of 394

Summary of Rate Analysis


Item No.

Unit

Descriptions
Laying Boulder Apron in Crates of Synthetic Geogrids (Providing, preparing and laying of geogrid crated apron 1 m x 5
m, 600 mm thick including excavation and backfilling with baffles at 1 metre interval, made with geogrids having
characteristics as per clause 704.2, joining sides with connectors/ring staples, top corners to be tie tensioned, placing of
suitable cross interval ties in layers of 300 mm connecting opposite side with lateral braces and tied with polymer braids to
avoid bulging, constructed as per clause 704.3. filled with stone with minimum size of 200 mm and specific gravity not less
than 2.65, packed with stone spalls, keyed to the foundation recess in case of sloping ground and laid over a layer of
geotextile to prevent migration of fines, all as per clause 704 and laid as per clause 2503.3 and approved design.)

7.4

Rate

cum

#VALUE!

sqm

#VALUE!

metre

#VALUE!
#VALUE!
#VALUE!

Reinforced Earth Retaining Wall (Reinforced earth retaining walls have four main components as under: a) Excavation
for foundation, foundation concrete and cement concrete grooved seating in the foundation for facing elements (facia
material). b) Facia material and its placement. c) Assembling, joining with facing elements and laying of the reinforcing
elements. d) Earthfill with granular material which is to be retained by the wall.)

7.5

(i)
(ii)
A
Type 1

Facing elements of RCC


Assembling, joining and laying of reinforcing elements.
With reinforcing element of steel / Aluminium strips / polymeric strips.
1.Galvanised carbon steel strips

Type 2
Type 3

2.Copper Strips
3.Aluminium Strips

metre
metre

Type 4

4.Stainless steel strips

metre

#VALUE!

Type 5

5.Glass reinforced polymer/fibre reinforced polymer/polymeric strips

metre

#VALUE!

With reinforcing elements of synthetic geogrids

sqm

553.00

Page 50 of 394

Summary of Rate Analysis


Item No.

Unit

Descriptions

Rate

CHAPTER-8
TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES
Cast in Situ Cement Concrete M20 kerb (Construction of cement concrete kerb with top and bottom width 115 and 165
mm respectively, 250 mm high in M 20 grade PCC on M-10 grade foundation 150 mm thick, foundation having 50 mm
projection beyond kerb stone, kerb stone laid with kerb laying machine, foundation concrete laid manually, all complete as
per clause 408)

8.1

Using Concrete Mixer

metre

316.00

Using Concrete Batching and Mixing Plant

metre

302.00

Cast in Situ Cement Concrete M 20 Kerb with Channel (Construction of cement concrete kerb with channel with top and
bottom width 115 and 165 mm respectively, 250 mm high in M 20 grade PCC on M10 grade foundation 150 mm thick, kerb
channel 300 mm wide, 50 mm thick in PCC M20 grade, sloped towards the kerb, kerb stone with channel laid with kerb
laying machine, foundation concrete laid manually, all complete as per clause 408)

8.2

Using Concrete Mixer

metre

591.00

Using Concrete Batching and Mixing Plant

metre

578.00

Printing new letter and figures of any shade (Printing new letter and figures of any shade with synthetic enamel paint
black or any other approved colour to give an even shade)

8.3
(i)
(ii)

Hindi ( Matras commas and the like not to be measured and paid for Half letter shall be counted as half )

cm height per
letter

1.10

English and Roman

cm height per
letter

0.60

Retro- reflectorised Traffic signs (Providing and fixing of retro- reflectorised cautionary, mandatory and informatory sign
as per IRC :67 made of encapsulated lens type reflective sheeting vide clause 801.3, fixed over aluminium sheeting, 1.5
mm thick supported on a mild steel angle iron post 75 mm x 75 mm x 6 mm firmly fixed to the ground by means of properly
designed foundation with M15 grade cement concrete 45 cm x 45 cm x 60 cm, 60 cm below ground level as per approved
drawing)

8.4

(i)

90 cm equilateral triangle

each

#VALUE!

( ii )
( iii )

60 cm equilateral triangle
60 cm circular

each
each

#VALUE!
#VALUE!

( iv )
(v)
(vi )

80 mm x 60 mm rectangular
60 cm x 60 cm square

each
each
each

#VALUE!
#VALUE!
#VALUE!

90 cm high octagon

each

#VALUE!

sqm

#VALUE!

sqm

#VALUE!

tonne

90149.00

tonne

1267.00

8.8

Painting Two Coats on New Concrete Surfaces (Painting two coats after filling the surface with synthetic enamel paint in
all shades on new plastered concrete surfaces)

sqm

80.00

8.9

Painting on Steel Surfaces (Providing and applying two coats of ready mix paint of approved brand on steel surface after
through cleaning of surface to give an even shade)

sqm

71.00

8.10

Painting on Wood Surfaces (Providing and applying two coats of ready mix paint of approved brand on wood surface after
through cleaning of surface to give an even shade)

sqm

78.00

8.11

Painting Lines, Dashes, Arrows etc on Roads in Two Coats on New Work (Painting lines, dashes, arrows etc on roads
in two coats on new work with ready mixed road marking paint conforming to IS:164 on bituminous surface, including
cleaning the surface of all dirt, dust and other foreign matter, demarcation at site and traffic control )
sqm

142.00

( vii )

60 cm x 45 cm rectangular

Direction and Place Identification signs upto 0.9 sqm size board. (Providing and erecting direction and place
identification retro-reflectorised sign asper IRC:67 made of encapsulated lens type reflective sheeting vide clause 801.3,
fixed over aluminium sheeting, 2 mm thick with area not exceeding 0.9 sqm supported on a mild steel single angle iron post
75 x 75 x 6 mm firmly fixed to the ground by means of properly designed foundation with M15 grade cement concrete 45 x
45 x 60 cm, 60 cm below ground level as per approved drawing)

8.5

Direction and Place Identification signs with size more than 0.9 sqm size board. (Providing and erecting direction and
place identification retro- reflectorised sign asper IRC :67 made of encapsulated lens type reflective sheeting vide clause
801.3, fixed over aluminium sheeting, 2 mm thick with area exceeding 0.9 sqm supported on a mild steel angle iron post 75
mm x 75 mm x 6 mm, 2 Nos. firmly fixed to the ground by means of properly designed foundation with M 15 grade cement
concrete45 cm x 45 cm x 60 cm, 60 cm below ground level as per approved drawing)

8.6

Overhead Signs (Providing and erecting overhead signs with a corrosion resistant aluminium alloy sheet reflectorised with
high intensity retro-reflective sheeting of encapsulated lense type with vertical and lateral clearance given in clause 802.2
and 802.3 and installed as per clause 802.7 over a designed support system of aluminium alloy or galvanised steel trestles
and trusses of sections and type as per structural design requirements and approved plans)

8.7

A
B

(i)

Truss and Vertical Support


Aluminium alloy plate for over head sign

Over 10 cm in width

Page 51 of 394

Summary of Rate Analysis


Item No.

Unit

Descriptions
(ii)

sqm

Up to 10 cm in width

Rate
122.00

Painting Lines, Dashes, Arrows etc on Roads in Two Coats on Old Work (Painting lines, dashes, arrows etc on roads in
two coats on old work with ready mixed road marking paint confirming to IS: 164 on bituminous surface, including cleaning
the surface of all dirt, dust and other foreign matter, demarcation at site and traffic control )

8.12
(i)
(ii)

sqm

99.00

sqm

107.00

sqm

436.00

Ordinary Kilometer stone (Precast)

each
each

3943.00
2391.00

Hectometer stone (Precast)

Over 10 cm in width
Up to 10 cm in width

8.13

Road Marking with Hot Applied Thermoplastic Compound with Reflectorising Glass Beads on Bituminous Surface
(Providing and laying of hot applied thermoplastic compound 2.5 mm thick including reflectorising glass beads @ 250 gms
per sqm area, thickness of 2.5 mm is exclusive of surface applied glass beads as per IRC:35 .The finished surface to be
level, uniform and free from streaks and holes.)

8.14

Kilo Metre Stone (Reinforced cement concrete M15grade kilometre stone of standard design as per IRC:8-1980, fixing in
position including painting and printing etc)
(i)
(ii)
(iii)

5th kilometre stone (precast)

each

679.00

8.15

Road Delineators (Supplying and installation of delineators (road way indicators, hazard markers, object markers), 80-100
cm high above ground level, painted black and white in 15 cm wide stripes, fitted with 80 x 100 mm rectangular or 75 mm
dia circular reflectorised panels at the top, buried or pressed into the ground and confirming toIRC-79 and the drawings.)

each

#VALUE!

8.16

Boundary pillar (Reinforced cement concrete M15 grade boundary pillars of standard design as per IRC:25-1967, fixed in
position including finishing and lettering but excluding painting)

each

544.00

metre

253.00

metre

416.00

8.19

Fencing with welded steel wire Fabric 75 mm x 50 mm (Suggestive) (Providing 1.20 metre high fencing with angle iron
posts 50 mm x 50 mm x 6 mm at 3 metre center to center with 0.40 metre embedded in M15 grade cement concrete,
corner, end and every 10th post to be strutted, provided with welded steel wire fabric of 75 mm x 50 mm mesh or 75 mm x
25 mm mesh and fixed to iron posts by flat iron 50 x 5 mm and bolts etc. complete in all respects.)

metre

#VALUE!

8.20

Tubular Steel Railing on Medium Weight steel channel ( ISMC series) 100 mm x 50 mm (Providing, fixing and erecting
50 mm dia steel pipe railing in 3 rows duly painted on medium weight steel channels (ISMC series) 100 mm x 50 mm, 1.2
metres high above ground, 2 m centre to centre, complete as per approved drawings)

metre

2019.00

8.21

Tubular Steel Railing on Precast RCC posts, 1.2 m high above ground level (Providing, fencing and erecting 50 mm dia
painted steel pipe railing in 3 rows on precast M20 grade RCC vertical posts1.8 metres high (1.2 m above GL) with 3 holes
50 mm dia for pipe, fixed 2 metres centre to, complete as per approved drawing)

metre

#VALUE!

metre

#VALUE!

metre

2897.00

G.I Barbed wire Fencing 1.2 metre high (Providing and fixing 1.2 metres high GI barbed wire fencing with 1.8 m angle iron
posts 40 mm x 40 mm x 6 mm placed every 3 metres center to center founded in M15 grade cement concrete, 0.6 metre
below ground level, every 15th post, last but one end post and corner post shall be strutted on both sides and end post on
one side only and provided with 9 horizontal lines and 2 diagonals interwoven with horizontal wires, fixed with GI staples,
turn buckles etc complete as per clause 807 )

8.17

G.I Barbed wire Fencing 1.8 metre high (Providing and fixing 1.8 metres high GI barbed wire fencing with 2.4 m angle iron
posts 50 mm x 50 mm x 6 mm placed every 3 metres center to center founded in M15 grade cement concrete, 0.6 metre
below ground level, every 15th post, last but one end post and corner post shall be strutted on both sides and end post on
one side only and provided with 12 horizontal lines and 2 diagonals interwoven with horizontal wires, fixed with GI staples,
turn buckles etc complete as per clause 807 )

8.18

Reinforced Cement Concrete Crash Barrier (Provision of an Reinforced cement concrete crash barrier at the edges of
the road, approaches to bridge structures and medians, constructed with M-20 grade concrete with HYSD reinforcement
conforming to IRC:21 and dowel bars 25 mm dia, 450 mm long at expansion joints filled with pre-moulded asphalt filler
board, keyed to the structure on which it is built and installed as per design given in the enclosure to MOST circular No.
RW/NH - 33022/1/94-DO III dated 24 June 1994 as per dimensions in the approved drawing and at locations directed by the
Engineer, all as specified)

8.22

(i)
8.23

M 20 grade concrete
Metal Beam Crash Barrier

Type - A, "W" : Metal Beam Crash Barrier (Providing and erecting a "W" metal beam crash barrier comprising of 3 mm
thick corrugated sheet metal beam rail, 70 cm above road/ground level, fixed on ISMC series channel vertical post, 150 x
75 x 5 mm spaced 2 m centre to centre, 1.8 m high, 1.1 m below ground/road level, all steel parts and fitments to be
galvanised by hot dip process, all fittings to conform to IS:1367 and IS:1364, metal beam rail to be fixed on the vertical
post with a spacer of channel section 150 x 75 x 5 mm, 330 mm long complete as per clause 810)

Page 52 of 394

Summary of Rate Analysis


Item No.

Flexible Crash Barrier, Wire Rope Safety Barrier (Providing and erecting a wire rope safety barrier with vertical posts of
medium weight RS Joist (ISMB series) 100 mm x 75 mm (11.50 kg/m), 1.50 m long 0.85 m above ground and 0.65 m below
ground level, split at the bottom for better grip, embedded in M 15 grade cement concrete 450 x 450 x 450 mm, 1.50 m
center to center and with 4 horizontal steel wire rope 40 mm dia and anchored at terminal posts 15 m apart. Terminal post to
be embedded in M 15 gradecementconcretefoundation2400 x 450 x 900 mm (depth), strengthened by a strut of RS joist
100 x 75 mm, 2 m long at 450 inclination and a tie 100 x 8 mm, 1.50 m long at the bottom, all embedded in foundation
concrete as per approved design and drawing, rate excluding excavation and cement concrete.)

8.25

8.26

metre

3853.00

metre

#VALUE!

metre

2026.00

metre

830.00

Plantation (Plantation of shrubs and plants of approved species in the median. apart from cutting off glare from vehicle
coming from opposite direction, these plants provide a pleasant envoirenment and are eco-friendly. The rate for this item is
available in the chapter 11 on horticulture. )

Anti - Glare Screen with 25 mm steel pipe framework fixed with circular and rectangular vans (Providing and
erecting an anti - glare screen with 25 mm dia vertical pipes fabricated and framed in the form of panels of one metre
length and 1.75 mtr height fixed with circular vane 250 mm dia at top and rectangular vane 600 x 300 mm at the middle,
made out of steel sheet of 3 mm thickness, end vertical pipes of the panel made larger for embedding in foundation
concrete, applying 2 coats of paint on all exposed surfaces, all as per approved design and drawings.)
Anti - Glare Screen with Rectangular Vane of MS sheet (Providing and erecting anti - glare screen with rectangular
vanes of size 750 x 500 mm made from MS sheet, 3 mm thick and fixed on MS angle 50 x 50 x 6 mm at an angle of 450
to the direction of flow of traffic, 1.5 m center to center, top edge of the screen 1.75 m above ground level, vertical post
firmly embedded in cement concrete foundation 0.60 m below ground level, applying 2 coats of paint on exposed faces,
all complete as per approved design and drawings)
Street Lighting (Providing and erecting street light mounted on a steel circular hollow pole of standard specifications for
street lighting, 9 m high spaced 40 m apart, 1.8 m overhang on both sides if fixed in the median and on one side if fixed on
the footpath, fitted with sodium vapour lamp and fixed firmly in concrete foundation.)

8.27
(i)

For Fixing in Median

each

#VALUE!

(ii)

For fixing in Footpath

each

#VALUE!

each

#VALUE!

metre
metre
metre

#VALUE!
#VALUE!
#VALUE!

Lighting on Bridges (Providing and fixing lighting on bridges, mounted on steel hollow circular poles of standard
specifications, 5 m high fixed on parapets with cement concrete, 20 m apart and fitted with sodium vapour lamp)

8.28

Cable Duct Across the Road (Providing and laying of a reinforced cement concrete pipe duct, 300 mm dia, across the
road (new construction), extending from drain to drain in cuts and toe of slope to toe of slope in fills, constructing head walls
at both ends, providing a minimum fill of granular material over top and sides of RCC pipe as per IRC:98-1997, bedded on a
0.3 m thick layer of granular material free of rock pieces, outer to outer distance of pipe at least half dia of pipe subject to
minimum 450 mm in case of double and triple row ducts, joints to be made leak proof, invert level of duct to be above higher
than ground level to prevent entry of water and dirt, all as per IRC: 98 - 1997 and approved drawings.)

8.29

(i)
(ii)
(iii)

8.32

Rate

Anti - Glare Devices in Median

8.31

Type - B, "THRIE" : Metal Beam Crash Barrier (Providing and erecting a "Thrie" metal beam crash barrier comprising
of 3 mm thick corrugated sheet metal beam rail, 85 cm above road/ground level, fixed on ISMC series channel vertical
post, 150 x 75 x 5 mm spaced 2 m centre to centre, 2 m high with 1.15 m below ground level, all steel parts and fitments
to be galvanised by hot dip process, all fittings to conform to IS:1367 and IS:1364, metal beam rail to be fixed on the
vertical post with a space of channel section 150 x 75 x 5 mm, 546 mm long complete as per clause 810)

Road Traffic Signals electrically operated (Since it is a ready made item commercially produced and erected by
specialised firm in the electrical and electronic field, rate may be taken based on market enquiry from firms specialised in
this field and ISI certified for the approved design and drawing.)

8.24

8.30

Unit

Descriptions

Single Row for one utility service


Double Row for two utility services
Triple Row for three utility services
Highway Patrolling and Traffic Aid Post (It is proposed to locate one Traffic Aid Post every 50-60 km of the highway. )
Items related to under pass/ subway/ overhead bridge/ overhead foot bridge (The items involved for underpass/
subway/ overhead bridge/ overhead foot bridge are earthwork, plain cement concrete, plastering, painting, information sign
etc. The rates for these items are available in respective chapters which can be adopted for the quantities derived from the
approved designs and drawings)
Traffic Control System and Communication system (Providing a traffic control centre and communication system
including telecommunication facilities and related accessories, CCTV, radar, vehicle detection camera, central computer
system These are specialised item of telecommunication system and are the commercial products. The designer is required
to contact the manufacturers to ascertain market prices. In case of civil works required to be executed for these
installations, pricing may be done as per rates in relevant chapters for quantities derived approved design and drawing.)

Page 53 of 394

Summary of Rate Analysis


Item No.

Descriptions

8.33

Gantry Mounted Variable Message Sign board (Providing and erecting gantry mounted variable message sign board
electronically operated capable of flashing the desired message over a designed support system of aluminium alloy or
galvanised steel, erected as per approved design and drawings and with lateral clearance as per clause 802.3)

Unit

(i)

Gantry Support System

(ii)

Message Display (Message display board 6 sqm electronically operated with complete electronic fitments for flashing
the pre-determined messages.)

8.34

Rate

tonne

87387.00

Traffic Impact Attenuators at Abutments and Piers


A

With Scrap Tyres (Provision and installation of traffic attenuators at abutment/pier of flyovers bridges using scrap tyres
of size 100 x 20 retrieved from trucks laid in 2 rows and 4 tiers, one above the other and tied with 20 mm wire rope as
per approved design and drawings.)

sqm

#VALUE!

Using Plastic/Steel Barrel, Filled with Sand (Provision and installation of traffic impact attenuator at abutment/pier of
flyovers bridges using plastic/steel barrels 0.60 m dia and 1.0 m in height, filled with sand in three rows and tied with20
mm steel wire rope as per approved design and drawings)

sqm

#VALUE!

With HI - DRO cell Sandwich (Patented) ((In this patented HI - DRO cell system, water gets discharged from plastic
tubes on impact over a pre-determined time, thus absorbing the energy))

sqm

#VALUE!

8.35

Road Markers/Road Stud with Lense Reflector (Providing and fixing of road stud 100x 100 mm, die cast in aluminium,
resistant to corrosive effect of salt and grit, fitted with lense reflectors, installed in concrete or asphaltic surface by drilling
hole 30 mm upto a depth of 60 mm and bedded in a suitable bituminous grout or epoxy mortar, all as per BS 873 part
4:1973)

each

#VALUE!

8.36

Traffic Cone (Provision of red fluorescent with white reflective sleeve traffic cone made of low density polyethylene (LDPE)
material with a square base of 390 x 390 x 35 mm and a height of 770 mm, 4 kg in weight, placed at 1.5 m interval, all as
per BS 873)

each

#VALUE!

8.37

Roadside Amenities

Rest Areas (Providing plainly furnished accommodation for rest rooms, dormitories, restaurants, stalls, shops, petrol pump,
telephone booth, first aid room, traffic aid post, police assistance booth, including electricity, toilet and sewerage system
Pricing may be done based on current plinth area rates approved by PWD/CPWD/MES for a particular zone. Area is
required to be assessed for specific location as per actual site conditions)

Parking areas and Bus Laybyes for Trucks, Buses and Light vehicles (Pricing of parking areas may be done for the
quantities of various items based on the approved dimensions and pavement design for a particular terrain and soil. Rates
for items may be from respective chapters.)

C
8.38

8.39

8.40

8.41

8.42

Lawn (Providing a lawn planted with grass and its maintenance )


Rumble Strips (Provision of 15 nos rumble strips covered with premix bituminous carpet, 15-20 mm high at center, 250 mm
wide placed at 1 m center to center at approved locations to control speed, marked with white strips of road marking paint.)
Policeman Umbrella (Provision of a 2 m high (floor to roof) umbrella for traffic policeman at road crossings, where
necessary, installed on a raised platform, built on a central support of a steel pipe 100 mm dia, roof made of 25 mm dia steel
pipe to provide covered area of 3 sqm, roofed with CGI sheets, all steel parts to be given 2 coats of paint)

sqm

each

High Mast Pole Lighting at Interchanges and Flyovers (Providing and erecting a high mast pole lighting with 30 m high
hot dip galvanised mast designed to withstand forces exerted with wind speeds of 180 km per hour with 3 seconds gust, as
per IS:875 (Part 3) - 1978, fitted with a base flange, door at the base of mast with heavy duty internal lock, lantern
carriage, suitable winching arrangement for safe working load of 750 kg and high powered electrically driven power tools
for raising and lowering of lantern carriage, flexible 8 core electric cable, lightening conductor, earthing terminal, and
fixing 2 nos aviation obstruction lights on top of the mast, all complete as per approved design and drawings This is a
specialised work and is generally done by firms who specialise in such jobs. The detailed designs and estimates are
submitted by the firms alongwith their tender for checks by the Department. The cost of this work is required to be worked
out based on approved design, drawings and estimate of the lowest tender. A separate contract for this work is concluded
as the contractors for road and bridge works generally donot undertake such jobs.)
Toll Plaza (The construction, operation and maintenance of Toll Plaza can be broken into separate items of work as under
based on the approved design and drawings:-)
Safety Devices and signs in Construction Zones (Provision and fixing of traffic signs for limited period at suitable
locations in construction zone comprising of warning zone, approach transition zone, working zone and terminal transition
zone with a minimum distance of 60 cm from the edge of the kerb in case of kerbed roads and 2 to 3 m from the edge of the
carriageway in case of un-kerbed roads, the bottom edge of the lowest sign plate to be not less than 2 m above the road
level, fixed on 60 mm x 60 mm x 6 mm angle iron post, founded and installed as per approved design and drawings,
removed and disposed of after completion of construction work, all as per IRC:SP:55-2001)

8.43

Portable Barricade in Construction Zone (Installation of a steel portable barricade with horizontal rail 300 mm wide, 2.5
m in length fitted on a 'A' frame made with 45 x 45 x 5 mm angle iron section, 1.5 m in height, horizontal rail painted (2
coats) with yellow and white stripes, 150 mm in width at an angle of 450, 'A' frame painted with 2 coats of yellow paint,
complete as per IRC:SP:55-2001 )

8.44

Permanent Type Barricade in Construction Zone

Page 54 of 394

each

2826.00

Summary of Rate Analysis


Item No.

Unit

Descriptions

Rate

With Steel Components (Construction of a permanent type barricade made of steel components, 1.5 m high from road
level, fitted with 3 horizontal rails 200 mm wide and 4 m long on 50 x 50 x 5 mm angle iron vertical support, painted with
yellow and white strips, 150 mm in width at an angle of450, complete as per IRC:SP:55-2001 )

each

4440.00

With Wooden Components (Construction of a permanent type barricade made of wooden components, 1.5 m high
from road level, fitted with 3 horizontal planks 200 mm wide and 3.66 m long on 100 x 100mm wooden vertical post,
painted with yellow and white striups, 150 mm in width at an angle of450, complete as per IRC:SP:55-2001 )

each

#VALUE!

With Bricks (Construction of a permanent type barricade made with brick work in mud mortar, 1.5 m high, 4 m long,
600 mm thick, plastered with cement mortar 1:6, painted with yellow and white strips)

each

12268.00

8.45

Drum Delineator in Construction Zone (Provision of metal drum/empty bitumen drum delineator, 300 mm in diameter,
800 mm high, filled with earth for stability, painted in circumferential strips of alternate black and white 100 mm wide fitted
with reflectors 3 Nos of 7.5 cm dia, all as per IRC:SP:55-2001)

each

666.00

8.46

Flagman (Positioning of a smart flagman with a yellow vest and a yellow cap and a red flag 600 x 600 mm securely
fastened to a staff 1 m in length for guiding the traffic)

each

#VALUE!

cum

4532.00

metre
metre

#VALUE!
#VALUE!

CHAPTER-9
PIPE CULVERTS
9.1

PCC 1:3:6 in Foundation (Plain cement concrete 1:3:6 mix with crushed stone aggregate 40 mm nominal size
mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days.)

9.2

Laying Reinforced Cement Concrete Pipe NP4/prestrssed concrete pipe on first class bedding in single row .
(Laying Reinforced cement concrete pipe NP4/prestrssed concrete pipe for culverts on first class bedding of granular
material in single row including fixing collar with cement mortar 1:2 but excluding excavation, protection works, backfilling,
concrete and masonry works in head walls and parapets . )
A
B

9.3

1000 mm dia
1200 mm dia
Laying Reinforced Cement Concrete Pipe NP 4 /prestrssed concrete pipe on first class bedding in double row .
(Laying Reinforced cement concrete pipe NP4 /prestrssed concrete pipe for culverts on first class bedding of granular
material in double row including fixing collar with cement mortar 1:2 but excluding excavation, protection works, backfilling,
concrete and masonry works in head walls and parapets . )

1000 mm dia

metre

#VALUE!

1200 mm dia

metre

#VALUE!

Page 55 of 394

Summary of Rate Analysis


Item No.

Unit

Descriptions

Rate

CHAPTER-10
MAINTENANCE OF ROADS
10.1

Restoration of Rain Cuts (Restoration of rain cuts with soil, moorum, gravel or a mixture of these, clearing the loose soil,
benching for 300 mm width, laying fresh material in layers not exceeding 250 mm and compacting with plate compactor or
power rammers to restore the original alignment, levels and slopes)

cum

#VALUE!

10.2

Maintenance of Earthen Shoulder (filling with fresh soil) (Making up loss of material/ irregularities on shoulder to the
design level by adding fresh approved soil and compacting it with appropriate equipment.)

sqm

#VALUE!

10.3

Maintenance of Earth Shoulder (stripping excess soil) (Stripping excess soil from the shoulder surface to achieve the
approved level and compacting with plate compactor)

sqm

#VALUE!

sqm

131.00

for grading I Material

sqm

294.00

for grading II Material

sqm

289.00

10.6

Crack Filling (Filling of crack using slow - curing bitumen emulsion and applying crusher dust in case crack are wider than
3mm.)

metre

4.00

10.7
10.8 A

Dusting (Applying crusher dust to areas of road where bleeding of excess bitumen has occurred.)
Fog Seal (ref item 5.17)

sqm
sqm

0.58
36.00

Crack Prevention courses. (ref item 5.21)


Stress Absorbing Membrane (SAM) crack width less than 6 mm

sqm

58.00

sqm
sqm
sqm

73.00
96.00
161.00

sqm

73.00

sqm
sqm

49.00
24.00

sqm
sqm

82.00
67.00

Filling Pot- holes and Patch Repairs with open - graded Premix surfacing, 20mm. (Removal of all failed material,
trimming of completed excavation to provide firm vertical faces, cleaning of surface, painting of tack coat on the sides and
base of excavation as per clause 503, back filling the pot holes with hot bituminous material as per clause 511, compacting,
trimming and finishing the surface to form a smooth continuous surface, all as per clause 3004.2)

10.4

Filling Pot- holes and Patch Repairs with - Bituminous concrete, 40mm. (Removal of all failed material, trimming of
completed excavation to provide firm vertical faces, cleaning of surface, painting of tack coat on the sides and base of
excavation as per clause 503, back filling the pot holes with hot bituminous material as per clause 504, compacting,
trimming and finishing the surface to form a smooth continuous surface, all as per clause 3004.2)

10.5

(i)
(ii)

B
(i)
(ii)
(iii)
(iv)
C

Stress Absorbing Membrane (SAM) with crack width 6 mm to 9 mm


Stress Absorbing Membrane (SAM) crack width above 9 mm and cracked area above 50 %
Bitumen Impregnated Geotextile
Slurry Seal (ref item 5.15)

(i)
(ii)
(iii)
D
(i)
(ii)

5 mm thickness
3 mm thickness
1.5 mm thickness
Surface Dressing for maintance works. (ref item 5.9)
19 mm nominal chipping size
13 mm nominal size chipping

10.9

Repair of joint Grooves with Epoxy Mortar Repair of spalled joint grooves of contraction joints, longitudinal joints and
expansion joints in concrete pavements using epoxy mortar or epoxy concrete)

metre

#VALUE!

10.10

Repair of old Joints Sealant (Removal of existing sealant and re sealing of contraction, longitudinal or expansion joints in
concrete pavement with fresh sealant material)

metre

#VALUE!

metre

52.00

10.11

Hill Side Drain Clearance (Removal of earth from the choked hill side drain and disposing it on the valley side manually)

10.12

Land Slide Clearance in soil (Clearance of land slides in soil and ordinary rock by a bull-dozer D 80 A-12, 180 HP and
disposal of the same on the valley side)

cum

75.00

10.13

Land slide Clearance in Hard Rock Requiring Blasting (Clearing of land slide in hard rock requiring blasting for 50% of
the boulders and disposal of the same on the valley side.)

cum

116.00

10.14

Snow Clearance on Roads with Dozer (Snow clearance from road surface by a bull- dozer 165 Hp and disposing it on the
valley side)

cum

5.00

10.15

Snow Clearance on Roads with Snow Blowers (Snow clearance from road surface by a snow blower and disposing on
the valley side.)

cum

#VALUE!

Page 56 of 394

Summary of Rate Analysis


Item No.

Unit

Descriptions

Rate

CHAPTER-11
HORTICULTURE
11.1

Spreading of Sludge Farm Yard Manure or/and good Earth (Spreading of sludge farm yard manure or/ and good earth in
required thickness (cost of sludge, farm- yard manure or/and good earth to be paid for separately))

11.2

Grassing with ' Doobs' Grass (Grassing with 'Doobs' grass including watering and maintenance of the lawn for 30 days or
more till the grass forms a thick lawn free from weeds and fit for moving including supplying good earth if needed)
(i)
(ii)

In rows 15 cm apart in either direction


In rows 7.5 cm apart in either direction

cum

33.00

sqm
sqm

#VALUE!
#VALUE!

11.3

Making Lawns including Ploughing and Dragging with 'Swagha' Breaking of Clod (Making lawns including ploughing
and breaking of clod, removal of rubbish, dressing and supplying doobs grass roots and planting at 15 cm apart, including
supplying and spreading of farm yard manure at rate of 0.18 cum per 100 sqm)

sqm

#VALUE!

11.4

Maintenance of Lawns or Turfing of Slopes (Maintenance of lawns or Turfing of slopes (rough grassing)
one year including watering etc)

sqm

102.00

11.5

Turfing Lawns with Fine Grassing including Ploughing, Dressing (Turfing lawns with fine grassing including ploughing,
dressing including breaking of clods, removal of rubbish, dressing and supplying doobs grass roots at 10 cm apart,
including supplying and spreading of farm yard manure at rate of0.6 cum per 100 sqm)

sqm

#VALUE!

11.6

Maintenance of Lawns with Fine Grassing for the First Year

sqm

111.00

11.7

a) Planting Permanent Hedges including Digging of Trenches (Planting permanent hedges including digging of
trenches, 60 cm wide and 45 cm deep, refilling the excavated earth mixed with farmyard manure, supplied at the rate of
4.65 cum per 100 metres and supplying and planting hedge plants at 30 cm apart)

metre

#VALUE!

metre

#VALUE!

km
km

#VALUE!
#VALUE!

(b)
11.8

Maintenance of Hedge for one year


a)

(b)

for a period of

Planting Flowering Plants and Shrubs in Central Verge


Maintenance of Flowering Plants and Shrubs in Central Verge for one Year

11.9

Planting of Trees and their Maintenance for one Year (Planting of trees by the road side (Avenue trees) in 0.60 m dia
holes, 1 m deep dug in the ground, mixing the soil with decayed farm yard/sludge mannure, planting the saplings,
backfilling the trench, watering, fixing the tree guard and maintaining the plants for one year)

each

#VALUE!

11.10

Renovation Lawns including, Weeding, Forking the Ground, Top Dressing with Forked Soil (Renovation lawns
including, weeding, forking the ground, top dressing with forked soil, watering and maintenance the lawns, for 30 days or
more, till the grass forms a thick lawn, free from weeds, and fit for moving and disposal of rubbish as directed, including
supplying good earth, if needed but excluding the cost of well decayed farm yard manure)

sqm

17.00

11.11

Supply at Site Well Decayed Farm Yard Manure (Supply at site of work well decayed farm yard manure, from any
available source, approved by the engineer in charge including screening and stacking)

cum

11.12

Supply at Site of Work/ Store - Deoiled Neem Cake (Supply at site of work/ store- deoiled neem cake duly packed in
used gunny bags)

11.13

Supplying Sludge (Supplying sludge duly stacked at site/ store)

11.14

11.15

11.16

11.17

11.18

Half Brick Circular Tree Guard, in 2nd class Brick, internal diametre 1.25 metres, and height 1.2 metres, above
ground and 0.20 metre below ground (Half brick circular tree guard, in 2nd class brick, internal diametre 1.25 metres,
and height 1.2 metres, above ground and 0.20 metre below ground, bottom two courses laid dry, and top three courses in
cement mortar 1:6 ( 1 cement 6 sand) and the intermediate courses being in dry honey comb masonry, as per design
complete)
Edging with 2nd class Bricks, laid dry lengthwise (Edging with 2nd class bricks, laid dry lengthwise, including
excavation, refilling, consolidation, with a hand packing and spreading nearly surplus earth within a lead of 50
metres)
Making Tree Guard 53 cm dia and 1.3 m high as per design from empty bitumen drum (Making tree guard 53 cm dia
and 1.3 m high as per design from empty bitumen drum, slit suitably to permit sun and air, (supplied by the department at
stock issue rate) including providing and fixing 2 nos MS sheet rings 50 x 0.5 mm with rivets, complete in all respect)

Making Tree Guard 53 cm dia and 2 metres high as per design from empty bitumen drums (Making tree guard 53 cm
dia and 2 metres high as per design from empty bitumen drums, slit suitably to permit sun and air, ( supplied by the
department at stock issue rate) including providing and fixing four legs 40 cm long of 30 x 3 mm MS riveted to tree guard
and providing and fixing 2 nos MS sheet rings 50 x 0.5 mm with rivets complete in all respects)

Wrought Iron and Mild Steel Welded Work (Wrought iron and mild steel welded work) (using angles, square bars,
tees and channel grills, grating frames, gates and tree guards of any size and design etc. including cost of screens and
welding rods or bolts and nuts complete fixed in position but without the cost of excavation and concrete for fixing which will
be paid separately)

Page 57 of 394

quintal
cum

each

1513.00

metre

28.00

each

479.00

each

820.00

quintal

8507.00

Summary of Rate Analysis


Item No.

Descriptions

11.19

Tree Guard with MS Iron (Providing and fixing MS iron tree guard 60 cm dia and 2 metre high above ground level formed
of 4 Nos (25 x 6 mm) and 8 Nos (25 x 3 mm) vertical MS riveted to 3 Nos (25 x 6 mm) iron rings in two halves, bolted
together with 8 mm dia and 30 mm long bolts including painting two coats with paint of approved brand over a coat of
priming, complete in all respects.)

each tree
guard

1980.00

11.20

Tree Guard with MS Angle Iron and Steel Wire (Providing and fixing tree guard 0.60 metre square, 2.00 metre high
fabricated with MS angle iron 30 x 30 x 3 mm, MS iron 25 x 3 mm and steel wire3 mm dia welded and fabricated as per
design in two halves bolted together)

each tree
guard

2737.00

Compensatory Afforestation (Planting trees as compensatory afforestation at the rate of 290 trees per hectare at a
spacing of 6 m by grubbing and leveling the ground upto a depth of 150 mm, digging holes 0.9 m dia, 1 m deep, mixing
farm yard/sludge manure with soil, planting of sapling 2 m high with 25 cm dia stem, backfilling the hole and watering)

hectare

#VALUE!

11.21

Unit

Page 58 of 394

Rate

Summary of Rate Analysis


Item No.

Unit

Descriptions

Rate

CHAPTER-12
FOUNDATIONS
Excavation for Structures (Earth work in excavation of foundation of structures as per drawing and technical specification,
including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of
sides and bottom and backfilling with approved material.)

12.1
I
A

Ordinary soil
Manual Means
(i)
(ii)
(iii)

3 m to 6 m depth

cum
cum

187.00
240.00

Above 6 m depth

cum

320.00

upto 3 m depth

Mechanical Means
(i)

Depth upto 3 m

cum

58.00

(ii)

Depth 3 m to 6 m

cum

66.00

(iii)

Depth above 6m

cum

83.00

cum

267.00

cum

72.00

Hard rock ( requiring blasting )


Manual Means

cum

563.00

Hard rock ( blasting prohibited )


Mechanical Means

cum

504.00

cum

653.00

cum
cum

151.00
416.00

II

Ordinary rock (not requiring blasting)

Manual Means
(i)

B
III
IV
V
(i)

Depth upto 3 m
Mechanical Means

Marshy soil
upto 3 m depth
A
B
VI

Manual means
Mechanical Means
Back Filling in Marshy Foundation Pits

12.2

Filling Annular Space Around Footing in Rock (Lean cement concrete 1:3:6 nominal mix. Rate may be taken as per
items 13.4.)

12.3

Sand Filling in Foundation Trenches as per Drawing & Technical Specification

cum

1134.00

12.4

PCC 1:3:6 in Foundation (Plain cement concrete 1:3:6 nominal mix in foundation with crushed stone aggregate 40 mm
nominal size mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days.)

cum

4952.00

12.5

Brick masonry work in cement mortar 1:3 in foundation complete excluding pointing and plastering, as per
drawing and technical specifications

cum

5792.00

cum

5916.00

cum
cum
cum

6590.00
5449.00
5286.00

cum

5568.00

cum

4916.00

cum
cum

5820.00
6465.00

12.6 A

Cement mortar1:3 (1cement :3 sand)


Cement mortar1:2 (1cement :2 sand)

B
C
D

Cement mortar1:4 (1cement :4 sand)


Cement mortar1:6 (1cement :6 sand)

12.7
(a)
(b)

Stone masonry work in cement mortar 1:3 in foundation complete as drawing and Technical Specification
Square Rubble Coursed rubble masonry( first sort )
Random Rubble Masonry
Plain/Reinforced cement concrete in open foundation complete as per drawing and technical specifications

12.8
A
B

PCC Grade M15


PCC Grade M20
RCC Grade M20

C
Case I
Case II

Using concrete mixer


With Batching Plant, Transit Mixer and Concrete Pump
PCC Grade M25

cum
cum

6662.00
#VALUE!

Case I
Case II

Using concrete Mixer


With Batching Plant, Transit Mixer and Concrete Pump

cum
cum

6899.00
#VALUE!

Case I

RCC Grade M25


Using concrete Mixer
With Batching Plant, Transit Mixer and Concrete Pump

cum

7101.00

cum

#VALUE!

PCC Grade M30


Using Concrete Mixer
Using Batching Plant, Transit Mixer and Concrete Pump

cum

6931.00

cum

#VALUE!

cum
cum

7111.00
#VALUE!

E
Case II
F
Case I
Case II
G
Case I
Case II

RCC Grade M30


Using Concrete Mixer
Using Batching Plant, Transit Mixer and Concrete Pump

Page 59 of 394

Summary of Rate Analysis


Item No.

Unit

Descriptions

Rate

RCC Grade M35


Case I

Using Concrete Mixer

cum

7201.00

Case II

Using Batching Plant, Transit Mixer and Concrete Pump

cum

#VALUE!

Providing and constructing temporary island 16 m diameter for construction of well foundation for 8m dia. Well.

12.9
A

Assuming depth of water 1.0 m and height of island to be 1.25m.

each

96675.00

Assuming depth of water 4.0 m and height of island 4.5 m.

each

#VALUE!

Providing and constructing one span service road to reach island location from one pier location to another pier
location

metre

4366.00

tonne

89541.00

12.10

Providing and laying cutting edge of mild steel weighing 40 kg per metre for well foundation complete as per
drawing and technical specification.

12.11

Plain/Reinforced cement concrete, in well foundation complete as per drawing and technical specification

Well curb

(i)

RCC M20 Grade


Case I

Using concrete mixer

cum

7687.00

Case II

With Batching Plant, Transit Mixer and Concrete Pump

cum

#VALUE!

(ii)

RCC M25 Grade


Case I

Case II
(iii)
Case I
Case II
B
(I)
(ii)
(iii)

Using concrete mixer


With Batching Plant, Transit Mixer and Concrete Pump
RCC M35 Grade
Using concrete mixer
With Batching Plant, Transit Mixer and Concrete Pump
Well steining
PCC M15 Grade
PCC M20 Grade

cum

8215.00

cum

#VALUE!

cum
cum

8390.00
#VALUE!

cum
cum

6156.00
6839.00

cum
cum

7047.00
#VALUE!
7315.00
#VALUE!

RCC M20 Grade

Case I
Case II
(iv)

Using concrete mixer


With Batching Plant, Transit Mixer and Concrete Pump
PCC M25 Grade

Case I
Case II

Using concrete mixer


With Batching Plant, Transit Mixer and Concrete Pump

cum
cum

Case I

RCC M25 Grade


Using concrete mixer
With Batching Plant, Transit Mixer and Concrete Pump

cum

7530.00

cum

#VALUE!

PCC M30 Grade


Using concrete mixer
With Batching Plant, Transit Mixer and Concrete Pump

cum

7367.00

cum

#VALUE!

cum
cum

7559.00
#VALUE!

cum
cum

7691.00
#VALUE!
#VALUE!

cum
cum

#VALUE!
#VALUE!

cum
cum

#VALUE!
#VALUE!

Using Concrete Mixer


Using Batching Plant, Transit Mixer and Crane/concrete pump
PCC Grade M35

cum
cum

#VALUE!
#VALUE!

Using Concrete Mixer


Using Batching Plant, Transit Mixer and Crane/concrete pump

cum

#VALUE!

cum

#VALUE!

cum

#VALUE!

(v)
Case II
(vi)
Case I
Case II
(vii)
Case I
Case II
(viii)
Case I
Case II
(ix)
C
(i)
Case I
Case II
(ii)
Case I
Case II
(iii)
Case I
Case II
(iv)
Case I
Case II
D
(I)
Case I

RCC M30 Grade


Using concrete mixer
With Batching Plant, Transit Mixer and Concrete Pump
RCC M35 Grade
Using concrete mixer
With Batching Plant, Transit Mixer and Concrete Pump
RCC M40 Grade
Bottom Plug
PCC Grade M20
Using Concrete Mixer
Using Batching Plant, Transit Mixer and Crane/concrete pump
PCC Grade M25
Using Concrete Mixer
Using Batching Plant, Transit Mixer and Crane/concrete pump
PCC Grade M30

Intermediate plug
Grade M20 PCC
Using Concrete Mixer

Page 60 of 394

Summary of Rate Analysis


Item No.

Unit

Descriptions

Case II
(ii)

Using Batching Plant, Transit Mixer and Crane/concrete pump

Rate

cum

#VALUE!

Grade M25 PCC


Case I

Using Concrete Mixer

cum

#VALUE!

Case II

Using Batching Plant, Transit Mixer and Crane/concrete pump

cum

#VALUE!

cum

#VALUE!

cum

#VALUE!

cum

5597.00

cum

6217.00

(iii)
Case I
Case II
E
(i)
Case I
(ii)

Grade M30 PCC


Using Concrete Mixer
Using Batching Plant, Transit Mixer and Crane/concrete pump
Top plug
Grade M15 PCC
Using Concrete Mixer
Grade M20 PCC

Case I
(iii)

Using Concrete Mixer


Grade M25 PCC

Case I
Case II
(iv)

Using Concrete Mixer

cum

6650.00

Using Batching Plant, Transit Mixer and Crane/concrete pump

cum

#VALUE!

cum
cum

6698.00
#VALUE!

cum
cum

6613.00
#VALUE!

cum
cum

7101.00
#VALUE!

cum
cum

7111.00
#VALUE!

cum
cum

7201.00
#VALUE!

cum

#VALUE!

metre
metre

2654.00
3571.00

metre

4717.00

metre

8847.00
10617.00

Grade M30 PCC

Case I
Case II
F
(i)
Case I
Case II
(ii)
Case I
Case II
(iii)
Case I
Case II
(iv)
Case I
Case II
(v)

Using Concrete Mixer


Using Batching Plant, Transit Mixer and Crane/concrete pump
Well cap
RCC Grade M20
Using concrete Mixer
Using Batching Plant, Transit Mixer and Concrete Pump
RCC Grade M25
Using concrete Mixer
Using Batching Plant, Transit Mixer and Concrete Pump
RCC Grade M30
Using Concrete Mixer
Using Batching Plant, Transit Mixer and Concrete Pump
RCC Grade M35
Using Concrete Mixer
Using Batching Plant, Transit Mixer and Concrete Pump
RCC M40 Grade
Sinking of 6 m external diameter well ( other than pneumatic method of sinking ) through all types of strata namely
sandy soil, clayey soil and rock as shown against each case, complete as per drawing and technical
specifications. Depth of sinking is reckoned from bed level.

12.12
A

Sandy soil
Depth below bed level upto 3.0 M

(i)
(ii)

Beyond 3m upto 10m depth


Beyond 10m upto 20m

(iii)
a
(iv)
a
b
(v)
a
b
B
(i)
(ii)

Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter
Beyond 20m upto 30 m
Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter
Add 20% of cost for Kentledge including supports, loading arrangement and Labour .
Beyond 30m upto 40 m
Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter
Add 20% of cost for Kentledge including supports, loading arrangement and Labour .
Clayey soil ( 6m dia. Well )
Depth below bed level upto 3.0 M
Beyond 3m upto 10m depth
Beyond 10 m upto 20 m

(iii)
a
b
(iv)
a
b
c
(v)
a
b
c

Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter
Add for dewatering @ 5% of cost, if required.
Beyond 20m upto 30 m
Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter
Add 5% of cost for dewatering of the cost, if required
Add 25% of cost for Kentledge including supports, loading arrangement and Labour ).
Beyond 30m upto 40 m
Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter
Add 5% of cost for dewatering, if required
Add 20% of cost for Kentledge including supports, loading arrangement and Labour).

Page 61 of 394

metre
metre

21019.00
25223.00

metre
metre

3581.00
8033.00

metre

10610.00

metre

11140.00

metre

19900.00

metre
metre

26119.00
24875.00

metre
metre

47281.00
59574.00

metre

56738.00

Summary of Rate Analysis


Item No.

Unit

Descriptions

Rate

Soft rock (6m dia well )

(i)

Depth of soft rock strata upto 3m

metre

17061.00

metre

15975.00

metre
metre

7283.00
4741.00

metre

6261.00

Hard rock (6m dia well )

(i)

Depth of soft rock strata upto 3m


Sinking of 7 m external diameter well ( other than pneumatic method of sinking ) through all types of strata namely
sandy soil, clayey soil and rock as shown against each case, complete as per drawing and technical
specifications. Depth of sinking is reckoned from bed level.

12.13
A

Sandy soil

(i)
(ii)

Depth below bed level upto 3.0 M


Beyond 3m upto 10m depth

(iii)

Beyond 10m upto 20m


a

(iv)

Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter
Beyond 20m upto 30 m

a
b
(v)

Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter

metre

11746.00

Add 20% of cost for Kentledge including supports, loading arrangement and Labour) .

metre

14095.00

metre
metre

27908.00
33490.00

metre

4741.00

metre

6643.00

metre

8774.00

metre

9212.00

Beyond 30m upto 40 m


a
b

B
(I)

Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter
Add 20% of cost for Kentledge including supports, loading arrangement, and Labour etc.
Clayey soil ( 7m dia. Well )
Depth below bed level upto 3.0 M
Beyond 3m upto 10m depth

(ii)
(iii)
a
b
(iv)

Beyond 10 m upto 20 m
Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter
Add for dewatering @ 5% of cost, if required.
Beyond 20m upto 30 m

Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter

metre

16457.00

b
c

Add 5% of cost for dewatering on the cost, if required

metre
metre

21600.00
20571.00

metre
metre

39098.00
49263.00

(v)
a
b
c
C
(i)
D
(i)

Add 25% of cost for Kentledge including supports, loading arrangement and Labour ).
Beyond 30m upto 40 m
Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter
Add 5% of cost for dewatering, if required

46917.00

Add 20% of cost for Kentledge including supports, loading arrangement and Labour).
Soft rock ( 7m dia well )
Depth of soft rock strata upto 3m

metre

12610.00

Hard rock ( 7m dia well )


Depth upto 3 m

metre

20030.00

metre

4488.00

metre

5440.00

Sinking of 8 m external diameter well ( other than pneumatic method of sinking ) through all types of strata namely
sandy soil, clayey soil and rock as shown against each case, complete as per drawing and technical
specifications. Depth of sinking is reckoned from bed level.

12.14
A
(i)

Sandy soil
Depth below bed level upto 3.0 M
Beyond 3m upto 10m depth

(ii)
(iii)
a
(iv)
a
b
(v)
a
b
B

Beyond 10m upto 20m


Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter

metre

7186.00

Beyond 20m upto 30 m


Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter
Add 20% of cost for Kentledge including supports, loading arrangement and Labour .

metre

13480.00

metre

16176.00

Beyond 30m upto 40 m


Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter
Add 20% of cost for Kentledge including supports, loading arrangement, and Labour etc.

metre

4739.00

metre

5686.00

metre
metre

5801.00
8435.00

metre
metre

11140.00
11697.00

metre
metre

20894.00
27423.00

metre

26118.00

Clayey soil ( 8m dia. Well )


Depth upto 3.0 M

(i)
(ii)
(iii)
a
b
(iv)
a
b
c

Beyond 3m upto 10m depth


Beyond 10 m upto 20 m
Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter
Add for dewatering @ 5% of cost, if required.
Beyond 20m upto 30 m
Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter
Add 5% of cost for dewatering on the cost, if required
Add 25% of cost for Kentledge including supports, loading arrangement and Labour ).

Page 62 of 394

Summary of Rate Analysis


Item No.

Unit

Descriptions

(v)

Rate

Beyond 30m upto 40 m


a

Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter

metre

49642.00

Add 5% of cost for dewatering, if required

metre

62549.00

Add 20% of cost for Kentledge including supports, loading arrangement and Labour).

metre

59570.00

(i)

Soft rock ( 8m dia well )


Depth in soft rock strata upto 3m

metre

14195.00

D
(i)

Hard rock ( 8m dia well )


Depth in hard rock strata upto 3 m

metre

21382.00

Sinking of 9 m external diameter well ( other than pneumatic method of sinking ) through all types of strata namely sandy
soil, clayey soil and rock as shown against each case, complete as per drawing and technical specifications. Depth
of sinking is reckoned from bed level.

12.15
A

Sandy soil

(i)

Depth below bed level upto 3.0 M

metre

4621.00

(ii)

Beyond 3m upto 10m depth

metre

5960.00

metre

7871.00

metre

14762.00

metre

17715.00

metre
metre

35073.00
42088.00

metre
metre

6205.00
9064.00

metre
metre

11971.00
12570.00

(iii)

Beyond 10m upto 20m


a

(iv)

Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter
Beyond 20m upto 30 m

a
b
(v)
a
b
B
(i)
(ii)
(iii)

Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter
Add 20% of cost for Kentledge including supports, loading arrangement and Labour .
Beyond 30m upto 40 m
Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter
Add 20% of cost for Kentledge including supports, loading arrangement, and Labour etc.
Clayey soil ( 9m dia. Well )
Depth below bed level upto 3.0 M
Beyond 3m upto 10m depth
Beyond 10 m upto 20 m

a
b
(iv)

Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter
Add for dewatering @ 5% of cost, if required.
Beyond 20m upto 30 m

a
b

Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter
Add 5% of cost for dewatering on the cost, if required

metre
metre

22455.00
29472.00

Add 25% of cost for Kentledge including supports, loading arrangement and Labour ).
Beyond 30m upto 40 m
Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter

metre

28068.00

metre
metre

53348.00
67219.00

metre

64018.00

Depth upto 3m
Hard rock ( 9m dia well )

metre

17137.00

Depth of hard rock strata upto 3 m

metre

24327.00

(v)
a
b
c
C
(i)
D
(i)

Add 5% of cost for dewatering, if required


Add 20% of cost for Kentledge including supports, loading arrangement and Labour).
Soft rock ( 9m dia well )

Sinking of 10 m external diameter well ( other than pneumatic method of sinking ) through all types of strata namely
sandy soil, clayey soil and rock as shown against each case, complete as per drawing and technical
specifications. Depth of sinking is reckoned from bed level.

12.16
A

Sandy soil

(i)
(ii)

Depth below bed level upto 3.0 M


Beyond 3m upto 10m depth
Beyond 10m upto 20m

metre
metre

5261.00
6381.00

Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter
Beyond 20m upto 30 m
Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter

metre

8427.00

metre
metre

15807.00
18969.00

Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter
Add 20% of cost for Kentledge including supports, loading arrangement, and Labour etc.
Clayey soil (10m dia. Well )

metre
metre

37554.00
45065.00

Depth below bed level upto 3.0 M


Beyond 3m upto 10m depth

metre

7346.00

metre

9491.00

metre

12534.00

metre

13160.00

(iii)
a
(iv)
a
b
(v)
a
b
B
(i)
(ii)
(iii)
a
b

Add 20% of cost for Kentledge including supports, loading arrangement and Labour .
Beyond 30m upto 40 m

Beyond 10 m upto 20 m
Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter
Add for dewatering @ 5% of cost, if required.

Page 63 of 394

Summary of Rate Analysis


Item No.
(iv)
a

Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter

metre

23509.00

'b

Add 5% of cost for dewatering on the cost, if required

metre

30855.00

Add 25% of cost for Kentledge including supports, loading arrangement and Labour ).

metre

29386.00

metre

55854.00

metre

70376.00
67025.00

metre

17419.00

metre

25663.00

metre
metre

11354.00
11256.00

metre

14864.00

metre
metre

27880.00
33456.00

metre
metre

66238.00
79486.00

metre

12203.00

metre

20040.00

metre

26467.00

metre

27790.00

metre
metre

49643.00
65157.00

metre

62054.00

a
b
c

Beyond 30m upto 40 m


Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter
Add 5% of cost for dewatering, if required
Add 20% of cost for Kentledge including supports, loading arrangement and Labour).

C
(i)

Soft rock (10m dia well )


Depth of soft rock strata upto 3m

D
(i)

Hard rock (10m dia well )


Depth of hard rock strata upto 3 m
Sinking of 11 m external diameter well ( other than pneumatic method of sinking ) through all types of strata namely
sandy soil, clayey soil and rock as shown against each case, complete as per drawing and technical
specifications. Depth of sinking is reckoned from bed level.

12.17
A

Sandy soil

(i)
(ii)

Depth from bed level upto 3.0 M


Beyond 3m upto 10m depth
Beyond 10m upto 20m

(iii)
a
(iv)
a
b
(v)

Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter
Beyond 20m upto 30 m
Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter
Add 20% of cost for Kentledge including supports, loading arrangement and Labour .
Beyond 30m upto 40 m

a
b
B
(i)

Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter
Add 20% of cost for Kentledge including supports, loading arrangement, and Labour etc.
Clayey soil (11 m dia. Well )
Depth from bed level upto 3.0 M
Beyond 3m upto 10m depth

(ii)
(iii)
a
b
(iv)
a
b
c
(v)
a
b
c
C
(i)
D
(i)

Beyond 10 m upto 20 m
Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter
Add for dewatering @ 5% of cost, if required.
Beyond 20m upto 30 m
Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter
Add 5% of cost for dewatering on the cost, if required
Add 25% of cost for Kentledge including supports, loading arrangement and Labour ).
Beyond 30m upto 40 m
Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter
Add 5% of cost for dewatering, if required
Add 20% of cost for Kentledge including supports, loading arrangement and Labour).
Soft rock (11m dia well )
Depth of soft rock strata upto 3m
Hard rock (11m dia well )
Depth of hard rock upto 3 m

metre

117946.00

metre
metre

148612.00
141536.00

metre

38676.00

metre

55978.00

metre

24676.00

metre

29331.00

metre

38738.00

metre

72661.00

metre

87193.00

metre
metre

172632.00
207158.00

metre

29155.00

Sinking of 12 m external diameter well ( other than pneumatic method of sinking ) through all types of strata namely
sandy soil, clayey soil and rock as shown against each case, complete as per drawing and technical
specifications. Depth of sinking is reckoned from bed level.

12.18
A
(i)

Sandy soil
I) Depth below bed level upto 3.0 M
Beyond 3m upto 10m depth

(ii)
(iii)
a
(iv)
a
b
(v)
a
b
(i)

Rate

Beyond 20m upto 30 m

(v)

Unit

Descriptions

Beyond 10m upto 20m


Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter
Beyond 20m upto 30 m
Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter
Add 20% of cost for Kentledge including supports, loading arrangement and Labour .
Beyond 30m upto 40 m
Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter
Add 20% of cost for Kentledge including supports, loading arrangement, and Labour etc.
Clayey soil (12 m dia. Well )
Depth below bed level upto 3.0 M

Page 64 of 394

Summary of Rate Analysis


Item No.

Descriptions

Unit

(ii)

Beyond 3m upto 10m depth

metre

46453.00

(iii)

Beyond 10 m upto 20 m
a

Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter

metre

61350.00

Add for dewatering @ 5% of cost, if required.

metre

64418.00

(iv)
a
b
c
(v)
a
b
c
C

Beyond 30m upto 40 m


Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter
Add 5% of cost for dewatering, if required
Add 20% of cost for Kentledge including supports, loading arrangement and Labour).

metre

115076.00

metre
metre

151038.00
143845.00

metre

273402.00

metre
metre

344486.00
328082.00

metre

87598.00

metre

117944.00

metre
metre

5504.00
6045.00

metre

7983.00

Hard rock (12m dia well )

(i)

Depth of hard rock strata upto 3 m


Sinking of Twin D Type well ( other than pneumatic method of sinking ) through all types of strata namely sandy soil,
clayey soil and rock as shown against each case, complete as per drawing and technical specifications. Depth of
sinking is reckoned from bed level.

12.19
A

Sandy soil
Depth from bed level upto 3.0 M

(i)
(ii)
(iii)

Beyond 3m upto 10m depth


Beyond 10m upto 20m
a

(iv)

Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter
Beyond 20m upto 30 m

Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter

metre

14973.00

Add 20% of cost for Kentledge including supports, loading arrangement and Labour .

metre

17968.00

metre
metre

35574.00
42689.00

Depth below bed level upto 3.0 M


Beyond 3m upto 10m depth
Beyond 10 m upto 20 m

metre
metre

6735.00
10476.00

Add 5% for every additional meter depth of sinking over the rate of sinking for the previous meter
Add for dewatering @ 5% of cost, if required.
Beyond 20m upto 30 m

metre

13836.00

metre

14528.00

metre

25954.00

metre
metre

34065.00
32443.00

metre
metre
metre

61663.00
77695.00
73995.00

Soft rock (Twin D Type well )


Depth of soft rock strata upto 3m
Hard rock (Twin D Type well )

metre

18761.00

Depth of hard rock strata upto 3 m

metre

26299.00

(v)
a
b
B
(i)
(ii)
(iii)
a
b
(iv)
a
b
c
(v)
a
b
c

12.20

Add 5% of cost for dewatering on the cost, if required


Add 25% of cost for Kentledge including supports, loading arrangement and Labour ).

Depth of soft rock strata upto 3m

D
(i)

Beyond 20m upto 30 m


Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter

Soft rock (12m dia well )

(i)

C
(i)

Rate

Beyond 30m upto 40 m


Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter
Add 20% of cost for Kentledge including supports, loading arrangement, and Labour etc.
Clayey soil (Twin D Type Well )

Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous meter
Add 5% of cost for dewatering on the cost, if required
Add 25% of cost for Kentledge including supports, loading arrangement and Labour ).
Beyond 30m upto 40 m
Add 10% for every additional meter depth of sinking over the rate of sinking for the previous meter
Add 5% of cost for dewatering, if required
Add 20% of cost for Kentledge including supports, loading arrangement and Labour).

Pneumatic sinking of wells with equipment of approved design, drawing and specifications worked by competent
and trained personnel and comprising of compression and decompression chambers, reducers, two air locks
separately for men and plant & materials, arrangement for supply of fresh air to working chambers, check valves,
exhaust valves, shafts made from steel plates of riveted construction not less than 6 mm thick to withstand an air
pressure of 0.50 MPa, controlled blasting of hard rock where required, staircases and 1 m wide landing plate
forms with railing, arrangement for compression and decompression, electric lighting of 50 V maximum, proper
rooms for rest and medical examinations and compliance with safety precautions as per IS:4138, all as per
clause1207.6 of MoRTH Specifications.

12.21

Sand filling in wells complete as per drawing and technical specifications

cum

1134.00

12.22

Providing steel liner 10 mm thick for curbs and 6mm thick for steining of wells including fabricating and setting out
as per detailed drawing

tonne

80138.00

Page 65 of 394

Summary of Rate Analysis


Item No.

Descriptions

Unit

12.23

Bored cast-in-situ M35 grade R.C.C. pile excluding reinforcement complete as per drawing and technical
specifications and removal of excavated earth with all lifts and lead upto 1000 m. (Pile diameter-750 mm)

metre

#VALUE!

12.24

Bored cast-in-situ M35 grade R.C.C. pile excluding reinforcement complete as per drawing and technical
specifications and removal of excavated earth with all lifts and lead upto 1000 m. (Pile diameter-1000 mm)

metre

#VALUE!

12.25

Bored cast-in-situ M35 grade R.C.C. pile excluding reinforcement complete as per drawing and technical
specifications and removal of excavated earth with all lifts and lead upto 1000 m. (Pile diameter-1200 mm)

metre

#VALUE!

12.26

Driven cast-in-place vertical M35 grade R.C.C. pile excluding reinforcement complete as per drawing and &
Technical Specification (Pile diameter - 750 mm)

metre

#VALUE!

12.27

Driven cast-in-place vertical M35 grade R.C.C. piles excluding reinforcement complete as per drawing and &
Technical Specification (Pile diameter - 1000 mm)

metre

#VALUE!

12.28

Driven cast-in-place vertical M35 grade R.C.C. piles excluding reinforcement complete as per drawing and &
Technical Specification (Pile diameter - 1200 mm)

metre

#VALUE!

12.29

Driven precast vertical M35 grade R.C.C. piles excluding reinforcement complete as per drawing and & Technical
Specification (Pile Diameter=500 mm)

metre

#VALUE!

12.30

Driven precast vertical M35 grade R.C.C. piles excluding reinforcement complete as per drawing and & Technical
Specification (Pile Diameter=750 mm)

metre

#VALUE!

12.31

Driven precast vertical M35 grade R.C.C. piles excluding reinforcement complete as per drawing and & Technical
Specification (Pile Diameter=1000 mm)

metre

#VALUE!

12.32

Driven precast vertical M35 grade R.C.C. piles excluding reinforcement complete as per drawing and & Technical
Specification (Size of pile - 300 mm x 300 mm)

metre

#VALUE!

12.33

Driven precast vertical M35 grade R.C.C. piles excluding reinforcement complete as per drawing and & Technical
Specification (Size of pile - 500 mm x 500 mm)

metre

#VALUE!

12.34

Driven precast vertical M35 grade R.C.C. piles excluding reinforcement complete as per drawing and & Technical
Specification (Size of pile - 750 mm x 750 mm)

metre

#VALUE!

12.35

Driven vertical steel piles complete as per drawing and & Technical Specification (Section of the pile - H Section steel
column 400 x 250 mm (ISHB Series) )

metre

#VALUE!

12.36

Driven vertical steel piles complete as per drawing and & Technical Specification (Section of the pile - H Section steel
column 450 x 250 mm (ISHB Series) )

metre

#VALUE!

6646.00
#VALUE!

12.37
12.38
A

Pile load test on single vertical pile in accordance with IS:2911(Part-IV)


Cement concrete for reinforced concrete in pile cap complete as per drawing and Technical Specification
RCC Grade M20
(i)
(ii)

Using Concrete Mixer


Using Batching Plant, Transit Mixer and Concrete Pump
RCC Grade M25

cum
cum

(i)

Using concrete mixer.


Using Batching Plant, Transit Mixer and Concrete Pump
RCC Grade M30

cum

7119.00

cum

#VALUE!

Using concrete mixer.


Using Batching Plant, Transit Mixer and Concrete Pump

cum

7178.00

cum

#VALUE!

B
(ii)
C
(i)
(ii)
D
(i)
(ii)
12.39
12.40
12.41

Rate

RCC Grade M35


Using concrete mixer.
Using Batching Plant, Transit Mixer and Concrete Pump
Levelling course for Pile cap
Supplying, fitting and placing un-coated HYSD bar reinforcement in foundation complete as per drawing and
technical specifications
Supplying, fitting and placing un-coated Mild steel reinforcement complete in foundation as per drawing and
technical specification

Page 66 of 394

cum

7303.00

cum
cum

#VALUE!
5592.00

tonne

77561.00

tonne

57211.00

Summary of Rate Analysis


Item No.

Unit

Descriptions

Rate

CHAPTER-13
SUB-STRUCTURE
13.1

Brick masonry work in 1:3 in sub-structure complete excluding pointing and plastering, as per drawing and
technical specifications

cum

13.2

Pointing with cement mortar (1:3 ) on brick work in substructure as per Technical specifications

sqm

849.00

13.3

Plastering with cement mortar (1:3 ) on brick work in sub-structure as per Technical specifications
Stone masonry work in cement mortar 1:3 for substructure complete as per drawing and Technical Specifications

sqm

1739.00

13.4

5630.00

Random Rubble Masonry

cum

4936.00

B
C

Coursed rubble masonry (first sort )

cum
cum

5127.00
7226.00

cum

6156.00

cum

6839.00

13.5

Ashlar masonry ( first sort )


Plain/Reinforced cement concrete in sub-structure complete as per drawing and technical specifications

PCC Grade M15


(p)

Height upto 5m
PCC Grade M20

(p)
C

Height upto 5m
PCC Grade M25
Height upto 5m

(p)
Case I
Case II
(q)
Case I
Case II
(r)

Using concrete Mixer


With Batching Plant, Transit Mixer and Concrete Pump
Height 5m to 10m
Using concrete Mixer
With Batching Plant, Transit Mixer and Concrete Pump

cum

7315.00

cum

#VALUE!

cum

7581.00

cum

#VALUE!

Height above 10m


Case I
Case II

cum

7914.00

cum

#VALUE!

Using concrete Mixer


With Batching Plant, Transit Mixer and Concrete Pump
Height 5m to 10m

cum
cum

7367.00
#VALUE!

Using concrete Mixer


With Batching Plant, Transit Mixer and Concrete Pump

cum

7635.00

cum

#VALUE!

Using concrete Mixer


With Batching Plant, Transit Mixer and Concrete Pump
PCC Grade M30
Height upto 5m

(p)
Case I
Case II
(q)
Case I
Case II
(r)
Case I

Height above 10m


Using concrete Mixer
With Batching Plant, Transit Mixer and Concrete Pump

cum

7970.00

cum

#VALUE!

Using concrete Mixer


With Batching Plant, Transit Mixer and Concrete Pump
Height 5m to 10m

cum
cum

#VALUE!
#VALUE!

Case I
Case II

Using concrete Mixer


With Batching Plant, Transit Mixer and Concrete Pump
Height above 10m

cum
cum

7303.00
#VALUE!

Case I

Using concrete Mixer


With Batching Plant, Transit Mixer and Concrete Pump

cum

7623.00

cum

#VALUE!

cum
cum

7530.00
#VALUE!

Case II
E
(p)

RCC Grade M20


Height upto 5m

Case I
Case II
(q)

(r)
Case II
F
(p)
Case I
Case II
(q)

RCC Grade M25


Height upto 5m
Using concrete Mixer
With Batching Plant, Transit Mixer and Concrete Pump
Height 5m to 10m

Case I
Case II

Using concrete Mixer


With Batching Plant, Transit Mixer and Concrete Pump
Height above 10m

cum
cum

7777.00
#VALUE!

Case I
Case II

Using concrete Mixer


With Batching Plant, Transit Mixer and Concrete Pump
RCC Grade M30

cum
cum

8146.00
#VALUE!

cum
cum

7559.00
#VALUE!

(r)

G
(p)
Case I
Case II

Height upto 5m
Using concrete Mixer
With Batching Plant, Transit Mixer and Concrete Pump

Page 67 of 394

Summary of Rate Analysis


Item No.

Unit

Descriptions

(q)

Rate

Height 5m to 10m
Case I

Using concrete Mixer

cum

7772.00

Case II

With Batching Plant, Transit Mixer and Concrete Pump

cum

#VALUE!

(r)

Height above 10m


Case I
Case II

H
(p)

Using concrete Mixer


With Batching Plant, Transit Mixer and Concrete Pump

cum

8075.00

cum

#VALUE!

cum
cum

7691.00
#VALUE!

RCC Grade M35


Height upto 5m

Case I
Case II
(q)

Using concrete Mixer


With Batching Plant, Transit Mixer and Concrete Pump
Height 5m to 10m

Case I

Using concrete Mixer

cum

7859.00

Case II

With Batching Plant, Transit Mixer and Concrete Pump

cum

#VALUE!

(r)

Height above 10m


Case I

Using concrete Mixer

cum

8111.00

Case II

With Batching Plant, Transit Mixer and Concrete Pump

cum

#VALUE!

13.6

Supplying, fitting and placing HYSD bar reinforcement in sub-structure complete as per drawing and technical
specifications

tonne

77756.00

13.7

Supplying, fitting and placing Mild steel reinforcement complete in sub-structure as per drawing and technical
specification

tonne

56085.00

13.8

Providing weep holes in Brick masonry/Plain/Reinforced concrete abutment, wing wall/return wall with 100 mm dia
AC pipe, extending through the full width of the structure with slope of 1V :20H towards drawing foce. Complete as
per drawing and Technical specifications

each

#VALUE!

Back filling behind abutment, wing wall and return wall complete as per drawing and Technical specification

13.9

13.10

Granular material

cum

#VALUE!

Sandy material

cum

#VALUE!

cum

1581.00

Providing and laying of Filter media with granular materials/stone crushed aggregates satisfying the requirements
laid down in clause 2504.2.2. of MoRTH specifications to a thickness of not less than 600 mm with smaller size
towards the soil and bigger size towards the wall and provided over the entire surface behind abutment, wing wall
and return wall to the full height compacted to a firm condition complete as per drawing and technical
specification.

13.11

Supplying, fitting and fixing in position true to line and level cast steel rocker bearing conforming to IRC: 83(Pt.-1)
section IX and clause 2003 of MoRTH specifications complete including all accessories as per drawing and
Technical Specifications.

tonne
capacity

#VALUE!

13.12

Supplying, fitting and fixing in position true to line and level forged steel roller bearing conforming to IRC: 83(Pt.1) section IX and clause 2003 of MoRTH specifications complete including all accessories as per drawing and
Technical Specifications.

tonne
capacity

#VALUE!

13.13

Supplying, fitting and fixing in position true to line and level sliding plate bearing with PTFE surface sliding on
stainless steel complete including all accessories as per drawing and Technical Specifications and BS: 5400,
section 9.1 & 9.2 (for PTFE) and clause 2004 of MoRTH Specifications.

tonne
capacity

#VALUE!

13.14

Supplying, fitting and fixing in position true to line and level elastomeric bearing conforming to IRC: 83 (Part-II)
section IX and clause 2005 of MoRTH specifications complete including all accessories as per drawing and
Technical Specifications.

cubic
centimetre

#VALUE!

13.15

Supplying, fitting and fixing in position true to line and level sliding plate bearing with stainless steel plate sliding
on stainless steel plate with mild steel matrix complete including all accessories as per drawing and Technical
Specifications.

tonne
capacity

#VALUE!

tonne
capacity

#VALUE!

13.16

Supplying, fitting and fixing in position true to line and level POT-PTFE bearing consisting of a metal piston
supported by a disc or unreinforced elastomer confined within a metal cylinder, sealing rings, dust seals, PTFE
surface sliding against stainless steel mating surface, completre assembly to be of cast steel/fabricated structural
steel, metal and elastomer elements to be as per IRC: 83 part-I & II respectively and other parts conforming to BS:
5400, section 9.1 & 9.2 and clause 2006 of MoRTH Specifications complete asper drawing and approved technical
specifications.

Page 68 of 394

Summary of Rate Analysis


Item No.

Unit

Descriptions

Rate

CHAPTER-14
SUPER-STRUCTURE
Furnishing and Placing Reinforced/Prestressed cement concrete in super-structure as per drawing and Technical
Specification

14.1
A

RCC Grade M20

Case I
(i)

Using Concrete Mixer


For solid slab super-structure, 20-30% of (a+b+c)
(p)
(q)
(r)

(ii)

Height 5m to 10m

cum
cum

7630.00
7948.00

Height above 10m

cum

8266.00

Height upto 5m

For T-beam & slab, 25-35% of (a+b+c)


(p)

Height upto 5m

cum

7948.00

(q)

Height 5m to 10m

cum

8266.00

(r)

Height above 10m

cum

8584.00

cum

#VALUE!

cum
cum

#VALUE!
#VALUE!

Case II

Using Batching Plant, Transit Mixer and Concrete Pump

(i)

For solid slab super-structure, 20-30% of (a+b+c)


(p)
(q)
(r)

(ii)
(p)

Height upto 5m
Height 5m to 10m
Height above 10m
For T-beam & slab, 25-35% of (a+b+c)
Height upto 5m
Height 5m to 10m

cum

#VALUE!

(q)

cum

#VALUE!

(r)

Height above 10m

cum

#VALUE!

cum

8176.00

cum
cum

8516.00
8857.00

cum
cum

8516.00
8857.00

cum

9198.00

cum
cum
cum

#VALUE!
#VALUE!
#VALUE!

cum

#VALUE!

cum
cum

#VALUE!
#VALUE!

cum
cum
cum

8287.00
8633.00
8978.00

cum
cum

8633.00
8978.00

cum

9323.00

cum
cum

#VALUE!
#VALUE!

cum

#VALUE!

cum
cum

#VALUE!
#VALUE!

B
Case I

RCC Grade M25


Using Concrete Mixer
For solid slab super-structure, 20-30% of (a+b+c)

(i)
(p)
(q)
(r)
(ii)
(p)
(q)
(r)
Case II
(i)
(p)
(q)
(r)
(ii)
(p)
(q)
(r)
C
Case I
(i)
(p)
(q)
(r)
(ii)
(p)
(q)
(r)
Case II
(i)
(p)
(q)
(r)
(ii)
(p)
(q)

Height upto 5m
Height 5m to 10m
Height above 10m
For T-beam & slab, 25-35% of (a+b+c)
Height upto 5m
Height 5m to 10m
Height above 10m
Using Batching Plant, Transit Mixer and Concrete Pump
For solid slab super-structure, 20-30% of (a+b+c)
Height upto 5m
Height 5m to 10m
Height above 10m
For T-beam & slab, 25-35% of (a+b+c)
Height upto 5m
Height 5m to 10m
Height above 10m
RCC Grade M 30
Using Concrete Mixer
For solid slab super-structure, 20-30% of (a+b+c)
Height upto 5m
Height 5m to 10m
Height above 10m
For T-beam & slab, 25-35% of (a+b+c)
Height upto 5m
Height 5m to 10m
Height above 10m
Using Batching Plant, Transit Mixer and Concrete Pump.
For solid slab super-structure, 20-30% of (a+b+c)
Height upto 5m
Height 5m to 10m
Height above 10m
For T-beam & slab, 25-35% of (a+b+c)
Height upto 5m
Height 5m to 10m

Page 69 of 394

Summary of Rate Analysis


Item No.

Unit

Descriptions
(r)

#VALUE!

cum

8291.00

cum

8643.00

cum

8994.00

Height upto 5m
Height 5m to 10m

cum
cum

8643.00
8994.00

Height above 10m

cum

9345.00

RCC/PSC Grade M35

Case 1

Using concrete mixer.

(i)

For solid slab super-structure, 18-28% of (a+b+c)


(p)
(q)
(r)

(ii)
(p)
(q)
(r)
(iii)

Rate

cum

Height above 10m

Height upto 5m
Height 5m to 10m
Height above 10m
For T-beam & slab, 23-33% of (a+b+c)

For box girder and balanced cantilever, 38-58% of cost of concrete.


(p)

Height upto 5m

cum

9696.00

(q)

Height 5m to 10m

cum

10399.00

Height above 10m

cum

11102.00

cum

#VALUE!

cum
cum

#VALUE!
#VALUE!

Height upto 5m
Height 5m to 10m

cum
cum

#VALUE!
#VALUE!

Height above 10m

cum

#VALUE!

(r)
Case II

Using Batching Plant, Transit Mixer and Concrete Pump

(i)

For solid slab super-structure, 18-28% of (a+b+c)


(p)
(q)
(r)

(ii)
(p)
(q)
(r)
(iii)

Height upto 5m
Height 5m to 10m
Height above 10m
For T-beam & slab, 23-33% of (a+b+c)

For box girder and balanced cantilever, 38-58% of cost of concrete.


(p)

Height upto 5m

cum

#VALUE!

(q)
(r)

Height 5m to 10m

cum
cum

#VALUE!
#VALUE!

cum
cum

#VALUE!
#VALUE!

cum

#VALUE!

cum

#VALUE!

cum
cum

#VALUE!
#VALUE!

cum

#VALUE!

cum
cum

#VALUE!
#VALUE!

cum
cum

#VALUE!
#VALUE!

cum

#VALUE!

cum

#VALUE!

cum
cum

#VALUE!
#VALUE!

cum

#VALUE!

cum
cum

#VALUE!
#VALUE!

cum

#VALUE!

cum

#VALUE!

E
Case 1
(i)

Height above 10m


PSC Grade M-40
Using concrete mixer.
For solid slab super-structure, 20-30% of (a+b+c)

(p)
(q)
(r)
(ii)
(p)
(q)
(r)
Case II
(i)
(p)
(q)
(r)
(ii)
(p)
(q)
(r)
(iii)
(p)
(q)
(r)
F
(i)
(p)
(q)
(r)

Height upto 5m
Height 5m to 10m
Height above 10m
For T-beam & slab, 25-35% of (a+b+c)
Height upto 5m
Height 5m to 10m
Height above 10m
Using Batching Plant, Transit Mixer and Concrete Pump
For solid slab super-structure, 18-28% of (a+b+c)
Height upto 5m
Height 5m to 10m
Height above 10m
For T-beam & slab, 23-33% of (a+b+c)
Height upto 5m
Height 5m to 10m
Height above 10m
For box girder and balanced cantilever, 38-58% of cost of concrete.
Height upto 5m
Height 5m to 10m
Height above 10m
PSC Grade M-45
For solid slab/voided slab super-structure, 16-26% of cost of concrete (a+b+c)
Height upto 5m
Height 5m to 10m
Height above 10m
For I-beam & slab including launching of precast girders by launching truss upto 40 m span, 21-31% of cost of
concrete.

(ii)
(p)
(q)

Height upto 5m
Height 5m to 10m

Page 70 of 394

Summary of Rate Analysis


Item No.

Unit

Descriptions
(r)

(iii)

Height above 10m

Rate

cum

#VALUE!

For cast-in-situ box girder, segmental construction and balanced cantilever, 36-56% of cost of concrete.
(p)

Height upto 5m

cum

#VALUE!

(q)

Height 5m to 10m

cum

#VALUE!

(r)

Height above 10m


PSC Grade M-50

cum

#VALUE!

cum

#VALUE!

cum
cum

#VALUE!
#VALUE!

G
(i)
(p)
(q)
(r)
H
(i)

For cast-in-situ box girder, segmental construction and balanced cantilever, 35-55% of cost of concrete
Height upto 5m
Height 5m to 10m
Height above 10m
PSC Grade M- 55
For cast-in-situ box girder, segmental construction and balanced cantilever, 35-55% of cost of concrete

(p)

Height upto 5m

cum

#VALUE!

(q)

Height 5m to 10m

cum

#VALUE!

Height above 10m

cum

#VALUE!

14.2

a) Supplying, fitting and placing HYSD bar reinforcement in super-structure complete as per drawing and
technical specifications

tonne

79481.00

14.3

High tensile steel wires/strands including all accessories for stressing, stressing operations and grouting
complete as per drawing and Technical Specifications

tonne

#VALUE!

14.4

Providing and laying Cement concrete wearing coat M-30 grade including reinforcement complete as per drawing
and Technical Specifications

cum

84940.00

sqm

#VALUE!

14.6

Construction of precast RCC railing of M30 Grade, aggregate size not exceeding 12 mm, true to line and grade,
tolurence of vertical RCC post not to exceed 1 in 500, centre to centre spacing between vertical post not to exceed
2000 mm, leaving adequate space between vertical post for expansion, complete as per approved drawings and
technical specifications.

metre

#VALUE!

14.7

Construction of RCC railing of M30 Grade in-situ with 20 mm nominal size aggregate, true to line and grade,
tolurence of vertical RCC post not to exceed 1 in 500, centre to centre spacing between vertical post not to exceed
2000 mm, leaving adequate space between vertical post for expansion, complete as per approved drawings and
technical specifications.

metre

#VALUE!

14.8
14.9

Providing, fitting and fixing mild steel railing complete as per drawing and Technical Specification
Drainage Spouts complete as per drawing and Technical specification

metre
each

3135.00
#VALUE!

14.10

PCC M15 Grade leveling course below approach slab complete as per drawing and Technical specification

cum

5597.00

14.11

Reinforced cement concrete approach slab including reinforcement and formwork complete as per drawing and
Technical specification

cum

#VALUE!

14.12

Providing anti-corrosive treatment to HYSD reinforcement with Fusion Bonded Epoxy Coating (FBEC)
taken as per the prevailing market rates.)

tonne

14.13

Precast - pretensioned Girders (Providing, precasting, transportation and placing in position precast pretensioned
concrete girders as per drawing and technical specifications)

cum

#VALUE!

14.14

Providing and fixing Helical pipes in voided concrete slabs

metre

#VALUE!

14.15

Crash Barriers (The rate analysis for rigid crash barrier in reinforced cement concrete, semi-rigid crash barrier with metal
beam and flexible crash barrier with wire ropes have been made and included in chapter-8 on Traffic and Transportation.)

14.16

Painting on concrete surface (Providing and applying 2 coats of water based cement paint to unplastered concrete
surface after cleaning the surface of dirt, dust, oil, grease, efflorescence and applying paint @ of 1 litre for 2 Sq.m. )

metre

#VALUE!

metre

1556.00

(r)

Mastic Asphalt (Providing and laying 12 mm thick mastic asphalt wearing course on top of deck slab excluding prime coat
with paving grade bitumen meeting the requirements given in table 500-29, prepared by using mastic cooker and laid to
required level and slope after cleaning the surface, including providing antiskid surface with bitumen precoated fine grained
hard stone chipping of 9.5 mm nominal size at the rate of 0.005cum per 10 sqm and at an approximate spacing of 10 cm
center to center in both directions, pressed into surface when the temperature of surfaces not less than 100 deg. C,
protruding 1 mm to 4 mm over mastic surface, all complete as per clause 515.)

14.5

(To be

14.17

Burried Joint (Providing and laying a burried expansion joint, expansion gap being 20 mm, covered with 12 mm thick,
200 mm wide galvanised wieldable structural steel plate as per IS: 2062, placed symmetrical to centre line of the joint,
resting freely over the top surface of the deck concrete, welding of 8 mm dia. 100 mm long galvanised nails spaced 300
mm c/c along the centre line of the plate, all as specified in clause 2604.)

14.18

Filler joint
(i)

Providing & fixing 2 mm thick corrugated copper plate in expansion joint complete as per drawing & Technical
Specification.

metre

3204.00

(ii)

Providing & fixing 20 mm thick compressible fibre board in expansion joint complete as per drawing & Technical
Specification.

metre

208.00

Page 71 of 394

Summary of Rate Analysis


Item No.

Unit

Descriptions

Rate

(iii)

Providing and fixing in position 20 mm thick premoulded joint filler in expansion joint for fixed ends of simply
supported spans not exceeding 10 m to cater for a horizontal movement upto 20 mm, covered with sealant
complete as per drawing and technical specifications.

metre

406.00

(iv)

Providing and filling joint sealing compound as per drawings and technical specifications with coarse sand and
6% bitumen by weight

metre

34.00

metre

#VALUE!

metre

#VALUE!

metre

#VALUE!

metre

#VALUE!

14.23

Modular Strip / Box Seal Joint (Providing and laying of a modular strip Box steel expansion joint including anchorage
catering to a horizontal movement beyond 70 mm and upto 140mm, complete as per approved drawings and standard
specifications to be installed by the manufacturer/supplier or their authorised representative ensuring compliance to the
manufacturer's instructions for installation.)

metre

#VALUE!

14.24

Modular Strip / Box Seal Joint (Providing and laying of a modular strip box seal expansion joint catering to a horizontal
movement beyond 140mm and upto 210mm, complete as per approved drawings and standard specifications to be
installed by the manufacturer/supplier or their authorised representative ensuring compliance to the manufacturer's
instructions for installation.)

metre

#VALUE!

14.19

14.20

14.21

14.22

Asphaltic Plug joint (Providing and laying of asphaltic plug joint to provide for horizontal movement of 25 mm and vertical
movement of 2 mm, depth of joint varying from 75 mm to 100 mm, width varying from 500 mm to 750 mm (in traffic
direction), covered with a closure plate of 200mm x 6mm of wieldable structural steel conforming to IS: 2062, asphaltic
plug to consist of polymer modified bitumen binder, carefully selected single size aggregate of 12.5 mm nominal size and a
heat resistant foam caulking/backer rod, all as per approved drawings and specifications.)
Elastomeric Slab Steel Expansion Joint (Providing and laying of an elastomeric slab steel expansion joint, catering to
right or skew (less than 20 deg., moderately curved with maximum horizontal movement upto 50 mm, complete as per
approved drawings and standard specifications to be installed by the manufacturer/supplier or their authorised
representative ensuring compliance to the manufacturer's instructions for installation and clause 2606 of MoRTH
specifications for road & bridge works.)
Compression Seal Joint (Providing and laying of compression seal joint consisting of steel armoured nosing at two edges
of the joint gap suitably anchored to the deck concrete and a preformed chloroprene elastomer or closed cell foam joint
sealer compressed and fixed into the joint gap with special adhesive binder to cater for a horizontal movement upto 40 mm
and vertical movement of 3 mm.)
Strip Seal Expansion Joint (Providing and laying of a strip seal expansion joint catering to maximum horizontal movement
upto 70 mm, complete as per approved drawings and standard specifications to be installed by the manufacturer/supplier
or their authorised representative ensuring compliance to the manufacturer's instructions for installation.)

Page 72 of 394

Summary of Rate Analysis


Item No.

Unit

Descriptions

Rate

CHAPTER-15
RIVER TRAINING AND PROTECTION WORKS
Providing and laying boulders apron on river bed for protection against scour with stone boulders weighing not
less than 40 kg each complete as per drawing and Technical specification.

15.1
A

cum

1003.00

15.2

Boulder apron laid in wire crates (Providing and laying of boulder apron laid in wire crates made with 4mm dia GI wire
conforming to IS: 280 & IS:4826 in 100mm x 100mm mesh (weaved diagonally) including 10% extra for laps and joints laid
with stone boulders weighing not less than 40 kg each.)

cum

#VALUE!

15.3

Cement concrete blocks (size 0.5 x 0.5 x 0.5 m) (Providing and laying of apron with cement concrete blocks of size
0.5x0.5x0.5 m cast in-situ and made with nominal mix of M-15 grade cement concrete with a minimum cement content of
250 kg/cum as per IRC: 21-2000.)

cum

5936.00

15.4

Providing and laying Pitching on slopes laid over prepared filter media including boulder apron laid dry in front of
toe of embankment complete as per drawing and Technical specifications
cum
cum

1003.00
5936.00

A
B

Boulder laid dry without wire crates.

Stone/Boulder
Cement Concrete blocks of size 0.3x0.3 x0.3 m cast in cement concrete of Grade M15

15.5

Providing and laying Filter material underneath pitching in slopes complete as per drawing and Technical
specification

cum

1825.00

15.6

Geotextile Filter (Laying of a geotextile filter between pitching and embankment slopes on which pitching is laid to prevent
escape of the embankment material through the voids of the stone pitching/cement concrete blocks as well as to allow free
movement of water without creating any uplift head on the pitching.)

sqm

609.00

15.7

Toe protection (A toe wall for toe protection can either be in dry rubble masonry in case of dry rubble pitching or pitching
with stones in wire crates or it can be in PCC M15 nominal mix if cement concrete block have been used for pitching . Rates
for toe wall can be adopted from respective clauses depending upon approved design. The rate for excavation for
foundation, dry rubble masonry and PCC M15 have been analysed and given in respective chapters.)

15.8

Providing and laying Flooring complete as per drawing and Technical specifications laid over cement concrete
bedding.
cum

5520.00

cum
cum

7818.00
1540.00

cum
cum

5568.00
5820.00

cum

1081.00

cum

#VALUE!

cum

#VALUE!

A
B
15.9

Dry rubble Flooring


Curtain wall complete as per drawing and Technical specification

15.10
A
B
15.11

15.12

15.13

Rubble stone laid in cement mortar 1:3


Cement Concrete blocks Grade M15

Stone masonry in cement mortar (1:3)


Cement concrete Grade M15
Flexible Apron :Construction of flexible apron 1 m thick comprising of loose stone boulders weighing not less than
40 kg beyond curtain wall.
Gabian Structure for Retaining Earth (Providing and construction of a gabain structure for retaining earth with segments
of wire crates of size 7 m x 3 m x 0.6 m each divided into 1.5 m compartments by cross netting, made from 4 mm
galvanised steel wire @ 32 kg per 10 sqm having minimum tensile strength of 300 Mpa conforming to IS:280 and
galvanizing coating conforming to IS:4826, woven into mesh with double twist, mesh size not exceeding 100 x 100 mm,
filled with boulders with least dimension of 200 mm, all loose ends to be tied with 4 mm galvanised steel wire)

Gabian Structure for Erosion Control, River Training Works and Protection works (Providing and constructing gabain
structures for erosion control, river training works and protection works with wire crates of size 2 m x 1 m x 0.3 m each
divided into 1m compartments by cross netting, made from 4 mm galvanised steel wire @ 32 kg per 10 sqm having
minimum tensile strength of 300 Mpa conforming to IS:280 and galvanizing coating conforming to IS:4826, woven into
mesh with double twist, mesh size not exceeding 100 mm x 100 mm, filled with boulders with least dimension of 200 mm,
all loose ends to be securely tied with 4 mm galvanised steel wire.)

Page 73 of 394

Summary of Rate Analysis


Item No.

Unit

Descriptions

Rate

CHAPTER-16
REPAIR AND REHABILITATION
16.1

Removal of existing cement concrete wearing coat including its disposal complete as per Technical specification
without causing any detrimental effect to any part of the bridge structure and removal of dismantled material with
all lifts and lead upto 1000m(Thickness 75 mm)

sqm

127.00

16.2

Removal of existing asphaltic wearing coat comprising of 50 mm thick asphaltic concrete laid over 12 mm thick
mastic asphalt including disposal with all lift and lead upto 1000m.

sqm

95.00

16.3

Guniting concrete surface with cement mortar applied with compressor after cleaning surface and spraying with
epoxy complete as per Technical specification

sqm

#VALUE!

16.4

Providing and inserting nipples with approved fixing compound after drilling holes for grouting as per Technical
specifications including subsequent cutting/removal and sealing of the hole as necessary of nipples after
completion of grouting with Cement/Epoxy

each

162.00

16.5

Sealing of cracks/porous concrete by injection process through nipples/Grouting complete as per Technical
specification.

16.6

16.7
16.8

16.9

Cement Grout

kg

#VALUE!

Cement mortar (1:1) Grouting

kg

#VALUE!

sqm

#VALUE!

kg

#VALUE!

sqm

#VALUE!

sqm

#VALUE!

Patching of damaged concrete surface with polymer concrete and curing compounds, initiator and promoter,
available in present formulations, to be applied as per instructions of manufacturer and as approved by the
Engineer.
Sealing of crack / porous concrete with Epoxy Grout by injection through nipples complete as per clause 2803.1.
Applying epoxy mortar over leached, honey combed and spalled concrete surface and exposed steel
reinforcement complete as per Technical specification
Removal of defective concrete, cleaning the surface thoroughly, applying the shotcrete mixture mechanically with
compressed air under pressure, comprising of cement, sand, coarse aggregates, water and quick setting
compound in the proportion as per clause 2807.1., sand and coarse aggregates conforming to IS: 383 and table 1
of IS: 9012 respectively, water cement ratio ranging from 0.35 to 0.50, density of gunite not less than 2000 kg/cum,
strength not less than 25 Mpa and workmanship conforming to clause 2807.6.

16.10

Applying pre-packed cement based polymer mortar of strength 45 Mpa at 28 days for replacement of spalled
concrete

sqm

#VALUE!

16.11

Eproxy bonding of new concrete to old concrete

sqm

#VALUE!

16.12

Providing external prestressing with high tensile steel wires/strands including drilling for passage of prestessing
steel, all accessories for stressing and stressing operation and grouting complete as per drawing and Technical
specification

tonne

#VALUE!

16.13

Providing external prestressing with high tensile steel wires/strands including drilling for passage of prestessing
steel, all accessories for stressing and stressing operation and grouting complete as per drawing and Technical
specification

tonne

#VALUE!

16.14

Providing external prestressing with high tensile steel wires/strands including drilling for passage of prestessing
steel, all accessories for stressing and stressing operation and grouting complete as per drawing and Technical
specification

tonne

#VALUE!

each

#VALUE!

each
metre
metre

#VALUE!
#VALUE!
337.00

metre
metre

626.00
280.00

metre

1851.00

metre
metre

688.00
294.00

16.15
16.16
16.17
16.18
16.19
16.20
16.21
16.22
16.23

Replacement of bearings complete as per Technical specification


Rectification of bearings as per Technical specifications
Replacement of Expansion Joints complete as per drawings
Replacement of damaged concrete railing.
Replacement of crash barrier.
Replacement of damaged mild steel railing
Repair of crash barrier (Repair of concrete crash barrier with cement concrete of M-30 grade by cutting and trimming the
damaged portion to a regular shape, cleaning the area to be repaired thoroughly, applying cement concrete after erection
of proper form work.)
Repair of RCC Railing (Carrying out repair of RCC M30 railing to bring it to the original shape.)
Repair of steel Railing (Repair of steel railing to bring it to the original shape)

Page 74 of 394

CHAPTER-1
CARRIAGE OF MATERIALS
Sr No

Ref. to
MoRTH
Spec.

1.1

Note
1.2

Note
1.3

Description

Unit

Loading and Unloading of Stone Boulder/Stone


aggregates/Sand/Kanker/Moorum.
Placing tipper at loading point, loading with front end loader,
dumping, turning for return trip, excluding time for haulage
and return trip
Unit = cum
Taking output = 5.5 cum
Time required for
i) Positioning of tipper at loading point
ii) Loading by front end loader 1 cum bucket
capacity @ 25 cum per hour
iii) Maneuvering, reversing, dumping and turning for
return
iv) Waiting time, unforeseen contingencies etc
Total
a) Machinery
Tipper 5.5 tonnes capacity
Front end-loader 1 cum bucket capacity @ 25
cum/hour
b) Overhead charges @ 0.1 on (a)
c) Contractor's profit @ 0.1 on (a+b)
Cost for 5.5 cum = a+b+c
Rate per cum = (a+b+c)/ 5.5
Unloading will be by tipping.
Loading and Unloading of Boulders by Manual Means

cum

Unit = cum
Taking output = 5.5 cum
a) Labour
Mate
Mazdoor for loading and unloading
b) Machinery
Tipper 5.5 tonne capacity
c) Overhead charges @ 0.1 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Cost for5.5 cum = a+b+c+d
Rate per cum = (a+b+c+d)/5.5
Unloading will be by tipping.
Loading and Unloading of Cement or Steel by Manual
Means and Stacking.
Unit = tonne
Taking output = 10 tonnes
a) Labour
Mate
Mazdoor for loading and unloading
b) Machinery
Truck 10 tonne capacity
c) Overhead charges @ 0.1 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Cost for10 tonnes = a+b+c+d
Rate per tonnes = (a+b+c+d)/10

Quantity

Rate Rs

Cost Rs

1 Min
13 Min
2 Min
4 Min
20 Min
hour
hour

0.330
0.330

291.00
756.00

96.03
249.48

say

34.55
38.01
418.07
76.01
76.00

P&M-048
P&M-017

day
day

0.110
0.750

673.00
377.00

74.03
282.75

L-12
L-13

hour

0.750

291.00

P&M-048

say

218.25
57.50
63.25
695.79
126.51
127.00

day
day

0.080
2.000

673.00
377.00

53.84
754.00

L-12
L-13

hour

2.000

291.00

582.00
138.98
152.88
1681.71
168.17
168.00

P&M-057

116.40
84.39
20.08
22.09

P&M-048
P&M-048

say
1.4

Remarks/
Input ref.

Cost of Haulage Excluding Loading and Unloading


Haulage of materials by tipper excluding cost of loading,
unloading and stacking.
Unit = t.km
Taking output 10 tonnes load and lead 10 km = 100 t.km
(i)

Surfaced Road
Speed with load : 25 km / hour.
Speed while Returning empty :35 km / hour.
a) Machinery.
Tipper 10 tonne capacity
Time taken for onward haulage with load
Time taken for empty return trip.
b) Overhead charges @ 0.1 on (a)
c) Contractor's profit @ 0.1 on (a+b)
Page 1 of 394

hour
hour

0.400
0.290

291.00
291.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

cost for 100 t km = a+b+c


Rate per t.km = (a+b+c)/100
1.4

(ii)

say

242.96
2.43
2.40

Remarks/
Input ref.

Unsurfaced Graveled Road


Speed with load: 20 km / hour
Speed for empty return trip :30 km / hour
a) Machinery
Tipper 10 tonnes capacity
Time taken for onward haulage with load

hour

0.500

291.00

145.50

P&M-048

Time taken for empty return trip

hour

0.330

291.00

96.03

P&M-048

b)

Overhead charges @ 0.1 on (a)

24.15

c)

Contractor's profit @ 0.1 on (a+b)

26.57

Cost for 100 t .km = a+b+c

292.25

Rate per t.Km = (a+b+c)/100


1.4

(iii)

2.92
say

2.90

Katcha Track and Track in River Bed/Nallah Bed and


Choe Bed.
Speed with load :10 km / hour
Speed while returning empty:15 km / hour
a)

Machinery
Tipper 10 tonnes capacity
Time taken for onward haulage

hour

1.000

291.00

291.00

P&M-048

Time taken for empty return trip

hour

0.670

291.00

194.97

P&M-048

b)

Overhead charges @ 0.1 on (a)

48.60

c)

Contractor's profit @ 0.1 on (a+b)

53.46

Cost for 100 t .km = a+b+c

588.02

Rate per t.Km = (a+b+c)/100

5.88
say

1.5

5.90

Hand Broken Stone Aggregates 63 mm Nominal Size


Supply of quarried stone, hand breaking into coarse
aggregate 63 mm nominal size (passing 80 mm and retained
on 50 mm sieve) and stacking as directed
Unit = cum
Taking output = 1 cum
a)

b)

Labour
Mate

day

0.060

673.00

40.38

L-12

Mazdoor

day

1.500

377.00

565.50

L-13

cum

1.100

240.00

264.00

M-002

Material
Supply of quarried stone 150 - 200 mm size

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

86.99
95.69

Rate per cum = a+b+c+d

1052.55
say

1.6

1053.00

Crushing of Stone Aggregates 13.2 mm Nominal Size.


Crushing of stone boulders of 150 mm size in an integrated
stone crushing unit of 200 tonnes per hour capacity
comprising of primary and secondary crushing units, belt
conveyor and vibrating screens to obtain stone aggregates
of 13.2 mm nominal size.
Unit = cum
Taking Output = 600 cum at crusher location.
a) Labour

b)

Mate

day

0.760

673.00

511.48

L-12

Mazdoor Skilled

day

2.000

377.00

754.00

L-14

Mazdoor including breaking of any oversize boulder.

day

17.000

377.00

6409.00

L-13

cum

800.000

210.00

168000.00

Material
Stone Boulder of size 150 mm and below
Page 2 of 394

M-001

Sr No

Ref. to
MoRTH
Spec.
c)

Cost Rs

Remarks/
Input ref.

17103.00

102618.00

P&M-028

20.000

756.00

15120.00

P&M-017

20.000

291.00

5820.00

P&M-048

Description

Unit

Quantity

Integrated stone crusher of 200 TPH including belt


conveyor and vibrating screens
Front end loader 1 cum bucket capacity

Hour

6.000

Hour

Tipper 5.5 cum capacity

Hour

Rate Rs

Machinery

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

29923.25
32915.57

Cost for 600 cum = a+b+c+d+e

362071.30

Rate per cum = (a+b+c+d+e)*0.95/600

573.28
say

Note

573.00

1. 800 cum of stone boulders are needed to get 600 cum of


stone chips of size 13.2 mm.
2. 95 per cent of above cost will be attributed to the
production of 600 cum of stone chips of 13.2 mm size and
balance 5 per cent to the production of stone dust which
comes out as a by-product.
3. The integrated stone crusher includes primary and
secondary crushing units.
Crushing of Stone Aggregates 20 mm Nominal Size

1.7

Crushing of stone boulders of 150 mm size in an integrated


stone crushing unit of 200 tonnes per hour capacity
comprising of primary and secondary crushing units, belt
conveyor and vibrating screens to obtain stone aggregates
of 20 mm nominal size.
Unit = cum
Taking Output = 670 cum at crusher location.
a) Labour
Mate

day

0.760

673.00

511.48

L-12

Mazdoor Skilled

day

2.000

377.00

754.00

L-14

Mazdoor including breaking of any size boulder.

day

17.000

377.00

6409.00

L-13

cum

800.000

210.00

168000.00

M-001

Integrated stone crusher of 200 TPH including belt


conveyor and vibrating screens
Front end loader 1 cum bucket capacity

Hour

6.000

17103.00

102618.00

P&M-028

Hour

20.000

756.00

15120.00

P&M-017

Tipper 5.5 cum capacity

Hour

20.000

291.00

5820.00

P&M-048

b)

Material

c)

Machinery

Stone Boulder of size 150 mm and below

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

29923.25
32915.57

Cost for 670 cum = a+b+c+d+e

362071.30

Rate per cum = (a+b+c+d+e)*0.90/670

486.36
say

Note

1.8

486.00

1. 800 cum of stone boulders are needed to get 600 cum of


stone chips of size 20 and 40 mm.
2. 90 per cent of above cost will be attributed to the
production of 670 cum of stone aggregates of 20mm size
and balance 10 per cent will be for smaller size aggregates
and stone dust which comes out as a by-product.
3. The integrated stone crusher includes primary and
secondary crushing units.
Crushing of Stone Aggregates 40 mm Nominal Size
Crushing of stone boulders of 150 mm size in an integrated
stone crushing unit of 200 tonnes per hour capacity
comprising of primary and secondary crushing units, belt
conveyor and vibrating screens to obtain stone aggregates
of 40 mm nominal size.
Unit = cum
Taking Output = 750 cum at crusher location.
a) Labour
Mate

day

0.760

673.00

511.48

L-12

Mazdoor Skilled

day

2.000

377.00

754.00

L-14

Page 3 of 394

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Mazdoor

Quantity

Rate Rs

Cost Rs

day

17.000

377.00

6409.00

cum

800.000

210.00

168000.00

M-001

Integrated stone crusher of 200 TPH including belt


conveyor and vibrating screens
Front end loader 1 cum bucket capacity

Hour

6.000

17103.00

102618.00

P&M-028

Hour

20.000

756.00

15120.00

P&M-017

Tipper 5.5 cum capacity

Hour

20.000

291.00

5820.00

P&M-048

b)

Material

c)

Machinery

Stone Boulder of size 150 mm and below

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

29923.25
32915.57

Cost for 750 cum = (a+b+c+d+e)x0.85

307760.61

Rate per cum = (a+b+c+d+e)x0.85/750

410.35
say

Note

Remarks/
Input ref.

1. 800 cum of stone boulders are needed to get 600 cum of


stone chips of size 13.2 mm.
2. 85 per cent of above cost will be attributed to the
production of 750 cum of stone aggregates of 40mm size
and balance 15 per cent will be for smaller size aggregates
and stone dust which comes out as a by-product.
3. The integrated stone crusher includes primary and
secondary crushing units.

Page 4 of 394

410.00

L-13

CHAPTER-2
SITE CLEARANCE
Sr No

Ref. to
MoRTH
Spec.

2.1

201

Description

Unit

Quantity

Rate Rs

Cost Rs

Cutting of Trees, including cutting of Trunks, Branches


and Removal
Cutting of trees, including cutting of trunks, branches and
removal of stumps, roots, stacking of serviceable material
with all lifts and up to a lead of 1000 metres and earth filling
in the depression/pit.
(i)

Unit = Each
Girth from 300 mm to 600 mm
a)

Labour
Mate

day

0.020

673.00

13.46

L-12

day

0.600

377.00

226.20

L-13

b)

Mazdoors for cutting trees including cutting, refilling,


compaction of backfilling and stacking of serviceable
materials within 1000 metres lead by manual means.
Machinery

hour

0.100

340.00

34.00

P&M-053

Tractor-trolley
c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

27.37
30.10

Rate for each tree = a+b+c+d

331.13
say

2.1

(ii)

Mate

day

0.040

673.00

26.92

L-12

Mazdoors for cutting trees including cutting, refilling,


compaction of backfilling, and stacking of serviceable
materials within 1000 metres lead by manual means

day

0.900

377.00

339.30

L-13

hour

0.300

340.00

102.00

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

46.82
51.50

Rate for each tree = a+b+c+d

566.55
say

(iii)

Mate

day

0.080

673.00

53.84

L-12

Mazdoors for cutting trees including cutting, refilling,


compaction of backfilling and stacking of serviceable
materials within 1000 metres

day

2.000

377.00

754.00

L-13

hour

0.400

340.00

136.00

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

94.38
103.82

Rate for each tree = a+b+c+d


(iv)

567.00

Girth from 900 mm to 1800 mm


a) Labour

b)

2.1

331.00

Girth from 600 mm to 900 mm


a) Labour

b)

2.1

Remarks/
Input ref.

1142.05

Girth above 1800 mm


a) Labour
Mate
Mazdoors for cutting trees including cutting, refilling,
compaction of backfilling and stacking of serviceable
materials within 1000 metres
Machinery
Tractor-trolley
c) Overhead charges @ 0.1 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Rate for each tree = a+b+c+d

say

1142.00

day
day

0.160
4.000

673.00
377.00

107.68
1508.00

L-12
L-13

hour

0.600

340.00

204.00
181.97
200.16
2201.81
2202.00

P&M-053

b)

say
2.2

201

Clearing Grass and Removal of Rubbish


Clearing grass and removal of rubbish up to a distance of 50
metres outside the periphery of the area .
By Manual Means
Unit = Hectare
Taking output = 1 Hectare
Page 1 of 394

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Labour
Mate
Mazdoor
b) Overhead charges @ 0.1 on (a)
c) Contractor's profit @ 0.1 on (a+b)
Rate per Hectare = a+b+c

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

a)

day
day

2.000
50.000

673.00
377.00

say
2.3

201

Unit = Hectare
Taking output = 1 Hectare
By Manual Means:In area of light jungle
a)

b)

Labour
Mate

day

6.000

673.00

4038.00

L-12

Mazdoor

day

150.000

377.00

56550.00

L-13

hour

1.000

340.00

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

6702.08

b)

Labour
Mate

day

8.000

673.00

5384.00

L-12

Mazdoor

day

200.000

377.00

75400.00

L-13

hour

2.000

340.00

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

By Mechanical Means

In area of light jungle


a)

b)

P&M-053

8961.04
98571.44
say

(ii)

680.00
8146.40

Rate per Hectare = a+b+c+d

98571.00

Labour
Mate

day

0.160

673.00

107.68

L-12

Mazdoor

day

4.000

377.00

1508.00

L-13

hour

10.000

3490.00

34900.00

P&M-014

hour

1.000

340.00

340.00

P&M-053

Machinery
Dozer 80 HP with attachment for removal of trees &
stumps
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

3685.57

d)

Contractor's profit @ 0.1 on (a+b+c)

4054.12

Rate per Hectare = a+b+c+d

44595.37
say

73723.00

In area of thorny jungle


a)

2.3 (ii)

P&M-053

73722.88
say

340.00
6092.80

Rate per Hectare = a+b+c+d

2.3

L-12
L-13

Clearing and Grubbing Road Land .


Clearing and grubbing road land including uprooting rank
vegetation, grass, bushes, shrubs, saplings and trees girth
up to 300 mm, removal of stumps of trees cut earlier and
disposal of unserviceable materials and stacking of
serviceable material to be used or auctioned, up to a lead of
1000 metres including removal and disposal of top organic
soil not exceeding 150 mm in thickness.

(i)

2.3 (i)

1346.00
18850.00
2019.60
2221.56
24437.16
24437.00

44595.00

In area of thorny jungle


a)

b)

Labour
Mate

day

0.240

673.00

161.52

L-12

Mazdoor

day

6.000

377.00

2262.00

L-13

hour

12.000

3490.00

41880.00

P&M-014

hour

1.500

340.00

510.00

P&M-053

Machinery
Dozer 80 HP with attachment for removal of trees &
stumps
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)


Page 2 of 394

4481.35

Sr No

Ref. to
MoRTH
Spec.

Description
d)

Unit

Quantity

Rate Rs

Cost Rs

Contractor's profit @ 0.1 on (a+b+c)

4929.49

Rate per Hectare = a+b+c+d

54224.36
say

2.4

202

Remarks/
Input ref.

54224.00

Dismantling of Structures
Dismantling of existing structures like culverts, bridges,
retaining walls and other structure comprising of masonry,
cement concrete, wood work, steel work, including T&P and
scaffolding wherever necessary, sorting the dismantled
material, disposal of unserviceable material and stacking the
serviceable material with all lifts and lead of 1000 metres
Unit = cum
Taking output = 1.25 cum
(i)

Lime /Cement Concrete


I

By Manual Means

Lime Concrete, cement concrete grade M-10 and below


a)

b)

Labour
Mate

day

0.040

673.00

26.92

L-12

Mazdoor for dismantling and loading

day

1.000

377.00

377.00

L-13

hour

0.270

340.00

91.80

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

49.57
54.53

Cost for 1.25 cum = a+b+c+d

599.82

Rate per cum = (a+b+c+d)/ 1.25

479.86
say

2.4 (i)

a)

b)

Labour
Mate

day

0.050

673.00

33.65

L-12

Mazdoor for dismantling and loading

day

1.250

377.00

471.25

L-13

hour

0.270

340.00

91.80

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

59.67
65.64

Cost for 1.25 cum = a+b+c+d

722.01

Rate per cum = (a+b+c+d)/ 1.25


2.4 (i)

577.61
say

578.00

Prestressed / Reinforced cement concrete grade M-20 &


above
a) Labour

b)

Mate

day

0.150

673.00

100.95

L-12

Blacksmith

day

0.250

500.00

125.00

L-02

Mazdoor for dismantling, loading and unloading

day

3.500

377.00

1319.50

L-13

hour

0.270

340.00

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

180.10
1584.86

II

By Mechanical Means for items No. 202( b)& ( c)

Cement Concrete Grade M-15 & M-20

b)

P&M-053

1981.07

Rate per cum = (a+b+c+d)/ 1.25

a)

91.80
163.73

Cost for 1.25 cum = a+b+c+d

2.4

480.00

Cement Concrete Grade M-15 & M-20

say

1585.00

Labour
Mate

day

0.020

673.00

13.46

L-12

Mazdoor for loading and unloading

day

0.250

377.00

94.25

L-13

Mazdoor with Pneumatic breaker

day

0.250

377.00

94.25

L-14

Machinery

Page 3 of 394

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Air Compressor 250 cfm with 2 leads of pneumatic


breaker @ 1.5 cum per hour
Tractor-trolley
c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

Quantity

Rate Rs

Cost Rs

hour

0.670

300.00

201.00

P&M-001

hour

0.270

340.00

91.80

P&M-053

49.48
54.42

Cost for 1.25 cum = a+b+c+d

598.66

Rate per cum = (a+b+c+d)/ 1.25

478.93
say

2.4 II

Mate

day

0.050

673.00

33.65

L-12

Mazdoor with Pneumatic breaker

day

0.660

377.00

248.82

L-14

Blacksmith

day

0.250

500.00

125.00

L-02

Mazdoor for loading and unloading

day

0.250

377.00

94.25

L-13

hour

1.000

300.00

300.00

P&M-001

hour

0.270

340.00

91.80

P&M-053

Machinery
Air Compressor 250 cfm with 2 leads of pneumatic
breaker @ 1.00 cum per hour
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

89.35
98.29

Cost for 1.25 cum = a+b+c+d

1081.16

Rate per cum = (a+b+c+d)/ 1.25

864.93
say

(ii)

Dismantling Brick / Tile work

In lime mortar
a)

b)

Mate

day

0.020

673.00

13.46

L-12

Mazdoor for dismantling, loading and unloading

day

0.500

377.00

188.50

L-13

hour

0.270

340.00

91.80

P&M-053

Machinery

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

29.38
32.31

Cost for 1.25 cum = a+b+c+d

355.45

Rate per cum = (a+b+c+d)/ 1.25

284.36
say

b)

Labour
Mate

day

0.030

673.00

20.19

L-12

Mazdoor for dismantling, loading and unloading

day

0.750

377.00

282.75

L-13

hour

0.270

340.00

91.80

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

39.47
43.42

Cost for 1.25 cum = a+b+c+d

477.64

Rate per cum = (a+b+c+d)/ 1.25

382.11
say

284.00

In cement mortar
a)

2.4 (ii)

865.00

Labour

Tractor-trolley

2.4 (ii)

479.00

Prestressed / reinforced cement concrete grade M-20 &


above
a) Labour

b)

2.4

Remarks/
Input ref.

382.00

In mud mortar
a)

b)

Labour
Mate

day

0.016

673.00

10.77

L-12

Mazdoor for dismantling and loading

day

0.400

377.00

150.80

L-13

hour

0.270

340.00

91.80

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

25.34
27.87

Cost for 1.25 cum = a+b+c+d

306.58

Rate per cum = (a+b+c+d)/ 1.25

245.26

Page 4 of 394

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs
say

2.4 (ii)

b)

Labour
Mate

day

0.014

673.00

9.42

L-12

Mazdoor for Dismantling, loading and unloading

day

0.350

377.00

131.95

L-13

hour

0.270

340.00

91.80

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

23.32
25.65

Cost for 1.25 cum = a+b+c+d

282.14

Rate per cum = (a+b+c+d)/ 1.25

225.71
say

(iii)
A

Rubble stone masonry in lime mortar

b)

Labour
Mate

day

0.024

673.00

16.15

L-12

Mazdoor for dismantling, loading and unloading.

day

0.600

377.00

226.20

L-13

hour

0.270

340.00

91.80

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

33.42
36.76

Cost for 1.25 cum = a+b+c+d

404.32

Rate per cum = (a+b+c+d)/ 1.25

323.46
say

b)

Labour
Mate

day

0.030

673.00

20.19

L-12

Mazdoor for dismantling, loading and unloading.

day

0.750

377.00

282.75

L-13

hour

0.270

340.00

91.80

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

39.47
43.42

Cost for 1.25 cum = a+b+c+d

477.64

Rate per cum = (a+b+c+d)/ 1.25

382.11
say

b)

Labour
Mate

day

0.020

673.00

13.46

L-12

Mazdoor for dismantling, loading and unloading.

day

0.500

377.00

188.50

L-13

hour

0.270

340.00

91.80

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

29.38
32.31

Cost for 1.25 cum = a+b+c+d

355.45

Rate per cum = (a+b+c+d)/ 1.25

284.36
say

382.00

Rubble Stone Masonry in mud mortar.


a)

2.4 (iii)

323.00

Rubble stone masonry in cement mortar.


a)

2.4 (iii)

226.00

Dismantling Stone Masonry


a)

2.4 (iii)

245.00

Dry brick pitching or brick soling


a)

2.4

Remarks/
Input ref.

284.00

Dry rubble masonry


a)

b)

Labour
Mate

day

0.018

673.00

12.11

L-12

Mazdoor for dismantling, loading and unloading.

day

0.450

377.00

169.65

L-13

hour

0.270

340.00

91.80

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

27.36
30.09

Cost for 1.25 cum = a+b+c+d

331.01

Rate per cum = (a+b+c+d)/ 1.25

264.81
Page 5 of 394

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs
say

2.4 (iii)

b)

Labour
Mate

day

0.016

673.00

10.77

L-12

Mazdoor for dismantling, loading and unloading.

day

0.400

377.00

150.80

L-13

hour

0.270

340.00

91.80

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

25.34
27.87

Cost for 1.25 cum = a+b+c+d

306.58

Rate per cum = (a+b+c+d)/ 1.25

245.26
say

b)

Labour
Mate

day

0.020

673.00

13.46

L-12

Mazdoor for dismantling, loading and unloading

day

0.500

377.00

188.50

L-13

hour

0.270

340.00

91.80

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

29.38
32.31

Cost for 1.25 cum = a+b+c+d

355.45

Rate per cum = (a+b+c+d)/ 1.25

284.36
say

(iv)

Mate

day

0.060

673.00

40.38

L-12

Carpenter

day

0.500

500.00

250.00

L-04

Mazdoor for dismantling, loading and unloading.

day

1.000

377.00

377.00

L-13

hour

0.270

340.00

91.80

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

75.92
83.51

Cost for 1.25 cum = a+b+c+d

918.61

Rate per cum = (a+b+c+d)/ 1.25

734.89
say

(v)

284.00

Wood Work wrought framed and fixed in frames of


trusses upto a height of 5 m above plinth level
a) Labour

b)

2.4

245.00

Dismantling boulders laid in wire crates including


opening of crates and stacking dismantled materials.
a)

2.4

265.00

Dismantling stone pitching/ dry stone spalls.


a)

2.4 (iii)

Remarks/
Input ref.

735.00

Steel Work in all types of sections upto a height of 5 m


above plinth level excluding cutting of rivet.
Unit = tonne
Taking output = 1 tonne

Including dismembering
a)

Labour
Mate

day

0.140

673.00

94.22

L-12

Blacksmith

day

1.000

500.00

500.00

L-02

Mazdoor for dismantling, loading and unloading

day

2.500

377.00

942.50

L-13

Add 2.5 per cent of cost of labour for gas cutting, ropes,
pulleys etc.
b) Machinery
Tractor-trolley

38.42

hour

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

0.170

340.00

P&M-053

179.62

Rate per tonne = a+b+c+d


2.4 (v)

57.80
163.29
1975.85

say

1976.00

673.00

148.06

Excluding dismembering.
a)

Labour
Mate

day
Page 6 of 394

0.220

L-12

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Mazdoor for dismantling, loading and unloading

day

2.000

377.00

754.00

L-13

Blacksmith

day

0.500

500.00

250.00

L-02

Add 2.5 per cent of cost of labour for gas cutting, ropes,
pulleys etc.
b) Machinery
Tractor-trolley

28.80

hour

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

0.170

340.00

P&M-053

136.25
1498.78
say

57.80
123.87

Rate per tonne = a+b+c+d


2.4 (v)

Remarks/
Input ref.

1499.00

Extra over item No( v ) A and( v ) B for cutting rivets.


Unit = each
Taking output = 10 rivets
a)

Labour
Mate

day

0.010

673.00

6.73

L-12

Blacksmith

day

0.130

500.00

65.00

L-02

Mazdoor

day

0.130

377.00

49.01

L-13

b)

Overhead charges @ 0.1 on (a)

12.07

c)

Contractor's profit @ 0.1 on (a+b)

13.28

Cost for 10 rivets = a+b+c

146.10

Rate for each rivet = ( a+b+c)/10

14.61
say

2.4

(vi)

15.00

Scraping of Bricks Dismantled from Brick Work


including Stacking.
Unit = numbers
Taking output = 1000 numbers

In lime/Cement mortar
a)

Labour
Mate

day

0.140

673.00

94.22

L-12

Mazdoor

day

3.500

377.00

1319.50

L-13

b)

Overhead charges @ 0.1 on (a)

c)

Contractor's profit @ 0.1 on (a+b)

141.37
155.51

Rate per1000 Nos = a+b+c

1710.60
say

2.4 (iv)

a)

Labour
Mate

day

0.050

673.00

33.65

L-12

Mazdoor

day

1.250

377.00

471.25

L-13

b)

Overhead charges @ 0.1 on (a)

50.49

c)

Contractor's profit @ 0.1 on (a+b)

55.54

Rate per1000 Nos = a+b+c

610.93
say

2.4

(vii)

1711.00

In mud mortar

611.00

Scraping of Stone from Dismantled Stone Masonry


Unit = cum
Taking output = 1 cum

In cement and lime mortar


a)

Labour
Mate

day

0.060

673.00

40.38

L-12

Mazdoor

day

1.400

377.00

527.80

L-13

b)

Overhead charges @ 0.1 on (a)

56.82

c)

Contractor's profit @ 0.1 on (a+b)

62.50

Rate per cum = a+b+c


2.4 (vii)

687.50
say

687.00

673.00

6.73

In Mud mortar
a)

Labour
Mate

day
Page 7 of 394

0.010

L-12

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Mazdoor

Quantity
day

b)

Overhead charges @ 0.1 on (a)

c)

Contractor's profit @ 0.1 on (a+b)

0.300

Rate Rs

Cost Rs

377.00

13.18
144.99
say

(viii)

L-13

11.98

Rate per cum = a+b+c


2.4

113.10

Remarks/
Input ref.

145.00

Scarping Plaster in Lime or Cement Mortar from Brick/


Stone Masonry
Unit = sqm
Taking output = 100 sqm
a)

b)

Labour
Mate

day

0.160

673.00

107.68

L-12

Mazdoor for scarping and loading

day

4.000

377.00

1508.00

L-13

hour

0.320

340.00

108.80

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

172.45
189.69

Cost for 100 sqm = a+b+c+d

2086.62

Rate per sqm = (a+b+c+d)/100

20.87
say

2.4

(ix)

21.00

Removing all type of Hume Pipes and Stacking within a


lead of 1000 metres including Earthwork and
Dismantling of Masonry Works.
Unit = metre
Taking output = 1 metre

Up to 600 mm dia
a)

Labour
Mate

day

0.020

673.00

13.46

L-12

Mazdoor

day

0.520

377.00

196.04

L-13

b)

Overhead charges @ 0.1 on (a)

20.95

c)

Contractor's profit @ 0.1 on (a+b)

23.05

Rate per metre = a+b+c

253.50
say

2.4 (ix)

a)

Labour
Mate

day

0.030

673.00

20.19

L-12

Mazdoor

day

0.700

377.00

263.90

L-13

b)

Overhead charges @ 0.1 on (a)

28.41

c)

Contractor's profit @ 0.1 on (a+b)

31.25

Rate per metre = a+b+c

343.75
say

2.4 (ix)

Labour
Mate

day

0.050

673.00

33.65

L-12

Mazdoor

day

1.200

377.00

452.40

L-13

b)

Overhead charges @ 0.1 on (a)

48.61

c)

Contractor's profit @ 0.1 on (a+b)

53.47

Rate per metre = a+b+c

588.12
say

2.5

202

344.00

Above 900 mm
a)

Note

253.00

Above 600 mm to 900 mm dia

1. The excavation of earth, dismantling of stone masonry


work in head walls and protection works is not included
which is to be measured and paid separately.
2. Credit for retrieved stone from masonry work may be
taken as per actual availability.
Dismantling of Flexible Pavements
Dismantling of flexible pavements and disposal of
dismantled materials up to a lead of 1000 metres, stacking
serviceable and unserviceable materials separately
Unit = cum
Taking output = 1 cum
Page 8 of 394

588.00

Sr No

Ref. to
MoRTH
Spec.

Description
I

By Manual Means

Bituminous courses
a)

b)

Unit

Quantity

Rate Rs

Cost Rs

Labour
Mate

day

0.060

673.00

40.38

L-12

Mazdoor for dismantling, loading and unloading

day

1.500

377.00

565.50

L-13

hour

0.380

340.00

129.20

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

73.51
80.86

Rate per cum = a+b+c+d

889.45
say

2.5 I

b)

Labour
Mate

day

0.040

673.00

26.92

L-12

Mazdoor for dismantling, loading and unloading.

day

1.000

377.00

377.00

L-13

hour

0.330

340.00

112.20

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

51.61
56.77

Rate per cum = a+b+c+d

624.51
say

II

By Mechanical Means

Bituminous course
a)

b)

Mate

day

0.010

673.00

6.73

L-12

Mazdoor

day

0.300

377.00

113.10

L-13

Tractor-trolley

hour

0.380

340.00

129.20

P&M-053

Farm tractor with ripper @ 60 cum per hour

hour

0.017

366.00

6.22

P&M-055

Machinery

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

25.53
28.08
308.85
say

202

625.00

Labour

Rate per cum = a+b+c+d


2.6

889.00

Granular courses
a)

2.5

Remarks/
Input ref.

309.00

Dismantling of Cement Concrete Pavement


Dismantling of cement concrete pavement by mechanical
means using pneumatic tools, breaking to pieces not
exceeding 0.02 cum in volume and stock piling at
designated locations and disposal of dismantled materials
up to a lead of 1000 metres, stacking serviceable and
unserviceable materials separately
Unit = cum
Taking output = 1 cum
a)

b)

Labour
Mate

day

0.030

673.00

20.19

L-12

Semi skilled mazdoor for operating pneumatic tools

day

0.500

377.00

188.50

L-14

Mazdoors as helpers including loading and unloading

day

0.500

377.00

188.50

L-13

Air compressor 250 cfm with two leads for pneumatic


cutters/ hammers @ 1 cum per hour
Tractor-trolley

hour

1.000

300.00

300.00

P&M-001

hour

0.400

340.00

136.00

P&M-053

Joint Cutting Machine with 2-3 blades

hour

1.000 Not in SOR

Machinery

#VALUE! P&M-083

c)

Overhead charges @ 0.1 on (a+b)

#VALUE!

d)

Contractor's profit @ 0.1 on (a+b+c)

#VALUE!

Rate per cum = a+b+c+d

#VALUE!
say

Page 9 of 394

#VALUE!

Sr No

Ref. to
MoRTH
Spec.

Description
Note

2.7

202

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

The above analysis is for removal of complete pavement. In


case full depth repair work is required to be done after
dismantling, provision of a concrete cutting and sawing
machine may be added for 0.25 hours.
Dismantling of Guard Rails
Dismantling guard rails by manual means and disposal of
dismantled material with all lifts and up to a lead of 1000
metres, stacking serviceable materials and unserviceable
materials separately.
Unit = running metre
Taking output = 1 metre
a)

b)

Labour
Mate

day

0.006

673.00

4.04

L-12

Mazdoor including loading and unloading

day

0.150

377.00

56.55

L-13

hour

0.050

340.00

17.00

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

7.76
8.53

Rate per metre = a+b+c+d

93.88
say

2.8

202

94.00

Dismantling of Kerb Stone


Dismantling kerb stone by manual means and disposal of
dismantled material with all lifts and up to a lead of 1000
metre
Unit = running metre
Taking output = 10 metre
a)

b)

Labour
Mate

day

0.010

673.00

6.73

L-12

Mazdoor including loading and unloading

day

0.150

377.00

56.55

L-13

hour

0.200

340.00

68.00

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

13.13
14.44

Cost for 10 m = a+b+c+d

158.85

Rate per metre = (a+b+c+d)/10


2.9

202

15.88
say

16.00

Dismantling of Kerb Stone Channel


Dismantling kerb stone channel by manual means and
disposal of dismantled material with all lifts and up to a lead
of 1000 metre
Unit = running metre
Taking output = 10 metre
a)

b)

Labour
Mate

day

0.015

673.00

10.10

L-12

Mazdoor including loading and unloading

day

0.225

377.00

84.83

L-13

hour

0.300

340.00

102.00

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

19.69
21.66

Cost for 10 m = a+b+c+d

238.27

Rate per metre = (a+b+c+d)/10

23.83
say

2.10

202

Dismantling of Kilometre Stone


Dismantling of kilometre stone including cutting of earth,
foundation and disposal of dismantled material with all lifts
and lead upto 1000 m and back filling of pit.
Unit = Each
Taking output = one KM stone

5th KM stone

Page 10 of 394

24.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Quantity of cement concrete = 0.392 cum


a)

b)

Labour
Mate

day

0.130

673.00

87.49

L-12

Mazdoor

day

0.750

377.00

282.75

L-13

hour

0.150

340.00

51.00

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

42.12
46.34

Rate for one 5th KM stone = a+b+c+d

509.70
say

510.00

Ordinary KM Stone
Quantity of cement concrete = 0.269 cum
a)

b)

Labour
Mate

day

0.020

673.00

13.46

L-12

Mazdoor

day

0.500

377.00

188.50

L-13

hour

0.100

340.00

34.00

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

23.60
25.96

Rate for one ordinary KM stone = a+b+c+d

285.51
say

286.00

Hectometre Stone
Quantity of cement concrete = 0.048 cum
a)

b)

Labour
Mate

day

0.004

673.00

2.69

L-12

Mazdoor

day

0.100

377.00

37.70

L-13

hour

0.020

340.00

6.80

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

4.72

d)

Contractor's profit @ 0.1 on (a+b+c)

5.19

Rate for one Hectometre stone = a+b+c+d

57.10
say

2.11

202

57.00

Dismantling of Fencing
Dismantling of barbed wire fencing/ wire mesh fencing
including posts, foundation concrete, back filling of pit by
manual means including disposal of dismantled material with
all lifts and up to a lead of 1000 metres, stacking serviceable
material and unserviceable material separately.
Unit = running metre
Taking output = 30 metres
a)

b)

Labour
Mate

day

0.150

673.00

100.95

L-12

Mazdoor including loading and unloading

day

3.000

377.00

1131.00

L-13

Blacksmith

day

0.750

500.00

375.00

L-02

hour

0.150

340.00

51.00

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

165.80
182.37

Cost for 30 metres = a+b+c+d

2006.12

Rate per metre = (a+b+c+d)/30

66.87
say

2.12

202

Dismantling of CI Water Pipe Line


Dismantling of CI water pipe line 600 mm dia including
disposal with all lifts and lead upto 1000 metres and stacking
of serviceable material and unserviceable material
separately under supervision of concerned department

Page 11 of 394

67.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Unit = running metre


Taking output = 10 metres
a)

b)

Labour
Mate

day

0.090

673.00

60.57

L-12

Mazdoor

day

2.000

377.00

754.00

L-13

Plumber

day

0.250

500.00

125.00

L-02

Truck 10 tonne capacity

hour

0.250

291.00

72.75

P&M-057

Light Crane 3 tonne capacity

hour

0.500

334.00

167.00

P&M-013

Machinery

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

117.93
129.73

Cost for 10 metres = a+b+c+d

1426.98

Rate per metre = (a+b+c+d)/10

142.70
say

Note

2.13

202

143.00

The rate analysis does not include any excavation in earth or


dismantling of masonry works which are to be measured and
paid separately.
Removal of Cement Concrete Pipe of Sewer Gutter
Removal of cement concrete pipe of sewer gutter 1500 mm
dia under the supervision of concerned department including
disposal with all lifts and up to a lead of 1000 metres and
stacking of serviceable and unserviceable material
separately but excluding earth excavation and dismantling of
masonry works.
Unit = running metre
Taking output = 10 metres
a)

b)

Labour
Mate

day

0.100

673.00

67.30

L-12

Mazdoor

day

2.500

377.00

942.50

L-13

Crane 5 tonne capacity

hour

0.300

334.00

100.20

P&M-070

Truck flat body 10 tonne

hour

1.000

291.00

291.00

P&M-057

Machinery

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

140.10
154.11

Cost for 10 metres = a+b+c+d

1695.21

Rate per metre = (a+b+c+d)/10

169.52
say

Note

2.14

202

170.00

The rate analysis does not include any excavation in earth or


dismantling of masonry works which are to be measured and
paid separately.
Removal of Telephone / Electric Poles and Lines
Removal of telephone / Electric poles including excavation
and dismantling of foundation concrete and lines under the
supervision of concerned department, disposal with all lifts
and up to a lead of 1000 metres and stacking the
serviceable and unserviceable material separately
Unit = each
Taking output = 30 Nos
a)

b)

Labour
Mate

day

0.480

673.00

323.04

L-12

Mazdoor

day

10.000

377.00

3770.00

L-13

Electrician/Lineman

day

2.000

500.00

1000.00

L-02

hour

1.500

340.00

510.00

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

560.30
616.33

Cost for 30 poles = a+b+c+d

6779.68

Rate per pole = (a+b+c+d)/30

225.99
say

Page 12 of 394

226.00

CHAPTER - 3
EARTH WORK, EROSION CONTROL AND DRAINAGE
Sr No

Ref. to
MoRTH
Spec.

3.1

301

Description
Excavation in Soil by Manual Means .
Excavation for roadway in soil using manual means
including loading in truck for carrying of cut earth to
embankment site with all lifts and lead upto1000 metres.
Unit = cum
Taking output = 120 cum
a) Labour
Mate
Mazdoor
b) Machinery
Truck 5.5 cum capacity
c) Overhead charges @ 0.1 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Cost of 120 cum = a+b+c+d
Rate per cum = (a+b+c+d)/120
Note

3.2

Unit

301

Cost Rs

Remarks/
Input ref.

day
day

1.800
45.000

673.00
377.00

1211.40
16965.00

L-12
L-13

hour

10.000

291.00

P&M-057

say

2910.00
2108.64
2319.50
25514.54
212.62
213.00

Excavation in Ordinary Rock by Manual Means


Excavation in ordinary rock using manual means including
loading in a truck and carrying of excavated material to
embankment site with in all lifts and leads upto 1000 metres

Note

301

Rate Rs

In case there is a situation where the cross-section is of cut


and fill and cut earth is required to be used in embankment
in the immediate vicinity, the item of carriage in the truck
shall be omitted.

Unit = cum
Taking output = 120 cum
a) Labour
Mate
Mazdoor
b) Machinery
Truck 5.5 cum capacity
c) Overhead charges @ 0.1 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Cost for 120 cum = a+b+c+d
Rate per cum = (a+b+c+d)/120

3.3

Quantity

day
day

2.800
70.000

673.00
377.00

1884.40
26390.00

L-12
L-13

hour

10.000

291.00

P&M-057

say

2910.00
3118.44
3430.28
37733.12
314.44
314.00

In case there is a situation where the cross-section is of cut


and fill and cut earth is required to be used in embankment
in the immediate vicinity, the item of carriage in the truck
shall be omitted.
Excavation in Soil with Dozer with lead upto 100 metres
Excavation for road way in soil by mechanical means
including cutting and pushing the earth to site of
embankment upto a distance of 100 metres (average lead50
metres), including trimming bottom and side slopes in
accordance with requirements of lines, grades and cross
sections.
Unit = cum
Taking output = 180 cum
a) Labour
Mate
Mazdoor
b) Machinery
Dozer, 80 HP @ 30 cum per hour
c) Overhead charges @ 0.1 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Cost for 180 cum = a+b+c+d
Rate per cum = (a+b+c+d)/180

day
day

0.080
2.000

673.00
377.00

53.84
754.00

hour

6.000

3490.00

20940.00
2174.78
2392.26
26314.89
146.19
146.00

say
3.4

301

Excavation in Ordinary Rock with Dozer with lead upto


100 metres

Page 1 of 394

L-12
L-13
P&M-014

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Excavation for roadway in ordinary rock by deploying a


dozer, 80 HP including cutting and pushing the cut earth to
site of embankment upto a distance of 100 metres ( average
lead 50 metres ), trimming bottom and side slopes in
accordance with the requirements of lines, grades and cross
sections.
Unit = cum
Taking output = 108 cum
a) Labour
Mate
Mazdoor
b) Machinery
Dozer, 80 HP @ 20 cum per hour
c) Overhead charges @ 0.1 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Cost for 108 cum = a+b+c+d
Rate per cum = (a+b+c+d)/108

day
day

0.120
3.000

673.00
377.00

80.76
1131.00

L-12
L-13

hour

6.000

3490.00

20940.00
2215.18
2436.69
26803.63
248.18
248.00

P&M-014

say
3.5

301

Excavation in Hard Rock (requiring blasting)


with
disposal upto 1000 metres
Excavation for roadway in hard rock (requiring blasting)
by drilling, blasting and breaking, trimming of bottom and
side slopes in accordance with requirements of lines, grades
and cross sections, loading and disposal of cut road with in
all lifts and leads upto 1000 metres
Unit = cum
Taking 0utput = 180 cum
a)

b)

Labour
Mate

day

0.220

673.00

148.06

L-12

Mazdoor

day

3.000

377.00

1131.00

L-13

Driller

day

2.000

400.00

800.00

L-06

Blaster

day

0.250

396.00

99.00

L-03

Dozer, 80 HP @ 30 cum per hour

hour

6.000

3490.00

20940.00

P&M-014

Air compressor, 250 cfm with 2 jack hammer

hour

6.000

300.00

1800.00

P&M-001

Front end loader 1 cum bucket capacity

hour

6.000

756.00

4536.00

P&M-017

Tipper10 tonne capacity

hour

11.250

291.00

3273.75

P&M-048
M-104

Machinery

c)

Materials

d)

Electric Detonators @ 1 detonator for 2 gelatin sticks of


125 gms each
Credit for excavated rock found suitable for use @ 50
per cent quantity blasted
Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

Gelatin 80 per cent

kg

63.000

74.08

4667.04

each

252.000

11.00

2772.00 M-094 /100

cum

90.000

(391.00)

547.45
6021.99

Rate per cum = (a+b+c+d+e)/180

3.6

301

M-089

497.69

Cost for 180 cum = a+b+c+d+e

Note

(35190.00)

33.46
say

33.00

673.00

53.84

1. The quality and availability of rock shall be checked


before affording credit.
2. In case some rock is issued to the contractor at site, the
item of carriage shall be reduced/restricted to that extent.
Excavation in Soil using Hydraulic Excavator CK 90 and
Tippers with Disposal upto 1000 metres.
Excavation for roadwork in soil with hydraulic excavator of
0.9 cum bucket capacity including cutting and loading in
tippers, trimming bottom and side slopes, in accordance with
requirements of lines, grades and cross sections, and
transporting to the embankment location within all lifts and
lead upto 1000m
Unit = cum
Taking output = 360 cum
a)

Labour
Mate

day
Page 2 of 394

0.080

L-12

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Mazdoor
b)

Quantity

Rate Rs

Cost Rs

day

2.000

377.00

754.00

L-13

hour

6.000

1222.00

7332.00

P&M-026

hour

16.000

291.00

4656.00

P&M-048

Machinery
Hydraulic excavator 0.9 cum bucket capacity @ 60
cum per hour
Tipper 5.5 cum capacity, 4 trips per hour.

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

1279.58
1407.54

Cost for 360 cum = a+b+c+d

15482.97

Rate per cum = (a+b+c+d)/360

43.01
say

3.7

Remarks/
Input ref.

43.00

Excavation in Ordinary Rock using Hydraulic Excavator


CK-90 and Tippers with Disposal upto 1000 metres.

301

Excavation for roadway in ordinary rock with hydraulic


excavator of 0.9 cum bucket capacity including cutting and
loading in tippers, transporting to embankment site within all
lifts and lead upto 1000 m, trimming bottom and side slopes
in accordance with requirements of lines, grades and cross
sections.
Unit = cum
Taking output = 240 cum
a)

b)

Labour
Mate

day

0.080

673.00

53.84

L-12

Mazdoor

day

2.000

377.00

754.00

L-13

hour

6.000

1222.00

7332.00

P&M-026

hour

11.000

291.00

3201.00

P&M-048

Machinery
Hydraulic Excavator 0.90 cum bucket capacity @ 36
cum per hour
Tipper 5.5 cum capacity, 4 trips per hour.

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

1134.08
1247.49

Cost for 240 cum = a+b+c+d

13722.42

Rate per cum = (a+b+c+d)/240

57.18
say

3.8

301

57.00

Excavation in Hard Rock (blasting prohibited)


Excavation for roadway in hard rock (blasting prohibited)
with rock breakers including breaking rock, loading in tippers
and disposal within all lifts and lead upto 1000 metres,
trimming bottom and side slopes in accordance with
requirements of lines, grades and cross sections.
A

Mechanised
Unit = cum
Taking output = 36 cum
a)

Labour
Mate

day

0.400

673.00

269.20

L-12

day

10.000

377.00

3770.00

L-13

b)

Mazdoor for trimming slopes including mannul loading


in truck
Machinery
Hydraulic excavator with rock breaker attachment @ 6
cum per hour
Tipper 5.5 cum capacity, 1 trip per hour.

hour

6.000

1222.00

7332.00

P&M-026

hour

6.500

291.00

1891.50

P&M-048

cum

18.000

(391.00)

(7038.00)

M-089

c)

Credit for excavated rock found suitable for use @ 50


per cent of excavated quantity
Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

622.47
684.72

Cost for 36 cum = a+b+c+d

7531.89

Rate per cum = (a+b+c+d)/36

209.22
say

Note

1. The quality and availability of rock shall be checked


before affording credit.
2. In case some rock is issued to the contractor at site, the
item of carriage shall be restricted/reduced to that extent.

Page 3 of 394

209.00

Sr No

Ref. to
MoRTH
Spec.

3.8

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

3.Being small quantity, manual loading will be economical in


this case and has been provided accordingly.
Manual Method
Unit = cum
Taking output = 16 cum
a)

Labour
Mate

day

1.640

673.00

1103.72

L-12

Mazdoor including loading in truck

day

16.000

377.00

6032.00

L-13

Chiseller

day

24.000

400.00

9600.00

L-05

Blacksmith

day

1.000

500.00

500.00

L-02

b)

Machinery
Tipper 5.5 cum capacity, 1 trip per hour.

hour

2.900

291.00

843.90

P&M-048

cum

8.000

(391.00)

(3128.00)

M-089

c)

Credit for excavated rock found suitable for use @ 50


per cent of excavated
Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

1495.16
1644.68

Cost for 16 cum = a+b+c+d

18091.46

Rate per cum = (a+b+c+d)/16

1130.72
say

Note

1131.00

1. Credit is considered for 50 per cent of quantity of work.


2. Loading for disposal will be done manually, being small
quantity.
3. In case some rock is issued to contractor at site, the item
of carriage shall be omitted to the extent of quantity issued
to the contractor.

3.9

301

Excavation in Hard Rock (controlled blasting) with


disposal upto 1000 metres
Excavation for roadway in hard rock with controlled blasting
by drilling, blasting and breaking, trimming of bottom and
side slopes in accordance with requirements of lines, grades
and cross sections, loading and disposal of cut road with in
all lifts and leads upto 1000 metres
Unit = cum
Taking output = 180 cum
a)

b)

c)

Labour
Mate

day

0.220

673.00

148.06

L-12

Mazdoor

day

3.000

377.00

1131.00

L-13

Driller

day

2.000

400.00

800.00

L-06

Blaster

day

0.500

396.00

198.00

L-03

Dozer 80 HP @ 30 cum per hour

hour

6.000

3490.00

20940.00

P&M-014

Air compressor, 250 cfm with 2 jack hammers

hour

6.000

300.00

1800.00

P&M-001

Front end loader 1 cum bucket capacity

hour

6.000

756.00

4536.00

P&M-017

Tipper 5.5 cum capacity, 4 trips per hour.

hour

8.200

291.00

2386.20

P&M-048

4667.04

M-104

Machinery

Materials
Gelatin 80 per cent
Electric Detonators @ 1 detonator for1/2 gelatin stick
of 125 gms each
Credit for excavated rock found suitable for use @ 50
per cent quantity blasted
Add 5 per cent of cost of a+b+c towards muffling
arrangements to guard against any rock fly off during
blasting

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

kg

63.000

74.08

each

1008.000

11.00

cum

90.000

(391.00)

(35190.00)
2384.72

1488.90
1637.79

Cost for 180 cum = a+b+c+d+e

18015.71

Rate per cum = (a+b+c+d+e)/180

100.09
say

Note

11088.00 M-094 /100

1. Credit is considered for 50 per cent of quantity of


blastered rock, if found suitable for construction..

Page 4 of 394

100.00

M-089

Sr No

3.10

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

2. In case some rock is issued to the contractor at site, the


item of carriage shall be reduced to that extent.
Excavation in Marshy Soil

301

Excavation for roadway in marshy soil with hydraulic


excavator 0.9 cum bucket capacity including cutting and
loading in tippers and disposal with in all lifts and lead upto
1000 metres, trimming of bottom and side slopes in
accordance with requirements of lines, grades and cross
sections.
Unit = cum
Taking output = 300 cum
a)

b)

Labour
Mate

day

0.080

673.00

53.84

L-12

Mazdoor

day

2.000

377.00

754.00

L-13

hour

6.000

1222.00

7332.00

P&M-026

hour

13.640

291.00

3969.24

P&M-048

Machinery
Hydraulic excavator 0.90 cum bucket capacity @ 50
cum per hour
Tipper 5.5 cum capacity, 4 trips per hour.

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

1210.91
1332.00

Cost for 300 cum = a+b+c+d

14651.99

Rate per cum = (a+b+c+d)/300

48.84
say

3.11

49.00

Removal of Unserviceable Soil with Disposal upto 1000


metres
Removal of unserviceable soil including excavation, loading
and disposal upto 1000 metres lead but excluding
replacement by suitable soil which shall be paid separately
as per clause 305.

301

Unit = cum
Taking output = 360 cum
a)

b)

Labour
Mate

day

0.080

673.00

53.84

L-12

Mazdoor

day

2.000

377.00

754.00

L-13

hour

6.000

1222.00

7332.00

P&M-026

hour

16.360

291.00

4760.76

P&M-048

Machinery
Excavator0.90 cum bucket capacity @ 60 cum per
hour
Tipper 5.5 cum capacity, 4 trips per hour.

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

1290.06
1419.07

Cost for 360 cum = a+b+c+d

15609.73

Rate per cum = (a+b+c+d)/360

43.36
say

Note

3.12

303

43.00

This item does not include replacement of unsuitable soil by


suitable soil. Replacement, where required, is to be provided
and paid separately under clause 305.
Presplitting of Rock Excavation Slopes
Carrying out excavation in hard rock to achieve a specified
slope of the rock face by controlled use of explosives and
blasting accessories in properly aligned and spaced drill
holes, collection of the excavated rock by a 80 HP dozer,
loading in tipper by a front end loader and disposing of the
material with all lifts and lead upto 1000 m, all as specified in
clause No. 303
Unit = sqm
Taking output = 400 sqm( 120 cum considering 300mm
average depth of excavation over the existing rock face)
a)

b)

Labour
Mate

day

0.600

673.00

403.80

L-12

Mazdoor

day

15.000

377.00

5655.00

L-13

Machinery
Page 5 of 394

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Air compressor 250 cfm with 2 leads @ 20 cum per


hour
Dozer, 80 HP

hour

6.000

300.00

1800.00

P&M-001

hour

6.000

3490.00

20940.00

P&M-014

Front end loader 1 cum bucket capacity

hour

6.000

756.00

4536.00

P&M-017

kg

42.000

74.08

3111.36

M-104

each

672.000

11.00

7392.00 M-094 /100

c)

Materials

d)

Electric Detonators @ 1 detonator for 1/2 gelatin stick


of 125 gms each
Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

Gelatin 80 per cent

4383.82
4822.20

Cost for 400 sqm = a+b+c+d+e

53044.17

Rate per sqm = (a+b+c+d+e)/400

132.61
say

Note

3.13

304

Remarks/
Input ref.

133.00

In case blasted rock is used to the contractor against


payment for constructed work, the cost of carriage shall be
reduced to that extent.
Excavation for Structures
Earth work in excavation of foundation of structures as per
drawing and technical specification, including setting out,
construction of shoring and bracing, removal of stumps and
other deleterious matter, dressing of sides and bottom,
backfilling the excavation earth to the extent required and
utilising the remaining earth locally for road work.

(i)

Ordinary soil
Unit = cum
Taking output = 10 cum

Manual Means (Depth upto 3 m)


a)

Labour
Mate

day

0.320

673.00

215.36

L-12

Mazdoor

day

8.000

377.00

3016.00

L-13

b)

Overhead charges @ 0.1 on (a)

323.14

c)

Contractor's profit @ 0.1 on (a+b)

355.45

Cost for 10 cum = a+b+c

3909.95

Rate per cum = (a+b+c)/10

390.99
say

Note

3.13 (i)

391.00

Cost of dewatering may be added where required upto 10


per cent of labour cost Assessment for dewatering shall be
made as per site conditions..
Mechanical Means (Depth upto 3 m)
Unit = cum
Taking output = 300 cum
a)

b)

Labour
Mate

day

0.320

673.00

215.36

L-12

Mazdoor

day

8.000

377.00

3016.00

L-13

hour

6.000

1222.00

7332.00

P&M-026

Machinery
Hydraulic excavator 1.0 cum bucket capacity

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

1056.34
1161.97

Cost for 300 cum = a+b+c+d

12781.67

Rate per cum = (a+b+c+d)/300


Note

3.13

42.61
say

43.00

673.00

269.20

Cost of dewatering upto 5 per cent of (a+b)


may be
added, where required. Assessment for dewatering shall be
made as per site conditions..

(ii)

Ordinary Rock (not requiring blasting)

Manual Means (Depth upto 3 m)


Unit = cum
Taking output = 10 cum
a)

Labour
Mate

day
Page 6 of 394

0.400

L-12

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Mazdoor

Quantity
day

b)

Overhead charges @ 0.1 on (a)

c)

Contractor's profit @ 0.1 on (a+b)

10.000

Rate Rs

Cost Rs

377.00

444.31
4887.43

Rate per cum = (a+b+c)/10

488.74
say

3.13 (ii)

L-13

403.92

Cost for 10 cum = a+b+c

Note

3770.00

Remarks/
Input ref.

489.00

Cost of dewatering upto 10 per cent of labour cost may be


added, where required. Assessment for dewatering shall be
made as per site conditions..
Mechanical Means
Unit = cum
Taking output = 216 cum
a)

b)

Labour
Mate

day

0.240

673.00

161.52

L-12

Mazdoor

day

6.000

377.00

2262.00

L-13

hour

6.000

1222.00

7332.00

P&M-026

Machinery
Hydraulic excavator 1.0 cum bucket capacity

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

975.55
1073.11

Cost for 216 cum = a+b+c+d

11804.18

Rate per cum = (a+b+c+d)/216


Note

3.13

(iii)
A

54.65
say

55.00

1.Cost of dewatering upto 5 per cent of (a+b), may be


added, where required Assessment for dewatering shall be
made as per site conditions.
2.In case of rock, foundation beyond3 m is not dug and
hence not included.
Hard Rock ( requiring blasting )
Manual Means
Unit = cum
Taking output = 10 cum
a)

Labour
i) Mate

day

0.530

673.00

356.69

L-12

ii) Driller

day

0.840

400.00

336.00

L-06

iii) Blaster

day

0.400

396.00

158.40

L-03

iv) Mazdoor

day

12.000

377.00

4524.00

L-13

hour

0.667

300.00

200.00

P&M-001

kg

3.500

74.08

259.28

M-104

each

14.000

11.00

154.00 M-094 /100

b)

Machinery

c)

Air Compressor 250 cfm with 2 jack hammer @ 15 cum


per hour
Material
Blasting Material
Detonator electric

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

598.84
658.72

Cost for 10 cum = a+b+c+d+e

7245.93

Rate per cum = (a+b+c+d+e)/10

724.59
say

3.13

Note

Cost of dewatering @ 10 per cent of labour cost may be


added, where required Assessment for dewatering shall be
made as per site conditions.

(iv)

Hard Rock ( blasting prohibited )

725.00

Unit = cum
Taking output = 10 cum
A

Mechanical Means
a)

Labour
Mate

day

0.200

673.00

134.60

L-12

Mazdoor

day

5.000

377.00

1885.00

L-13

Page 7 of 394

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

b)

Machinery

c)

Air Compressor 250 cfm with 2 leads of pneumatic


breaker @ 1 cum per hour
Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

Quantity

hour

10.000

Rate Rs

Cost Rs

300.00

552.16
6073.72

Rate per cum = (a+b+c+d)/10

607.37
say

3.13

(v)

P&M-001

501.96

Cost for 10 cum = a+b+c+d

Note

3000.00

Remarks/
Input ref.

607.00

1. Cost of dewatering upto 5 per cent of (a+b), may be


added, where required Assessment for dewatering shall be
made as per site conditions.
2.In case of rock, foundation beyond 3 m is not dug and
hence not included.
Marshy soil
Unit = cum
Taking output = 10 cum

Manual means ( upto 3 m depth)


a)

b)

Labour
Mate/Supervisor

day

0.400

673.00

269.20

L-12

Mazdoor

day

10.000

377.00

3770.00

L-13

hour

2.670

340.00

907.80

P&M-053

cum

5.000

137.00

685.00

M-163

Machinery
Tractor-trolley

c)

Material
Selected earth for refilling

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

563.20
619.52

Cost for 10 cum = a+b+c+d+e

6814.72

Rate per cum = ( a+b+c+d+e)/ 10

681.47
say

Note

681.00

1. Cost of dewatering @ 30 per cent of (a), may be added,


where required Assessment for dewatering shall be made as
per site conditions.
2. Shoring & strutting 20 per cent of (a), where required may
be added
3. It is assumed that Marshy Soil will be available upto 3 m
depth only. For deeper excavation below 3 m depth, refer
analysis in item (i) to (iv) for ordinary soil

3.13 (v)

Mechanical Means
a)

b)

Labour
i) Mate

day

0.080

673.00

53.84

L-12

ii) Mazdoor for dressing sides, bottom and backfilling

day

2.000

377.00

754.00

L-13

hour

0.170

1222.00

207.74

P&M-026

hour

0.450

291.00

130.95

P&M-048

cum

5.000

137.00

685.00

M-163

Machinery
Hydraulic excavator 1.0 cum bucket capacity @ 60
cum per hour
Tipper 5.5 cum capacity, 4 trips per hour.

c)

Material
Selected earth for refilling

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

183.15
201.47

Cost for 10 cum = a+b+c+d+e

2216.15

Rate per cum = (a+b+c+d+e)/10

221.62
say

Note

3.14

305.4.3

1. Cost of dewatering @ 20 per cent of (a+b) may be


added, where required
2. Shoring & strutting @ 10 per cent of (a+b), where
required may be added
3. It is assumed that Marshy Soil will be available upto 3 m
depth only. For deeper excavation below 3 m depth, refer
analysis in item (i) to (iv) for ordinary soil
Scarifying Existing Granular Surface to a Depth of 50
mm by Manual Means
Page 8 of 394

222.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Scarifying the existing granular road surface to a depth of 50


mm and disposal of scarified material within all lifts and
leads upto 1000 metres.
Unit = sqm
Taking output = 100 sqm
a)

b)

Labour
Mate

day

0.200

673.00

134.60

L-12

Mazdoor including loading and unloading

day

5.000

377.00

1885.00

L-13

hour

1.670

340.00

567.80

P&M-053

Machinery
Tractor-trolley

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

258.74
284.61

Cost for 100 sqm = a+b+c+d

3130.75

Rate per sqm = (a+b+c+d)/100

31.31
say

Note
3.15

305.4.3

31.00

In case material is to be reused at site, transportation cost


catered above for disposal shall be deleted.
Scarifying Existing Bituminous Surface to a depth of 50
mm by Mechanical Means
Scarifying the existing bituminous road surface to a depth of
50 mm and disposal of scarified material with in all lifts and
lead upto 1000 metres.
Unit = sqm
Taking output = 100 sqm
a)

b)

Labour
Mate

day

0.010

673.00

6.73

L-12

Mazdoor

day

0.250

377.00

94.25

L-13

Tractor with ripper attachment @ 60 cum per hour

hour

0.080

366.00

29.28

P&M-055

Front end loader 1 cum bucket capacity @ 25 cum per


hour
Tipper 5.5 cum capacity, 4 trips per hour.

hour

0.200

756.00

151.20

P&M-017

hour

0.230

291.00

66.93

P&M-048

Machinery

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

34.84
38.32

Cost for 100 sqm = a+b+c+d

421.55

Rate per sqm = (a+b+c+d)/100

4.22
say

3.16

305

4.00

Construction of Embankment with Material obtained


from Borrowpits
Construction of embankment with approved material
obtained from borrow pits with all lifts and leads, transporting
to site, spreading, grading to required slope and compacting
to meet requirement of table 300-2.
Unit = cum
Taking output = 100 cum
a)

b)

Labour
Mate

day

0.040

673.00

26.92

L-12

Mazdoor

day

1.000

377.00

377.00

L-13

hour

1.670

1222.00

2040.74

P&M-026

tonne.km

160 x L

2.00

320.00

Lead =1
km & P&M058

Machinery
Hydraulic Excavator1 cum bucket capacity @ 60 cum
per hour
Tipper 10 tonne capacity

c)

Add 10 per cent of cost of carriage to cover cost of


loading and unloading
Dozer 80 HP for spreading @ 200 cum per hour

hour

0.500

3490.00

1745.00

P&M-014

Motor grader for grading @ 100 cum per hour

hour

1.000

2247.00

2247.00

P&M-032

Water tanker6 KL capacity

hour

4.000

233.00

932.00

P&M-060

Vibratory roller 8 -10 tonnes @ 100 cum per hour

hour

1.000

1446.00

1446.00

P&M-059

Material
Page 9 of 394

32.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Cost of water
Compensation for earth taken from private land
d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

Quantity

Rate Rs

Cost Rs

KL

24.000

13.00

312.00

M-189

cum

100.000

137.00

13700.00

M-092

2317.87
2549.65

Cost for 100 cum = a+b+c+d+e

28046.18

Rate per cum = (a+b+c+d+e)/100

280.46
say

Note

3.17

305

Remarks/
Input ref.

280.00

Compensation for earth will vary from place to place and will
have to be assessed realistically as per particular ground
situation. In case earth is available from Govt. land,
compensation for earth will not be required. The position is
required to be clearly stated in the cost estimate.
Construction of Embankment with Material Deposited
from Roadway Cutting
Construction of embankment with approved materials
deposited at site from roadway cutting and excavation from
drain and foundation of other structures graded and
compacted to meet requirement of table 300-2.
Unit = cum
Taking output = 100 cum
a)

b)

c)

Labour
Mate

day

0.020

673.00

13.46

L-12

Mazdoor

day

0.500

377.00

188.50

L-13

Dozer 80 HP for spreading @ 200 cum per hour

hour

0.500

3490.00

1745.00

P&M-014

Motor grader for grading @ 100 cum per hour

hour

1.000

2247.00

2247.00

P&M-032

Water tanker6 KL capacity

hour

4.000

233.00

932.00

P&M-060

Vibratory roller 8-10 tonnes @ 100 cum per hour

hour

1.000

1446.00

1446.00

P&M-059

KL

24.000

13.00

312.00

M-189

Machinery

Material
Cost of water

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

688.40
757.24

Rate for 100 cum = a+b+c+d+e

8329.59

Rate per cum = (a+b+c+d+e)/100

83.30
say

Note

3.18

305

83.00

In case the earth cutting is done by dozer and pushed for


filling in the embankment, the input of dozer in the cost of
embankment shall be deleted as the same is already
provided in the cost of excavation. However, if the earth is
dumped by tippers from roadway cutting, the input of dozer
for spreading is required to be provided.
Construction of Subgrade and Earthen Shoulders
Construction of sub-grade and earthen shoulders with
approved material obtained from borrow pits with all lifts &
leads, transporting to site, spreading, grading to required
slope and compacted to meet requirement of table No. 3002
Unit = cum
Taking output = 100 cum
a)

b)

Labour
Mate

day

0.040

673.00

26.92

L-12

Mazdoor

day

1.000

377.00

377.00

L-13

hour

1.670

1222.00

2040.74

P&M-026

tonne.km

175xL

2.00

350.00

Lead =1
km & P&M058

Machinery
Hydraulic excavator1 cum bucket capacity @ 60 cum
per hour
Tipper 10 tonne capacity

Add 10 per cent of cost of carriage to cover cost of


loading and unloading
Dozer 80 HP for spreading @ 200 cum per hour

hour

0.500

3490.00

1745.00

P&M-014

Motor grader for grading @ 50 cum per hour

hour

2.000

2247.00

4494.00

P&M-032

Page 10 of 394

35.00

Sr No

Ref. to
MoRTH
Spec.

Description

c)

Unit

Quantity

Rate Rs

Cost Rs

Water tanker with 6 km lead

hour

4.000

233.00

932.00

P&M-060

Vibratory roller 8-10 tonnes @ 80 cum per hour

hour

1.250

1446.00

1807.50

P&M-059

Material
Cost of water
Compensation for earth taken from private land

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

KL

24.000

13.00

312.00

M-189

cum

100.000

137.00

13700.00

M-092

2582.02
2840.22

Cost for 100 cum = a+b+c+d+e

31242.39

Rate per cum = (a+b+c+d+e)/100

312.42
say

3.19

305.3.4

Remarks/
Input ref.

312.00

Compacting Original Ground


Case-I Compacting original ground supporting sub-grade
Loosening of the ground upto a level of 500 mm below the
sub-grade level, watered, graded and compacted in layers to
meet requirement of table 300-2 for sub-grade construction.
Unit = cum
Taking output = 600 cum
a)

b)

c)

Labour
Mate

day

0.120

673.00

80.76

L-12

Mazdoor

day

3.000

377.00

1131.00

L-13

Tractor with ripper attachment

hour

9.000

366.00

3294.00

P&M-055

Motor grader for grading

hour

6.000

2247.00

13482.00

P&M-032

Water tanker 6 KL capacity

hour

4.000

233.00

932.00

P&M-060

Vibratory roller 8-10 tonne @ 80 cum/hour

hour

7.500

1446.00

10845.00

P&M-059

KL

24.000

13.00

Machinery

Material
Cost of water

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

M-189

3308.44

Cost for 600 cum = a+b+c+d+e

36392.88

Rate per cum = (a+b+c+d+e)/600

60.65
say

3.19

312.00
3007.68

61.00

Case-II :Compacting original ground supporting embankment


Loosening, leveling and Compacting original ground
supporting embankment to facilitate placement of first layer
of embankment, scarified to a depth of 150 mm, mixed with
water at OMC and then compacted by rolling so as to
achieve minimum dry density as given in Table 300-2 for
embankment construction.
Unit = cum
Taking output = 600 cum
a)

b)

c)

Labour
Mate

day

0.080

673.00

53.84

L-12

Mazdoor

day

2.000

377.00

754.00

L-13

Tractor with ripper attachment

hour

6.000

366.00

2196.00

P&M-055

Vibratory road roller 8-10 tonne capacity

hour

7.500

1446.00

10845.00

P&M-059

Water tanker6 KL capacity

hour

4.000

233.00

932.00

P&M-060

KL

24.000

13.00

312.00

M-189

Machinery

Material
Cost of water

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

1509.28
1660.21

Cost for 600 cum = (a+b+c+d+e)

18262.34

Rate per sqm = (a+b+c+d+e)/600

30.44
say

3.20

305

Stripping and Storing Top Soil

Page 11 of 394

30.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Stripping, storing of top soil by road side at 15 m internal and


re-application on embankment slopes, cut slopes and other
areas in localities where the available embankment material
is not conducive to plant growth.
Unit = cum
Taking output = 10 cum
a)

b)

Labour
Mate

day

0.200

673.00

134.60

L-12

Mazdoor

day

5.000

377.00

1885.00

L-13

hour

0.100

3490.00

349.00

P&M-014

Machinery
Dozer 80 HP @ 100 cum per hour

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

236.86
260.55

Cost for 10 cum = (a+b+c+d)

2866.01

Rate per cum = (a+b+c+d)/10


3.21

286.60
say

287.00

Stripping, Storing and Re-laying Top Soil from Borrow


Areas in Agriculture Fields.
Stripping of top soil from borrow areas located in agriculture
fields, storing at a suitable place, spreading and re-laying
after taking the borrow earth to maintain fertility of the
agricultural field, finishing it to the required levels and
satisfaction of the farmer.
Unit = cum
Taking output = 300 cum
a)

b)

Labour
Mate

day

0.080

673.00

53.84

L-12

Mazdoor

day

2.000

377.00

754.00

L-13

hour

6.000

3490.00

20940.00

Machinery
Dozer, 80 HP

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

2392.26

Cost for 300 cum = (a+b+c+d)

26314.89

Rate per cum = (a+b+c+d)/300

87.72
say

3.22

307

P&M-014

2174.78

88.00

Turfing with Sods


Furnishing and laying of the live sods of perennial turf
forming grass on embankment slope, verges or other
locations shown on the drawing or as directed by the
engineer including preparation of ground, fetching of sods
and watering.
Unit = sqm
Taking output = 100 sqm
a)

b)

c)

Labour
Mate

day

0.120

673.00

80.76

L-12

Mazdoor for preparation of ground and fetching of sods

day

3.000

377.00

1131.00

L-13

Water tanker including watering for 3 months

hour

2.000

233.00

466.00

P&M-060

Tractor-trolley

hour

1.000

340.00

340.00

P&M-053

cum

0.180 Not in SOR

#VALUE!

M-167

156.00

M-189

Machinery

Material
Farm yard manure @ 0.18 cum per 100 sqm at site of
work
Cost of water

KL

12.000

13.00

d)

Overhead charges @ 0.1 on (a+b+c)

#VALUE!

e)

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!

Cost for 100 sqm = a+b+c+d+e

#VALUE!

Rate per 100 sqm = (a+b+c+d+e)/100

#VALUE!
say

3.23

308

Seeding and Mulching


Page 12 of 394

#VALUE!

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Preparation of seed bed on previously laid top soil,


furnishing and placing of seeds, fertilizer, mulching material,
applying bituminous emulsion at the rate of 0.23 litres per
sqm and laying and fixing jute netting, including watering for
3 months all as per clause 308.
Unit = sqm
Taking output = 240 sqm
a)

b)

Labour
Mate

day

0.400

673.00

269.20

L-12

Mazdoor

day

10.000

377.00

3770.00

L-13

hour

14.000

233.00

3262.00

P&M-060

hour

2.400

340.00

816.00

P&M-053

3.600 Not in SOR

#VALUE!

M-162

0.430 Not in SOR

#VALUE!

M-167

1930.62

M-077

#VALUE!

M-121

1092.00

M-189

Machinery
Water tanker 6 KL capacity including watering for 3
months
Tractor-trolley

c)

Material
Seeds

kg

Sludge/Farm yard manure @ 0.18 cum per 100 sqm

cum

Bitumen Emulsion

litre

Jute netting, open weave, 2.5 cm square opening

sqm

Cost of water for 3 months

KL

55.200

34.98

264.000 Not in SOR


84.000

13.00

d)

Overhead charges @ 0.1 on (a+b+c)

#VALUE!

e)

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!

Cost for 240 sqm = a+b+c+d+e

#VALUE!

Rate per sqm = (a+b+c+d+e)/240

#VALUE!
say

3.24

309

#VALUE!

Surface Drains in Soil


Construction of unlined surface drains of average cross
sectional area 0.40 sqm in soil to specified lines, grades,
levels and dimensions to the requirement of clause 301 and
309. Excavated material to be used in embankment within a
lead of 50 metres (average lead 25 metres)
Unit = metre
Taking output = 10 metres
A

Mechanical means
a)

Labour
Mate

day

0.010

673.00

6.73

L-12

Mazdoor for dressing of bed and side of drain

day

0.250

377.00

94.25

L-13

hour

0.330

1222.00

403.26

P&M-026

b)

Machinery

c)

Hydraulic Excavator 0.3 cum bucket capacity @ 30


metres per hour
Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

50.42
55.47

Cost for 10 metres = a+b+c+d

610.13

Rate per metre = (a+b+c+d)/10

61.01
say

3.24

a)

Labour
Mate

day

0.080

673.00

53.84

L-12

Mazdoor

day

2.000

377.00

754.00

L-13

b)

Overhead charges @ 0.1 on (a)

80.78

c)

Contractor's profit @ 0.1 on (a+b)

88.86

Cost for 10 metres = a+b+c

977.49

Rate per metre = (a+b+c)/10

97.75
say

Note

3.25

309

61.00

Manual Means

Where lining of drain is provided, quantity shall be worked


out based on approved design and drawing and priced on
rate of cement concrete of approved grade or stone/brick
masonry as the case may be.
Surface Drains in Ordinary Rock

Page 13 of 394

98.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Construction of unlined surface drain of average cross


sectional area 0.4 sqm in ordinary rock to specified lines,
grades, levels and dimensions as per approved design and
to the requirement of clause 301 to 309. Excavated material
to be used in embankment at site.
Unit = metre
Taking output = 10 metres
A

Mechanical Means
a)

Labour
Mate

day

0.020

673.00

13.46

L-12

Mazdoor for dressing of bed and side of drain

day

0.500

377.00

188.50

L-13

hour

0.670

1222.00

818.74

P&M-026

b)

Machinery

c)

Hydraulic Excavator 0.3 cum bucket capacity @ 15


metres per hour
Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

102.07
112.28

Cost for 10 metres = a+b+c+d

1235.05

Rate per metre = (a+b+c+d)/10

123.50
say

3.25

a)

Labour
Mate

day

0.120

673.00

80.76

L-12

Mazdoor

day

3.000

377.00

1131.00

L-13

b)

Overhead charges @ 0.1 on (a)

121.18

c)

Contractor's profit @ 0.1 on (a+b)

133.29

Cost for 10 metres = a+b+c

1466.23

Rate per metre = (a+b+c)/10

146.62
say

3.26

3.27

124.00

Manual Means

309

Surface Drains in Hard Rock

309

Rate per metre may be worked out based on quantity of


hard rock as per design.
For rate of hard rock cutting, refer relevant item in this
chapter
Sub-Surface Drains with Perforated Pipe

147.00

Construction of subsurface drain with perforated pipe of 100


mm internal diameter of metal/ asbestos cement/ cement
concrete/PVC, closely jointed, perforations ranging from 3
mm to 6 mm depending upon size of material surrounding
the pipe, with 150 mm bedding below the pipe and 300 mm
cushion above the pipe, cross section of excavation 450 x
550 mm. Excavated material to be utilised in roadway at site.
Unit = metre
Taking output = 10 metres
a)

c)

Labour
Mate

day

0.040

673.00

26.92

L-12

Mazdoor for excavation and back filling

day

2.000

377.00

754.00

L-13

metre

10.000

54.00

540.00

M-135

cum

2.400

725.00

1740.00

M-012

Material
Perforated pipe of cement concrete, internal dia 100
mm
Crushed stone as per table 300-3

d)

Overhead charges @ 0.1 on (a+b+c)

306.09

e)

Contractor's profit @ 0.1 on (a+b+c+d)

336.70

Cost for 10 metres = a+b+c+d+e

3703.71

Rate per metre = (a+b+c+d+e)/10

370.37
say

Note
3.28

309

Type of pipe may be modified depending upon provision in


design.
Aggregate Sub-Surface Drains

Page 14 of 394

370.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Construction of aggregate sub surface drain 300 mm x 450


mm with aggregates conforming to table 300-4, excavated
material to be utilised in roadway.
Unit = metre
Taking output = 10 metres
a)

Labour
Mate

day

0.020

673.00

13.46

L-12

day

1.500

377.00

565.50

L-13

b)

Mazdoor for excavation and back filling with


aggregates
Material
Crushed stone as per table 300-3

cum

1.350

725.00

978.75

M-012

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

155.77
171.35

Cost for 10 metres = a+b+c+d

1884.83

Rate per metre = (a+b+c+d)/10

188.48
say

3.29

309

188.00

Underground Drain at Edge of Pavement


Construction of an underground drain 1 m x 1 m (inside
dimensions) lined with RCC-20 cm thick and covered with
RCC slab10 cm in thickness on urban roads.
Unit = Running metre
Taking output = one metre
a) Earthwork in soil

cum

1.500

43.00

b) RCC work M-20

cum

0.495

4853.00

Rate per metre = (a+b)


3.30

310

Rates for these items may be taken from chapters on earth


work and substructures respectively.
Preparation and Surface Treatment of Formation.

say

Item No.
3.13
2402.24 Item 12.8
(C) RCC
2466.74
64.50

2467.00

Preparation and surface treatment of formation by removing


mud and slurry, watering to the extent needed to maintain
the desired moisture content, trimming to the required line,
grade, profile and rolling with 8-10 tonne smooth wheeled
roller, complete as per clause 310.
Unit = sqm
Taking output = 3500sqm
a)

b)

c)

Labour
Mate

day

0.280

673.00

188.44

L-12

Mazdoor

day

6.000

377.00

2262.00

L-13

Mazdoor skilled

day

1.000

408.00

408.00

L-15

Smooth 3 wheeled steel roller 8-10 tonnes

hour

3.000

432.00

1296.00

P&M-044

Water tanker 6 KL, one trip per hour

hour

3.000

233.00

699.00

P&M-060

KL

18.000

13.00

234.00

M-189

Machinery

Material
Cost of water

d)

Overhead charges @ 0.1 on (a+b+c)

508.74

e)

Contractor's profit @ 0.1 on (a+b+c+d)

559.62

Cost for 3500 sqm = a+b+c+d+e

6155.80

Rate per sqm = (a+b+c+d+e)/3500

1.76
say

3.31

313

Construction of Rock fill Embankment


Construction of rock fill embankment with broken hard rock
fragments of size not exceeding 300 mm laid in layers not
exceeding 500 mm thick including filling of surface voids with
stone spalls, blinding top layer with granular material, rolled
with vibratory road roller, all complete as per clause 313.
Unit = cum
Taking output = 100 cum
a)

Labour
Page 15 of 394

2.00

Sr No

Ref. to
MoRTH
Spec.

Description

b)

c)

Unit

Quantity

Rate Rs

Cost Rs

Mate

day

0.040

673.00

26.92

L-12

Mazdoor

day

1.500

377.00

565.50

L-13

Dozer 80 HP for spreading @ 200 cum per hour

hour

0.500

3490.00

1745.00

P&M-014

Vibratory road roller 8-10 tonnes @ 100 cum per hour

hour

1.000

1446.00

1446.00

P&M-059

Water tanker 6 KL, one trip per hour

hour

2.000

233.00

466.00

P&M-060

KL

12.000

13.00

156.00

M-189

Machinery

Material
Cost of water

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

440.54
484.60

Cost for 100 cum = a+b+c+d+e

5330.56

Rate per cum = (a+b+c+d+e)/100

53.31
say

Note

Remarks/
Input ref.

53.00

It is assumed that rock is available locally at site from


roadway cutting. In case, portion of the rock requires
breaking to acceptable size of 300 mm, breaking charges
will have to be added.
EARTH WORK ON HILL ROAD

3.32

301

Excavation in Hill Area in Soil by Mechanical Means


Excavation in soil in hilly area by mechanical means
including cutting and trimming of side slopes and disposing
of excavated earth with all lifts and lead upto 1000 metres.
Unit = cum
Taking output = 260 cum
a)

Labour
Mate

day

0.240

673.00

161.52

L-12

day

6.000

377.00

2262.00

L-13

b)

Mazdoor for trimming slopes and helping in excavation


etc.
Machinery
Dozer 80 HP (D-80 A 12)@ 43.28 cum per hour

hour

6.000

3490.00

20940.00

P&M-014

Front end loader

hour

6.000

756.00

4536.00

P&M-017

Tipper 5.5cum capacity, 4 trips per hour.

hour

12.000

291.00

3492.00

P&M-048

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

3139.15
3453.07

Cost for 260 cum = a+b+c+d

37983.74

Rate per cum = (a+b+c+d)/260

146.09
say

Note

3.33

301

146.00

In case the land on the valley side is barren and there is no


objection for disposing of excavated earth on the valley side,
the provision of front end loader and tipper shall be deleted
as excavated earth shall be disposed off on the valley side.
Excavation in Hilly Area in Ordinary Rock by Mechanical
Means not Requiring Blasting.
Excavation in hilly area in ordinary rock not requiring blasting
by mechanical means including cutting and trimming of
slopes and disposal of cut material with all lift and lead upto
1000 metres.
Unit = cum
Taking output = 170 cum
a)

b)

Labour
Mate

day

0.320

673.00

215.36

L-12

Mazdoor

day

8.000

377.00

3016.00

L-13

Dozer 80 HP (D-80 A 12)@ 28.32 cum per hour

hour

6.000

3490.00

20940.00

P&M-014

Front end loader

hour

7.000

756.00

5292.00

P&M-017

Tipper 5.5cum capacity, 4 trips per hour.

hour

7.000

291.00

2037.00

P&M-048

Machinery

c)

Overhead charges @ 0.1 on (a+b)

3150.04

d)

Contractor's profit @ 0.1 on (a+b+c)

3465.04

Page 16 of 394

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Cost for 170 cum = a+b+c+d

38115.44

Rate per cum = (a+b+c+d)/170

224.21
say

Note

3.34

Remarks/
Input ref.

224.00

In case the land on the valley side is barren and there is no


objection for disposing of excavated earth on the valley side,
the provision of front end loader and tipper shall be deleted
as excavated earth can be disposed off on the valley side.
Excavation in Hilly Areas in Hard Rock Requiring
Blasting
Excavation in hilly areas in hard rock requiring blasting, by
mechanical means including trimming of slopes and disposal
of cut material with all lifts and lead upto 1000 metres.

301

Unit = cum
Taking output = 170 cum
a)

b)

Labour
Mate

day

0.490

673.00

329.77

L-12

Mazdoor

day

10.000

377.00

3770.00

L-13

Driller

day

2.000

400.00

800.00

L-06

Blaster

day

0.250

396.00

99.00

L-03

Machinery
Dozer 80 HP (D-80 A 12)@ 28.32 cum per hour

hour

6.000

3490.00

20940.00

P&M-014

Air compressor 250 cfm with two jack hammer @ 20


cum per hour
Front end loader

hour

5.000

300.00

1500.00

P&M-001

hour

7.000

756.00

5292.00

P&M-017

Tipper 5.5cum capacity, 4 trips per hour.

hour

7.000

291.00

2037.00

P&M-048

kg

35.000

74.08

2592.80

M-104

each

140.000

11.00

1540.00 M-094 /100

c)

Materials

d)

Electric Detonators @ 1 Detonator for 2 Gelatine sticks


of 125 gms each
Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

Gelatine 80 per cent

3890.06
4279.06

Cost for 170 cum = a+b+c+d+e

47069.69

Rate per cum = (a+b+c+d+e)/170

276.88
say

Note

In case the land on the valley side is barren and there is no


objection for disposing of excavated earth on the valley side,
the provision of front end loader and tipper shall be deleted
as excavated earth can be disposed off on the valley side.
In case of hill roads, the altitude effect comes into play. The
output of men and machines decreases progressively after
2100 m elevation leading to increase in cost . High altitude
effect has been explained in the basic approach.

3.35

Work in Urban Roads


The cost of earth work in urban roads inhabited area will be
comparatively higher due to following reasons:
a) There is mixed traffic on urban roads like slow moving
hand and animal driven carts, rickshaws, cycles, two/ three
wheeler apart from the usual vehicular traffic resulting into
traffic jams. This causes loss of working time which may be
in the range of 10 -15 per cent
b)
There is considerable disruption of traffic adversely
affecting the efficiency of the working parties including
machines due to congestion caused by pedestrian traffic,
local road side venders, parking of vehicles by the road side,
encroachments by the shopkeepers and local shops who
make use of the berms of the road in front of these shops
and unauthorised conversion of road berms into mini local
market The output of manpower and machines is
substantially reduced due to factors mentioned above.
c)
Cost of living in urban areas is comparatively more
resulting into higher wages.
Page 17 of 394

277.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

d)
At times, work is executed during night time due to
heavy traffic during day time. This involves extra expenditure
by way of making arrangement for lighting and special
transport for working parties due to odd hour
In the light of above, the authorities engaged in preparing
the cost estimates may exercise their judgment and cater for
the additional cost to the extent of 2 to 3 per cent, keeping in
view the severity of factors mentioned above. Supporting
details for the extra cost based on the actual conditions in
specific cases will have to give in justification.
3.36

Suggest
ive

Embankment Construction with Flyash/Pond ash


available from coal or lignite burning Thermal Plants as
waste material.
Construction of embankment with Flyash conforming to table
1 of IRC: SP: 58 - 2001 obtained from coal or lignite burning
thermal power stations as waste material, spread and
compacted in layer of 200mm thickness each at OMC, all as
specified in IRC: SP: 58-2001 and as per approved plans.
Unit = cum
Taking output = 360 cum
a)

b)

Labour
Mate

day

0.160

673.00

107.68

L-12

Mazdoor

day

4.000

377.00

1508.00

L-13

hour

6.000

1222.00

7332.00

P&M-026

tonne.km

432 x L

2.00

864.00

Lead =1
km & P&M058

Machinery
Hydraulic Excavator 0.9 cum bucket capacity @ 60
cum/hour
Tipper 10Tcapacity flyash 360 x 1.2 = 432 tonnes

Add 10 per cent of cost of carriagefor loading and


unloading
Dozer 80 HP for spreading @ 200 cum/hour

hour

1.800

3490.00

6282.00

P&M-014

Motor Grader for grading @ 100 cum/hour

hour

3.600

2247.00

8089.20

P&M-032

Water tanker6 KL capacity

hour

12.000

233.00

2796.00

P&M-060

Vibratory Roller 8-10 tonne @ 100 cum/hour

hour

3.600

1446.00

5205.60

P&M-059

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

86.40

3227.09
3549.80

Cost for 360 cum = a+b+c+d

39047.76

Rate per cum = (a+b+c+d)/360

108.47
say

Note

1.As flyash is available free of cost as waste material from


Thermal Plants, cost of material has not been added.
2.The earth cover on sides and intermediate layers of earth
sandwiching the flyash have not been included in this
analysis. The same are required to be provided as per
approved design and priced separately as embankment
construction.

Page 18 of 394

108.00

CHAPTER - 4
SUB-BASES, BASES ( NON- BITUMINOUS) AND SHOULDERS
Sr No

Ref. to
MoRTH
Spec.

4.1

401

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Granular Sub-Base with Close Graded Material (Table:400-1)


Plant Mix Method
Construction of granular sub-base by providing close graded
Material, mixing in a mechanical mix plant at OMC, carriage of
mixed Material to work site, spreading in uniform layers with
motor grader on prepared surface and compacting with
vibratory power roller to achieve the desired density, complete
as per clause 401
Unit = cum
Taking output = 225 cum (450 tonne)
a) Labour
Mate
Mazdoor skilled
Mazdoor
b) Machinery
Wet mix plant @ 75 tonne capacity per hour
Electric generator 125 KVA
Water tanker 6 KL capacity 5 km lead with one trip per
hour
Front end loader 1 cum bucket capacity
Tipper 10 tonne

Add 10 per cent of cost of carriage to cover loading and


unloading
Motor Grader 110 HP
Vibratory roller 8-10 t
c) Material
Close graded Granular sub-base Material as per table 400-1

4.1A

4.1A

4.1A

(i)

(ii)

(iii)

For Grading-I Material


53 mm to 9.5 mm @ 50 per cent
9.5 mm to 2.36 mm @ 20 per cent
2.36 mm below @ 30 per cent
Cost of water
OR
For Grading-II Material
26.5 mm to 9.5 mm @ 35 per cent
9.5 mm to 2.36 mm @ 25 per cent
2.36 mm below @ 40 per cent
Cost of water
OR
For Grading-III Material
9.5 mm to 4.75 mm @ 35 per cent
4.75 mm to 2.36 mm @ 12.5 per cent
2.36 mm below @ 52.5 per cent
Cost of water
Rate per cum for grading-I Material
d) Overhead charges @ 0.1 on (a+b+c)
e) Contractor's profit @ 0.1 on (a+b+c+d)
Cost for 225 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/225

day
day
day

0.400
2.000
8.000

673.00
408.00
377.00

269.20
816.00
3016.00

L-12
L-15
L-13

hour
hour
hour

6.000
6.000
4.500

1130.00
654.00
233.00

6780.00
3924.00
1048.50

P&M-093
P&M-018
P&M-060

hour
tonne.km

6.000
450 x L

756.00
2.00

4536.00
900.00

P&M-017
Lead =1
km & P&M058

90.00
hour
hour

6.000
6.000

2247.00
1446.00

13482.00
8676.00

P&M-032
P&M-059

cum
cum
cum
KL

144.000
57.000
86.400
27.000

655.20
692.60
137.00
13.00

94348.80
39478.20
11836.80
351.00

M-013
M-017
M-020
M-189

cum
cum
cum
KL

100.800
72.000
115.200
27.000

923.00
692.60
137.00
13.00

93038.40
49867.20
15782.40
351.00

M-015
M-017
M-020
M-189

cum
cum
cum
KL

100.800
36.000
151.200
27.000

692.60
137.00
137.00
13.00

69814.08
4932.00
20714.40
351.00

M-016
M-018
M-020
M-189

say

18955.25
20850.78
229358.53
1019.37
1019.00

say

20257.67
22283.44
245117.81
1089.41
1089.00

say

13934.92
15328.41
168612.51
749.39
749.00

Rate per cum for grading-II Material


d) Overhead charges @ 0.1 on (a+b+c)
e) Contractor's profit @ 0.1 on (a+b+c+d)
Cost for 225 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/225
Rate per cum for grading-III Material
d) Overhead charges @ 0.1 on (a+b+c)
e) Contractor's profit @ 0.1 on (a+b+c+d)
Cost for 225 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/225

Page 1 of 394

Sr No

Ref. to
MoRTH
Spec.

Description
Note

4.1

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Any one of the grading for material may be adopted as per


design
By Mix in Place Method
Construction of granular sub-base by providing close graded
material, spreading in uniform layers with motor grader on
prepared surface, mixing by mix in place method with rotavator
at OMC, and compacting with vibratory roller to achieve the
desired density, complete as per clause 401
Unit = cum
Taking output = 300 cum
a)

b)

c)

Labour
Mate

day

0.480

673.00

323.04

L-12

Mazdoor skilled

day

2.000

408.00

816.00

L-15

Mazdoor unskilled

day

10.000

377.00

3770.00

L-13

Motor Grader 110 HP @ 50 cum

hour

6.000

2247.00

13482.00

P&M-032

Vibratory roller 8 -10 tonne

hour

6.000

1446.00

8676.00

P&M-059

Tractor - Rotavator

hour

12.000

356.00

4272.00

P&M-054

Water tanker 6 KL capacity

hour

3.000

233.00

699.00

P&M-060

53 mm to 9.5 mm @ 50 per cent

cum

192.000

655.20

125798.40

M-013

9.5 mm to 2.36 mm @ 20 per cent

cum

76.000

692.60

52637.60

M-017

2.36 mm below @ 30 per cent

cum

115.200

137.00

15782.40

M-020

KL

18.000

13.00

234.00

M-189

26.5 mm to 9.5 mm @ 35 per cent

cum

134.400

923.00

124051.20

M-015

9.5 mm to 2.36 mm @ 25 per cent

cum

96.000

692.60

66489.60

M-017

2.36 mm below @ 40 per cent

cum

153.600

137.00

21043.20

M-020

KL

18.000

13.00

234.00

M-189

9.5 mm to 4.75 mm @ 35 per cent

cum

134.400

692.60

93085.44

M-016

4.75 mm to 2.36 mm @ 12.5 per cent

cum

48.000

137.00

6576.00

M-018

2.36 mm below @ 52.5 per cent

cum

201.600

137.00

27619.20

M-020

KL

18.000

13.00

234.00

M-189

Machinery

Material

Close graded Granular sub-base Material as per table 400-1


For Grading-I Material

Cost of water
OR
For Grading-II Material

Cost of water
OR
For Grading-III Material

Cost of water
4.1B

(i)

Rate per cum for grading-I Material


d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

22649.04
24913.95

Cost for 300 cum = a+b+c+d+e

274053.43

Rate per cum = (a+b+c+d+e)/300

913.51
say

4.1B

(ii)

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

24385.60
26824.16

Cost for 300 cum = a+b+c+d+e

295065.81

Rate per cum = (a+b+c+d+e)/300

983.55
say

4.1B

(iii)

984.00

Rate per cum for grading-III Material


d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

15955.27
17550.79

Cost for 300 cum = a+b+c+d+e

193058.74

Rate per cum = (a+b+c+d+e)/300

643.53
say

Note

914.00

Rate per cum for grading-II Material

Any one of the grading for material may be adopted as per


design
Page 2 of 394

644.00

Sr No

Ref. to
MoRTH
Spec.

4.2

401

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Granular Sub-Base with Coarse Graded Material (Table:400- 2)


Construction of granular sub-base by providing coarse graded
material, spreading in uniform layers with motor grader on
prepared surface, mixing by mix in place method with rotavator
at OMC, and compacting with vibratory roller to achieve the
desired density, complete as per clause 401.
Unit = cum
Taking output = 300 cum
a)

b)

c)

Labour
Mate

day

0.400

673.00

269.20

L-12

Mazdoor skilled

day

2.000

408.00

816.00

L-15

Mazdoor

day

8.000

377.00

3016.00

L-13

Mortar Grader 110 HP @ 50 cum per hour

hour

6.000

2247.00

13482.00

P&M-032

Vibratory roller 8 -10 tonne

hour

6.000

1446.00

8676.00

P&M-059

Water tanker 6 KL capacity

hour

3.000

233.00

699.00

P&M-060

53 mm to 26.5 mm @ 35 per cent

cum

134.400

713.00

95827.20

M-029

26.5 mm to 4.75 mm @ 45 per cent

cum

172.800

511.40

88369.92

M-026

2.36 mm below @ 20 per cent (Coarse Sand)

cum

76.800

137.00

10521.60

M-022

KL

18.000

13.00

234.00

M-189

26.5 mm to 4.75 mm @ 75 per cent

cum

288.000

511.40

147283.20

M-026

2.36 mm below @ 25 per cent

cum

96.000

137.00

13152.00

M-022

KL

18.000

13.00

234.00

M-189

9.5 mm to 4.75 mm @ 66 per cent

cum

255.000

137.00

34935.00

M-025

2.36 mm below @ 34 per cent

cum

129.000

137.00

17673.00

M-022

KL

18.000

13.00

234.00

M-189

Machinery

Material

For coarse graded Granular sub-base Materials per table 4002


For grading-I Material

Cost of water
OR
For Grading-II Material

Cost of water
OR
For Grading-III Material

Cost of water
4.2

(i)

Rate per cum for grading-I Material


d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

22191.09
24410.20

Cost for 300 cum = a+b+c+d+e

268512.21

Rate per cum = (a+b+c+d+e)/300

895.04
say

4.2

(ii)

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

18762.74
20639.01

Cost for 300 cum = a+b+c+d+e

227029.15

Rate per cum = (a+b+c+d+e)/300

756.76
say

4.2

(iii)

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

7980.02
8778.02
96558.24

Rate per cum = (a+b+c+d+e)/300

321.86
say

4.3

402

757.00

Rate per cum for grading-III Material

Cost for 300 cum = a+b+c+d+e

Note

895.00

Rate per cum for grading-II Material

Any one of the grading for material may be adopted as per


design
Lime Stabilisation for Improving Sub-grade

Page 3 of 394

322.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Laying and spreading available soil in the sub-grade on a


prepared surface, pulverising, mixing the spread soil in place
with rotavator with 3 per cent slaked lime having minimum
content of 70 per cent of CaO, grading with motor grader and
compacting with the road roller at OMC to the desired density
to form a layer of improved sub grade
Unit = cum
Taking output = 300 cum (525 tonne)
A

By Mechanical Means
a)

b)

c)

Labour
Mate

day

0.360

673.00

242.28

L-12

Skilled mazdoor for alignment and geometrics

day

1.000

408.00

408.00

L-15

Mazdoor for spraying lime

day

8.000

377.00

3016.00

L-13

Tractor with ripper and rotavator attachments @ 60 cum


per hour for ripping and 25 cum per hour for mixing

hour

12.000

366.00

4392.00

P&M-055

Motor Grader 110 HP @ 50 cum per hour

hour

6.000

2247.00

13482.00

P&M-032

Vibratory roller 8 - 10 tonne capacity

hour

6.00x0.65*

1446.00

5639.40

P&M-059

Water tanker 6 KL capacity

hour

12.000

233.00

2796.00

P&M-060

tonne

15.750

3200.00

50400.00

M-188

KL

72.000

13.00

936.00

M-189

Machinery

Material
Lime at site
Cost of water

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

8131.17
8944.28

Cost for 300 cum= a+b+c+d+e

98387.13

Rate per cum =( a+b+c+d+e)/300


Note

4.3

327.96
say

328.00

* Though vibratory roller is required only for 3 hours as per


norms, but the same has to be available at site for 6 hours as
other machines for spreading and mixing will take 6 hours. The
usage rates of roller have been multiplied with a factor of 0.65.
By Manual Means
Unit = cum
Taking output = 150 cum (263 tonnes)
a)

b)

c)

Labour
Mate

day

1.440

673.00

969.12

L-12

Mazdoor skilled

day

1.000

408.00

408.00

L-15

Mazdoor

day

35.000

377.00

13195.00

L-13

Vibratory roller 8 - 10 tonne @ 60 cum per hour

hour

2.500

1446.00

3615.00

P&M-059

Water tanker 6 KL capacity

hour

6.000

233.00

1398.00

P&M-060

tonne

8.000

3200.00

25600.00

M-188

KL

36.000

13.00

468.00

M-189

Machinery

Material
Lime at site
Cost of water

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

4565.31
5021.84

Cost for 150 cum= a+b+c+d+e

55240.28

Rate per cum =( a+b+c+d+e)/150

368.27
say

4.4

402

Lime Treated Soil for Sub- Base


Providing, laying and spreading soil on a prepared sub grade,
pulverising, mixing the spread soil in place with rotavator with
3 per cent slaked lime with minimum content of 70 per cent
of CaO, grading with motor grader and compacting with the
road roller at OMC to achieve at least 98 per cent of the max
dry density to form a layer of sub base.
Unit = cum
Page 4 of 394

368.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Taking output = 300 cum (525 tonnes)


a)

b)

Labour
Mate

day

0.480

673.00

323.04

L-12

Mazdoor skilled

day

2.000

408.00

816.00

L-15

Mazdoor

day

10.000

377.00

3770.00

L-13

hour

6.000

1222.00

7332.00

P&M-026

tonne.km

525 x L

2.00

1050.00

Lead =1
km & P&M058

Machinery
Excavator 0.90 cum bucket capacity
Tipper for carriage of soil

c)

Add 10 per cent of cost of carriage to cover cost of


loading and unloading
Motor Grader 110 HP @ 50 cum per hour

105.00
hour

6.000

2247.00

13482.00

P&M-032

Vibratory roller 8 - 10 tonne

hour

6.000

1446.00

8676.00

P&M-059

Tractor with Rotavator and blade @ 25 cum per hour

hour

12.000

356.00

4272.00

P&M-054

Water tanker 6 KL capacity

hour

12.000

233.00

2796.00

P&M-060

tonne

15.750

3200.00

50400.00

M-188

KL

72.000

13.00

936.00

M-189

Material
Lime at site
Cost of water

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

9395.80
10335.38

Cost for 300 cum = a+b+c+d+e

113689.23

Rate per cum= (a+b+c+d+e)/300


4.5

403

378.96
say

379.00

Cement Treated Soil Sub Base/ Base


Providing, laying and spreading soil on a prepared sub grade,
pulverising, adding the designed quantity of cement to the
spread soil, mixing in place with rotavator, grading with the
motor grader and compacting with the road roller at OMC to
achieve the desired unconfined compressive strength and to
form a layer of sub-base/base.
Unit = cum
Taking output = 300 cum (525 tonnes)
For 4 per cent quantity of cement by weight of soil
a)

b)

Labour
Mate

day

0.480

673.00

323.04

L-12

Mazdoor skilled

day

2.000

408.00

816.00

L-15

Mazdoor

day

10.000

377.00

3770.00

L-13

hour

6.000

1222.00

7332.00

P&M-026

tonne.km

525 x L

2.00

1050.00

Lead =1
km & P&M058

Machinery
Excavator 0.90 cum bucket capacity
Tipper for carriage of soil

c)

Add 10 per cent of cost of carriage to cover cost of


loading and unloading
Motor Grader 110 HP @ 50 cum per hour

105.00
hour

6.000

2247.00

13482.00

P&M-032

Vibratory roller 8 - 10 tonne

hour

6.000

1446.00

8676.00

P&M-059

Tractor with Rotavator and blade @ 25 cum per hour

hour

12.000

356.00

4272.00

P&M-054

Water tanker 6 KL capacity

hour

12.000

233.00

2796.00

P&M-060

tonne

21.000

5940.00

124740.00

M-081

KL

72.000

13.00

936.00

M-189

Material
Cement at site (@ 4 per cent of 525 tonne)
Cost of water

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

16829.80
18512.78

Cost for 300 cum = a+b+c+d+e

203640.63

Rate per cum= (a+b+c+d+e)/300

678.80
say

4.6

403

Cement Treated Crushed Rock or combination as per


clause 403.2 and table 400.4in Sub base/ Base

Page 5 of 394

679.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Providing, laying and spreading Material on a prepared sub


grade, adding the designed quantity of cement to the spread
Material, mixing in place with rotavator, grading with the motor
grader and compacting with the road roller at OMC to achieve
the desired unconfined compressive strength and to form a
layer of sub-base/base.
Unit = cum
Taking output = 300 cum (600 tonnes)
Quantity of cement assumed as 4 per cent of quantity of
crushed rock by weight.
a) Labour

b)

c)

Mate

day

0.480

673.00

323.04

L-12

Mazdoor skilled

day

2.000

408.00

816.00

L-15

Mazdoor

day

10.000

377.00

3770.00

L-13

Motor Grader 110 HP @ 50 cum per hour

hour

6.000

2247.00

13482.00

P&M-032

Vibratory roller 8 - 10 tonne

hour

6.000

1446.00

8676.00

P&M-059

Tractor with Rotavator and blade @ 25 cum per hour

hour

12.000

356.00

4272.00

P&M-054

Water tanker 6 KL capacity

hour

10.000

233.00

2330.00

P&M-060

tonne

24.000

5940.00

142560.00

M-081

37.5 mm to 9.5 mm @ 55 per cent

cum

211.200

923.00

194937.60

M-014

9.5 mm to 4.75 mm @ 20 per cent

cum

76.800

137.00

10521.60

M-025

4.75 mm to 75 micron @ 25 per cent

cum

96.000

137.00

13152.00

M-019

KL

60.000

13.00

780.00

M-189

37.5 mm to 9.5 mm @ 32.5 per cent

cum

124.800

713.00

88982.40

M-028

9.5 mm to 4.75 mm @ 5 per cent

cum

19.200

137.00

2630.40

M-025

4.75 mm to 75 micron @ 62.5 per cent

cum

240.000

137.00

32880.00

M-023

KL

60.000

13.00

780.00

M-189

Machinery

Material

Cement at site @ 4 per cent by weight of crushed


aggregate (600 tonne)
Grading of material for sub-base course

Cost of water
or
Grading of material for Base course

Cost of water
4.6

(i)

For Sub-Base course


d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

39562.02
43518.23

Cost for 300 cum = a+b+c+d+e

478700.49

Rate per cum = (a+b+c+d+e)/300

1595.67
say

4.6

(ii)

d)

Overhead charges @ 0.1 on (a+b+c)

30150.18

e)

Contractor's profit @ 0.1 on (a+b+c+d)

33165.20

Cost for 300 cum = a+b+c+d+e

364817.23

Rate per cum = (a+b+c+d+e)/300

1216.06
say

Note
4.7

404.3.1

1596.00

For Base course

1216.00

Quantities of aggregates provided under 'c' above are


uncompacted quantities.
Making 50 mm x 50 mm Furrows
Making 50 mm x 50 mm furrows, 25mm/ 50mm deep, 450 to
the center line of the road and at one metre interval in the
existing thin bituminous wearing coarse including sweeping
and disposal of excavated material within 1000 metres lead
Unit = sqm
Taking output = 30 m x 7 m = 210 sqm

(i)

25mm deep furrow cutting


a)

b)

Labour
Mate

day

0.080

673.00

53.84

L-12

Mazdoor

day

2.000

377.00

754.00

L-13

Machinery
Page 6 of 394

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Tractor-trolley

Quantity

hour

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

0.200

Rate Rs

Cost Rs

340.00

96.34
1059.77

Rate per sqm =(a+b+c+d)/210

1049.77
say

b)

Labour
Mate

day

0.160

673.00

107.68

L-12

Mazdoor

day

4.000

377.00

1508.00

L-13

hour

0.400

340.00

136.00

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

175.17

d)

Contractor's profit @ 0.1 on (a+b+c)

192.68

Cost for 210 sqm= a+b+c+d

2119.53

Rate per sqm =(a+b+c+d)/210


404.3.2

1050.00

50mm deep furrow cutting


a)

4.8

P&M-053

87.58

Cost for 210 sqm= a+b+c+d

(ii)

68.00

Remarks/
Input ref.

2109.53
say

2110.00

0.920

673.00

619.16

L-12

Inverted Choke
Construction of inverted choke by providing, laying, spreading
and compacting screening B type/ coarse sand of specified
grade in uniform layer on a prepared surface with motor grader
and compacting with power roller etc
Unit = cum
Taking output = 600 cum
a)

b)

c)

Labour
Mate

day

Mazdoor skilled

day

2.000

408.00

816.00

L-15

Mazdoor

day

21.000

377.00

7917.00

L-13

Motor Grader 110 HP

hour

6.000

2247.00

13482.00

P&M-032

Vibratory roller 8-10 tonnes @ 60 cum per hour

hour

6.000

1446.00

8676.00

P&M-059

Water tanker 6 KL capacity

hour

18.000

233.00

4194.00

P&M-060

cum

720.000

2400.00

1728000.00

M-004

KL

108.000

13.00

1404.00

M-189

Machinery

Material
Screening type 'B' or coarse sand
Cost of water

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

176510.82
194161.90

Cost for 600 cum = a+b+c+d+e

2135780.87

Rate per cum = ( a+b+c+d+e)/600


4.9

404

3559.63
say

3560.00

Water Bound Macadam


Providing, laying, spreading and compacting stone aggregates
of specific sizes to water bound macadam specification
including spreading in uniform thickness, hand packing, rolling
with 3 wheeled steel/ vibratory roller 8-10 tonnes in stages to
proper grade and camber, applying and brooming requisite
type of screening/ binding Materials to fill up the interstices of
coarse aggregate, watering and compacting to the required
density.
A

By Manual Means
Unit = cum
Taking output = 360 cum
a)

b)

Labour
Mate

day

10.080

673.00

6783.84

L-12

Mazdoor skilled

day

2.000

408.00

816.00

L-15

Mazdoor

day

250.000

377.00

94250.00

L-13

hour

6.000

1446.00

8676.00

P&M-059

Machinery
Vibratory roller 8 - 10 tonne @ 60cum per hour
Page 7 of 394

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

or

4.9A

(i)

Smooth 3 wheeled steel roller @ 30cum/hour

hour

12.000

Water tanker 6 KL capacity

hour

24.000

233.00

5592.00

cum

435.600

581.10

253127.16

cum

97.200

928.00

90201.60 M-052

cum

108.000

450.00

48600.00

M-007

cum

28.800

450.00

12960.00

M-007

KL

144.000

13.00

1872.00

M-189

P&M-060

c) Material ( Refer table 400 - 7, 8 & 9 )


Grading-I
Aggregate
Grading-I 90 mm to 45 mm@ 1.21cum per 10 sqm for
compacted thickness of 100 mm

M-039

Stone Screening
Type A 13.2 mm for grading-I @ 0.27 cum per 10 sqm
OR
Crushable type such as Moorum or Gravel for grading-I
@ 0.30 cum per 10 sqm
Binding material
Binding Material @ 0.08cum per 10 sqm for grading I
material
Cost of water
4.9A (i)

(a)

Using Scrining Crushable type such as Moorum or Gravel


d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

41971.70
46168.87

Cost for 360 cum = a+b+c+d+e

507857.57

Rate per cum = (a+b+c+d+e)/360

1410.72
say

1411.00

OR
4.9A (i)

(b)

Using Scrining Type-A (13.2mm agg.)


d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

47427.86
52170.65

Cost for 360 cum = a+b+c+d+e

573877.11

Rate per cum = (a+b+c+d+e)/360


4.9A

(ii)

1594.10
say

1594.00

261011.52

Grading-II
Aggregate
Grading-II 63 mm to 45 mm /Grading-III 53 mm to 22.4
mm@ 0.91 cum per 10 sqm for compacted thickness of
75 mm

cum

435.600

599.20

M-038

cum

57.600

928.00

53452.80 M-052

Crushable type such as Moorum or Gravel for grading II


&III @ 0.22 cum per 10 sqm
OR

cum

105.590

450.00

47515.50

Type B11.2 mm for grading-III @ 0.18 cum per 10 sqm

cum

86.400

1063.00

cum

28.800

450.00

12960.00

M-007

KL

144.000

13.00

1872.00

M-189

Stone Screening
Type A 13.2 mm for grading-II@ 0.12 cum per 10 sqm
OR
M-007

91843.20 M-051

Binding material
Binding Material @ 0.06cum per 10 sqm for grading II
material
Cost of water
4.9A
(ii)

(a)

Using Scrining Crushable type such as Moorum or Gravel


d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

42651.69
46916.85

Cost for 360 cum = a+b+c+d+e

516085.40

Rate per cum = (a+b+c+d+e)/360

1433.57
say

OR
Page 8 of 394

1434.00

Sr No
4.9A
(ii)

Ref. to
MoRTH
Spec.

Description
(b)

Unit

Quantity

Rate Rs

Cost Rs

Using Scrining Type-A (13.2mm agg.)


d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

44541.42
48995.56

Cost for 360 cum = a+b+c+d+e

538951.13

Rate per cum = (a+b+c+d+e)/360

1497.09
say

4.9A
(ii)

(c)

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

48380.46
53218.50
585403.52

Rate per cum = (a+b+c+d+e)/360


(iii)

1497.00

Using Scrining Type-B (11.2mm agg.)

Cost for 360 cum = a+b+c+d+e

4.9A

Remarks/
Input ref.

1626.12
say

1626.00

345648.60

Grading-III
Aggregate
Grading-III 53 mm to 22.4 mm@ 0.91 cum per 10 sqm
for compacted thickness of 75 mm

cum

435.600

793.50

M-036

cum

86.400

1063.00

cum

105.590

450.00

47515.50

M-007

cum

28.800

450.00

12960.00

M-007

KL

144.000

13.00

1872.00

M-189

Stone Screening
Type B 11.2 mm for grading-III @ 0.18 cum per 10 sqm

91843.20 M-051

OR
Crushable type such as Moorum or Gravel for grading II
&III @ 0.22 cum per 10 sqm
Binding material
Binding Material @ 0.06cum per 10 sqm for grading II
material
Cost of water
4.9A
(iii)

(a)

Using Scrining Crushable type such as Moorum or Gravel


d)

Overhead charges @ 0.1 on (a+b+c)

51115.39

e)

Contractor's profit @ 0.1 on (a+b+c+d)

56226.93

Cost for 360 cum = a+b+c+d+e

618496.27

Rate per cum = (a+b+c+d+e)/360

1718.05
say

1718.00

OR
4.9A
(iii)

(b)

Using Scrining Type-B (11.2mm agg.)


d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

56844.16
62528.58

Cost for 360 cum = a+b+c+d+e

687814.38

Rate per cum = (a+b+c+d+e)/360

4.9

1910.60
say

1911.00

( Anyone of the aggregate grading, screening and binding


material may be used as per design)
By Mechanical Means:
Unit = cum
Taking output = 360 cum
a)

b)

Labour
Mate

day

0.680

673.00

457.64

L-12

Mazdoor skilled

day

2.000

408.00

816.00

L-15

Mazdoor

day

15.000

377.00

5655.00

L-13

Motor grader 110 HP @ 50cum/hr. for spreading

hour

7.200

2247.00

16178.40

P&M-032

Vibratory roller 8-10 tonnes @ 60cum/hr.

hour

6.000

1446.00

8676.00

P&M-059

Smooth 3 wheeled steel roller @ 30cum/hr.

hour

12.000

Water tanker 6 KL capacity

hour

24.000

233.00

5592.00

P&M-060

Machinery

or

Page 9 of 394

Sr No

4.9B

Ref. to
MoRTH
Spec.

Description

(i)

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

c) Material ( Refer table 400 - 7, 8 & 9 )


Grading-I
Aggregate
Grading-I 90 mm to 45 mm@ 1.21cum per 10 sqm for
compacted thickness of 100 mm

cum

435.600

581.10

253127.16

M-039

cum

97.200

928.00

90201.60 M-052

cum

108.000

450.00

48600.00

M-007

cum

28.800

450.00

12960.00

M-007

KL

144.000

13.00

1872.00

M-189

Stone Screening
Type A 13.2 mm for grading-I @ 0.27 cum per 10 sqm
OR
Crushable type such as Moorum or Gravel for grading-I
@ 0.30 cum per 10 sqm
Binding material
Binding Material @ 0.08cum per 10 sqm for grading I
material
Cost of water
4.9B (i)

(a)

Using Scrining Crushable type such as Moorum or Gravel


d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

34097.42
37507.16

Cost for 360 cum = a+b+c+d+e

412578.78

Rate per cum = (a+b+c+d+e)/360

1146.05
say

1146.00

OR
4.9B (i)

(b)

Using Scrining Type-A (13.2mm agg.)


d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

39553.58
43508.94

Cost for 360 cum = a+b+c+d+e

478598.32

Rate per cum = (a+b+c+d+e)/360


4.9B

(ii)

1329.44
say

1329.00

261011.52

Grading-II
Aggregate
Grading-II 63 mm to 45 mm /Grading-III 53 mm to 22.4
mm@ 0.91 cum per 10 sqm for compacted thickness of
75 mm

cum

435.600

599.20

M-038

cum

57.600

928.00

53452.80 M-052

Crushable type such as Moorum or Gravel for grading II


&III @ 0.22 cum per 10 sqm
OR

cum

105.590

450.00

47515.50

Type B11.2 mm for grading-III @ 0.18 cum per 10 sqm

cum

86.400

1063.00

cum

28.800

450.00

12960.00

M-007

KL

144.000

13.00

1872.00

M-189

Stone Screening
Type A 13.2 mm for grading-II@ 0.12 cum per 10 sqm
OR
M-007

91843.20 M-051

Binding material
Binding Material @ 0.06cum per 10 sqm for grading II
material
Cost of water
4.9B
(ii)

(a)

Using Scrining Crushable type such as Moorum or Gravel


d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

34777.41
38255.15

Cost for 360 cum = a+b+c+d+e

420806.61

Rate per cum = (a+b+c+d+e)/360

1168.91
say

1169.00

OR
4.9B
(ii)

(b)

Using Scrining Type-A (13.2mm agg.)


d)

Overhead charges @ 0.1 on (a+b+c)


Page 10 of 394

36667.14

Sr No

Ref. to
MoRTH
Spec.

Description
e)

Unit

Quantity

Rate Rs

Cost Rs

Contractor's profit @ 0.1 on (a+b+c+d)

40333.85

Cost for 360 cum = a+b+c+d+e

443672.35

Rate per cum = (a+b+c+d+e)/360

1232.42
say

4.9B
(ii)

(c)

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

40506.18
44556.79
490124.73

Rate per cum = (a+b+c+d+e)/360


(iii)

1232.00

Using Scrining Type-B (11.2mm agg.)

Cost for 360 cum = a+b+c+d+e

4.9B

Remarks/
Input ref.

1361.46
say

1361.00

345648.60

Grading-III
Aggregate
Grading-III 53 mm to 22.4 mm@ 0.91 cum per 10 sqm
for compacted thickness of 75 mm

cum

435.600

793.50

M-036

cum

86.400

1063.00

cum

105.590

450.00

47515.50

M-007

cum

28.800

450.00

12960.00

M-007

KL

144.000

13.00

1872.00

M-189

Stone Screening
Type B11.2 mm for grading-III @ 0.18 cum per 10 sqm

91843.20 M-051

OR
Crushable type such as Moorum or Gravel for grading II
&III @ 0.22 cum per 10 sqm
Binding material
Binding Material @ 0.06cum per 10 sqm for grading II
material
Cost of water
4.9B
(iii)

(a)

Using Scrining Crushable type such as Moorum or Gravel


d)

Overhead charges @ 0.1 on (a+b+c)

43241.11

e)

Contractor's profit @ 0.1 on (a+b+c+d)

47565.23

Cost for 360 cum = a+b+c+d+e

523217.48

Rate per cum = (a+b+c+d+e)/360

1453.38
say

1453.00

OR
4.9B
(iii)

(b)

Using Scrining Type-B (11.2mm agg.)


d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

48969.88
53866.87

Cost for 360 cum = a+b+c+d+e

592535.60

Rate per cum = (a+b+c+d+e)/360


Note
4.10

405

1645.93
say

1646.00

As three wheeled smooth rollers are also very commonly


used, the same has been provided as an alternative.
Crushed Cement Concrete Sub-base / Base
Breaking and crushing of material obtained by breaking
damaged cement concrete slabs to size range not exceeding
75 mm as specified in table 400.7 transporting the aggregates
obtained from breaking of cement concrete slabs at a lead of L
km., laying and compacting the same as sub base/ base
course, constructed as WBM to clause 404 except the use of
screening or binding Material.
Unit = cum
Taking output =360 cum
a)

b)

Labour
Mate

day

4.160

673.00

2799.68

L-12

Mazdoor skilled

day

2.000

408.00

816.00

L-15

Mazdoor for crushing broken cement concrete


pavement/slabs into aggregate
Machinery

day

102.000

377.00

38454.00

L-13

hour

6.000

2247.00

13482.00

P&M-032

Motor Grader,110 HP @ 50 cum/hr.


Page 11 of 394

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Vibratory roller 8 - 10 tonne@ 60 cum per hour

Quantity

hour

6.000

Smooth 3 wheeled steel roller @ 30cum/hr.

hour

12.000

Front end loader 1 cum bucket capacity

hour
tonne.km

Rate Rs

Cost Rs

Remarks/
Input ref.

1446.00

8676.00

P&M-059

6.000

756.00

4536.00

P&M-017

720 x L

2.00

1440.00

Lead =1
km & P&M058

or

Tipper 10 tonne capacity

c)

Add 10 per cent of cost of carriage to cover cost of


loading and unloading
Water tanker 6 KL capacity with 5 km lead @ 1 trip per
hour
Material

144.00
hour

12.000

233.00

KL

72.000

13.00

2796.00

P&M-060

936.00

M-189

Material available from dismantled concrete slab after crushing


/ breaking and only carriage is required to be provided
Cost of water
d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

7407.97
8148.76

Cost for 360 cum = a+b+c+d+e

89636.41

Rate per cum = (a+b+c+d+e)/360


Note

4.11

405.2

248.99
say

249.00

1. It is assumed that dismantling of concrete slab/pavement


has been considered separately. Hence same is not added in
this analysis. Only labour for crushing the dismantled slab into
aggregate has been added. Carriage from stock pile to work
site has been provided with a lead of L km.
2. In case of breaking of slabs is done locally without
involvement of transportation, the provision of tipper, front end
loader and loading/unloading charges may be deleted.
3. As three wheeled smooth steel rollers are commonly in use,
the same has been provided as an alternative.
Penetration Coat Over Top Layer of Crushed Cement
Concrete Base
Spraying of bitumen over cleaned dry surface of crushed
cement concrete base at the rate of 25 kg per 10 sqm by a
bitumen pressure distributor, spreading of key aggregates at
the rate of 0.13 cum per 10 sqm by a mechanical gritter and
rolling the surface as per clause 506.3.8
Unit = sqm
Taking output = 7500 sqm
a)

b)

c)

Labour
Mate

day

0.560

673.00

376.88

L-12

Mazdoor skilled

day

2.000

408.00

816.00

L-15

Mazdoor

day

12.000

377.00

4524.00

L-13

Mechanical broom hydraulic @ 1250 sqm per hour

hour

6.000

334.00

2004.00

P&M-031

Hydraulic self propelled chips spreader

hour

6.000

2472.00

14832.00

P&M-025

Front end loader 1 cum bucket capacity

hour

6.000

756.00

4536.00

P&M-017

Tipper 10 tonne capacity

hour

6.000

291.00

1746.00

P&M-048

Vibratory roller 8 -10 tonnes @ 30 cum per hour

hour

6.00x0.65*

1446.00

5639.40

P&M-059

Bitumen pressure distributor @ 1750 sqm per hour

hour

4.280

1006.00

4305.68

P&M-004

cum

97.500

1063.00

103642.50

M-051

tonne

0.250

41320.00

10330.00

M-074

Machinery

Material
Crushed stone aggregate 11.2 mm size
Bitumen (60-70 grade)

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

15275.25
16802.77

Cost for 7500 sqm = a+b+c+d+e

184830.48

Rate per sqm = (a+b+c+d+e)/7500

24.64
say

Page 12 of 394

25.00

Sr No

Ref. to
MoRTH
Spec.

Description
Note

4.12

406

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Though vibratory roller is required only for 3 hours as per


norms, the same is required to be available at site for 6 hours
to match with other machines. The usage rates of vibratory
roller may be multiplied with a factor of 0.65.
Wet Mix Macadam
Providing, laying, spreading and compacting graded stone
aggregate to wet mix macadam specification including
premixing the Material with water at OMC in mechanical mix
plant carriage of mixed Material by tipper to site, laying in
uniform layers with paver in sub- base / base course on well
prepared surface and compacting with vibratory roller to
achieve the desired density.
Unit = cum
Taking output = 225 cum (495 tonnes)
a)

b)

Labour
Mate

day

0.480

673.00

323.04

L-12

Mazdoor skilled

day

2.000

408.00

816.00

L-15

Mazdoor

day

10.000

377.00

3770.00

L-13

Wet mix plant of 75 tonne hourly capacity

hour

9.000

1130.00

10170.00

P&M-094

Electric generator 125 KVA

hour

6.000

654.00

3924.00

P&M-018

Front end loader 1 cum capacity

hour

6.000

756.00

4536.00

P&M-017

Paver finisher

hour

6.000

915.00

5490.00

P&M-035

Vibratory roller 8 - 10 tonne

hour

6x0.65

1446.00

5639.40

P&M-059

Smooth 3 wheeled steel roller @ 8-10 tonnes.

hour

12.000

Water tanker 6 KL capacity

hour

3.000

233.00

699.00

P&M-060

tonne.km

495 x L

2.00

990.00

Lead =1
km & P&M058

Machinery

or

Tipper

c)

Add 10 per cent of cost of carriage to cover cost of


loading and unloading
Material ( Table 400-11)

99.00

45 mm to 22.4 mm@ 30 per cent

cum

89.100

863.55

76942.31

M-034

22.4 mm to 2.36 mm @ 40 per cent

cum

118.800

653.00

77576.40

M-031

2.36 mm to 75 micron@ 30 per cent

cum

89.100

137.00

12206.70

M-022

KL

18.000

13.00

234.00

M-189

Cost of water
d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

20341.58
22375.74

Cost for 225 cum = a+b+c+d+e

246133.17

Rate per cum = (a+b+c+d+e)/225

1093.93
say

Note

1094.00

1. Though vibratory roller is required only for 3 hours as per


norms, the same is required to be available at site for 6 hours
to match with other machines. The usage rates of vibratory
roller may be multiplied with a factor of 0.65
2. As three wheeled smooth steel rollers are commonly in use,
the same has been provided as an alternative which can be
used if the thickness of individual layer does not exceed 100
mm..

4.13

407

Construction of Median and Island with Soil Taken from


Roadway Cutting
Construction of Median and Island above road level with
approved material deposited at site from roadway cutting and
excavation for drain and foundation of other structures,
spread, graded and compacted as per clause 407
Unit = cum
Taking output =21 cum
a)

b)

Labour
Mate

day

0.240

673.00

161.52

L-12

Mazdoor

day

6.000

377.00

2262.00

L-13

Machinery
Page 13 of 394

Sr No

Ref. to
MoRTH
Spec.

Description

c)

Unit

Quantity

Rate Rs

Water tanker 6 KL with 5 km lead and 1 trip per hour

hour

1.000

Plate compactor @ 3.5 cum per hour

hour

6.000 input

Cost Rs

233.00

KL

6.000

13.00

Overhead charges @ 0.1 on (a+b+c)

#VALUE!

e)

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!

M-189

#VALUE!

Rate per cum = (a+b+c+d+e)/21

#VALUE!
say

407

78.00

d)

Cost for 21 cum = a+b+c+d+e

4.14

P&M-060

#VALUE! P&M-086

Material
Cost of water

Note

233.00

Remarks/
Input ref.

#VALUE!

This analysis provides for median and island with earthen top.
In case the surface is required to be turfed or planted with
shrubs, the same is required to be provided separately as per
analysis given in the chapter on horticulture. In case granular
fill is required to be paved, quantities of paving are required to
be calculated as per approved design and paid separately.
Construction of Median and Island with Soil Taken from
Borrow Areas
Construction of median and Island above road level with
approved material brought from borrow pits, spread, sloped
and compacted as per clause 407
Unit = cum
Taking output = 21 cum
a)

b)

Labour
Mate

day

0.160

673.00

107.68

L-12

Mazdoor

day

4.000

377.00

1508.00

L-13

Water tanker with 5 km lead

hour

1.000

233.00

233.00

P&M-060

Plate Compactor @ 3.5 cum per hour

hour

6.000 input

Hydraulic Excavator1.0 cum bucket capacity @60 cum


per hour
Tipper 10 tonne capacity

hour

0.500

1222.00

611.00

P&M-026

tonne.km

52.5 x L

2.00

105.00

Lead =1
km & P&M058

Machinery
#VALUE! P&M-086

Add 10 per cent of cost of transportation to cover cost


of loading and unloading
c) Material
Cost of water

10.50

KL

6.000

13.00

Overhead charges @ 0.1 on (a+b+c)

#VALUE!

e)

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!

Cost for 21 cum = a+b+c+d+e

#VALUE!

Rate per cum = (a+b+c+d+e)/ 21

#VALUE!
say

Note

4.15

This analysis provides for median and island with earthen top.
In case the surface is required to be turfed or planted with
shrubs, the same is required to be provided separately as per
analysis given in the chapter on horticulture. In case surface
finish is of hard type, the same may be provided separately as
per approved design.
Construction of Shoulders
A. Earthen Shoulders
The rate as applicable for sub-grade construction may be
adopted.
B. Hard Shoulders
Rate as applicable for sub-base and or base may be adopted
as per approved design.
C. Paved shoulders
The rate may be adopted as applicable for different layers of
pavement depending upon approved design of paved
shoulders.

4.16

409

78.00

d)

Footpaths and Separators

Page 14 of 394

#VALUE!

M-189

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Construction of footpath/separator by providing a 150 mm


compacted granular sub base as per clause 401 and 25 mm
thick cement concrete grade M15, over laid with pre-cast
concrete tiles in cement mortar 1:3 including provision of all
drainage arrangements but excluding kerb channel..
Unit = sqm
Taking output = 300 sqm
a)

b)

c)

Labour
Mate

day

1.360

673.00

915.28

Mason

day

4.000

500.00

2000.00

L-12
L-11

Mazdoor

day

30.000

377.00

11310.00

L-13

Vibratory road roller 8 -10 tonnes @60 cum per hour

hour

0.750

1446.00

1084.50

P&M-059

Water tanker 6 KL capacity @ 1 trip per hour

hour

2.000

233.00

466.00

P&M-060

Concrete mixer 0.4/0.28 cum per hour

hour

6.000

218.00

1308.00

P&M-009

53 mm to 26.5 mm @ 35 per cent

cum

20.790

713.00

14823.27

M-029

26.5 mm to 4.75 mm @ 45 per cent

cum

26.730

511.40

13669.72

M-026

2.36 mm below @ 20 per cent

cum

11.880

137.00

1627.56

M-022

Aggregate 12 mm crushed @ 0.9 cum of concrete

cum

6.750

928.00

6264.00

M-052

Sand @ 0.45 cum/cum of concrete

cum

3.380

2400.00

8112.00

M-005

tonne

1.880

5940.00

11167.20

M-081

cum

3.840

2400.00

9216.00

M-005

tonne

1.830

5940.00

10870.20

M-081

#VALUE!

M-184

#VALUE!

M-137

156.00

M-189

Machinery

Material

i) For Granular sub base material

ii) For cement concrete grade M157.5 cum

Cement
iii) For cement plaster 1:3
Sand
Cement
iv) Pre-cast cement concrete tiles
Tiles size 300 x 300 mm and 25 mm thick

each

3300.000 input

metre

22.500 input

v) RCC pipes
Pipes 200 mm dia,2.5 m long for drainage
vi) Cost of water

KL

12.000

13.00

d)

Overhead charges @ 0.1 on (a+b+c)

#VALUE!

e)

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!

Cost for 300 sqm = a+b+c+d+e

#VALUE!

Rate per sqm = (a+b+c+d+e)/300


4.17

410

#VALUE!
say

#VALUE!

Crusher Run Macadam Base


Providing crushed stone aggregate, depositing on a prepared
surface by hauling vehicles, spreading and mixing with a motor
grader, watering and compacting with a vibratory roller to
clause 410 to form a layer of sub-base/Base
Unit = cum
Taking output = 360 cum
A

By Mix in Place Method


a)

b)

c)

Labour
Mate

day

0.480

673.00

323.04

L-12

Mazdoor skilled

day

2.000

408.00

816.00

L-15

Mazdoor

day

10.000

377.00

3770.00

L-13

Tractor attached with rotavator @ 25 cum per hour

hour

12.000

356.00

4272.00

P&M-054

Motor grader 110 HP

hour

6.000

2247.00

13482.00

P&M-032

Vibratory roller 8 -10 tonnes @ 60 cum per hour

hour

6.000

1446.00

8676.00

P&M-059

Water tanker 6 KL capacity

hour

6.000

233.00

1398.00

P&M-060

Machinery

Material

Aggregate at site
i) For 53 mm maximum size
Page 15 of 394

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

63 mm to 45 mm @ 33 per cent

cum

157.460

599.20

94350.03

M-038

22.5 mm to 5.6 mm@ 32 per cent

cum

151.060

137.00

20695.22

M-032

Below 5.6 mm @ 35 per cent

cum

166.680

1507.00

251186.76

M-030

KL

36.000

13.00

468.00

M-189

Cost of water
Or
ii) For 45 mm maximum size
45 mm to 22.5 mm@ 5 per cent

cum

24.120

713.00

17197.56

M-034

22.4 mm to 5.6 mm@ 50 per cent

cum

237.600

137.00

32551.20

M-032

Below 5.6 mm@ 45 per cent

cum

213.480

1507.00

321714.36

M-030

KL

36.000

13.00

468.00

M-189

Cost of water
4.17A

(i)

For 53 mm maximum size


d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

39943.71
43938.08

Cost for 360.0cum = a+b+c+d+e

483318.83

Rate per cum = (a+b+c+d+e)/360

1342.55

or
4.17A

(ii)

say

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

40466.82
44513.50

Cost for 360.0cum = a+b+c+d+e

489648.47

Rate per cum = (a+b+c+d+e)/360


Note
4.17

1343.00

For 45 mm maximum size

1360.13
say

1360.00

Any one of the aggregate grading may be adopted


By Mixing Plant :
Unit = cum
Taking output = 225 cum (450 tonnes)
a)

b)

Labour
Mate

day

0.280

673.00

188.44

L-12

Mazdoor skilled

day

1.000

408.00

408.00

L-15

Mazdoor

day

6.000

377.00

2262.00

L-13

Wet mix plant @ 75 tonne per hour

hour

6.000

1130.00

6780.00

P&M-093

Electric generator 125 KVA

hour

6.000

654.00

3924.00

P&M-018

Front end loader 1 cum bucket capacity

hour

6.000

756.00

4536.00

P&M-017

Motor grader 110 HP

hour

6.000

2247.00

13482.00

P&M-032

Vibratory roller 8 - 10 tonne

hour

6.000

1446.00

8676.00

P&M-059

Water tanker 6 KL capacity

hour

3.000

233.00

699.00

P&M-060

tonne.km

450 x L

2.00

900.00

Lead =1
km & P&M058

Machinery

Tipper 10 tonne capacity

c)

Add 10 per cent of cost of carriage to cover cost of


loading and unloading
Material

90.00

Aggregate at site
i) For 53 mm maximum size
63 mm to 45 mm @ 33 per cent

cum

98.400

22.5 mm to 5.6 mm@ 32 per cent

cum

94.410

Below 5.6 mm @ 35 per cent

cum

104.180

599.20

58961.28

M-038

137.00

12934.17

M-032

1507.00

156999.26

M-030

Or
ii) For 45 mm maximum size
45 mm to 22.5 mm@ 5 per cent

cum

15.060

713.00

10737.78

M-034

22.4 mm to 5.6 mm@ 50 per cent

cum

148.500

137.00

20344.50

M-032

Below 5.6 mm@ 45 per cent

cum

133.430

1507.00

201079.01

M-030

KL

18.000

13.00

234.00

M-189

Cost of water
4.17 B

(i)

For 53 mm maximum size


d)

Overhead charges @ 0.1 on (a+b+c)

27084.02

e)

Contractor's profit @ 0.1 on (a+b+c+d)

29792.42

Page 16 of 394

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Cost for 225cum = a+b+c+d+e

327716.58

Rate per cum = (a+b+c+d+e)/225

1456.52
say

4.17 B

(ii)

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

27434.07
30177.48
331952.28

Rate per cum = (a+b+c+d+e)/360

922.09
say

Suggest
ive

1457.00

For 45 mm maximum size

Cost for 360.0cum = a+b+c+d+e

4.18

Remarks/
Input ref.

922.00

Lime, Flyash Stabilised Soil Sub-Base


Construction of Sub-base using lime - Flyash admixture with
granular soil, free from organic matter/ deleterious material or
clayey silts and low plasticity clays having PI between 5 and
20 and liquid limit less than 25 and commercial dry lime,
slaked at site or pre-slaked with CaO content not less than 50
per cent, Flyash to conform to gradation as per clause 4.3 of
IRC: 88-1984, lime + Flyash content ranging between 10 to 30
per cent, the minimum un-confined compressive strength and
CBR value after 28 days curing and 4 days soaking to be
7.5kg/sq, cm and 25 per cent respectively, all as specified in
IRC: 88-1984.
Unit = cum
Taking output = 480 cum (720 tonnes, density 1.50 t/cum)
Assumptions made
Total mass taken for analysis = 720 t
Lime + Flyash admixture @ 20 per cent = 0.2 x 720=144 t
Soil = 720 -144 = 576 t
576 /1.6 = 360 cum
Lime + Flyash = 144 t
Ratio Lime 4 : Flyash 16
Lime = 29 kg.
Flyash = 115 kg.
a)

b)

c)

Labour
Mate

day

0.240

673.00

161.52

L-12

Mazdoor

day

6.000

377.00

2262.00

L-13

Mazdoor (Skilled)

day

1.000

408.00

408.00

L-15
P&M-026

Machinery
Hydraulic Excavator 0.90 cum bucket capacity @
60cum/hr. for 360 cum soil
Tipper 10T capacity for carriage of soil 576 tonnes

hour

6.000

1222.00

7332.00

tonne.km

576 x L

2.00

1156.00

Tipper 10T capacity for carriage of 115 tonnes Flyash

tonne.km

115 x L

2.00

Tipper 10T capacity for carriage of 29 tonnes of lime from


store to work site
Add 10 per cent of cost of carriage to cover cost of
loading and unloading
Tractor with disc harrows for pulverisation

hour

3.000

291.00

hour

6.000

340.00

2040.00

P&M-053

Motor Grader 110 HP @ 50 cum per hour for mixing inplace and grading
Vibratory roller 8 - 10 tonne

hour

9.600

2247.00

21571.20

P&M-032

hour

6.000

1446.00

8676.00

P&M-059

Water tanker 6 KL capacity

hour

12.000

233.00

2796.00

P&M-060

tonne

29.000

3200.00

92800.00

M-188

cum

360.000

137.00

49320.00

M-092

Lead =1
km & P&M058
230.00 Lead =1
km & P&M058
873.00

P&M-048

87.30

Material
Slaked Lime
Compensation for earth taken from private source

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

Cost for 480 cum = a+b+c+d+e

18971.30
20868.43
229552.75

Page 17 of 394

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Rate per cum= (a+b+c+d+e)/480

478.23
say

Note

1.Compensation for earth will vary from place to place and will
have to be assessed realistically as per particular ground
situation. In case earth is available from Govt. land,
compensation for earth will not be required. The position is
required to be clearly stated in the cost estimate.
2.Cost of Flyash has not been considered as same will be
available free of cost. Only carriage of Flyash has been
provided.
3.Lime + Flyash has been taken as 20 per cent of total mass
and ratio of lime and Flyash as 1:4 for estimating purposes.
Total quantities will be as per approved design.

Page 18 of 394

478.00

Remarks/
Input ref.

CHAPTER - 5
BASES AND SURFACE COURSES (BITUMINOUS)
Sr No

Ref. to
MoRTH
Spec.

5.1

502

Description

Unit

Quantity

Rate Rs

Cost Rs

Prime Coat
Providing and applying primer coat with bitumen
emulsion on prepared surface of granular Base
including clearing of road surface and spraying primer
at the rate of 0.60 kg/sqm using mechanical means.
Unit = sqm
Taking output = 3500 sqm
a) Labour
Mate
Mazdoor
b) Machinery
Mechanical broom @ 1250 sqm per hour

c)

day
day

0.080
2.000

673.00
377.00

53.84
754.00

L-12
L-13

hour

2.800

334.00

935.20

P&M-031

Air compressor 250 cfm

hour

2.800

300.00

840.00

P&M-001

Emulsion pressure distributor @ 1750 sqm per hour

hour

2.000

750.00

Water tanker 6 KL capacity @ 1 trip per hour


Material
Bitumen emulsion @ 0.6 kg per sqm

hour

1.000

233.00

233.00

tonne

2.100

34975.00

73447.50

M-077

KL

6.000

13.00

78.00
7784.15
8562.57
94188.26
26.91
27.00

M-189

Cost of water
d) Overhead charges @ 0.1 on (a+b+c)
e) Contractor's profit @ 0.1 on (a+b+c+d)
Cost for 3500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/3500

say
Note

5.2

503

P&M-060

Tack Coat
Providing and applying tack coat with bitumen emulsion
using emulsion pressure distributor at the rate of 0.20 kg per
sqm on the prepared bituminous/granular surface cleaned
with mechanical broom.

c)

389.85
day
day

0.080
2.000

673.00
377.00

53.84
754.00

L-12
L-13

hour

2.800

334.00

935.20

P&M-031

Air compressor 250 cfm

hour

2.800

300.00

840.00

P&M-001

Emulsion pressure distributor @ 1750 sqm per hour

hour

2.000

750.00

tonne

0.700

34975.00

24482.50

say

2856.55
3142.21
34564.30
9.88
10.00

Material
Bitumen emulsion @ 0.2 kg per sqm

d) Overhead charges @ 0.1 on (a+b+c)


e) Contractor's profit @ 0.1 on (a+b+c+d)
Cost for 3500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/3500
Note

1. Bitumen emulsion has been provided @ 0.20 kg per sqm


as per clause 503.8. Payment shall be made with
adjustment, plus or minus, for the variation between this
quantity and actual quantity approved by the Engineer after
preliminary trials referred to in clause No. 503.4.3
2. An output of 3500 sqm has been considered in case of
prime coat and tack coat which can be covered by
bituminous courses on the same day.

504

1500.00 p&M -016

Bitumen primer has been provided @ 0.60 kg per sqm as


per clause 502.8. Payment shall be made with adjustment,
plus or minus, for the variation between this quantity and the
actual quantity approved by the Engineer after the
preliminary trials referred to in clause No. 502.4.3.

Unit = sqm
Taking output = 3500 sqm
a) Labour
Mate
Mazdoor
b) Machinery
Mechanical broom @ 1250 sqm per hour

5.3

Remarks/
Input ref.

Bituminous Macadam

Page 1 of 394

1500.00 p&M -016

M-077

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Providing and laying bituminous macadam with 100-120


TPH hot mix plant producing an average output of 75 tonnes
per hour using crushed aggregates of specified grading
premixed with bituminous binder, transported to site, laid
over a previously prepared surface with paver finisher to the
required grade, level and alignment and rolled as per
clauses 501.6 and 501.7 to achieve the desired compaction
Unit = cum
Taking output = 205 cum (450 tonnes)
a) Labour

b)

Mate

day

0.840

673.00

565.32

L-12

Mazdoor working with HMP, mechanical broom, paver,


roller, asphalt cutter and assistance for setting out
lines, levels and layout of construction

day

16.000

377.00

6032.00

L-13

Skilled mazdoor for checking line & levels

day

5.000

408.00

2040.00

L-15

Batch mix HMP 100-120 TPH @ 75 tonne per hour


actual output
Mechanical broom hydraulic @ 1250 sqm per hour

hour

6.000

15906.00

95436.00

P&M-021

hour

2.200

334.00

734.80

P&M-031

Air compressor 250 cfm

hour

2.200

300.00

660.00

P&M-001

Paver finisher hydrostatic with sensor control @ 75


cum per hour
Generator 250 KVA

hour

6.000

2509.00

15054.00

P&M-034

hour

6.000

700.00

4200.00

P&M-081

Front end loader 1 cum bucket capacity

hour

6.000

756.00

4536.00

P&M-017

tonne.km

450 x L

2.00

900.00

Lead =1
km & P&M058

Machinery

Tipper 10 tonne capacity

Add 10 per cent of cost of carriage to cover cost of loading


and unloading
Smooth wheeled roller 8-10 tonnes for initial break
down rolling.
Vibratory roller 8 tonnes for intermediate rolling.

c)

Finish rolling with 6-8 tonnes smooth wheeled tandem


roller.
Material
i) Bitumen@ 3.3 per cent of mix(60-70)

90.00
hour

6.00x0.65*

432.00

1684.80

P&M-044

hour

6.00x0.65*

1446.00

5639.40

P&M-059

hour

6.00x0.65*

1073.00

4184.70

P&M-045

tonne

14.850

41320.00

613602.00

M-074

weight of mix = 205 x 2.2 = 450 tonne


ii) Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 14.85 tonnes
Weight of aggregate = 450 -14.85 = 435.15 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 290.1 cum
*Grading I ( 40 mm nominal size )
37.5 - 25 mm 15 per cent

cum

43.510

713.00

31022.63

M-049

25 - 10 mm 45 per cent

cum

130.550

965.75

126078.66

M-046

10 - 5 mm 25 per cent

cum

72.530

700.00

50771.00

M-040

5 mm and below15 per cent

cum

43.510

1507.00

65569.57

M-030

25 - 10 mm 40 per cent

cum

116.040

965.75

112065.63

M-046

10 - 5 mm 40 per cent

cum

116.040

700.00

81228.00

M-040

5 mm and below 20 per cent

cum

58.020

1507.00

87436.14

M-030

or
GradingII(19 mm nominal size)

(i)

* Any one of the alternative may be adopted as per


approved design
for Grading I ( 40 mm nominal size )
d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

Cost for 205 cum = a+b+c+d+e

102880.09
113168.10
1244849.07

Page 2 of 394

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Rate per cum = (a+b+c+d+e)/205 (For Grading I)

6072.43
say

(ii)

6072.00

for GradingII(19 mm nominal size)


d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

103608.88
113969.77

Cost for 205 cum = a+b+c+d+e

1253667.44

Rate per cum = (a+b+c+d+e)/205 (For Grading-II)

6115.45
say

Note

Remarks/
Input ref.

6115.00

*1. Although the rollers are required only for 3 hours as per
norms of output, but the same have to be available at site for
six hours as the hot mix plant and paver will take six hours
for mixing and paving the output of 450 tonnes considered in
this analysis. To cater for the idle period of these rollers, their
usage rates have been multiplied by a factor of 0.65.
2.Quantity of Bitumen has been taken for analysis purpose.
The actual quantity will depend upon job mix formula.
3. Labour for traffic control, watch and ward and other
miscellaneous duties at site including sundries have been
included in administrative overheads of the contractor.
4. In case BM is laid over freshly laid tack coat, provision of
Mechanical broom and 2 mazdoors for the same shall be
deleted as the same has been included in the cost of tack
coat.

5.4

505

Bituminous Penetration Macadam


Construction of penetration macadam over prepared Base
by providing a layer of compacted crushed coarse aggregate
using chips spreader with alternate applications of
bituminous binder and key aggregates and rolling with a
smooth wheeled steel roller 8-10 tonne capacity to achieve
the desired degree of compaction
A

50 mm thick
Unit = sqm
Taking output = 4500 sqm (225 cum)
a) Labour

b)

c)

Mate

day

0.320

673.00

215.36

L-12

Mazdoor including for brooming of key aggregates

day

6.000

377.00

2262.00

L-13

Mazdoor skilled

day

2.000

408.00

816.00

L-15

Hydraulic self propelled chip spreader both for


aggregates and key aggregates@ 1500 sqm per hour
for 4500 x 2 sqm = 9000 sqm

hour

6.000

2472.00

14832.00

P&M-025

Bitumen pressure distributor for @ 1750 sqm per hour

hour

2.570

1006.00

2585.42

P&M-004

Tipper 5.5 cum capacity for carriage of aggregates


from stockpile to chip spreader
Vibratory roller 8 tonnes

hour

10.000

291.00

2910.00

P&M-048

hour

6.000

1446.00

8676.00

P&M-059

Front end loader 1 cum bucket capacity

hour

6.000

756.00

4536.00

P&M-017

tonne

22.500

41320.00

929700.00

M-074

cum

270.000

912.95

246496.50

M-033

cum

67.500

678.60

45805.50

M-031

Machinery

Material
Bitumen@ 5 kg per sqm

d)

Crushed stone coarse aggregate passing 45 mm and


retained on 2.8 mm sieve @ 0.06 cum per sqm
Key aggregates passing 22.4 mm and retained on 2.8
mm sieve @ 0.015 cum per sqm
Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

125883.48
138471.83

Cost for 4500 sqm = a+b+c+d+e

1523190.08

Rate per sqm = (a+b+c+d+e)/4500

338.49
say

Note

2 tippers will be needed to match the capacity of chip


spreader and front end loader.
Page 3 of 394

338.00

Sr No

Ref. to
MoRTH
Spec.

5.4

Description
B

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

75 mm thick
Unit = sqm
Taking output = 4500 sqm (337.5 cum compacted).
a) Labour

b)

Mate

day

0.400

673.00

269.20

L-12

Mazdoor including for brooming of key aggregates

day

8.000

377.00

3016.00

L-13

Mazdoor skilled

day

2.000

408.00

816.00

L-15

Hydraulic self propelled chip spreader both for


aggregates and key aggregates@ 1500 sqm per hour
for 4500 x 2 sqm

hour

6.000

2472.00

14832.00

P&M-025

Bitumen pressure distributor for@ 1750 sqm per hour

hour

2.570

1006.00

2585.42

P&M-004

Tipper 5.5 cum capacity for carriage of aggregates


from stockpile to chip spreader
Vibratory roller 8 tonnes

hour

10.000

291.00

2910.00

P&M-048

hour

6.000

1446.00

8676.00

P&M-059

Front end loader 1 cum bucket capacity

hour

6.000

756.00

4536.00

P&M-017

tonne

30.600

41320.00

1264392.00

M-074

cum

405.000

1010.70

409333.50

M-037

cum

81.000

511.40

41423.40

M-026

Machinery

c)

Material

d)

Crushed stone coarse aggregate (loose passing 63


mm and retained on 2.8 mm sieve @ 0.09 cum per
sqm
Key aggregates passing 26.5 mm and retained on 2.8
mm sieve @ 0.018 cum per sqm
Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

Bitumen@ 6.8 kg per sqm

175278.95
192806.85

Cost for 4500 sqm = a+b+c+d+e

2120875.32

Rate per sqm = (a+b+c+d+e)/4500

471.31
say

Note
5.5

506

471.00

2 tippers and 2 rollers will be needed to match the capacity


of chip spreader and front end loader.
Built-up-Spray Grout
Providing, laying and rolling of built-up-spray grout layer over
prepared base consisting of a two layer composite
construction of compacted crushed coarse aggregates using
motor grader for aggregates. key stone chips spreader may
be used with application of bituminous binder after each
layer, and with key aggregates placed on top of the second
layer to serve as a Base conforming to the line, grades and
cross-section specified, the compacted layer thickness being
75 mm
Unit = sqm
Taking output = 3000 sqm (225 cum)
a) Labour

b)

c)

Mate

day

0.400

673.00

269.20

L-12

Mazdoor including for brooming of key aggregates

day

8.000

377.00

3016.00

L-13

Mazdoor skilled

day

2.000

408.00

816.00

L-15

Hydraulic self propelled chip spreader both for


aggregates and key aggregates@ 1500 sqm per hour
for 3000 x 3 sqm

hour

6.000

2472.00

14832.00

P&M-025

Bitumen pressure distributor for 3000 x 2 sqm @ 1750


sqm per hour
Tipper 5.5 cum capacity

hour

3.430

1006.00

3450.58

P&M-004

hour

10.000

291.00

2910.00

P&M-048

Vibratory roller 8 tonnes

hour

6.000

1446.00

8676.00

P&M-059

Front end loader 1 cum bucket capacity

hour

6.000

756.00

4536.00

P&M-017

tonne

9.000

41320.00

371880.00

M-074

cum

300.000

900.55

270165.00

M-035

Machinery

Material
Bitumen30 kg per 10 sqm @ 15 kg per 10 sqm for
each layer
Crushed stone coarse aggregate passing 53 mm and
retained on 2.8 mm sieve @ 0.5 cum per 10 sqm for
each layer

Page 4 of 394

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

d)

Key aggregates passing 22.4 mm and retained on 2.8


mm sieve @ 0.13 cum per 10 sqm
Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

Quantity

cum

39.000

Rate Rs

Cost Rs

757.70

78111.12
859222.31

Rate per sqm = (a+b+c+d+e)/3000

286.41
say

5.6

507

M-031

71010.11

Cost for 3000 sqm = a+b+c+d+e

Note

29550.30

Remarks/
Input ref.

286.00

2 tippers will be needed to match the capacity of hydraulic


chip spreader and front end loader.
Dense Graded Bituminous Macadam
Providing and laying dense graded bituminous macadam
with 100-120 TPH batch type HMP producing an average
output of 75 tonnes per hour using crushed aggregates of
specified grading, premixed with bituminous binder @ 4.0 to
4.5 per cent by weight of total mix and filler, transporting the
hot mix to work site, laying with a hydrostatic paver finisher
with sensor control to the required grade, level and
alignment, rolling with smooth wheeled, vibratory and
tandem rollers to achieve the desired compaction as per
MoRTH specification clause No. 507 complete in all
respects.
Unit = cum
Taking output = 195 cum (450 tonnes)
a) Labour

b)

Mate

day

0.840

673.00

565.32

L-12

Mazdoor working with HMP, mechanical broom, paver,


roller, asphalt cutter and assistance for setting out
lines, levels and layout of construction

day

16.000

377.00

6032.00

L-13

Skilled mazdoor for checking line & levels

day

5.000

408.00

2040.00

L-15

Machinery
Batch mix HMP @ 75 tonne per hour

hour

6.000

12360.00

74160.00

P&M-022

Paver finisher hydrostatic with sensor control @ 75


cum per hour
Generator 250 KVA

hour

6.000

2509.00

15054.00

P&M-034

hour

6.000

700.00

4200.00

P&M-081

Front end loader 1 cum bucket capacity

hour

6.000

756.00

4536.00

P&M-017

tonne.km

450 x L

2.00

900.00

Lead =1
km & P&M058

Tipper 10 tonne capacity

Add 10 per cent of cost of carriage to cover cost of loading


and unloading
smooth wheeled roller 8-10 tonnes for initial break
down rolling.
Vibratory roller 8 tonnes for intermediate rolling.

c)

90.00
hour

6.00x0.65*

432.00

1684.80

P&M-044

hour

6.00x0.65*

1446.00

5639.40

P&M-059

hour

6.00x0.65*

1073.00

4184.70

P&M-045

tonne

19.130

41320.00

790451.60

M-074

37.5 - 25 mm 22 per cent

cum

63.190

711.00

44928.09

M-049

25 - 10 mm 13 per cent

cum

37.340

928.00

34651.52

M-046

10 -4.75 mm 19 per cent

cum

54.580

2314.00

126298.12

M-040

4.75 mm and below 44 per cent

cum

126.390

1507.00

190469.73

M-030

tonne

8.620

72.00

620.64

M-188

Finish rolling with 6-8 tonnes smooth wheeled tandem


roller.
Materials
Bitumen @ 4.25 per cent of weight of mix
Aggregate

Total weight of mix = 450 tonnes


Weight of bitumen = 19.13 tonnes
Weight of aggregate = 450 -19.13 = 430.87 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 287.25 cum
Grading - I40 mm (Nominal Size)

Filler @ 2 per cent of weight of aggregates.


or
Grading - II19 mm (Nominal Size)
Page 5 of 394

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Rate Rs

Cost Rs

cum

86.160

928.00

79956.48

M-046

10 - 5 mm 28 per cent

cum

80.430

2314.00

186115.02

M-040

5 mm and below 40 per cent

cum

114.900

1507.00

173154.30

M-030

tonne

8.620

72.00

620.64

M-188

* Any one of the alternative may be adopted as per


approved design
For Grading I ( 40 mm nominal size )
d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

130650.59
143715.65

Cost for 205 cum = a+b+c+d+e

1580872.16

Rate per cum = (a+b+c+d+e)/195 (For Grading I)

8107.04
say

(ii)

8107.00

For GradingII(19 mm nominal size)


d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

134938.43
148432.27

Cost for 205 cum = a+b+c+d+e

1632754.95

Rate per cum = (a+b+c+d+e)/195 (For Grading-II)

8373.10
say

Note

Remarks/
Input ref.

25 - 10 mm 30 per cent

Filler @ 2 per cent of weight of aggregates.

(i)

Quantity

8373.00

*1. Although the roller are required only for 3 hours as per
norms of output, but the same have to be available at site for
six hours as the hot mix plant and paver will take six hours
for mixing and paving the output of 450 tonnes considered in
this analysis. To cater for the idle period of these rollers, their
usage rates have been multiplied by a factor of 0.65.
2.Quantity of Bitumen has been taken for analysis purpose.
The actual quantity will depend upon job mix formula.
3. Labour for traffic control, watch and ward and other
miscellaneous duties at site including sundries have been
included in administrative overheads of the contractor.
4. In case DBM is laid over freshly laid tack coat, provision of
mechanical broom and 2 mazdoors shall be deleted as the
same has been included in the cost of tack coat.
5. The individual density for each size of aggregates to be
used for construction I.e. 37.5-25 mm, 25-10 mm etc. should
be found in the laboratory and accordingly the quantities
should be ammended for use in field. The average density of
1.5 tonne/cum is only a reference density in this Data Book.
6. The individual percentage of aggregates should be
calculated from the total weight of dry aggregates i.e..
excluding the weight of bitumen. The weight of filler will also
be 2 per cent by weight of dry aggregates.

5.7

508

Semi-Dense Bituminous Concrete


Providing and laying semi dense bituminous concrete with
100-120 TPH batch type HMP producing an average output
of 75 tonnes per hour using crushed aggregates of specified
grading, premixed with bituminous binder @ 4.5 to 5 per
cent of mix and filler, transporting the hot mix to work site,
laying with a hydrostatic paver finisher with sensor control to
the required grade, level and alignment, rolling with smooth
wheeled, vibratory and tandem rollers to achieve the desired
compaction as per MoRTH specification clause No. 508
complete in all respects
Unit = cum
Taking output = 195 cum (450 tonnes)
a) Labour
Mate

day

0.840

673.00

565.32

L-12

Mazdoor working with HMP, mechanical broom, paver,


roller, asphalt cutter and assistance for setting out
lines, levels and layout of construction

day

16.000

377.00

6032.00

L-13

Skilled mazdoor for checking line & levels

day

5.000

408.00

2040.00

L-15

Page 6 of 394

Sr No

Ref. to
MoRTH
Spec.

Description
b)

Unit

Rate Rs

Cost Rs

Remarks/
Input ref.

Machinery
Batch mix HMP @ 75 tonne per hour

hour

6.000

12360.00

74160.00

P&M-022

Paver finisher hydrostatic with sensor control @ 75


cum per hour
Generator 250 KVA

hour

6.000

2509.00

15054.00

P&M-034

hour

6.000

700.00

4200.00

P&M-081

Front end loader 1 cum bucket capacity

hour

6.000

756.00

4536.00

P&M-017

tonne.km

450 x L

2.00

900.00

Lead =1
km & P&M058

Tipper 10 tonne capacity

Add 10 per cent of cost of carriage to cover cost of


loading and unloading
Smooth wheeled roller 8-10 tonnes for initial break
down rolling.
Vibratory roller 8 tonnes for intermediate rolling.

c)

Quantity

Finish rolling with 6-8 tonnes smooth wheeled tandem


roller
Material

90.00
hour

6.00x0.65*

432.00

1684.80

P&M-044

hour

6.00x0.65*

1446.00

5639.40

P&M-059

hour

6.00x0.65*

1073.00

4184.70

P&M-045

tonne

20.250

41320.00

836730.00

M-074

* Grading I: 13 mm (Nominal Size)


i) Bitumen@ 4.5 per cent of weight of mix
ii) Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 20.25 tonnes
Weight of aggregate = 450-20.25 = 429.75 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 286.5 cum
13.2 - 10 mm20 per cent

cum

57.300

989.20

56681.16

M-044

10 - 5 mm 38 per cent

cum

108.870

700.00

76209.00

M-040

5 mm and below 40 per cent

cum

114.600

1507.00

172702.20

M-030

tonne

8.620

72.00

620.64

M-188

tonne

22.500

41320.00

929700.00

M-074

9.5 - 4.75 mm@ 57 per cent

cum

162.450

700.00

113715.00

M-040

4.75 and below@ 41 per cent

cum

116.850

1507.00

176092.95

M-030

tonne

8.620

72.00

620.64

M-188

Filler @ 2 per cent of weight of aggregates.


or
Grading II: 10 mm (Nominal Size)
Bitumen@5 per cent of weight of mix
weight of mix = 450 tonne
Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 22.5 tonnes
Weight of aggregate = 450 -22.50 = 427.50 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 285 cum

Filler @ 2 per cent of weight of aggregates.

(i)

*Any one of the alternative may be adopted as per


approved design
for Grading I ( 13 mm nominal size )
d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

126202.92
138823.21

Cost for 205 cum = a+b+c+d+e

1527055.36

Rate per cum = (a+b+c+d+e)/195 (For Grading I)

7831.05
say

5.7

(ii)

7831.00

for GradingII(10 mm nominal size)


d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

133921.48
147313.63

Cost for 205 cum = a+b+c+d+e

1620449.92

Rate per cum = (a+b+c+d+e)/195 (For Grading-II)

8310.00
say

Page 7 of 394

8310.00

Sr No

Ref. to
MoRTH
Spec.

Description
Note

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

*1. Although the rollers are required only for 3 hours as per
norms of output, but the same have to be available at site for
six hours as the hot mix plant and paver will take six hours
for mixing and paving the output of 450 tonnes considered in
this analysis. To cater for the idle period of these rollers, their
usage rates have been multiplied by a factor of 0.65
2.Quantity of Bitumen has been taken for analysis purpose.
The actual quantity will depend upon job mix formula.
3. Labour for traffic control, watch and ward and other
miscellaneous duties at site including sundries have been
included in administrative overheads of the contractor.
4. In case SDBC is laid over freshly laid tack coat, provision
of broom and 2 mazdoor shall be deleted as the same has
been included in the cost of tack coat.

5.8

509

5. The quantity of Bitumen to be adjusted as per job mix


formula.
Bituminous Concrete
Providing and laying bituminous concrete with 100-120 TPH
batch type hot mix plant producing an average output of 75
tonnes per hour using crushed aggregates of specified
grading, premixed with bituminous binder @ 5.4 to 5.6 per
cent of mix and filler, transporting the hot mix to work site,
laying with a hydrostatic paver finisher with sensor control to
the required grade, level and alignment, rolling with smooth
wheeled, vibratory and tandem rollers to achieve the desired
compaction as per MORTH specification clause No. 509
complete in all respects
Unit = cum
Taking output = 191 cum (450 tonnes)
a) Labour

b)

Mate

day

0.840

673.00

565.32

L-12

Mazdoor working with HMP, mechanical broom, paver,


roller, asphalt cutter and assistance for setting out
lines, levels and layout of construction

day

16.000

377.00

6032.00

L-13

Skilled mazdoor for checking line & levels

day

5.000

408.00

2040.00

L-15

Machinery
Batch mix HMP @ 75 tonne per hour

hour

6.000

12360.00

74160.00

P&M-022

Paver finisher hydrostatic with sensor control @ 75


cum per hour
Generator 250 KVA

hour

6.000

2509.00

15054.00

P&M-034

hour

6.000

700.00

4200.00

P&M-081

Front end loader 1 cum bucket capacity

hour

6.000

756.00

4536.00

P&M-017

tonne.km

450 x L

2.00

900.00

Lead =1
km & P&M058

Tipper 10 tonne capacity

Add 10 per cent of cost of carriage to cover cost of loading


and unloading
Smooth wheeled roller 8-10 tonnes for initial break
down rolling.
Vibratory roller 8 tonnes for intermediate rolling.

c)

90.00
hour

6.00x0.65*

432.00

1684.80

P&M-044

hour

6.00x0.65*

1446.00

5639.40

P&M-059

Finish rolling with 6-8 tonnes smooth wheeled tandem


roller.
Material

hour

6.00x0.65*

1073.00

4184.70

P&M-045

i) Bitumen@ 5 per cent of weight of mix(80-100)

tonne

22.500

42677.00

960232.50

M-075

20 - 10 mm 35 per cent

cum

99.750

1025.40

102283.65

M-045

10 - 5 mm 23 per cent

cum

65.550

1063.00

69679.65

M-040

ii) Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 22.5 tonnes
Weight of aggregate = 450 -22.50 = 427.50 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 285 cum
* Grading - I-19 mm (Nominal Size)

Page 8 of 394

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

5 mm and below 40 per cent

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

cum

114.000

1507.00

171798.00

M-030

tonne

8.620

72.00

620.64

M-188

13.2 - 10 mm30 per cent

cum

85.500

1063.00

90886.50

M-044

10 - 5 mm 25 per cent

cum

71.250

1063.00

75738.75

M-040

5 mm and below43 per cent

cum

122.550

1507.00

184682.85

M-030

tonne

8.620

72.00

620.64

M-188

Filler @ 2 per cent of weight of aggregates.


or
Grading - II-13 mm (Nominal Size)

Filler @ 2 per cent of weight of aggregates.

(i)

*Any one of the alternative may be adopted as per


approved design
for Grading-I ( 13 mm nominal size )
d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

142370.07
156607.07

Cost for 205 cum = a+b+c+d+e

1722677.80

Rate per cum = (a+b+c+d+e)/191

9019.26
say

5.8

(ii)

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

143124.75
157437.22

Cost for 205 cum = a+b+c+d+e

1731809.43

Rate per cum = (a+b+c+d+e)/191 (For Grading-II)

9067.07
say

Note

9019.00

for Grading-II(10 mm nominal size)

9067.00

*1. Although the rollers are required only for 3 hours as per
norms of output, but the same have to be available at site for
six hours as the hot mix plant and paver will take six hours
for mixing and paving the output of 450 tonnes considered in
this analysis. To cater for the idle period of these rollers, their
usage rates have been multiplied by a factor of 0.65
2.Quantity of Bitumen has been taken for analysis purpose.
The actual quantity will depend upon job mix formula.
3. Labour for traffic control, watch and ward and other
miscellaneous duties at site including sundries have been
included in administrative overheads of the contractor.
4. In case BC is laid over freshly laid tack coat, provision of
mechanical broom and 2 mazdoors shall be deleted as the
same has been included in the cost of tack coat.
5. The individual density for each size of aggregates to be
used for construction i.e. 37.5-25 mm, 25-10 mm etc. should
be found in the laboratory and accordingly the quantities
should be ammended for use in field. The average density of
1.5 tonne/cum is only a reference density in this Data Book.
6. The individual percentage of aggregates should be
calculated from the total weight of dry aggregates i.e..
excluding the weight of bitumen. The weight of filler will also
be 2 per cent by weight of dry aggregates.

5.9

510

Surface Dressing
Providing and laying surface dressing as wearing course in
single coat using crushed stone aggregates of specified size
on a layer of bituminous binder laid on prepared surface and
rolling with 8-10 tonne smooth wheeled steel roller
Unit = sqm
Taking output = 9000 sqm
Case -1 :-19 mm nominal chipping size
a) Labour

b)

Mate

day

0.440

673.00

296.12

L-12

Mazdoor

day

9.000

377.00

3393.00

L-13

Mazdoor skilled

day

2.000

408.00

816.00

L-15

hour

7.200

334.00

2404.80

P&M-031

Machinery
Mechanical broom @ 1250 sqm per hour
Page 9 of 394

Sr No

Ref. to
MoRTH
Spec.

Description

c)

Unit

Quantity

Rate Rs

Cost Rs

Air compressor 250 cfm

hour

7.200

300.00

2160.00

P&M-001

Hydraulic self propelled chip spreader @ 1500 sqm per


hour
Tipper 10 tonne capacity for carriage of stone chips
from stockpile on road side to chip spreader
Front end loader 1 cum bucket capacity

hour

6.000

2472.00

14832.00

P&M-025

hour

6.000

291.00

1746.00

P&M-048

hour

6.000

756.00

4536.00

P&M-017

Bitumen pressure distributor

hour

6.000

1006.00

6036.00

P&M-004

Smooth wheeled roller 8-10 tonne weight

hour

6.000

432.00

2592.00

P&M-044

tonne

10.800

41320.00

446256.00

M-074

cum

135.000

942.00

127170.00

M-053

Material
Bitumen@ 1.20 kg per sqm

d)

Crushed stone chipping,19 mm nominal size @ 0.015


cum per sqm
Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

61223.79
67346.17

Cost for 9000 sqm = a+b+c+d+e

740807.88

Rate per sqm = (a+b+c+d+e)/9000

82.31
say

5.9

Remarks/
Input ref.

82.00

Case - II 13 mm nominal size chipping


a) Labour

b)

Mate

day

0.440

673.00

296.12

L-12

Mazdoor

day

9.000

377.00

3393.00

L-13

Mazdoor skilled

day

2.000

408.00

816.00

L-15

Mechanical broom @ 1250 sqm per hour

hour

7.200

334.00

2404.80

P&M-031

Air compressor 250 cfm

hour

7.200

300.00

2160.00

P&M-001

Hydraulic self propelled chip spreader @ 1500 sqm per


hour
Tipper 10 tonne capacity for carriage of stone chips
from stockpile on road side to chip spreader
Front end loader 1 cum bucket capacity

hour

6.000

2472.00

14832.00

P&M-025

hour

6.000

291.00

1746.00

P&M-048

hour

6.000

756.00

4536.00

P&M-017

Bitumen pressure distributor @ 1750 sqm per hour

hour

6.000

1006.00

6036.00

P&M-004

Vibratory roller 8-10 tonne weight

hour

6.000

1446.00

8676.00

P&M-059

tonne

9.000

41320.00

371880.00

M-074

cum

90.000

928.00

83520.00

M-052

Machinery

c)

Material

d)

Crushed stone chipping,13 mm nominal size @ 0.01


cum per sqm
Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

Bitumen@ 1.00 kg per sqm

50029.59
55032.55

Cost for 9000 sqm = a+b+c+d+e

605358.06

Rate per sqm = (a+b+c+d+e)/9000

67.26
say

Note

5.10

1.Where the proposed aggregate fails to pass the stripping


test, an approved adhesion agent may be added to the
binder as per clause 510.2.4. Alternatively, chips may be
pre-coated as per clause 510.2.5
2.Input for the second coat, where required, will be the same
as per the Ist coat mentioned above
Open - Graded Premix Surfacing

511

Providing, laying and rolling of open - graded premix


surfacing of 20 mm thickness composed of 13.2 mm to 5.6
mm aggregates either using penetration grade bitumen or
cut-back or emulsion to required line, grade and level to
serve as wearing course on a previously prepared base,
including mixing in a suitable plant, laying and rolling with a
smooth wheeled roller 8-10 tonne capacity, finished to
required level and grades.
Unit = sqm
Taking output = 10250 sqm (205 cum)
(i)

Case - I: Mechanical method using Penetration grade


Bitumen and HMP of appropriate capacity not less than
75 tonnes/hour .
Page 10 of 394

67.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

a) Labour

b)

Mate

day

0.840

673.00

565.32

L-12

Mazdoor working with HMP, road sweeper, paver and


roller
Skilled mazdoor for checking line & levels

day

16.000

377.00

6032.00

L-13

day

5.000

408.00

2040.00

L-15

i) Batch type HMP 75 tonne per hour

hour

6.000

15906.00

95436.00

P&M-021

ii) Electric Generator Set 250 KVA

hour

6.000

700.00

4200.00

P&M-081

iii) Front end loader 1 cum bucket capacity

hour

6.000

756.00

4536.00

P&M-017

tonne.km

450 x L

2.00

900.00

Lead =1
km & P&M058

Machinery

iv) Tipper 10 tonne capacity

Add 10 per cent of cost of carriage to cover cost of loading


and unloading
v) Paver finisher hydrostatic with sensor attachment
iv) Smooth wheeled/tandom roller 8-10 tonnes weight
c)

90.00
hour

6.000

2509.00

15054.00

P&M-034

hour

6.000

1073.00

6438.00

P&M-045

tonne

14.970

41320.00

618560.40

M-074

cum

276.750

941.20

260477.10

M-043

Material
Bitumen@ 14.60 kg per 10 sqm

d)

Crushed stone chipping,13.2 mm to 5.6 mm @ 0.27


cum per 10 sqm
Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

101432.88
111576.17

Cost for 10250 sqm = a+b+c+d+e

1227337.87

Rate per sqm = (a+b+c+d+e)/10250

119.74
say

5.10

Note

If a premix sand seal coat of 'B' type is proposed, the same


is required to be provided over the open graded premix
carpet immediately on the same day. As the same HMP and
other machines will be used for laying of premix sand seal
coat, out of 6 effective working hours, 4.00 hours may be
utilised for laying of premix carpet and balance 2.00 hours
for the seal coat. The rate for the premix sand seal coat
under clause 513 (case II) has been worked out accordingly
by utilising the HMP for 2.00 hours for the purpose of seal
coat. In case type 'A' seal coat is proposed, HMP can be
worked for six hours for the premix carpet as type 'A' seal
coat does not require the use of HMP.

(ii)

Case - II: Open-Graded Premix Surfacing using cationic


Bitumen Emulsion
Unit = sqm

120.00

Taking output = 900 sqm (24.3 cum)


a) Labour

b)

Mate

day

0.800

673.00

538.40

L-12

Mazdoor

day

18.000

377.00

6786.00

L-13

Mazdoor skilled

day

2.000

408.00

816.00

L-15

Concrete mixer 0.4/0.28 cum capacity

hour

6.000

218.00

1308.00

P&M-009

Smooth wheeled steel roller 8-10 tonne

hour

6.000

432.00

2592.00

P&M-044

tonne

1.940

34975.00

67851.50

M-073

cum

24.300

941.20

22871.16

M-043

Machinery

c)

Material

d)

Crushed stone aggregates 13.2 mm to 5.6 mm @ 0.27


cum per 10 sqm
Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

Cationic Bitumen Emulsion @ 21.50 kg per 10 sqm

10276.31
11303.94

Cost for 900 sqm = a+b+c+d+e

124343.30

Rate per sqm = (a+b+c+d+e)/900

138.16
say

5.11

512

Close Graded Premix Surfacing/Mixed Seal Surfacing

Page 11 of 394

138.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Case I Mechanical means using HMP of appropriate capacity not


less than 75 tonnes/hour.
Providing, laying and rolling of close-graded premix
surfacing material of 20 mm thickness composed of 11.2 mm
to 0.09 mm (Type-a) or 13.2 mm to 0.09 mm (Type-b)
aggregates using penetration grade bitumen to the required
line, grade and level to serve as wearing course on a
previously prepared base, including mixing in a suitable
plant, laying and rolling with a Smooth wheeled roller 8-10
tonne capacity, and finishing to required level and grade.
Unit = sqm
Taking output = 10250 sqm (205 cum)
a) Labour

b)

Mate

day

0.840

673.00

565.32

L-12

Mazdoor working with HMP, road sweeper, paver and


roller
Skilled mazdoor for checking line & levels

day

16.000

377.00

6032.00

L-13

day

5.000

408.00

2040.00

L-15

i) HMP of appropicate capacity.

hour

6.000

15906.00

95436.00

P&M-021

ii) Electric Generator Set 250 KVA

hour

6.000

700.00

4200.00

P&M-081

iii) Front end loader 1 cum bucket capacity

hour

6.000

756.00

4536.00

P&M-017

tonne.km

450 x L

2.00

900.00

Lead =1
km & P&M058

Machinery

iv) Tipper 10 tonne capacity

Add 10 per cent of cost of carriage to cover cost of loading


and unloading
v) Paver finisher hydrostatic with sensor attachment
iv) Smooth wheeled8-10 tonnes weight
c)

90.00
hour

6.000

2509.00

15054.00

P&M-034

hour

6.000

432.00

2592.00

P&M-044

tonne

22.500

41320.00

929700.00

M-074

cum

276.750

1749.10

484063.43

M-041

tonne

19.480

41320.00

804913.60

M-074

cum

276.750

1375.20

380586.60

M-042

Material

Type - A
* Bitumen@ 22 kg per 10 sqm
Stone crushed aggregates 11.2 mm to 0.09 @ 0.27
cum per 10 sqm
or
Type - B
Bitumen @ 19 kg per 10 sqm

d)

Stone crushed aggregates 13.2 mm to 0.09 mm @


0.27 cum per 10 sqm
Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

154520.87
169972.96

Cost for 10250 sqm = a+b+c+d+e

1869702.58

Rate per sqm = (a+b+c+d+e)/10250

182.41
say

182.00

* Any one of the alternative may be adopted


5.12

513

Seal Coat
Providing and laying seal coat sealing the voids in a
bituminous surface laid to the specified levels, grade and
cross fall using Type A and B seal coats
Unit = sqm
Taking output = 10250 sqm (92.25 cum)
(i)

Case - I : Type A
a) Labour

b)

Mate

day

0.240

673.00

161.52

L-12

Mazdoor

day

6.000

377.00

2262.00

L-13

Hydraulic self propelled chip spreader

hour

6.000

2472.00

14832.00

P&M-025

Tipper 5.5 cum capacity

hour

6.000

291.00

1746.00

P&M-048

Front end loader 1 cum bucket capacity

hour

6.000

756.00

4536.00

P&M-017

Bitumen pressure distributor @ 1750 sqm per hour

hour

6.000

1006.00

6036.00

P&M-004

Smooth wheeled roller 8 -10 tonne weight

hour

6.000

432.00

2592.00

P&M-044

Machinery

Page 12 of 394

Sr No

Ref. to
MoRTH
Spec.

Description
c)

Unit

Quantity

Rate Rs

Cost Rs

Material
Bitumen@ 9.80 kg per 10 sqm

d)

Crushed stone chipping of 6.7 mm size defined as 100


per cent passing 11.2 mm sieve and retained on 2.36
mm sieve applied @ 0.09 cum per 10 sqm
Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

tonne

10.050

41320.00

415266.00

M-074

cum

92.250

700.00

64575.00

M-050

51200.65
56320.72

Cost for 10250 sqm = a+b+c+d+e

619527.89

Rate per sqm = (a+b+c+d+e)/10250

60.44
say

Note

5.12

(ii)

Remarks/
Input ref.

60.00

Since seal coat is provided immediately over the bituminous


layers, mechanical broom for clearing has not been catered.
Case - II : Type B
Providing and laying of premix sand seal coat with HMP of
appropriate capacity not less than 75 tonnes/ hours using
crushed stone chipping 6.7 mm size and penetration
bitumen of suitable grade.
Unit = sqm
Taking output = 7858 sqm (47.16 cum)
a) Labour

b)

Mate

day

0.160

673.00

107.68

L-12

Mazdoor

day

4.000

377.00

1508.00

L-13

Machinery
HMP of 75 tonnes/hour.

hour

2.000

12360.00

24720.00

P&M-022

Electric Generator Set 250 KVA

hour

2.000

700.00

1400.00

P&M-081

Front end loader 1 cum bucket capacity

hour

2.000

756.00

1512.00

P&M-017

tonne.km

104 x 'L'

2.00

208.00

Lead =1
km & P&M058

Tipper 10 tonne capacity

Add 10 per cent of cost of carriage to cover cost of loading


and unloading
Paver finisher hydrostatic with sensor attachment
Smooth wheeled 8-10 tonnes capacity
c)

20.80
hour

2.000

2509.00

5018.00

P&M-034

hour

2.000

432.00

864.00

P&M-044

tonne

5.340

41320.00

220648.80

M-074

cum

47.160

700.00

33012.00

M-050

Material
Bitumen@ 6.80 kg per 10 sqm
Crushed stone chipping of 6.7 mm size defined as
passing 11.2 mm sieve and retained on 2.36 mm sieve
applied @ 0.06 cum per 10 sqm

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

28901.93
31792.12

Cost for 7858 sqm = a+b+c+d+e

349713.33

Rate per sqm = (a+b+c+d+e)/7858

44.50
say

Note

5.13

514

Since seal coat is required to be provided over the premix


carpet on the same day, out of the 6 working hours of the
HMP, 4.00 hours are proposed to be utilised for the premix
carpet and the balance 2.00 hours for the seal coat. Hence
2.00 hours have been considered for this case. This may be
linked to rate analysis worked out under clause 511.
Supply of Stone Aggregates for Pavement Courses
Supply of stone aggregates from approved sources
conforming to the physical requirement, specified in the
respective specified clauses, including royalties, fees rents,
collection, transportation, stacking and testing and measured
in cum as per clause 514.5

Page 13 of 394

45.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Competitive market rates to be as certained. Alternatively,


rates for stone crushing given in chapter 1may be adopted, if
found economical. In case for supply of aggregates at site
are not available, nearest crusher site may be as certained.
Loading and un-loading charges and cost of carriage may be
added to these rates to arrive at the cost at site.
5.14

515

Mastic Asphalt
Providing and laying 25 mm thick mastic asphalt wearing
course with paving grade bitumen meeting the requirements
given in table 500-29, prepared by using mastic cooker and
laid to required level and slope after cleaning the surface,
including providing antiskid surface with bitumen precoated
finegrained hard stone chipping of 13.2 mm nominal size at
the rate of 0.005cum per 10 sqm and at an approximate
spacing of 10 cm center to center in both directions, pressed
into surface when the temperature of surfaces is not less
than 1000C, protruding 1 mm to 4 mm over mastic surface,
all complete as per clause 515.

Unit = sqm
Taking output = 35.00 sqm (0.87 cum ) assuming a
density of 2.3 tonnes/cum.-2 tonnes
a) Labour

b)

c)

Mate

day

0.440

673.00

296.12

L-12

Mazdoor

day

10.000

377.00

3770.00

L-13

Mazdoor skilled

day

1.000

408.00

408.00

L-15

Mechanical broom @ 1250 sqm per hour

hour

0.060

334.00

20.04

P&M-031

Air compressor 250 cfm

hour

0.060

300.00

18.00

P&M-001

Mastic cooker 1 tonne capacity

hour

6.000

58.00

348.00

P&M-030

Bitumen boiler 1500 litres capacity

hour

6.000

186.00

1116.00

P&M-005

Tractor for towing and positioning of mastic cooker and


bitumen boiler
Material

hour

1.000

340.00

340.00

P&M-053

tonne

0.204

41320.00

8429.28

M-074

cum

0.390

137.00

53.43

M-021

tonne

0.360

3200.00

1152.00

M-188

cum

0.550

941.20

517.66

M-043

cum

0.018 input

#VALUE!

M-142

20.50

M-074

Machinery

Base mastic (without coarse aggregates) = 60 per cent


Coarse aggregate (6.3mm to 13.2 mm) = 40 per cent .
Proportion of material required for mastic asphalt with coarse
aggregates (based on mix design done by CRRI for a
specific case)
I) Bitumen 85/25 or 30/40 @ 10.2 per cent by weight
of mix. 2 x 10.2/100 = 0.204
ii) Fine aggregate passing 2.36mm and retained on
0.075mm sieve @ 31.9 per cent by weight of mix = 2 x
31.9/100 = 0.638 tonnes = 0.638/1.625 = 0.39
iii) Lime stone dust filler with calcium content not less
than 80 per cent by weight @ 17.92 per cent by
weight of mix = 2 x 17.92/100 = 0.36
iv) Coarse aggregates 6.3 mm to 13.2 mm @ 40 per
cent by weight of mix = 2 x 40/100 = 0.8 MT =
0.8/1.456 = 0.55
v) Pre-coated stone chips of 13.2 mm nominal size for
skid resistance = 35 x 0.005/10 = 0.018
vi) Bitumen for coating of chips @ 2 per cent by weight
= 0.018 x 1.456 x 2/100 = 0.0005 MT = 0.5kg

kg

0.500

41.00

d)

Overhead charges @ 0.1 on (a+b+c)

#VALUE!

e)

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!

Cost for 35.00 sqm = a+b+c+d+e

#VALUE!

Rate per sqm = (a+b+c+d+e)/35

#VALUE!
say

Note

1.The rates for 50 mm & 40 mm thick layers may be worked


out on pro-rata basis.

Page 14 of 394

#VALUE!

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

2.Where tack coat is required to be provided before laying


mastic asphalt, the same is required to be measured and
paid separately.
3.The quantities of binder, filler and aggregates are for
estimating purpose. Exact quantities shall be as per mix
design.
4.This rate analysis is based on design made by CRRI for a
specific case and is meant for estimating purposes only.
Actual design is required to be done for each case.
5.15

516

Slurry Seal
Providing and laying slurry seal consisting of a mixture of
fine aggregates, portland cement filler, bituminous emulsion
and water on a road surface including cleaning of surface,
mixing of slurry seal in a suitable mobile plant, laying and
compacting to provide even riding surface
(i)

5 mm thickness
Unit = sqm
Taking output = 16000 sqm (80 cum)
Taking density of 2.2 tonnes per cum
weight of mix = 176 tonnes
a) Labour

b)

c)

Mate

day

0.240

673.00

161.52

L-12

Mazdoor

day

6.000

377.00

2262.00

L-13

Mechanical broom

hour

6.000

334.00

2004.00

P&M-031

Air compressor 250 cfm

hour

6.000

300.00

1800.00

P&M-001

Mobile slurry seal equipment

hour

6.000

945.00

5670.00

P&M-033

Front end loader 1 cum bucket capacity

hour

6.000

756.00

4536.00

P&M-017

Tipper 5.5 cum capacity for carriage of aggregate from


stockpile on road side to slurry equipment, bitumen
emulsion and filler.

hour

6.000

291.00

1746.00

P&M-048

Pneumatic tyred roller with individual wheel load not


exceeding 1.5 tonnes
Water tanker6 KL capacity

hour

6.000

1166.00

6996.00

P&M-037

hour

2.000

233.00

466.00

P&M-060

tonne

19.360

34975.00

677116.00

M-077

cum

102.080

1507.00

153834.56

M-030

tonne

3.520

72.00

253.44

M-188

KL

12.000

13.00

156.00

M-189

Machinery

Material
Residual Binder @ 11 per cent of mix 80 x 2.2 x 0.11
Fine aggregate 4.75 mm and below 87 per cent of
total mix,80 x 2.2 x 0.87 = 153.12 tonnes. Taking
density1.5, = 153.12/1.5 = 102.08 cum
Filler @ 2 per cent of total mix = 80 x 2.2 x 0.02
Cost of water

d)

Overhead charges @ 0.1 on (a+b+c)

85700.15

e)

Contractor's profit @ 0.1 on (a+b+c+d)

94270.17

Cost for 16000 sqm = a+b+c+d+e

1036971.84

Rate per sqm = (a+b+c+d+e)/16000

64.81
say

5.15

(ii)

65.00

3 mm thickness
Unit = sqm
Taking output = 20000 sqm (60 cum)
a) Labour

b)

Mate

day

0.200

673.00

134.60

L-12

Mazdoor

day

5.000

377.00

1885.00

L-13

Mechanical broom

hour

6.000

334.00

2004.00

P&M-031

Air compressor 250 cfm

hour

6.000

300.00

1800.00

P&M-001

Mobile slurry seal equipment

hour

6.000

945.00

5670.00

P&M-033

Front end loader 1 cum bucket capacity

hour

6.000

756.00

4536.00

P&M-017

Tipper 5.5 cum capacity for carriage of aggregate from


stockpile on road side to slurry equipment, bitumen
emulsion and filler

hour

6.000

291.00

1746.00

P&M-048

Machinery

Page 15 of 394

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Water tanker6 KL capacity


c)

Quantity

Rate Rs

Cost Rs

hour

2.000

233.00

466.00

Residual Binder @ 13 per cent of mix = 60 x 2.2 x


0.13
Fine aggregate 3 mm and below 85 per cent of total
mix, 60x 2.2 x 0.85 = 112.2 tonnes. Taking density 1.5,

tonne

17.160

34975.00

600171.00

M-077

cum

74.800

137.00

10247.60

M-022

Filler @ 2 per cent of total mix = 60x 2.2 x 0.02

tonne

2.640

72.00

190.08

M-188

KL

12.000

13.00

156.00

M-189

d)

Overhead charges @ 0.1 on (a+b+c)

62900.63

e)

Contractor's profit @ 0.1 on (a+b+c+d)

69190.69

Cost for 30000 sqm = a+b+c+d+e

761097.60

Rate per sqm = (a+b+c+d+e)/20000

38.05
say

(iii)

P&M-060

Material

Cost of water

5.15

Remarks/
Input ref.

38.00

1.5 mm thickness
Unit = sqm
Taking output = 24000 sqm (36 cum)
a) Labour

b)

c)

Mate

day

0.200

673.00

134.60

L-12

Mazdoor

day

5.000

377.00

1885.00

L-13

Mechanical broom

hour

6.000

334.00

2004.00

P&M-031

Air compressor 250 cfm

hour

6.000

300.00

1800.00

P&M-001

Mobile slurry seal equipment

hour

6.000

945.00

5670.00

P&M-033

Front end loader 1 cum bucket capacity

hour

6.000

756.00

4536.00

P&M-017

Tipper 5.5 cum capacity for carriage of aggregate from


stockpile on road side to slurry equipment, bitumen
emulsion and filler.
Water tanker6 KL capacity

hour

6.000

291.00

1746.00

P&M-048

hour

2.000

233.00

466.00

P&M-060

Residual Binder @ 16 per cent of mix, 36 x 2.2 x 0.16

tonne

12.670

34975.00

443133.25

M-077

Fine aggregate 2.36 mm and below,82 per cent of


total mix,36x 2.2 x 0.82 = 64.94 tonnes. Taking density
1.5
Filler @ 2 per cent of total mix = 36x 2.2 x 0.02

cum

43.300

137.00

5932.10

M-022

tonne

1.580

72.00

113.76

M-188

KL

12.000

13.00

156.00

M-189

Machinery

Material

Cost of water
d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

46757.67
51433.44

Cost for 24000 sqm = a+b+c+d+e

565767.82

Rate per sqm = (a+b+c+d+e)/24000

23.57
say

Note
5.16

517

24.00

1.Tack coat, if required to be provided, before laying slurry


seal may be measured and paid separately
Recycling of Bituminous Pavement with Central
Recycling Plant
Recycling pavement by cold milling of existing bituminous
layers, planning the surface after cold milling, reclaiming
excavated material to the extent of 30 per cent of the
required quantity, hauling and stock piling the reclaimed
material near the central recycling plant after carrying out
necessary checks and evaluation, adding fresh material
including rejuvenators as required, mixing in a hot mix plant,
transporting and laying at site and compacting to the
required grade, level and thickness, all as specified in clause
517.
Unit = cum
Taking output = 120 cum (276 tonnes)
a) Labour
Mate

day

0.480

673.00

323.04

L-12

Mazdoor

day

10.000

377.00

3770.00

L-13

Page 16 of 394

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Mazdoor skilled
b)

c)

Quantity
day

Rate Rs

2.000

Cost Rs

408.00

816.00

Remarks/
Input ref.
L-15

Machinery
Cold milling machine @ 20 cum per hour

hour

6.000 input

Mechanical broom @ 1250 sqm per hour

hour

1.280

334.00

#VALUE! P&M-069
427.52

P&M-031

Air compressor 250 cfm

hour

1.280

300.00

384.00

P&M-001

Bitumen pressure distributor @ 1750 sqm per hour

hour

0.910

1006.00

915.46

P&M-004

Hot mix plant 100-120 TPH producing an average of 75


tonnes per hour
Electric generator set 250 KVA

hour

3.000

15906.00

47718.00

P&M-021

hour

3.000

700.00

2100.00

P&M-081

Front end loader 1.00 cum bucket capacity

hour

3.000

756.00

2268.00

P&M-017

Tipper 5.5 cum capacity

hour

18.000

291.00

5238.00

P&M-048

Smooth wheeled roller 8-10 tonnes

hour

3.00x0.65*

432.00

842.40

P&M-044

Vibratory roller 8 tonnes

hour

3.00x0.65*

1446.00

2819.70

P&M-059

Smooth wheeled tandem roller 6-8 tonnes

hour

3.00x0.65*

1073.00

2092.35

P&M-045

tonne

1.987

41320.00

82111.10

M-074

tonne

7.728

41320.00

319320.96

M-074

37.5 - 25 mm @ 23 per cent

cum

28.440

713.00

20277.72

M-049

25 - 10 mm @ 15 per cent

cum

18.550

965.75

17914.66

M-046

10- 5 mm @ 20 per cent

cum

24.730

700.00

17311.00

M-040

Below 5 mm @40 per cent

cum

49.460

1507.00

74536.22

M-030

tonne

5.520

5940.00

32788.80

M-081

Material

i) Bitumen
A bitumen content is 4.5 per cent bitumen weight of mix. For
reclaimed material, fresh bitumen will be required to the
extent of 60 per cent of normal requirement.
In a mix of 276 tonnes, 82.8 tonne is reclaimed and balance
193.2 tonne is fresh mix.
Bitumen required for reclaimed mix of 82.8 tonne @ 60
per cent = 82.8 x 0.60 x0.04 = 1.99
Bitumen required for fresh mix of 193.2 tonnes = 193.2
x 0.04 = 7.73
ii) Aggregates
Percentage of mix requiring fresh aggregates - 70 per cent
Weight of fresh mix = 276 x 0.70 = 193.2 tonne
Weight of fresh aggregate in the mix = 193.2 x 0.96 = 185.47
tonne
Taking average density of 1.5 tonnes/cum, total volume
of aggregate = 123.65 cum.
Size wise requirement of fresh aggregates

d)

Filler (cement) @ 2 per cent = 5.52tonnes of 276


tonne
Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!
#VALUE!

Cost for 120 cum of DBM = a+b+c+d+e

#VALUE!

Rate per cum = (a+b+c+d+e)/120

#VALUE!
say

Note

5.17

518

#VALUE!

Although the total rolling time is only 4 hours as per norms,


all the three rollers have to be available at site for 3 hours
each to match with the output of re-cycling plant. To cater for
their idling time, these have been multiplied with a factor of
0.65.
Fog Spray
Providing and applying low viscosity bitumen emulsion for
sealing cracks less than 3 mm wide or incipient fretting or
disintegration in an existing bituminous surfacing.
Unit = sqm
Taking output = 10500 sqm
a) Labour

b)

Mate

day

0.120

673.00

80.76

L-12

Mazdoor

day

3.000

377.00

1131.00

L-13

hour

6.000

334.00

2004.00

P&M-031

Machinery
Mechanical broom @ 1250 sqm per hour

Page 17 of 394

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Air compressor 250 cfm

c)

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

hour

6.000

300.00

1800.00

P&M-001

Bitumen emulsion pressure distributor @ 1750 sqm per


hour
Material

tonne

6.000

1006.00

6036.00

P&M-004

Bitumen emulsion @ 0.75 kg per sqm

tonne

7.880

34975.00

275603.00

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

M-077

28665.48
31532.02

Cost for 10500 sqm = a+b+c+d+e

346852.26

Rate per sqm = (a+b+c+d+e)/10500

33.03
say

33.00

1.In case it is decided by the engineer to blind the fog spray,


the following may be added
a) Labour

b)

Mate

day

0.160

673.00

107.68

L-12

Mazdoor for precoating of grit

day

4.000

377.00

1508.00

L-13

cum

26.250

137.00

3596.25

M-024

tonne

0.790

34975.00

27630.25

M-077

Material
Crushed stone grit 3 mm size @ 3.75 kg per sqm
Bitumen emulsion for precoating grit @ 2 per cent of
grit,39.38 x 0.02

32842.18
3.13
say
5.18

519

3.00

Bituminous Cold Mix ( Including Gravel Emulsion)


Providing, laying and rolling of bituminous cold mix on
prepared base consisting of a mixture of unheated mineral
aggregate and emulsified or cutback bitumen, including
mixing in a plant of suitable type and capacity, transporting,
laying, compacting and finishing to specified grades and
levels.
Unit = cum
Taking output = 205 cum (450 tonne)
(i)

Using bitumen emulsion and 9.5 mm or 13.2 mm size


aggregate
Composition of mix (450 tonne) is assumed to be as
under:Bitumen Emulsion 8 per cent

By weight
of total mix

Filler2 per cent


Total aggregates 90 per cent
Proportion of aggregates
19 mm to 9.5 mm25 per cent
9.5 mm to 6 mm29 per cent
6 mm to 0.075 mm 36 per cent
a) Labour

b)

Mate

day

0.840

673.00

565.32

L-12

Mazdoor

day

16.000

377.00

6032.00

L-13

Mazdoor skilled

day

5.000

408.00

2040.00

L-15

Machinery
Drum mix plant for cold mixes of appropriate capacity
but not less than 75 tonnes/hour.
Electric generator 125 KVA

hour

6.000 input

hour

6.000

654.00

3924.00

P&M-018

Front end loader 1 cum bucket capacity

hour

6.000

756.00

4536.00

P&M-017

tonne.km

450 x L

2.00

900.00

Lead =1
km & P&M058

Tipper 10 tonne capacity

Add 10 per cent of cost of carriage to cover cost of loading


and unloading
Paver finisher

c)

#VALUE! P&M-077

90.00
hour

6.000

2509.00

15054.00

P&M-034

Pneumatic tyred roller 12-15 tonnes

hour

6.00x0.65*

1166.00

4547.40

P&M-037

Smooth wheeled steel tandem roller 6-8 tonnes

hour

6.00x0.65*

1073.00

4184.70

P&M-045

Material
Page 18 of 394

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Bitumen emulsion @ 8 per cent

tonne

36.000

34975.00

1259100.00

M-077

Filler (lime)@ 2 per cent

tonne

9.000

3200.00

28800.00

M-188

Aggregates size 19 to 9.5 mm - 450 x 0.25 x 1/1.5

cum

75.000

1025.40

76905.00

M-045

Aggregates size 9.5 to 6 mm - 450 x 0.29 x 1/1.5

cum

87.000

700.00

60900.00

M-040

Aggregates size 6 to 0.075 mm - 450 x 0.36 x 1/1.5

cum

108.000

1507.00

162756.00

M-030

d)

Overhead charges @ 0.1 on (a+b+c)

#VALUE!

e)

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!

Cost for 205 cum = a+b+c+d+e

#VALUE!

Rate per cum = (a+b+c+d+e)/205

#VALUE!
say

#VALUE!

(Applicable to cases I to IV)


Note

1.Density of aggregates has been assumed 1.5 gms/cc


2. Tack coat where provided will be measured and paid
separately.
*3. Though the rollers are required only for 3.5 hours each
as per norms of output, but these are required to be
available at site for 6 hours as the drum mix plant and the
paver would take 6 hours for mixing and paving. To cater for
the idle period, their usage rates have been multiplied by a
factor of 0.65

5.18

(ii)

Using bitumen emulsion and 19 mm or 26.5 mm nominal


size aggregate
Composition of mix (450 tonne)
is assumed to be as
under:Bitumen Emulsion 8 per cent
Filler2 per cent
Total aggregates 90 per cent
Proportion of aggregates
37.5 mm to 19 mm25 per cent
19 mm to 6 mm 30 per cent
6 mm to 0.075 mm 35 per cent
a) Labour

b)

Mate

day

0.840

673.00

565.32

L-12

Mazdoor

day

16.000

377.00

6032.00

L-13

Mazdoor skilled

day

5.000

408.00

2040.00

L-15

Machinery
Drum mix plant for cold mixes 60-90 tonne per hour
producing average output of 75 tonnes per hour
Electric generator 125 KVA

hour

6.000 input

hour

6.000

654.00

3924.00

P&M-018

Front end loader 1 cum bucket capacity

hour

6.000

756.00

4536.00

P&M-017

tonne.km

450 x L

2.00

900.00

Lead =1
km & P&M058

Tipper 10 tonne capacity

Add 10 per cent of cost of carriage to cover cost of loading


and unloading
Paver finisher

c)

#VALUE! P&M-077

90.00
hour

6.000

2509.00

15054.00

P&M-034

Pneumatic tyred roller 12-15 tonnes

hour

6.00x0.65*

1166.00

4547.40

P&M-037

Smooth wheeled steel tandom roller 6-8 tonnes

hour

6.00x0.65*

1073.00

4184.70

P&M-045

Bitumen emulsion @ 8 per cent

tonne

36.000

34975.00

1259100.00

M-077

Filler (lime)@ 2 per cent

tonne

9.000

3200.00

28800.00

M-188

Aggregates size 37.5 to 19 mm - 450 x 0.25 x 1/1.5

cum

75.000

0.00

M-048

Aggregates size 19 to 6 mm - 450 x 0.3 x 1/1.5

cum

90.000

0.00

M-047

Aggregates size 6 to 0.075 mm - 450 x 0.35 x 1/1.5

cum

105.000

158235.00

M-030

Material

1507.00

d)

Overhead charges @ 0.1 on (a+b+c)

#VALUE!

e)

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!

Cost for 205 cum = a+b+c+d+e

#VALUE!

Rate per cum = (a+b+c+d+e)/205

#VALUE!
say

Note

1.Density of aggregates has been assumed 1.5 gms/cc


Page 19 of 394

#VALUE!

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

2. Tack coat where provided will be measured and paid


separately.
*3. Though the rollers are required only for 3.5 hours each
as per norms of output, but these are required to be
available at site for 6 hours as the drum mix plant and the
paver would take 6 hours for mixing and paving. To cater for
the idle period, their usage rates have been multiplied by a
factor of 0.65
5.18

(iii)

Using cutback bitumen and 9.5 mm or 13.2 mm nominal


size aggregate
Composition of mix (450 tonne)
is assumed to be as
under:Cutback bitumen 5 per cent
Filler (lime)

2 per cent

Total aggregates 93 per cent


Proportion of aggregates
19 mm to 9.5 mm26 per cent
9.5 mm to 6 mm31 per cent
6 mm to 0.075 mm 36 per cent
a) Labour

b)

Mate

day

0.840

673.00

565.32

L-12

Mazdoor

day

16.000

377.00

6032.00

L-13

Mazdoor skilled

day

5.000

408.00

2040.00

L-15

Machinery
Drum mix plant for cold mixes 60-90 tonne per hour
producing average output of 75 tonnes per hour
Electric generator 125 KVA

hour

6.000 input

hour

6.000

654.00

3924.00

P&M-018

Front end loader 1 cum bucket capacity

hour

6.000

756.00

4536.00

P&M-017

tonne.km

450 x L

2.00

900.00

Lead =1
km & P&M058

Tipper 10 tonne capacity

Add 10 per cent of cost of carriage to cover cost of loading


and unloading
Paver finisher

c)

#VALUE! P&M-077

90.00
hour

6.000

2509.00

15054.00

P&M-034

Pneumatic tyred roller 12-15 tonnes

hour

6.00x0.65*

1166.00

4547.40

P&M-037

Smooth wheeled steel tandem roller 6-8 tonnes

hour

6.00x0.65*

1073.00

4184.70

P&M-045

Cutback bitumen @ 5 per cent

tonne

22.500

40367.00

908257.50

M-076

Filler (lime)@ 2 per cent

tonne

9.000

3200.00

28800.00

M-188

Aggregates size 19 to 9.5 mm - 450 x 0.26 x 1/1.5

cum

78.000

1025.40

79981.20

M-045

Aggregates size 9.5 to 6 mm - 450 x 0..31 x 1/1.5

cum

93.000

700.00

65100.00

M-040

Aggregates size 6 to 0.075 mm - 450 x 0.36 x 1/1.5

cum

108.000

1507.00

162756.00

M-030

Material

d)

Overhead charges @ 0.1 on (a+b+c)

#VALUE!

e)

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!

Cost for 205 cum = a+b+c+d+e

#VALUE!

Rate per cum = (a+b+c+d+e)/205

#VALUE!
say

Note

1.Density of aggregates has been assumed 1.5 gms/cc


2. Tack coat where provided will be measured and paid
separately.
*3. Though the rollers are required only for 3.5 hours each
as per norms of output, but these are required to be
available at site for 6 hours as the drum mix plant and the
paver would take 6 hours for mixing and paving. To cater for
the idle period, their usage rates have been multiplied by a
factor of 0.65

5.18

(iv)

Using cutback bitumen and 19 mm or 26.5 mm nominal


size aggregate
Composition of mix (450 tonne)
is assumed to be as
under:Cutback bitumen 5 per cent
Filler2 per cent
Page 20 of 394

#VALUE!

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Total aggregates 93 per cent


Proportion of aggregates
37.5 mm to 19 mm25 per cent
19 mm to 6 mm 30 per cent
6 mm to 0.075 mm 38 per cent
a) Labour

b)

Mate

day

0.840

673.00

565.32

L-12

Mazdoor

day

16.000

377.00

6032.00

L-13

Mazdoor skilled

day

5.000

408.00

2040.00

L-15

Machinery
Drum mix plant for cold mixes 60-90 tonne per hour
producing output of 75 tonnes per hour
Electric generator 125 KVA

hour

6.000 input

hour

6.000

654.00

3924.00

P&M-018

Front end loader 1 cum bucket capacity

hour

6.000

756.00

4536.00

P&M-017

tonne.km

450 x L

2.00

900.00

Lead =1
km & P&M058

Tipper 10 tonne capacity

Add 10 per cent of cost of carriage to cover cost of loading


and unloading
Paver finisher

c)

#VALUE! P&M-077

90.00
hour

6.000

2509.00

15054.00

P&M-034

Pneumatic tyred roller 12-15 tonnes.

hour

6.00x0.65*

1166.00

4547.40

P&M-037

Smooth wheeled steel tandem roller 6-8 tonnes

hour

6.00x0.65*

1073.00

4184.70

P&M-045

Cutback bitumen on @ 5 per cent

tonne

22.500

40367.00

908257.50

M-076

Filler (lime)@ 2 per cent

tonne

9.000

3200.00

28800.00

M-188

Material

Aggregates size 37.5 to 19 mm - 450 x 0.25 x 1/1.5

cum

75.000 input

#VALUE!

M-048

Aggregates size 19 to 6 mm - 450 x 0.3 x 1/1.5

cum

90.000 input

#VALUE!

M-047

Aggregates size 6 to 0.075 mm - 450 x0.38 x 1/1.5

cum

171798.00

M-030

114.000

1507.00

d)

Overhead charges @ 0.1 on (a+b+c)

#VALUE!

e)

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!

Cost for 205 cum = a+b+c+d+e

#VALUE!

Rate per cum = (a+b+c+d+e)/205


Note

#VALUE!
say

#VALUE!

1.Density of aggregates has been assumed 1.5 gms/cc


2. Tack coat where provided will be measured and paid
separately.
*3. Though the rollers are required only for 3.5 hours each
as per norms of output, but these are required to be
available at site for 6 hours as the drum mix plant and the
paver would take 6 hours for mixing and paving. To cater for
the idle period, their usage rates have been multiplied by a
factor of 0.65

5.19

520

Sand Asphalt Base Course


Providing, laying and rolling sand-asphalt base course
composed of sand, mineral filler and bituminous binder on a
prepared sub-grade or sub-base to the lines, levels, grades
and cross sections as per the drawings including mixing in a
plant of suitable type and capacity, transporting, laying,
compacting and finishing.
Unit = cum
Taking output = 205 cum (450 tonne)
a) Labour

b)

Mate

day

0.840

673.00

565.32

L-12

Mazdoor

day

16.000

377.00

6032.00

L-13

Mazdoor skilled

day

5.000

408.00

2040.00

L-15

Hot Mix Plant of appropriate capacity but not less than


75 tonnes/hour
Electric generator set 250 KVA

hour

6.000

10256.00

61536.00

P&M-023

hour

6.000

700.00

4200.00

P&M-081

Front end loader 1 cum bucket capacity

hour

6.000

756.00

4536.00

P&M-017

Machinery

Page 21 of 394

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Tipper 10 tonne capacity

tonne.km

Add 10 per cent of cost of carriage to cover cost of loading


and unloading
Paver finisher

c)

Quantity
450 x L

Rate Rs

Cost Rs

2.00

900.00

Remarks/
Input ref.
Lead =1
km & P&M058

90.00
hour

6.000

2509.00

15054.00

P&M-034

smooth wheeled roller 8-10 tonnes for initial break


down rolling.
Vibratory roller 8 tonnes for intermediate rolling.

hour

6.00x0.65

432.00

1684.80

P&M-044

hour

6.00x0.65

1446.00

5639.40

P&M-059

Finish rolling with 6-8 tonnes smooth wheeled tandom


rollers.
Material

hour

6.00x0.65

1073.00

4184.70

P&M-045

Bitumen@ 5 per cent

tonne

22.500

41320.00

929700.00

M-074

Filler (lime)@ 2 per cent

tonne

9.000

3200.00

28800.00

M-188

cum

288.620

2400.00

692688.00

M-004

Composition of mix (450 tonne)


under:Density 2.20 tonne per cum

is assumed to be as

Weight450 tonne
Bitumen5 per cent
Filler2 per cent
Sand of size 4.75 to 0.075 mm 93 per cent

Sand of size 4.75 to 0.075 mm - 450 x 0.93 x 1/1.5


d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

175765.02
193341.52

Cost for 205 cum = a+b+c+d+e

2126756.77

Rate per cum = (a+b+c+d+e)/205

10374.42
say

Note

1. Tack coat will be measured and paid separately


2. Although the rollers are required only for 3 hours as per
norms of output, but the same have to be available at site for
six hours as the hot mix plant and paver will take six hours
for mixing and paving the output of 450 tonnes considered in
this analysis. To cater for the idle period of this roller, their
usage rates has been multiplied by a factor of 0.65

5.20

521

Modified Binder
Supply of modified binder produced by mixing bitumen with
modifier such as natural rubber or crumb rubber or any other
polymer found compatible with bitumen and which allows
properties given in clause 521.3 and IRC:SP: 53 blending of
modifier with bitumen to be done either at the refinery or at
central unit with all facilities by proper industrial process, is
essential.
Unit = tonne
The use of modified binder is expected to result in an
extended service life of bituminous pavements subject to
heavy traffic loads in extreme climatic conditions, thus
justifying the entire cost of adding modifiers/fibres. Other
advantages include lower temperature susceptibility, higher
resistance to aging, higher fatigue life, higher resistance to
cracking and better adhesion between aggregates and
binder.
Detailed information and inductive dose level on the use of
polymer modified binder is available in IRC : SP-53 / 2002. A
number of proprietary products are now available in the
market. For such proprietary products, test reports and cost
effectiveness should be the basis for their selection in road
works.
The modifier, in the required quantity shall be blended at the
refinery or at central unit with all facilities by proper industrial
process, is essential. If supplied in drums it shall be agitated
in melted condition with suitable device for achieving
homogeneity

Page 22 of 394

10374.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Proposals to use glass fibre, polypropylene fibres or any


other similar material in a bituminous mixture should be
substantiated, complete with all details including test results,
manufacturer's recommendations for addition or means of
incorporating the fibres, homogeneously, without
segregation, into the mixture.
Before agreeing to the use of a fibre, it should have been
proved to be satisfactory in use under circumstances, similar
to the work, elsewhere or it would have under gone
appropriate performance trials. Documented evidence of use
and trials of the fibre, in any country having conditions
similar to Indian will be acceptable.
where information on use of trials is inadequate or lacking,
trials may be required to be under taken before agreeing to
the use of the fibre.
Note

1. The modified binder is usually manufactured by


specialised firms as a proprietary product. The rate for this
product is required to be as certained from the market.
2.The specifications for various item of road works using
polymer/rubber modified bitumens are same as those for
penetration grade bitumen except those for any special
conditions which the manufacturer may indicate

3.The other controls during mixing, laying shall be same as


specified in IRC - 14, 29, 94 and 95 for open graded premix
carpet, bituminous concrete, DBM and SDBC respectively
4.The temperature of mixing and rolling will be slightly higher
than conventional bituminous mixes as indicated in Table 8
of IRC: SP: 53 - 2002
5.21

522

Crack Prevention Courses


(i)

Stress absorbing membrane (SAM) crack width less


than 6 mm
Providing and laying of a stress absorbing membrane over a
cracked road surface, with crack width below 6 mm after
cleaning with a mechanical broom, using modified binder
complying with clause 521, sprayed at the rate of 9 kg per
10 sqm and spreading 5.6 mm crushed stone aggregates @
0.11 cum per 10 sqm with hydraulic chip spreader, sweeping
the surface for uniform spread of aggregates and surface
finished to conform to clause 902.
Unit = sqm
Taking output = 10500 sqm
a) Labour

b)

c)

Mate

day

0.240

673.00

161.52

L-12

Mazdoor

day

6.000

377.00

2262.00

L-13

Mechanical broom @ 1250 sqm per hour

hour

6.000

334.00

2004.00

P&M-031

Air compressor 250 cfm

hour

6.000

300.00

1800.00

P&M-001

Bitumen pressure distributor @ 1750 sqm per hour

hour

6.000

1006.00

6036.00

P&M-004

Hydraulic Chip spreader

hour

6.000

2472.00

14832.00

P&M-025

Smooth wheeled road roller 8-10 tonne

hour

6.000

432.00

2592.00

P&M-044

tonne

9.450

42677.00

403297.65

M-078

cum

105.000

700.00

73500.00

M-050

Machinery

Material
Modified binder
Crushed stone aggregates 5.6 mm size

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

50648.52
55713.37

Cost for 10500 sqm = a+b+c+d+e

612847.06

Rate per sqm = (a+b+c+d+e)/10500

58.37
say

5.21

(ii)

Stress absorbing membrane (SAM) with crack width 6


mm to 9 mm

Page 23 of 394

58.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Providing and laying of a stress absorbing membrane over a


cracked road surface, with crack width 6 to 9 mm after
cleaning with a mechanical broom, using modified binder
complying with clause 521, sprayed at the rate of 11 kg per
10 sqm and spreading 11.2 mm crushed stone aggregates
@ 0.12 cum per 10 sqm, sweeping the surface for uniform
spread of aggregates and surface finished to conform to
clause 902.
Unit = sqm
Taking output = 10500 sqm
a) Labour

b)

c)

Mate

day

0.240

673.00

161.52

L-12

Mazdoor

day

6.000

377.00

2262.00

L-13

Mechanical broom @ 1250 sqm per hour

hour

6.000

334.00

2004.00

P&M-031

Air compressor 250 cfm capacity

hour

6.000

300.00

1800.00

P&M-001

Bitumen pressure distributor @ 1750 sqm per hour

hour

6.000

1006.00

6036.00

P&M-004

Hydraulic Chip spreader

hour

6.000

2472.00

14832.00

P&M-025

Smooth wheeled road roller 8-10 tonne

hour

6.000

432.00

2592.00

P&M-044

tonne

11.550

42677.00

492919.35

M-078

cum

105.000

1063.00

111615.00

M-051

Machinery

Material
Modified binder
Crushed stone chipping 11.2 mm size

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

63422.19
69764.41

Cost for 10500 sqm = a+b+c+d+e

767408.46

Rate per sqm = (a+b+c+d+e)/10500

73.09
say

5.21

(iii)

73.00

Stress absorbing membrane (SAM) crack width above 9


mm and cracked area above 50 per cent
Providing and laying a single coat of a stress absorbing
membrane over a cracked road surface, with crack width
above 9 mm and cracked area above 50 per cent after
cleaning with a mechanical broom, using modified binder
complying with clause 521, sprayed at the rate of 15 kg per
10 sqm and spreading 11.2 mm crushed stone aggregates
@ 0.12 cum per 10 sqm, sweeping the surface for uniform
spread of aggregates and surface finished to conform to
clause 902.
Unit = sqm
Taking output = 10500 sqm
a) Labour

b)

c)

Mate

day

0.240

673.00

161.52

L-12

Mazdoor

day

6.000

377.00

2262.00

L-13

Mazdoor skilled

day

2.000

408.00

816.00

L-15

Mechanical broom @ 1250 sqm per hour

hour

6.000

334.00

2004.00

P&M-031

Air compressor 250 cfm capacity

hour

6.000

300.00

1800.00

P&M-001

Bitumen pressure distributor @ 1750 sqm per hour

hour

6.000

1006.00

6036.00

P&M-004

Hydraulic Chip spreader

hour

6.000

2472.00

14832.00

P&M-025

Smooth wheeled road roller 8-10 tonne

hour

6.000

432.00

2592.00

P&M-044

tonne

15.750

42677.00

672162.75

M-078

cum

126.000

1063.00

133938.00

M-051

Machinery

Material
Modified binder
Crushed stone aggregates 11.2 mm size

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

83660.43
92026.47

Cost for 10500 sqm = a+b+c+d+e

1012291.17

Rate per sqm = (a+b+c+d+e)/10500

96.41
say

Note

In case 2nd coat is also required to be provided, material


provided for the 2nd coat shall be as per table 500-47.
Page 24 of 394

96.00

Sr No

Ref. to
MoRTH
Spec.

5.21

Description
(iv)

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Case - IV : Bitumen impregnated geotextile


Providing and laying a bitumen impregnated geotextile layer
after cleaning the road surface, geotextile conforming to
requirements of clause 703.3, laid over a tack coat with 1.05
kg per sqm of paving grade bitumen 80 - 100 penetration
and constructed to the requirement of clause 703.4.5
Unit = sqm
Taking output = 3500 sqm
a) Labour

b)

Mate

day

0.560

673.00

376.88

L-12

Mazdoor

day

12.000

377.00

4524.00

L-13

Mazdoor skilled

day

2.000

408.00

816.00

L-15

Mechanical broom @ 1250 sqm per hour

hour

2.800

334.00

935.20

P&M-031

Air compressor 250 cfm capacity

hour

2.800

300.00

840.00

P&M-001

tonne

2.000

1006.00

2012.00

P&M-004

hour

2.000

1166.00

2332.00

P&M-037

tonne

3.680

40367.00

148550.56

M-075

sqm

3850.000

79.00

304150.00

M-108

Machinery

Bitumen pressure distributor @ 1750 sqm per hour


Pneumatic roller
c)

Material
Paving grade bitumen of 80 - 100 penetration @ 1.05
kg per sqm
Geotextile including 10 per cent for overlaps

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

46453.66
51099.03

Cost for 10500 sqm = a+b+c+d+e

562089.33

Rate per sqm = (a+b+c+d+e)/3500

160.60
say

161.00

NOTE As bitumen overlay construction shall follow closely the


fabric placement on the same day, an output of 3500 sqm
only has been considered for the analysis which will cover a
length of 500 m, of 7 m wide carriagway. This can be
conveniently overlaid by a bitumenious course in a day
5.22

519.3

Recipe Cold Mix


Providing and laying of premix of crushed stone aggregates
and emulsion binder, mixed in a batch type cold mixing
plant, laid over prepared surface, by paver finisher, rolled
with a pneumatic tyred roller initially and finished with a
smooth steel wheel roller, all as per clause 519.3
Unit = cum
Taking output = 205 cum (450 tonnes)
(i)

75 mm thickness
a) Labour

b)

Mate

day

1.000

673.00

673.00

L-12

Mazdoor

day

12.000

377.00

4524.00

L-13

Mazdoor skilled

day

5.000

408.00

2040.00

L-15

Machinery
Batch type cold mixing plant 100-120 TPH capacity
producing an average output of 75 tonne per hour
Electric generator 125 KVA

hour

6.000 input

hour

6.000

654.00

3924.00

P&M-018

Front end loader 1 cum capacity

hour

6.000

756.00

4536.00

P&M-017

Paver finisher hydrostatic with sensor control @ 75


cum per hour
Tipper 10 tonne capacity

hour

6.000

2509.00

15054.00

P&M-034

tonne.km

450 x L

2.00

900.00

Add 10 per cent of cost of carriage to cover cost of loading


and unloading
Pneumatic tyred roller12-15 tonnes.

#VALUE! P&M-064

Lead =1
km & P&M058

90.00
hour

6.00x0.65*

1166.00

4547.40

P&M-037

Smooth wheeled steel roller6-8 tonnes.

hour

6.00x0.65*

432.00

1684.80

P&M-044

Water tanker6 KL capacity

hour

1.000

233.00

233.00

P&M-060

Page 25 of 394

Sr No

Ref. to
MoRTH
Spec.

Description
c)

Unit

Quantity

Rate Rs

Cost Rs

Material
Bitumen emulsion @ 45 litres per tonne
Crushed stone aggregates 40 mm nominal size
Cost of water

tonne

20.250

34975.00

708243.75

M-077

cum

297.000

659.00

195723.00

M-055

KL

6.000

13.00

78.00

M-189

d)

Overhead charges @ 0.1 on (a+b+c)

#VALUE!

e)

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!

Cost for 10500 sqm = a+b+c+d+e

#VALUE!

Rate per sqm = (a+b+c+d+e)/205

#VALUE!
say

Note

Remarks/
Input ref.

#VALUE!

(Case I to III)
1. These mixes are considered suitable for minor repair work
and temporary road surface improvement.
2. In case concrete mixtures are required to be used for
mixing, a number of these will be needed to match the
capacity of road rollers.
3. Tack coat, where provided, will be measured and paid
separately.
*4.Both the rollers have to be available at site to match with
the output of batch mixing plant and paver finisher. A
multiplying factor of 0.65 has been adopted to cater for the
idling period of road rollers.

5.22

(ii)

40 mm thickness
a) Labour

b)

Mate

day

1.000

673.00

673.00

L-12

Mazdoor

day

12.000

377.00

4524.00

L-13

Mazdoor skilled

day

5.000

408.00

2040.00

L-15

Machinery
Batch type cold mixing plant100-120 TPH capacity
producing an average output of 75 tonne per hour
Electric generator 125 KVA

hour

6.000 input

hour

6.000

654.00

3924.00

P&M-018

Front end loader 1 cum capacity

hour

6.000

756.00

4536.00

P&M-017

Paver finisher hydrostatic with sensor control @ 75


cum per hour
Tipper 10 tonne capacity

hour

6.000

2509.00

15054.00

P&M-034

tonne.km

450 x L

2.00

900.00

Add 10 per cent of cost of carriage to cover cost of loading


and unloading
Pneumatic tyred roller 12-15 tonnes.

c)

#VALUE! P&M-064

90.00
hour

6.00x0.65*

1166.00

4547.40

P&M-037

Smooth wheeled steel roller 6-8 tonnes.

hour

6.00x0.65*

432.00

1684.80

P&M-044

Water tanker6 KL capacity

hour

1.000

233.00

233.00

P&M-060

tonne

31.500

34975.00

1101712.50

M-077

cum

287.000

928.00

266336.00

M-052

KL

6.000

13.00

78.00

M-189

Material
Bitumen emulsion @ 70 litres per tonne
Crushed stone aggregates 14 mm nominal size
Cost of water

d)

Overhead charges @ 0.1 on (a+b+c)

#VALUE!

e)

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!

Cost for 10500 sqm = a+b+c+d+e

#VALUE!

Rate per sqm = (a+b+c+d+e)/205

#VALUE!
say

5.22

(iii)

Lead =1
km & P&M058

#VALUE!

25 mm thickness
a) Labour

b)

Mate

day

1.000

673.00

673.00

L-12

Mazdoor

day

12.000

377.00

4524.00

L-13

Mazdoor skilled

day

5.000

408.00

2040.00

L-15

Machinery
Batch type cold mixing plant 100-120 TPH capacity
producing an average output of 75 tonne per hour
Electric generator 125 KVA

hour

6.000 input

hour

6.000

654.00

3924.00

P&M-018

Front end loader 1 cum capacity

hour

6.000

756.00

4536.00

P&M-017

Page 26 of 394

#VALUE! P&M-064

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Paver finisher hydrostatic with sensor control @ 75


cum per hour
Tipper 10 tonne capacity

Add 10 per cent of cost of carriage to cover cost of loading


and unloading
Pneumatic tyred roller

c)

Quantity

Rate Rs

Cost Rs

hour

6.000

2509.00

15054.00

tonne.km

450 x L

2.00

900.00

Remarks/
Input ref.
P&M-034
Lead =1
km & P&M058

90.00
hour

6.00x0.65*

1166.00

4547.40

P&M-037

Smooth wheeled steel roller

hour

6.00x0.65*

432.00

1684.80

P&M-044

Water tanker6 KL capacity

hour

1.000

233.00

233.00

P&M-060

tonne

38.250

34975.00

1337793.75

M-077

cum

270.000

700.00

189000.00

M-050

KL

6.000

13.00

78.00

M-189

Material
Bitumen emulsion @ 85 litres per tonne
Crushed stone aggregates 6 mm nominal size
Cost of water

d)

Overhead charges @ 0.1 on (a+b+c)

#VALUE!

e)

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!

Cost for 10500 sqm = a+b+c+d+e

#VALUE!

Rate per sqm = (a+b+c+d+e)/205

#VALUE!
say

Page 27 of 394

#VALUE!

CHAPTER- 6
CEMENT CONCRETE PAVEMENTS
Sr No
6.1

Ref. to
MoRTH
Spec.

Description

601

Unit

Add 10 per cent of cost of carriage to cover cost of loading


and unloading
c) Material
Crushed stone coarse aggregate of 25 mm and 12.5
mm nominal sizes graded as per table 600-1 @ 0.90
cum/cum of concrete conforming to clause 602.2.4.
Coarse Sand as per IS: 383 @ 0.45 cum/cum of
concrete
Cement @ 150 kg/cum of concrete
Cost of water
d) Overhead charges @ 0.1 on (a+b+c)
e) Contractor's profit @ 0.1 on (a+b+c+d)
Cost for 205 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/450
Note
602

Rate Rs

Cost Rs

Remarks/
Input ref.

Dry Lean Cement Concrete Sub- base


Construction of dry lean cement concrete Sub- base over a
prepared sub-grade with coarse and fine aggregate
conforming to IS: 383, the size of coarse aggregate not
exceeding 25 mm, aggregate cement ratio not to exceed
15:1, aggregate gradation after blending to be as per table
600-1, cement content not to be less than 150 kg/ cum,
optimum moisture content to be determined during trial
length construction, concrete strength not to be less than 10
Mpa at 7 days, mixed in a batching plant, transported to site,
laid with a paver with electronic sensor, compacting with 810 tonnes vibratory roller, finishing and curing.

Unit = cum
Taking output = 450 cum (990 tonne)
a) Labour
Mate
Mazdoor skilled
Mazdoor
b) Machinery
Front end loader 1 cum bucket capacity
Cement concrete batch mix plant @ 75 cum per hour
Electric generator 100 KVA
Paver with electronic sensor
Vibratory roller 8-10 t capacity
Water tanker6 KL capacity
Tipper

6.2

Quantity

day
day
day
hour
hour
hour
hour
hour
hour
tonne.km

1.120
6.000
22.000

673.00
408.00
377.00

753.76
2448.00
8294.00

L-12
L-15
L-13

6.000
6.000 input
6.000
6.000
8.000
8.000
990 x L

756.00

4536.00
#VALUE!
3924.00
15054.00
11568.00
1864.00
1980.00

P&M-017
P&M-068
P&M-080
P&M-034
P&M-059
P&M-060
Lead =1
km & P&M058

654.00
2509.00
1446.00
233.00
2.00

198.00

cum

405.000

0.00

0.00 M-052 and


M-054

cum

203.000

2400.00

487200.00

M-004

tonne
KL

67.500
48.000

5940.00
13.00

M-081
M-189

say

400950.00
624.00
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

673.00
408.00
377.00

1346.00
6120.00
13195.00

L-12
L-15
L-13

Quantity provided for aggregate is for estimating purpose.


Exact quantity shall be as per mix design.
Cement Concrete Pavement
Construction of un-reinforced, dowel jointed, plain cement
concrete pavement over a prepared sub base with 43 grade
cement @ 400 kg per cum, coarse and fine aggregate
conforming to IS 383, maximum size of coarse aggregate
not exceeding 25 mm, mixed in a batching and mixing plant
as per approved mix design, transported to site, laid with a
fixed form or slip form paver, spread, compacted and
finished in a continuous operation including provision of
contraction, expansion, construction and longitudinal joints,
joint filler, separation membrane, sealant primer, joint
sealant, debonding strip, dowel bar, tie rod, admixtures as
approved, curing compound, finishing to lines and grades as
per drawing
Unit = cum
Taking output = 1050 cum (2415 tonne)
a) Labour
Mate
Mazdoor skilled
Mazdoor
b) Machinery
Page 1 of 394

day
day
day

2.000
15.000
35.000

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Road Sweeper @ 1250 sqm per hour


Front end loader 1 cum bucket capacity
Cement concrete batch mix plant @ 175 cum per hour
(effective output)
Electric generator 250 KVA
Slip form paver with electronic sensor
Water tanker6 KL capacity
Transit truck agitator 5 cum capacity.

Add 10 per cent of cost of carriage to cover cost of loading


and unloading
Concrete joint cutting machine .
Texturing machine .
c) Material
Crushed stone coarse aggregates of 25mm and
12.5mm nominal size @ 0.90 cum/cum of concrete
conforming to clause 602.2.4. .
Sand as per IS: 383 and conforming to clause 602.2.4
@ 0.45 cum/cum of concrete
Cement 43 grade @ 400 kg/cum of concrete
32 mm mild steel dowel bars of grade S 240
16 mm deformed steel tie bars of grade S 415
Separation Membrane of impermeable plastic sheeting
125 micron thick
Pre moulded Joint filler, 25 mm thick for expansion
joint.
Joint sealant
Sealant primer
Plastic sheath,1.25 mm thick for dowel bars
Curing compound
Super plastisizer admixture IS marked as per 91031999 @ 0.5 per cent by weight of cement
Cost of water

Quantity

hour
hour
hour
hour
hour
hour
tonne.km

Rate Rs

2.800
18.000
6.000 input
6.000
6.000
36.000
2415xL

Cost Rs

334.00
756.00

700.00
2690.00
233.00
2.00

hour
hour

12.000 input
12.000 input

P&M-081
P&M-006
P&M-060
Lead =1
km & P&M058

cum

945.000

0.00

cum

473.000

2400.00

1135200.00

M-004

414.000
5940.00
9.450
37100.00
1.170
52100.00
3675.000 input

2459160.00
350595.00
60957.00
#VALUE!

M-081
M-126
M-082
M-164

16199.36

M-141

#VALUE!
#VALUE!
#VALUE!
1344950.00
#VALUE!

M-120
M-097
M-138
M-090
M-180

2808.00

M-189

tonne
tonne
tonne
sqm
sqm

16.330

kg
kg
sqm
liter
kg

875.000
116.670
46.670
1850.000
2070.000

KL

216.000

992.00
input
input
input
727.00
input
13.00

0.00 M-052 and


M-054

Add 1 per cent of material for cost of miscellaneous


materials like tarpauline, Hessian cloth, metal cap, cotton /
compressible sponge and cradle for dowel bars, work
bridges for men to approach concrete surface without
walking over it, cutting blades and bites, minor equipments
like scabbling machine, threads, ropes, guide wires and any
other unforeseen items.

#VALUE!

d)

Overhead charges @ 0.1 on (a+b+c)

#VALUE!

e)

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!
#VALUE!
#VALUE!
say

603

4200.00
16140.00
8388.00
4830.00

#VALUE! P&M-083
#VALUE! P&M-088

Rate per cum = (a+b+c+d+e)/1050

6.3

935.20 P&M-031
13608.00 P&M-017
#VALUE! P&M-067

483.00

Cost for 1050cum = a+b+c+d+e

Note

Remarks/
Input ref.

#VALUE!

The quantities for cement, coarse aggregate and fine


aggregates are for estimating only .The exact quantities will
be as per mix design.
Rolled Cement Concrete Base
Construction of rolled cement concrete base course with
coarse and fine aggregate conforming to IS:383, the size of
coarse aggregate not exceeding 25 mm with minimum,
aggregate cement ratio15:1 and minimum cement content of
200 kg/cum, aggregate gradation to be as per table 600-4
after blending, mixing in batching plant at optimum moisture
content, transporting to site, laying with a paver with
electronic sensor, compacting with 8-10 tonnes smooth
wheeled vibratory roller to achieve, the designed flexural
strength, finishing and curing.
Unit = cum
Taking output = 450 cum (990 tonne)
a)

Labour
Mate

day

1.200

673.00

807.60

L-12

Mazdoor skilled

day

7.000

408.00

2856.00

L-15

Mazdoor

day

23.000

377.00

8671.00

L-13

Page 2 of 394

Sr No

Ref. to
MoRTH
Spec.

Description
b)

Unit

Quantity

Rate Rs

Cost Rs

Machinery
Front end loader 1 cum bucket capacity

hour

6.000

Cement concrete batch mix plant @ 75 cum per hour

hour

6.000 input

Electric generator 100 KVA

hour

6.000

654.00

3924.00

P&M-080

Paver with electronic sensor @ 75 cum/hr.

hour

6.000

2509.00

15054.00

P&M-034

Vibratory roller 8-10 t capacity

hour

8.000

1446.00

11568.00

P&M-059

Water tanker with 5 km lead 6 KL capacity

hour

8.000

233.00

1864.00

P&M-060

tonne.km

990xL

2.00

1980.00

Lead =1
km & P&M058

Tipper

756.00

198.00

cum

405.000

847.50

Sand as per IS: 383 and conforming to clause 602.2.3


@ 0.45 cum/cum of concrete
Cement @ 200 kg/cum of concrete

cum

203.000

2400.00

487200.00

M-004

tonne

90.000

5940.00

534600.00

M-081

KL

48.000

13.00

624.00

343237.50 M-052 and


M-054

M-189

d)

Overhead charges @ 0.1 on (a+b+c)

#VALUE!

e)

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!

Cost for 450cum = a+b+c+d+e

#VALUE!

Rate per cum = (a+b+c+d+e)/450

#VALUE!
say

New

P&M-017

Crushed stone coarse aggregates of 25mm and


12.5mm nominal size @ 0.90 cum/cum of concrete
conforming to clause 602.2.3.

Cost of water

6.4

4536.00

#VALUE! P&M-068

Add 10 per cent of cost of carriage to cover cost of loading


and unloading
c) Material

Note

Remarks/
Input ref.

#VALUE!

The quantities for cement, coarse aggregate and fine


aggregates are for estimating only .The exact quantities will
be as per mix design.
Transition Section between Rigid and Flexible Pavement
Due to change in the properties of materials and type of
construction, a gradual changeover from rigid pavement to
flexible pavement is desirable to avoid any damage at the
butting joint. After provision of an expansion joint in the
cement concrete slab, the thickness of slab should be
tapered to 10 cm over a length of 3 m towards the flexible
pavement. The deficiency of thickness caused due to
tapering of the slab should be made up by the asphaltic
layers.
The quantities of items should be worked out based on the
approved design and drawings and priced as per rates given
under respective clauses for cement concrete and asphaltic
work.

6.5

Suggestive

Construction of Base/Sub-Base of Pavement with Lean


Concrete - Flyash.
Construction of Base/sub-base using cement, sand, fly ash
and coarse aggregates proportioned as per table 4 of IRC:
74/1979 and with water content ratio, slump and
compressive strength as defined in the said table, mix
prepared in a batching and mixing plant and compacted with
a vibratory roller 8-10 tonnes capacity within the time limit
laid down vide clause 7.6.3 of IRC: 74-1979, construction
joints properly formed at the end of day's work, cured for 14
days, all as specified in IRC: 74-1979 and as per approved
plans.
Unit = cum
Taking output = 450 cum (990 tonne)
a)

b)

Labour
Mate

day

1.120

673.00

753.76

L-12

Mazdoor skilled

day

6.000

408.00

2448.00

L-15

Mazdoor

day

22.000

377.00

8294.00

L-13

Front end loader 1 cum bucket capacity

hour

6.000

756.00

4536.00

P&M-017

Cement concrete batch mix plant @ 75 cum per hour

hour

6.000 input

Machinery

Page 3 of 394

#VALUE! P&M-068

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Electric generator 100 KVA

hour

6.000

654.00

3924.00

P&M-080

Paver finisher with electronic sensor

hour

6.000

2509.00

15054.00

P&M-034

Vibratory roller 8-10 t capacity

hour

8.000

1446.00

11568.00

P&M-059

Water tanker6 KL capacity

hour

8.000

233.00

1864.00

P&M-060

tonne.km

990 x L

2.00

1980.00

Lead =1
km & P&M058

Tipper 10 T Capacity

Add 10 per cent of cost of carriage to cover cost of loading


and unloading
c) Material
Crushed stone coarse aggregate of 40 mm nominal
size @ 0.90 cum/cum of concrete conforming to table 2
of IRC: 74-1979.
Coarse Sand as per IS: 383 - 1970
Cement @ 150 kg/cum of concrete
Fly ash conforming to IS: 3812 ( Part II )

198.00

cum

405.000 input

cum

110.960

tonne

67.500

cum

#VALUE!

M-055

2400.00

266304.00

M-004

5940.00

400950.00

M-081

#VALUE!

M-011

91.540 Nil

( Total fine aggregates = 450 x 0.45 = 202.50 cum To be


divided in ratio of 2 sand : 1.65 flyash. Refer table 4 of IRC:
74-1979).
d) Overhead charges @ 0.1 on (a+b+c)

#VALUE!

e)

#VALUE!

Contractor's profit @ 0.1 on (a+b+c+d)

Cost for 450cum = a+b+c+d+e

#VALUE!

Rate per cum = (a+b+c+d+e)/450


Note

6.6

Suggestive

Remarks/
Input ref.

#VALUE!
say

#VALUE!

1.Depending upon approved designs, crushed stone


aggregates of nominal size 20mm can also be used as per
gradation given in table 2 of IRC: 74-1979.
2.The ratio of specific gravities of fly ash and sand has been
assumed to be 0.827.
3.The quantities of materials given in the analyses are for
estimating purposes. Actual quantities shall be as per job
mix formula.
4.Construction procedure as laid down in clause, of IRC: 741979 shall be followed.
Cement - Flyash Concrete Pavement.
Construction reinforced-reinforced, dowel jointed, plain
cement concrete pavement over a prepared sub base with
43 grade cement, coarse and fine aggregate conforming to
IS 383, maximum size of coarse aggregate not exceeding 25
mm, replacing cement by fly ash to the extent of 15 per cent
and sand by 10 per cent, mixed in a batching and mixing
plant as per approved mix design, transported to site, laid
with a fixed form or slip form paver, spread, compacted and
finished in a continuous operation including provision of
contraction, expansion, construction and longitudinal joints,
joint filler, separation membrane, sealant primer, joint
sealant, debonding strip, dowel bar, tie rod, admixtures as
approved, curing compound, finishing to lines and grades as
per drawing
Unit = cum
Taking output = 1050 cum (2415 tonne)
a)

b)

Labour
Mate

day

2.000

673.00

1346.00

L-12

Mazdoor skilled

day

15.000

408.00

6120.00

L-15

Mazdoor

day

35.000

377.00

13195.00

L-13

Machinery
Road Sweeper @ 1250 sqm per hour

hour

2.800

334.00

935.20

P&M-031

Front end loader 1 cum bucket capacity

hour

18.000

756.00

13608.00

P&M-017

Cement concrete batch mix plant @ 175 cum per hour


(effective output)
Electric generator 250 KVA

hour

6.000 input

hour

6.000

700.00

4200.00

P&M-081

Slip form paver with electronic sensor

hour

6.000

2690.00

16140.00

P&M-006

Water tanker6 KL capacity

hour

36.000

233.00

8388.00

P&M-060

Page 4 of 394

#VALUE! P&M-067

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Transit truck agitator 5 cum capacity.

Add 10 per cent of cost of carriage to cover cost of loading


and unloading
Concrete joint cutting machine .
Texturing machine .
c)

Quantity

tonne.km

Rate Rs

Cost Rs

2415xL input

#VALUE! P&M-050
Lead= 1
km
#VALUE!

hour

12.000 input

#VALUE! P&M-083

hour

12.000 input

#VALUE! P&M-088

Material
Crushed stone coarse aggregates of 25mm and
12.5mm nominal size @ 0.90 cum/cum of concrete
conforming to clause 602.2.4. .

cum

945.000

0.00

Sand as per IS: 383 and conforming to clause 602.2.4

cum

425.000

2400.00

1020000.00

M-004

Cement 43 grade

tonne

357.000

5940.00

2120580.00

M-081

Fly ash conforming to IS: 3812-1966 (Part-I)

tonne

109.000 Nil

32 mm mild steel dowel bars of grade S 240

tonne

16 mm deformed steel tie bars of grade S 415

tonne

Separation Membrane of impermeable plastic sheeting


125 micron thick
Pre moulded Joint filler, 25 mm thick for expansion
joint.
Joint sealant

sqm
sqm

0.00 M-052 and


M-054

#VALUE!

M-011

9.450

37100.00

350595.00

M-126

1.170

52100.00

60957.00

M-082

#VALUE!

M-164

16199.36

M-141

3675.000 input
16.330

992.00

kg

875.000 input

#VALUE!

M-120

kg

116.670 input

#VALUE!

M-097

Plastic sheath,1.25 mm thick for dowel bars

sqm

46.670 input

#VALUE!

M-138

Curing compound

liter

1344950.00

M-090

#VALUE!

M-180

2808.00

M-189

Sealant primer

Super plastisizer admixture IS marked as per 91031999 @ 0.5 per cent by weight of cement
Cost of water

kg
KL

1850.000

727.00

2070.000 input
216.000

13.00

Add 1 per cent of material for cost of miscellaneous


materials like tarpauline, Hessian cloth, metal cap, cotton /
compressible sponge and cradle for dowel bars, work
bridges for men to approach concrete surface without
walking over it, cutting blades and bites, minor equipments
like scabbling machine, threads, ropes, guide wires and any
other unforeseen items.

#VALUE!

d)

Overhead charges @ 0.1 on (a+b+c)

#VALUE!

e)

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!

Cost for 1050cum = a+b+c+d+e

#VALUE!

Rate per cum = (a+b+c+d+e)/1050

#VALUE!
say

Note

Remarks/
Input ref.

1.The quantities for cement, coarse aggregate and fine


aggregates are for estimating only .The exact quantities will
be as per mix design.
2.IRC: 68-1976 may be referred for guidelines on the design
of cement-fly ash concrete for rigid pavement construction.
*Calculation of cement, sand and fly ash.
Cement @ 400 kg/cum = 1050 x 400 = 420 tonnes. 15
per cent of cement to be replaced by fly ash = 63
tonnes. Balance cement = 357 tonnes. Quantity of fly
ash = 63 x specific gravity of fly ash /specific gravity of
cement = 63 x 2.25/3.15 = 45 tonnes.
Sand @ 0.45 cum / cum of concrete = 1050 x 0.45 =
472.50 x 1.6 = 756 tonnes.10 per cent to be replaced by
flyash. Balance sand = 756 x 0.9 = 680.4 tonnes = 680.4 /
1.6 = 425 cum. Quantity of flyash = (756-680.4) x specific
gravity of fly ash/specific gravity of sand = 76.4 x 2.25 /
2.687 = 63.97 tonnes (say 64 tonnes)
Fly ash Total fly ash = 45 + 64 = 109 tonnes.

Page 5 of 394

#VALUE!

CHAPTER-7
GEOSYNTHETICS AND REINFORCED EARTH
Sr No

Ref. to
MoRTH
Spec.

7.1

702

Description

Unit

Rate Rs

Cost Rs

Geonets
Geomembrane
Geotextile
Add 2 per cent cost of material for miscellaneous items like
synthetic cord
c) Overhead charges @ 0.1 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Rate per metre = a+b+c+d
Note
702.4

day
day
day

0.040
0.250
0.500

sqm
sqm
sqm

1.000 input
1.000 input
2.000

673.00
408.00
377.00

79.00

703

L-12
L-15
L-13

#VALUE!
#VALUE!
158.00
#VALUE!

M-107
M-106
M-108

say

#VALUE!
#VALUE!
#VALUE!
#VALUE!

day
day
day
metre
sqm

0.040
0.250
0.500

673.00
408.00
377.00

26.92
102.00
188.50

L-12
L-15
L-13

#VALUE!
#VALUE!
#VALUE!

M-134
M-109

1.000 input
1.250 input

say
Note

26.92
102.00
188.50

Surplus excavated material to be used at site. Hence


seprate cost for disposal not added.
Narrow Filter Sub-Surface Drain
Construction of a narrow filter sub- surface drain consisting
of porous or perforated pipe laid in narrow trench
surrounded by a geotextile filter fabric, with a minimum of
450 mm overlap of fabric and installed as per clause 702.3
and 309.3.5 including excavation and backfilling
Unit = Running metre length
Taking output = one metre
a) Labour
Mate
Mazdoor skilled
Mazdoor
b) Material
Perforated geosynthetic pipe 150 mm dia
Geotextile filter fabric
Add 2 per cent cost of material for miscellaneous item like
synthetic cord
c) Overhead charges @ 0.1 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Rate per metre = a+b+c+d

7.3

Remarks/
Input ref.

Sub-Surface Drain with Geotextiles


Construction of sub surface drain 200 mm dia using
geotextiles treated with carbon black with physical properties
as given in clause 702.2.3 formed in to a stable network and
a planar geocomposite structure, joints wrapped with
geotextile to prevent ingress of soil, all as per clause 702
and approved drawings including excavation and backfilling
Unit = Running metre
Taking output = one metre
a) Labour
Mate
Mazdoor skilled
Mazdoor
b) Material
Geonets, geomembrane and geotextile to make planar
geocomposite stable network for sub surface drain including
wrapping of joints with 160 mm over lapping with geotextile .

7.2

Quantity

Surplus excavated material to be used at site. Hence


Separate cost for disposal not added.
Laying Paving Fabric Beneath a Pavement Overlay
Providing and laying paving fabric with physical
requirements as per table 704-2 over a tack coat of paving
grade Bitumen 80-100 penetration, laid at the rate of 1 kg
per sqm over thoroughly cleaned and repaired surface to
provide a water resistant membrane and crack retarding
layer. Paving fabric to be free of wrinkling and folding and to
be laid before cooling of tack coat, brooming and rolling of
surface with pneumatic roller to maximise paving fabric
contact with pavement surface
Unit = sqm
Taking output = 2800 sqm
a) Labour
Page 1 of 394

#VALUE!
#VALUE!
#VALUE!
#VALUE!

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Mate
Mazdoor
b) Machinery
Road sweeper 1250 sqm per hour
Pneumatic roller 14 tonnes 2000 sqm per hour
Bitumen pressure distributor 1750 sqm per hour
c) Material
Paving Fabric
Paving Bitumen 80-100
c) Overhead charges @ 0.1 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Cost for 2800 sqm = a+b+c+d+e
Rate per sqm =(a+b+c+d+e)/2800

Quantity

Rate Rs

Cost Rs

day
day

0.800
20.000

673.00
377.00

538.40
7540.00

L-12
L-13

hour
hour
hour

2.240
1.400
1.680

334.00
1166.00
1006.00

748.16
1632.40
1690.08

P&M-031
P&M-037
P&M-004

2940.000 input
2.800
40367.00

#VALUE!
113027.60
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

sqm
tonne

say
7.4

704

Remarks/
Input ref.

M-133
M-075

Laying Boulder Apron in Crates of Synthetic Geogrids


Providing, preparing and laying of geogrid crated apron 1 m
x 5 m, 600 mm thick including excavation and backfilling with
baffles at 1 metre interval, made with geogrids having
characteristics as per clause 704.2, joining sides with
connectors/ring staples, top corners to be tie tensioned,
placing of suitable cross interval ties in layers of 300 mm
connecting opposite side with lateral braces and tied with
polymer braids to avoid bulging, constructed as per clause
704.3. filled with stone with minimum size of 200 mm and
specific gravity not less than 2.65, packed with stone spalls,
keyed to the foundation recess in case of sloping ground
and laid over a layer of geotextile to prevent migration of
fines, all as per clause 704 and laid as per clause 2503.3
and approved design.
Unit = cum
Taking output = 3.00 cum
a) Labour

b)

Mate

day

0.060

673.00

40.38

L-12

Mazdoor skilled

day

0.500

408.00

204.00

L-15

Mazdoor

day

1.500

377.00

565.50

L-13

Geo grids

sqm

21.000

404.00

8484.00

M-105

Connectors/ Staples

each

50.000

7.00

350.00

M-085

#VALUE!

M-140

Material

Polymer braids

metre

20.000 input

Stones with minimum size of 200 mm

cum

3.450

240.00

828.00

M-003

Stones spall for filling voids

cum

0.450

175.00

78.75

M-008

c)

Overhead charges @ 0.1 on (a+b)

#VALUE!

d)

Contractor's profit @ 0.1 on (a+b+c)

#VALUE!

Cost for 3 cum = a+b+c+d

#VALUE!

Rate per cum = (a+b+c+d)/ 3

#VALUE!
say

7.5

3100

Reinforced Earth Structures


Reinforced earth Structures have four main components as
under:
a)
Excavation for foundation, foundation concrete and
cement concrete grooved seating in the foundation for facing
elements (facia material).
b)

Facia material and its placement.

c)
Assembling, joining with facing elements and laying of
the reinforcing elements.
d)
Earth fill with granular material which is to be retained
by the wall.
Each component is analysed separately as under:
considering Average height of wall = 8 m.
7.5

3102

(i)

Assembling, joining and laying of reinforcing elements.

With reinforcing element of steel / Aluminium strips /


polymeric strips.
Unit = Running Metre
Page 2 of 394

#VALUE!

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Taking Output = 450 m


a)

b)

Labour
Mate

day

0.360

673.00

242.28

L-12

Mazdoor

day

6.000

377.00

2262.00

L-13

Mazdoor skilled

day

3.000

408.00

1224.00

L-15

Material

@ Reinforcement strips 60 mm wide 5 mm thick as per


clause 3102.
1.Galvanised carbon steel strips

metre

450*1.1 input

#VALUE!

M-154

metre

450*1.1 input

#VALUE!

M-153

metre

450*1.1 input

#VALUE!

M-157

metre

450*1.1 input

#VALUE!

M-156

metre

450*1.1 input

#VALUE!

M-155

or
2.Copper Strips
or
3.Aluminium Strips
or
4.Stainless steel strips
or
5.Glass reinforced polymer/fibre reinforced
polymer/polymeric strips
@ Any one of the above alternative may be adopted as per
approved design.
Add 10 per cent of the cost of reinforcing strip towards
accessories like tie-strips, nuts and bolts and loops/lugs for
joining reinforcing elements with the facia pannels, overlaps,
heat bonding or extension.
Type 1

1.Galvanised carbon steel strips


c)

Overhead charges @ 0.1 on (a+b)

#VALUE!

d)

Contractor's profit @ 0.1 on (a+b+c)

#VALUE!

Cost of 450 m = a+b+c+d

#VALUE!

Rate per metre =(a+b+c+d)/450

#VALUE!
say

Type 2

2.Copper Strips
c)

Overhead charges @ 0.1 on (a+b)

#VALUE!

d)

Contractor's profit @ 0.1 on (a+b+c)

#VALUE!

Cost of 450 m = a+b+c+d

#VALUE!

Rate per metre =(a+b+c+d)/450

#VALUE!
say

Type 3

c)

Overhead charges @ 0.1 on (a+b)

#VALUE!

d)

Contractor's profit @ 0.1 on (a+b+c)

#VALUE!
#VALUE!

Rate per metre =(a+b+c+d)/450

#VALUE!
say

c)

Overhead charges @ 0.1 on (a+b)

#VALUE!

d)

Contractor's profit @ 0.1 on (a+b+c)

#VALUE!
#VALUE!

Rate per metre =(a+b+c+d)/450

#VALUE!
say

#VALUE!

d)

#VALUE!

Contractor's profit @ 0.1 on (a+b+c)

#VALUE!

Rate per metre =(a+b+c+d)/450

#VALUE!
say

#VALUE!

5.Glass reinforced polymer/fibre reinforced


polymer/polymeric strips
c) Overhead charges @ 0.1 on (a+b)
Cost of 450 m = a+b+c+d

7.5(i)

#VALUE!

4.Stainless steel strips

Cost of 450 m = a+b+c+d

Type 5

#VALUE!

3.Aluminium Strips

Cost of 450 m = a+b+c+d

Type 4

#VALUE!

With reinforcing elements of synthetic geogrids


Unit = sqm
Taking output = 300 sqm
a)

Labour
Page 3 of 394

#VALUE!

Ref. to
MoRTH
Spec.

Sr No

Description

b)

Unit

Quantity

Rate Rs

Cost Rs

Mate

day

0.360

673.00

242.28

L-12

Mazdoor

day

6.000

377.00

2262.00

L-13

Mazdoor skilled

day

3.000

408.00

1224.00

L-15

sqm

300.000

404.00

121200.00

Material
Synthetic Geogrids as per clause 3102.8 and approved
design and specifications.
Add 10 per cent of the cost of reinforcing elements
(synthetic geogrids) for accessories like tie-strips, nuts
and bolts and loops/lugs for joining reinforcing
elements with the facia pannels, overlaps and other
protective elements for synthetic geogrids.

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

13704.83
15075.31

Cost of 300 sqm of Synthetic geogrids = a+b+c+d

165828.42
552.76
say

3104

(ii)

M-181

12120.00

Rate per sqm = (a+b+c+d)/ 300


7.5

Remarks/
Input ref.

553.00

Facing elements of RCC


Unit = sqm
Taking output = 75 sqm
a)

b)

Labour
Mate

day

0.180

673.00

121.14

L-12

Mazdoor

day

3.000

377.00

1131.00

L-13

Mazdoor skilled

day

1.500

408.00

612.00

L-15

hour

6.000

334.00

2004.00

P&M-013

cu.m

13.500

#VALUE!

#VALUE! Item 12.8


(H)

tonnes

0.380

77756.00

29547.28 Item 13.6

Machinery
Light crane with lifting capacity upto 3 tonne

c)

Material
Pre-cast RCC M-35 facing elements of size as per
design and 18 cm thick for 75 sqm. (Refer Item 12.8
(H))
HYSD steel @ 5 kg / sqm (Refer Item 12.6)

Add 2 per cent of cost of facia pannels, for all necessary


temporary form work, scaffolding and provision of loops/lugs
for lifting of pannels and joining the reinforcing elements.
d)

Overhead charges @ 0.1 on (a+b)

e)

Contractor's profit @ 0.1 on (a+b+d)

#VALUE!

386.81
425.50

Cost for 75 sqm = a+b+c+d+e

#VALUE!

Rate per sqm = (a+b+c+d+e)/ 75

#VALUE!
say

Note

1.The specification and construction details to be adopted


shall be as per section 3100 of MoRTH Specification.
2.Drainage arrangement shall be made as per approved
design and drawings.
3.The quantity of filler media shall be calculated as per
approved design and specifications and shall be priced
separately.The rate for same to be adopted from chapter 15.
4.Excavation for foundation including foundation concrete
and groove in the foundation for seating of bottom most
facia panel and capping beam to be calculated as per
design and priced separately. The rates for excavation and
foundation concrete shall be taken from the chapter 12 & 13
in bridge section.

5.The earth fill to be retained is not included in this analysis.


The same is to be worked out and provided separately
complete as per clause 305.
6.For compaction of Earthwork, attention is invited to clause
3105.5 of MoRTH Specification.
7.Length of reinforcing strips will vary with the height of wall
and will be as per approved design and drawings.
8.The type of reinforcing elements to be adopted shall be as
per approved design and specifications.

Page 4 of 394

#VALUE!

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

9.The market rate for supply of reinforcing elements and


their accessories are to be ascertained from reputed firms in
the field of earth reinforcement.
10.The earth fill material shall be clean, free draining,
granular with high friction and low cohesion, non-corrosive,
coarse grained with not 10 per cent of particles passing 75
micron sieve, free of any deleterious matter, chlorides, salts,
acids, alkalies, mineral oil, fungus and microbes and shall be
of specified PH value.
11.Capping beam is to be priced separately as per approved
design. The rate for cement concrete shall be taken from the
chapter of sub-structure in bridge section.
12.The cost of reinforced earth retaining wall shall include
following:
(I) Excavation for foundation including backfilling.
(ii) Foundation concrete as per approved design.
(iii) Cost of facial pannels and their erection .
(iv) Cost of reinforcing elements including their fixing and
joining with the facial pannels.
(v) Drainage arrangement including filter media as per
approved design and drawings.
13. The compacted earth filling to be retained shall form part
of embankment.

Page 5 of 394

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

CHAPTER-8
TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES
Sr No
8.1

Ref. to
MoRTH
Spec.
408

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Cast in Situ Cement Concrete M20 Kerb


Construction of cement concrete kerb with top and bottom
width 115 and 165 mm respectively, 250 mm high in M 20
grade PCC on M-10 grade foundation 150 mm thick,
foundation having 50 mm projection beyond kerb stone, kerb
stone laid with kerb laying machine, foundation concrete laid
manually, all complete as per clause 408

A.

Unit = Running metre


Taking output = 360 metre
Using Concrete Mixer
Cement Concrete
Cement concrete of grade M20 = 12.60 cum
Cement concrete of grade M10 for base= 11.61 cum
Total Concrete = 24.21 cu.m
a) Labour
Mate
Mason
Mazdoor
b) Machinery
Kerb casting machine @ 60 metres/hour
Concrete mixer 0.48/0.28 cum capacity
Water tanker6 KL capacity
c) Material
Crushed stone aggregate 20 mm nominal size 59 per
cent
Coarse sand 30 per cent
Cement 11 per cent
Cost of water
d) Overhead charges @ 0.1 on (a+b+c)
e) Contractor's profit @ 0.1 on (a+b+c+d)
Cost for 360 meter = a+b+c+d+e
Rate per metre = (a+b+c+d+e)/360
Using Concrete Batching and Mixing Plant
Cement Concrete
Cement concrete of grade M20 = 12.60 cum
Cement concrete of grade M10 for base = 11.61 cum
Total Concrete = 24.21 cu.m
a) Labour
Mate
Mason
Mazdoor
b) Machinery
Kerb casting machine @ 60 metres/hour
Concrete batching and mixing plant @ 15 cum/hr.
Water tanker6 KL capacity
Tipper 5.5 cum capacity
c) Material
Crushed stone aggregate 20 mm nominal size 59 per
cent
Coarse sand 30 per cent
Cement 11 per cent
Cost of water
d) Overhead charges @ 0.1 on (a+b+c)
e) Contractor's profit @ 0.1 on (a+b+c+d)
Cost for 360 meter = a+b+c+d+e
Rate per metre = (a+b+c+d+e)/360

day
day
day

0.720
2.000
16.000

673.00
500.00
377.00

484.56
1000.00
6032.00

L-12
L-11
L-13

hour
hour
hour

6.000
12.000
5.000

291.00
218.00
233.00

1746.00
2616.00
1165.00

P&M-029
P&M-009
P&M-060

cum

21.790

942.00

20526.18

M-053

cum
tonne
KL

10.900
5.700
30.000

2400.00
5940.00
13.00

M-005
M-081
M-189

say

26160.00
33858.00
390.00
9397.77
10337.55
113713.07
315.87
316.00

day
day
day

0.120
1.000
2.000

673.00
500.00
377.00

80.76
500.00
754.00

L-12
L-11
L-13

hour
hour
hour
hour

6.000
1.600
5.000
6.000

291.00
1745.00
233.00
291.00

1746.00
2792.00
1165.00
1746.00

P&M-029
P&M-003
P&M-060
P&M-048

cum

21.790

942.00

20526.18

M-053

cum
tonne
KL

10.900
5.700
30.000

2400.00
5940.00
13.00

26160.00
33858.00
390.00
8971.79
9868.97
108558.71
301.55
302.00

M-004
M-081
M-189

say
8.2

408

Cast in Situ Cement Concrete M 20 Kerb with Channel


Construction of cement concrete kerb with channel with top
and bottom width 115 and 165 mm respectively, 250 mm
high in M 20 grade PCC on M10 grade foundation 150 mm
thick, kerb channel 300 mm wide, 50 mm thick in PCCM20
grade, sloped towards the kerb, kerb stone with channel laid
with kerb laying machine, foundation concrete laid manually,
all complete as per clause 408
Page 1 of 394

Sr No

Ref. to
MoRTH
Spec.

Description
A

Unit

Quantity

Rate Rs

Cost Rs

Using Concrete Mixer


Unit = Running metre
Taking output = 300 metre length
Cement Concrete
Cement concrete of grade M20= 17.48 cum
Cement concrete of grade M10 for base = 23.18 cum
Total Concrete = 40.66 cum
a)

b)

c)

Labour
Mate

day

0.720

673.00

484.56

Mason

day

2.000

500.00

1000.00

L-11

Mazdoor

day

16.000

377.00

6032.00

L-13

Machinery
Kerb casting machine @ 50 metres/hour for laying kerb
and channel
Concrete mixer 0.48/0.28

hour

6.000

291.00

1746.00

P&M-029

hour

16.000

218.00

3488.00

P&M-009

Water tanker6 KL capacity

hour

6.000

233.00

1398.00

P&M-060

Material
Crushed stone aggregate 20 mm nominal size 60 per
cent
Coarse sand 30 per cent

cum

36.590

942.00

34467.78

M-053

cum

18.300

2400.00

43920.00

M-005

Cement 10 per cent

tonne

9.010

5940.00

53519.40

M-081

KL

36.000

13.00

468.00

M-189

Cost of water
d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

16117.61
177293.73

Rate per metre = (a+b+c+d+e)/300

590.98
say

L-12

14652.37

Cost for 360 meter = a+b+c+d+e

8.2

Remarks/
Input ref.

591.00

Using Concrete Batching and Mixing Plant


Unit = Running metre
Taking output = 300 metre length
Cement Concrete
Cement concrete of grade M20= 17.48 cum
Cement concrete of grade M10 for base = 23.18 cum
Total Concrete = 40.66 cum
a)

b)

c)

Labour
Mate

day

0.120

673.00

80.76

Mason

day

1.000

500.00

500.00

L-11

Mazdoor

day

2.000

377.00

754.00

L-13

Machinery
Kerb casting machine @ 50 metres/hour for laying kerb
and channel
Concrete batching and mixing plant @ 15 cum/hr.

hour

6.000

291.00

1746.00

P&M-029

hour

2.700

1745.00

4711.50

P&M-003

Water tanker6 KL capacity

hour

6.000

233.00

1398.00

P&M-060

Tipper of 5.5 cum capacity

hour

6.000

291.00

1746.00

P&M-048

Material
Crushed stone aggregate 20 mm nominal size 60 per
cent
Coarse sand 30 per cent

cum

36.590

942.00

34467.78

M-053

cum

18.300

2400.00

43920.00

M-004

Cement 10 per cent

tonne

9.010

5940.00

53519.40

M-081

KL

36.000

13.00

468.00

M-189

Cost of water
d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

14331.14
15764.26

Cost for 300 meter = a+b+c+d+e

173406.84

Rate per metre = (a+b+c+d+e)/300

578.02
say

8.3

801

Printing New Letter and Figures of any Shade


Printing new letter and figures of any shade with synthetic
enamel paint black or any other approved colour to give an
even shade
Page 2 of 394

578.00

L-12

Sr No

Ref. to
MoRTH
Spec.

Description
(i)

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Hindi ( Matras commas and the like not to be measured


and paid for Half letter shall be counted as half )
Details for 100 letters of 16 cm height i.e. 1600 cm
Unit = per cm height per letter
a)

b)

Labour
Mate

day

0.120

673.00

80.76

L-12

Painter

day

2.000

396.00

792.00

L-18

Mazdoor

day

1.000

377.00

377.00

L-13

Litre

0.700

211.00

147.70

M-131

Material
Paint

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

139.75
153.72

Cost for 1600 cm = a+b+c+d

1690.93

Rate per cm height per letter = (a+b+c+ d)/1600

1.06
say

8.3

(ii)

1.10

English and Roman


Hyphens and the like not to be measured and paid for
Detail for 100 letters of 16 cm height. i.e.1600 cm
Unit = per cm height per letter
a)

b)

Labour
Mate

day

0.070

673.00

47.11

L-12

Painter Ist class

day

1.250

396.00

495.00

L-18

Mazdoor

day

0.500

377.00

188.50

L-13

Litre

0.500

211.00

105.50

M-131

Material
Paint

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

83.61
91.97

Cost for 1600 cm = a+b+c+d

1011.69

Rate per cm height per letter = (a+b+c +d)/1600


8.4

801

0.63
say

0.60

Retro-Reflectorised Traffic Signs


Providing and fixing of retro- reflectorised cautionary,
mandatory and informatory sign as per IRC :67 made of high
intensity grade sheeting vide clause 801.3, fixed over
aluminium sheeting, 1.5 mm thick supported on a mild steel
angle iron post 75 mm x 75 mm x 6 mm firmly fixed to the
ground by means of properly designed foundation with M15
grade cement concrete 45 cm x 45 cm x 60 cm, 60 cm
below ground level as per approved drawing
Unit = Each
Taking output = one traffic sign

a)

b)

i)

Excavation for foundation

cum

0.216

391.00

84.46

ii)

Cement concrete M15 grade

cum

0.120

5820.00

698.40

iii)

Painting angle iron post two coats

sqm

0.430

68.00

29.24

Item No.
3.13
Item 12.8
(A)
Item 8.9

Mate

day

0.010

673.00

6.73

L-12

Mazdoor

day

0.250

377.00

94.25

L-13

kg

19.000

44.10

837.90

M-179 /
1000

Labour (For fixing at site)

Material
Mild steel angle iron 75 x 75 x 6 mm

(i)

Aluminium sheeting fixed with encapsulated lens type


reflective sheeting of size including lettering and signs as
applicable
Add 2 per cent of cost of angle iron towards cost of drilling
holes, nuts, bolts etc.
90 cm equilateral triangle

sqm

0.350 input

#VALUE!

M-061

sqm

0.156 input

#VALUE!

M-061

or
( ii )

60 cm equilateral triangle
Page 3 of 394

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

or
( iii )

60 cm circular

sqm

0.283 input

#VALUE!

M-061

sqm

0.480 input

#VALUE!

M-061

sqm

0.270 input

#VALUE!

M-061

sqm

0.360 input

#VALUE!

M-061

sqm

0.672 input

#VALUE!

M-061

hour

0.010

or
( iv )

80 mm x 60 mm rectangular
or

(v)

60 cm x 45 cm rectangular
or

(vi )

60 cm x 60 cm square
or

( vii )

90 cm high octagon
c)

Machinery
Tractor-trolley

(i)

340.00

d)

Overhead charges @ 0.1 on (a+b+c)

#VALUE!

e)

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!

Rate per traffic sign = ( i+ii+iii+a+b+c+d+e)

#VALUE!
say

( ii )

d)

Overhead charges @ 0.1 on (a+b+c)

#VALUE!

e)

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!
#VALUE!
say

d)

Overhead charges @ 0.1 on (a+b+c)

#VALUE!

e)

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!
#VALUE!
say

d)

Overhead charges @ 0.1 on (a+b+c)

#VALUE!

e)

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!
#VALUE!
say

d)

Overhead charges @ 0.1 on (a+b+c)

#VALUE!

e)

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!
#VALUE!
say

d)

Overhead charges @ 0.1 on (a+b+c)

#VALUE!

e)

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!
#VALUE!
say

d)

Overhead charges @ 0.1 on (a+b+c)

#VALUE!

e)

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!
#VALUE!
say

1.Any one area of aluminium sheeting given at (i) to (vii) may


be adopted as per site requirement and in accordance with
IRC : 67
2.Rate for excavation, cement concrete M-15 and painting
may be taken from respective chapters
3. The depth of foundation and quantity of cement concrete
in the foundation are indicative. These may be increased for
areas having higher wind velocities like in coastal areas.
This is applicable to all road signs and directions boards.

8.5

801

#VALUE!

90 cm high octagon

Rate per traffic sign = ( i+ii+iii+a+b+c+d+e)

Note

#VALUE!

60 cm x 60 cm square

Rate per traffic sign = ( i+ii+iii+a+b+c+d+e)


( vii )

#VALUE!

60 cm x 45 cm rectangular

Rate per traffic sign = ( i+ii+iii+a+b+c+d+e)


(vi )

#VALUE!

80 mm x 60 mm rectangular

Rate per traffic sign = ( i+ii+iii+a+b+c+d+e)


(v)

#VALUE!

60 cm circular

Rate per traffic sign = ( i+ii+iii+a+b+c+d+e)


( iv )

#VALUE!

60 cm equilateral triangle

Rate per traffic sign = ( i+ii+iii+a+b+c+d+e)


( iii )

3.40

90 cm equilateral triangle

Direction and Place Identification Signs upto 0.9 sqm


Size Board.
Page 4 of 394

#VALUE!

P&M-053

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Providing and erecting direction and place identification


retro-reflectorised sign as per IRC:67 made of high intensity
grade sheeting vide clause 801.3, fixed over aluminium
sheeting, 2 mm thick with area not exceeding 0.9 sqm
supported on a mild steel single angle iron post 75 x 75 x 6
mm firmly fixed to the ground by means of properly designed
foundation with M15 grade cement concrete 45 x 45 x 60
cm, 60 cm below ground level as per approved drawing
Unit = sqm
Taking output = 0.9 sqm

a)

i) Excavation for foundation

cum

0.216

391.00

84.46

ii) Cement concrete M15 grade

cum

0.120

5820.00

698.40

iii) Painting angle iron post two coats

sqm

0.430

68.00

29.24

Item No.
3.13
Item 12.8
(A)
Item 8.9

Mate

day

0.010

673.00

6.73

L-12

Mazdoor

day

0.200

377.00

75.40

L-13

kg

19.000

44.10

837.90

M-179 /
1000
M-061

Labour (For fixing at site)

b)

Material
Mild steel angle iron 75 mm x 75 mm x 6 mm,2.85
metres long
Aluminium sheeting fixed with encapsulated lens type
reflective sheeting of size 0.9 sqm
Add 2 per cent of cost of materials for drilling holes, nuts,
bolts, fabrication etc.
c) Machinery
Tractor-trolley

sqm

0.900 input

hour

0.020

#VALUE!

340.00

Overhead charges @ 0.1 on (a+b+c)

#VALUE!

e)

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!

Cost for 0.9 sqm =I+ii+ii+ a+b+c+d+e


Rate per sqm (for sign having area upto 0.9 sqm) =
(I+ii+iii+a+b+c+d+e)/0.90

Note

8.6

801

6.80

d)

P&M-053

#VALUE!
#VALUE!
say

#VALUE!

I) Lettering and arrow marks on sign board to be provided


separately as per actual requirement. Rates for these items
have been analysed separately
ii) Rate for excavation, cement concrete M-15 and painting
may be taken from respective chapters
Direction and Place Identification Signs with size more
than 0.9 sqm size Board.
Providing and erecting direction and place identification
retro- reflectorised sign as per IRC :67 made of high
intensity grade sheeting vide clause 801.3, fixed over
aluminium sheeting, 2 mm thick with area exceeding 0.9
sqm supported on a mild steel angle iron post 75 mm x 75
mm x 6 mm, 2 Nos. firmly fixed to the ground by means of
properly designed foundation with M 15 grade cement
concrete45 cm x 45 cm x 60 cm, 60 cm below ground level
as per approved drawing
Unit = sqm
Taking output = 1.50 sqm

a)

b)

i)

Excavation for foundation

cum

0.430

391.00

168.13

ii)

Cement concrete M15 grade

cum

0.240

5820.00

1396.80

iii)

Painting angle iron post 2 coats

sqm

0.860

68.00

58.48

Item No.
3.13
Item 12.8
(A)
Item 8.9

Mate

day

0.010

673.00

6.73

L-12

Mazdoor

day

0.300

377.00

113.10

L-13

kg

38.000

44.10

1675.80

M-179 /
1000
M-061

Labour (For fixing at site)

Material
Mild steel angle iron 75 mm x 75 mm x 6 mm, 2.85
metres long, 2 nos
Aluminium sheeting fixed with encapsulated lens type
reflective sheeting
Page 5 of 394

sqm

1.500 input

#VALUE!

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Add 2 per cent of cost of materials for drilling holes, nuts,


bolts, fabrication etc.
c) Machinery
Tractor-trolley

hour

0.020

340.00

Overhead charges @ 0.1 on (a+b+c)

#VALUE!

e)

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!

Cost for 1.5 sqm =I+ii+ii+ a+b+c+d+e


Rate per sqm ( for sign having area more than 0.9 sqm)
= ( i+ii+iii+a+b+c+d+e)/1.50

8.7

802

P&M-053

#VALUE!
#VALUE!
say

Note

6.80

d)

#VALUE!

i) Lettering and arrow marks on sign board to be provided


separately as per actual requirement. Rates for these items
have been analysed separately
ii) Rate for excavation, cement concrete M-15 and painting
may be taken from respective chapters
Overhead Signs
Providing and erecting overhead signs with a corrosion
resistant 2mm thick aluminium alloy sheet reflectorised with
high intensity retro-reflective sheeting of encapsulated lense
type with vertical and lateral clearance given in clause 802.2
and 802.3 and installed as per clause 802.7 over a designed
support system of aluminium alloy or galvanised steel
trestles and trusses of sections and type as per structural
design requirements and approved plans

Truss and Vertical Support


Unit = tonne
Taking output = 1 tonne
a)

Labour
Mate

day

0.240

673.00

161.52

L-12

Blacksmith

day

2.000

500.00

1000.00

L-02

Mazdoor including for handling & fixing at site.

day

4.000

377.00

1508.00

L-13

tonne

1.050

57960.00

60858.00

M-060

b)

Material
Aluminium alloy/galvanised steel including 5 per cent
wastage
Add 1 per cent on cost of material for nuts, bolts and drilling
and welding consumables
Add 15 per cent on cost of material for fabrication of trusses
as per approved design
c) Machinery

608.58
9219.99

Crane 3 tonne capacity

hour

3.000

334.00

1002.00

P&M-013

Truck

hour

0.500

291.00

145.50

P&M-057

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

7450.36
8195.39

Rate per tonne = (a+b+c+d+e)


8.7

90149.34
say

90149.00

Aluminium Alloy Plate for Over Head Sign


Unit = sqm
Taking output = 1 sqm
a)

Labour
Mate

day

0.020

673.00

13.46

L-12

Blacksmith

day

0.100

500.00

50.00

L-02

Mazdoor

day

0.150

377.00

56.55

L-13

sqm

1.000

926.00

926.00

M-059

b)

Material
Aluminium alloy plate,2 mm thick, fixed with high
intensity grade sheeting vide clause 801.3
Miscellaneous
Add 1 per cent of cost of labour for lifting arrangement, like
ladders, pulleys, ropes etc
c) Overhead charges @ 0.1 on (a+b)
d)

Contractor's profit @ 0.1 on (a+b+c)

Rate per sqm = (a+b+c+d)

1.20
104.72
115.19
1267.12

Page 6 of 394

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs
say

Note

Remarks/
Input ref.

1267.00

1. The cost of excavation and foundation concrete for fixing


of vertical support system to be worked out separately as
per the approved drawing/design and to be included in the
estimate.
2. Lettering and arrow marks on sign board to be provided
separately as per actual requirement. Rates for these items
have been included separately in this chapter.

8.8

803

Painting Two Coats on New Concrete Surfaces


Painting two coats after filling the surface with synthetic
enamel paint in all shades on new plastered concrete
surfaces
Unit = sqm
Taking output = 40 sqm
a)

b)

Labour
Mate

day

0.120

673.00

80.76

L-12

day

2.000

396.00

792.00

L-18

Mazdoor

day

1.000

377.00

377.00

L-13

Litre

6.000

211.00

1266.00

M-132

Material
Paint conforming to requirement of clause 803.3.
Add for scaffolding @ 1 per cent of labour cost where
required
Add @ 5 per cent cost of labour and materials to
prepare the surface by filling minuts roughness on the
surface and priming the surface before laying 2 coats
of painting.

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

12.66
125.79

265.42
291.96

Cost for 40 sqm = a+b+c+d

3211.59

Rate per sqm = (a+b+c+d)/40

80.29
say

8.9

803

80.00

Painting on Steel Surfaces


Providing and applying two coats of ready mix paint of
approved brand on steel surface after through cleaning of
surface to give an even shade
Unit = sqm
Taking output = 10 sqm
a)

b)

Labour
Mate

day

0.030

673.00

20.19

L-12

Painter

day

0.450

396.00

178.20

L-18

Mazdoor

day

0.250

377.00

94.25

L-13

Litre

1.250

211.00

263.75

M-131

Material
Paint ready mixed approved brand.
Add @ 1 per cent on cost of material for scaffolding

2.64

Add @ 5 per cent cost of labour and materials to


prepare the surface by filling minuts roughness on the
surface and priming the surface before laying 2 coats
of painting.

27.82

c)

Overhead charges @ 0.1 on (a+b)

58.68

d)

Contractor's profit @ 0.1 on (a+b+c)

64.55

Cost for 10 sqm = a+b+c+d

710.08

Rate per sqm= (a+b+c+d)/10


8.10

803

71.01
say

71.00

673.00

20.19

Painting on Wood Surfaces


Providing and applying two coats of ready mix paint of
approved brand on wood surface after thorough cleaning of
surface to give an even shade
Unit = sqm
Taking output = 10 sqm
a)

Labour
Mate

day
Page 7 of 394

0.030

L-12

Sr No

Ref. to
MoRTH
Spec.

Description

b)

Unit

Quantity

Rate Rs

Cost Rs

Painter

day

0.500

396.00

198.00

L-18

Mazdoor

day

0.200

377.00

75.40

L-13

Litre

1.500

211.00

316.50

M-131

Material
Paint ready mixed of approved brand.
Add @ 1 per cent on cost of material for scaffolding

3.17

Add @ 5 per cent cost of labour and materials to


prepare the surface by filling minuts roughness on the
surface and priming the surface before laying 2 coats
of painting.

30.50

c)

Overhead charges @ 0.1 on (a+b)

64.38

d)

Contractor's profit @ 0.1 on (a+b+c)

70.81

Cost for 10 sqm = a+b+c+d

778.95

Rate per sqm = (a+b+c+d)/10

77.89
say

8.11

Remarks/
Input ref.

78.00

Painting Lines, Dashes, Arrows etc on Roads in Two


Coats on New Work

803

Painting lines, dashes, arrows etc on roads in two coats on


new work with ready mixed road marking paint conforming to
IS:164 on bituminous surface, including cleaning the surface
of all dirt, dust and other foreign matter, demarcation at site
and traffic control
(i)

Over 10 cm in width
Unit = sqm
Taking output = 10 sqm
a)

b)

Labour
Mate

day

0.090

673.00

60.57

L-12

Painter

day

0.550

396.00

217.80

L-18

Mazdoor

day

1.550

377.00

584.35

L-13

Litre

1.480

211.00

312.28

M-132

Material
Road marking Paint as per IS :164

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

117.50
129.25

Cost for 10 sqm = a+b+c+d

1421.75

Rate per sqm= (a+b+c+d)/10

142.18
say

8.11

(ii)

142.00

Up to 10 cm in width
Unit = sqm
Taking output = 10 sqm
a)

b)

Labour
Mate

day

0.070

673.00

47.11

L-12

Painter

day

0.350

396.00

138.60

L-18

Mazdoor

day

1.350

377.00

508.95

L-13

Litre

1.480

211.00

312.28

M-132

Material
Road marking paint

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

100.69
110.76

Cost for 10 sqm = a+b+c+d

1218.40

Rate per sqm = (a+b+c+d)/10

121.84
say

8.12

Painting Lines, Dashes, Arrows etc on Roads in Two


Coats on Old Work

803

Painting lines, dashes, arrows etc on roads in two coats on


old work with ready mixed road marking paint conforming to
IS: 164 on bituminous surface, including cleaning the
surface of all dirt, dust and other foreign matter, demarcation
at site and traffic control
(i)

Over 10 cm in width
Unit = sqm
Taking output = 10 sqm
a)

Labour
Page 8 of 394

122.00

Sr No

Ref. to
MoRTH
Spec.

Description

b)

Unit

Quantity

Rate Rs

Cost Rs

Mate

day

0.060

673.00

40.38

L-12

Painter Ist class

day

0.300

396.00

118.80

L-18

Mazdoor

day

1.250

377.00

471.25

L-13

Litre

0.900

211.00

189.90

M-132

Material
Road marking paint

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

82.03
90.24

Cost for 10 sqm = a+b+c+d

992.60

Rate per sqm = (a+b+c+d)/10


8.12

(ii)

Remarks/
Input ref.

99.26
say

99.00

Up to 10 cm in width
Unit = sqm
Taking output = 10 sqm
a)

b)

Labour
Mate

day

0.070

673.00

47.11

L-12

Painter Ist class

day

0.350

396.00

138.60

L-18

Mazdoor

day

1.350

377.00

508.95

L-13

Litre

0.900

211.00

189.90

M-132

Material
Road marking Paint

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

88.46
97.30

Cost for 10 sqm= a+b+c+d

1070.32

Rate per sqm = (a+b+c+d)/10

107.03
say

8.13

107.00

Road Marking with Hot Applied Thermoplastic


Compound with Reflectorising Glass Beads on
Bituminous Surface

803

Providing and laying of hot applied thermoplastic compound


2.5 mm thick including reflectorising glass beads @ 250 gms
per sqm area, thickness of 2.5 mm is exclusive of surface
applied glass beads as per IRC:35 .The finished surface to
be level, uniform and free from streaks and holes.
Unit = sqm
Taking output = 600 sqm
a)

b)

c)

Labour
Mate

day

0.030

673.00

20.19

L-12

Mazdoor

day

0.750

377.00

282.75

L-13

Road marking machine @ 60 sqm per hour

hour

10.000

87.00

870.00

P&M-043

Tractor-trolley

hour

0.500

340.00

170.00

P&M-053

Litre

1500.000

137.00

205500.00

M-118

kg

150.000

61.00

9150.00

M-152

Machinery

Material
Hot applied thermoplastic compound
Reflectorising glass beads

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

21599.29
23759.22

Cost for 600 sqm = a+b+c+d+e

261351.46

Rate per sqm = a+b+c+d+e)/600

435.59
say

Note

8.14

1. A sealing primer may be applied in advance on cement


concrete pavement to ensure proper bonding. Any laitance
and/or curing compound to be removed where paint is
required to be applied on concrete surface.
2.Cost of painter is already included in hire charges of road
marking machine.
Kilometre Stone

804

Reinforced cement concrete M15grade kilometre stone of


standard design as per IRC:8-1980, fixing in position
including painting and printing etc
(i)

5th kilometre stone (precast)


Page 9 of 394

436.00

Sr No

Ref. to
MoRTH
Spec.

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Description

Unit

a)

M-15 grade of concrete

cum

2.350

5820.00

b)

Steel reinforcement @ 5 kg per sqm

kg

22.080

77.76

c)

Excavation in soil for foundation

cum

1.680

391.00

sqm
per cm per
letter

9.850

76.00

1800.000

0.60

1080.00

Item 8.3

L-12

Unit = Nos.
Taking output = 6 Nos.

d) Painting two coats on concrete surface


e) Lettering on km post (average 30 letters of 10
cm height each)
Transportation and fixing
f)

g)

Mate

day

0.260

673.00

174.98

Mason

day

0.600

500.00

300.00

L-11

Mazdoor including loading/unloading

day

6.000

377.00

2262.00

L-13

hour

6.000

340.00

2040.00

P&M-053

Machinery

h)

Overhead charges @ 0.1 on (f+g)

i)

Contractor's profit @ 0.1 on (f+g+h)

Cost for 6 Nos. 5th km stone = a+b+c+ d+e +f+g+h +i


Rate for each 5th km stone = (a+b+c+ d+e +f+g+h +i )
6
(ii)

Item 12.8
(A)
1716.85 Item 13.6 /
1000
656.88 Item No.
3.13
748.60 Item 8.8

Labour

Tractor-trolley

8.14

13677.00

477.70
525.47
23659.48
/

3943.25
say

3943.00

21941.40

Ordinary kilometer stone (precast)


Unit = Nos.
Taking output = 14 Nos.
a)

M-15 grade of concrete

b)

Steel reinforcement @ 5 kg per sqm

c)

Excavation in soil for foundation

d) Painting two coats on concrete surface


e) Lettering on km post ( average 12 letters of 10
cm height each)
Transportation and fixing
f)

g)

3.770

5820.00

kg

26.320

77.76

cum

2.770

391.00

sqm
per cm per
letter

11.410

76.00

1680.000

0.60

1008.00

Item 8.3

L-12

Mate

day

0.320

673.00

215.36

Mason

day

1.000

500.00

500.00

L-11

Mazdoor

day

7.000

377.00

2639.00

L-13

hour

6.000

340.00

2040.00

P&M-053

Machinery
Overhead charges @ 0.1 on (f+g)

539.44

i) Contractor's profit @ 0.1 on (f+g+h)


Cost for 14 Nos. ordinary km stone = (a+b+ c +d+e+f+g+h+i)

593.38
33473.34

Rate for each ordinary km stone = (a+b+ c


+d+e+f+g+h+j) /14
8.14

(iii)

Item 12.8
(A)
2046.54 Item 13.6 /
1000
1083.07 Item No.
3.13
867.16 Item 8.8

Labour

Tractor-trolley
h)

cum

2390.95
say

2391.00

9195.60

Hectometer stone (precast)


Unit = Nos.
Taking output = 33 Nos.
a)

M-15 grade of concrete

b)

Steel reinforcement @ 5 kg per sqm

c)

Excavation in soil for foundation

cum

1.580

5820.00

kg

66.000

77.76

cum

1.390

391.00

6.270

76.00

330.000

0.60

d) Painting two coats on concrete surface


sqm
e) Lettering on km post (average 1 letter of 10 cm per cm per
height each)
letter
Page 10 of 394

Item 12.8
(A)
5131.90 Item 13.6 /
1000
543.49 Item No.
3.13
476.52 Item 8.8
198.00

Item 8.3

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Transportation and fixing


f)

g)

Labour
Mate

day

0.340

673.00

228.82

Mason

day

1.500

500.00

750.00

L-11

Mazdoor

day

7.000

377.00

2639.00

L-13

hour

6.000

340.00

2040.00

P&M-053

Machinery
Tractor-trolley

h)

Overhead charges @ 0.1 on (f+g)

565.78

i) Contractor's profit @ 0.1 on (f+g+h)


Cost for 33 Nos. Hectometer stone = (a+b +c +d+e+f+
g+h+i)
Rate for each Hectometer stone = (a+b +c +d+e+f+
g+h+i) 33

622.36
22391.47
678.53
say

Note
8.15

805

L-12

679.00

The rate for excavation, cement concrete, steel


reinforcement, painting and lettering may be taken from
respective chapters.
Road Delineators
Supplying and installation of delineators (road way
indicators, hazard markers, object markers), 80-100 cm high
above ground level, painted black and white in 15 cm wide
strips, fitted with 80 x 100 mm rectangular or 75 mm dia
circular reflectorised panels at the top, buried or pressed into
the ground and conforming toIRC-79 and the drawings.
Unit = Each
Taking output= 30 Nos.
a)

Labour
Mate

day

0.040

673.00

26.92

L-12

Mazdoor for fixing

day

1.000

377.00

377.00

L-13

#VALUE!

M-091

b)

Material
Cost of approved type of delineators from ISI certified
firm as per the standard drawing given in IRC - 79
Add 10 per cent cost of material for installation

each

30.000 input

#VALUE!

c)

Overhead charges @ 0.1 on (a+b)

#VALUE!

d)

Contractor's profit @ 0.1 on (a+b+c)

#VALUE!

Cost for 30 Nos. delineators = (a+b+ c+d)

#VALUE!

Rate per delineators = (a+b+c+d) /30

Note

8.16

806

#VALUE!
say

#VALUE!

7275.00

In case of soft ground, a proper foundation may be provided


as per approved design. In case foundation is required to be
provided, the items of excavation and foundation concrete
are required to be measured and paid separately.
Boundary pillar
Reinforced cement concrete M15 grade boundary pillars of
standard design as per IRC:25-1967, fixed in position
including finishing and lettering but excluding painting
Unit = Each
Taking output = 57 Nos.
a)

M-15 grade of the boundary stone

b)

Steel reinforcement

c)

Excavation in soil

d)

Lettering, each 10 cm high

cum

1.250

5820.00

kg

79.800

77.76

cum

10.720

391.00

per letter
per cm high

2280.000

0.60

Item 12.8
(A)
6204.93 Item 13.6 /
1000
4191.52 Item No.
3.13
1368.00 Item 8.3

Transportation and fixing


e)

Labour
Mate

day

0.570

673.00

383.61

L-12

Mazdoor

day

14.250

377.00

5372.25

L-13

Page 11 of 394

Sr No

Ref. to
MoRTH
Spec.

Description
f)

Unit

Cost Rs

hour

6.000

340.00

2040.00

P&M-053

cum

11.970

175.00

2094.75

M-008

Overhead charges @ 0.1 on (e+f+g)

989.06

i) Contractor's profit @ 0.1 on (e+f+g+h)


Cost for 57 Nos. boundary pillar = (a+b +c+d +e+ f+g+h+i )

1087.97
31007.09

Rate for each boundary pillar = (a+b+c+d+e+ f+g+h+i)/57

543.98
say

Note

8.17

807

Remarks/
Input ref.

Material
Stone spall

h)

Rate Rs

Machinery
Tractor-trolley

g)

Quantity

544.00

In case of soft ground, a proper foundation may be provided


as per approved design. In case foundation is required to be
provided, the items of excavation and foundation concrete
are required to be measured and paid separately.
G.I Barbed Wire Fencing 1.2 Metre High
Providing and fixing 1.2 metres high GI barbed wire fencing
with 1.8 m angle iron posts 40 mm x 40 mm x 6 mm placed
every 3 metres center to center founded in M15 grade
cement concrete, 0.6 metre below ground level, every 15th
post, last but one end post and corner post shall be strutted
on both sides and end post on one side only and provided
with 9 horizontal lines and 2 diagonals interwoven with
horizontal wires, fixed with GI staples, turn buckles etc
complete as per clause 807
Unit = per running metre
Taking output = 30 metres
a)

Labour
Mate

day

0.090

673.00

60.57

L-12

Blacksmith

day

0.250

500.00

125.00

L-02

Mazdoor

day

2.000

377.00

754.00

L-13

kg

31.420

49.68

1560.95

M-063

kg

80.500

44.10

3550.05

M-179 /
1000

b)

Material
Barbed wire 335 metres length @ 9.38 kg per 100
metres
MS angle iron 40 mm x 40mm x 6 mm, 23 metres in
length @ 3.5 kg per metre
Add for GI staple binding wire, drilling holes etc. @ 2 per
cent of the cost of material
c) Painting
Applying two coats of painting on exposed surface of
angle iron posts ( Rate as per item no. 8.9)
d) Overhead charges @ 0.1 on (a+b)
e)

102.22

sqm

2.110

68.00

615.28

Contractor's profit @ 0.1 on (a+b+d)

676.81

Cost for 30 metres fencing = a+b+c+d+e

7588.35

Rate per metre = (a+b+c+d+e)/30

252.95
say

Note
8.18

807

Cost of excavation for foundation and foundation concrete to


be added separately in the cost estimate as per approved
design. The rate for these items may be taken from
respective chapters.
G.I Barbed Wire Fencing 1.8 Metre High
Providing and fixing 1.8 metres high GI barbed wire fencing
with 2.4 m angle iron posts 50 mm x 50 mm x 6 mm placed
every 3 metres center to center founded in M15 grade
cement concrete, 0.6 metre below ground level, every 15th
post, last but one end post and corner post shall be strutted
on both sides and end post on one side only and provided
with 12 horizontal lines and 2 diagonals interwoven with
horizontal wires, fixed with GI staples, turn buckles etc
complete as per clause 807
Unit = per running metre
Taking output = 30 metres
a)

143.48

Labour
Page 12 of 394

253.00

Item 8.9

Sr No

Ref. to
MoRTH
Spec.

Description

b)

Unit

Rate Rs

Cost Rs

day

0.120

673.00

80.76

L-12

Blacksmith

day

0.400

500.00

200.00

L-02

Mazdoor

day

2.500

377.00

942.50

L-13

kg

40.150

49.68

1994.65

M-063

kg

152.000

44.10

6703.20

M-179 /
1000

d)
e)

Contractor's profit @ 0.1 on (a+b+d)

173.96

sqm

3.960

68.00

1110.46
416.14
say

Suggest
ive

Item 8.9

12484.31

Rate per metre fencing = (a+b+c +d+e)/30

8.19

269.28
1009.51

Cost for 30 metres fencing = a+b+c+d+e

Note

Remarks/
Input ref.

Mate

Material
Barbed wire 428 metres length @ 9.38 kg per 100
metres
MS angle iron 50 mm x 50 mm x 6 mm,33.8 metres in
length @ 4.5 kg per metre
Add for GI staple, binding wire, drilling holes etc. @ 2
per cent of the cost of material
Painting
Applying two coats of painting on exposed surface of
angle iron posts
Overhead charges @ 0.1 on (a+b)

c)

Quantity

416.00

Cost of excavation for foundation and foundation concrete to


be added separately in the cost estimate as per approved
design. The rate for these items may be taken from
respective chapters.
Fencing With Welded Steel Wire Fabric 75 mm x 50 mm
Providing 1.20 metre high fencing with angle iron posts 50
mm x 50 mm x 6 mm at 3 metre center to center with 0.40
metre embedded in M15 grade cement concrete, corner, end
and every 10th post to be strutted, provided with welded
steel wire fabric of 75 mm x 50 mm mesh or 75 mm x 25 mm
mesh and fixed to iron posts by flat iron 50 x 5 mm and bolts
etc. complete in all respects.
Unit = Running metre
Taking output = 30 m
a)

b)

Labour
Mate

day

0.120

673.00

80.76

L-12

Welder

day

1.000

500.00

500.00

L-02

Mazdoor

day

2.000

377.00

754.00

L-13

i) Angle iron for posts 50 x 50 x 6 mm

kg

106.000

44.10

4674.60

ii) Runner flat 50 x 5 mm

kg

26.000

44.10

1146.60

M-179 /
1000
M-179 /
1000
M-191

Material

iii) Welded steel wire fabric 75x50 mm mesh @ 4


kg/sqm,4 x 30 x 1.2 + 5 per cent wastage
OR
Welded steel wire fabric 75 x 25 mm mesh @ 7.75
kg/sqm, 7.75 x 30 x 1.2 + 5 per cent wastage
Add 2.5 per cent of cost of material for drilling holes in
angles, flats, splitting angle at bottom, nuts and bolts and
welded consumables
c)

151.000 input

kg

293.000

#VALUE!

Machinery
Tractor-trolley

d)

kg

hour

0.100

340.00

sqm

8.000

68.00

Painting two coats including priming

P&M-053

544.00

Item 8.9

e)

Overhead charges @ 0.1 on (a+b+c)

#VALUE!

f)

Contractor's profit @ 0.1 on (a+b+c+e)

#VALUE!

Cost for 30 metre = a+b+c+d+e+f

#VALUE!

Rate per metre = (a+b+c+d+e+f)/30

#VALUE!
say

Note

34.00

Painting

i) Adopt any one type of welded steel wire fabric 75 x 50 mm


or 75 x 25 mm as per approved design.

Page 13 of 394

#VALUE!

Sr No

8.20

Ref. to
MoRTH
Spec.

808

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

ii) The item of excavation and cement concrete in foundation


shall be measured and paid separately
Tubular Steel Railing on Medium Weight Steel Channel
( ISMC series) 100 mm x 50 mm
Providing, fixing and erecting 50 mm dia steel pipe railing in
3 rows duly painted on medium weight steel channels (ISMC
series) 100 mm x 50 mm, 1.2 metres high above ground, 2
m centre to centre, complete as per approved drawings
Unit = Running metre
Taking output = 10metres
i) Excavation for foundation (6 Nos)6 x 0.6 x 0.6 x
0.6
ii) Foundation concrete M-15 grade PCC 6 x 0.6 x
0.6 x 0.3
iii) Painting of pipe
iv) Painting of channel section 6 nos,1.8 metres
each 0.2 x 1.8 x 6 = 2.16
a) Labour (For fixing at site)

b)

cum

1.296

391.00

506.74

cum

0.648

5820.00

3771.36

sqm

4.710

68.00

320.28

Item No.
3.13
Item 12.8
(A)
Item 8.9

sqm

2.160

68.00

146.88

Item 8.9

Mate

day

0.010

673.00

6.73

L-12

Mazdoor

day

0.250

377.00

94.25

L-13

Plumber

day

0.010

500.00

5.00

L-02

metre

30.000

245.00

7350.00

M-175

99.360

44.10

4381.78

M-179 /
1000

Material

Steel pipe 50 mm external dia as per IS:1239


Medium weight steel channel (ISMC series) 100 mm x
50 mm,10.8 metres length @ 9.2 kg per metre
Add for drilling holes @ 2 per cent of cost of channels
c)

kg

87.64

Machinery
Tractor-trolley

hour

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

0.040

340.00

20185.08

Rate per metre = (i+ii+iii+iv+a+b+c+d+e)/10

808

P&M-053

1833.77

Cost for 10 metre =i+ii+iii+iv+ a+b+c+d+e

8.21

13.60
1667.06

2018.51
say

2019.00

506.74

Tubular Steel Railing on Precast RCC Posts, 1.2 m High


Above Ground Level
Providing, fencing and erecting 50 mm dia painted steel pipe
railing in 3 rows on precast M20 grade RCC vertical posts1.8
metres high (1.2 m above GL) with 3 holes 50 mm dia for
pipe, fixed 2 metres centre to, complete as per approved
drawing
Unit = Running metre
Taking output = 10metres
i) Excavation for foundation (6 Nos)6 x 0.6 x 0.6 x
0.6
ii) Foundation concrete M - 15 grade PCC 6 x 0.6 x
0.6 x 0.3
iii) RCC M - 20 for pre cast posts 6 nos of 1.8
metres each
iv) Painting of pipe
a)

b)

cum

1.296

391.00

cum

0.648

5820.00

cum

0.320

#VALUE!

sqm

4.710

68.00

Mate

day

0.014

673.00

9.42

L-12

Mazdoor

day

0.350

377.00

131.95

L-13

Plumber

day

0.010

500.00

5.00

L-02

metre

30.000

245.00

7350.00

hour

0.250

340.00

Labour

Material
Steel pipe 50 mm dia as per IS:1239

c)

Item No.
3.13
3771.36 Item 12.8
(A)
#VALUE!
Item
14.1(A)
320.28 Item 8.9

M-175

Machinery
Tractor-trolley

85.00

d)

Overhead charges @ 0.1 on (a+b+c)

758.14

e)

Contractor's profit @ 0.1 on (a+b+c+d)

833.95

Cost for 10 metre =i+ii+iii+iv+ a+b+c+d+e

#VALUE!

Rate per metre = (i+ii+iii+iv+a+b+c+d+e)/10

#VALUE!

Page 14 of 394

P&M-053

Sr No

Ref. to
MoRTH
Spec.

8.22

809

Description

Unit

Quantity

Rate Rs

Cost Rs
say

#VALUE!

#VALUE!

Remarks/
Input ref.

Reinforced Cement Concrete Crash Barrier


Provision of an Reinforced cement concrete crash barrier at
the edges of the road, approaches to bridge structures and
medians, constructed with M-20 grade concrete with HYSD
reinforcement conforming to IRC:21 and dowel bars 25 mm
dia, 450 mm long at expansion joints filled with pre-moulded
asphalt filler board, keyed to the structure on which it is built
and installed as per design given in the enclosure to MOST
circular No. RW/NH - 33022/1/94-DO III dated 24 June 1994
as per dimensions in the approved drawing and at locations
directed by the Engineer, all as specified
Unit = Linear metre
Taking output = 10 m
(i)

a)

M 20 grade concrete
cum

3.000

#VALUE!

Mate

day

0.040

673.00

26.92

L-12

Mazdoor

day

1.000

377.00

377.00

L-13

HYSD steel reinforcement including dowel bars

tonne

0.280

52100.00

14588.00

M-082

Pre-moulded asphalt filler board

sqm

0.320 input

#VALUE!

M-144

M 20 grade concrete
b)

c)

Labour

Material

d)

Overhead charges @ 0.1 on (b+c)

#VALUE!

e)

Contractor's profit @ 0.1 on (b+c+d)

#VALUE!

Cost for 10 metre = a+b+c+d+e

#VALUE!

Rate per metre = (a+b+c+d+e)/10

#VALUE!
say

Note

8.23

810
A

Item
14.1(A)

#VALUE!

i) Excavation and backfilling are incidental to work and not to


be measured separately.
ii) Rate for RCC M 20 may be taken from chapter on super
structure.
Metal Beam Crash Barrier
Type - A, "W" : Metal Beam Crash Barrier
Providing and erecting a "W" metal beam crash barrier
comprising of 3 mm thick corrugated sheet metal beam rail,
70 cm above road/ground level, fixed on ISMC series
channel vertical post, 150 x 75 x 5 mm spaced 2 m centre to
centre, 1.8 m high, 1.1 m below ground/road level, all steel
parts and fitments to be galvanised by hot dip process, all
fittings to conform to IS:1367 and IS:1364, metal beam rail to
be fixed on the vertical post with a spacer of channel section
150 x 75 x 5 mm, 330 mm long complete as per clause 810
Unit = Running metre
Taking output = 4.5 metre length
a)

b)

Labour
Mate

day

0.060

673.00

40.38

L-12

Blacksmith

day

0.500

500.00

250.00

L-02

Mazdoor

day

1.000

377.00

377.00

L-13

hour

0.100

340.00

34.00

P&M-053

kg

41.210

44.10

1817.36

kg

88.560

44.10

3905.50

kg

16.240

44.10

716.18

kg

20.000

81.00

1620.00

Machinery
Tractor-trolley

c)

Material
Corrugated sheet,3 mm thick, "W" beam section
railing,4.5 m in length
Channel post 150 x 75 x 5 mm,1.8 m long,3 Nos @
16.4 kg per metre
Spacer 150 x 75 x 5 mm channel 0.33 m long,3 Nos @
16.4 kg per metre
Nuts and bolts
Add 25 per cent of the cost of material for fabrication, nuts,
bolts and washers etc.)
Page 15 of 394

2014.76

M-179 /
1000
M-179 /
1000
M-179 /
1000
M-130

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

Quantity

Rate Rs

Cost Rs
1077.52
1185.27

Cost for 4.5 metre = a+b+c+d+e

13037.97

Rate per metre = (a+b+c+d+e)/4.5

2897.33
say

8.23

Remarks/
Input ref.

2897.00

Type - B, "THRIE" : Metal Beam Crash Barrier


Providing and erecting a "Thrie" metal beam crash barrier
comprising of 3 mm thick corrugated sheet metal beam rail,
85 cm above road/ground level, fixed on ISMC series
channel vertical post, 150 x 75 x 5 mm spaced 2 m centre to
centre, 2 m high with 1.15 m below ground level, all steel
parts and fitments to be galvanised by hot dip process, all
fittings to conform to IS:1367 and IS:1364, metal beam rail to
be fixed on the vertical post with a space of channel section
150 x 75 x 5 mm, 546 mm long complete as per clause 810
Unit = Running metre
Taking output = 4.5 metre length
a)

b)

Labour
Mate

day

0.060

673.00

40.38

L-12

Blacksmith

day

0.500

500.00

250.00

L-02

Mazdoor

day

1.000

377.00

377.00

L-13

hour

0.100

340.00

34.00

P&M-053

kg

72.940

53.40

3895.00

M-088

kg

98.400

44.10

4339.44

kg

26.860

44.10

1184.53

kg

30.000

81.00

2430.00

M-179 /
1000
M-179 /
1000
M-130

Machinery
Tractor-trolley

c)

Material
Corrugated sheet,3 mm thick, "Thrie" beam section
railing,4.5 m in length
Channel post 150 x 75 x 5 mm, 2 m long,3 Nos @ 16.4
kg per metre
Spacer 150 x 75 x 5 mm channel 0.546 m long,3 Nos

Nuts and bolts


Add 15 per cent of the cost of material for fabrication, nuts,
bolts and washers etc.)
d) Overhead charges @ 0.1 on (a+b+c)
e)

1777.34
1432.77

Contractor's profit @ 0.1 on (a+b+c+d)

1576.05

Cost for 4.5 metre = a+b+c+d+e

17336.50

Rate per metre= (a+b+c+d+e)/4.5

3852.56
say

Note

8.24

811

Road Traffic Signals electrically operated

Note

8.25

Suggest
ive

In the case of median crash barrier, 'W' metal beam or thrie


beam section should be provided on both sides of the
vertical posts fixed in the median. Extra provision for metal
beam railing and spacer is required to be made when fixed
in the median depending on approved design.
Since it is a ready made item commercially produced and
erected by specialised firm in the electrical and electronic
field, rate may be taken based on market enquiry from firms
specialised in this field and ISI certified for the approved
design and drawing.
Flexible Crash Barrier, Wire Rope Safety Barrier

Page 16 of 394

3853.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Providing and erecting a wire rope safety barrier with vertical


posts of medium weight RS Joist (ISMB series) 100 mm x 75
mm (11.50 kg/m), 1.50 m long 0.85 m above ground and
0.65 m below ground level, split at the bottom for better grip,
embedded in M 15 grade cement concrete 450 x 450 x 450
mm, 1.50 m center to center and with 4 horizontal steel wire
rope 40 mm dia and anchored at terminal posts 15 m apart.
Terminal post to be embedded in M 15 grade cement
concrete foundation 2400 x 450 x 900 mm (depth),
strengthened by a strut of RS joist 100 x 75 mm, 2 m long
at 450 inclination and a tie 100 x 8 mm, 1.50 m long at the
bottom, all embedded in foundation concrete as per
approved design and drawing, rate excluding excavation and
cement concrete.
Unit = Running metre
Taking output = 15 metre
a) Labour

b)

Mate

day

0.120

673.00

80.76

L-12

Mazdoor

day

2.000

377.00

754.00

L-13

Blacksmith

day

1.000

500.00

500.00

L-02

kg

190.000

44.10

8379.00

kg

46.000

44.10

2028.60

kg

188.400

44.10

8308.44

M-179 /
1000
M-179 /
1000
M-179 /
1000
M-177

Material
i) RS Joist 100 x 75 mm - 16.5 m @ 11.5 kg per metre

ii) Struts - 2 Nos. for terminal posts,2 m long each 2 x 2


x 11.50
iii) Tie 2 Nos. of 8 mm steel plate,1.5 sqm each for
terminal posts @ 62.80 kg/sqm (2 x 1.5)
iv) Steel wire rope 40 mm, including 7.50 per cent
extra for fixing at ends 15 x 4 x 1.075 @ 1 kg per m
Add 5 per cent of cost of material for drilling, gripping, fixing,
fabrication and welding consumables
c) Painting
Applying 2 coats of painting on exposed surface
d)

kg

65.000 input

#VALUE!
#VALUE!

sqm

16.500

68.00

hour

0.250

340.00

Tractor-trolley
Overhead charges @ 0.1 on (a+b+d)

#VALUE!

f)

Contractor's profit @ 0.1 on (a+b+d+e)

#VALUE!
#VALUE!

Rate per m = (a+b+c+d+e+f)/15

#VALUE!
say

8.26

Suggest
ive

The items of excavations and cement concrete works will be


measured and included separately as per the approved
designs and drawings.
Anti-Glare Devices in Median

Plantation
Plantation of shrubs and plants of approved species in the
median. apart from cutting off glare from vehicle coming from
opposite direction, these plants provide a pleasant
envoirenment and are eco-friendly. The rate for this item is
available in the chapter 11 on horticulture.

85.00

e)

Cost for 15 m = a+b+c+d+e+f

Note

1122.00

Anti-glare screen with 25 mm steel pipe framework fixed


with circular and rectangular vans
Providing and erecting an anti - glare screen with 25 mm dia
vertical pipes fabricated and framed in the form of panels of
one metre length and 1.75 metre height fixed with circular
vane 250 mm dia at top and rectangular vane 600 x 300 mm
at the middle, made out of steel sheet of 3 mm thickness,
end vertical pipes of the panel made larger for embedding in
foundation concrete, applying 2 coats of paint on all exposed
surfaces, all as per approved design and drawings.
Unit = Running metre
Taking output = one metre
a)

Item 8.9

Machinery

Labour
Page 17 of 394

#VALUE!

P&M-053

Sr No

Ref. to
MoRTH
Spec.

Description

b)

Unit

Quantity

Rate Rs

Cost Rs

Mate

day

0.004

673.00

2.69

L-12

Mazdoor

day

0.100

377.00

37.70

L-13

metre

16.000

66.00

1056.00

M-174

kg

4.320

44.10

190.51

kg

4.800

44.10

211.68

M-179 /
1000
M-179 /
1000

Material

i) 25 mm steel pipe
ii) MS sheet for 600 x 300 x 3 mm rectangular vane,
one number @ 24kg/sqm
iii) MS sheet for 250 mm dia circular vane 3 mm thick,4
numbers @ 24 kg/sqm
Add 5 per cent cost of material for fabrication, welding,
bending, nuts, bolts etc
c) Painting
Applying 2 coats of painting on exposed surface
d)

Overhead charges @ 0.1 on (a+b)

e)

Contractor's profit @ 0.1 on (a+b+d)

72.91

sqm

1.830

68.00

Item 8.9

172.86
2025.95
say

8.26

124.44
157.15

Rate per metre = a+b+c+d+e

Note

Remarks/
Input ref.

2026.00

The items of excavation and cement concrete as per


approved design to be measured and paid separately
Anti-glare screen with rectangular vane of MS sheet
Providing and erecting anti - glare screen with rectangular
vanes of size 750 x 500 mm made from MS sheet, 3 mm
thick and fixed on MS angle 50 x 50 x 6 mm at an angle of
450 to the direction of flow of traffic, 1.5 m center to center,
top edge of the screen 1.75 m above ground level, vertical
post firmly embedded in M-15 cement concrete foundation
0.60 m below ground level, applying 2 coats of paint on
exposed faces, all complete as per approved design and
drawings
Unit = Running metre
Taking output = 1.50 metre
a)

b)

Labour
Mate

day

0.004

673.00

2.69

L-12

Mazdoor

day

0.100

377.00

37.70

L-13

i) Angle iron post,50 x 50 x 6 mm, length 2.35 m

kg

10.580

44.10

466.58

ii) MS sheet 3 mm thick @ 24 kg/sqm

kg

9.000

44.10

396.90

M-179 /
1000
M-179 /
1000

Material

Add 5 per cent of cost of material for fabrication, nuts, bolts


etc
c) Machinery
Tractor-trolley
d)

43.17
hour

0.100

340.00

34.00

P&M-053

sqm

0.850

68.00

57.80

Item 8.9

Painting
Applying 2 coats of painting

e)

Overhead charges @ 0.1 on (a+b+c)

f)

Contractor's profit @ 0.1 on (a+b+c+e)

98.10
107.91

Cost for 1.5 m = a+b+c+d+e+f

1244.86

Rate per metre = (a+b+c+d+e+f)/1.50

829.91
say

Note

8.27

Suggest
ive

The items of excavation and cement concrete as per


approved design to be measured and paid separately. Rate
of painting has been analaysed separately in this chapter.
Street Lighting
Providing and erecting street light mounted on a steel
circular hollow pole of standard specifications for street
lighting, 9 m high spaced 40 m apart, 1.8 m overhang on
both sides if fixed in the median and on one side if fixed on
the footpath, fitted with sodium vapour lamp and fixed firmly
in concrete foundation.
Unit = Each
Page 18 of 394

830.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Taking output = one light


a)

b)

Labour
Mate

day

0.030

673.00

20.19

L-12

Mazdoor

day

0.500

377.00

188.50

L-13

Electrician

day

0.250

500.00

125.00

L-02

each

1.000

input

#VALUE!

M-171

each

1.000 input

#VALUE!

M-168

Material
i) Steel circular hollow pole of standard specification for
street lighting to mount light at 9 m height above road
level

ii) Sodium vapour lamp


Add 5 per cent of cost of material for holder, electric cable,
insulation, ladder, scaffolding etc
c) Painting

(i)

For Fixing in Median


Providing two coats of alluminium paint over steel
circular hollow pipe with overhang on both sides
For fixing in Footpath
Providing two coats of alluminium paint over steel
circular hollow pipe with overhang on one side
For Fixing in Median

#VALUE!

sqm

5.750

68.00

391.00

Item 8.9

sqm

4.630

68.00

314.84

Item 8.9

d)

Overhead charges @ 0.1 on (a+b)

#VALUE!

e)

Contractor's profit @ 0.1 on (a+b+d)

#VALUE!

Rate per light for fixing in Median= a+b+c+d+e


(ii)

#VALUE!
say

#VALUE!

say

#VALUE!

For fixing in Footpath


Rate per light for Fixing in Footpath = a+b+c+d+e

Note

8.28

Suggest
ive

#VALUE!

The items of excavation and cement concrete foundation will


be measured and included separately in the estimate as per
approved design and drawing. The rate for painting has
been analysed in this chapter.
Lighting on Bridges
Providing and fixing lighting on bridges, mounted on steel
hollow circular poles of standard specifications, 5 m high
fixed on parapets with cement concrete, 20 m apart and
fitted with sodium vapour lamp
Unit = Each
Taking output = one light
a)

b)

Labour
Mate

day

0.020

673.00

13.46

L-12

Mazdoor

day

0.400

377.00

150.80

L-13

Electrician

day

0.200

500.00

100.00

L-02

each

1.000

input

#VALUE!

M-170

each

1.000 input

#VALUE!

M-168

Material
i) Steel circular hollow pole of standard specification for
street lighting to mount light at 5 m above deck level

ii) Sodium vapour lamp 70 watt


Add 1 per cent of cost of material for holder, electric cable,
insulation, ladder, scaffolding etc
c) Painting
Providing two coats of alluminium paint over steel
circular hollow pipe
d) Overhead charges @ 0.1 on (a+b)
e)

#VALUE!

sqm

2.760

68.00

#VALUE!

Contractor's profit @ 0.1 on (a+b+d)

#VALUE!

Rate per light = a+b+c+d+e

#VALUE!
say

Note
8.29

Suggest
ive

187.68

The items of cement concrete to be measured and paid


separately as per approved design. The rate for painting has
already been analysed in this chapter.
Cable Duct Across the Road

Page 19 of 394

#VALUE!

Item 8.9

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Providing and laying of a reinforced cement concrete pipe


duct, 300 mm dia, across the road (new construction),
extending from drain to drain in cuts and toe of slope to toe
of slope in fills, constructing head walls at both ends,
providing a minimum fill of granular material over top and
sides of RCC pipe as per IRC:98-1997, bedded on a 0.3 m
thick layer of granular material free of rock pieces, outer to
outer distance of pipe at least half dia of pipe subject to
minimum 450 mm in case of double and triple row ducts,
joints to be made leak proof, invert level of duct to be above
higher than ground level to prevent entry of water and dirt,
all as per IRC: 98 - 1997 and approved drawings.
(i)

Single row for one utility service


Unit = Running metre
Taking output = 20metres
a) Random Rubble masonry/Brick masonry in
cement mortar 1:6 for head wall both side
b) Labour

c)

cum

2.360

4523.00

Mate

day

0.050

673.00

33.65

L-12

Mazdoor

day

1.000

377.00

377.00

L-13

Mazdoor skilled

day

0.250

408.00

102.00

L-15

#VALUE!

M-151

1368.00

M-009

Cement mortar 1:2 for joints

metre

20.000 input

cum

7.200

each

9.000 input

190.00

cum

0.020

6598.00

hour

0.500

340.00

M-083

131.96

Item 12.6
(B)

170.00

P&M-053

e)

Overhead charges @ 0.1 on (b+c+d)

#VALUE!

f)

Contractor's profit @ 0.1 on (b+c+d+e)

#VALUE!

Cost for 20 metre = a+b+c+d+e+f

#VALUE!

Rate per metre = (a+b+c+d+e+f)/20


(ii)

#VALUE!

Machinery
Tractor-trolley

8.29

Item 12.7
(Addl) B)

Material
Reinforced Cement Concrete pipe 300 mm dia
Granular soil with PI less than 6 for bedding and sides
of pipe (0.6 x 0.6 x 20 m)
Collar for joints 300 mm dia

d)

10674.28

#VALUE!
say

#VALUE!

15242.51

Double row for two utility services


Unit = Running metre
Taking output = 20metres
a) Random Rubble brick/Brick masonry in cement
mortar 1:6 for head wall both sides.
b) Labour

c)

cum

3.370

4523.00

Mate

day

0.050

673.00

33.65

L-12

Mazdoor

day

2.000

377.00

754.00

L-13

Mazdoor skilled

day

0.250

408.00

102.00

L-15

#VALUE!

M-151

2736.00

M-009

Material
Reinforced Cement Concrete pipe 300 mm dia
Granular soil with PI less than 6 for bedding and sides
of pipe (0.6 x 0.6 x 40 m)
Collar for joints 300 mm dia
Cement mortar 1:2 for joints

d)

metre

40.000 input

cum

14.400

each

18.000 input

190.00

cum

0.040

6598.00

hour

1.000

340.00

M-083

263.92

Item 12.6
(B)

340.00

P&M-053

e)

Overhead charges @ 0.1 on (b+c+d)

#VALUE!

f)

Contractor's profit @ 0.1 on (b+c+d+e)

#VALUE!

Cost for 20 metre = a+b+c+d+e+f

#VALUE!

Rate per metre = (a+b+c+d+e+f)/20

#VALUE!
say

(iii)

#VALUE!

Machinery
Tractor-trolley

8.29

Item 12.7
(Addl) B)

Triple rRow for three utility services


Unit = Running metre
Page 20 of 394

#VALUE!

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Taking output = 20metres


a) Random Rubble brick/Brick masonry in cement
mortar 1:6 for head wall both sides.
b) Labour

c)

Rate Rs

Cost Rs

4523.00

Mate

day

0.160

673.00

107.68

L-12

Mazdoor

day

3.000

377.00

1131.00

L-13

Mazdoor skilled

day

1.000

408.00

408.00

L-15

#VALUE!

M-151

4104.00

M-009

Material
metre

60.000 input

cum

21.600

each

27.000 input

190.00

cum

0.060

6598.00

hour

1.500

340.00

Contractor's profit @ 0.1 on (b+c+d+e)

#VALUE!
#VALUE!
#VALUE!

1.Inspection chamber at both ends is the responsibility of the


agency who is laying the duct. Hence not included.
2.The rates for stone masonry / brick masonry and cement
mortar to be adopted from respective clauses.
Highway Patrolling and Traffic Aid Post
It is proposed to locate one Traffic Aid Post every 50-60 km
of the highway.
The organisation and financial aspect are required to be
finalised in consultation with administrative and traffic
authorities .
Items Related to Underpass/ Subway/ Overhead Bridge/
Overhead Foot Bridge

Suggest
ive

Traffic Control System and Communication System


Providing a traffic control centre and communication system
including telecommunication facilities and related
accessories, CCTV, radar, vehicle detection camera, central
computer system
These are specialised item of telecommunication system
and are the commercial products. The designer is required
to contact the manufacturers to ascertain market prices. In
case of civil works required to be executed for these
installations, pricing may be done as per rates in relevant
chapters for quantities derived as per approved design and
drawing.
As regards the locations where such devices are required to
be installed, the traffic control authority should be consulted
to finalise the location

8.33

Suggest
ive

Gantry Mounted Variable Message Sign Board


Providing and erecting gantry mounted variable message
sign board electronically operated capable of flashing the
desired message over a designed support system of
aluminium alloy or galvanised steel, erected as per approved
design and drawings and with lateral clearance as per
clause 802.3
(i)

P&M-053

f)

The items involved for underpass/ subway/ overhead bridge/


overhead foot bridge are earthwork, plain cement concrete,
plastering, painting, information sign etc. The rates for these
items are available in respective chapters which can be
adopted for the quantities derived from the approved
designs and drawings
8.32

510.00
#VALUE!

say

Suggest
ive

Item 12.6
(B)

Overhead charges @ 0.1 on (b+c+d)

Rate per metre = (a+b+c+d+e+f)/20

8.31

M-083

395.88

e)

Cost for 20 metre = a+b+c+d+e+f

Suggest
ive

#VALUE!

Machinery
Tractor-trolley

8.30

Item 12.7
(Addl) B)

4.380

Cement mortar 1:2 for joints

Note

19810.74

Remarks/
Input ref.

cum

Reinforced Cement Concrete pipe 300 mm dia


Granular soil with PI less than 6 for bedding and sides
of pipe (0.6 x 0.6 x 60 m)
Collar for joints 300 mm dia

d)

Quantity

Gantry Support System


Unit = tonne
Page 21 of 394

#VALUE!

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Taking output=1 tonne


a)

b)

c)

Labour
Mate

day

0.120

673.00

80.76

L-12

Mazdoor

day

2.000

377.00

754.00

L-13

Blacksmith

day

1.000

500.00

500.00

L-02

tonne

1.050

57960.00

60858.00

Material
Alluminium alloy/galvanised steel including 5 per cent
wastage
Add 15 per cent of cost of material for fabrication and
erection.
Add 1 per cent of cost of material for nuts, bolts and
welding
Machinery
Truck 10 tonne

9128.70
608.58
hour

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

1.000

291.00

P&M-057

7944.31
87387.46
say

(ii)

291.00
7222.10

Rate per tonne = a+b+c+d+e


8.33

M-060

87387.00

Message Display
Message display board 6 sqm electronically operated with
complete electronic fitments for flashing the pre-determined
messages.
This is a specilised commercial product and the lumpsum
rate including erection at site is required to be as certained
from the market and including in the rate analysis. The size
of the board will vary depending upon specific location.
The rate for the gantry mounted variable sign would be the
addition of cost of gantry support system as per approved
design determined at (i) above and the cost of message
display board as certained from the market at (ii) above

8.34

Suggest
ive

Traffic Impact Attenuators at Abutments and Piers


A

With Scrap Tyres


Provision and installation of traffic attenuators at
abutment/pier of flyovers bridges using scrap tyres of size
100 x 20 retrieved from trucks laid in 2 rows and 4 tiers, one
above the other and tied with 20 mm wire rope as per
approved design and drawings.
Unit = sqm
Taking output = 20sqm
a)

b)

Labour
Mate

day

0.080

673.00

53.84

L-12

Mazdoor

day

1.500

377.00

565.50

L-13

Blacksmith

day

0.250

500.00

125.00

L-02

Material
Scrap tyres of size 900 x 20
20 mm steel wire rope

each

80.000 input

#VALUE!

M-161

kg

150.000 input

#VALUE!

M-176

Add 1 per cent of cost of wire rope for clamps etc.


c)

#VALUE!

Machinery
Tractor-trolley

hour

3.000

340.00

Overhead charges @ 0.1 on (a+b+c)

#VALUE!

e)

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!

Cost for 20 sqm = a+b+c+d+e

#VALUE!

Rate per sqm = (a+b+c+d+e)/20

#VALUE!
say

8.34

1020.00

d)

Using Plastic/Steel Barrel, Filled with Sand

Page 22 of 394

#VALUE!

P&M-053

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Provision and installation of traffic impact attenuator at


abutment/pier of flyovers bridges using plastic/steel barrels
0.60 m dia and 1.0 m in height, filled with sand in three rows
and tied with20 mm steel wire rope as per approved design
and drawings
Unit = sqm
Taking output = 20sqm
a)

b)

Labour
Mate

day

0.130

673.00

87.49

L-12

Mazdoor

day

3.000

377.00

1131.00

L-13

Blacksmith

day

0.250

500.00

125.00

L-02

each

50.000

Steel barrels

each

50.000

238.00

11900.00

M-172

Sand

cum

8.000

2400.00

19200.00

M-004

#VALUE!

M-176

Material
Plastic barrels
or

20 mm steel wire rope

kg

15.000 input

Add 1 per cent of cost of wire rope for clamps etc.


c)

#VALUE!

Machinery
Tractor-trolley

hour

2.000

340.00

Overhead charges @ 0.1 on (a+b+c)

#VALUE!

e)

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!

Cost for 20 sqm = a+b+c+d+e

#VALUE!
say

P&M-053

#VALUE!

Rate per sqm = (a+b+c+d+e)/20


8.34

680.00

d)

#VALUE!

With HI - DRO cell Sandwich (Patented)


(In this patented HI - DRO cell system, water gets
discharged from plastic tubes on impact over a predetermined time, thus absorbing the energy)
Providing and installing a patentend HI - DRO cell system as
a traffic impact attenuators, using plastic tubes 50 cm dia,
1.2 m in height, 25 mm opening at the top, placed in three
rows, filled with water and tied with a 20 mm steel wire rope
Unit = sqm
Taking output = 10sqm
a)

b)

Labour
Mate

day

0.100

673.00

67.30

L-12

Mazdoor

day

2.500

377.00

942.50

L-13

#VALUE!

M-139

156.00

M-189

#VALUE!

M-176

Material
Plastic tubes 50 cm dia,1.2 m high

each

Cost of water

KL

20 mm steel wire rope

kg

40.000 input
12.000

13.00

100.000 input

Add 1 per cent of cost of wire rope for clamps etc.


c)

#VALUE!

Machinery
Tractor-trolley

hour

2.000

340.00

680.00

P&M-053

Water tanker6 KL capacity

hour

2.000

233.00

466.00

P&M-060

d)

Overhead charges @ 0.1 on (a+b+c)

#VALUE!

e)

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!

Cost for 10 sqm = a+b+c+d+e

#VALUE!

Rate per sqm = (a+b+c+d+e)/10

#VALUE!
say

8.35

Suggest
ive

Road Markers/Road Stud with Lense Reflector


Providing and fixing of road stud 100x 100 mm, die-cast in
aluminium, resistant to corrosive effect of salt and grit, fitted
with lense reflectors, installed in concrete or asphaltic
surface by drilling hole 30 mm upto a depth of 60 mm and
bedded in a suitable bituminous grout or epoxy mortar, all as
per BS 873 part 4:1973
Page 23 of 394

#VALUE!

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Unit = Nos
Taking output = 50Nos
a)

b)

Labour
Mate

day

0.040

673.00

26.92

L-12

Mazdoor

day

1.000

377.00

377.00

L-13

#VALUE!

M-062

Material
Aluminium studs 100 x 100 mm fitted with lense
reflectors

each

50.000 input

Add 10 per cent of cost of material for fixing and installation

#VALUE!

c)

Overhead charges @ 0.1 on (a+b)

#VALUE!

d)

Contractor's profit @ 0.1 on (a+b+c)

#VALUE!

Cost for 50 studs = a+b+c+d

#VALUE!

Rate per studs = (a+b+c+d)/50

#VALUE!
say

8.36

Suggest
ive

#VALUE!

Traffic Cone
Provision of red fluorescent with white reflective sleeve traffic
cone made of low density polyethylene (LDPE)
material
with a square base of 390 x 390 x 35 mm and a height of
770 mm, 4 kg in weight, placed at 1.5 m interval, all as per
BS 873
Unit = Running metre
Taking output = 68 Nos.
a)

Labour
Mate

day

0.020

673.00

13.46

L-12

Mazdoor

day

0.500

377.00

188.50

L-13

#VALUE!

M-186

b)

Material
Traffic cones with 150 mm reflective sleeve

c)

each

68.000 input

Machinery
Tractor-trolley

hour

0.100

340.00

Overhead charges @ 0.1 on (a+b+c)

#VALUE!

e)

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!

Cost for 68 Nos. = a+b+c+d+e

#VALUE!

Rate per metre = (a+b+c+d+e)/68

#VALUE!
say

8.37

Suggest
ive

Roadside Amenities
A

Rest areas
Providing plainly furnished accommodation for rest rooms,
dormitories, restaurants, stalls, shops, petrol pump,
telephone booth, first aid room, traffic aid post, police
assistance booth, including electricity, toilet and sewerage
system
Pricing may be done based on current plinth area rates
approved by PWD/CPWD/MES for a particular zone. Area is
required to be assessed for specific location as per actual
site conditions

Parking areas and bus laybyes for trucks, buses and


light vehicles
Pricing of parking areas may be done for the quantities of
various items based on the approved dimensions and
pavement design for a particular terrain and soil. Rates for
items may be from respective chapters.
Lawn
Providing a lawn planted with grass and its maintenance
Pricing of lawn may be done as per rates given in the
chapter on horticulture for the quantities as per approved
dimensions in the drawings

8.38

Suggest
ive

34.00

d)

Rumble Strips

Page 24 of 394

#VALUE!

P&M-053

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Provision of 15 nos rumble strips covered with premix


bituminous carpet, 15-20 mm high at center, 250 mm wide
placed at 1 m center to center at approved locations to
control speed, marked with white strips of road marking
paint.
Unit = sqm
Taking output = 100 sqm (including gaps)
The rate per sqm of premix carpet and road marking may be
adopted from chapter 5 & 8 respectively for the quantities
calculated from approved drawings
8.39

Suggest
ive

Policeman Umbrella
Provision of a 2 m high (floor to roof) umbrella for traffic
policeman at road crossings, where necessary, installed on a
raised platform, built on a central support of a steel pipe 100
mm dia, roof made of 25 mm dia steel pipe to provide
covered area of 3 sqm, roofed with CGI sheets, all steel
parts to be given 2 coats of paint
Unit = each
Taking output = one number
Earthwork
Cement Concrete
brick masonry or

Quantities of these items to be


calculated as per approved design and
cost added as per rates of these items
given in chapter 3 and 13

stone masonry

b)

cum
cum
cum

Painting
a)

cum

sqm

2.500

Mate

day

0.090

Mazdoor

day

1.000

Blacksmith

day

1.000

Welder

day

0.250

Labour

Material
Steel pipe 100 mm dia

metre

3.500

Steel pipe 25 mm dia

metre

10.000

kg

8.000

hour

0.500

CGI sheets
Add 25 per cent of cost of material for fabrication
Add 2 per cent of cost of material for welding consumables,
J-hooks, washers etc.
c) Machinery
Tractor-trolley
d)

Overheads @ per cent on (a+b+c)

e)

Contractors Profit@ per cent on (a+b+c+d)

Rate per policeman umbrella = a+b+c+d+e


8.40

suggesti
ve

High Mast Pole Lighting at Interchanges and Flyovers


Providing and erecting a high mast pole lighting with 30 m
high hot dip galvanised mast designed to withstand forces
exerted with wind speeds of 180 km per hour with 3 seconds
gust, as per IS:875 (Part 3) - 1978, fitted with a base flange,
door at the base of mast with heavy duty internal lock,
lantern carriage, suitable winching arrangement for safe
working load of 750 kg and high powered electrically driven
power tools for raising and lowering of lantern carriage,
flexible 8 core electric cable, lightening conductor, earthing
terminal, and fixing 2 nos aviation obstruction lights on top of
the mast, all complete as per approved design and drawings

Page 25 of 394

Rate Rs

Cost Rs

Remarks/
Input ref.

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

This is a specialised work and is generally done by firms


who specialise in such jobs. The detailed designs and
estimates are submitted by the firms along with their tender
for checks by the Department. The cost of this work is
required to be worked out based on approved design,
drawings and estimate of the lowest tender. A separate
contract for this work is concluded as the contractors for
road and bridge works generally donot undertake such jobs.
8.41

Toll Plaza
The construction, operation and maintenance of Toll Plaza
can be broken into separate items of work as under based
on the approved design and drawings:a)
Provision of toll collection service lane to separate
different categories of vehicles for purpose of toll collection.
This involves considerable increase in carriage way width
b)
Provision of 2.5 m wide separators for different toll
collection service lanes for safety
c) Toll booths with integrated roof cover
d) Barrier gates for individual lanes
e)
Provision of building to provide facility to toll plaza
personnel
f) Toll plaza office equipment and furniture
g)
Water supply, electricity, sanitation, septic-tank system
and drainage
h)
Telephone, intercomes, wireless communication
system
i) High mast lighting
j) Pavement marking
k) Overhead signs
l) Fixed message signs (Advance)
m) Variable message signs
n) Traffic cones and pylons
o) First aid post
p) Traffic aid post and security
The quantities for the above mentioned items may be
calculated from the approved design and drawings and their
rates adopted from respective chapters of the Standard Data
Book

8.42

Safety Devices and Signs in Construction Zones


Provision and fixing of traffic signs for limited period at
suitable locations in construction zone comprising of warning
zone, approach transition zone, working zone and terminal
transition zone with a minimum distance of 60 cm from the
edge of the kerb in case of kerbed roads and 2 to 3 m from
the edge of the carriageway in case of un-kerbed roads, the
bottom edge of the lowest sign plate to be not less than 2 m
above the road level, fixed on 60 mm x 60 mm x 6 mm angle
iron post, founded and installed as per approved design and
drawings, removed and disposed of after completion of
construction work, all as per IRC:SP:55-2001
Unit = each
Taking output = one sign post
Following types of signs are required to be fixed in
construction zones for safety of traffic
a) Diversion one km ahead
b)

Traffic sign ahead

c)

Road ahead closed

d)

Men at work

e)

Road narrow

f)

Single file traffic

g)

Right lane diverted

h)

Left lane diverted


Page 26 of 394

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Sr No

Ref. to
MoRTH
Spec.

Description
i)

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Right lane closed

j) Left lane closed


k) Median closed
l) Diversion to other carriageway
m) Traffic signal ahead
n) Two way traffic
o) Un - even road
p) Slippery road
q) Loose chippings
r) Dual carriageway ends
s) Diversion
t) Do not enter
u) Road closed
v) Stop
w) Slow
x) One way
y) Give way
z)
aa)

Overtaking prohibited
Speed limit

bb)

Weight limit

cc)

Height and length limit

dd)

No stopping or standing

ee)
Any other warning or regulatory safety sign as per
site requirement and consistent with IRC:SP:55-2001 and
IRC:67
The rate for traffic signs are already worked out and given
elsewhere in this chapter. The same may be adopted.
8.43

suggesti
ve

Portable Barricade in Construction Zone


Installation of a steel portable barricade with horizontal rail
300 mm wide, 2.5 m in length fitted on a 'A' frame made with
45 x 45 x 5 mm angle iron section, 1.5 m in height,
horizontal rail painted (2 coats) with yellow and white stripes,
150 mm in width at an angle of 450, 'A' frame painted with 2
coats of yellow paint, complete as per IRC:SP:55-2001
Unit = each
Taking output = one steel portable barricade
a)

b)

Labour
Mate

day

0.020

673.00

13.46

L-12

Mazdoor

day

0.250

377.00

94.25

L-13

Painter

day

0.500

396.00

198.00

L-18

Welder

day

0.250

500.00

125.00

L-02

Angle iron 45 x 45 x 5 mm

kg

25.000

44.10

1102.50

MS sheet 300 mm wide,2.5 m long and 2.6 mm thick

kg

15.000

44.10

661.50

litre

0.500

211.00

105.50

M-179 /
1000
M-179 /
1000
M-131

Material

Paint
Add 2 per cent of cost of steel for welding consumables,
nuts & bolts and drilling holes
c) Overhead charges @ 0.1 on (a+b)
d)

35.28
233.55

Contractor's profit @ 0.1 on (a+b+c)

256.90

Rate per barricade = a+b+c+d

2825.94
say

8.44

suggesti
ve

Permanent Type Barricade in Construction Zone


A

With steel components

Page 27 of 394

2826.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Construction of a permanent type barricade made of steel


components, 1.5 m high from road level, fitted with 3
horizontal rails 200 mm wide and 4 m long on 50 x 50 x 5
mm angle iron vertical support, painted with yellow and white
strips, 150 mm in width at an angle of450, complete as per
IRC:SP:55-2001
Unit = each
Taking output = one barricade
a)

b)

Labour
Mate

day

0.050

673.00

33.65

L-12

Mazdoor

day

0.300

377.00

113.10

L-13

Painter

day

0.600

396.00

237.60

L-18

Welder

day

0.300

500.00

150.00

L-02

kg

15.000

44.10

661.50

kg

50.000

44.10

2205.00

litre

1.000

211.00

211.00

M-179 /
1000
M-179 /
1000
M-131

Material
Angle iron 50 x 50 x 5 mm,2 m long,2 Nos.

MS sheet of 12 SWG,3 Nos of 200 mm width and 4 m


length
Paint
Add 1 per cent of cost of steel for welding consumables,
nuts & bolts and drilling holes
c) Overhead charges @ 0.1 on (a+b)
d)

57.33
366.92

Contractor's profit @ 0.1 on (a+b+c)

403.61

Rate per barricade = a+b+c+d

4439.71
say

8.44

4440.00

With wooden components


Construction of a permanent type barricade made of wooden
components, 1.5 m high from road level, fitted with 3
horizontal planks 200 mm wide and 3.66 m long on 100 x
100mm wooden vertical post, painted with yellow and white
strips, 150 mm in width at an angle of450, complete as per
IRC:SP:55-2001
Unit = each
Taking output = one barricade
a)

b)

Labour
Mate

day

0.050

673.00

33.65

L-12

Mazdoor

day

0.300

377.00

113.10

L-13

Painter

day

0.600

396.00

237.60

L-18

Carpenter

day

0.600

500.00

300.00

L-04

cum

0.180 input

#VALUE!

M-185

Material
Timber

Add 1 per cent of cost of timber for nuts & bolts, nails, etc.

#VALUE!

c)

Overhead charges @ 0.1 on (a+b)

#VALUE!

d)

Contractor's profit @ 0.1 on (a+b+c)

#VALUE!

Rate per barricade = a+b+c+d

#VALUE!
say

8.44

#VALUE!

With bricks
Construction of a permanent type barricade made with brick
work in mud mortar, 1.5 m high, 4 m long, 600 mm thick,
plastered with cement mortar 1:6, painted with yellow and
white strips
Unit = each
Taking output = one barricade
a)

b)

Labour
Mate

day

0.240

673.00

161.52

L-12

Mazdoor

day

3.000

377.00

1131.00

L-13

Painter

day

1.000

396.00

396.00

L-18

Mason

day

2.000

500.00

1000.00

L-11

each

1800.000

3.80

6840.00

M-079

Material
Brick

Page 28 of 394

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

kg

22.000

5.94

130.68

Sand

cum

0.090

2400.00

216.00

M-081 /
1000
M-005

Paint

litre

1.250

211.00

263.75

M-131

Cement

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

1013.90
1115.28

Rate per barricade = a+b+c+d

8.45

suggesti
ve

Remarks/
Input ref.

12268.13
say

12268.00

Drum Delineator in Construction Zone


Provision of metal drum/empty bitumen drum delineator, 300
mm in diameter, 800 mm high, filled with earth for stability,
painted in circumferential strips of alternate black and white
100 mm wide fitted with reflectors 3 Nos of 7.5 cm dia, all as
per IRC:SP:55-2001
Unit = each
Taking output = one drum delineator
a)

b)

Labour
Mate

day

0.020

673.00

13.46

L-12

Mazdoor

day

0.250

377.00

94.25

L-13

Painter

day

0.250

396.00

99.00

L-18

Material
Steel drum 300 mm dia 1.2 m high/empty bitumen
drum
Paint

each

1.000

238.00

238.00

M-172

litre

0.500

211.00

105.50

M-131

c)

Overhead charges @ 0.1 on (a+b)

55.02

d)

Contractor's profit @ 0.1 on (a+b+c)

60.52

Rate per drum delineator = a+b+c+d

665.75
say

8.46

suggesti
ve

666.00

Flagman
Positioning of a smart flagman with a yellow vest and a
yellow cap and a red flag 600 x 600 mm securely fastened to
a staff 1 m in length for guiding the traffic
Unit = each
Taking output = one flagman
a)

Labour
Mate

day

0.040

673.00

26.92

L-12

Mazdoor

day

1.000

377.00

377.00

L-13

each

1.000 input

#VALUE!

M-099

7.00

M-196

b)

Material

c)

Flag of red color cloth 600 x 600 mm


Wooden staff for fastening of flag 25 mm dia, one m
long
Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

each

1.000

7.00

#VALUE!
#VALUE!

Rate per flagman = a+b+c+d

#VALUE!
say

Page 29 of 394

#VALUE!

CHAPTER-9
PIPE CULVERTS
Sr No

Ref. to
MoRTH
Spec.

9.1

408

Description

Unit

Rate Rs

Cost Rs

Remarks/
Input ref.

PCC 1:3:6 in Foundation


Plain cement concrete 1:3:6 mix with crushed stone
aggregate 40 mm nominal size mechanically mixed, placed
in foundation and compacted by vibration including curing for
14 days.
Unit = cum
Taking output = 15 cum
a) Labour
Mate
Mason
Mazdoor
b) Material
40mm Aggregate at site
Sand at site
Cement at site
Cost of water
c) Machinery
Concrete mixer0.4/ 0.28 cum
Generator set 33 KVA
Water tanker6 KL capacity
d) Overhead charges @ 0.1 on (a+b+c)
e) Contractor's profit @ 0.1 on (a+b+c+d)
Cost for 15 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/15
Note

9.2

Quantity

2900

day
day
day

0.640
1.000
15.000

673.00
500.00
377.00

430.72
500.00
5655.00

L-12
L-11
L-13

cum
cum
tonne
KL

13.800
6.900
3.300
18.000

659.00
2400.00
5940.00
13.00

9094.20
16560.00
19602.00
234.00

M-055
M-005
M-081
M-189

hour
hour
hour

6.000
6.000
3.000

218.00
349.00
233.00

P&M-009
P&M-079
P&M-060

say

1308.00
2094.00
699.00
5617.69
6179.46
67974.07
4531.60
4532.00

673.00
500.00
377.00

121.14
250.00
1508.00

L-12
L-11
L-13

2400.00
5940.00

168.00
297.00
#VALUE!

M-005
M-081
M-149

190.00

M-009

say

855.00
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

673.00
500.00

188.44
500.00

L-12
L-11

Vibrator is a part of minor T & P which is already included in


overhead charges of the contractor.
Laying Reinforced Cement Concrete Pipe NP4 /
Prestressed Concrete Pipe on First Class Bedding in
Single Row .
Laying Reinforced cement concrete pipe NP4/prestressed
concrete pipe for culverts on first class bedding of granular
material in single row including fixing collar with cement
mortar 1:2 but excluding excavation, protection works,
backfilling, concrete and masonry works in head walls and
parapets .

Unit = metre
Taking output = 12.5 metres ( 5 pipes of 2.5 m length
each )
1000 mm dia
a)

Labour
Mate
Mason
Mazdoor
b) Material
Sand at site
Cement at site
RCC pipe NP-4 /prestressed concrete pipe including
collar at site
Granular material passing 5.6 mm sieve for bedding
c) Overhead charges @ 0.1 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Cost for 12.5 metres = a+b+c+d
Rate per metre = (a+b+c+d)/12.5
Note

day
day
day
cum
tonne
metre
cum

0.180
0.500
4.000
0.070
0.050
12.500 input
4.500

1. In case of cement craddle bedding, quantity of PCC M15


is to be calculated as per design and priced separately and
added .
2. The rate analysis does not include excavation, cement
/masonry works in head walls, backfilling, protection works
and parapet walls. The same are to be calculated as per
approved design and drawings and priced separately on
rates available under respective sections

9.2

1200 mm dia
a) Labour
Mate
Mason

day
day
Page 1 of 394

0.280
1.000

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Mazdoor
Material
Sand at site
Cement at site
RCC pipe NP-4/prestressed concrete pipe including
collar at site
Granular material passing 5-6 mm sieve for class
bedding
c) Overhead charges @ 0.1 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Cost for 12.5 metres = a+b+c+d
Rate per metre= (a+b+c+d)/12.5

Quantity
day

Rate Rs

6.000

Cost Rs

Remarks/
Input ref.

377.00

2262.00

L-13

2400.00
5940.00

216.00
415.80
#VALUE!

M-005
M-081
M-150

190.00

950.00

M-009

say

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

b)

Note

9.3

2900

cum
tonne
metre
cum

0.090
0.070
12.500 input
5.000

1. In case of cement craddle bedding, quantity of PCC M15


is to be calculated as per design and priced separately and
added .
2. The rate analysis does not include excavation, cement
/masonry works in head walls, backfilling, protection works
and parapet walls. The same are to be calculated as per
approved design and drawings and priced separately on
rates available under respective sections
Laying Reinforced Cement Concrete Pipe NP4 /
Prestressed Concrete Pipe on First Class Bedding in
Double Row .
Laying Reinforced cement concrete pipe NP4 / prestressed
concrete pipe for culverts on first class bedding of granular
material in double row including fixing collar with cement
mortar 1:2 but excluding excavation, protection works,
backfilling, concrete and masonry works in head walls and
parapets .
Unit = metre

Taking output = 12.5 metres ( 10 pipes of 2.5 m length


each in two rows.)
1000 mm dia
a)

b)

Labour
Mate

day

0.360

673.00

242.28

Mason

day

1.000

500.00

500.00

L-11

Mazdoor

day

8.000

377.00

3016.00

L-13

Material
Sand at site

cum

0.140

2400.00

336.00

M-005

Cement at site

tonne

0.100

5940.00

594.00

M-081

RCC pipe NP-4/prestressed concrete pipe including


collar at site
Granular material passing 5.6 mm sieve for bedding

metre

#VALUE!

M-149

2375.00

M-009

cum

25.000 input
12.500

190.00

c)

Overhead charges @ 0.1 on (a+b)

#VALUE!

d)

Contractor's profit @ 0.1 on (a+b+c)

#VALUE!

Cost for 12.5 metres = a+b+c+d

#VALUE!

Rate per metre = (a+b+c+d)/12.5


Note

9.3

L-12

#VALUE!

1. In case of cement craddle bedding, quantity of PCC M15


is to be calculated as per design and priced separately and
added .
2. The rate analysis does not include excavation, cement
/masonry works in head walls, backfilling, protection works
and parapet walls. The same are to be calculated as per
approved design and drawings and priced separately on
rates available under respective sections

say

#VALUE!

1200 mm dia
a)

b)

Labour
Mate

day

0.560

673.00

376.88

Mason

day

2.000

500.00

1000.00

L-12
L-11

Mazdoor

day

12.000

377.00

4524.00

L-13

cum

0.180

2400.00

432.00

M-005

tonne

0.140

5940.00

831.60

M-081

Material
Sand at site
Cement at site
Page 2 of 394

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

c)

RCC pipe NP-4 /prestressed concrete pipe including


collar at site
Granular material passing 5-6 mm sieve for class
bedding
Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

metre
cum

Quantity

Rate Rs

Cost Rs

25.000 input
13.750

190.00

M-150

2612.50

M-009

#VALUE!
#VALUE!

Rate per metre= (a+b+c+d)/12.5


Note

#VALUE!

#VALUE!

Cost for 12.5 metres = a+b+c+d

#VALUE!

1. In case of cement craddle bedding, quantity of PCC M15


is to be calculated as per design and priced separately and
added .
2. The rate analysis does not include excavation, cement
/masonry works in head walls, backfilling, protection works
and parapet walls. The same are to be calculated as per
approved design and drawings and priced separately on
rates available under respective sections

Page 3 of 394

say

Remarks/
Input ref.

#VALUE!

CHAPTER- 10
MAINTENANCE OF ROADS
Sr No

Ref. to
MoRTH
Spec.

10.1

3002

Description

Unit

Quantity

Rate Rs

Cost Rs

Restoration of Rain Cuts


Restoration of rain cuts with soil, moorum, gravel or a
mixture of these, clearing the loose soil, benching for 300
mm width, laying fresh material in layers not exceeding 250
mm and compacting with plate compactor or power rammers
to restore the original alignment, levels and slopes
Unit = cum
Taking output = 10 cum
a) Labour
Mate
Mazdoor
b) Machinery
Excavator1.0 cum bucket capacity @ 60 cum per hour
Tipper ( L is average lead in km for borrow earth)

Add 10 per cent of cost of carriage towards loading and


unloading charges.
Plate compactor
c) Overhead charges @ 0.1 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Cost for 10 cum = a+b+c+d
Rate per cum = (a+b+c+d)/10

day
day

0.080
2.000

673.00
377.00

53.84
754.00

L-12
L-13

hour

0.130

1222.00

158.86

P&M-026

tonne.km

12 x L

2.00

24.00

Lead =1
km & P&M058

2.40
hour

0.500 input

say
Note

10.2

3003

Remarks/
Input ref.

#VALUE! P&M-086
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

Only 75 per cent of fresh material has been provided as 25


per cent can be retrieved at site from earth that is flown
down the slope in the form of slurry and deposited at the foot
of there in cuts
Maintenance of Earthen Shoulder (filling with fresh soil)
Making up loss of material/ irregularities on shoulder to the
design level by adding fresh approved soil and compacting it
with appropriate equipment.
Unit = sqm
Taking output = 100 sqm
Assuming average thickness of filling to be 150 mm
Quantity of fresh material = 15 cum
a) Labour
Mate
Mazdoor
b) Machinery
Excavator1.0 cum bucket capacity @ 60 cum per hour
Tipper ( L is average lead in km for borrow earth)

Add 10 per cent of cost of transportation to cover cost of


loading and unloading
Plate compactor @ 25 sqm per hour
c) Overhead charges @ 0.1 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Cost for 100 sqm = a+b+c+d
Rate per sqm = (a+b+c+d)100

day
day

0.180
4.500

673.00
377.00

121.14
1696.50

L-12
L-13

hour

0.250

1222.00

305.50

P&M-026

tonne.km

24xL

2.00

48.00

Lead =1
km & P&M058

4.80
hour

12.000 input

say
10.3

3003

#VALUE! P&M-086
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

Maintenance of Earth Shoulder (stripping excess soil)


Stripping excess soil from the shoulder surface to achieve
the approved level and compacting with plate compactor
Unit = sqm
Taking output = 100 sqm
Assuming average depth of stripping as 75 mm
Quantity of earth cutting involved = 7.5 cum
a) Labour
Mate
Mazdoor
Page 1 of 394

day
day

0.100
2.500

673.00
377.00

67.30
942.50

L-12
L-13

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Machinery
Plate compactor @ 25 sqm per hour
c) Overhead charges @ 0.1 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Cost for 100 sqm = a+b+c+d
Rate per sqm on = (a+b+c+d)100

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

b)

hour

4.000 input

say
Note
10.4

3004.2

The earth stripped from earthen shoulders to be dumped on


the side slopes locally for disposal.
Filling Pot-holes and Patch Repairs with open-Graded
Premix surfacing, 20mm.
Removal of all failed material, trimming of completed
excavation to provide firm vertical faces, cleaning of surface,
painting of tack coat on the sides and base of excavation as
per clause 503, back filling the pot holes with hot bituminous
material as per clause 511, compacting, trimming and
finishing the surface to form a smooth continuous surface, all
as per clause 3004.2
Unit = Sqm
Taking out put = 10250 sqm (205 cum)(405 tonne)
a) Labour
Mate

Day

3.760

673.00

2530.48

L-12

Mazdoor

Day

90.000

377.00

33930.00

L-13

Mazdoor skilled

Day

4.000

408.00

1632.00

L-15

Air compressor 250 cfm

hour

6.000

300.00

1800.00

P&M-001

HMP 100-110 TPH Capacity

hour

6.000

15906.00

95436.00

P&M-021

Tipper 10 tonnes capacity

hour

45.000

291.00

13095.00

P&M-048

Smooth wheeled roller 8-10 tonnes

hour

12.000

432.00

5184.00

P&M-044

Crushed stone aggregates nominal size 13.2mm

cum

184.500

928.00

171216.00

M-052

Crushed stone aggregates nominal size 11.2mm

cum

92.250

1063.00

98061.75

M-051

Bitumen 80/100

tonne

14.970

40367.00

604293.99

M-075

tonne

2.460

34975.00

86038.50

M-077

d)

Bitumen emulsion for tack coat including vertical sides


of pot hole.
Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

b)

c)

Machinery

Material

111321.77
122453.95

Cost for 10250 sqm = a+b+c+d+e

1346993.44

Rate per sqm = (a+b+c+d+e)/10250

131.41
say

10.5

3004.2

#VALUE! P&M-086
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

131.00

Filling Pot-holes and Patch Repairs with Bituminous


concrete, 40mm.
Removal of all failed material, trimming of completed
excavation to provide firm vertical faces, cleaning of surface,
painting of tack coat on the sides and base of excavation as
per clause 503, back filling the pot holes with hot bituminous
material as per clause 504, compacting, trimming and
finishing the surface to form a smooth continuous surface, all
as per clause 3004.2
Unit = Sqm
Taking out put = 4900 sqm (196 cum)(450 Tonnes)
a)

b)

c)

Labour
Mate

Day

2.920

673.00

1965.16

L-12

Mazdoor

Day

70.000

377.00

26390.00

L-13

Mazdoor skilled

Day

3.000

408.00

1224.00

L-15

Air compressor 250 cfm

hour

6.000

300.00

1800.00

P&M-001

HMP 100-110 TPH Capacity

hour

6.000

12360.00

74160.00

P&M-022

Tipper 10 tonnes capacity

hour

45.000

291.00

13095.00

P&M-048

Smooth wheeled roller 8-10 tonnes

hour

12.000

432.00

5184.00

P&M-044

tonne

22.500

40367.00

908257.50

Machinery

Material
I) Bitumen

Page 2 of 394

M-075

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

ii) Bitumen emulsion for tack coat .

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

tonne

1.180

34975.00

41270.50

M-077

20-10mm 35 per cent

cum

99.750

925.00

92268.75

M-051,M052,M-053
and M-054

10-5 mm 23 per cent

cum

65.550

137.00

8980.35

M-025

5mm and below40 per cent

cum

114.000

100.00

11400.00

M-021,M022 and
M-024

iii) Aggregates
Grading I - 19mm(Nominal size)

Add 5 per cent for wastage

5632.46

or
Grading-II 13mm (Nominal size)
85.500

740.00

cum

71.250

137.00

63270.00 M-051 and


M-052
9761.25
M-025

cum

122.550

137.00

16789.35

tonne

9.000

72.00

13.2-10 mm 30 per cent

cum

10-5 mm 25 per cent


5 mm and Below43 per cent

Filler 2 per cent


Add 5 per cent for wastage

648.00

M-021,M022 and
M-024
M-188

4523.43

Any one of the above alternatives of aggregate i.e. 19mm or


13mm nominal size may be adopted as per approved
design.
10.5

(i)

for grading I Material


d)

Overhead charges @ 0.1 on (a+b+c)

119162.77

e)

Contractor's profit @ 0.1 on (a+b+c+d)

131079.05

Cost for 4900 cum = a+b+c+d+e

1441869.54

Rate per cum = (a+b+c+d+e)/4900

294.26
say

10.5

(ii)

d)

Overhead charges @ 0.1 on (a+b+c)

116833.82

e)

Contractor's profit @ 0.1 on (a+b+c+d)

128517.20

Cost for 4900 cum = a+b+c+d+e

1413689.21

Rate per cum = (a+b+c+d+e)/4900

288.51
say

Note
10.6

3004.3.3

294.00

for grading II Material

289.00

For detailed working of quantities of aggregates, refer item


5.8 of chapter 5
Crack Filling
Filling of crack using slow - curing bitumen emulsion and
applying crusher dust in case crack are wider than 3mm.
Unit = Running Meter
Taking out put = 500m
a)

b)

Labour
Mate

day

0.040

673.00

26.92

L-12

Mazdoor

day

1.000

377.00

377.00

L-13

Kg

33.000

35.00

1155.00

M-077

cum

0.020

137.00

2.74

M-021

Material
Slow-curing bitumen emulsion
Stone crusher dust

c)

Overhead charges @ 0.1 on (a+b)

156.17

d)

Contractor's profit @ 0.1 on (a+b+c)

171.78

Cost for 500sqm = a+b+c+d

1889.61

Rate per meter = (a+b+c+d+e)/500

3.78
say

10.7

3004.4

Dusting
Applying crusher dust to areas of road where bleeding
of excess bitumen has occurred.
Unit = Sqm
Taking output = 3500 sqm
Page 3 of 394

4.00

Sr No

Ref. to
MoRTH
Spec.

Description
a)

Unit

Quantity

Rate Rs

Cost Rs

Labour
Mate

day

0.080

673.00

53.84

L-12

Mazdoor

day

2.000

377.00

754.00

L-13

cum

6.250

137.00

856.25

M-021

b)

Material

c)

Stone crusher dust finer than 3mm with not more


than 10 per cent passing 0.075 sieve.
Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

166.41
183.05

Cost for 3500sqm = a+b+c+d

2013.55

Rate per meter = (a+b+c+d)/3500

0.58
say

10.8

(A)
3004.3.2

Fog Seal

(B)
3004.3.4

Crack Prevention courses.

(i)
(ii)
(iii)
(iv)
10.8

10.8

10.9

(C)
3004.5

Stress Absorbing Membrane (SAM) crack width less than 6


mm
Stress Absorbing Membrane (SAM) with crack width 6 mm to
9 mm
Stress Absorbing Membrane (SAM) crack width above 9 mm
and cracked area above 50 per cent
Bitumen Impregnated Geotextile

0.58

sqm

36.00

Item 5.17

sqm

58.00

sqm

73.00

sqm

96.00

sqm

161.00

Item 5.21
Case-I
Item 5.21
Case-II
Item 5.21
Case-IV
Item 5.21
Case-IV

Slurry Seal
(i)

5 mm thickness

sqm

73.00

(ii)

3 mm thickness

sqm

49.00

(iii)

1.5 mm thickness

sqm

24.00

(D)
3004.6

3005.1

Remarks/
Input ref.

Item 5.15
Case-I
Item 5.15
Case-II
Item 5.15
Case-III

Surface Dressing for maintenance works.


(i)

19 mm nominal chipping size

sqm

82.00

(ii)

13 mm nominal size chipping

sqm

67.00

Item 5.9
Case-I
Item 5.9
Case-II

The above mentioned items have already been included in


chapter 5.
Repair of Joint Grooves with Epoxy Mortar
Repair of spalled joint grooves of contraction joints,
longitudinal joints and expansion joints in concrete
pavements using epoxy mortar or epoxy concrete
Unit = running metre
Taking output = 10 metres
a)

Labour
Mate

day

0.040

673.00

26.92

L-12

Mazdoor

day

0.500

377.00

188.50

L-13

Chiseller

day

0.500

400.00

200.00

L-05

b)

Material
Epoxy primer

kg

2.500 input

#VALUE!

M-097

kg

10.000 input

#VALUE!

M-095

c)

Epoxy compound with accessories for preparing epoxy


mortar
Machinery
Air compressor 250 cfm for cleaning

hour

0.050

300.00

Overhead charges @ 0.1 on (a+b+c)

#VALUE!

e)

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!

Cost for 10 metres = a+b+c+d+e

#VALUE!

Rate per metre = (a+b+c+d+e)/10

#VALUE!
say

10.10

3005.2

15.00

d)

Repair of old Joints Sealant


Page 4 of 394

#VALUE!

P&M-001

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Removal of existing sealant and re sealing of contraction,


longitudinal or expansion joints in concrete pavement with
fresh sealant material
Unit = running metre
Taking output = 10 metres
a)

b)

c)

Labour
Mate

day

0.040

673.00

26.92

L-12

Mazdoor

day

0.500

377.00

188.50

L-13

Material
Primer

kg

0.250 input

#VALUE!

M-146

Sealant

kg

1.000 input

#VALUE!

M-120

Machinery
Air compressor 250 cfm for cleaning

hour

0.050

300.00

Overhead charges @ 0.1 on (a+b+c)

#VALUE!

e)

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!

Cost for 10 metres = a+b+c+d+e

#VALUE!
say

3000

P&M-001

#VALUE!

Rate per metre = (a+b+c+d+e)/10


10.11

15.00

d)

#VALUE!

Hill Side Drain Clearance


Removal of earth from the choked hill side drain and
disposing it on the valley side manually
Unit = running metre
Taking output = 10 metres
Assuming muck causing choking of drain to be 0.2 cum per
metre, quantity of earth to be removed for 10 metres = 2
cum
a)

Labour
Mate

day

0.080

673.00

53.84

L-12

Mazdoor

day

1.000

377.00

377.00

L-13

b)

Overhead charges @ 0.1 on (a+b)

c)

Contractor's profit @ 0.1 on (a+b)

43.08
47.39

Cost for 10 metres = a+b+c

521.32

Rate per metre = (a+b+c)/10

52.13
say

10.12

3000

52.00

Land Slide Clearance in soil


Clearance of land slides in soil and ordinary rock by a bulldozer D 80 A-12, 180 HP and disposal of the same on the
valley side
Unit = cum
Taking output = 100 cum
a)

b)

Labour
Mate

day

0.040

673.00

26.92

L-12

Mazdoor

day

1.000

377.00

377.00

L-13

hour

1.670

3490.00

5828.30

P&M-014

Machinery
Dozer 180 HP @ 60 cum per hour

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

623.22
685.54

Cost for 100 cum = a+b+c+d

7540.99

Rate per cum = (a+b+c+d)/100

75.41
say

Note

10.13

3000

Land Slide clearance involves pushing of loose earth slided


on the road surface from hill face on the valley side. Since
no cutting of original ground is involved, the output of dozer
has been taken as 60 cum per hour for soil, ordinary rock
and blasted hard rock. However, if there are objection to
disposing of earth on valley side, additional resources for its
disposal shall be considered as per site conditions.
Landslide Clearance in Hard Rock Requiring Blasting

Page 5 of 394

75.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Clearing of land slide in hard rock requiring blasting for 50


per cent of the boulders and disposal of the same on the
valley side.
Unit = cum
Taking output = 100 cum
a)

b)

Labour
Mate

day

0.090

673.00

60.57

L-12

Mazdoor

day

1.500

377.00

565.50

L-13

Driller

day

0.750

400.00

300.00

L-06

Blaster

day

0.070

396.00

27.72

L-03

Dozer D 80 A-12,180 HP @ 60 cum per hour

hour

1.670

3490.00

5828.30

P&M-014

Air compressor 250 cfm with two jack hammer

hour

2.500

300.00

750.00

P&M-001

kg

17.500

74.08

1296.40

M-104

each

70.000

11.00

Machinery

c)

Materials

c)

Electric Detonators @ 1 Detonator for 2 Gelatine sticks


of 125 gms each
Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

Gelatine 80 per cent @ 35 kg per 100 cum

959.85
1055.83

Cost for 100 cum = a+b+c+d+e

11614.17

Rate per cum = (a+b+c+d+e)/100

116.14
say

Note
10.14

3000

770.00 M-094 /100

116.00

Credit for the rock if found acceptable as construction


material shall be afforded
Snow Clearance on Roads with Dozer
Snow clearance from road surface by a bull- dozer 165 Hp
and disposing it on the valley side
Unit = cum
Taking output = 5000 cum
a)

b)

Labour
Mate

day

0.080

673.00

53.84

L-12

Mazdoor

day

2.000

377.00

754.00

L-13

hour

5.880

3490.00

20521.20

Machinery
Dozer D 80 A-12,180 HP @ 850 cum per hour

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

2346.19

Cost for 5000 cum = a+b+c+d

25808.14

Rate per cum = (a+b+c+d)/5000

5.16
say

Note

10.15

3000

P&M-014

2132.90

5.00

i) Labour provided will not be cutting the snow. They will be


guiding the dozer operator on the alignment of the road as
entire surface gets covered with snow and the edges of the
road are not visible and for changing the blade angle. Also
they will keep a watch on the hill side for any eventuality of
avalanches, slide etc
Snow Clearance on Roads with Snow Blowers
Snow clearance from road surface by a snow blower and
disposing on the valley side.
Unit = cum
Taking output = 3600 cum
a)

b)

Labour
Mate

day

0.080

673.00

53.84

L-12

Mazdoor

day

2.000

377.00

754.00

L-13

Machinery
Snow blower equipment 140 HP @ 600 cum per hour

hour

6.000 input

#VALUE! P&M-087

c)

Overhead charges @ 0.1 on (a+b)

#VALUE!

d)

Contractor's profit @ 0.1 on (a+b+c)

#VALUE!

Cost for 3600 cum (a+b+c+d)

#VALUE!

Rate per cum = (a+b+c+d)/3600

#VALUE!
Page 6 of 394

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs
say

Page 7 of 394

#VALUE!

Remarks/
Input ref.

CHAPTER-11
HORTICULTURE
Sr No

Ref. to
MoRTH
Spec.

11.1

307

11.2

Description

Unit

Spreading of Sludge Farm Yard Manure or/and good


Earth
Spreading of sludge farm yard manure or/ and good earth in
required thickness (cost of sludge, farm yard manure or/and
good earth to be paid for separately)
Unit = cum
Taking output = 15 cum
a) Labour
Mate
Mazdoor
b) Overhead charges @ 0.1 on (a)
c) Contractor's profit @ 0.1 on (a+b)
Cost for 15 cum= a+b+c
Rate per cum = (a+b+c)/15

307

Quantity

day
day

Rate Rs

0.040
1.000

Cost Rs

673.00
377.00

Remarks/
Input ref.

L-12
L-13

say

26.92
377.00
40.39
44.43
488.74
32.58
33.00

Grassing with ' Doobs' Grass


Grassing with 'Doobs' grass including watering and
maintenance of the lawn for 30 days or more till the grass
forms a thick lawn free from weeds and fit for moving
including supplying good earth if needed

(i)

Unit = sqm
Taking output = 100 sqm
In rows 15 cm apart in either direction
a)

Labour
Mate
Mazdoor for grassing
Mazdoor for maintenance for 30 days
b) Machinery
Water tanker6 KL capacity
c) Material
Doob grass
d) Overhead charges @ 0.1 on (a+b+c)
e) Contractor's profit @ 0.1 on (a+b+c+d)
Cost for 100 sqm = a+b+c+d+e
Rate per sqm= (a+b+c+d+e)/100
11.2

(ii)

Note

11.3

307

In rows 7.5 cm apart in either direction


a) Labour
Mate
Mazdoor for grassing.
for maintenance for 30 days
b) Machinery
Water tanker6 KL capacity
c) Material
Doob grass
d) Overhead charges @ 0.1 on (a+b+c)
e) Contractor's profit @ 0.1 on (a+b+c+d)
Cost for 100 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/100

day
day
day

0.170
0.750
1.000

673.00
377.00
377.00

114.41
282.75
377.00

L-12
L-13
L-13

hour

0.500

233.00

116.50

P&M-060
M-112

say

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

kg

100.000 input

day
day
day

0.220
1.250
1.000

673.00
377.00
377.00

148.06
471.25
377.00

L-12
L-13
L-13

hour

0.750

233.00

174.75

P&M-060
M-112

say

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

673.00
377.00
377.00

100.95
188.50
377.00

L-12
L-13
L-09

kg

200.000 input

In the case of horticulture one mate has been provided for


every 10 mazdoors as maintenance of grass and plants
require more care.
Making Lawns including Ploughing and Dragging with
'Swagha' Breaking of Clod
Making lawns including ploughing and breaking of clod,
removal of rubbish, dressing and supplying doobs grass
roots and planting at 15 cm apart, including supplying and
spreading of farm yard manure at rate of 0.18 cum per 100
sqm
Unit = sqm
Taking output = 100 sqm
a) Labour
Mate
Mazdoor for preparation of ground
Mali for fetching doobs grass roots and grassing at 15
cm apart
Page 1 of 394

day
day
day

0.150
0.500
1.000

Spreading of sludge farm yard manure or/ and good earth in


required thickness (cost of sludge, farm yard manure or/and
good earth to be paid for separately)
b) Machinery
Water tanker6 KL capacity
Tractor with tiller
c) Material
Supply of farm yard manure at site of work
Fine grass
d) Overhead charges @ 0.1 on (a+b+c)
e) Contractor's profit @ 0.1 on (a+b+c+d)
Cost for 100 sqm = a+b+c+d+e

hour
hour
cum
kg

0.500
0.010

233.00
340.00

0.180 input
100.000 input

Rate per sqm = (a+b+c+d+e)/100


11.4

307

116.50
3.40

P&M-060
P&M-053

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

M-167
M-113

#VALUE!
say

#VALUE!

Maintenance of Lawns or Turfing of Slopes


Maintenance of lawns or Turfing of slopes (rough grassing)
for a period of one year including watering etc
Unit = sqm
Taking output = 100 sqm
a)

Labour
Mali

b)

Water tanker6 KL capacity


c)

day

10.000

377.00

3770.00

L-09

hour

15.000

233.00

3495.00

P&M-060

KL

90.000

13.00

1170.00

M-189

Machinery
Material
Cost of water

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

843.50
927.85

Cost for 100 sqm = a+b+c+d+e

10206.35

Rate per sqm = (a+b+c+d+e)/100


11.5

307

102.06
say

102.00

Turfing Lawns with Fine Grassing including Ploughing,


Dressing
Turfing lawns with fine grassing including ploughing,
dressing including breaking of clods, removal of rubbish,
dressing and supplying doobs grass roots at 10 cm apart,
including supplying and spreading of farm yard manure at
rate of0.6 cum per 100 sqm
Unit = sqm
Taking output = 100 sqm
a)

b)

c)

Labour
Mate

day

0.250

673.00

168.25

L-12

Mazdoor for preparation of ground

day

1.000

377.00

377.00

L-13

Mali for fetching doobs grass roots hedges and


grassing at 10 cm apart
Machinery

day

1.500

377.00

565.50

L-09

Water tanker6 KL capacity

hour

0.500

233.00

116.50

P&M-060

Tractor with tiller

hour

0.010

340.00

3.40

P&M-053

cum

0.600 input

#VALUE!

M-167

kg

100.000 input

#VALUE!

M-113

Material
Supply of farm yard manure at site of work @ 0.6 cum
per 100 sqm
Fine grass

d)

Overhead charges @ 0.1 on (a+b+c)

#VALUE!

e)

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!

Cost for 100 sqm = a+b+c+d+e

#VALUE!

Rate per sqm = (a+b+c+d+e)/100

#VALUE!
say

11.6

307

Maintenance of Lawns with Fine Grassing for the First


Year
Maintenance of lawns with fine grassing for the first year
including watering etc
Unit = sqm
Taking output = 100 sqm
a)

Labour
Page 2 of 394

#VALUE!

Spreading of sludge farm yard manure or/ and good earth in


required thickness (cost of sludge, farm yard manure or/and
good earth to be paid for separately)
Mali
b)

Water tanker6 KL capacity


c)

day

10.000

377.00

3770.00

L-09

hour

20.000

233.00

4660.00

P&M-060

KL

60.000

13.00

780.00

M-189

Machinery
Material
Cost of water

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

921.00
1013.10

Cost for 100 sqm = a+b+c+d+e

11144.10

Rate per sqm = (a+b+c+d+e)/100

111.44
say

11.7

307

111.00

Planting and Maintaining of Permanent Hedges


(a)

Planting permanent hedges including digging of


trenches
Planting permanent hedges including digging of trenches, 60
cm wide and 45 cm deep, refilling the excavated earth mixed
with farmyard manure, supplied at the rate of 4.65 cum per
100 metres and supplying and planting hedge plants at 30
cm apart
Unit = Running metre
Taking output = 100metre
a)

b)

Labour
Mate

day

1.400

673.00

942.20

L-12

Mazdoor for digging of trench 60 cm wide and 45 cm


deep
Mazdoor for refilling the excavated earth mixed with
cow dung, preparation of ground and digging of plant,
from the nursery carriage to site and planting in
position

day

10.000

377.00

3770.00

L-13

day

4.000

377.00

1508.00

L-13

hour

0.500

233.00

116.50

P&M-060

Cost of hedge plants 2 rows at 30 cm apart

each

2x340 input

#VALUE!

M-116

Supply of farm yard manure at site of work

cum

4.670 input

Machinery
Water tanker6 KL capacity

c)

Material
#VALUE!

M-167

Pesticide

kg

0.250

463.00

115.75

M-136

Cost of water

KL

3.000

13.00

39.00

M-189

d)

Overhead charges @ 0.1 on (a+b+c)

#VALUE!

e)

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!

Cost for 100 metres = a+b+c+d+e

#VALUE!

Rate per metre = a+b+c+d+e)/100

#VALUE!
say

(b)

#VALUE!

Maintenance of hedge for one year


Unit = Running metre
Taking output = 100 m
a)

b)

Labour
Mate

day

3.000

673.00

2019.00

L-12

Mazdoor

day

30.000

377.00

11310.00

L-13

hour

5.000

233.00

1165.00

P&M-060

cum

2.000 input

Machinery
Water tanker6 KL capacity

c)

Material
Manure sludge/Farm yard manure

#VALUE!

M-167

Pesticide

kg

0.500

463.00

231.50

M-136

Cost of water

KL

30.000

13.00

390.00

M-189

#VALUE!

M-116

Cost of hedge plants @ 10 per cent casualty

each

68.000 input

d)

Overhead charges @ 0.1 on (a+b+c)

#VALUE!

e)

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!

Cost for 100 metres = a+b+c+d+e

#VALUE!

Rate per metre = a+b+c+d+e)/100

#VALUE!
say

Page 3 of 394

#VALUE!

11.8

307
(a)

Spreading of sludge farm yard manure or/ and good earth in


required thickness (cost of sludge, farm yard manure or/and
good earth to be paid for separately)
Planting and Maintaining of Flowering Plants and
Shrubs
Planting flowering plants and shrubs in central verge
Unit = Running metres 200 plants and 800 shrubs in two
rows in one km length of road where width of verge is
3m and above.
Taking output = 1000 metres
a)

b)

Labour
Mate

day

1.200

673.00

807.60

L-12

Mazdoor

day

12.000

377.00

4524.00

L-13

hour

6.000

233.00

1398.00

P&M-060

Machinery
Water tanker6 KL capacity

c)

Material
Plants

each

200.000 input

#VALUE!

M-100

Shrubs

each

800.000 input

#VALUE!

M-166

Manure sludge/Farm yard manure

cum

63.640 input

#VALUE!

M-167

Pesticide

kg

0.500

463.00

231.50

M-136

Cost of water

KL

36.000

13.00

468.00

M-189

d)

Overhead charges @ 0.1 on (a+b+c)

#VALUE!

e)

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!

Rate per Km = (a+b+c+d+e)

#VALUE!
say

11.8

(b)

#VALUE!

Maintenance of flowering plants and shrubs in central


verge for one year
Unit = km
Taking output = one km
a)

b)

Labour
Mate

day

36.000

673.00

24228.00

L-12

Mazdoor

day

365.000

377.00

137605.00

L-13

hour

90.000

233.00

20970.00

P&M-060

#VALUE!

M-167

2340.00

M-189

Machinery
Water tanker6 KL capacity

c)

Material
Manure Sludge / farm yard manure at site
Cost of water

cum
KL

10.000 input
180.000

13.00

Replacement of casualties @ 10 per cent


Plants

each

20.000 input

#VALUE!

M-100

Shrubs

each

80.000 input

#VALUE!

M-166

694.50

M-136

Pesticides

kg

1.500

463.00

d)

Overhead charges @ 0.1 on (a+b+c)

#VALUE!

e)

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!

Rate per Km for one year = (a+b+c+d+e)


11.9

307

#VALUE!
say

#VALUE!

Planting of Trees and their Maintenance for one Year


Planting of trees by the road side (Avenue trees) in 0.60 m
dia holes, 1 m deep dug in the ground, mixing the soil with
decayed farm yard/sludge manure, planting the saplings,
backfilling the trench, watering, fixing the tree guard and
maintaining the plants for one year
Unit = Each
Taking output = 10 trees
a)

b)

Labour
Mate

day

1.700

673.00

1144.10

L-12

Mazdoor for planting

day

2.000

377.00

754.00

L-13

Mazdoor for maintenance for one year

day

15.000

377.00

5655.00

L-13

hour

2.000

233.00

466.00

P&M-060

Machinery
Water tanker6 KL capacity

c)

Material
Page 4 of 394

Spreading of sludge farm yard manure or/ and good earth in


required thickness (cost of sludge, farm yard manure or/and
good earth to be paid for separately)
Sapling 2 m high 25 mm dia
Farm yard manure

each

10.000 input

#VALUE!

M-160

cum

0.940 input

#VALUE!

M-167

Pesticide

kg

0.500

463.00

231.50

M-136

Cost of water

KL

12.000

13.00

156.00

M-189

d)

Overhead charges @ 0.1 on (a+b+c)

#VALUE!

e)

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!

Cost for 10 trees = a+b+c+d+e

#VALUE!

Rate per trees = (a+b+c+d+e)/10


11.10

308

#VALUE!
say

#VALUE!

Renovation Lawns including, Weeding, Forking the


Ground, Top Dressing with Forked Soil
Renovation lawns including, weeding, forking the ground,
top dressing with forked soil, watering and maintenance the
lawns, for 30 days or more, till the grass forms a thick lawn,
free from weeds, and fit for moving and disposal of rubbish
as directed, including supplying good earth, if needed but
excluding the cost of well decayed farm yard manure
Unit = sqm
Taking output = 100 sqm
a)

b)

Labour
Mate

day

0.120

673.00

80.76

L-12

Mazdoor

day

3.000

377.00

1131.00

L-13

hour

0.500

233.00

116.50

P&M-060

KL

3.000

13.00

39.00

M-189

Machinery
Water tanker6 KL capacity

c)

Material
Cost of water

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

136.73
150.40

Cost for 100 sqm = a+b+c+d+e

1654.38

Rate per sqm = (a+b+c+d+e)

16.54
say

11.11

308.2

17.00

Supply at Site Well Decayed Farm Yard Manure


Supply at site of work well decayed farm yard manure, from
any available source, approved by the engineer in charge
including screening and stacking
Unit = cum
Taking output = one cum
a)

Material

b)

a) Cost of well decayed farm yard manure duly


screened, loading, carriage, unloading and
stacking at site
Overhead charges @ 0.1 on (a)

c)

Contractor's profit @ 0.1 on (a+b)

cum

1.000 input

#VALUE!

#VALUE!
#VALUE!

Rate per cum = (a+b+c)

#VALUE!
#VALUE!

11.12

308.20

Supply at Site of Work/ Store-Deoiled Neem Cake


Supply at site of work/ store-deoiled neem cake duly packed
in used gunny bags
Unit = quintal
Taking output = one quintal
a) Cost, carriage, loading, unloading and stacking in
store/site
b) Overheads@ per cent on (a)
c)

Contractors profit@ per cent on (a+b)

Rate per quintal = a+b+c


11.13

308.2

Supplying Sludge
Supplying sludge duly stacked at site/ store
Unit = cum
Taking output = one cum
Page 5 of 394

quintal

1.000

M-167

Spreading of sludge farm yard manure or/ and good earth in


required thickness (cost of sludge, farm yard manure or/and
good earth to be paid for separately)
a) Cost of sludge including carriage, loading,
unloading and stacking at site
b) Overheads@ per cent on (a)
c)

cum

1.000

Mate

day

0.050

673.00

33.65

Mason

day

0.250

500.00

125.00

L-11

Mazdoor

day

0.250

377.00

94.25

L-13

Brick 2nd class including carriage

each

230.000

3.80

874.00

M-079

Cement mortar 1:6

cum

0.025

4957.00

123.93

Item 12.6
(D)

Contractors profit@ per cent on (a+b)

Rate per cum = a+b+c


11.14

New

Half Brick Circular Tree Guard, in 2nd Class Brick,


internal diametre 1.25 metres, and height 1.2 metres,
above ground and 0.20 metre below ground
Half brick circular tree guard, in 2nd class brick, internal
diametre 1.25 metres, and height 1.2 metres, above ground
and 0.20 metre below ground, bottom two courses laid dry,
and top three courses in cement mortar 1:6 (1 cement 6
sand) and the intermediate courses being in dry honey comb
masonry, as per design complete
Unit = Each
Taking output = one tree guard
a)

b)

Labour

Material

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

125.08
137.59

Rate per tree Guard = a+b+c+d

1513.50
say

11.15

New

L-12

1513.00

Edging with 2nd Class Bricks, Laid Dry Lengthwise


Edging with 2nd class bricks, laid dry lengthwise, including
excavation, refilling, consolidation, with a hand packing and
spreading nearly surplus earth within a lead of 50 metres
Unit = Metre
Taking output= 10 metres
a)

b)

Labour
Mate

day

0.002

673.00

1.35

Mason

day

0.050

500.00

25.00

L-11

Mazdoor

day

0.050

377.00

18.85

L-13

each

50.000

3.80

190.00

M-079

Material
Brick 2nd class including carriage

c)

Overhead charges @ 0.1 on (a+b)

23.52

d)

Contractor's profit @ 0.1 on (a+b+c)

25.87

Cost for 10 metre = a+b+c+d

284.59

Rate per metre = (a+b+c+d)/10


11.16

New

L-12

28.46
say

28.00

Making Tree Guard 53 cm dia and 1.3 m High as per


Design from Empty Bitumen Drums
Making tree guard 53 cm dia and 1.3 m high as per design
from empty bitumen drum, slit suitably to permit sun and air,
(supplied by the department at stock issue rate) including
providing and fixing 2 nos MS sheet rings 50 x 0.5 mm with
rivets, complete in all respect
Unit = Each
Taking output = one tree guard
a)

b)

Labour
Mate

day

0.020

673.00

13.46

L-12

Blacksmith

day

0.150

500.00

75.00

L-02

Mazdoor

day

0.070

377.00

26.39

L-13

each

1.000

238.00

238.00

M-172

Material
Empty bitumen drum
Page 6 of 394

Spreading of sludge farm yard manure or/ and good earth in


required thickness (cost of sludge, farm yard manure or/and
good earth to be paid for separately)
MS sheet 50 x 0.5 mm
Rivets 6 mm dia and 10 mm in length
d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

kg

0.650

44.10

28.67

each

22.000

0.65

14.30
39.58
43.54

Rate for each tree guard = a+b+c+d

478.94
say

11.17

New

M-179 /
1000
M-158

479.00

Making Tree Guard 53 cm dia and 2 Metre High as per


Design from Empty Bitumen Drums
Making tree guard 53 cm dia and 2 metres high as per
design from empty bitumen drums, slit suitably to permit sun
and air, ( supplied by the department at stock issue rate)
including providing and fixing four legs 40 cm long of 30 x 3
mm MS riveted to tree guard and providing and fixing 2 nos
MS sheet rings 50 x 0.5 mm with rivets complete in all
respects
Unit = Each
Taking output = one tree guard
a)

Labour
Mate
Blacksmith

0.040

673.00

26.92

L-12

0.200

500.00

100.00

L-02

0.200

377.00

75.40

L-13

each

1.500

238.00

357.00

M-172

kg

0.650

44.10

28.67

each

50.000

0.65

32.50

M-179 /
1000
M-158

kg

1.300

44.10

57.33

day

Mazdoor
b)

Material
Empty bitumen drum
MS sheet50 x 0.5 mm
Rivets 6 mm dia and 10 mm in length
MSplate30 x 3 mm

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

67.78
74.56

Rate for each tree guard = a+b+c+d

820.16
say

11.18

New

M-179 /
1000

820.00

Wrought Iron and Mild Steel Welded Work


Wrought iron and mild steel welded work (using angles,
square bars, tees and channel grills, grating frames, gates
and tree guards of any size and design etc. including cost of
screens and welding rods or bolts and nuts complete fixed in
position but without the cost of excavation and concrete for
fixing which will be paid separately
Unit = quintal
Taking output = one quintal
a)

b)

Labour
Mate

day

0.450

673.00

302.85

L-12

Blacksmith/ welder for cutting to design and shape and


jointing
Mazdoor for fixing and helper for Blacksmith/welder

day

2.000

500.00

1000.00

L-02

day

2.500

377.00

942.50

L-13

Angle, tees, channels etc

quintal

1.050

4410.00

4630.50 M-179 /10

Deduct the cost of scrap

quintal

0.050

(1470.00)

(73.50) M-179/10/3

Material

Add 5 per cent of cost of material for welding rods and other
welding accessories
c) Overhead charges @ 0.1 on (a+b)
d)

227.85
703.02

Contractor's profit @ 0.1 on (a+b+c)

773.32

Rate per quintal = a+b+c+d

8506.54
say

11.19

New

Tree Guard with MS Iron

Page 7 of 394

8507.00

Spreading of sludge farm yard manure or/ and good earth in


required thickness (cost of sludge, farm yard manure or/and
good earth to be paid for separately)
Providing and fixing MS iron tree guard 60 cm dia and 2
metre high above ground level formed of 4 Nos (25 x 6 mm)
and 8 Nos (25 x 3 mm) vertical MS riveted to 3 Nos (25 x 6
mm) iron rings in two halves, bolted together with 8 mm dia
and 30 mm long bolts including painting two coats with paint
of approved brand over a coat of priming, complete in all
respects.
Unit = Each
Taking output = one tree guard
a)

b)

c)

Labour
Mate

day

0.050

673.00

33.65

L-12

Blacksmith

day

0.250

500.00

125.00

L-02

Mazdoor

day

0.250

377.00

94.25

L-13

MS iron 25 x 6 mm

kg

19.200

44.10

846.72

MS iron 25 x 3 mm

kg

9.600

44.10

423.36

M-179 /
1000
M-179 /
1000

hour

0.040

340.00

13.60

P&M-053

sqm

1.770

68.00

120.36

Item 8.9

Material

Add 5 per cent of cost of material for riveting, bolting


and welding accessories
Machinery
Tractor-trolley

d)

Painting
Painting two coats including priming

e)

Overhead charges @ 0.1 on (a+b+c)

f)

Contractor's profit @ 0.1 on (a+b+c+e)

153.66
169.02

Rate per tree guard =a+b+c+d+e+f

1979.62
say

Note

11.20

New

1980.00

1 The items of excavation and concreting to be measured


and paid separately as per design .
2 . Rate of painting may be adopted from the chapter as
Traffic signs.
Tree Guard with MS Angle Iron and Steel Wire
Providing and fixing tree guard 0.60 metre square, 2.00
metre high fabricated with MS angle iron 30 x 30 x 3 mm,
MS iron 25 x 3 mm and steel wire3 mm dia welded and
fabricated as per design in two halves bolted together
Unit = Each
Taking output = one
a)

b)

c)

Labour
Mate

day

0.050

673.00

33.65

L-12

Blacksmith

day

0.250

500.00

125.00

L-02

Welder

day

0.250

500.00

125.00

L-02

Mazdoor

day

0.250

377.00

94.25

L-13

MS angle 30 x 30 x 3 mm

kg

13.500

44.10

595.35

MS iron 25 x 3 mm

kg

18.000

44.10

793.80

Steel wire 3 mm dia

kg

6.000

52.00

312.00

M-179 /
1000
M-179 /
1000
M-192

Material

Add 5 per cent of cost of material for riveting, bolting


and welding accessories
Machinery
Tractor-trolley

d)

85.06

hour

0.040

340.00

13.60

P&M-053

sqm

1.500

68.00

102.00

Item 8.9

Painting
Painting two coats including priming

e)

Overhead charges @ 0.1 on (a+b+c)

f)

Contractor's profit @ 0.1 on (a+b+c+e)

217.77
239.55

Rate per tree guard = a+b+c+d+e+f

2737.03
say

11.21

New

Compensatory Afforestation

Page 8 of 394

2737.00

Spreading of sludge farm yard manure or/ and good earth in


required thickness (cost of sludge, farm yard manure or/and
good earth to be paid for separately)
Planting trees as compensatory afforestation at the rate of
290 trees per hectare at a spacing of 6 m by grubbing and
leveling the ground upto a depth of 150 mm, digging holes
0.9 m dia, 1 m deep, mixing farm yard/sludge manure with
soil, planting of sapling 2 m high with 25 cm dia stem,
backfilling the hole and watering
Unit = Hectare
Taking output = one hectare
a)

Labour

i) Planting
Mate

day

2.500

673.00

1682.50

L-12

Mazdoor

day

25.000

377.00

9425.00

L-13

ii) For Maintenance for one year

b)

c)

Mate

day

5.000

673.00

3365.00

L-12

Mazdoor

day

50.000

377.00

18850.00

L-13

Dozer 80 HP @ 1000 sqm/hour

hour

10.000

2069.00

20690.00

P&M-015

Water tanker6 KL capacity (for planting)

hour

3.000

233.00

699.00

P&M-060

Water tanker6 KL capacity (for maintenance)

hour

25.000

233.00

5825.00

P&M-060

Sapling 1 to 1.5 m high 2 cm dia stem

each

290.000

#VALUE!

#VALUE!

Add 10 per cent of sapling

each

29.000

#VALUE!

#VALUE!

Decayed farm yard/sludge manure (planting)

cum

60.900 input

#VALUE!

M-160 x
0.8
M-160 x
0.8
M-167

Decayed farm yard/sludge manure (maintenance)

cum

4.000 input

Machinery

Material

#VALUE!

M-167

Pesticides for planting

kg

0.500

463.00

231.50

M-136

Pesticides for maintenance

kg

1.500

463.00

694.50

M-136

Cost of water

KL

18.000

13.00

234.00

M-189

d)

Overhead charges @ 0.1 on (a+b+c)

#VALUE!

e)

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!

Rate per hectare = a+b+c+d+e

#VALUE!
say

Note

Cost of fencing to be provided as per size of plot and


approved design, measured and paid separately

Page 9 of 394

#VALUE!

CHAPTER-12
FOUNDATIONS
Sr No

Ref. to
MoRTH
Spec.

12.1

304

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Excavation for Structures


Earth work in excavation of foundation of structures as per
drawing and technical specification, including setting out,
construction of shoring and bracing, removal of stumps and
other deleterious matter, dressing of sides and bottom and
backfilling with approved material.
I

Ordinary soil
Unit = cum
Taking output = 10 cum

A
(i)

Manual Means
Depth upto 3 m
a) Labour
Mate
Mazdoor
b) Overhead charges @ 0.2 on (a)
c) Contractor's profit @ 0.1 on (a+b)
Cost for 10 cum = a+b+c
Rate per cum = (a+b+c)/10

day
day

0.14
3.50

673.00
377.00

94.22
1319.50
282.74
169.65
1866.11
186.61
187.00

L-12
L-13

121.14
1696.50
363.53
218.12
2399.28
239.93
240.00

L-12
L-13

L-12
L-13

say

161.52
2262.00
484.70
290.82
3199.05
319.90
320.00

say
Note

12.1 (I) A

(ii)

1. Cost of dewatering may be added where required upto, 10


per cent of labour cost Assessment for dewatering shall be
made as per site conditions.
2.The excavated earth can be used partially for backfilling of
foundation pit and partly for road work except for marshy
soil. Hence cost of disposal has not been added except for
marshy soil. This remark is common to all cases of item 12.1
excluding marshy soil.
3.The cost of shoring and shuttering, where needed, may be
added @ 1 per cent on cost of excavation for open
foundation.
Depth 3 m to 6 m
a) Labour
Mate/Supervisor
Mazdoor
b) Overhead charges @ 0.2 on (a)
c) Contractor's profit @ 0.1 on (a+b)
Cost for 10 cum = a+b+c
Rate per cum = (a+b+c)/10

day
day

0.18
4.50

673.00
377.00

say

12.1 (I) A

Note

Cost of dewatering may be added where required upto 15


per cent of labour cost. Assessment for dewatering shall be
done as per actual ground conditions.

(iii)

Depth above 6 m
a) Labour
Mate/Supervisor
Mazdoor
b) Overhead charges @ 0.2 on (a)
c) Contractor's profit @ 0.1 on (a+b)
Cost for 10 cum = a+b+c
Rate per cum = (a+b+c)/10

Note

12.1 (I)

B
(i)

1. Cost of dewatering may be added where required upto 20


per cent of labour cost. Assessment for dewatering shall be
made as per site conditions..
Mechanical Means
Depth upto 3 m
Unit = cum
Taking output = 240 cum
a) Labour
Mate
Mazdoor
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity
c) Overhead charges @ 0.2 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Cost for 240 cum = a+b+c+d
Rate per cum = (a+b+c+d)/240
Page 1 of 394

day
day

0.24
6.00

673.00
377.00

day
day

0.32
8.00

673.00
377.00

215.36
3016.00

L-12
L-13

hour

6.00

1222.00

7332.00
2112.67
1267.60
13943.64
58.10

P&M-026

Sr No

Ref. to
MoRTH
Spec.

Description

Note

12.1 (I) B

(ii)

Unit

Quantity

Rate Rs
say

58.00

Remarks/
Input ref.

Cost of dewatering upto 5 per cent of (a+b) may be added,


where required. Assessment for dewatering shall be made
as per site conditions..
Depth 3 m to 6 m
Unit = cum
Taking output = 210 cum
a) Labour
Mate
Mazdoor
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity
c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

day
day

0.32
8.00

673.00
377.00

215.36
3016.00

L-12
L-13

hour

6.00

1222.00

7332.00

P&M-026

2112.67
1267.60

Cost for 210 cum = a+b+c+d

13943.64

Rate per cum = (a+b+c+d)/210

66.40
say

12.1 (I) B

Cost Rs

Note

Cost of dewatering upto 7.5 per cent of (a+b)


may be
added, where required. Assessment for dewatering shall be
made as per site conditions..

(iii)

Depth above 6m

66.00

Unit = cum
Taking output = 180 cum
a)

b)

Labour
Mate

day

0.40

673.00

269.20

L-12

Mazdoor

day

10.00

377.00

3770.00

L-13

hour

6.00

1222.00

7332.00

P&M-026

Machinery
Hydraulic excavator 1.0 cum bucket capacity

c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

2274.24
1364.54

Cost for 180 cum = a+b+c+d

15009.98

Rate per cum = (a+b+c+d)/180

83.39
say

Note

12.1

83.00

1. Cost of dewatering upto 10 per cent of (a+b)


may be
added, where required. Assessment for dewatering shall be
made as per site conditions..

II

2.Labour provided for excavation by mechanical means


includes that required for trimming of bottom and side
slopes.
Ordinary Rock (not requiring blasting)

Manual Means

(i)

Depth upto 3 m
Unit = cum
Taking output = 10 cum
a)

Labour
Mate

day

0.20

673.00

134.60

L-12

Mazdoor

day

5.00

377.00

1885.00

L-13

b)

Overhead charges @ 0.2 on (a)

c)

Contractor's profit @ 0.1 on (a+b)

403.92
242.35

Cost for 10 cum = a+b+c

2665.87

Rate per cum = (a+b+c)/10

266.59
say

Note

12.1(II)

Cost of dewatering upto 10 per cent of labour cost may be


added, where required. Assessment for dewatering shall be
made as per site conditions..
Mechanical Means
Unit = cum
Taking output = 180 cum
a)

Labour
Page 2 of 394

267.00

Sr No

Ref. to
MoRTH
Spec.

Description

b)

Unit

Quantity

Rate Rs

day

0.24

673.00

161.52

L-12

Mazdoor

day

6.00

377.00

2262.00

L-13

hour

6.00

1222.00

7332.00

P&M-026

Machinery

c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

1951.10
1170.66

Cost for 180 cum = a+b+c+d

12877.29

Rate per cum = (a+b+c+d)/180

12.1

Remarks/
Input ref.

Mate

Hydraulic excavator 1.0 cum bucket capacity

Note

Cost Rs

71.54

III

1.Cost of dewatering upto 10 per cent of (a+b), may be


added, where required Assessment for dewatering shall be
made as per site conditions.
2.In case of rock, foundation beyond3 m is not dug and
hence not included.
Hard Rock ( requiring blasting )

Manual Means

say

72.00

Unit = cum
Taking output = 10 cum
a)

b)

Labour
Mate

day

0.35

673.00

235.55

L-12

Driller

day

0.50

400.00

200.00

L-06

Blaster

day

0.25

396.00

99.00

L-03

Mazdoor

day

8.00

377.00

3016.00

L-13

hour

1.00

300.00

300.00

P&M-001

M-104

Machinery
Air Compressor 250 cfm with 2 jack hammer for drilling.

c)

Material
Blasting Material

kg

3.50

74.08

259.28

Detonator electric

each

14.00

11.00

154.00 M-094/100

d)

Overhead charges @ 0.2 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

852.77
511.66

Cost for 10 cum = a+b+c+d+e

5628.26

Rate per cum = (a+b+c+d+e)/10

562.83
say

Note

12.1

IV

563.00

Cost of dewatering @ 10 per cent of (a+b)


may be
added, where required Assessment for dewatering shall be
made as per site conditions.
Hard Rock ( blasting prohibited )
Unit = cum
Taking output = 10 cum

Mechanical Means
a)

Labour
Mate

day

0.20

673.00

134.60

L-12

Mazdoor

day

5.00

377.00

1885.00

L-13

hour

6.00

300.00

1800.00

P&M-001

b)

Machinery

c)

Air Compressor 250 cfm with 2 leads of pneumatic


breaker
Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

763.92
458.35

Cost for 10 cum = a+b+c+d

5041.87

Rate per cum = (a+b+c+d)/10

504.19
say

Note

12.1

1. Cost of dewatering upto10 per cent of (a+b), may be


added, where required Assessment for dewatering shall be
made as per site conditions.
2.In case of rock, foundation beyond3 m is not dug and
hence not included.
Marshy Soil
Unit = cum

Page 3 of 394

504.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Taking output = 10 cum


Depth upto 3 m
A

Manual means
a)

b)

Labour
Mate/Supervisor

day

0.40

673.00

269.20

L-12

Mazdoor

day

10.00

377.00

3770.00

L-13

hour

2.67

340.00

907.80

P&M-053

Machinery
Tractor-trolley for removal.

c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

989.40
593.64

Cost for 10 cum = a+b+c+d

6530.04

Rate per cum = ( a+b+c+d)/ 10

653.00
say

Note

12.1 (V)

2. Shoring & strutting 15 per cent of (a), where required may


be added
3. It is assumed that Marshy Soil will be available upto 3 m
depth only. For deeper excavation below 3 m depth, refer
analysis in item12.1 (i) to (iv) for ordinary soil
Mechanical Means
a)

b)

Labour
Mate

day

0.08

673.00

53.84

L-12

Mazdoor for dressing sides, bottom and backfilling

day

2.00

377.00

754.00

L-13

hour

0.17

1222.00

207.74

P&M-026

hour

0.45

291.00

130.95

P&M-048

Machinery
Hydraulic excavator 1.0 cum bucket capacity @ 60
cum per hour
Tipper 5.5 cum capacity, 4 trips per hour.

c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

229.31
137.58

Cost for 10 cum = a+b+c+d

1513.42

Rate per cum = (a+b+c+d)/10

151.34
say

Note

VI

653.00

1. Cost of dewatering @ 30 per cent of (a), may be added,


where required Assessment for dewatering shall be made as
per site conditions.

151.00

1. Cost of dewatering @ 20 per cent of (a+b)


may be
added, where required
2. Shoring & strutting @ 10 per cent of (a+b), where
required may be added
3. It is assumed that Marshy Soil will be available upto 3 m
depth only. For deeper excavation below 3 m depth, refer
analysis in item 12.1 (i) to (iv) for ordinary soil
Back Filling in Marshy Foundation Pits
Unit : Cum
Taking Output : 6 cum
a)

b)

Labour
Mate

day

0.12

673.00

80.76

L-12

Mazdoor for dressing sides, bottom and backfilling

day

3.00

377.00

1131.00

L-13

hour

2.00

340.00

680.00

P&M-053

Machinery
Tractor-trolley for transportation

c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

378.35
227.01

Cost for 6 cum = a+b+c+d

2497.12

Rate per cum = (a+b+c+d)/6

416.19
say

12.2

304

Filling Annular Space Around Footing in Rock


Unit = cum
Taking out put = 1 cum
Lean cement concrete 1:3:6 nominal mix. Rate may be
taken as per item 12.4.

Page 4 of 394

416.00

Sr No
12.3

Ref. to
MoRTH
Spec.

Description

304

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Sand Filling in Foundation Trenches as per Drawing &


Technical Specification
Unit = cum
Taking output = 1 cum
a)

b)

Labour
Mate

day

0.01

673.00

6.73

L-12

Mazdoor

day

0.30

377.00

113.10

L-13

cum

1.20

616.00

739.20

M-006

Material
Sand (assuming 20 per cent voids)

c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

171.81
103.08

Rate per cum = a+b+c+d


12.4

2100

1133.92
say

1134.00

PCC 1:3:6 in Foundation


Plain cement concrete 1:3:6 nominal mix in foundation with
crushed stone aggregate 40 mm nominal size mechanically
mixed, placed in foundation and compacted by vibration
including curing for 14 days.
Unit = cum
Taking output = 15 cum
a)

b)

Labour
Mate

day

0.64

673.00

430.72

Mason

day

1.00

500.00

500.00

L-11

Mazdoor

day

15.00

377.00

5655.00

L-13

40 mm Aggregate

cum

13.50

659.00

8896.50

M-055

coarse Sand

cum

6.75

2400.00

16200.00

M-005

cement

tonne

3.45

5940.00

20493.00

M-081

KL

18.00

13.00

234.00

M-189

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

218.00

1308.00

P&M-009

Generator 33 KVA

hour

6.00

349.00

2094.00

P&M-079

Water tanker 6 KL capacity

hour

2.00

233.00

466.00

P&M-060

Material

Cost of water
c)

Machinery

d)

Overhead charges @ 0.2 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

11255.44
6753.27

Cost for 15 cum = a+b+c+d+e

74285.93

Rate per cum = (a+b+c+d+e)/15


Note
12.5

1300

L-12

4952.40
say

4952.00

Vibrator is a part of minor T & P which is already included in


overhead charges of the contractor.
Brick Masonry Work in Cement Mortar 1:3 in Foundation
complete excluding Pointing and Plastering, as per
Drawing and Technical Specifications.
Unit = cum
Taking output = 5 cum
a)

b)

Material
Bricks Ist class

each

2500.00

3.80

9500.00

M-079

Cement mortar 1:3 (Rate as in Item 12.6 A subanalysis)


Labour

cum

1.20

5916.00

7099.20

Item 12.6
(A)

Mate

day

0.48

673.00

323.04

L-12

Mason

day

4.00

500.00

2000.00

L-11

Mazdoor

day

8.00

377.00

3016.00

L-13

c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

4387.65
2632.59

Cost for 5 cum = a+b+c+d

28958.48

Rate per cum (a+b+c+d)/5

5791.70
say
Page 5 of 394

5792.00

Sr No
12.6

Ref. to
MoRTH
Spec.
Subanalysis

Description
(A)

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Cement Mortar 1:3 (1 cement : 3 sand)

Unit = 1 cum
Taking output = 1 cum
a)

b)

Materials
Cement

tonne

0.51

5940.00

3029.40

M-081

Sand

cum

1.05

2400.00

2520.00

M-005

Mate

day

0.04

673.00

26.92

L-12

Mazdoor

day

0.90

377.00

339.30

L-13

say

5916.00

Labour

Total Material and Labour = (a+b)


Subanalysis
(Addl.)

(B)

Cement Mortar1:2 (1cement :2 sand)

Unit = 1 cum
Taking output = 1 cum
a)

b)

Materials
Cement

tonne

0.67

5940.00

3991.68

M-081

Sand

cum

0.93

2400.00

2232.00

M-005

Mate

day

0.04

673.00

26.92

L-12

Mazdoor

day

0.90

377.00

339.30

L-13

say

6590.00

Labour

Total Material and Labour = (a+b)


Subanalysis
(Addl.)

(C)

Cement Mortar1:4 (1cement :4 sand)

Unit = 1 cum
Taking output = 1 cum
a)

b)

Materials
Cement

tonne

0.40

5940.00

2395.01

M-081

Sand

cum

1.12

2400.00

2688.00

M-005

Mate

day

0.04

673.00

26.92

L-12

Mazdoor

day

0.90

377.00

339.30

L-13

say

5449.00

Labour

Total Material and Labour = (a+b)


Subanalysis
(Addl.)

(D)

Cement Mortar1:6 (1cement :6 sand)

Unit = 1 cum
Taking output = 1 cum
a)

b)

Materials
Cement

tonne

0.29

5940.00

1710.72

M-081

Sand

cum

1.34

2400.00

3209.14

M-005

Mate

day

0.04

673.00

26.92

L-12

Mazdoor

day

0.90

377.00

339.30

L-13

say

5286.00

753.00

4141.50

Labour

Total Material and Labour = (a+b)


12.7

1400

Stone Masonry Work in Cement Mortar 1:3 in


Foundation complete as per Drawing and Technical
Specifications.
Unit = cum
Taking output = 5 cum

1405.4

(A)

Square Rubble Coursed Rubble Masonry (first sort)


a)

Material
Stone

cum
Page 6 of 394

5.50

M-169

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Through and bond stone

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

each

35.00

14.00

490.00

M-182

Cement mortar 1:3 (Rate as in Item 12.6 A subanalysis)


Labour

cum

1.50

5916.00

8874.00

Item 12.6
(A)

Mate

day

0.66

673.00

444.18

L-12

Mason

day

7.50

500.00

3750.00

L-11

Mazdoor

day

9.00

377.00

3393.00

L-13

(35no.x0.24mx0.24mx0.39m = 0.79 cu.m)

b)

c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

4218.54
2531.12

Cost for 5 cum = a+b+c+d

27842.34

Rate per cum (a+b+c+d)/5


1405.3

(B)

5568.47
say

5568.00

Random Rubble Masonry


( coursed/uncoursed )
Unit = cum
Taking output = 5 cum
a)

Material
Stone

cum

5.50

391.00

2150.50

M-148

Through and bond stone

each

35.00

14.00

490.00

M-182

Cement mortar 1:3 (Rate as in Item 12.6 A subanalysis)


Labour

cum

1.55

5916.00

9169.80

Item 12.6
(A)

Mate

day

0.62

673.00

417.26

L-12

Mason

day

6.00

500.00

3000.00

L-11

Mazdoor

day

9.00

377.00

3393.00

L-13

(35nos.x0.24mx0.24mx0.39m = 0.79 cu.m)

b)

c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

3724.11
2234.47

Cost for 5 cum = a+b+c+d

24579.14

Rate per cum (a+b+c+d)/5


Note

12.8

1500,
1700 &
2100
A

4915.83
say

4916.00

The labour already considered in cement mortar has been


taken into account while proposing labour for masonry
works.
Plain/Reinforced Cement Concrete in Open Foundation
complete as per Drawing and Technical Specifications.
PCC Grade M15
Unit = cum
Taking output = 15 cum
a)

b)

c)

Material
Cement

tonne

4.13

5940.00

24532.20

M-081

Coarse sand

cum

6.75

2400.00

16200.00

M-005

40 mm Aggregate

cum

8.10

659.00

5337.90

M-055

20 mm Aggregate

cum

4.05

942.00

3815.10

M-053

10 mm Aggregate

cum

1.35

1063.00

1435.05

M-051

Mate

day

0.86

673.00

578.78

L-12

Mason

day

1.50

500.00

750.00

L-11

Mazdoor

day

20.00

377.00

7540.00

L-13

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

218.00

1308.00

P&M-009

Generator 63 KVA

hour

6.00

349.00

2094.00

P&M-019

Labour

Machinery

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
d) Formwork @ 4 per cent on cost of concrete i.e. cost
of material, labour and machinery

Page 7 of 394

4240.00
2543.64

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

e)

Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

Quantity

Rate Rs

7936.16
87297.77

Rate per cum = (a+b+c+d+e+f)/15

12.8

Remarks/
Input ref.

13226.93

Cost for 15 cum = a+b+c+d+e+f

Note

Cost Rs

5819.85
say

5820.00

Needle Vibrator is an item of minor T & P which is already


included in overhead charges. Hence not added in rate
analysis of cement concrete works.
PCC Grade M20
Unit : cum
Taking output = 15 cum
a)

b)

c)

Material
Cement

tonne

5.16

5940.00

30650.40

M-081

Coarse sand

cum

6.75

2400.00

16200.00

M-005

40 mm Aggregate

cum

5.40

659.00

3558.60

M-055

20 mm Aggregate

cum

5.40

942.00

5086.80

M-053

10 mm Aggregate

cum

2.70

1063.00

2870.10

M-051

Mate

day

0.86

673.00

578.78

L-12

Mason

day

1.50

500.00

750.00

L-11

Mazdoor

day

20.00

377.00

7540.00

L-13

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

218.00

1308.00

P&M-009

Generator 33 KVA

hour

6.00

349.00

2094.00

P&M-079

Labour

Machinery

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
d)
Formwork @ 4 per cent on cost of concrete i.e. cost
of material, labour and machinery
e) Overhead charges @ 0.2 on (a+b+c+d)
f)

4710.00
2825.47
14692.43

Contractor's profit @ 0.1 on (a+b+c+d+e)

8815.46

Cost for 15 cum = a+b+c+d+e+f

96970.03

Rate per cum = (a+b+c+d+e+f)/15


12.8

C
Case I

6464.67
say

6465.00

RCC Grade M20


Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a)

b)

c)

Material
Cement

tonne

5.21

5940.00

30947.40

M-081

Coarse sand

cum

6.75

2400.00

16200.00

M-005

20 mm Aggregate

cum

8.10

942.00

7630.20

M-053

10 mm Aggregate

cum

5.40

1063.00

5740.20

M-051

Mate

day

0.86

673.00

578.78

L-12

Mason

day

1.50

500.00

750.00

L-11

Mazdoor

day

20.00

377.00

7540.00

L-13

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

218.00

1308.00

P&M-009

Generator 33 KVA

hour

6.00

349.00

2094.00

P&M-079

Labour

Machinery

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
d) Formwork @ 4 per cent on (a+b+c)
e)

Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

4853.00
2911.54
15140.02
9084.01

Cost for 15 cum = a+b+c+d+e+f

99924.16

Rate per cum = ( a+b+c+d+e+f )/15

6661.61
say

Page 8 of 394

6662.00

Sr No
12.8 C

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Case II With Batching Plant, Transit Mixer and Concrete Pump


Unit : cum
Taking Output = 120 cum
a) Material

b)

c)

Cement

tonne

41.66

5940.00

247460.40

M-081

Coarse Sand

cum

54.00

2400.00

129600.00

M-004

20 mm Aggregate

cum

64.80

942.00

61041.60

M-053

10 mm Aggregate

cum

43.20

1063.00

45921.60

M-051

Mate

day

0.84

673.00

565.32

Mason

day

3.00

500.00

1500.00

L-11

Mazdoor

day

18.00

377.00

6786.00

L-13

Batching Plant @ 20 cum/hour

hour

6.00

2094.00

12564.00

P&M-002

Generator 100 KVA

hour

6.00

654.00

3924.00

P&M-080

Loader 1 cum capacity

hour

6.00

756.00

4536.00

P&M-017

Transit Mixer 4 cum capacity for lead upto 1 km.

hour

15.00

873.00

13095.00

P&M-049

tonne.km

300L

input

240.00

Labour

Machinery

Lead beyond 1 km, L-lead in km

Concrete Pump

hour

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
d) Formwork @ 4 per cent on cost of concrete i.e. cost
of material, labour and machinery
e) Overhead charges @ 0.2 on (a+b+c+d)
f)

#VALUE!
#VALUE!

Contractor's profit @ 0.1 on (a+b+c+d+e)

#VALUE!
#VALUE!

Rate per cum = ( a+b+c+d+e+f )/120


D
Case I

#VALUE! P&M-050
Lead= 1
km
1440.00 P&M-007

#VALUE!

Cost for 120 cum = a+b+c+d+e+f

12.8

L-12

#VALUE!
say

#VALUE!

PCC Grade M25


Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a)

b)

c)

Material
Cement

tonne

5.99

5940.00

35580.60

M-081

Coarse sand

cum

6.75

2400.00

16200.00

M-005

40 mm Aggregate

cum

5.40

659.00

3558.60

M-055

20 mm Aggregate

cum

5.40

942.00

5086.80

M-053

10 mm Aggregate

cum

2.70

1063.00

2870.10

M-051

Mate

day

0.86

673.00

578.78

L-12

Mason

day

1.50

500.00

750.00

L-11

Mazdoor

day

20.00

377.00

7540.00

L-13

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

218.00

1308.00

P&M-009

Generator 33 KVA

hour

6.00

349.00

2094.00

P&M-079

Labour

Machinery

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
d) Formwork @ 3.75 per cent of (a+b+c)
e)

Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

5038.00
2833.76
15680.13
9408.08

Cost for 15 cum = a+b+c+d+e+f

103488.84

Rate per cum = ( a+b+c+d+e+f )/15

6899.26
say

12.8 D

Case II With Batching Plant, Transit Mixer and Concrete Pump


Unit : cum
Page 9 of 394

6899.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Taking Output = 120 cum


a)

b)

c)

Material
Cement

tonne

47.95

5940.00

284823.00

M-081

Coarse sand

cum

54.00

2400.00

129600.00

M-004

40 mm Aggregate

cum

43.20

659.00

28468.80

M-055

20 mm Aggregate

cum

43.20

942.00

40694.40

M-053

10 mm Aggregate

cum

21.60

1063.00

22960.80

M-051

Mate

day

0.84

673.00

565.32

Mason

day

3.00

500.00

1500.00

L-11

Mazdoor

day

18.00

377.00

6786.00

L-13

Batching Plant @ 20 cum/hour

hour

6.00

2094.00

12564.00

P&M-002

Generator 100 KVA

hour

6.00

654.00

3924.00

P&M-080

Loader 1 cum capacity

hour

6.00

756.00

4536.00

P&M-017

hour

15.00

873.00

13095.00

P&M-049

tonne.km

300L

input

240.00

Labour

Machinery

Transit Mixer 4 cum capacity for lead upto 1 km.


Transit Mixer 4 cum capacity lead beyond 1 Km, L lead in Kilometer
Concrete Pump

hour

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
d)
Formwork @ 3.75 per cent of cost of concrete i.e.
cost of material, labour and machinery
e) Overhead charges @ 0.2 on (a+b+c+d)
f)

#VALUE!
#VALUE!

Contractor's profit @ 0.1 on (a+b+c+d+e)

#VALUE!
#VALUE!

Rate per cum = (a+b+c+d+e+f)/120


E
Case I

#VALUE! P&M-050
Lead= 1
km
1440.00 P&M-007

#VALUE!

cost of 120 cum = a+b+c+d+e+f

12.8

L-12

#VALUE!
say

#VALUE!

RCC Grade M25


Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a)

b)

c)

Material
Cement

tonne

6.05

5940.00

35937.00

M-081

Coarse sand

cum

6.75

2400.00

16200.00

M-005

20 mm Aggregate

cum

8.10

942.00

7630.20

M-053

10 mm Aggregate

cum

5.40

1063.00

5740.20

M-051

Mate

day

0.86

673.00

578.78

L-12

Mason

day

1.50

500.00

750.00

L-11

Mazdoor

day

20.00

377.00

7540.00

L-13

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

218.00

1308.00

P&M-009

Generator 33 KVA

hour

6.00

349.00

2094.00

P&M-079

Labour

Machinery

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
d) Formwork @ 3.75 per cent of a+b+c.
e)

Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

5186.00
2916.68
16138.97
9683.38

cost of 15 cum = a+b+c+d+e+f

106517.22

Rate per cum (a+b+c+d+e+f )/15

7101.15
say

12.8 E

Case II With Batching Plant, Transit Mixer and Concrete Pump


Unit: cum
Taking Output = 120 cum
a)

Material

Page 10 of 394

7101.00

Sr No

Ref. to
MoRTH
Spec.

Description

b)

c)

Unit

Rate Rs

tonne

48.38

5940.00

287377.20

M-081

cum

54.00

2400.00

129600.00

M-004

20 mm Aggregate

cum

64.80

942.00

61041.60

M-053

10 mm Aggregate

cum

43.20

1063.00

45921.60

M-051

Mate

day

0.84

673.00

565.32

Mason

day

3.00

500.00

1500.00

L-11

Mazdoor

day

18.00

377.00

6786.00

L-13

Batching Plant @ 20 cum/hour

hour

6.00

2094.00

12564.00

P&M-002

Generator 100 KVA

hour

6.00

654.00

3924.00

P&M-080

Loader 1 cum capacity 1 cum

hour

6.00

756.00

4536.00

P&M-017

Transit Mixer 4 cum capacity for lead upto 1 km.

hour

15.00

873.00

13095.00

P&M-049

tonne.km

300L

input

6.00

240.00

Labour

hour

#VALUE! P&M-050
Lead= 1
km
1440.00

P&M-007

#VALUE!
#VALUE!
#VALUE!

Contractor's profit @ 0.1 on (a+b+c+d+e)

#VALUE!

cost of 120 cum = a+b+c+d+e+f

#VALUE!

Rate per cum (a+b+c+d+e+f )/120

#VALUE!
say

L-12

Machinery

Concrete Pump

Case I

Remarks/
Input ref.

Coarse sand

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
d)
Formwork @ 3.75 per cent on cost of concrete i.e.
cost of material, labour and machinery
e) Overhead charges @ 0.2 on (a+b+c+d)

12.8

Cost Rs

Cement

Transit Mixer 4 cum capacity lead beyond 1 Km, L lead in Kilometer

f)

Quantity

#VALUE!

PCC Grade M30


Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a)

b)

c)

Material
Cement

tonne

6.08

5940.00

36115.20

M-081

Coarse sand

cum

6.75

2400.00

16200.00

M-005

40 mm Aggregate

cum

5.40

659.00

3558.60

M-055

20 mm Aggregate

cum

5.40

942.00

5086.80

M-053

10 mm Aggregate

cum

2.70

1063.00

2870.10

M-051

Mate

day

0.86

673.00

578.78

L-12

Mason

day

1.50

500.00

750.00

L-11

Mazdoor

day

20.00

377.00

7540.00

L-13

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

218.00

1308.00

P&M-009

Generator 33 KVA

hour

6.00

349.00

2094.00

P&M-079

Labour

Machinery

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
d) Formwork @ 3.50 per cent of cost of concrete i.e.
cost of material, labour and machinery
e) Overhead charges @ 0.2 on (a+b+c+d)
f)

5074.00
2663.55
15753.01

Contractor's profit @ 0.1 on (a+b+c+d+e)

9451.80

cost of 15 cum = a+b+c+d+e+f

103969.84

Rate per cum (a+b+c+d+e+f )/15


12.8 F

6931.32
say

6931.00

Case II Using Batching Plant, Transit Mixer and Concrete Pump


Unit : cum
Taking Output = 120 cum
a)

Material
Cement

tonne

48.60

5940.00

288684.00

M-081

Coarse sand

cum

54.00

2400.00

129600.00

M-004

Page 11 of 394

Sr No

Ref. to
MoRTH
Spec.

Description

b)

c)

Unit

Rate Rs

cum

43.20

659.00

28468.80

M-055

cum

43.20

942.00

40694.40

M-053

10 mm Aggregate

cum

21.60

1063.00

22960.80

M-051

Mate

day

0.84

673.00

565.32

Mason

day

3.00

500.00

1500.00

L-11

Mazdoor

day

18.00

377.00

6786.00

L-13

Batching Plant @ 20 cum/hour

hour

6.00

2094.00

12564.00

P&M-002

Generator 100 KVA

hour

6.00

654.00

3924.00

P&M-080

Loader 1 cum capacity

hour

6.00

756.00

4536.00

P&M-017

Transit Mixer 4 cum capacity for lead upto 1 km.

hour

15.00

873.00

13095.00

P&M-049

tonne.km

300L

input

6.00

240.00

Labour

hour

#VALUE! P&M-050
Lead= 1
km
1440.00

P&M-007

#VALUE!
#VALUE!
#VALUE!

Contractor's profit @ 0.1 on (a+b+c+d+e)

#VALUE!

cost of 120 cum = a+b+c+d+e+f

#VALUE!

Rate per cum (a+b+c+d+e+f )/120


G

L-12

Machinery

Concrete Pump

Case I

Remarks/
Input ref.

20 mm Aggregate

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
d) Formwork @ 3.50 per cent of cost of concrete i.e.
cost of material, labour and machinery
e) Overhead charges @ 0.2 on (a+b+c+d)

12.8

Cost Rs

40 mm Aggregate

Transit Mixer 4 cum capacity lead beyond 1 Km, L lead in Kilometer

f)

Quantity

#VALUE!
say

#VALUE!

RCC Grade M30


Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a)

b)

c)

Material
Cement

tonne

6.10

5940.00

36234.00

M-081

Coarse sand

cum

6.75

2400.00

16200.00

M-005

20 mm Aggregate

cum

8.10

942.00

7630.20

M-053

10 mm Aggregate

cum

5.40

1063.00

5740.20

M-051

Mate

day

0.86

673.00

578.78

L-12

Mason

day

1.50

500.00

750.00

L-11

Mazdoor

day

20.00

377.00

7540.00

L-13

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

218.00

1308.00

P&M-009

Generator 33 KVA

hour

6.00

349.00

2094.00

P&M-079

Labour

Machinery

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
d) Formwork @ 3.5 per cent on cost of concrete i.e.
cost of material, labour and machinery
e) Overhead charges @ 0.2 on (a+b+c+d)
f)

5206.00
2732.63
16161.56

Contractor's profit @ 0.1 on (a+b+c+d+e)

9696.94

cost of 15 cum = a+b+c+d+e+f

106666.31

Rate per cum = (a+b+c+d+e+f)/15


12.8 G

Case II

7111.09
say

7111.00

Using Batching Plant, Transit Mixer and Concrete Pump


Unit = cum
Taking output = 120 cum
a)

Material
Cement

tonne

48.80

5940.00

289872.00

M-081

Coarse sand

cum

54.00

2400.00

129600.00

M-004

20 mm Aggregate

cum

64.80

942.00

61041.60

M-053

10 mm Aggregate

cum

43.20

1063.00

45921.60

M-051

Page 12 of 394

Sr No

Ref. to
MoRTH
Spec.

Description
b)

c)

Unit

Rate Rs

day

0.84

673.00

565.32

Mason

day

3.00

500.00

1500.00

L-11

Mazdoor

day

18.00

377.00

6786.00

L-13

Batching Plant @ 20 cum/hour

hour

6.00

2094.00

12564.00

P&M-002

Generator 100 KVA

hour

6.00

654.00

3924.00

P&M-080

Loader 1 cum capacity

hour

6.00

756.00

4536.00

P&M-017

Transit Mixer 4 cum capacity for lead upto 1 km.

hour

15.00

873.00

13095.00

P&M-049

tonne.km

300L

input

6.00

240.00

hour

#VALUE! P&M-050
Lead= 1
km
1440.00 P&M-007

#VALUE!
#VALUE!
#VALUE!

Contractor's profit @ 0.1 on (a+b+c+d+e)

#VALUE!

cost of 120 cum = a+b+c+d+e+f

#VALUE!

Rate per cum (a+b+c+d+e+f )/120


H

L-12

Machinery

Concrete Pump

Case I

Remarks/
Input ref.

Labour

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
d) Formwork @ 3.5 per cent of cost of concrete i.e. cost
of material, labour and machinery
e) Overhead charges @ 0.2 on (a+b+c+d)

12.8

Cost Rs

Mate

Transit Mixer 4 cum capacity lead beyond 1 Km, L lead in Kilometer

f)

Quantity

#VALUE!
say

#VALUE!

RCC Grade M35


Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a)

b)

c)

Material
Cement

tonne

6.33

5940.00

37600.20

M-081

Coarse sand

cum

6.75

2400.00

16200.00

M-005

20 mm Aggregate

cum

8.10

942.00

7630.20

M-053

10 mm Aggregate

cum

5.40

1063.00

5740.20

M-051

Mate

day

0.86

673.00

578.78

L-12

Mason

day

1.50

500.00

750.00

L-11

Mazdoor

day

20.00

377.00

7540.00

L-13

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

218.00

1308.00

P&M-009

Generator 33 KVA

hour

6.00

349.00

2094.00

P&M-079

Labour

Machinery

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
d) Formwork @ 3 per cent on a+b+c
e)

Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

5297.00
2383.24
16364.92
9818.95

cost of 15 cum = a+b+c+d+e+f

108008.50

Rate per cum = (a+b+c+d+e+f)/15


12.8 H

7200.57
say

7201.00

Case II Using Batching Plant, Transit Mixer and Concrete Pump


Unit ; cum
Taking Output = 120 cum
a)

b)

Material
Cement

tonne

50.64

5940.00

300801.60

M-081

Coarse sand

cum

54.00

2400.00

129600.00

M-004

20 mm Aggregate

cum

64.80

942.00

61041.60

M-053

10 mm Aggregate

cum

43.20

1063.00

45921.60

M-051

Mate

day

0.84

673.00

565.32

L-12

Mason

day

3.00

500.00

1500.00

L-11

Labour

Page 13 of 394

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Mazdoor
c)

Rate Rs

Remarks/
Input ref.

day

18.00

377.00

6786.00

L-13

Batching Plant @ 20 cum/hour

hour

6.00

2094.00

12564.00

P&M-002

Generator 100 KVA

hour

6.00

654.00

3924.00

P&M-080

Loader1 cum capacity

hour

6.00

756.00

4536.00

P&M-017

Transit Mixer 4 cum capacity for lead upto 1 km.

hour

15.00

873.00

13095.00

P&M-049

tonne.km

300L

input

6.00

240.00

Concrete Pump

hour

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
d)
Formwork @ 3 per cent on cost of concrete i.e. cost
of material, labour and machinery
e) Overhead charges @ 0.2 on (a+b+c+d)

#VALUE! P&M-050
Lead= 1
km
1440.00

P&M-007

#VALUE!
#VALUE!
#VALUE!

Contractor's profit @ 0.1 on (a+b+c+d+e)

#VALUE!

cost of 120 cum = a+b+c+d+e+f

#VALUE!

Rate per cum = (a+b+c+d+e+f)/120


Note:

Cost Rs

Machinery

Transit Mixer 4 cum capacity lead beyond 1 Km, L lead in Kilometer

f)

Quantity

#VALUE!
say

#VALUE!

Where ever concrete is carried out using batching plant,


transit mixer, concrete pump, Admixtures @ 0.4 per cent of
weight of cement may be added for achieving desired slump
of concrete.

WELL FOUNDATION
12.9

1200

Providing and Constructing Temporary Island 16 m


diameter for Construction of Well Foundation for 8m dia.
Well.
Assuming depth of water 1.0 m and height of island to
be 1.25 m.
Unit = 1 No
Taking output = 1 No.
a)

b)

c)

Material
Earth (compacted)

cum

251.20

137.0

34414.40

M-092

Sand bags

each

750.00

22.00

16500.00

M-159

Labour
Mate

day

0.40

673.00

269.20

L-12

Mazdoor for filling sand bags, stitching and placing

day

15.00

377.00

5655.00

L-13

hour

20.00

800.00

16000.00

P&M-012

Machinery
Crane with grab 1 cum capacity

Consumables @ 2.5 per cent of (c) above


d)

Overhead charges @ 0.2 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

400.00
14647.72
8788.63

Rate per No. (a+b+c+d+e)


Note
12.9

96674.95
say

96675.00

It is assumed that earth will be available within the working


space of crane with grab bucket.
Assuming depth of water 4.0 m and height of island 4.5
m.
Unit = 1No
Taking output = 1 No
a)

b)

Material
Earth (compacted)

cum

904.32

137.00

123891.84

M-092

Sand bags

each

6000.00

22.00

132000.00

M-159

Wooden ballies 8" Dia and 9 m long

each

95.00

337.00

32015.00

M-194

Wooden ballies 2" Dia for bracing

metre

190.00

input

#VALUE!

M-193

Labour
Mate

day

5.60

673.00

3768.80

L-12

Mazdoor for piling 8" dia ballies for piling 8" dia ballies

day

18.00

377.00

6786.00

L-13

Mazdoor for bracing with 2" dia ballies

day

12.00

377.00

4524.00

L-13

Page 14 of 394

Sr No

Ref. to
MoRTH
Spec.
c)

Quantity

Rate Rs

Unit

Mazdoor for filling sand bags, stitching and placing

day

110.00

377.00

41470.00

L-13

hour

50.00

800.00

40000.00

P&M-012

Machinery
Crane with grab 1 cum capacity

Consumables and other arrangements for piling ballies @


2.5 per cent of (a+b+c).
d) Overhead charges @ 0.2 on (a+b+c)

#VALUE!

e)

#VALUE!

#VALUE!

Contractor's profit @ 0.1 on (a+b+c+d)

Rate per No. (a+b+c+d+e)


Note

12.9

Cost Rs

Remarks/
Input ref.

Description

#VALUE!
say

#VALUE!

For other well diameters rate can be worked out on the basis
of cross-sectional area of well. The diameter of the island
shall be in the conformity with clause 1203.2 of MoRTH
specifications.
Providing and constructing one span service road to
reach island location from one pier location to another
pier location
Assuming span length 30 m, width of service road 10m and
depth of water 1m
Unit = 1 meter
Taking output = 30 metre
a)

b)

c)

Material
Earth

cum

450.00

137.00

61650.00

M-092

Sand bags

each

300.00

22.00

6600.00

M-159

Mate

day

0.24

673.00

161.52

L-12

Mazdoor for filling sand bags, stitching and placing

day

6.00

377.00

2262.00

L-13

Front end Loader 1 cum capacity

hour

27.00

756.00

20412.00

P&M-017

Tipper 5.5 cum capacity

hour

28.00

291.00

8148.00

P&M-048

Labour

Machinery

d)

Overhead charges @ 0.2 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

19846.70
11908.02

Cost for 30 m (a+b+c+d+e)

130988.25

Rate per m (a+b+c+d+e)/30


12.10

1200 &
1900

4366.27
say

4366.00

Providing and Laying Cutting Edge of Mild Steel


weighing 40 kg per metre for Well Foundation complete
as per Drawing and Technical Specification.
Unit = 1 MT
Taking output = 1 MT
a)

Material
Structural steel in plates, angles, etc including 5 per
cent wastage
Nuts & bolts

b)

tonne

1.05

44100.00

46305.00

M-179

Kg

20.00

81.00

1620.00

M-130

day

1.32

673.00

888.36

L-12

Fitter

day

5.50

456.00

2508.00

L-08

Blacksmith

day

5.50

500.00

2750.00

L-02

Welder

day

5.50

500.00

2750.00

L-02

Mazdoor

day

16.50

377.00

6220.50

L-13

Labour

(for cutting, bending, making holes, joining, welding and


erecting in position)
Mate

Electrodes, cutting gas and other consumables @ 10 per


cent of cost of (a) above
c) Overhead charges @ 0.2 on (a+b)
d)

4792.50
13566.87

Contractor's profit @ 0.1 on (a+b+c)

8140.12

Rate per MT (a+b+c+d)

89541.36
say

12.11

1200,
1500 &
1700

Plain/Reinforced Cement Concrete, in Well Foundation


complete as per Drawing and Technical Specification.

Page 15 of 394

89541.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Unit = 1 cum
Taking output = 1 cum
A

Well curb

(i)

RCC M20 Grade


Same as for 12.8 (C) except for formwork which shall be@
20 per cent of the cost of concrete instead of 4 per cent.

Case I

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c)
d) formwork @ 20 per cent of the cost of concrete

4853.00

e)

Overhead charges @ 0.2 on (a+b+c+d)

1164.72

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

970.60
698.83

Rate perm (a+b+c+d+e+f)

7687.15
say

12.11 A (i)

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
d) formwork @ 20 per cent of the cost of concrete

#VALUE!

e)

Overhead charges @ 0.2 on (a+b+c+d)

#VALUE!

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

#VALUE!

#VALUE!

Rate perm (a+b+c+d+e+f)

#VALUE!
say

12.11 A

7687.00

Case II With Batching Plant, Transit Mixer and Concrete Pump

(ii)

#VALUE!

RCC M25 Grade


Same as for 12.8 (E) except for formwork which shall be@
20 per cent of the cost of concrete instead of 3.75 per cent.

Case I

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c)
d) formwork @ 20 per cent of the cost of concrete

5186.00

e)

Overhead charges @ 0.2 on (a+b+c+d)

1244.64

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

1037.20
746.78

Rate perm (a+b+c+d+e+f)

8214.62
say

12.11 A
(ii)

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
d) formwork @ 20 per cent of the cost of concrete

#VALUE!

e)

Overhead charges @ 0.2 on (a+b+c+d)

#VALUE!

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

#VALUE!

#VALUE!

Rate perm (a+b+c+d+e+f)

#VALUE!
say

12.11 A

8215.00

Case II With Batching Plant, Transit Mixer and Concrete Pump

(iii)

#VALUE!

RCC M35 Grade


Same as for 12.8 (H) except for formwork which shall be@
20 per cent of the cost of concrete instead of 3.0 per cent.

Case I

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c)
d) formwork @ 20 per cent of the cost of concrete

5297.00

e)

Overhead charges @ 0.2 on (a+b+c+d)

1271.28

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

1059.40
762.77

Rate perm (a+b+c+d+e+f)

8390.45
say

12.11 A
(iii)

8390.00

Case II With Batching Plant, Transit Mixer and Concrete Pump


Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c)
Page 16 of 394

#VALUE!

Remarks/
Input ref.

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

d)

formwork @ 20 per cent of the cost of concrete

#VALUE!

e)

Overhead charges @ 0.2 on (a+b+c+d)

#VALUE!

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

#VALUE!

Rate perm (a+b+c+d+e+f)

#VALUE!
say

Note.

12.11

Cost Rs

#VALUE!

If curb concrete is carried out within steel liner, cost of


formwork shall be excluded.

Well steining

(I)

PCC M15 Grade


Same as for 12.8 (A) except for formwork which shall be @
10 per cent of the cost of concrete instead of 4 per cent.

Case I

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete
e)

Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

4240.00
424.00
932.80
559.68

Rate perm (a+b+c+d+e+f)

6156.48
say

12.11 B

(ii)

6156.00

PCC M20 Grade


Same as for 12.8 (B) except for formwork which shall be @
10 per cent of the cost of concrete instead of 4 per cent.

Case I

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete

4710.00

e)

Overhead charges @ 0.2 on (a+b+c+d)

1036.20

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

471.00
621.72

Rate perm (a+b+c+d+e+f)

6838.92
say

12.11 B

(iii)

6839.00

RCC M20 Grade


Same as for 12.8 (C) except for formwork which shall be @
10 per cent of the cost of concrete instead of 4 per cent.

Case I

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete

4853.00

e)

Overhead charges @ 0.2 on (a+b+c+d)

1067.66

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

640.60

485.30

Rate perm (a+b+c+d+e+f)

7046.56
say

12.11 B
(iii)

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
d) formwork @ 10 per cent of the cost of concrete

#VALUE!

e)

Overhead charges @ 0.2 on (a+b+c+d)

#VALUE!

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

#VALUE!

#VALUE!

Rate perm (a+b+c+d+e+f)

#VALUE!
say

12.11 B

7047.00

Case II With Batching Plant, Transit Mixer and Concrete Pump

(iv)

#VALUE!

PCC M25 Grade


Same as for 12.8 (D) except for formwork which shall be @
10 per cent of the cost of concrete instead of 4 per cent.

Case I

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c)
Page 17 of 394

5038.00

Remarks/
Input ref.

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

d)

formwork @ 10 per cent of the cost of concrete

e)

Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

Quantity

Rate Rs

503.80
1108.36
665.02

Rate perm (a+b+c+d+e+f)

7315.18
say

12.11 B
(iv)

7315.00

Case II With Batching Plant, Transit Mixer and Concrete Pump


Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete

#VALUE!

e)

Overhead charges @ 0.2 on (a+b+c+d)

#VALUE!

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

#VALUE!

#VALUE!

Rate perm (a+b+c+d+e+f)

#VALUE!
say

'12.11 B

Cost Rs

(v)

#VALUE!

RCC M25 Grade


Same as for 12.8 (E) except for formwork which shall be @
10 per cent of the cost of concrete instead of 3.5 per cent.

Case I

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete

5186.00

e)

Overhead charges @ 0.2 on (a+b+c+d)

1140.92

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

518.60
684.55

Rate perm (a+b+c+d+e+f)

7530.07
say

12.11 B
(v)

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
d) formwork @ 10 per cent of the cost of concrete

#VALUE!

e)

Overhead charges @ 0.2 on (a+b+c+d)

#VALUE!

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

#VALUE!

#VALUE!

Rate perm (a+b+c+d+e+f)

#VALUE!
say

'12.11 B

7530.00

Case II With Batching Plant, Transit Mixer and Concrete Pump

(vi)

#VALUE!

PCC M30 Grade


Same as for 12.8 (F) except for formwork which shall be @
10 per cent of the cost of concrete instead of 3.5 per cent.

Case I

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete

5074.00

e)

Overhead charges @ 0.2 on (a+b+c+d)

1116.28

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

507.40
669.77

Rate perm (a+b+c+d+e+f)

7367.45
say

12.11 B
(vi)

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
d) formwork @ 10 per cent of the cost of concrete

#VALUE!

e)

Overhead charges @ 0.2 on (a+b+c+d)

#VALUE!

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

#VALUE!

#VALUE!

Rate perm (a+b+c+d+e+f)

#VALUE!
say

'12.11 B

7367.00

Case II With Batching Plant, Transit Mixer and Concrete Pump

(vii)

RCC M30 Grade


Same as for 12.8 (G) except for formwork which shall be @
10 per cent of the cost of concrete instead of 3.5 per cent.

Case I

Using Concrete Mixer


Page 18 of 394

#VALUE!

Remarks/
Input ref.

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
d) formwork @ 10 per cent of the cost of concrete

5206.00

e)

Overhead charges @ 0.2 on (a+b+c+d)

1145.32

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

687.19
7559.11
say

7559.00

Case II With Batching Plant, Transit Mixer and Concrete Pump


Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete

#VALUE!

e)

Overhead charges @ 0.2 on (a+b+c+d)

#VALUE!

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

#VALUE!

#VALUE!

Rate perm (a+b+c+d+e+f)

#VALUE!
say

'12.11 B

Remarks/
Input ref.

520.60

Rate perm (a+b+c+d+e+f)


12.11 B
(vii)

Cost Rs

(viii)

#VALUE!

RCC M35 Grade


Same as for 12.8 (H) except for formwork which shall be @
10 per cent of the cost of concrete instead of 3 per cent.

Case I

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c)
d) formwork @ 10 per cent of the cost of concrete

5297.00

e)

Overhead charges @ 0.2 on (a+b+c+d)

1165.34

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

529.70
699.20

Rate perm (a+b+c+d+e+f)

7691.24
say

12.11 B
(viii)

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
d) formwork @ 10 per cent of the cost of concrete

#VALUE!

e)

Overhead charges @ 0.2 on (a+b+c+d)

#VALUE!

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

#VALUE!

#VALUE!

Rate perm (a+b+c+d+e+f)


'12.11 B

7691.00

Case II With Batching Plant, Transit Mixer and Concrete Pump

(ix)

#VALUE!
say

#VALUE!

RCC M40 Grade


Using Batching Plant, Transit Mixer and Concrete Pump
Unit = cum
Taking output = 120 cum
a)

Material
Cement

tonne

51.60

5940.00

306504.00

M-081

Coarse Sand

cum

54.00

2400.00

129600.00

M-004

20 mm Aggregate

cum

64.80

942.00

61041.60

M-053

10 mm Aggregate

cum

43.20

1063.00

45921.60

M-051

kg

206.00

input

#VALUE!

M-180

Mate

day

0.84

673.00

565.32

L-12

Meson

day

3.00

500.00

1500.00

L-11

Mazdoor

day

18.00

377.00

6786.00

L-13

Admixture
b)

c)

Labour

Machinery
Batching Plant

hour

6.00

2094.00

12564.00

P&M-002

Generator 100 KVA

hour

6.00

654.00

3924.00

P&M-080

Loader 1 cum capacity

hour

6.00

756.00

4536.00

P&M-017

Transit Mixer 4 cum capacity for lead upto 1 km.

hour

15.00

873.00

13095.00

P&M-049

tonne.km

300xL

input

hour

6.00

240.00

Transit Mixer 4 cum capacity for lead beyond 1 km.


Concrete Pump
Page 19 of 394

#VALUE! Lead= 1 ,
P&M-050
1440.00 P&M-007

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
d) Formwork @ 10 per cent on cost of concrete i.e. cost
of material, labour and machinery
e) Overhead charges @ 0.2 on (a+b+c+d)
f)

Quantity

Rate Rs

#VALUE!
#VALUE!

Contractor's profit @ 0.1 on (a+b+c+d+e)

#VALUE!
#VALUE!

Rate per cum = (a+b+c+d+e+f)/120


C

Remarks/
Input ref.

#VALUE!

cost of 120 cum = a+b+c+d+e+f

12.11 C

Cost Rs

#VALUE!
say

#VALUE!

Bottom Plug
Concrete to be placed using tremie pipe

(i)
Case I

Note: 10% extra cement to be added where under water


concreting is involved
PCC Grade M20
Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a)

b)

c)

Material
Cement

tonne

5.55

5940.00

32967.00

M-081

Coarse sand

cum

6.75

2400.00

16200.00

M-005

40 mm Aggregate

cum

5.40

659.00

3558.60

M-055

20 mm Aggregate

cum

5.40

942.00

5086.80

M-053

10 mm Aggregate

cum

2.70

1063.00

2870.10

M-051

Admixture

Kg

18.60

input

#VALUE!

M-180

Mate

day

0.90

673.00

605.70

L-12

Mason

day

1.50

500.00

750.00

L-11

Mazdoor

day

20.00

377.00

7540.00

L-13

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

218.00

1308.00

P&M-009

Generator 33 KVA

hour

6.00

349.00

2094.00

P&M-079

Light Crane 3 tonnes capacity for handling tremie pipe

hour

6.00

334.00

2004.00

P&M-013

Labour

Machinery

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
Add 5 per cent of cost of material and labour towards cost
of forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe..

#VALUE!
#VALUE!

d)

Overhead charges @ 0.2 on (a+b+c)

#VALUE!

e)

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!

cost of 15 cum = a+b+c+d+e

#VALUE!

Rate per cum = (a+b+c+d+e)/15


12.11 C
(i)

#VALUE!
say

#VALUE!

Case II Using Batching Plant, Transit Mixer and Crane/concrete


pump
Unit ; cum
Taking Output = 120 cum
a)

b)

c)

Material
Cement

tonne

44.40

5940.00

263736.00

M-081

Coarse sand

cum

54.00

2400.00

129600.00

M-004

20 mm Aggregate

cum

64.80

942.00

61041.60

M-053

10 mm Aggregate

cum

43.20

1063.00

45921.60

M-051

Admixture

Kg

148.80

input

#VALUE!

M-180

Mate

day

0.88

673.00

592.24

L-12

Mason

day

3.00

500.00

1500.00

L-11

Mazdoor

day

18.00

377.00

6786.00

L-13

Labour

Machinery
Page 20 of 394

Sr No

Ref. to
MoRTH
Spec.

Unit

Batching Plant @ 20 cum/hour

hour

6.00

2094.00

12564.00

P&M-002

Generator 100 KVA

hour

6.00

654.00

3924.00

P&M-080

Loader 1 cum capacity

hour

6.00

756.00

4536.00

P&M-017

Transit Mixer 4 cum capacity for lead upto 1 km.

hour

15.00

873.00

13095.00

P&M-049

tonne.km

300L

input

6.00

240.00

Transit Mixer 4 cum capacity, lead beyond 1 Km, L lead in Kilometer


Concrete Pump

hour

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
Add 5 per cent of cost of material and labour towards cost
of forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe..

Quantity

Rate Rs

#VALUE!

d)

Overhead charges @ 0.2 on (a+b+c)

#VALUE!

e)

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!
#VALUE!

Rate per cum = (a+b+c+d+e)/120


(ii)
Case I

#VALUE! P&M-050
Lead= 1
km
1440.00 P&M-007

#VALUE!

cost of 120 cum = a+b+c+d+e

'12.11 C

Cost Rs

Remarks/
Input ref.

Description

#VALUE!
say

#VALUE!

PCC Grade M25


Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a)

b)

c)

Material
Cement

tonne

5.99

5940.00

35580.60

M-081

Coarse sand

cum

6.75

2400.00

16200.00

M-005

40 mm Aggregate

cum

5.40

659.00

3558.60

M-055

20 mm Aggregate

cum

5.40

942.00

5086.80

M-053

10 mm Aggregate

cum

2.70

1063.00

2870.10

M-051

Admixture

Kg

21.60

input

#VALUE!

M-180

Mate

day

0.90

673.00

605.70

L-12

Mason

day

1.50

500.00

750.00

L-11

Mazdoor

day

20.00

377.00

7540.00

L-13

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

218.00

1308.00

P&M-009

Generator 33 KVA

hour

6.00

349.00

2094.00

P&M-079

hour

6.00

334.00

2004.00

P&M-013

Labour

Machinery

Light Crane of 3 tonnes capacity for handling tremie


pipe
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c)
Add 5 per cent of cost of material and labour towards cost
of forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe..

#VALUE!
#VALUE!

d)

Overhead charges @ 0.2 on (a+b+c)

#VALUE!

e)

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!

cost of 15 cum = a+b+c+d+e

#VALUE!

Rate per cum = (a+b+c+d+e)/15


12.11 C
(ii)

#VALUE!
say

#VALUE!

Case II Using Batching Plant, Transit Mixer and Crane/concrete


pump
Unit = cum
Taking output = 120 cum
a)

Material
Cement

tonne

47.88

5940.00

284407.20

M-081

Coarse sand

cum

54.00

2400.00

129600.00

M-004

20 mm Aggregate

cum

64.80

942.00

61041.60

M-053

10 mm Aggregate

cum

43.20

1063.00

45921.60

M-051

Admixture

Kg

172.80

input

#VALUE!

M-180

Page 21 of 394

Sr No

Ref. to
MoRTH
Spec.

Description
b)

c)

Unit

Quantity

Rate Rs

Labour
day

0.88

673.00

592.24

Mason

day

3.00

500.00

1500.00

L-11

Mazdoor

day

18.00

377.00

6786.00

L-13

Batching Plant @ 20 cum/hour

hour

6.00

2094.00

12564.00

P&M-002

Generator 100 KVA

hour

6.00

654.00

3924.00

P&M-080

Loader 1 cum capacity

hour

6.00

756.00

4536.00

P&M-017

Transit Mixer 4 cum capacity for lead upto 1 km.

hour

15.00

873.00

13095.00

P&M-049

tonne.km

300L

input

6.00

240.00

Concrete Pump

hour

#VALUE! P&M-050
Lead= 1
km
1440.00 P&M-007

#VALUE!
#VALUE!

d)

Overhead charges @ 0.2 on (a+b+c)

#VALUE!

e)

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!

cost of 120 cum = a+b+c+d+e

#VALUE!

Rate per cum = (a+b+c+d+e)/120

#VALUE!
say

(iii)

L-12

Machinery

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
Add 5 per cent of cost of material and labour towards cost
of forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe..

Case I

Remarks/
Input ref.

Mate

Transit Mixer 4 cum capacity, lead beyond 1 Km, L lead in Kilometer

'12.11 C

Cost Rs

#VALUE!

PCC Grade M30


Using Concrete Mixer
Unit = 1 cum
Taking output = 15 cum
a)

b)

c)

Material
Cement

tonne

6.08

5940.00

36115.20

M-081

Coarse sand

cum

6.75

2400.00

16200.00

M-005

40 mm Aggregate

cum

5.40

659.00

3558.60

M-055

20 mm Aggregate

cum

5.40

942.00

5086.80

M-053

10 mm Aggregate

cum

2.70

1063.00

2870.10

M-051

Admixture

Kg

21.60

input

#VALUE!

M-180

Mate

day

0.90

673.00

605.70

L-12

Mason

day

1.50

500.00

750.00

L-11

Mazdoor

day

20.00

377.00

7540.00

L-13

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

218.00

1308.00

P&M-009

Generator 33 KVA

hour

6.00

349.00

2094.00

P&M-079

hour

6.00

334.00

2004.00

P&M-013

Labour

Machinery

Light Crane of 3 tonnes capacity for handling tremie


pipe
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c)
Add 5 per cent of cost of material and labour towards cost
of forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe..

#VALUE!
#VALUE!

d)

Overhead charges @ 0.2 on (a+b+c)

#VALUE!

e)

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!

cost of 15 cum = a+b+c+d+e

#VALUE!

Rate per cum = (a+b+c+d+e)/15

#VALUE!
say

12.11 C
(iii)

Case II Using Batching Plant, Transit Mixer and Crane/concrete


pump
Unit = cum
Taking output = 120 cum
a)

Material
Page 22 of 394

#VALUE!

Sr No

Ref. to
MoRTH
Spec.

Description

b)

c)

Unit

Quantity

Rate Rs

tonne

48.64

5940.00

288921.60

M-081

Coarse sand

cum

54.00

2400.00

129600.00

M-004

20 mm Aggregate

cum

64.80

942.00

61041.60

M-053

10 mm Aggregate

cum

43.20

1063.00

45921.60

M-051

Admixture

Kg

172.80

input

#VALUE!

M-180

Mate

day

0.88

673.00

592.24

L-12

Mason

day

3.00

500.00

1500.00

L-11

Mazdoor

day

18.00

377.00

6786.00

L-13

Batching Plant @ 20 cum/hour

hour

6.00

2094.00

12564.00

P&M-002

Generator 100 KVA

hour

6.00

654.00

3924.00

P&M-080

Loader 1 cum capacity

hour

6.00

756.00

4536.00

P&M-017

Transit Mixer 4 cum capacity for lead upto 1 km.

hour

15.00

873.00

13095.00

P&M-049

tonne.km

300L

input

6.00

240.00

Labour

Machinery

Concrete Pump

hour

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
Add 5 per cent of cost of material and labour towards cost
of forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe..

1440.00

P&M-007

#VALUE!

d)

Overhead charges @ 0.2 on (a+b+c)

#VALUE!

e)

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!
#VALUE!

Rate per cum = (a+b+c+d+e)/120


(iv)

#VALUE! P&M-050
Lead= 1
km

#VALUE!

cost of 120 cum = a+b+c+d+e

Case I

Remarks/
Input ref.

Cement

Transit Mixer 4 cum capacity, lead beyond 1 Km, L lead in Kilometer

'12.11 C

Cost Rs

#VALUE!
say

#VALUE!

PCC Grade M35


Using Concrete Mixer
Unit = 1 cum
Taking output = 15 cum
a)

b)

c)

Material
Cement

tonne

6.29

5940.00

37362.60

M-081

Coarse sand

cum

6.75

2400.00

16200.00

M-005

40 mm Aggregate

cum

5.40

659.00

3558.60

M-055

20 mm Aggregate

cum

5.40

942.00

5086.80

M-053

10 mm Aggregate

cum

2.70

1063.00

2870.10

M-051

Admixture

Kg

21.60

input

#VALUE!

M-180

Mate

day

0.90

673.00

605.70

L-12

Mason

day

1.50

500.00

750.00

L-11

Mazdoor

day

20.00

377.00

7540.00

L-13

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

218.00

1308.00

P&M-009

Generator 33 KVA

hour

6.00

349.00

2094.00

P&M-079

hour

6.00

334.00

2004.00

P&M-013

Labour

Machinery

Light Crane of 3 tonnes capacity for handling tremie


pipe
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c)
Add 5 per cent of cost of material and labour towards cost
of forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe..

#VALUE!
#VALUE!

d)

Overhead charges @ 0.2 on (a+b+c)

#VALUE!

e)

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!

cost of 15 cum = a+b+c+d+e

#VALUE!

Rate per cum = (a+b+c+d+e)/15

#VALUE!

Page 23 of 394

Sr No

12.11 C
(iv)

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

say

#VALUE!

Remarks/
Input ref.

Case II Using Batching Plant, Transit Mixer and Crane/concrete


pump
Unit = cum
Taking output = 120 cum
a)

b)

c)

Material
Cement

tonne

50.28

5940.00

298663.20

M-081

Coarse sand

cum

54.00

2400.00

129600.00

M-004

20 mm Aggregate

cum

64.80

input

#VALUE!

M-053

10 mm Aggregate

cum

43.20

input

#VALUE!

M-051

Admixture

Kg

172.80

input

#VALUE!

M-180

Mate

day

0.88

673.00

592.24

L-12

Mason

day

3.00

500.00

1500.00

L-11

Mazdoor

day

18.00

377.00

6786.00

L-13

Batching Plant @ 20 cum/hour

hour

6.00

2094.00

12564.00

P&M-002

Generator 100 KVA

hour

6.00

654.00

3924.00

P&M-080

Loader 1 cum capacity

hour

6.00

756.00

4536.00

P&M-017

Transit Mixer 4 cum capacity for lead upto 1 km.

hour

15.00

873.00

13095.00

P&M-049

tonne.km

300L

input

6.00

240.00

Labour

Machinery

Transit Mixer 4 cum capacity, lead beyond 1 Km, L lead in Kilometer


Concrete Pump

hour

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
Add 5 per cent of cost of material and labour towards cost
of forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe..

#VALUE!

d)

Overhead charges @ 0.2 on (a+b+c)

#VALUE!

e)

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!
#VALUE!

Rate per cum = (a+b+c+d+e)/120

#VALUE!
say

Intermediate plug

(i)

Grade M20 PCC

Case I

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
d) Overhead charges @ 0.2 on (a+b+c)

#VALUE!

e)

#VALUE!

#VALUE!

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!
say

Case II Using Batching Plant, Transit Mixer and Crane/concrete


pump
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c)
d) Overhead charges @ 0.2 on (a+b+c)
e)

#VALUE!

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!
#VALUE!
say

(ii)

Case I

#VALUE!

#VALUE!

Rate per cum = (a+b+c+d+e)


'12.11 D

#VALUE!

Same as in bottom plug concrete, excluding cost of forming


sump, protective bunds, chiseling etc.
Using Concrete Mixer

Rate per cum = (a+b+c+d+e)


12.11 D
(i)

1440.00

#VALUE!

cost of 120 cum = a+b+c+d+e

12.11

#VALUE! P&M-050
Lead= 1
km

#VALUE!

Grade M25 PCC


Same as in bottom plug concrete, excluding cost of forming
sump, protective bunds, chiseling etc.
Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c)
d) Overhead charges @ 0.2 on (a+b+c)
Page 24 of 394

#VALUE!
#VALUE!

P&M-007

Sr No

Ref. to
MoRTH
Spec.

Description
e)

Unit

Quantity

Rate Rs

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!

Rate per cum = (a+b+c+d+e)

#VALUE!
say

12.11 D
(ii)

Case II Using Batching Plant, Transit Mixer and Crane/concrete


pump
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c)
d) Overhead charges @ 0.2 on (a+b+c)
e)

#VALUE!

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!
#VALUE!
say

(iii)

Case I

Same as in bottom plug concrete, excluding cost of forming


sump, protective bunds, chiseling etc.
Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c)
d) Overhead charges @ 0.2 on (a+b+c)

#VALUE!

e)

#VALUE!

#VALUE!

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!
say

Case II Using Batching Plant, Transit Mixer and Crane/concrete


pump
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c)
d) Overhead charges @ 0.2 on (a+b+c)
e)

#VALUE!

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!
#VALUE!
say

Top plug

(i)

Grade M15 PCC

#VALUE!

#VALUE!

Rate per cum = (a+b+c+d+e)


12.11

#VALUE!

Grade M30 PCC

Rate per cum = (a+b+c+d+e)


12.11 D
(iii)

#VALUE!

#VALUE!

Rate per cum = (a+b+c+d+e)


'12.11 D

Cost Rs

#VALUE!

Same as Item 12.8(a) excluding formwork


Case I

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c)
d) Overhead charges @ 0.2 on (a+b+c)
e)

4240.00
848.00

Contractor's profit @ 0.1 on (a+b+c+d)

508.80

Rate per cum = (a+b+c+d+e)

5596.80
say

'12.11 E

(ii)

5597.00

Grade M20 PCC


Same as Item 12.8(b) excluding formwork

Case I

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c)
d) Overhead charges @ 0.2 on (a+b+c)
e)

4710.00
942.00

Contractor's profit @ 0.1 on (a+b+c+d)

565.20

Rate per cum = (a+b+c+d+e)

6217.20
say

'12.11 E

(iii)

Same as Item 12.8 (d)


Case I

excluding formwork

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c)
d) Overhead charges @ 0.2 on (a+b+c)
e)

5038.00
1007.60

Contractor's profit @ 0.1 on (a+b+c+d)

604.56

Rate per cum = (a+b+c+d+e)

6650.16
say

12.11 E
(iii)

6217.00

Grade M25 PCC

Case II Using Batching Plant, Transit Mixer and Crane/concrete


pump

Page 25 of 394

6650.00

Remarks/
Input ref.

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
d) Overhead charges @ 0.2 on (a+b+c)

#VALUE!

e)

#VALUE!
#VALUE!
say

(iv)

Remarks/
Input ref.

#VALUE!

Contractor's profit @ 0.1 on (a+b+c+d)

Rate per cum = (a+b+c+d+e)


'12.11 E

Cost Rs

#VALUE!

Grade M30 PCC


Same as Item 12.8(f) excluding formwork

Case I

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c)
d) Overhead charges @ 0.2 on (a+b+c)
e)

5074.00
1014.80

Contractor's profit @ 0.1 on (a+b+c+d)

608.88

Rate per cum = (a+b+c+d+e)

6697.68
say

12.11 E
(iv)

Case II Using Batching Plant, Transit Mixer and Crane/concrete


pump
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c)
d) Overhead charges @ 0.2 on (a+b+c)
e)

#VALUE!
#VALUE!

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!

Rate per cum = (a+b+c+d+e)


12.11

F
(i)
Case I

6698.00

#VALUE!
say

#VALUE!

Well cap
RCC Grade M20
Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a)

b)

c)

Material
Cement

tonne

5.12

5940.00

30412.80

M-081

Coarse sand

cum

6.75

2400.00

16200.00

M-005

20 mm Aggregate

cum

8.10

942.00

7630.20

M-053

10 mm Aggregate

cum

5.40

1063.00

5740.20

M-051

Mate

day

0.86

673.00

578.78

L-12

Mason

day

1.50

500.00

750.00

L-11

Mazdoor

day

20.00

377.00

7540.00

L-13

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

218.00

1308.00

P&M-009

Generator 33 KVA

hour

6.00

349.00

2094.00

P&M-079

Labour

Machinery

Form Work @ 4 per cent of a+b+c


d)

Overhead charges @ 0.2 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

2890.16
15028.83
9017.30

cost of 15 cum = a+b+c+d+e

99190.26

Rate per cum = (a+b+c+d+e)/15


12.11 F (i)

6612.68
say

6613.00

Case II Using Batching Plant, Transit Mixer and Concrete Pump


Unit = cum
Taking output = 120 cum
a)

b)

Material
Cement

tonne

40.92

5940.00

243064.80

M-081

Coarse sand

cum

54.00

2400.00

129600.00

M-004

20 mm Aggregate

cum

64.80

942.00

61041.60

M-053

10 mm Aggregate

cum

43.20

1063.00

45921.60

M-051

Mate

day

0.84

673.00

565.32

L-12

Mason

day

3.00

500.00

1500.00

L-11

Labour

Page 26 of 394

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Mazdoor
c)

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

day

18.00

377.00

6786.00

L-13

Batching Plant @ 20 cum/hour

hour

6.00

2094.00

12564.00

P&M-002

Generator 100 KVA

hour

6.00

654.00

3924.00

P&M-080

Loader (capacity 1 cum)

hour

6.00

756.00

4536.00

P&M-017

13095.00

P&M-049

Machinery

Transit Mixer ( capacity 4.0 cu.m )


Transit Mixer 4 cum capacity for lead upto 1 km.
Lead beyond 1 Km, L - lead in Kilometer

Concrete Pump

hour

15.00

873.00

tonne.km

300L

input

hour

6.00

240.00

#VALUE!

d)

Overhead charges @ 0.2 on (a+b+c)

#VALUE!

e)

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!

(ii)

P&M-007

#VALUE!

Rate per cum = (a+b+c+d+e)/120

Case I

1440.00

Formwork @ 4 per cent of (a+b+c)

cost of 120 cum = a+b+c+d+e

12.11 F

#VALUE! P&M-050
Lead= 1
km

#VALUE!
say

#VALUE!

RCC Grade M25


Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a)

b)

c)

Material
Cement

tonne

6.05

5940.00

35937.00

M-081

Coarse sand

cum

6.75

2400.00

16200.00

M-005

20 mm Aggregate

cum

8.10

942.00

7630.20

M-053

10 mm Aggregate

cum

5.40

1063.00

5740.20

M-051

Mate

day

0.86

673.00

578.78

L-12

Mason

day

1.50

500.00

750.00

L-11

Mazdoor

day

20.00

377.00

7540.00

L-13

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

218.00

1308.00

P&M-009

Generator 33 KVA

hour

6.00

349.00

2094.00

P&M-079

Labour

Machinery

Form Work @ 3.75 per cent of a+b+c

2916.68

d)

Overhead charges @ 0.2 on (a+b+c)

16138.97

e)

Contractor's profit @ 0.1 on (a+b+c+d)

9683.38

cost of 15 cum = a+b+c+d+e

106517.22

Rate per cum = (a+b+c+d+e)/15


12.11 F
(ii)

7101.15
say

7101.00

Case II Using Batching Plant, Transit Mixer and Concrete Pump


Unit = cum
Taking output = 120 cum
a)

b)

c)

Material
Cement

tonne

48.40

5940.00

287496.00

M-081

Coarse sand

cum

54.00

2400.00

129600.00

M-004

20 mm Aggregate

cum

64.80

942.00

61041.60

M-053

10 mm Aggregate

cum

43.20

1063.00

45921.60

M-051

Mate

day

0.84

673.00

565.32

Mason

day

3.00

500.00

1500.00

L-11

Mazdoor

day

18.00

377.00

6786.00

L-13

Batching Plant @ 20 cum/hour

hour

6.00

2094.00

12564.00

P&M-002

Generator 100 KVA

hour

6.00

654.00

3924.00

P&M-080

Loader (capacity 1 cum)

hour

6.00

756.00

4536.00

P&M-017

Labour
L-12

Machinery

Transit Mixer ( capacity 4.0 cu.m )


Page 27 of 394

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Transit Mixer 4 cum capacity for lead upto 1 km.


Lead beyond 1 Km, L - lead in Kilometer

Concrete Pump

Quantity

Rate Rs

hour

15.00

873.00

tonne.km

300L

input

hour

6.00

240.00

(iii)

Remarks/
Input ref.
P&M-049

#VALUE! P&M-050
Lead= 1
km
1440.00
#VALUE!

d)

Overhead charges @ 0.2 on (a+b+c)

#VALUE!

e)

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!

P&M-007

#VALUE!

Rate per cum = (a+b+c+d+e)/120

Case I

13095.00

Formwork @ 3.75 per cent of ( a+b+c)

cost of 120 cum = a+b+c+d+e

12.11 F

Cost Rs

#VALUE!
say

#VALUE!

RCC Grade M30


Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a)

b)

c)

Material
Cement

tonne

6.10

5940.00

36234.00

M-081

Coarse sand

cum

6.75

2400.00

16200.00

M-005

20 mm Aggregate

cum

8.10

942.00

7630.20

M-053

10 mm Aggregate

cum

5.40

1063.00

5740.20

M-051

Mate

day

0.86

673.00

578.78

L-12

Mason

day

1.50

500.00

750.00

L-11

Mazdoor

day

20.00

377.00

7540.00

L-13

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

218.00

1308.00

P&M-009

Generator 33 KVA

hour

6.00

349.00

2094.00

P&M-079

Labour

Machinery

Formwork @ 3.5 per cent of (a+b+c)

2732.63

d)

Overhead charges @ 0.2 on (a+b+c)

16161.56

e)

Contractor's profit @ 0.1 on (a+b+c+d)

9696.94

cost of 15 cum = a+b+c+d+e

106666.31

Rate per cum = (a+b+c+d+e)/15


12.11 F
(iii)

7111.09
say

7111.00

Case II Using Batching Plant, Transit Mixer and Concrete Pump


Unit = cum
Taking output = 120 cum
a)

b)

c)

Material
Cement

tonne

48.79

5940.00

289812.60

M-081

Coarse sand

cum

54.00

2400.00

129600.00

M-004

20 mm Aggregate

cum

64.80

942.00

61041.60

M-053

10 mm Aggregate

cum

43.20

1063.00

45921.60

M-051

Mate

day

0.84

673.00

565.32

Mason

day

3.00

500.00

1500.00

L-11

Mazdoor

day

18.00

377.00

6786.00

L-13

Batching Plant @ 20 cum/hour

hour

6.00

2094.00

12564.00

P&M-002

Generator 100 KVA

hour

6.00

654.00

3924.00

P&M-080

Loader (capacity 1 cum)

hour

6.00

756.00

4536.00

P&M-017

13095.00

P&M-049

Labour
L-12

Machinery

Transit Mixer ( capacity 4.0 cu.m )


Transit Mixer 4 cum capacity for lead upto 1 km.
Lead beyond 1 Km, L - lead in Kilometer

Concrete Pump
d)

hour

15.00

873.00

tonne.km

300L

input

hour

6.00

240.00

#VALUE! P&M-050
Lead= 1
km
1440.00

Formwork @ 3.5 per cent of (a+b+c)

#VALUE!

Overhead charges @ 0.2 on (a+b+c)

#VALUE!

Page 28 of 394

P&M-007

Sr No

Ref. to
MoRTH
Spec.

Description
e)

Unit

Quantity

Rate Rs

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!

Rate per cum = (a+b+c+d+e)/120


(iv)
Case I

Remarks/
Input ref.

#VALUE!

cost of 120 cum = a+b+c+d+e

12.11 F

Cost Rs

#VALUE!
say

#VALUE!

RCC Grade M35


Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a)

b)

c)

Material
Cement

tonne

6.33

5940.00

37600.20

M-081

Coarse sand

cum

6.75

2400.00

16200.00

M-005

20 mm Aggregate

cum

8.10

942.00

7630.20

M-053

10 mm Aggregate

cum

5.40

1063.00

5740.20

M-051

Mate

day

0.86

673.00

578.78

L-12

Mason

day

1.50

500.00

750.00

L-11

Mazdoor

day

20.00

377.00

7540.00

L-13

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

218.00

1308.00

P&M-009

Generator 33 KVA

hour

6.00

349.00

2094.00

P&M-079

Labour

Machinery

Formwork @ 3 per cent of (a+b+c)


d)

Overhead charges @ 0.2 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

2383.24
16364.92
9818.95

cost of 15 cum = a+b+c+d+e

108008.50

Rate per cum = (a+b+c+d+e)/15


12.11 F
(iv)

7200.57
say

7201.00

Case II Using Batching Plant, Transit Mixer and Concrete Pump


Unit = cum
Taking output = 120 cum
a)

b)

c)

Material
Cement

tonne

50.64

5940.00

300801.60

M-081

Coarse sand

cum

54.00

2400.00

129600.00

M-004

20 mm Aggregate

cum

64.80

942.00

61041.60

M-053

10 mm Aggregate

cum

43.20

1063.00

45921.60

M-051

Mate

day

0.84

673.00

565.32

Mason

day

3.00

500.00

1500.00

L-11

Mazdoor

day

18.00

377.00

6786.00

L-13

Batching Plant @ 20 cum/hour

hour

6.00

2094.00

12564.00

P&M-002

Generator 100 KVA

hour

6.00

654.00

3924.00

P&M-080

Loader (capacity 1 cum)

hour

6.00

756.00

4536.00

P&M-017

13095.00

P&M-049

Labour
L-12

Machinery

Transit Mixer ( capacity 4.0 cu.m )


Transit Mixer 4 cum capacity for lead upto 1 km.
Lead beyond 1 Km, L - lead in Kilometer

Concrete Pump

hour

15.00

873.00

tonne.km

300L

input

hour

6.00

240.00

#VALUE! P&M-050
Lead= 1
km
1440.00

Formwork @ 3 per cent of (a+b+c)

#VALUE!

d)

Overhead charges @ 0.2 on (a+b+c)

#VALUE!

e)

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!

cost of 120 cum = a+b+c+d+e

#VALUE!

Rate per cum = (a+b+c+d+e)/120

#VALUE!
say

Page 29 of 394

#VALUE!

P&M-007

Sr No

Ref. to
MoRTH
Spec.

Description
Note

'12.11 F

(v)

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Where ever concrete is carried out using batching plant,


transit mixer, concrete pump, Admixtures @ 0.4 per cent of
weight of cement may be added for achieving desired slump
of concrete.
RCC M40 Grade
Using Batching Plant, Transit Mixer and Concrete Pump
Unit = cum
Taking output = 120 cum
a)

Material
Cement

tonne

52.20

5940.00

310068.00

M-081

Coarse Sand

cum

54.00

2400.00

129600.00

M-004

20 mm Aggregate

cum

64.80

942.00

61041.60

M-053

10 mm Aggregate

cum

43.20

1063.00

45921.60

M-051

kg

206.00

input

#VALUE!

M-180

Mate

day

0.84

673.00

565.32

L-12

Mason

day

3.00

500.00

1500.00

L-11

Mazdoor

day

18.00

377.00

6786.00

L-13

Admixture
b)

c)

Labour

Machinery
Batching Plant

hour

6.00

2094.00

12564.00

P&M-002

Generator 100 KVA

hour

6.00

654.00

3924.00

P&M-080

Loader 1 cum capacity

hour

6.00

756.00

4536.00

P&M-017

Transit Mixer 4 cum capacity for lead upto 1 km.

hour

15.00

873.00

13095.00

P&M-049

tonne.km

300.L

input

hour

6.00

240.00

Transit Mixer 4 cum capacity for lead beyond 1 km.

Concrete Pump

#VALUE!

d)

Formwork @ 3 per cent on cost of concrete i.e. cost of


material, labour and machinery
Overhead charges @ 0.2 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!

#VALUE!

cost of 120 cum = a+b+c+d+e

#VALUE!

Rate per cum = (a+b+c+d+e)/120

#VALUE!
say

12.12

Section
1200

#VALUE! P&M-050
Lead= 1
km
1440.00 P&M-007

#VALUE!

Sinking of 6 m external diameter well (other than


pneumatic method of sinking) through all types of strata
namely sandy soil, clayey soil and rock as shown
against each case, complete as per drawing and
technical specifications. Depth of sinking is reckoned
from bed level.
Unit = Running Meter.
Taking output = 1 m
Diameter of well - 6 m.
A
(i)

Sandy Soil
Depth below bed level upto 3.0 M
Rate of sinking = 0.50 m per hour.
a)

b)

Labour
Mate

day

0.12

673.00

80.76

L-12

Sinker ( skilled )

day

1.00

408.00

408.00

L-15

Sinking helper ( semi-skilled )

day

2.00

377.00

754.00

L-14

hour

2.00

349.00

698.00

P&M-075

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b)

c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

69.80
402.11
241.27

Rate per metre = (a+b+c+d)

2653.94
say

12.12 A

(ii)

Beyond 3m upto 10m depth


Page 30 of 394

2654.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Rate of sinking = 0.33 m per hour.


a)

b)

Labour
Mate

day

0.15

673.00

100.95

L-12

Sinker

day

1.25

408.00

510.00

L-15

Sinking helper ( semi-skilled )

day

2.50

377.00

942.50

L-14

hour

3.00

349.00

1047.00

P&M-075

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories
Consumables in sinking @10 per cent of (b)

c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

104.70
541.03
324.62

Rate per metre = (a+b+c+d)

3570.80
say

12.12 A

(iii)
a

Beyond 10m upto 20m


Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m

5%

3750.00

12th m

5%

3938.00

13th m

5%

4135.00

14th m

5%

4342.00

15th m

5%

4559.00

16th m

5%

4787.00

17th m

5%

5026.00

18th m

5%

5277.00

19th m

5%

5541.00

20th m

5%

5818.00

Total Cost from 10m upto 20m

47173.00

Avg Rate per metre


12.12 A

(iv)
a
b

4717.00

Beyond 20m upto 30 m


Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports,
loading arrangement and Labour.
21st m

7.5%

6254.00

Including 20%
for Kentledge
7505.00

22nd m

7.5%

6723.00

8068.00

23rd m

7.5%

7227.00

8672.00

24th m

7.5%

7769.00

9323.00

25th m

7.5%

8352.00

10022.00

26th m

7.5%

8978.00

10774.00

27th m

7.5%

9651.00

11581.00

28th m

7.5%

10375.00

12450.00

29th m

7.5%

11153.00

13384.00

30th m

7.5%

11989.00

14387.00

88471.00

106166.00

8847.00

10617.00

Total Cost from 20m upto 30m


Avg Rate per metre
12.12 A

(v)

Beyond 30m upto 40 m

Add 10 per cent for every additional meter depth of sinking


over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports,
loading arrangement and Labour.
31st m

10%

13188.00

Including 20%
for Kentledge
15826.00

32nd

10%

14507.00

17408.00

33rd m

10%

15958.00

19150.00

34th m

10%

17554.00

21065.00

35th m

10%

19309.00

23171.00

36th m

10%

21240.00

25488.00

37th m

10%

23364.00

28037.00

38th m

10%

25700.00

30840.00

39th m

10%

28270.00

33924.00

Page 31 of 394

3571.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

40th m

10%

Total Cost from 30m upto 40m


Avg Rate per metre
12.12

Quantity

Rate Rs

31097.00

37316.00

210187.00

252225.00

21019.00

25223.00

Cost Rs

Remarks/
Input ref.

Clayey Soil ( 6m dia. Well )


Unit = Running Meter.
Taking output = 1 meter

(i)

Depth below bed level upto 3.0 M


Rate of sinking = 0.33 m per hour.
a)

b)

Labour
Mate

day

0.15

673.00

100.95

L-12

Sinker ( skilled )

day

1.50

408.00

612.00

L-15

Sinking helper ( semi-skilled )

day

2.25

377.00

848.25

L-14

hour

3.00

349.00

1047.00

P&M-075

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories
Consumables in sinking @ 10 per cent of (b)

c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

104.70
542.58
325.55

Rate per metre = (a+b+c+d)

3581.03
say

12.12 B

(ii)

3581.00

Beyond 3m upto 10m depth


Rate of sinking = 0.17 m per hour.
a)

b)

Labour
Mate

day

0.30

673.00

201.90

L-12

Sinker

day

3.00

408.00

1224.00

L-15

Sinking helper ( semi-skilled )

day

4.50

377.00

1696.50

L-14

hour

6.00

349.00

2094.00

P&M-075

hour

2.00

300.00

600.00

P&M-063

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for
cutting hard clay.
Consumables in sinking @ 10 per cent of (b)

c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

269.40
1217.16
730.30

Rate per metre = (a+b+c+d)

8033.26
say

12.12 B

(iii)
a
b

Beyond 10 m upto 20 m
Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add for dewatering @ 5 per cent of cost, if required.

11th m

5%

8435.00

8857.00

12th m

5%

8857.00

9300.00

13th m

5%

9300.00

9765.00

14th m

5%

9765.00

10253.00

15th m

5%

10253.00

10766.00

16th m

5%

10766.00

11304.00

17th m

5%

11304.00

11869.00

18th m

5%

11869.00

12462.00

19th m

5%

12462.00

13085.00

20th m

5%

13085.00

13739.00

106096.00

111400.00

10610.00

11140.00

Total Cost from 10m upto 20m


Avg Rate per metre
12.12 B

(iv)
a

Including for
dewatering @
5% of cost, if
required

Beyond 20m upto 30 m


Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter

Page 32 of 394

8033.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Add 5 per cent of cost for dewatering of the cost, if required

Add 25 per cent of cost for Kentledge including supports,


loading arrangement and Labour ).

7.5%

14066.00

17583.00

18462.00

22nd m

7.5%

15121.00

18901.00

19846.00

23rd m

7.5%

16255.00

20319.00

21335.00

24th m

7.5%

17474.00

21843.00

22935.00

25th m

7.5%

18785.00

23481.00

24655.00

26th m

7.5%

20194.00

25243.00

26505.00

27th m

7.5%

21709.00

27136.00

28493.00

28th m

7.5%

23337.00

29171.00

30630.00

29th m

7.5%

25087.00

31359.00

32927.00

30th m

7.5%

26969.00

33711.00

35397.00

198997.00

248747.00

261185.00

19900.00

24875.00

26119.00

Avg Rate per metre


Beyond 30m upto 40 m

Add 10 per cent for every additional meter depth of sinking


over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering, if required

Add 20 per cent of cost for Kentledge including supports,


loading arrangement and Labour).

31st m

10%

29666.00

35599.00

32nd

10%

32633.00

39160.00

41118.00

33rd m

10%

35896.00

43075.00

45229.00

34th m

10%

39486.00

47383.00

49752.00

35th m

10%

43435.00

52122.00

54728.00

36th m

10%

47779.00

57335.00

60202.00

37th m

10%

52557.00

63068.00

66221.00

38th m

10%

57813.00

69376.00

72845.00

39th m

10%

63594.00

76313.00

80129.00

40th m

10%

69953.00

83944.00

88141.00

472812.00

567375.00

595744.00

47281.00

56738.00

59574.00

Avg Rate per metre


C

Remarks/
Input ref.

Including 20% Including 5%


for Kentledge
for
dewatering, if
required

Total Cost from 30m upto 40m


12.12

Cost Rs

21st m

(v)

Rate Rs

Including 25% Including 5%


for Kentledge
for
dewatering, if
required

Total Cost from 20m upto 30m


12.12 B

Quantity

37379.00

Soft Rock (6m dia well )


Unit = Running Meter.
Taking output = 1 m
Depth in Soft rock strata up to 3m
Rate of sinking = 0.25 m per hour.
a)

b)

Labour
Mate

day

0.92

673.00

619.16

L-12

Sinker ( skilled )

day

3.00

408.00

1224.00

L-15

Sinking helper ( semi-skilled )

day

20.00

377.00

7540.00

L-14

Diver

day

0.50

471.00

235.50

L-07

hour

4.00

349.00

1396.00

P&M-075

hour

3.50

300.00

1050.00

P&M-063

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Air compressor with pneumatic breakers
Consumables in sinking @ 10 per cent of (b)

244.60
615.46

c)

Add for dewatering @ of 5 per cent of (a+b), if


required
Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

2584.94
1550.97

Rate per metre = (a+b+c+d)

17060.63
say
Page 33 of 394

17061.00

Sr No

Ref. to
MoRTH
Spec.

12.12

Description
D

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Hard Rock (6m dia well )


Unit = Running Meter
Taking output = 1 m
Depth in hard rock strata upto 3 m
Rate of sinking = 0.17 m per hour.
a)

b)

c)

Material
Gelatine 80 per cent

Kg

4.00

74.08

296.32

Electric Detonators

each

18.00

11.00

198.00 M-094/100

Mate

day

1.56

673.00

1049.88

L-12

Driller

day

2.00

400.00

800.00

L-06

Blaster

day

0.25

396.00

99.00

L-03

Mazdoor

day

12.00

377.00

4524.00

L-13

Mazdoor (Skilled)

day

4.00

408.00

1632.00

L-15

hour

6.00

349.00

2094.00

P&M-075

hour

2.00

300.00

600.00

P&M-063

Labour

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Hire & running charges of compressor with pneumatic
breaker/Jack hammer for drilling.
Dewatering @ 5 per cent of cost of (b+c), if required.

539.94

Consumables in sinking @ 10 per cent of cost of (b).


d)

Overhead charges @ 0.2 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

269.40
2420.51
1452.31

Rate per metre = (a+b+c+d+e)


12.13

Section
1200

M-104

15975.36
say

15975.00

Sinking of 7 m external diameter well ( other than


pneumatic method of sinking ) through all types of
strata namely sandy soil, clayey soil and rock as shown
against each case, complete as per drawing and
technical specifications. Depth of sinking is reckoned
from bed level.
Unit = Running Meter.
Taking output = 1 m
Diameter of well - 7 m.
A
(i)

Sandy Soil
Depth below bed level upto 3.0 M
Rate of sinking = 0.30 m per hour.
a)

b)

Labour
Mate

day

0.15

673.00

100.95

L-12

Sinker ( skilled )

day

1.25

408.00

510.00

L-15

Sinking helper ( semi-skilled )

day

2.50

377.00

942.50

L-14

hour

3.25

349.00

1134.25

P&M-075

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b)

113.43

c)

Overhead charges @ 0.2 on (a+b)

560.23

d)

Contractor's profit @ 0.1 on (a+b+c)

280.11

Rate per metre = (a+b+c+d)


12.13 A

(ii)

3641.46

Beyond 3m upto 10m depth

7282.93

Rate of sinking = 0.22 m per hour.


a)

b)

7283.00

Labour
Mate

day

0.18

673.00

121.14

L-12

Sinker

day

1.50

408.00

612.00

L-15

Sinking helper ( semi-skilled )

day

3.00

377.00

1131.00

L-14

hour

4.50

349.00

1570.50

P&M-075

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b)

c)

say

Overhead charges @ 0.2 on (a+b)


Page 34 of 394

157.05
718.34

Sr No

Ref. to
MoRTH
Spec.

Description
d)

Unit

Quantity

Rate Rs

Contractor's profit @ 0.1 on (a+b+c)

431.00

Rate per metre = (a+b+c+d)

4741.03
say

12.13 A

(iii)
a

Beyond 10m upto 20m


Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m

0.165

5%

4978.00

12th m

5%

5227.00

13th m

5%

5488.00

14th m

5%

5762.00

15th m

5%

6050.00

16th m

5%

6353.00

17th m

5%

6671.00

18th m

5%

7005.00

19th m

5%

7355.00

20th m

5%

Total Cost from 10m upto 20m


(iv)
a
b

6261.00

Beyond 20m upto 30 m


Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports,
loading arrangement and Labour).
21st m

7.5%

8302.00

Including 20%
for Kentledge
9962.00

22nd m

7.5%

8925.00

10710.00

23rd m

7.5%

9594.00

11513.00

24th m

7.5%

10314.00

12377.00

25th m

7.5%

11088.00

13306.00

26th m

7.5%

11920.00

14304.00

27th m

7.5%

12814.00

15377.00

28th m

7.5%

13775.00

16530.00

29th m

7.5%

14808.00

17770.00

30th m

7.5%

15919.00

19103.00

117459.00

140952.00

11746.00

14095.00

Total Cost from 20m upto 30m


Avg Rate per metre
12.13 A

(v)

Beyond 30m upto 40 m

Add 10 per cent for every additional meter depth of sinking


over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports,
loading arrangement, and Labour etc.
31st m

10%

17511.00

Including 20%
for Kentledge
21013.00

32nd

10%

19262.00

23114.00

33rd m

10%

21188.00

25426.00

34th m

10%

23307.00

27968.00

35th m

10%

25638.00

30766.00

36th m

10%

28202.00

33842.00

37th m

10%

31022.00

37226.00

38th m

10%

34124.00

40949.00

39th m

10%

37536.00

45043.00

40th m

10%

41290.00

49548.00

279080.00

334895.00

27908.00

33490.00

Total Cost from 30m upto 40m


Avg Rate per metre
12.13

Clayey Soil ( 7m dia. Well )


Unit = Running Meter.
Taking output = 1 cum

(I)

7723.00
62612.00

Avg Rate per metre


12.13 A

Depth below bed level upto 3.0 M


Rate of sinking = 0.22 m per hour.
a)

Cost Rs

Labour
Page 35 of 394

4741.00

Remarks/
Input ref.

Sr No

Ref. to
MoRTH
Spec.

Description

b)

Unit

Quantity

Rate Rs

day

0.18

673.00

121.14

L-12

Sinker ( skilled )

day

1.50

408.00

612.00

L-15

Sinking helper ( semi-skilled )

day

3.00

377.00

1131.00

L-14

hour

4.50

349.00

1570.50

P&M-075

Machinery

d)

Overhead charges @ 0.2 on (a+b)

e)

Contractor's profit @ 0.1 on (a+b+c)

157.05
718.34
431.00

Rate per metre = (a+b+c+d)


(ii)

Remarks/
Input ref.

Mate

Hire & running charges of crane with grab bucket of


0.75 cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b)

12.13 B

Cost Rs

4741.03
say

4741.00

Beyond 3m upto 10m depth


Rate of sinking = 0.17 m per hour.
a)

b)

Labour
Mate

day

0.26

673.00

174.98

L-12

Sinker

day

2.00

408.00

816.00

L-15

Sinking helper ( semi-skilled )

day

4.00

377.00

1508.00

L-14

hour

6.00

349.00

2094.00

P&M-075

hour

3.25

300.00

209.40

P&M-063

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for
cutting hard clay.
Consumables in sinking @ 10 per cent of (b)

c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

230.34
1006.54
603.93

Rate per metre = (a+b+c+d)

6643.19
say

12.13 B

(iii)
a
b

Add 5 per cent for every additional meter depth of sinking


over the rate of sinking for the previous meter
Add for dewatering @ 5 per cent of cost, if required.

Including for
dewatering @
5% of cost, if
required

11th m

5%

6975.00

7324.00

12th m

5%

7324.00

7690.00

13th m

5%

7690.00

8075.00

14th m

5%

8075.00

8479.00

15th m

5%

8479.00

8903.00

16th m

5%

8903.00

9348.00

17th m

5%

9348.00

9815.00

18th m

5%

9815.00

10306.00

19th m

5%

10306.00

10821.00

20th m

5%

10821.00

11362.00

87736.00

92123.00

8774.00

9212.00

Total Cost from 10m upto 20m


Avg Rate per metre
12.13 B

(iv)
a
b
c

6643.00

Beyond 10 m upto 20 m

Beyond 20m upto 30 m


Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering on the cost, if required
Add 25 per cent of cost for Kentledge including supports,
loading arrangement and Labour ).

Including 25% Including 5%


for Kentledge
for
dewatering, if
required

31st m

7.5%

11633.00

14541.00

15268.00

32nd

7.5%

12505.00

15631.00

16413.00

33rd m

7.5%

13443.00

16804.00

17644.00

34th m

7.5%

14451.00

18064.00

18967.00

35th m

7.5%

15535.00

19419.00

20390.00

Page 36 of 394

Sr No

Ref. to
MoRTH
Spec.

Description

Unit
7.5%

16700.00

20875.00

21919.00

7.5%

17953.00

22441.00

23563.00

38th m

7.5%

19299.00

24124.00

25330.00

39th m

7.5%

20746.00

25933.00

27230.00

40th m

7.5%

22302.00

27878.00

29272.00

164567.00

205710.00

215996.00

16457.00

20571.00

21600.00

Avg Rate per metre


Beyond 30m upto 40 m

Add 10 per cent for every additional meter depth of sinking


over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering, if required

Add 20 per cent of cost for Kentledge including supports,


loading arrangement and Labour).

31st m

10%

24532.00

29438.00

30910.00

32nd

10%

26985.00

32382.00

34001.00

33rd m

10%

29684.00

35621.00

37402.00

34th m

10%

32652.00

39182.00

41141.00

35th m

10%

35917.00

43100.00

45255.00

36th m

10%

39509.00

47411.00

49782.00

37th m

10%

43460.00

52152.00

54760.00

38th m

10%

47806.00

57367.00

60235.00

39th m

10%

52587.00

63104.00

66259.00

40th m

10%

57846.00

69415.00

72886.00

390978.00

469172.00

492631.00

39098.00

46917.00

49263.00

Avg Rate per metre


C

Remarks/
Input ref.

Including 20% Including 5%


for Kentledge
for
dewatering, if
required

Total Cost from 30m upto 40m


12.13

Cost Rs

37th m

(v)

Rate Rs

36th m

Total Cost from 30m upto 40m


12.13 B

Quantity

Soft Rock ( 7m dia well )


Unit = Running Meter.
Taking output = 1 m
Depth in soft rock strata upto 3m
Rate of sinking = 0.22 m per hour.
a)

b)

Labour
Mate

day

0.58

673.00

390.34

L-12

Sinker ( skilled )

day

4.00

408.00

1632.00

L-15

Sinking helper ( semi-skilled )

day

10.00

377.00

3770.00

L-14

Diver

day

0.75

471.00

353.25

L-07

hour

4.50

349.00

1570.50

P&M-075

hour

3.75

300.00

1125.00

P&M-063

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Air compressor with pneumatic breakers
Consumables in sinking @ 10 per cent of (b)

269.55
442.05

c)

Add for dewatering @ of 5 per cent of (a+b), if


required
Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

1910.54
1146.32

Rate per metre = (a+b+c+d)


12.13

12609.56
say

12610.00

Hard Rock ( 7m dia well )


Unit = Running Meter
Taking output = 1 m
Depth in Hard rock strata up to 3 m
Rate of sinking = 0.17 m per hour.
a)

b)

Material
Gelatine 80 per cent

Kg

7.00

74.08

518.56

Electric Detonators

each

30.00

11.00

330.00 M-094/100

M-104

day

1.60

673.00

Labour
Mate
Page 37 of 394

1076.80

L-12

Sr No

Ref. to
MoRTH
Spec.

Description

c)

Unit

Quantity

Rate Rs

day

2.00

400.00

800.00

L-06

Blaster

day

0.25

396.00

99.00

L-03

Mazdoor

day

18.00

377.00

6786.00

L-13

Mazdoor (Skilled)

day

4.00

408.00

1632.00

L-15

Diver

day

0.50

471.00

235.50

L-07

hour

6.00

349.00

2094.00

P&M-075

hour

2.00

300.00

600.00

P&M-063

Machinery

666.17

Consumables in sinking @ 10 per cent of cost of (b).


d)

Overhead charges @ 0.2 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

336.02
3034.81
1820.88

Rate per metre = (a+b+c+d+e)


Section
1200

Remarks/
Input ref.

Driller

Hire & running charges of crane with grab bucket of


0.75 cum capacity and accessories.
Hire & running charges of compressor with pneumatic
breaker/Jack hammer for drilling.
Dewatering @ 5 per cent of cost of (b+c), if required.

12.14

Cost Rs

20029.73
say

20030.00

Sinking of 8 m external diameter well ( other than


pneumatic method of sinking ) through all types of
strata namely sandy soil, clayey soil and rock as shown
against each case, complete as per drawing and
technical specifications. Depth of sinking is reckoned
from bed level.
Unit = Running Meter.
Taking output = 1 m
Diameter of well - 8 m.
A
(i)

Sandy Soil
Depth below bed level upto 3.0 M
Rate of sinking @ 0.25 m/hour
a)

b)

Labour
Mate

day

0.18

673.00

121.14

L-12

Sinker ( skilled )

day

1.50

408.00

612.00

L-15

Sinking helper ( semi-skilled )

day

3.00

377.00

1131.00

L-14

hour

4.00

349.00

1396.00

P&M-075

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b)

c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

139.60
679.95
407.97

Rate per metre = (a+b+c+d)


12.14 A

(ii)

4487.66
say

4488.00

Beyond 3m upto 10m depth


Rate of sinking @ 0.20 m/hour
a)

b)

Labour
Mate

day

0.25

673.00

168.25

L-12

Sinker

day

1.75

408.00

714.00

L-15

Sinking helper ( semi-skilled )

day

3.50

377.00

1319.50

L-14

hour

5.00

349.00

1745.00

P&M-075

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b)

174.50

c)

Overhead charges @ 0.2 on (a+b)

824.25

d)

Contractor's profit @ 0.1 on (a+b+c)

494.55

Rate per metre = (a+b+c+d)

5440.05
say

12.14 A

(iii)
a

Beyond 10m upto 20m


Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m
12th m
Page 38 of 394

5%

5712.00

5%

5998.00

5440.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

13th m

5%

6298.00

14th m

5%

6613.00

15th m

5%

6944.00

16th m

5%

7291.00

17th m

5%

7656.00

18th m

5%

8039.00

19th m

5%

8441.00

20th m

5%

Total Cost from 10m upto 20m


(iv)
a
b

Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports,
loading arrangement and Labour.
21st m

7.5%

9528.00

22nd m

7.5%

10243.00

12292.00

23rd m

7.5%

11011.00

13213.00

24th m

7.5%

11837.00

14204.00

25th m

7.5%

12725.00

15270.00

26th m

7.5%

13679.00

16415.00

27th m

7.5%

14705.00

17646.00

28th m

7.5%

15808.00

18970.00

29th m

7.5%

16994.00

20393.00

30th m

7.5%

18269.00

21923.00

134799.00

161760.00

13480.00

16176.00

Beyond 30m upto 40 m

Add 10 per cent for every additional meter depth of sinking


over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports,
loading arrangement, and Labour etc.
31st m

10%

20096.00

Including 20%
for Kentledge
24115.00

32nd

10%

22106.00

26527.00

33rd m

10%

24317.00

29180.00

34th m

10%

26749.00

32099.00

35th m

10%

29424.00

35309.00

36th m

10%

32366.00

38839.00

37th m

10%

35603.00

42724.00

38th m

10%

39163.00

46996.00

39th m

10%

43079.00

51695.00

40th m

10%

47387.00

56864.00

47387.00

56864.00

4739.00

5686.00

Total Cost from 30m upto 40m


Avg Rate per metre
B

8863.00

Including 20%
for Kentledge
11434.00

Avg Rate per metre

12.14

Remarks/
Input ref.

7186.00

(v)

Cost Rs

Beyond 20m upto 30 m

Total Cost from 20m upto 30m


12.14 A

Rate Rs

71855.00

Avg Rate per metre


12.14 A

Quantity

Clayey Soil ( 8m dia. Well )


Unit = Running Meter.
Taking output = 1 meter

(i)

Depth from bed level upto 3.0 M


Rate of sinking @ 0.18 m/hour
a)

b)

Labour
Mate

day

0.22

673.00

148.06

L-12

Sinker ( skilled )

day

2.00

408.00

816.00

L-15

Sinking helper ( semi-skilled )

hour

3.50

377.00

1319.50

L-14

5.50

349.00

1919.50

P&M-075

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b)

c)

Overhead charges @ 0.2 on (a+b)


Page 39 of 394

191.95
879.00

Sr No

Ref. to
MoRTH
Spec.

Description
d)

Unit

Quantity

Rate Rs

Contractor's profit @ 0.1 on (a+b+c)

5801.41
say

(ii)

Remarks/
Input ref.

527.40

Rate per metre = (a+b+c+d)


12.14 B

Cost Rs

5801.00

Beyond 3m upto 10m depth


Rate of sinking @ 0.17 m/hour
a)

b)

Labour
Mate

day

0.32

673.00

215.36

L-12

Sinker

day

2.50

408.00

1020.00

L-15

Sinking helper ( semi-skilled )

day

4.50

377.00

1696.50

L-14

hour

6.00

349.00

2094.00

P&M-075

hour

3.50

300.00

1050.00

P&M-063

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for
cutting hard clay.
Consumables in sinking @ 10 per cent of (b)

c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

314.40
1278.05
766.83

Rate per metre = (a+b+c+d)

8435.14
say

12.14 B

(iii)
a
b

Add 5 per cent for every additional meter depth of sinking


over the rate of sinking for the previous meter
Add for dewatering @ 5 per cent of cost, if required.

Including for
dewatering @
5% of cost, if
required

11th m

5%

8857.00

12th m

5%

9300.00

9765.00

13th m

5%

9765.00

10253.00

14th m

5%

10253.00

10766.00

15th m

5%

10766.00

11304.00

16th m

5%

11304.00

11869.00

17th m

5%

11869.00

12462.00

18th m

5%

12462.00

13085.00

19th m

5%

13085.00

13739.00

20th m

5%

13739.00

14426.00

111400.00

116969.00

11140.00

11697.00

Total Cost from 10m upto 20m


Avg Rate per metre
12.14 B

(iv)
a
b
c

Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering on the cost, if required
Add 25 per cent of cost for Kentledge including supports,
loading arrangement and Labour ).

Including 25% Including 5%


for Kentledge
for
dewatering, if
required

31st m

7.5%

14769.00

18461.00

19384.00

32nd

7.5%

15877.00

19846.00

20838.00

33rd m

7.5%

17068.00

21335.00

22402.00

34th m

7.5%

18348.00

22935.00

24082.00

35th m

7.5%

19724.00

24655.00

25888.00

36th m

7.5%

21203.00

26504.00

27829.00

37th m

7.5%

22793.00

28491.00

29916.00

38th m

7.5%

24502.00

30628.00

32159.00

39th m

7.5%

26340.00

32925.00

34571.00

40th m

7.5%

28316.00

35395.00

37165.00

208940.00

261175.00

274234.00

20894.00

26118.00

27423.00

Avg Rate per metre


(v)

9300.00

Beyond 20m upto 30 m

Total Cost from 30m upto 40m


12.14 B

8435.00

Beyond 10 m upto 20 m

Beyond 30m upto 40 m


Page 40 of 394

Sr No

Ref. to
MoRTH
Spec.

Description
a
b
c

Unit

Add 20 per cent of cost for Kentledge including supports,


loading arrangement and Labour).

Cost Rs

Remarks/
Input ref.

Including 20% Including 5%


for Kentledge
for
dewatering, if
required

31st m

10%

31148.00

37378.00

39247.00

32nd

10%

34263.00

41116.00

43172.00

33rd m

10%

37689.00

45227.00

47488.00

34th m

10%

41458.00

49750.00

52238.00

35th m

10%

45604.00

54725.00

57461.00

36th m

10%

50164.00

60197.00

63207.00

37th m

10%

55180.00

66216.00

69527.00

38th m

10%

60698.00

72838.00

76480.00

39th m

10%

66768.00

80122.00

84128.00

40th m

10%

73445.00

88134.00

92541.00

496417.00

595703.00

625489.00

49642.00

59570.00

62549.00

Avg Rate per metre


C

Rate Rs

Add 10 per cent for every additional meter depth of sinking


over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering, if required

Total Cost from 30m upto 40m


12.14

Quantity

Soft Rock ( 8m dia well )


Unit = Running Meter.
Taking output = 1 m
Depth in soft rock strata upto 3m
Rate of sinking @ 0.20 m/hour
a)

b)

Labour
Mate

day

0.68

673.00

457.64

L-12

Sinker ( skilled )

day

4.00

408.00

1632.00

L-15

Sinking helper ( semi-skilled )

day

12.00

377.00

4524.00

L-14

Diver

day

1.00

471.00

471.00

L-07

hour

5.00

349.00

1745.00

P&M-075

hour

3.75

300.00

1125.00

P&M-063

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Air compressor with pneumatic breakers
Consumables in sinking @ 10 per cent of (b)

287.00
512.08

c)

Add for dewatering @ of 5 per cent of (a+b), if


required
Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

2150.74
1290.45

Rate per metre = (a+b+c+d)


12.14

14194.91
say

14195.00

Hard Rock ( 8m dia well )


Unit = Running Meter
Taking output = 1 m
Depth in hard rock strata upto 3 m
Rate of sinking @ 0.17 m/hour
a)

b)

c)

Material
Gelatine 80 per cent

Kg

8.00

74.08

592.64

Electric Detonators

each

32.00

11.00

352.00 M-094/100

M-104

Mate

day

1.09

673.00

733.57

L-12

Driller

day

2.00

400.00

800.00

L-06

Blaster

day

0.25

396.00

99.00

L-03

Mazdoor

day

20.00

377.00

7540.00

L-13

Mazdoor (Skilled)

day

4.00

408.00

1632.00

L-15

hour

6.00

349.00

2094.00

P&M-075

hour

2.00

300.00

600.00

P&M-063

Labour

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Hire & running charges of compressor with pneumatic
breaker/Jack hammer for drilling.
Page 41 of 394

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Dewatering @ 5 per cent of cost of (b+c), if required.

674.93

Consumables in sinking @ 10 per cent of cost of (b).

1080.46

d)

Overhead charges @ 0.2 on (a+b+c)

3239.72

e)

Contractor's profit @ 0.1 on (a+b+c+d)

Section
1200

Remarks/
Input ref.

1943.83

Rate per metre = (a+b+c+d+e)


12.15

Cost Rs

21382.15
say

21382.00

Sinking of 9 m external diameter well ( other than


pneumatic method of sinking ) through all types of
strata namely sandy soil, clayey soil and rock as shown
against each case, complete as per drawing and
technical specifications. Depth of sinking is reckoned
from bed level.
Unit = Running Meter.
Taking output = 1 m
Diameter of well - 9 m.
A
(i)

Sandy Soil
Depth below bed level upto 3.0 M
Rate of sinking @ 0.25 m/hour
a)

b)

Labour
Mate

day

0.19

673.00

127.87

L-12

Sinker ( skilled )

day

1.50

408.00

612.00

L-15

Sinking helper ( semi-skilled )

day

3.25

377.00

1225.25

L-14

hour

4.00

349.00

1396.00

P&M-075

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b)

c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

139.60
700.14
420.09

Rate per metre = (a+b+c+d)


12.15 A

(ii)

4620.95
say

4621.00

Beyond 3m upto 10m depth


Rate of sinking @ 0.18 m/hour
a)

b)

Labour
Mate

day

0.27

673.00

181.71

L-12

Sinker

day

1.75

408.00

714.00

L-15

Sinking helper ( semi-skilled )

day

4.00

377.00

1508.00

L-14

hour

5.50

349.00

1919.50

P&M-075

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b)

191.95

c)

Overhead charges @ 0.2 on (a+b)

903.03

d)

Contractor's profit @ 0.1 on (a+b+c)

541.82

Rate per metre = (a+b+c+d)

5960.01
say

12.15 A

(iii)
a

Beyond 10m upto 20m


Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m

5%

6258.00

12th m

5%

6571.00

13th m

5%

6900.00

14th m

5%

7245.00

15th m

5%

7607.00

16th m

5%

7987.00

17th m

5%

8386.00

18th m

5%

8805.00

19th m

5%

9245.00

20th m

5%

Total Cost from 10m upto 20m

9707.00
78711.00

Avg Rate per metre

7871.00
Page 42 of 394

5960.00

Sr No
12.15 A

Ref. to
MoRTH
Spec.

Description
(iv)
a
b

Unit

Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports,
loading arrangement and Labour.
21st m

10435.03

Including 20%
for Kentledge
12522.00

22nd m

7.5%

11218.00

13462.00

23rd m

7.5%

12059.00

14471.00

24th m

7.5%

12963.00

15556.00

25th m

7.5%

13935.00

16722.00

26th m

7.5%

14980.00

17976.00

27th m

7.5%

16104.00

19325.00

28th m

7.5%

17312.00

20774.00

29th m

7.5%

18610.00

22332.00

30th m

7.5%

20006.00

24007.00

147622.03

177147.00

14762.00

17715.00

7.5%

Avg Rate per metre


(v)

Beyond 30m upto 40 m

Add 10 per cent for every additional meter depth of sinking


over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports,
loading arrangement, and Labour etc.
31st m

10%

22006.60

Including 20%
for Kentledge
26408.00

32nd

10%

24207.00

29048.00

33rd m

10%

26628.00

31954.00

34th m

10%

29291.00

35149.00

35th m

10%

32220.00

38664.00

36th m

10%

35442.00

42530.00

37th m

10%

38986.00

46783.00

38th m

10%

42885.00

51462.00

39th m

10%

47174.00

56609.00

40th m

10%

51891.00

62269.00

350730.60

420876.00

35073.00

42088.00

Total Cost from 30m upto 40m


Avg Rate per metre
12.15

Rate Rs

Cost Rs

Remarks/
Input ref.

Beyond 20m upto 30 m

Total Cost from 20m upto 30m


12.15 A

Quantity

Clayey Soil ( 9m dia. Well )


Unit = Running Meter.
Taking output = 1 cum

(i)

Depth below bed level upto 3.0 M


Rate of sinking 0.17 m / hour
a)

b)

Labour
Mate

day

0.24

673.00

161.52

L-12

Sinker ( skilled )

day

2.25

408.00

918.00

L-15

Sinking helper ( semi-skilled )

day

3.75

377.00

1413.75

L-14

hour

5.75

349.00

2006.75

P&M-075

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b)

c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

200.68
940.14
564.08

Rate per metre = (a+b+c+d)

6204.92
say

12.15 B

(ii)

6205.00

Beyond 3m upto 10m depth


Rate of sinking 0.15 m / hour
a)

b)

Labour
Mate

day

0.34

673.00

228.82

L-12

Sinker

day

2.50

408.00

1020.00

L-15

Sinking helper ( semi-skilled )

day

5.00

377.00

1885.00

L-14

Machinery
Page 43 of 394

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Hire & running charges of crane with grab bucket of


0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for
cutting hard clay.
Consumables in sinking @ 10 per cent of (b)
c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

Quantity

Rate Rs

6.50

349.00

2268.50

P&M-075

hour

3.75

300.00

1125.00

P&M-063

339.35
1373.33
824.00
9064.00
say

(iii)
a
b

Add 5 per cent for every additional meter depth of sinking


over the rate of sinking for the previous meter
Add for dewatering @ 5 per cent of cost, if required.

Including for
dewatering @
5% of cost, if
required

11th m

5%

9517.00

9993.00

12th m

5%

9993.00

10493.00

13th m

5%

10493.00

11018.00

14th m

5%

11018.00

11569.00

15th m

5%

11569.00

12147.00

16th m

5%

12147.00

12754.00

17th m

5%

12754.00

13392.00

18th m

5%

13392.00

14062.00

19th m

5%

14062.00

14765.00

20th m

5%

14765.00

15503.00

119710.00

125696.00

11971.00

12570.00

Avg Rate per metre


(iv)
a
b
c

Beyond 20m upto 30 m


Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering on the cost, if required
Add 25 per cent of cost for Kentledge including supports,
loading arrangement and Labour ).

Including 25% Including 5%


for Kentledge
for
dewatering, if
required

31st m

7.5%

15872.00

19840.00

20832.00

32nd

7.5%

17062.00

21328.00

22394.00

33rd m

7.5%

18342.00

22928.00

24074.00

34th m

7.5%

19718.00

24648.00

25880.00

35th m

7.5%

21197.00

26496.00

27821.00

36th m

7.5%

22787.00

28484.00

29908.00

37th m

7.5%

24496.00

30620.00

32151.00

38th m

7.5%

26333.00

32916.00

34562.00

39th m

7.5%

28308.00

35385.00

37154.00

40th m

7.5%

30431.00

38039.00

39941.00

224546.00

280684.00

294717.00

22455.00

28068.00

29472.00

Total Cost from 30m upto 40m


Avg Rate per metre
12.15 B

(v)
a
b
c

9064.00

Beyond 10 m upto 20 m

Total Cost from 10m upto 20m


12.15 B

Beyond 30m upto 40 m


Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering, if required
Add 20 per cent of cost for Kentledge including supports,
loading arrangement and Labour).

Including 20% Including 5%


for Kentledge
for
dewatering, if
required

31st m

10%

33474.00

40169.00

42177.00

32nd

10%

36821.00

44185.00

46394.00

33rd m

10%

40503.00

48604.00

51034.00

34th m

10%

44553.00

53464.00

56137.00

Page 44 of 394

Remarks/
Input ref.

hour

Rate per metre = (a+b+c+d)


12.15 B

Cost Rs

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Cost Rs

Remarks/
Input ref.

10%

49008.00

58810.00

61751.00

36th m

10%

53909.00

64691.00

67926.00

37th m

10%

59300.00

71160.00

74718.00

38th m

10%

65230.00

78276.00

82190.00

39th m

10%

71753.00

86104.00

90409.00

40th m

10%

78928.00

94714.00

99450.00

533479.00

640177.00

672186.00

53348.00

64018.00

67219.00

0.76

673.00

511.48

L-12

Avg Rate per metre


C

Rate Rs

35th m

Total Cost from 30m upto 40m


12.15

Quantity

Soft Rock ( 9m dia well )


Unit = Running Meter.
Taking output = 1 m
Depth in soft rock strata up to 3m
Rate of sinking 0.15 m / hour
a)

b)

Labour
Mate

day

Sinker ( skilled )

day

4.00

408.00

1632.00

L-15

Sinking helper ( semi-skilled )

day

14.00

377.00

5278.00

L-14

Diver

day

1.20

471.00

565.20

L-07

hour

6.50

349.00

2268.50

P&M-075

hour

4.00

300.00

1200.00

P&M-063

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Air compressor with pneumatic breakers
Consumables in sinking @ 10 per cent of (b)

346.85
1180.20

c)

Add for dewatering @ of 5 per cent of (a+b), if


required
Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

2596.45
1557.87

Rate per metre = (a+b+c+d)


12.15

17136.55
say

17137.00

Hard Rock ( 9m dia well )


Unit = Running Meter
Taking output = 1 m
Depth in hard rock strata upto 3 m
Rate of sinking 0.15 m / hour
a)

b)

c)

Material
Gelatine 80 per cent

Kg

10.00

74.08

740.80

Electric Detonators

each

40.00

11.00

440.00 M-094/100

M-104

Mate

day

1.17

673.00

787.41

L-12

Driller

day

2.00

400.00

800.00

L-06

Blaster

day

0.25

396.00

99.00

L-03

Mazdoor

day

22.00

377.00

8294.00

L-13

Mazdoor (Skilled)

day

4.00

408.00

1632.00

L-15

Diver

day

1.00

471.00

471.00

L-07

hour

7.00

349.00

2443.00

P&M-075

hour

2.50

300.00

750.00

P&M-063

Labour

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Hire & running charges of compressor with pneumatic
breaker/Jack hammer for drilling.
Dewatering @ 5 per cent of cost of (b+c), if required.

763.82

Consumables in sinking @ 10 per cent of cost of (b).

1208.34

d)

Overhead charges @ 0.2 on (a+b+c)

3685.87

e)

Contractor's profit @ 0.1 on (a+b+c+d)

2211.52

Rate per metre = (a+b+c+d+e)

24326.77
say

Page 45 of 394

24327.00

Sr No

Ref. to
MoRTH
Spec.

12.16

1200

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Sinking of 10 m external diameter well ( other than


pneumatic method of sinking ) through all types of
strata namely sandy soil, clayey soil and rock as shown
against each case, complete as per drawing and
technical specifications. Depth of sinking is reckoned
from bed level.
Unit = Running Meter
Taking output = 1 m
Diameter of well - 10 m.
A

Sandy Soil

(i)

Depth below bed level upto 3.0 M


Rate of sinking 0.20 m / hour
a)

b)

Labour
Mate

day

0.20

673.00

134.60

L-12

Sinker ( skilled )

day

1.50

408.00

612.00

L-15

Sinking helper ( semi-skilled )

day

3.50

377.00

1319.50

L-14

hour

5.00

349.00

1745.00

P&M-075

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b)

c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

174.50
797.12
478.27

Rate per metre = (a+b+c+d)


12.16 A

(ii)

5260.99
say

5261.00

Beyond 3m upto 10m depth


Rate of sinking 0.17 m / hour
a)

b)

Labour
Mate

day

0.31

673.00

208.63

L-12

Sinker

day

2.00

408.00

816.00

L-15

Sinking helper ( semi-skilled )

day

4.25

377.00

1602.25

L-14

hour

5.75

349.00

2006.75

P&M-075

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b)

c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

200.68
966.86
580.12

Rate per metre = (a+b+c+d)

6381.28
say

12.16 A

(iii)
a

Beyond 10m upto 20m


Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m

5%

6700.00

12th m

5%

7035.00

13th m

5%

7387.00

14th m

5%

7756.00

15th m

5%

8144.00

16th m

5%

8551.00

17th m

5%

8979.00

18th m

5%

9428.00

19th m

5%

9899.00

20th m

5%

10394.00

Total Cost from 10m upto 20m

84273.00

Avg Rate per metre


12.16 A

(iv)
a
b

8427.00

Beyond 20m upto 30 m


Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports,
loading arrangement and Labour.
21st m
Page 46 of 394

7.5%

11174.00

Including 20%
for Kentledge
13409.00

6381.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit
7.5%

12012.00

14414.00

23rd m

7.5%

12913.00

15496.00

24th m

7.5%

13881.00

16657.00

25th m

7.5%

14922.00

17906.00

26th m

7.5%

16041.00

19249.00

27th m

7.5%

17244.00

20693.00

28th m

7.5%

18537.00

22244.00

29th m

7.5%

19927.00

23912.00

30th m

7.5%

21422.00

25706.00

158073.00

189686.00

15807.00

18969.00

Including 20%
for Kentledge
28277.00

Avg Rate per metre


(v)

Beyond 30m upto 40 m

Add 10 per cent for every additional meter depth of sinking


over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports,
loading arrangement, and Labour etc.
31st m

10%

23564.00

32nd

10%

25920.00

31104.00

33rd m

10%

28512.00

34214.00

34th m

10%

31363.00

37636.00

35th m

10%

34499.00

41399.00

36th m

10%

37949.00

45539.00

37th m

10%

41744.00

50093.00

38th m

10%

45918.00

55102.00

39th m

10%

50510.00

60612.00

40th m

10%

55561.00

66673.00

375540.00

450649.00

37554.00

45065.00

Total Cost from 30m upto 40m


Avg Rate per metre
12.16

Rate Rs

22nd m

Total Cost from 20m upto 30m


12.16 A

Quantity

Cost Rs

Remarks/
Input ref.

Clayey Soil (10m dia. Well )


Unit = Running Meter
Taking output = 1 cum

(i)

Depth below bed level upto 3.0 M


Rate of sinking 0.18m/hour.
a)

b)

Labour
Mate

day

0.25

673.00

168.25

L-12

Sinker ( skilled )

day

2.50

408.00

1020.00

L-15

Sinking helper ( semi-skilled )

day

5.50

377.00

2073.50

L-14

hour

6.00

349.00

2094.00

P&M-075

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b)

c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

209.40
1113.03
667.82

Rate per metre = (a+b+c+d)

7346.00
say

12.16 B

(ii)

7346.00

Beyond 3m upto 10m depth


Rate of sinking 0.15m/hour.
a)

b)

Labour
Mate

day

0.40

673.00

269.20

L-12

Sinker

day

3.00

408.00

1224.00

L-15

Sinking helper ( semi-skilled )

day

5.50

377.00

2073.50

L-14

hour

6.00

349.00

2094.00

P&M-075

hour

4.00

300.00

1200.00

P&M-063

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for
cutting hard clay
Consumables in sinking @ 10 per cent of (b)

c)

Overhead charges @ 0.2 on (a+b)


Page 47 of 394

329.40
1438.02

Sr No

Ref. to
MoRTH
Spec.

Description
d)

Unit

Quantity

Rate Rs

Contractor's profit @ 0.1 on (a+b+c)

862.81

Rate per metre = (a+b+c+d)

9490.93
say

12.16 B

(iii)
a
b

Add 5 per cent for every additional meter depth of sinking


over the rate of sinking for the previous meter
Add for dewatering @ 5 per cent of cost, if required.

Including for
dewatering @
5% of cost, if
required

11th m

5%

9965.00

10463.00

12th m

5%

10463.00

10986.00

13th m

5%

10986.00

11535.00

14th m

5%

11535.00

12112.00

15th m

5%

12112.00

12718.00

16th m

5%

12718.00

13354.00

17th m

5%

13354.00

14022.00

18th m

5%

14022.00

14723.00

19th m

5%

14723.00

15459.00

20th m

5%

15459.00

16232.00

125337.00

131604.00

12534.00

13160.00

Avg Rate per metre


(iv)
a
b
c

Beyond 20m upto 30 m


Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering on the cost, if required
Add 25 per cent of cost for Kentledge including supports,
loading arrangement and Labour ).

Including 25% Including 5%


for Kentledge
for
dewatering, if
required

31st m

7.5%

16618.00

20773.00

21812.00

32nd

7.5%

17864.00

22330.00

23447.00

33rd m

7.5%

19204.00

24005.00

25205.00

34th m

7.5%

20644.00

25805.00

27095.00

35th m

7.5%

22192.00

27740.00

29127.00

36th m

7.5%

23856.00

29820.00

31311.00

37th m

7.5%

25645.00

32056.00

33659.00

38th m

7.5%

27568.00

34460.00

36183.00

39th m

7.5%

29636.00

37045.00

38897.00

40th m

7.5%

31859.00

39824.00

41815.00

235086.00

293858.00

308551.00

23509.00

29386.00

30855.00

Total Cost from 30m upto 40m


Avg Rate per metre
12.16 B

(v)
a
b
c

9491.00

Beyond 10 m upto 20 m

Total Cost from 10m upto 20m


12.16 B

Cost Rs

Beyond 30m upto 40 m


Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering, if required
Add 20 per cent of cost for Kentledge including supports,
loading arrangement and Labour).

Including 20% Including 5%


for Kentledge
for
dewatering, if
required

31st m

10%

35045.00

42054.00

44157.00

32nd

10%

38550.00

46260.00

48573.00

33rd m

10%

42405.00

50886.00

53430.30

34th m

10%

46646.00

55975.00

58773.75

35th m

10%

51311.00

61573.00

64651.65

36th m

10%

56442.00

67730.00

71116.50

37th m

10%

62086.00

74503.00

78228.15

38th m

10%

68295.00

81954.00

86051.70

39th m

10%

75125.00

90150.00

94657.50

Page 48 of 394

Remarks/
Input ref.

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

40th m

10%

Total Cost from 30m upto 40m


Avg Rate per metre
12.16

Quantity

Rate Rs

Cost Rs

82638.00

99166.00

104124.30

558543.00

670251.00

703763.85

55854.00

67025.00

70376.00

Remarks/
Input ref.

Soft Rock (10m dia well )


Unit = Running Meter.
Taking output = 1 m
Depth in soft rock strata upto 3m
Rate of sinking 0.14m/hour.
a)

b)

Labour
Mate

day

0.86

673.00

578.78

L-12

Sinker ( skilled )

day

4.00

408.00

1632.00

L-15

Sinking helper ( semi-skilled )

day

16.00

377.00

6032.00

L-14

Diver

day

1.40

471.00

659.40

L-07

hour

7.00

349.00

2443.00

P&M-075

hour

4.25

300.00

1275.00

P&M-063

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Air compressor with pneumatic breakers
Consumables in sinking @ 10 per cent of (b)

371.80

Add for dewatering @ 5 per cent of cost, if required

204.49

c)

Overhead charges @ 0.2 on (a+b)

2639.29

d)

Contractor's profit @ 0.1 on (a+b+c)

1583.58

Rate per metre = (a+b+c+d)


12.16

17419.34
say

17419.00

Hard Rock (10m dia well )


Unit = Running Meter.
Taking output = 1 m
Depth in hard rock strata upto 3 m
Rate of sinking 0.12 m/ hour.
a)

b)

c)

Material
Gelatine 80 per cent

Kg

11.00

74.08

814.88

Electric Detonators

each.

44.00

11.00

484.00 M-094/100

Mate

day

1.27

673.00

854.71

L-12

Driller

day

2.00

400.00

800.00

L-06

Blaster

day

0.25

396.00

99.00

L-03

Mazdoor

day

24.00

377.00

9048.00

L-13

Mazdoor (Skilled)

day

4.00

408.00

1632.00

L-15

hour

8.50

349.00

2966.50

P&M-075

hour

3.00

300.00

900.00

P&M-063

Labour

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Hire & running charges of compressor with pneumatic
breaker/Jack hammer or drill
Dewatering @ 5 per cent of cost (c), if required.

d)

Consumables in sinking @ 10 per cent of cost of


(b+c).
Overhead charges @ 0.2 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

193.33
1649.35
3888.35
2333.01

Rate per metre = (a+b+c+d+e)

25663.13
say

12.17

1200

Sinking of 11 m external diameter well ( other than


pneumatic method of sinking ) through all types of
strata namely sandy soil, clayey soil and rock as shown
against each case, complete as per drawing and
technical specifications. Depth of sinking is reckoned
from bed level.
Unit = Running Meter
Taking output = 0.50 m
Diameter of well - 11 m.
A

M-104

Sandy Soil
Page 49 of 394

25663.00

Sr No

Ref. to
MoRTH
Spec.

Description
(i)

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Depth from bed level upto 3.0 M


Rate of sinking @ 0.15 m/hour
a)

b)

Labour
Mate

day

0.21

673.00

141.33

L-12

Sinker ( skilled )

day

1.50

408.00

612.00

L-15

Sinking helper (semi-skilled)

day

3.30

377.00

1244.10

L-14

hour

6.00

349.00

2094.00

P&M-075

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b)

d)

Overhead charges @ 0.2 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

209.40
860.17
516.10

Cost for 0.5m = a+b+c+d

5677.10

Rate per metre = (a+b+c+d)/0.50


12.17 A

(ii)

11354.19
say

11354.00

Beyond 3m upto 10m depth


Rate of sinking @ 0.13 m/hour
a)

b)

Labour
Mate

day

0.32

673.00

215.36

L-12

Sinker

day

2.00

408.00

816.00

L-15

Sinking helper (semi-skilled)

day

4.50

377.00

1696.50

L-14

hour

4.00

349.00

1396.00

P&M-075

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b)

c)

Overhead charges @ 0.2 on (a+b+c)

d)

Contractor's profit @ 0.1 on (a+b+c+d)

139.60
852.69
511.62

Cost for 0.5m = a+b+c+d

5627.77

Rate per metre = (a+b+c+d)/0.50

11255.53
say

12.17 A

(iii)
a

Beyond 10m upto 20m


Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m

5%

11818.00

12th m

5%

12409.00

13th m

5%

13029.00

14th m

5%

13680.00

15th m

5%

14364.00

16th m

5%

15082.00

17th m

5%

15836.00

18th m

5%

16628.00

19th m

5%

17459.00

20th m

5%

Total Cost from 10m upto 20m


Avg Rate per metre
12.17 A

(iv)
a
b

18332.00
148637.00
14864.00

Beyond 20m upto 30 m


Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports,
loading arrangement and Labour.
21st m

19707.00

Including 20%
for Kentledge
23648.00

22nd m

7.5%

21185.00

25422.00

23rd m

7.5%

22774.00

27329.00

24th m

7.5%

24482.00

29378.00

25th m

7.5%

26318.00

31582.00

26th m

7.5%

28292.00

33950.00

27th m

7.5%

30414.00

36497.00

28th m

7.5%

32695.00

39234.00

Page 50 of 394

7.5%

11256.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit
7.5%

35147.00

30th m

7.5%

37783.00

45340.00

278797.00

334556.00

27880.00

33456.00

Avg Rate per metre


(v)

Beyond 30m upto 40 m

Add 10 per cent for every additional meter depth of sinking


over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports,
loading arrangement, and Labour etc.
31st m

10%

41561.00

32nd

10%

45717.00

54860.00

33rd m

10%

50289.00

60347.00

34th m

10%

55318.00

66382.00

35th m

10%

60850.00

73020.00

36th m

10%

66935.00

80322.00

37th m

10%

73629.00

88355.00

38th m

10%

80992.00

97190.00

39th m

10%

89091.00

106909.00

40th m

10%

Avg Rate per metre


B

Cost Rs

Remarks/
Input ref.

42176.00

Including 20%
for Kentledge
49873.00

Total Cost from 30m upto 40m


12.17

Rate Rs

29th m
Total Cost from 20m upto 30m
12.17 A

Quantity

98000.00

117600.00

662382.00

794858.00

66238.00

79486.00

Clayey Soil (11 m dia. Well )


Unit = Running Meter
Taking output = 0.50 meter

(i)

Depth from bed level upto 3.0 M


Rate of sinking @ 0.10 m/hour
a)

b)

Labour
Mate

day

0.26

673.00

174.98

L-12

Sinker ( skilled )

day

2.50

408.00

1020.00

L-15

Sinking helper (semi-skilled)

day

4.00

377.00

1508.00

L-14

hour

5.00

349.00

1745.00

P&M-075

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b)

c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

174.50
924.50
554.70

Cost for 0.5m = a+b+c+d

6101.67

Rate per metre = (a+b+c+d)/0.50

12203.35
say

12.17 B

(ii)

12203.00

Beyond 3m upto 10m depth


Rate of sinking @ 0.08 m/hour
a)

b)

Labour
Mate

day

0.43

673.00

289.39

L-12

Sinker

day

3.50

408.00

1428.00

L-15

Sinking helper (semi-skilled)

day

5.75

377.00

2167.75

L-14

hour

6.00

349.00

2094.00

P&M-075

hour

4.25

300.00

1275.00

P&M-063

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for
cutting hard clay
Consumables in sinking @ 10 per cent of (b)

c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

336.90
1518.21
910.92

Cost for 0.5m = a+b+c+d

10020.17

Rate per metre = (a+b+c+d)/0.50

20040.35
say

12.17 B

(iii)
a

Beyond 10 m upto 20 m
Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Page 51 of 394

20040.00

Sr No

Ref. to
MoRTH
Spec.

Description
b

Unit

Add for dewatering @ 5 per cent of cost, if required.

11th m

5%

21042.00

22094.00

12th m

5%

22094.00

23199.00

13th m

5%

23199.00

24359.00

14th m

5%

24359.00

25577.00

15th m

5%

25577.00

26856.00

16th m

5%

26856.00

28199.00

17th m

5%

28199.00

29609.00

18th m

5%

29609.00

31089.00

19th m

5%

31089.00

32643.00

20th m

5%

32643.00

34275.00

264667.00

277900.00

26467.00

27790.00

Avg Rate per metre


(iv)
a
b
c

Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering on the cost, if required
Add 25 per cent of cost for Kentledge including supports,
loading arrangement and Labour ).

Including 25% Including 5%


for Kentledge
for
dewatering, if
required

31st m

7.5%

35091.00

43864.00

46057.00

32nd

7.5%

37723.00

47154.00

49512.00

33rd m

7.5%

40552.00

50690.00

53225.00

34th m

7.5%

43593.00

54491.00

57216.00

35th m

7.5%

46862.00

58578.00

61507.00

36th m

7.5%

50377.00

62971.00

66120.00

37th m

7.5%

54155.00

67694.00

71079.00

38th m

7.5%

58217.00

72771.00

76410.00

39th m

7.5%

62583.00

78229.00

82140.00

40th m

7.5%

67277.00

84096.00

88301.00

496430.00

620538.00

651565.00

49643.00

62054.00

65157.00

Avg Rate per metre


(v)
a
b
c

Beyond 30m upto 40 m


Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering, if required
Add 20 per cent of cost for Kentledge including supports,
loading arrangement and Labour).

10%

74005.00

88806.00

93246.00

32nd

10%

81406.00

97687.00

102571.00

33rd m

10%

89547.00

107456.00

112829.00

34th m

10%

98502.00

118202.00

124112.00

35th m

10%

108352.00

130022.00

136523.00

36th m

10%

119187.00

143024.00

150175.00

37th m

10%

131106.00

157327.00

165193.00

38th m

10%

144217.00

173060.00

181713.00

39th m

10%

158639.00

190367.00

199885.00

40th m

10%

174503.00

209404.00

219874.00

1179464

1415355

1486121

117946.00

141536.00

148612.00

Avg Rate per metre


C

Including 20% Including 5%


for Kentledge
for
dewatering, if
required

31st m

Total Cost from 30m upto 40m


12.17

Cost Rs

Beyond 20m upto 30 m

Total Cost from 30m upto 40m


12.17 B

Rate Rs
Including for
dewatering @
5% of cost, if
required

Total Cost from 10m upto 20m


12.17 B

Quantity

Soft Rock (11m dia well )


Unit = Running Meter.
Taking output = 0.50 m
Page 52 of 394

Remarks/
Input ref.

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Depth in soft rock strata upto 3m


Rate of sinking @ 0.06 m/hour
a)

b)

Labour
Mate

day

0.95

673.00

639.35

L-12

Sinker ( skilled )

day

4.25

408.00

1734.00

L-15

Sinking helper (semi-skilled)

day

18.00

377.00

6786.00

L-14

Diver

day

1.50

471.00

706.50

L-07

hour

8.00

349.00

2792.00

P&M-075

hour

4.50

300.00

1350.00

P&M-063

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Air compressor with pneumatic breakers
Consumables in sinking @ 10 per cent of (b)

414.20

Add for dewatering @ 5 per cent of cost, if required


c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

227.81
2929.97
1757.98

Cost for 0.5m = a+b+c+d

19337.82

Rate per metre = (a+b+c+d)/0.50


12.17

38675.63
say

38676.00

Hard Rock (11m dia well )


Unit = Running Meter.
Taking output = 0.50 m
Depth in hard rock upto 3 m
Rate of sinking @ 0.05 m/hour
a)

b)

c)

Material
Gelatine 80 per cent

Kg

12.00

74.08

888.96

Electric Detonators

each.

48.00

11.00

528.00 M-094/100

Mate

day

1.35

673.00

908.55

L-12

Driller

day

2.00

400.00

800.00

L-06

Blaster

day

0.25

396.00

99.00

L-03

Mazdoor

day

26.00

377.00

9802.00

L-13

Mazdoor (Skilled)

day

4.00

408.00

1632.00

L-15

hour

10.00

349.00

3490.00

P&M-075

hour

3.50

300.00

1050.00

P&M-063

Labour

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Hire & running charges of compressor with pneumatic
breaker/Jack hammer or drill
Dewatering @ 5 per cent of cost (c), if required.

d)

Consumables in sinking @ 10 per cent of cost of


(b+c).
Overhead charges @ 0.2 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

227.00
1778.16
4240.73
2544.44

Cost for 0.5m = a+b+c+d

27988.84

Rate per metre = (a+b+c+d)/0.50


12.18

1200

M-104

55977.68
say

55978.00

673.00

148.06

Sinking of 12 m external diameter well ( other than


pneumatic method of sinking ) through all types of
strata namely sandy soil, clayey soil and rock as shown
against each case, complete as per drawing and
technical specifications. Depth of sinking is reckoned
from bed level.
Unit = Running Meter
Taking output = 0.25 m
Diameter of well - 12 m.
A

Sandy Soil

(i)

I) Depth below bed level upto 3.0 M


Rate of sinking @ 0.05 m/hour
a)

Labour
Mate

day
Page 53 of 394

0.22

L-12

Sr No

Ref. to
MoRTH
Spec.

Description

b)

Unit

Quantity

Rate Rs

day

1.75

408.00

714.00

L-15

Sinking helper (semi-skilled)

day

4.00

377.00

1508.00

L-14

hour

6.00

349.00

2094.00

P&M-075

Machinery

c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

209.40
934.69
560.82

Cost for 0.25m = a+b+c+d

6168.97

Rate per metre = (a+b+c+d)/0.25

24675.87
say

(ii)

Remarks/
Input ref.

Sinker ( skilled )

Hire & running charges of crane with grab bucket of


0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b)

12.18 A

Cost Rs

24676.00

Beyond 3m upto 10m depth


Rate of sinking @ 0.038 m/hour
a)

b)

Labour
Mate

day

0.37

673.00

249.01

L-12

Sinker

day

2.50

408.00

1020.00

L-15

Sinking helper (semi-skilled)

day

4.75

377.00

1790.75

L-14

hour

6.50

349.00

2268.50

P&M-075

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b)

c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

226.85
1111.02
666.61

Cost for 0.25m = a+b+c+d

7332.75

Rate per metre = (a+b+c+d)/0.25

29330.98
say

12.18 A

(iii)
a

Beyond 10m upto 20m


Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m

5%

30798.00

12th m

5%

32338.00

13th m

5%

33954.90

14th m

5%

35652.65

15th m

5%

37435.28

16th m

5%

39307.04

17th m

5%

41272.39

18th m

5%

43336.01

19th m

5%

45502.81

20th m

5%

Total Cost from 10m upto 20m


Avg Rate per metre
12.18 A

(iv)
a
b

47777.95
387375.04
38738.00

Beyond 20m upto 30 m


Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports,
loading arrangement and Labour.
21st m

7.5%

51361.00

Including 20%
for Kentledge
61633.00

22nd m

7.5%

55213.00

66256.00

23rd m

7.5%

59354.00

71225.00

24th m

7.5%

63806.00

76567.00

25th m

7.5%

68591.00

82309.00

26th m

7.5%

73735.00

88482.00

27th m

7.5%

79265.00

95118.00

28th m

7.5%

85210.00

102252.00

29th m

7.5%

91601.00

109921.00

30th m

7.5%

98471.00

118165.00

726607.00

871928.00

72661.00

87193.00

Total Cost from 20m upto 30m


Avg Rate per metre
Page 54 of 394

29331.00

Sr No
12.18 A

Ref. to
MoRTH
Spec.

Description

Unit

(v)

Beyond 30m upto 40 m

Add 10 per cent for every additional meter depth of sinking


over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports,
loading arrangement, and Labour etc.
31st m

108318.00

32nd

10%

119150.00

142980.00

33rd m

10%

131065.00

157278.00

34th m

10%

144172.00

173006.00

35th m

10%

158589.00

190307.00

36th m

10%

174448.00

209338.00

37th m

10%

191893.00

230272.00

38th m

10%

211082.00

253298.00

39th m

10%

232190.00

278628.00

40th m

10%

255409.00

306491.00

10%

Avg Rate per metre


B

Rate Rs

Including 20%
for Kentledge
129982.00

Total Cost from 30m upto 40m


12.18

Quantity

1726316

2071580

172632.00

207158.00

Cost Rs

Remarks/
Input ref.

Clayey Soil (12 m dia. Well )


Unit = Running Meter.
Taking output = 0.25 meter.

(i)

Depth below bed level upto 3.0 M


Rate of sinking @ 0.04 m/hour
a)

b)

Labour
Mate

day

0.30

673.00

201.90

L-12

Sinker ( skilled )

day

3.00

408.00

1224.00

L-15

Sinking helper (semi-skilled)

day

4.50

377.00

1696.50

L-14

hour

6.25

349.00

2181.25

P&M-075

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b)

c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

218.13
1104.36
662.61

Cost for 0.25m = a+b+c+d

7288.74

Rate per metre = (a+b+c+d)/0.25

29154.97
say

12.18 B

(ii)

29155.00

Beyond 3m upto 10m depth


Rate of sinking @ 0.03 m/hour
a)

b)

Labour
Mate

day

0.48

673.00

323.04

L-12

Sinker

day

3.75

408.00

1530.00

L-15

Sinking helper (semi-skilled)

day

6.00

377.00

2262.00

L-14

hour

8.33

349.00

2907.17

P&M-075

hour

4.50

300.00

1350.00

P&M-063

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for
cutting hard clay.
Consumables in sinking @ 10 per cent of (b)

c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

425.72
1759.59
1055.75

Cost for 0.25m = a+b+c+d

11613.26

Rate per metre = (a+b+c+d)/0.25

46453.05
say

12.18 B

(iii)
a
b

Beyond 10 m upto 20 m
Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add for dewatering @ 5 per cent of cost, if required.

Page 55 of 394

Including for
dewatering @
5% of cost, if
required

46453.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit
5%

48776.00

51215.00

12th m

5%

51215.00

53776.00

13th m

5%

53776.00

56465.00

14th m

5%

56465.00

59288.00

15th m

5%

59288.00

62252.00

16th m

5%

62252.00

65365.00

17th m

5%

65365.00

68633.00

18th m

5%

68633.00

72065.00

19th m

5%

72065.00

75668.00

20th m

5%

75668.00

79451.00

613503.00

644178.00

61350.00

64418.00

Avg Rate per metre


(iv)
a
b
c

Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering on the cost, if required
Add 25 per cent of cost for Kentledge including supports,
loading arrangement and Labour ).

Including 25% Including 5%


for Kentledge
for
dewatering, if
required

31st m

7.5%

81343.00

101679.00

32nd

7.5%

87444.00

109305.00

114770.00

33rd m

7.5%

94002.00

117503.00

123378.00

34th m

7.5%

101052.00

126315.00

132631.00

35th m

7.5%

108631.00

135789.00

142578.00

36th m

7.5%

116778.00

145973.00

153272.00

37th m

7.5%

125536.00

156920.00

164766.00

38th m

7.5%

134951.00

168689.00

177123.00

39th m

7.5%

145072.00

181340.00

190407.00

40th m

7.5%

155952.00

194940.00

204687.00

1150761

1438453

1510375

115076.00

143845.00

151038.00

Avg Rate per metre


(v)
a
b
c

Add 10 per cent for every additional meter depth of sinking


over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering, if required
Add 20 per cent of cost for Kentledge including supports,
loading arrangement and Labour).

10%

171547.00

205856.00

216149.00

32nd

10%

188702.00

226442.00

237764.00

33rd m

10%

207572.00

249086.00

261540.00

34th m

10%

228329.00

273995.00

287695.00

35th m

10%

251162.00

301394.00

316464.00

36th m

10%

276278.00

331534.00

348111.00

37th m

10%

303906.00

364687.00

382921.00

38th m

10%

334297.00

401156.00

421214.00

39th m

10%

367727.00

441272.00

463336.00

40th m

10%

404500.00

485400.00

509670.00

2734020

3280822

3444864

273402.00

328082.00

344486.00

Soft Rock (12m dia well )


Unit = Running Meter
Taking output = 0.25 m
Depth in soft rock strata upto 3m
Rate of sinking @ 0.025 m/hour
a)

Including 20% Including 5%


for Kentledge
for
dewatering, if
required

31st m

Avg Rate per metre


C

106763.00

Beyond 30m upto 40 m

Total Cost from 30m upto 40m


12.18

Cost Rs

Beyond 20m upto 30 m

Total Cost from 30m upto 40m


12.18 B

Rate Rs

11th m

Total Cost from 10m upto 20m


12.18 B

Quantity

Labour
Page 56 of 394

Remarks/
Input ref.

Sr No

Ref. to
MoRTH
Spec.

Description

b)

Unit

Quantity

Rate Rs

day

1.06

673.00

713.38

L-12

Sinker ( skilled )

day

4.50

408.00

1836.00

L-15

Sinking helper (semi-skilled)

day

20.00

377.00

7540.00

L-14

Diver

day

1.75

471.00

824.25

L-07

hour

10.00

349.00

3490.00

P&M-075

hour

4.75

300.00

1425.00

P&M-063

Machinery

491.50

Add for dewatering @ 5 per cent, if required


c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

270.33
3318.09
1990.85

Cost for 0.25m = a+b+c+d

21899.40

Rate per metre = (a+b+c+d)/0.25


D

Remarks/
Input ref.

Mate

Hire & running charges of crane with grab bucket of


0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for
cutting hard clay.
Consumables in sinking @ 10 per cent of (b)

12.18

Cost Rs

87597.60
say

87598.00

1037.12

Hard Rock (12m dia well )


Unit = Running Meter
Taking output = 0.25 m

(i)

Depth in hard rock strata upto 3 m


Rate of sinking @ 0.020 m/hour
a)

Material
Gelatine80 per cent

Kg

14.00

74.08

each.

56.00

11.00

Mate

day

1.44

673.00

969.12

L-12

Driller

day

2.00

400.00

800.00

L-06

Blaster

day

0.25

396.00

99.00

L-03

Mazdoor

day

28.00

377.00

10556.00

L-13

Mazdoor (Skilled)

day

4.50

408.00

1836.00

L-15

hour

12.50

349.00

4362.50

P&M-075

hour

4.00

300.00

1200.00

P&M-063

Electric detonator
b)

c)

Labour

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Hire & running charges of compressor with pneumatic
breaker/Jack hammer or drill
Dewatering @ 5 per cent, if required.

278.13

Consumables in sinking @ 10 per cent of (c).


d)

Overhead charges @ 0.2 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

584.06
4467.59
2680.55

Cost for 0.25m = a+b+c+d+e

29486.06

Rate per metre = (a+b+c+d+e)/0.25


12.19

1200

M-104

616.00 M-094/100

117944.26
say

117944.00

Sinking of Twin D Type well (other than pneumatic


method of sinking) through all types of strata namely
sandy soil, clayey soil and rock as shown against each
case, complete as per drawing and technical
specifications. Depth of sinking is reckoned from bed
level.
Unit = Running Meter
Taking output = 1 m
Dimensions of well.
Overall length = 12 m
Overall width = 6 m
A

Sandy Soil

(i)

Depth from bed level upto 3.0 M


Rate of sinking @ 0.18 m/hour
a)

Labour
Mate

day

0.20

673.00

134.60

L-12

Sinker ( skilled )

day

1.25

408.00

510.00

L-15

Page 57 of 394

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Sinking helper (semi-skilled)


b)

Quantity

Rate Rs

day

3.75

377.00

1413.75

L-14

hour

5.50

349.00

1919.50

P&M-075

c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

191.95
833.96
500.38

Rate per metre = (a+b+c+d)


(ii)

Remarks/
Input ref.

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b)

12.19 A

Cost Rs

5504.14
say

5504.00

Beyond 3m upto 10m depth


Rate of sinking @ 0.17 m/hour
a)

b)

Labour
Mate

day

0.30

673.00

201.90

L-12

Sinker

day

1.50

408.00

612.00

L-15

Sinking helper (semi-skilled)

day

4.00

377.00

1508.00

L-14

hour

5.88

349.00

2052.12

P&M-075

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b)

c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

205.21
915.85
549.51

Rate per metre = (a+b+c+d)

6044.59
say

12.19 A

(iii)
a

Beyond 10m upto 20m


Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m

5%

6347.00

12th m

5%

6664.00

13th m

5%

6997.00

14th m

5%

7347.00

15th m

5%

7714.00

16th m

5%

8100.00

17th m

5%

8505.00

18th m

5%

8930.00

19th m

5%

9377.00

20th m

5%

Total Cost from 10m upto 20m


Avg Rate per metre
12.19 A

(iv)
a
b

7983.00

Beyond 20m upto 30 m


Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports,
loading arrangement and Labour.
21st m

10584.00

Including 20%
for Kentledge
12701.00

22nd m

7.5%

11378.00

13654.00

23rd m

7.5%

12231.00

14677.00

24th m

7.5%

13148.00

15778.00

25th m

7.5%

14134.00

16961.00

26th m

7.5%

15194.00

18233.00

27th m

7.5%

16334.00

19601.00

28th m

7.5%

17559.00

21071.00

29th m

7.5%

18876.00

22651.00

30th m

7.5%

20292.00

24350.00

149730.00

179677.00

14973.00

17968.00

Total Cost from 20m upto 30m


Avg Rate per metre
12.19 A

9846.00
79827.00

(v)

Beyond 30m upto 40 m

Add 10 per cent for every additional meter depth of sinking


over the rate of sinking for the previous meter

Page 58 of 394

7.5%

6045.00

Sr No

Ref. to
MoRTH
Spec.

Description
b

Unit

Add 20 per cent of cost for Kentledge including supports,


loading arrangement, and Labour etc.
31st m

10%

22321.00

32nd

10%

24553.00

29464.00

33rd m

10%

27008.00

32410.00

34th m

10%

29709.00

35651.00

35th m

10%

32680.00

39216.00

36th m

10%

35948.00

43138.00

37th m

10%

39543.00

47452.00

38th m

10%

43497.00

52196.00

39th m

10%

47847.00

57416.00

40th m

10%

52632.00

63158.00

355738.00

426886.00

35574.00

42689.00

Avg Rate per metre


B

Rate Rs
Including 20%
for Kentledge
26785.00

Total Cost from 30m upto 40m


12.19

Quantity

Cost Rs

Remarks/
Input ref.

Clayey Soil (Twin D Type Well )


Unit = Running Meter
Taking output = 1 meter

(i)

Depth below bed level upto 3.0 M


Rate of sinking @ 0.16 m/hour
a)

b)

Labour
Mate

day

0.26

673.00

174.98

L-12

Sinker ( skilled )

day

2.50

408.00

1020.00

L-15

Sinking helper (semi-skilled)

day

4.00

377.00

1508.00

L-14

hour

6.25

349.00

2181.25

P&M-075

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b)

c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

218.13
1020.47
612.28

Rate per metre = (a+b+c+d)

6735.11
say

12.19 B

(ii)

6735.00

Beyond 3m upto 10m depth


Rate of sinking @ 0.15 m/hour
a)

b)

Labour
Mate

day

0.45

673.00

302.85

L-12

Sinker

day

3.25

408.00

1326.00

L-15

Sinking helper (semi-skilled)

day

6.00

377.00

2262.00

L-14

hour

6.67

349.00

2327.83

P&M-075

hour

4.50

300.00

1350.00

P&M-063

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for
cutting hard clay.
Consumables in sinking @ 10 per cent of (b)

c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

367.78
1587.29
952.38

Rate per metre = (a+b+c+d)

10476.13
say

12.19 B

(iii)
a
b

Beyond 10 m upto 20 m
Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add for dewatering @ 5 per cent of cost, if required.

Including for
dewatering @
5% of cost, if
required

11th m

5%

11000.00

11550.00

12th m

5%

11550.00

12128.00

13th m

5%

12128.00

12734.00

14th m

5%

12734.00

13371.00

15th m

5%

13371.00

14040.00

Page 59 of 394

10476.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit
5%

14040.00

14742.00

17th m

5%

14742.00

15479.00

18th m

5%

15479.00

16253.00

19th m

5%

16253.00

17066.00

20th m

5%

17066.00

17919.00

138363.00

145282.00

13836.00

14528.00

Avg Rate per metre


(iv)
a
b
c

a
b
c

Add 25 per cent of cost for Kentledge including supports,


loading arrangement and Labour ).

Including 25% Including 5%


for Kentledge
for
dewatering, if
required

31st m

7.5%

18346.00

22933.00

24080.00

32nd

7.5%

19722.00

24653.00

25886.00

33rd m

7.5%

21201.00

26501.00

27826.00

34th m

7.5%

22791.00

28489.00

29913.00

35th m

7.5%

24500.00

30625.00

32156.00

36th m

7.5%

26338.00

32923.00

34569.00

37th m

7.5%

28313.00

35391.00

37161.00

38th m

7.5%

30436.00

38045.00

39947.00

39th m

7.5%

32719.00

40899.00

42944.00

40th m

7.5%

35173.00

43966.00

46164.00

259539.00

324425.00

340646.00

25954.00

32443.00

34065.00

Beyond 30m upto 40 m


Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering, if required
Add 20 per cent of cost for Kentledge including supports,
loading arrangement and Labour).

Including 20% Including 5%


for Kentledge
for
dewatering, if
required

31st m

10%

38690.00

46428.00

48749.00

32nd

10%

42559.00

51071.00

53625.00

33rd m

10%

46815.00

56178.00

58987.00

34th m

10%

51497.00

61796.00

64886.00

35th m

10%

56647.00

67976.00

71375.00

36th m

10%

62312.00

74774.00

78513.00

37th m

10%

68543.00

82252.00

86365.00

38th m

10%

75397.00

90476.00

95000.00

39th m

10%

82937.00

99524.00

104500.00

40th m

10%

Total Cost from 30m upto 40m


Avg Rate per metre
12.19

Remarks/
Input ref.

Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering on the cost, if required

Avg Rate per metre


(v)

Cost Rs

Beyond 20m upto 30 m

Total Cost from 30m upto 40m


12.19 B

Rate Rs

16th m

Total Cost from 10m upto 20m


12.19 B

Quantity

91231.00

109477.00

114951.00

616628.00

739952.00

776951.00

61663.00

73995.00

77695.00

Soft Rock (Twin D Type Well )


Unit = Running Meter
Taking output = 1 m
Depth in soft rock strata upto 3m
Rate of sinking @ 0.12 m/hour
a)

b)

Labour
Mate

day

0.86

673.00

578.78

L-12

Sinker ( skilled )

day

4.50

408.00

1836.00

L-15

Sinking helper (semi-skilled)

day

15.00

377.00

5655.00

L-14

Diver

day

1.50

471.00

706.50

L-07

Machinery
Page 60 of 394

Sr No

Ref. to
MoRTH
Spec.

Quantity

Rate Rs

Unit

Hire & running charges of crane with grab bucket of


0.75 cum capacity and accessories.
Air compressor with pneumatic breakers

hour

8.33

349.00

2907.17

P&M-075

hour

6.00

300.00

1800.00

P&M-063

Consumables in sinking @ 10 per cent of (b)

470.72

Add for dewatering @ 5 per cent, if required


c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

258.89
2842.61
1705.57

Rate per metre = (a+b+c+d)


12.19

Cost Rs

Remarks/
Input ref.

Description

18761.24
say

18761.00

Hard Rock (Twin D Type Well )


Unit = Running Meter
Taking output = 1 m
Depth in hard rock strata upto 3 m
Rate of sinking @ 0.10 m/hour
a)

b)

c)

Material
Geletine80 per cent

Kg

10.00

74.08

740.80

Electric detonators

each.

40.00

11.00

440.00 M-094/100

Mate

day

1.34

673.00

901.82

L-12

Driller

day

2.00

400.00

800.00

L-06

Blaster

day

0.25

396.00

99.00

L-03

Mazdoor

day

25.00

377.00

9425.00

L-13

Mazdoor (Skilled)

day

4.25

408.00

1734.00

L-15

hour

10.00

349.00

3490.00

P&M-075

hour

3.00

300.00

900.00

P&M-063

Labour

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Hire & running charges of compressor with pneumatic
breaker/Jack hammer or drill
Dewatering @ 5 per cent of cost of (b+c), if required.

867.49

Consumables in sinking @ 10 per cent of (b).


d)

Overhead charges @ 0.2 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

525.75
3984.77
2390.86

Rate per metre = (a+b+c+d+e)

26299.50
say

12.20

1200

M-104

26299.00

Pneumatic sinking of wells with equipment of approved


design, drawing and specifications worked by
competent and trained personnel and comprising of
compression and decompression chambers, reducers,
two air locks separately for men and plant & materials,
arrangement for supply of fresh air to working
chambers, check valves, exhaust valves, shafts made
from steel plates of riveted construction not less than 6
mm thick to withstand an air pressure of 0.50 MPa,
controlled blasting of hard rock where required,
staircases and 1 m wide landing plateforms with railing,
arrangement for compression and decompression,
electric lighting of 50 V maximum, proper rooms for rest
and medical examinations and compliance with safety
precautions as per IS:4138, all as per clause1207.6 of
MoRTH Specifications.

Unit - 1 cum
Taking output = 5 cum
a)

Material
M35 grade RCC corbel provided for supporting of
equipment (Dimensions as per ground conditions).
Rate may be adopted vide Item 12.8 (H)

Cum

8.00

#VALUE!

#VALUE! Item 12.8


(H)

HYSD bar reinforcement in corbel

tonne

0.48

52100.00

25008.00

M-082

Gelatine 80 per cent

Kg

1.50

74.08

111.12

M-104

Electric detonators

each

6.00

11.00

Blasting material

Page 61 of 394

66.00 M-094/100

Sr No

Ref. to
MoRTH
Spec.

Description
b)

c)

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Labour
Medical Officer

day

0.50

852.00

426.00

L-16

Para medical personnel

day

1.00

852.00

852.00

L-19

Mate

day

1.86

673.00

1251.78

L-12

Driller

day

1.00

400.00

400.00

L-06

Blaster

day

0.50

396.00

198.00

L-03

Mazdoor (for cutting, blasting, cleaning, removal of


Material etc.)
Mazdoor (Skilled) (for fixation and removal of adopter
for air lock, carrying out mechanical and electrical
operations and repairs and other skilled jobs.)

day

30.00

377.00

11310.00

L-13

day

10.00

408.00

4080.00

L-15

Diver

day

4.00

471.00

1884.00

L-07

(i) Induction, deinduction and erection of plant and


equipment including all components and
accessories for pneumatic method of well sinking.

hour

6.00

input

Induction and deinduction

L.S

Erection at site and commissioning

L.S

Usage of plant and equipment for pneumatic method of


well sinking
Air compressor 250 cfm, 2 nos.

hour

Hire and running charges of crane of 15 tonne capacity

Machinery
#VALUE! P&M-082

100000.00
150000.00
6.00

3912.00

23472.00

P&M-038

hour

2x6

300.00

hour

6.00

input

#VALUE! P&M-072

3600.00

P&M-001

Motorised barge of 20 tonne capacity

hour

6.00

input

#VALUE! P&M-066

Boat to carry atleast 20 persons

hour

6.00

input

#VALUE! P&M-066

Electric generating set 33 KVA

hour

6.00

349.00

2094.00

P&M-079

Tipper 10 tonne capacity

hour

6.00

291.00

1746.00

P&M-048

d)

Overhead charges @ 0.2 on (a+b+c)

#VALUE!

e)

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!

Cost for 5 cum = a+b+c+d+e (see notes below)


Rate per cum = (a+b+c+d+e)/5
Note

1.The cost of induction, deinduction and erection of


equipment shall be divided by the total quantity of pneumatic
sinking for all the wells of a particular bridge to arrive at the
per cum rate on account of this item.
2.Cost of pneumatic sinking per cum of individual wells will
be added to the cost indicated at (1) above to arrive at the
final rate of pneumatic sinking per cum.
3.The cost of induction and deinduction will depend upon the
distance involved for shifting of equipment which may be
assessed in individual cases as per actual ground conditions
at the time of making of cost estimates.
4.In case pneumatic sinking is involved on a dry bed, the
provision of barge and boat may be omitted.
5.The necessity and dimensions of the corbel will be as per
actual ground conditions.
6.Small equipments like welding sets, pumps, vibrators,
pneumatic tools, portable lamps, fire extinguishers, hose
pipes etc., have not been included as the same are covered
as items of minor T&P under overhead charges.
7.Depth of sinking shall be restricted to 30 m.

12.21

1207

Sand Filling in Wells complete as per Drawing and


Technical Specifications.
Unit = 1 cum
Taking output = 1 cum
a)

Material
Sand (assuming 20 per cent voids )

b)

c)

cum

1.20

616.00

739.20

M-006

Mate

day

0.01

673.00

6.73

L-12

Mazdoor

day

0.30

377.00

113.10

L-13

Labour

Overhead charges @ 0.2 on (a+b)


Page 62 of 394

171.81

Sr No

Ref. to
MoRTH
Spec.

Description
d)

Unit

Quantity

Rate Rs

Contractor's profit @ 0.1 on (a+b+c)

1200 &
1900

Remarks/
Input ref.

103.08

Rate per cum (a+b+c+d)


12.22

Cost Rs

1133.92
say

1134.00

46305.00

Providing Steel Liner 10 mm thick for Curbs and 6 mm


thick for Steining of Wells including Fabricating and
Setting out as per Detailed Drawing.
Unit = 1 MT
Taking output = 1 MT
a)

Material
i) Structural steel including 5 per cent wastage

b)

tonne

1.05

44100.00

Mate

day

1.24

673.00

834.52

L-12

Fitter

day

6.00

456.00

2736.00

L-08

Blacksmith

day

5.00

450.00

2250.00

L-01

Welder

day

5.00

500.00

2500.00

L-02

Mazdoor

day

10.00

377.00

3770.00

L-13

c)

Electrodes, cutting gas and other consumables @ 5


per cent on cost a (a) above.
Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

2315.25
12142.15
7285.29

Rate for per MT (a+b+c+d)

80138.22
say

12.23

1100 &
1700

M-179

Labour

80138.00

Bored cast-in-situ M35 grade R.C.C. Pile excluding


Reinforcement complete as per Drawing and Technical
Specifications and removal of excavated earth with all
lifts and lead upto 1000 m.
Pile diameter-750 mm
Unit = meter
Taking output = 15 m
a)

Materials
PCC Grade M35

cum

6.62

#VALUE!

#VALUE! Item 12.11


(C) iv

Hire and running charges of hydraulic piling rig with


power unit and complete accessories including shifting
from one bore location to another.

hour

6.00

5126.00

30756.00

P&M-036

Hire and running charges of light crane for lowering


reinforcement cage
Hire and running charges of Bentonite pump

hour

0.50

334.00

167.00

P&M-013

hour

Loader I cum bucket capacity.

hour

6.00 Rate included in


piling rig
0.30
756.00

226.80

P&M-017

Tipper 5.5 cum capacity for disposal of muck from pile


bore hole
Bentonite

hour

0.30

291.00

87.30

P&M-048

kg

300.00

6.35

1905.00

Mate/Supervisor

day

0.14

673.00

94.22

L-12

Mazdoor

day

3.50

377.00

1319.50

L-13

Rate for concrete may be adopted same as for bottom plug


vide item no. 12.11( C ) (IV)
Concrete to be cast with a tremie pipe 200mm dia.
b)

c)

Machinery( for boring and construction )

d)

Overhead charges @ 0.2 on (b+c)

e)

Contractor's profit @ 0.1 on (b+c+d)

6911.16
4146.70

Cost for 15 m = a+b+c+d+d+e

#VALUE!

Rate per metre (a+b+c+d+e)/15

#VALUE!
say

12.24
1100,160
0 & 1700

M-071

Labour

Bored cast-in-situ M35 grade R.C.C. Pile excluding


Reinforcement complete as per Drawing and Technical
Specifications and removal of excavated earth with all
lifts and lead upto 1000 m.
Pile diameter-1000 mm

Page 63 of 394

#VALUE!

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Unit = meter
Taking output = 10 m
a)

Materials
PCC Grade M35

cum

7.85

#VALUE!

#VALUE! Item 12.11


(C) iv

Hire and running charges of hydraulic piling rig with


power unit and complete accessories including shifting
from one bore location to another.

hour

6.00

5126.00

30756.00

P&M-036

Hire and running charges of light crane for lowering


reinforcement cage
Hire and running charges of Bentonite pump

hour

0.50

334.00

167.00

P&M-013

hour

Loader I cum bucket capacity.

hour

6.00 Rate included in


piling rig
0.40
756.00

302.40

P&M-017

Tipper 5.5 cum capacity for disposal of muck from pile


bore hole
Bentonite

hour

0.40

291.00

116.40

P&M-048

kg

350.00

6.35

2222.50

M-071

Mate/Supervisor

day

0.16

673.00

107.68

L-12

Mazdoor

day

4.00

377.00

1508.00

L-13

Rate for concrete may be adopted same as for bottom


plug vide item no. 12.11( C ) (IV)
Concrete to be cast with a tremie pipe 200mm dia.
b)

c)

Machinery( for boring and construction )

Labour

d)

Overhead charges @ 0.2 on (b+c)

e)

Contractor's profit @ 0.1 on (b+c+d)

7036.00
4221.60

Cost for 10 m = a+b+c+d+d+e

#VALUE!

Rate per metre (a+b+c+d+e)/10

#VALUE!
say

12.25

1100 &
1700

#VALUE!

Bored cast-in-situ M35 grade R.C.C. Pile excluding


Reinforcement complete as per Drawing and Technical
Specifications and removal of excavated earth with all
lifts and lead upto 1000 m.
Pile diameter-1200 mm
Unit = meter
Taking output = 9 m
a)

Materials
PCC Grade M35

cum

10.17

#VALUE!

#VALUE! Item 12.11


(C) iv

Hire and running charges of hydraulic piling rig with


power unit and complete accessories including shifting
from one bore location to another.
Hire and running charges of light crane for lowering
reinforcement cage
Hire and running charges of Bentonite pump

hour

6.00

5126.00

30756.00

P&M-036

hour

0.50

334.00

167.00

P&M-013

hour

Loader I cum bucket capacity.

hour

6.00 Rate included in


piling rig
0.50
756.00

378.00

P&M-017

Tipper 5.5 cum capacity for disposal of muck from pile


bore hole
Bentonite

hour

0.50

291.00

145.50

P&M-048

kg

385.00

6.35

2444.75

M-071

Mate/Supervisor

day

0.18

673.00

121.14

L-12

Mazdoor

day

4.50

377.00

1696.50

L-13

Rate for concrete may be adopted same as for bottom plug


vide item no. 12.11( C ) (IV)
Concrete to be cast with a tremie pipe 200mm dia.
b)

c)

Machinery( for boring and construction )

Labour

d)

Overhead charges @ 0.2 on (b+c)

e)

Contractor's profit @ 0.1 on (b+c+d)

7141.78
4285.07

Cost for 9 m = a+b+c+d+d+e

#VALUE!

Rate per metre (a+b+c+d+e)/9

#VALUE!
say

Page 64 of 394

#VALUE!

Sr No
12.26

Ref. to
MoRTH
Spec.

Description

1100 &
1700

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Driven cast-in-place vertical M35 grade R.C.C. Pile


excluding Reinforcement complete as per Drawing and
& Technical Specification
Pile diameter - 750 mm
Unit = Running meter
Taking output = 40 metre
a)

Materials
PCC Grade M35

cum

17.66

#VALUE!

#VALUE! Item 12.11


(C) iv

i) C.I. shoes for the pile

Kg

160.00

53.00

8480.00

M-080

ii) M.S. clamps for shoe @ 35 Kg per pile of 15 m

Kg

70.00

55.00

3850.00

M-124

iii) Steel helmet and cushion block on top of casing


head during driving
Machinery

Kg

50.00

input

#VALUE!

M-173

hour

6.00

input

#VALUE! P&M-085

hour

0.50

334.00

Mate/Supervisor

day

0.12

Mazdoor

day

3.00

Rate for concrete may be adopted same as for bottom plug


vide item no. 12.11( C ) (IV)
b) Materials Pile shoes

c)

Hire and running charges of piling rig Including double


acting pile driving hammer complete with power unit
and accessories..
Hiring and running charges for light crane 5 tonnes
lifting capacity for lowering reinforcement and handling
steel casing.
d)

167.00

P&M-070

673.00

80.76

L-12

377.00

1131.00

L-13

Labour

e)

Overhead charges @ 0.2 on (b+c+d)

#VALUE!

f)

Contractor's profit @ 0.1 on (b+c+d+e)

#VALUE!

Cost for 40 m = a+b+c+d+e

#VALUE!

Rate per metre (a+b+c+d+e)/40

#VALUE!
say

Note

12.27

1100 &
1700

#VALUE!

1.The quantity of concrete required to be removed above the


designed top level of concrete, if any, will be provided for in
the rate analysis.
2.In case steel lining is included in the design for driven castin-situ pile and is planned to be retained, the same may be
included in the rate analysis. In case the temporary steel
casing used during casting is planned to be removed, an
additional cost @ 0.50 per cent of cost of concrete may be
provided to cover its usage.
Driven cast-in-place vertical M35 grade R.C.C. Pile
excluding Reinforcement complete as per Drawing and
& Technical Specification
Pile diameter - 1000 mm
Unit = Running meter
Taking output = 30 metre
a)

Materials
PCC Grade M35

cum

23.55

#VALUE!

#VALUE! Item 12.11


(C) iv

i) C.I. shoes for the pile

Kg

160.00

53.00

8480.00

M-080

ii) M.S. clamps for shoe @ 35 Kg per pile of 15 m

Kg

70.00

55.00

3850.00

M-124

iii) Steel helmet and cushion block on top of casing


head during driving
Machinery

Kg

50.00

input

#VALUE!

M-173

hour

6.00

input

#VALUE! P&M-085

hour

0.50

334.00

Rate for concrete may be adopted same as for bottom


plug vide item no. 12.11( C ) (IV)
b) Materials Pile shoes

c)

Hire and running charges of piling rig Including double


acting pile driving hammer complete with power unit
and accessories.
Hiring and running charges for light crane 5 tonnes
lifting capacity for lowering reinforcement and handling
steel casing.

Page 65 of 394

167.00

P&M-070

Sr No

Ref. to
MoRTH
Spec.

Description

d)

Unit

Quantity

Rate Rs

Hire and running charges for light crane for lowering


reinforcement cage.
Labour

hour

0.50

334.00

Mate/Supervisor

day

0.16

Mazdoor

day

4.00

P&M-013

673.00

107.68

L-12

377.00

1508.00

L-13

e)

Overhead charges @ 0.2 on (b+c+d)

#VALUE!

f)

Contractor's profit @ 0.1 on (b+c+d+e)

#VALUE!
#VALUE!

Rate per metre (a+b+c+d+e)/30

#VALUE!
say

12.28

1100 &
1700

Remarks/
Input ref.

167.00

Cost for 30 m = a+b+c+d+e

Note

Cost Rs

#VALUE!

1.The quantity of concrete required to be removed above the


designed top level of concrete, if any, will be provided for in
the rate analysis.
2.In case steel lining is included in the design for driven castin-situ pile and is planned to be retained, the same may be
included in the rate analysis. In case the temporary steel
casing used during casting is planned to be removed, an
additional cost @ 0.50 per cent of cost of concrete may be
provided to cover its usage.
Driven cast-in-place vertical M35 grade R.C.C. Pile
excluding Reinforcement complete as per Drawing and
& Technical Specification
Pile diameter - 1200 mm
Unit = Running meter
Taking output = 20 metre
a)

Materials
PCC Grade M35

cum

22.61

#VALUE!

#VALUE! Item 12.11


(C) iv

i) C.I. shoes for the pile

Kg

160.00

53.00

8480.00

M-080

ii) M.S. clamps for shoe @ 35 Kg per pile of 15 m

Kg

70.00

55.00

3850.00

M-124

iii) Steel helmet on top of casing head during driving

Kg

50.00

input

#VALUE!

M-173

Hire and running charges of piling rig Including double


acting pile driving hammer complete with power unit
and accessories.

hour

6.00

input

#VALUE! P&M-085

Hiring and running charges for light crane 5 tonnes


lifting capacity for lowering reinforcement and handling
steel casing.
Labour

hour

0.50

334.00

Mate/Supervisor

day

0.18

Mazdoor

day

4.50

Rate for concrete may be adopted same as for bottom


plug vide item no. 12.11( C ) (IV)
b) Materials Pile shoes

c)

d)

Machinery

167.00

P&M-070

673.00

121.14

L-12

377.00

1696.50

L-13

e)

Overhead charges @ 0.2 on (b+c+d)

#VALUE!

f)

Contractor's profit @ 0.1 on (b+c+d+e)

#VALUE!

Cost for 20 m = a+b+c+d+e

#VALUE!

Rate per metre (a+b+c+d+e)/20

#VALUE!
say

Note

12.29

1100 &
1700

1.The quantity of concrete required to be removed above the


designed top level of concrete, if any, will be provided for in
the rate analysis.
2.In case steel lining is included in the design for driven castin-situ pile and is planned to be retained, the same may be
included in the rate analysis. In case the temporary steel
casing used during casting is planned to be removed, an
additional cost @ 0.50 per cent of cost of concrete may be
provided to cover its usage.
Driven precast vertical M35 grade R.C.C. Piles excluding
Reinforcement complete as per Drawing and &
Technical Specification
Pile Diameter = 500 mm
Unit = Running Meter
Page 66 of 394

#VALUE!

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Taking output = 60 m
a)

Materials
RCC Grade M35

cum

11.78

#VALUE!

#VALUE! Item 12.11


(F) iv

a) C.I Shoes

Kg

240.00

53.00

12720.00

M-080

b) M.S. shoes

Kg

105.00

53.00

5565.00

M-125

Kg

30.00

input

#VALUE!

M-173

c)

c) Steel helmet and cushion block on top of pile head


during driving.
Machinery
Crane20 t capacity

hour

6.00

input

#VALUE! P&M-073

hour

6.00

input

#VALUE! P&M-092

d)

Vibrating Pile driving hammer complete with power unit


and accessories.
Labour
Mate/Supervisor

day

0.12

673.00

80.76

L-12

Mazdoor

day

3.00

377.00

1131.00

L-13

Rate for concrete may be adopted same as for bottom


plug vide item no. 12.11( F ) (IV)
b ) Material Pile shoes

#VALUE!

e)

Add 1 per cent of (a+b+c) for carriage of piles from


casting yard to work site and stacking, and other
imponderables during installation.
Overhead charges @ 0.2 on (b+c+d)

f)

Contractor's profit @ 0.1 on (b+c+d+e)

#VALUE!

#VALUE!

Cost for 60 m = a+b+c+d+e+f

#VALUE!

Rate per metre (a+b+c+d+e+f)/60

#VALUE!
say

Note

12.30

1100 &
1700

#VALUE!

The quantity of concrete required to be removed above the


designed top level of concrete, if any, will be provided for in
the rate analysis.
Driven precast vertical M35 grade R.C.C. Piles excluding
Reinforcement complete as per Drawing and &
Technical Specification
Pile Diameter = 750 mm
Unit = Running Meter
Taking output = 50 m
a)

Materials
RCC Grade M35

cum

22.08

#VALUE!

#VALUE! Item 12.11


(F) iv

a) C.I. shoes

Kg

160.00

53.00

8480.00

M-080

b) M.S. shoes

Kg

70.00

53.00

3710.00

M-125

Kg

40.00

input

#VALUE!

M-173

c)

c) Steel helmet and cushion block on top of pile head


during driving.
Machinery
Crane 40 T capacity

hour

6.00

800.00

4800.00

P&M-074

hour

6.00

input

d)

Vibrating Pile driving hammer complete with power unit


and accessories.
Labour
Mate/Supervisor

day

0.16

673.00

107.68

L-12

Mazdoor

day

4.00

377.00

1508.00

L-13

Rate for concrete may be adopted same as for bottom


plug vide item no. 12.11( F ) (IV)
b ) Material Pile shoes

#VALUE! P&M-092

Add 1 per cent of (a+b+c) for carriage of piles from


casting yard to work site and stacking, and other
imponderables during installation.

#VALUE!

e)

Overhead charges @ 0.2 on (b+c+d)

#VALUE!

f)

Contractor's profit @ 0.1 on (b+c+d+e)

#VALUE!

Cost for 50 m = a+b+c+d+e+f

#VALUE!

Rate per metre (a+b+c+d+e+f)/50

#VALUE!
say

Page 67 of 394

#VALUE!

Sr No

Ref. to
MoRTH
Spec.

Description
Note

12.31

1100 &
1700

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

The quantity of concrete required to be removed above the


designed top level of concrete, if any, will be provided for in
the rate analysis.
Driven precast vertical M35 grade R.C.C. Piles excluding
Reinforcement complete as per Drawing and &
Technical Specification
Pile Diameter = 1000 mm
Unit = Running Meter
Taking output = 40 m
a)

Materials
RCC Grade M35

cum

31.40

#VALUE!

#VALUE! Item 12.11


(F) iv

a) C.I. shoes for the pile

Kg

160.00

53.00

8480.00

M-080

b) M.S. shoes @ 35 Kg per pile of 15 m

Kg

70.00

53.00

3710.00

M-125

Kg

50.00

input

#VALUE!

M-173

c)

c) Steel helmet and cushion block on top of pile head


during driving.
Machinery
Crane 50 t capacity.

hour

6.00

1200.00

7200.00

P&M-011

hour

6.00

input

d)

Vibrating Pile driving hammer complete with power unit


and accessories.
Labour
Mate/Supervisor

day

0.20

673.00

134.60

L-12

Mazdoor

day

5.00

377.00

1885.00

L-13

Rate for concrete may be adopted same as for bottom


plug vide item no. 12.11( F ) (IV)
b ) Material Pile shoes

#VALUE!

e)

Add 1 per cent of (a+b+c) for carriage of piles from


casting yard to work site and stacking, and other
imponderables during installation.
Overhead charges @ 0.2 on (b+c+d)

f)

Contractor's profit @ 0.1 on (b+c+d+e)

#VALUE!

#VALUE!

Cost for 40 m = a+b+c+d+e+f

#VALUE!

Rate per metre (a+b+c+d+e+f)/40

#VALUE!
say

Note

12.32

1100&17
00

#VALUE! P&M-092

#VALUE!

The quantity of concrete required to be removed above the


designed top level of concrete, if any, will be provided for in
the rate analysis.
Driven precast vertical M35 grade R.C.C. Piles excluding
Reinforcement complete as per Drawing and &
Technical Specification
Size of pile - 300 mm x 300 mm
Unit = Running Meter
Taking output = 60 m
a)

Materials

RCC Grade M-35


Rate for concrete may be adopted same as for bottom
plug vide item no. 12.11( F ) (IV)
b ) Material Pile shoes

c)

cum

5.40

#VALUE!

#VALUE! Item 12.11


(F) iv

a) C I shoes

kg

240.00

53.00

12720.00

M-080

b) M. S shoes

kg

105.00

53.00

5565.00

M-125

c) Steel helmet and cushion block on top of pile head


during driving.
Machinery

Kg

30.00

input

#VALUE!

M-173

hour

6.00

input

#VALUE! P&M-071

hour

6.00

input

#VALUE! P&M-092

Mate/Supervisor

day

0.12

673.00

80.76

L-12

Mazdoor

day

3.00

377.00

1131.00

L-13

Crane 10 tonne capacity


Vibrating Pile driving hammer complete with power unit
and accessories.
d ) Labour

Add 1 per cent of (a+b+c) for carriage of piles from


casting yard to work site and stacking, and other
imponderables during installation.
Page 68 of 394

#VALUE!

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

e)

Overhead charges @ 0.2 on (b+c+d)

#VALUE!

f)

Contractor's profit @ 0.1 on (b+c+d+e)

#VALUE!

Cost for 60 m = a+b+c+d+e+f

#VALUE!
say

12.33

1100
&1700

Remarks/
Input ref.

#VALUE!

Rate per metre (a+b+c+d+e+f)/60


Note

Cost Rs

#VALUE!

The quantity of concrete required to be removed above the


designed top level of concrete, if any, will be provided for in
the rate analysis.
Driven precast vertical M35 grade R.C.C. Piles excluding
Reinforcement complete as per Drawing and &
Technical Specification
Size of pile - 500 mm x 500 mm
Unit = Running Meter
Taking output = 50 m
a)

Materials

RCC Grade M-35


Rate for concrete may be adopted same as for bottom
plug vide item no. 12.11( F ) (IV)
b ) Material Pile shoes

c)

cum

12.50

#VALUE!

a) C I shoes

kg

160.00

53.00

8480.00

M-080

b) M. S shoes

kg

70.00

53.00

3710.00

M-125

c) Steel helmet and cushion block on top of pile head


during driving.
Machinery

Kg

30.00

input

#VALUE!

M-173

hour

6.00

input

#VALUE! P&M-073

hour

6.00

input

#VALUE! P&M-092

Mate/Supervisor

day

0.16

673.00

107.68

L-12

Mazdoor

day

4.00

377.00

1508.00

L-13

Crane 20 tonne capacity


Vibrating Pile driving hammer complete with power unit
and accessories.
d ) Labour

Add 1 per cent of (a+b+c) for carriage of piles from


casting yard to work site and stacking, and other
imponderables during installation.

#VALUE!

e)

Overhead charges @ 0.2 on (b+c+d)

#VALUE!

f)

Contractor's profit @ 0.1 on (b+c+d+e)

#VALUE!

Cost for 50 m = a+b+c+d+e+f

#VALUE!

Rate per metre (a+b+c+d+e+f)/50

#VALUE!
say

Note

12.34

1100
&1700

#VALUE! Item 12.11


(F) iv

#VALUE!

The quantity of concrete required to be removed above the


designed top level of concrete, if any, will be provided for in
the rate analysis.
Driven precast vertical M35 grade R.C.C. Piles excluding
Reinforcement complete as per Drawing and &
Technical Specification
Size of pile - 750 mm x 750 mm
Unit = Running Meter
Taking output = 40 m
a)

Materials

RCC Grade M-35


Rate for concrete may be adopted same as for bottom
plug vide item no. 13.11( F ) (IV)
b ) Material

cum

22.50

#VALUE!

#VALUE! Item 12.11


(F) iv

a) C I shoes

kg

160.00

53.00

8480.00

M-080

b) M. S shoes

kg

70.00

53.00

3710.00

M-125

c) Steel helmet and cushion block on top of pile head


during driving.
Machinery

Kg

30.00

input

#VALUE!

M-173

Crane 20 tonne capacity

hour

6.00

input

#VALUE! P&M-073

Vibrating Pile driving hammer complete with power unit


and accessories.

hour

6.00

input

#VALUE! P&M-092

Pile shoes

c)

Page 69 of 394

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

d ) Labour
Mate/Supervisor

day

0.18

673.00

121.14

L-12

Mazdoor

day

4.50

377.00

1696.50

L-13

#VALUE!

e)

Add 1 per cent of (a+b+c) for carriage of piles from


casting yard to work site and stacking, and other
imponderables during installation.
Overhead charges @ 0.2 on (b+c+d)

f)

Contractor's profit @ 0.1 on (b+c+d+e)

#VALUE!

#VALUE!

Cost for 40 m = a+b+c+d+e+f

#VALUE!

Rate per metre (a+b+c+d+e+f)/40


Note

12.35

1100,
1900

#VALUE!
say

#VALUE!

266364.00

The quantity of concrete required to be removed above the


designed top level of concrete, if any, will be provided for in
the rate analysis.
Driven Vertical Steel Piles complete as per Drawing and
& Technical Specification
Section of the pile - H Section steel column 400 x 250 mm
(ISHB Series)
Unit = Running Meter
Taking output = 70 m
a)

Materials

b)

Structural steel including 5 per cent wastage @ 82.20


kg/m
Machinery

c)

tonnes

6.04

44100.00

Crane 10 T capacity

hour

6.00

input

#VALUE! P&M-071

Vibrating Pile driving hammer complete with power unit


and other accessories.
Labour

hour

6.00

input

#VALUE! P&M-092

Mate/Supervisor

day

0.12

673.00

80.76

L-12

Mazdoor

day

3.00

377.00

1131.00

L-13

Add 0.5 per cent of (a+b+c) for providing steel


helmet on top of pile head during driving, stacking of
piles at site, providing anti-corrosion treatment and
other imponderables during installation.

#VALUE!

d)

Overhead charges @ 0.2 on (a+b+c)

#VALUE!

e)

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!

Cost for 70 m = a+b+c+d+e

#VALUE!

Rate per metre (a+b+c+d+e)/70


12.36

1100
&1900

M-179

#VALUE!
say

#VALUE!

257103.00

Driven Vertical Steel Piles complete as per Drawing and


& Technical Specification
Section of the pile - H Section steel column 450 x 250 mm
(ISHB Series)
Unit = Running Meter
Taking output = 60 m
a)

Materials

b)

Structural steel including 5 per cent wastage @92.50


kg/m
Machinery

c)

tonnes

5.83

44100.00

Crane 10 T capacity

hour

6.00

input

#VALUE! P&M-071

Vibrating Pile driving hammer complete with power unit


and accessories.
Labour

hour

6.00

input

#VALUE! P&M-092

Mate/Supervisor

day

0.14

673.00

94.22

L-12

Mazdoor

day

3.50

377.00

1319.50

L-13

Add 0.5 per cent of (a+b+c) for providing steel


helmet and cushion block on top of pile head during
driving, stacking of piles at site, providing anti-corrosive
treatment and other imponderables during installation.

#VALUE!

d)

Overhead charges @ 0.2 on (a+b+c)

#VALUE!

e)

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!

Page 70 of 394

M-179

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost for 60 m = a+b+c+d+e

#VALUE!
say

1100

Remarks/
Input ref.

#VALUE!

Rate per metre (a+b+c+d+e)/60


12.37

Cost Rs

#VALUE!

Pile Load Test on single Vertical Pile in accordance with


IS:2911(Part-IV)
Unit = 1 MT
Taking output = 1 MT

Note

12.38

1100,
1500
&1700

a) Initial and routine load test

tonne

1.00

300.00

b) Lateral load test

tonne

1.00

5000.00

Cement

tonne

5.12

5940.00

30412.80

M-081

Coarse sand

cum

6.75

2400.00

16200.00

M-005

20 mm Aggregate

cum

8.10

942.00

7630.20

M-053

10 mm Aggregate

cum

5.40

1063.00

5740.20

M-051

Mate

day

0.90

673.00

605.70

L-12

Mason

day

1.50

471.00

706.50

L-10

Mazdoor for concreting

day

20.00

377.00

7540.00

L-13

Mazdoor for breaking pile head, bending bars, cleaning


etc.
Machinery

day

1.00

377.00

377.00

L-13

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

218.00

1308.00

P&M-009

Generator (capacity 33 KVA)

hour

6.00

349.00

2094.00

P&M-079

Although, this item is incidental to work and is not required to


be included in BOQ of contract, the same is required to be
added in the estimate to assess cost of work.
Cement Concrete for Reinforced Concrete in Pile Cap
complete as per Drawing and Technical Specification

RCC Grade M20


Unit = cum
Taking output = 15 cum

(i)

Using Concrete Mixer


a)

b)

c)

Material

Labour

d)

Formwork @ 4 per cent on cost of concrete i.e. cost


of a) Material, b) Labour and c) Machinery
Overhead charges @ 0.2 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

2904.58
15103.80
9062.28

Cost for 15 cum = a+b+c+d+e

99685.05

Rate per metre (a+b+c+d+e)/15


12.38A

(ii)

6645.67
say

6646.00

Using Batching Plant, Transit Mixer and Concrete Pump


a)

b)

c)

Material
Cement

tonne

5.12

5940.00

30412.80

M-081

Coarse sand

cum

6.75

2400.00

16200.00

M-004

20 mm Aggregate

cum

8.10

942.00

7630.20

M-053

10 mm Aggregate

cum

5.40

1063.00

5740.20

M-051

Mate

day

0.16

673.00

107.68

L-12

Mason

day

0.38

471.00

178.98

L-10

Mazdoor for concreting

day

2.50

377.00

942.50

L-13

Mazdoor for breaking pile head, bending bars, cleaning


etc.
Machinery

day

1.00

377.00

377.00

L-13

Batching Plant @ 20 cum/hour

hour

0.75

2094.00

1570.50

P&M-002

Generator 100 KVA

hour

0.75

654.00

490.50

P&M-080

Loader (capacity 1 cum)

hour

0.75

756.00

567.00

P&M-017

hour

2.00

873.00

1746.00

P&M-049

Labour

Transit Mixer ( capacity 4.0 cu.m )


Lead upto 1 Km
Page 71 of 394

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Lead beyond 1 Km, L - lead in Kilometer

Concrete Pump

Quantity

Rate Rs

tonne.km

37.5L

input

hour

0.75

240.00

Lead =1
km & P&M050

180.00

P&M-007

#VALUE!

d)
e)

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!

#VALUE!
#VALUE!

Rate per metre (a+b+c+d+e)/15

12.38

Remarks/
Input ref.

#VALUE!

Formwork @ 4 per cent on cost of concrete i.e. cost


of a) Material, b) Labour and c) Machinery
Overhead charges @ 0.2 on (a+b+c)

Cost for 15 cum = a+b+c+d+e

Note

Cost Rs

#VALUE!
say

#VALUE!

The value of a, b and c may be taken as applicable i.e.


either using concrete mixer or batching plant.
RCC Grade M25
Unit = cum
Taking output = 15 cum

(i)

Using Concrete Mixer


a)

b)

c)

Material
Cement

tonne

5.99

5940.00

35580.60

M-081

Coarse sand

cum

6.75

2400.00

16200.00

M-005

20 mm Aggregate

cum

8.10

942.00

7630.20

M-053

10 mm Aggregate

cum

5.40

1063.00

5740.20

M-051

Mate

day

0.90

673.00

605.70

L-12

Mason

day

1.50

471.00

706.50

L-10

Mazdoor for concreting

day

20.00

377.00

7540.00

L-13

Mazdoor for breaking pile head, bending bars, cleaning


etc.
Machinery

day

1.00

377.00

377.00

L-13

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

218.00

1308.00

P&M-009

Generator (capacity 33 KVA)

hour

6.00

349.00

2094.00

P&M-079

Labour

d)

Formwork @ 4 per cent on cost of concrete i.e. cost


of a) Material, b) Labour and c) Machinery
Overhead charges @ 0.2 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

3111.29
16178.70
9707.22

Cost for 15 cum = a+b+c+d+e

106779.40

Rate per metre (a+b+c+d+e)/15


12.38B

(ii)

7118.63
say

7119.00

Using Batching Plant, Transit Mixer and Concrete Pump


a)

b)

c)

Material
Cement

tonne

5.99

5940.00

35580.60

M-081

Coarse sand

cum

6.75

2400.00

16200.00

M-004

20 mm Aggregate

cum

8.10

942.00

7630.20

M-053

10 mm Aggregate

cum

5.40

1063.00

5740.20

M-051

Mate

day

0.16

673.00

107.68

L-12

Mason

day

0.38

471.00

178.98

L-10

Mazdoor for concreting

day

2.50

377.00

942.50

L-13

Mazdoor for breaking pile head, bending bars, cleaning


etc.
Machinery

day

1.00

377.00

377.00

L-13

Batching Plant @ 20 cum/hour

hour

0.75

2094.00

1570.50

P&M-002

Generator 125 KVA

hour

0.75

654.00

490.50

P&M-018

Loader (capacity 1 cum)

hour

0.75

756.00

567.00

P&M-017

hour

2.00

873.00

1746.00

P&M-049

tonne.km

37.5L

input

#VALUE!

Lead =1
km & P&M050

Labour

Transit Mixer ( capacity 4.0 cu.m )


Lead upto 1 Km
Lead beyond 1 Km, L - lead in Kilometer

Page 72 of 394

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Concrete Pump

hour

Quantity
0.75

Rate Rs
240.00

#VALUE!

d)
e)

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!

Remarks/
Input ref.
P&M-007

#VALUE!
#VALUE!

Rate per metre (a+b+c+d+e)/15

12.38

180.00

Formwork @ 4 per cent on cost of concrete i.e. cost


of a) Material, b) Labour and c) Machinery
Overhead charges @ 0.2 on (a+b+c)

Cost for 15 cum = a+b+c+d+e

Note

Cost Rs

#VALUE!
say

#VALUE!

The value of a, b and c may be taken as applicable i.e.


either using concrete mixer or batching plant.
RCC Grade M30
Unit = cum
Taking output = 15 cum

(i)

Using Concrete Mixer


a)

b)

c)

Material
Cement

tonne

6.10

5940.00

36234.00

M-081

Coarse sand

cum

6.75

2400.00

16200.00

M-005

20 mm Aggregate

cum

8.10

942.00

7630.20

M-053

10 mm Aggregate

cum

5.40

1063.00

5740.20

M-051

Mate

day

0.90

673.00

605.70

L-12

Mason

day

1.50

471.00

706.50

L-10

Mazdoor for concreting

day

20.00

377.00

7540.00

L-13

Mazdoor for breaking pile head, bending bars, cleaning


etc.
Machinery

day

1.00

377.00

377.00

L-13

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

218.00

1308.00

P&M-009

Generator (capacity 33 KVA)

hour

6.00

349.00

2094.00

P&M-079

Labour

d)

Formwork @ 4 per cent on cost of concrete i.e. cost


of a) Material, b) Labour and c) Machinery
Overhead charges @ 0.2 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

3137.42
16314.60
9788.76

Cost for 15 cum = a+b+c+d+e

107676.39

Rate per metre (a+b+c+d+e)/15


'12.38C

(ii)

7178.43
say

7178.00

Using Batching Plant, Transit Mixer and Concrete Pump


a)

b)

c)

Material
Cement

tonne

6.10

5940.00

36234.00

M-081

Coarse sand

cum

6.75

2400.00

16200.00

M-004

20 mm Aggregate

cum

8.10

942.00

7630.20

M-053

10 mm Aggregate

cum

5.40

1063.00

5740.20

M-051

Mate

day

0.16

673.00

107.68

L-12

Mason

day

0.38

471.00

178.98

L-10

Mazdoor for concreting

day

2.50

377.00

942.50

L-13

Mazdoor for breaking pile head, bending bars, cleaning


etc.
Machinery

day

1.00

377.00

377.00

L-13

Batching Plant @ 20 cum/hour

hour

0.75

2094.00

1570.50

P&M-002

Generator 100 KVA

hour

0.75

654.00

490.50

P&M-080

Loader (capacity 1 cum)

hour

0.75

756.00

567.00

P&M-017

Labour

Transit Mixer ( capacity 4.0 cu.m )


Lead upto 1 Km
Lead beyond 1 Km, L - lead in Kilometer

Concrete Pump

Page 73 of 394

hour

2.00

873.00

1746.00

P&M-049

tonne.km

37.5L

input

#VALUE!

Lead =1
km & P&M050

hour

0.75

240.00

180.00

P&M-007

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

#VALUE!

d)

Formwork @ 4 per cent on cost of concrete i.e. cost


of a) Material, b) Labour and c) Machinery
Overhead charges @ 0.2 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!
#VALUE!

Rate per metre (a+b+c+d+e)/15

12.38

Remarks/
Input ref.

#VALUE!

Cost for 15 cum = a+b+c+d+e

Note

Cost Rs

#VALUE!
say

#VALUE!

The value of a, b and c may be taken as applicable i.e.


either using concrete mixer or batching plant.
RCC Grade M35
Unit = cum
Taking output = 15 cum

(i)

Using Concrete Mixer


a)

b)

c)

Material
Cement

tonne

6.33

5940.00

37600.20

M-081

Coarse sand

cum

6.75

2400.00

16200.00

M-005

20 mm Aggregate

cum

8.10

942.00

7630.20

M-053

10 mm Aggregate

cum

5.40

1063.00

5740.20

M-051

Mate

day

0.90

673.00

605.70

L-12

Mason

day

1.50

471.00

706.50

L-10

Mazdoor

day

20.00

377.00

7540.00

L-13

Mazdoor for breaking pile head, bending bars, cleaning


etc.
Machinery

day

1.00

377.00

377.00

L-13

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

218.00

1308.00

P&M-009

Generator (capacity 33 KVA)

hour

6.00

349.00

2094.00

P&M-079

Labour

d)

Formwork @ 4 per cent on cost of concrete i.e. cost


of a) Material, b) Labour and c) Machinery
Overhead charges @ 0.2 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

3192.07
16598.77
9959.26

Cost for 15 cum = a+b+c+d+e

109551.91

Rate per metre (a+b+c+d+e)/15


'12.38D

(ii)

7303.46
say

7303.00

Using Batching Plant, Transit Mixer and Concrete Pump


a)

b)

c)

Material
Cement

tonne

6.33

5940.00

37600.20

M-081

Coarse sand

cum

6.75

2400.00

16200.00

M-004

20 mm Aggregate

cum

8.10

942.00

7630.20

M-053

10 mm Aggregate

cum

5.40

1063.00

5740.20

M-051

Mate

day

0.16

673.00

107.68

L-12

Mason

day

0.38

471.00

178.98

L-10

Mazdoor for concreting

day

2.50

377.00

942.50

L-13

Mazdoor for breaking pile head, bending bars, cleaning


etc.
Machinery

day

1.00

377.00

377.00

L-13

Batching Plant @ 20 cum/hour

hour

0.75

2094.00

1570.50

P&M-002

Generator 125 KVA

hour

0.75

654.00

490.50

P&M-018

Loader (capacity 1 cum)

hour

0.75

756.00

567.00

P&M-017

Labour

Transit Mixer ( capacity 4.0 cu.m )


Lead upto 1 Km
Lead beyond 1 Km, L - lead in Kilometer

Concrete Pump
Formwork @ 4 per cent on cost of concrete i.e. cost
of a) Material, b) Labour and c) Machinery

Page 74 of 394

hour

2.00

873.00

1746.00

P&M-049

tonne.km

37.5L

input

#VALUE!

Lead =1
km & P&M050

hour

0.75

240.00

180.00

P&M-007

#VALUE!

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

d)

Overhead charges @ 0.2 on (a+b+c)

#VALUE!

e)

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!

Cost for 15 cum = a+b+c+d+e

1100&17
00

Remarks/
Input ref.

#VALUE!

Rate per metre (a+b+c+d+e)/15


12.39

Cost Rs

#VALUE!
say

#VALUE!

Levelling Course for Pile cap


Providing and laying of PCC M15 levelling course
100mm thick below the pile cap.
Unit = cum
Taking output = 15 cum
a)

b)

c)

Material
Cement

tonne

4.13

5940.00

24532.20

M-081

Coarse sand

cum

6.75

2400.00

16200.00

M-005

40 mm aggregate

cum

8.10

659.00

5337.90

M-055

20 mm Aggregate

cum

4.05

942.00

3815.10

M-053

10 mm Aggregate

cum

1.35

1063.00

1435.05

M-051

Mate

day

0.86

673.00

578.78

L-12

Mason

day

1.50

471.00

706.50

L-10

Mazdoor

day

20.00

377.00

7540.00

L-13

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

218.00

1308.00

P&M-009

Generator 33 KVA

hour

6.00

349.00

2094.00

P&M-079

Labour

Machinery

d)

Overhead charges @ 0.2 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

12709.51
7625.70

Cost for 15 cum = a+b+c+d+e

83882.74

Rate per metre (a+b+c+d+e)/15


12.40

1600

5592.18
say

5592.00

Supplying, Fitting and Placing un-coated HYSD bar


Reinforcement in Foundation complete as per Drawing
and Technical Specifications.
Unit = 1 MT
Taking output = 1 MT
a)

Material
HYSD bars including5 per cent overlaps and wastage
Binding wire

b)
Labour for cutting, bending, shifting to site, tying
and placing in position
Mate

tonne

1.05

52100.00

54705.00

M-082

Kg

6.00

87.00

522.00

M-072

day

0.40

673.00

269.20

L-12

Blacksmith

day

2.00

500.00

1000.00

L-02

Mazdoor

day

6.00

377.00

2262.00

L-13

11751.64
7050.98
77560.82
12.41

1600

say

77561.00

Supplying, fitting and placing un-coated Mild steel


reinforcement complete in foundation as per drawing
and technical specification
Unit = 1 MT
Taking output = 1 MT
a)

Material
MS bars including 5 per cent overlaps and wastage
Binding wire

b)
Labour for straightening, cutting, bending, shifting
to site, tying and placing in position
Mate
Blacksmith
Page 75 of 394

tonne

1.05

37100.00

38955.00

M-126

Kg

6.00

87.00

522.00

M-072

day

0.43

673.00

289.39

L-12

day

2.25

500.00

1125.00

L-02

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Mazdoor

day

c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

Quantity
6.50

Rate Rs
377.00

Cost Rs
2450.50
8668.38
5201.03

Rate for per MT (a+b+c+d)

57211.29
say

Page 76 of 394

57211.00

Remarks/
Input ref.
L-13

CHAPTER-13
SUB-STRUCTURE
Sr No
13.1

13.2

Ref. to
MoRTH
Spec.

Description

1300 &
2200

Unit

Brick masonry work in 1:3 in sub-structure complete


excluding pointing and plastering, as per drawing and
Technical Specifications
Unit = cum
Taking output = 1 cum
a) Material
Bricks Ist class
Cement mortar 1:3 (Rate as in Item 12.6 A subanalysis)
b) Labour
Mate
Mason
Mazdoor
Add for scaffolding @ 5 per cent of cost of material
and labour
c) Overhead charges @ 0.2 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Rate per cum (a+b+c+d)

1300 &
2200

Pointing with cement mortar (1:3 ) on brick work in


substructure as per Technical Specifications
Unit = 10 sqm
Taking output = 10 sqm
a) Material
Cement mortar 1:3 (Rate as in Item 12.6 )
Labour
Mate
Mason
Mazdoor
c) Overhead charges @ 0.2 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Rate per 10 sqm (a+b+c+d)

each
cum

day
day
day

Quantity

Rate Rs

Cost Rs

Remarks/ Input
ref.

500.00
0.24

3.80
5916.00

1900.00
1419.84

M-079
Item 12.6 (A)

0.06
0.80
0.80

673.00
500.00
377.00

40.38
400.00
301.60
203.09

L-12
L-11
L-13

say

852.98
511.79
5629.68
5630.00

cum

0.03

5916.00

177.48

Item 12.6 (A)

day
day
day

0.04
0.50
0.50

673.00
500.00
377.00

L-12
L-11
L-13

say

26.92
250.00
188.50
128.58
77.15
848.63
849.00

b)

13.3

13.4

Note
1300 &
2200

Scaffolding is already included in item 13.1


Plastering with cement mortar (1:3 ) on brick work in
sub-structure as per Technical Specifications
Unit = 10 sqm
Taking output = 10 sqm
a) Material
Cement mortar 1:3 (Rate as in Item 12.6)
b) Labour
Mate
Mason
Mazdoor
c) Overhead charges @ 0.2 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Rate per 10 sqm (a+b+c+d)

Note

1.Scaffolding is already included in item no. 13.1


2.The number of masons and Mazdoors already catered in
the cement mortar have been taken into account while
providing these categories in brick masonry, pointing and
plastering.

1400 &
2200

Stone masonry work in cement mortar 1:3 for


substructure complete as per drawing and Technical
Specifications
Random Rubble Masonry
( coursed/uncoursed )
Unit = cum
Taking output = 1 cum
a) Material
Stone

Through and bond stone


(7no.x0.24mx0.24mx0.39m = 0.16 cu.m)
Page 1 of 394

cum

0.144

5916.00

851.90

Item 12.6 (A)

day
day
day

0.04
0.50
0.50

673.00
500.00
377.00

L-12
L-11
L-13

say

26.92
250.00
188.50
263.46
158.08
1738.87
1739.00

cum

1.00

391.00

391.00

M-148

No

7.00

14.00

98.00

M-182

Sr No

Ref. to
MoRTH
Spec.

Description

b)

Unit

Quantity

Rate Rs

Cost Rs

Cement mortar 1:3 (Rate as in Item 12.6)


Labour

cum

0.33

5916.00

1952.28

Mate

day

0.10

673.00

67.30

L-12

Mason

day

1.20

500.00

600.00

L-11

Mazdoor

day

1.20

377.00

452.40

L-13

c)

Add for scaffolding @ 5 per cent of cost of a)


Material and b) Labour
Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

Item 12.6 (A)

178.05
747.81
448.68

Rate per cum (a+b+c+d)


13.4

Remarks/ Input
ref.

4935.52
say

4936.00

Coursed rubble masonry (first sort )


Unit = cum
Taking output = 1 cum
a) Material
Stone

cum

1.10

391.00

430.10

M-148

Through and bond stone

each

7.00

14.00

98.00

M-182

cum

0.30

5916.00

1774.80

Mate

day

0.12

673.00

80.76

Mason

day

1.50

500.00

750.00

L-11

Mazdoor

day

1.50

377.00

565.50

L-13

(7no.x0.24mx0.24mx0.39m = 0.16 cu.m)


Cement mortar 1:3 (Rate as in Item 12.6)
b)

c)

Add for scaffolding @ 5 per cent of cost of material


and labour
Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

L-12

184.96
776.82
466.09

Rate per cum (a+b+c+d)


13.4

Item 12.6 (A)

Labour

5127.04
say

5127.00

Ashlar masonry ( first sort )


Plain ashlar
Unit = cum
Taking output = 1 cum
a) Material
Stone

cum

1.11

753.00

835.83

M-169

Through and bond stone

each

7.00

14.00

98.00

M-182

cum

0.33

5916.00

1952.28

Item 12.6 (A)

Mate

day

0.20

673.00

134.60

L-12

Mason

day

2.50

500.00

1250.00

L-11

Mazdoor

day

2.50

377.00

942.50

L-13

(7no.x0.24mx0.24mx0.39m = 0.16 cu.m)


Cement mortar 1:3 (Rate as in Item 12.6)
b)

Labour for masonry work

c)

Add for scaffolding @ 5 per cent of cost of a)


Material and b) Labour
Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

260.66
1094.77
656.86

Rate per cum (a+b+c+d)

7225.51
say

Note

13.5

The labour already considered in the cement mortar have


been taken into account while providing these categories in
the stone masonry works.
Plain/Reinforced cement concrete in sub-structure
complete as per drawing and Technical Specifications

1500,
1700 &
2200

Unit = cum
Taking output = 1 cum
A

PCC Grade M15


Page 2 of 394

7226.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/ Input
ref.

(p) Height upto 5m


Same as Item 12.8 (A) upto 5 m height, except for formwork
which shall be 10 per cent instead of 4 per cent of cost of
material, labour and machinery.
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (A)
d) formwork

e)

Add 10 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

4240.00 Item 12.8 (A)

10.00

424.00
932.80
559.68

Rate perm (a+b+c+d+e+f)

6156.48
say

13.5

6156.00

PCC Grade M20

(p) Height upto 5m


Same as Item 12.8 (B) upto 5 m height, except for formwork
which shall be 10 per cent instead of 4 per cent of cost of
material, labour and machinery.
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (B)
d) formwork

e)

Add 10 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

4710.00 Item 12.8 (B) PCC

10.00

471.00
1036.20
621.72

Rate perm (a+b+c+d+e+f)

6838.92
say

13.5

6839.00

PCC Grade M25

(p) Height upto 5m


Same as Item 12.8 (D) upto 5 m height with the only change
that the provision of form work shall be 10 per cent instead
of 3.75 per cent of cost of material, labour and machinery.
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (D) Case I
d) formwork

e)

Add 10 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

5038.00 Item 12.8 (D)

10.00

503.80
1108.36
665.02

Rate perm (a+b+c+d+e+f)

7315.18
say

13.5 C
(p)

Case With Batching Plant, Transit Mixer and Concrete Pump


II
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (D) Case II
d) formwork

e)

Add 10 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

#VALUE! Item 12.8 (D)

10.00

#VALUE!
#VALUE!
#VALUE!

Rate perm (a+b+c+d+e+f)

#VALUE!
say

13.5 C

7315.00

(q) Height 5m to 10m


Same as Item 12.8 (D) with the following changes: (i) Add 2
per cent of cost of material, Labour and machinery
excluding form work to cater for extra lift. (ii) The provision of
form work shall be 12 per cent instead of 3.75 per cent of
cost of material, labour and machinery
Case Using concrete Mixer
I
Page 3 of 394

#VALUE!

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c) of Item 12.8 (D) Case I
d) formwork

e)

Add 12 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Add 2 per cent of cost of material, Labour and
machinery excluding formwork to cater for extra lift
Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

5038.00 Item 12.8 (D)

12.00

604.56

2.00

100.76
1148.66
689.20

Rate perm (a+b+c+d+e+f)

7581.18
say

13.5 C
(q)

Case With Batching Plant, Transit Mixer and Concrete Pump


II
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (D) Case II
d) formwork

e)

Add 12 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Add 2 per cent of cost of material, Labour and
machinery excluding formwork to cater for extra lift
Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

12.00

#VALUE!

2.00

#VALUE!
#VALUE!
#VALUE!
#VALUE!
say

(r)

7581.00

#VALUE!

Rate perm (a+b+c+d+e+f)


13.5 C

Remarks/ Input
ref.

#VALUE!

Height above 10m


Same as Item 12.8 (D) with the following changes: (i) Add 4
per cent of cost of material, labour and machinery excluding
form work to cater for extra lift. (ii) The provision of form work
shall be 15 per cent instead of 3.75 per cent of cost of
material, labour and machinery.

Case Using concrete Mixer


I
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (D) Case I
d) formwork

e)

Add 15 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and
machinery excluding formwork to cater for extra lift
Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

5038.00 Item 12.8 (D)

15.00

755.70

4.00

201.52
1199.04
719.43

Rate perm (a+b+c+d+e+f)

7913.69
say

13.5 C
(r)

Case With Batching Plant, Transit Mixer and Concrete Pump


II
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (D) Case II
d) formwork

e)

Add 15 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and
machinery excluding formwork to cater for extra lift
Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

#VALUE! Item 12.8 (D)

15.00

#VALUE!

4.00

#VALUE!
#VALUE!
#VALUE!

Rate perm (a+b+c+d+e+f)

#VALUE!
say

13.5

7914.00

PCC Grade M30

(p) Height upto 5m


Same as Item 12.8 (F) upto 5 m height with the only change
that the provision of form work shall be 10 per cent instead
of 3.50 per cent of cost of material, labour and machinery.
Case Using concrete Mixer
I
Page 4 of 394

#VALUE!

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c) of Item 12.8 (F) Case I
d) formwork

e)

Add 10 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

5074.00

10.00

507.40
1116.28
669.77

Rate perm (a+b+c+d+e+f)

7367.45
say

13.5 D
(p)

Case With Batching Plant, Transit Mixer and Concrete Pump


II
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (F) Case II
d) formwork

e)

Add 10 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

#VALUE!

10.00

#VALUE!
#VALUE!
#VALUE!

Rate perm (a+b+c+d+e+f)

#VALUE!
say

13.5 D

7367.00

#VALUE!

(q) Height 5m to 10m


Same as Item 12.8 (F) with the following changes: (i) Add 2
per cent of cost of material, Labour and machinery
excluding form work to cater for extra lift. (ii) The provision of
form work shall be 12 per cent instead of 3.50 per cent of
cost of material, labour and machinery.
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (F) Case I
d) formwork

e)

Add 12 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Add 2 per cent of cost of material, Labour and
machinery excluding formwork to cater for extra lift
Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

5074.00

12.00

608.88

2.00

101.48
1156.87
694.12

Rate perm (a+b+c+d+e+f)

7635.36
say

13.5 D
(q)

Case With Batching Plant, Transit Mixer and Concrete Pump


II
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (F) Case II
d) formwork

e)

Add 12 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Add 2 per cent of cost of material, Labour and
machinery excluding formwork to cater for extra lift
Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

#VALUE!

12.00

#VALUE!

2.00

#VALUE!
#VALUE!
#VALUE!

Rate perm (a+b+c+d+e+f)

#VALUE!
say

13.5 D

(r)

7635.00

#VALUE!

Height above 10m


Same as Item 12.8 (F) with the following changes: (i) Add 4
per cent of cost of material, labour and machinery excluding
form work to cater for extra lift. (ii) The provision of form work
shall be 15 per cent instead of 3.50 per cent of cost of
material, labour and machinery

Case Using concrete Mixer


I
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (F) Case I
d) formwork

Page 5 of 394

5074.00

Remarks/ Input
ref.

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

e)

Add 15 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and
machinery excluding formwork to cater for extra lift
Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

Quantity

Rate Rs

Cost Rs

15.00

761.10

4.00

202.96
1207.61
724.57

Rate perm (a+b+c+d+e+f)

7970.24
say

13.5 D
(r)

Case With Batching Plant, Transit Mixer and Concrete Pump


II
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (F) Case II
d) formwork

e)

Add 15 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and
machinery excluding formwork to cater for extra lift
Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

#VALUE!

15.00

#VALUE!

4.00

#VALUE!
#VALUE!
#VALUE!

Rate perm (a+b+c+d+e+f)

#VALUE!
say

13.5

7970.00

#VALUE!

RCC Grade M20

(p) Height upto 5m


Same as Item 12.8 (C) upto 5 m height, except for formwork
which shall be 10 per cent instead of 4 per cent of cost of
material, labour and machinery.
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (C) Case I
d) formwork

e)

Add 10 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

10.00

#VALUE!
#VALUE!
#VALUE!

Rate perm (a+b+c+d+e+f)

#VALUE!
say

13.5 E
(p)

Case With Batching Plant, Transit Mixer and Concrete Pump


II
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (C) Case II
d) formwork

e)

Add 10 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

#VALUE!

10.00

#VALUE!
#VALUE!
#VALUE!

Rate perm (a+b+c+d+e+f)

#VALUE!
say

13.5 E

#VALUE!

#VALUE!

(q) Height 5m to 10m


For height, upto 10m, add 2 per cent of cost as above
excluding formwork. For cost of formwork add 12 per cent of
cost of material, labour and machinery instead of 4 per cent .
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (C) Case I
d) formwork

e)

Add 12 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Add 2 per cent of cost of material, Labour and
machinery excluding formwork to cater for extra lift
Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)


Page 6 of 394

4853.00

12.00

582.36

2.00

97.06
1106.48
663.89

Remarks/ Input
ref.

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Rate perm (a+b+c+d+e+f)

7302.79
say

13.5 E
(q)

Case With Batching Plant, Transit Mixer and Concrete Pump


II
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (C) Case II
d) formwork

e)

Add 12 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Add 2 per cent of cost of material, Labour and
machinery excluding formwork to cater for extra lift
Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

#VALUE!

12.00

#VALUE!

2.00

#VALUE!
#VALUE!
#VALUE!

Rate perm (a+b+c+d+e+f)

#VALUE!
say

13.5 E

(r)

7303.00

#VALUE!

Height above 10m


Same as Item 12.8 (C) with the following changes: (i) Add 4
per cent of cost of material, labour and machinery excluding
form work to cater for extra lift. (ii) The provision of form work
shall be 15 per cent instead of 4 per cent of cost of
material, labour and machinery.

Case Using concrete Mixer


I
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (C) Case I
d) formwork

e)

Add 15 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and
machinery excluding formwork to cater for extra lift
Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

4853.00

15.00

727.95

4.00

194.12
1155.01
693.01

Rate perm (a+b+c+d+e+f)

7623.09
say

13.5 E
(r)

Case With Batching Plant, Transit Mixer and Concrete Pump


II
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (C) Case II
d) formwork

e)

Add 15 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and
machinery excluding formwork to cater for extra lift
Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

#VALUE!

15.00

#VALUE!

4.00

#VALUE!
#VALUE!
#VALUE!

Rate perm (a+b+c+d+e+f)

#VALUE!
say

13.5

7623.00

#VALUE!

RCC Grade M25

(p) Height upto 5m


Same as Item 12.8 (E) upto 5m height, excluding formwork.
For cost of formwork, add 10 per cent of cost of material,
labour and machinery instead of 3.75 per cent .
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (E) Case I
d) formwork

e)

Add 10 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

5186.00

10.00

518.60
1140.92
684.55

Rate perm (a+b+c+d+e+f)

7530.07
say

Page 7 of 394

7530.00

Remarks/ Input
ref.

Sr No
13.5 F
(p)

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Case With Batching Plant, Transit Mixer and Concrete Pump


II
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (E) Case II
d) formwork

e)

Add 10 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

#VALUE!

10.00

#VALUE!
#VALUE!
#VALUE!

Rate perm (a+b+c+d+e+f)

#VALUE!
say

13.5 F

(q) Height 5m to 10m


For height, upto 10m, add 1.8 per cent of cost as above
excluding formwork. For cost of formwork add 11.8 per cent
of cost of material, labour and machinery
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (E) Case I
d) formwork

e)

Add 11.8 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Add 1.8 per cent of cost of material, Labour and
machinery excluding formwork to cater for extra lift
Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

5186.00

11.80

611.95

1.80

93.35
1178.26
706.96

Rate perm (a+b+c+d+e+f)

7776.51
say

13.5 F
(q)

Case With Batching Plant, Transit Mixer and Concrete Pump


II
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (E) Case II
d) formwork

e)

Add 11.8 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Add 1.8 per cent of cost of material, Labour and
machinery excluding formwork to cater for extra lift
Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

11.80

#VALUE!

1.80

#VALUE!
#VALUE!
#VALUE!
#VALUE!
say

(r)

#VALUE!

Height above 10m

For height, above 10m, add 4 per cent of cost as above


excluding formwork. For cost of formwork add 15 per cent of
cost of material, labour and machinery
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (E) Case I
d) formwork

e)

Add 15 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and
machinery excluding formwork to cater for extra lift
Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

5186.00

15.00

777.90

4.00

207.44
1234.27
740.56

Rate perm (a+b+c+d+e+f)

8146.17
say

13.5 F
(r)

7777.00

#VALUE!

Rate perm (a+b+c+d+e+f)


13.5 F

#VALUE!

Case With Batching Plant, Transit Mixer and Concrete Pump


II
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (E) Case II
d) formwork

Page 8 of 394

8146.00

#VALUE!

Remarks/ Input
ref.

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

e)

Add 15 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and
machinery excluding formwork to cater for extra lift
Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

Quantity

Rate Rs

Cost Rs

15.00

#VALUE!

4.00

#VALUE!
#VALUE!
#VALUE!

Rate perm (a+b+c+d+e+f)

#VALUE!
say

13.5

#VALUE!

RCC Grade M30

(p) Height upto 5m


Same as Item 12.8 (G) upto 5m height, excluding formwork.
For cost of formwork, add 10 per cent of cost of material,
labour and machinery instead of 3.5 per cent .
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (G) Case I
d) formwork

e)

Add 10 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

5206.00

10.00

520.60
1145.32
687.19

Rate perm (a+b+c+d+e+f)

7559.11
say

13.5 G
(p)

Case With Batching Plant, Transit Mixer and Concrete Pump


II
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (G) Case II
d) formwork

e)

Add 10 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

#VALUE!

10.00

#VALUE!
#VALUE!
#VALUE!

Rate perm (a+b+c+d+e+f)

#VALUE!
say

13.5 G

#VALUE!

(q) Height 5m to 10m


For height, upto 10m, add 1.6 per cent of cost as above
excluding formwork. For cost of formwork add 11.5 per cent
of cost of material, labour and machinery
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (G) Case I
d) formwork

e)

Add 11.5 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Add 1.6 per cent of cost of material, Labour and
machinery excluding formwork to cater for extra lift
Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

5206.00

11.50

598.69

1.60

83.30
1177.60
706.56

Rate perm (a+b+c+d+e+f)

7772.14
say

13.5 G
(q)

7559.00

Case With Batching Plant, Transit Mixer and Concrete Pump


II
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (G) Case II
d) formwork

e)

Add 11.5 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Add 1.6 per cent of cost of material, Labour and
machinery excluding formwork to cater for extra lift
Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

Page 9 of 394

7772.00

#VALUE!

11.50

#VALUE!

1.60

#VALUE!
#VALUE!
#VALUE!

Remarks/ Input
ref.

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Rate perm (a+b+c+d+e+f)

#VALUE!
say

13.5 G

(r)

Height above 10m

For height, above 10m, add 3.5 per cent of cost as above
excluding formwork. For cost of formwork add 14 per cent of
cost of material, labour and machinery
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (G) Case I
d) formwork

e)

Add 14 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Add 3.5 per cent of cost of material, Labour and
machinery excluding formwork to cater for extra lift
Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

5206.00

14.00

728.84

3.50

182.21
1223.41
734.05

Rate perm (a+b+c+d+e+f)

8074.51
say

13.5 G
(r)

Case With Batching Plant, Transit Mixer and Concrete Pump


II
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (G) Case II
d) formwork

e)

Add 14 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Add 3.5 per cent of cost of material, Labour and
machinery excluding formwork to cater for extra lift
Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

14.00

#VALUE!

3.50

#VALUE!
#VALUE!
#VALUE!
#VALUE!
say

8075.00

#VALUE!

Rate perm (a+b+c+d+e+f)


13.5

#VALUE!

#VALUE!

RCC Grade M35

(p) Height upto 5m


Same as Item 12.8 (H) upto 5m height, excluding formwork.
For cost of formwork, add 10 per cent of cost of material,
labour and machinery instead of 3 per cent .
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (H) Case I
d) formwork

e)

Add 10 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

5297.00

10.00

529.70
1165.34
699.20

Rate perm (a+b+c+d+e+f)

7691.24
say

13.5 H
(p)

Case With Batching Plant, Transit Mixer and Concrete Pump


II
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (H) Case II
d) formwork

e)

Add 10 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

#VALUE!

10.00

#VALUE!
#VALUE!
#VALUE!

Rate perm (a+b+c+d+e+f)

#VALUE!
say

13.5 H

7691.00

(q) Height 5m to 10m


For height, upto 10m, add 1.4 per cent of cost as above
excluding formwork. For cost of formwork add 11 per cent of
cost of material, labour and machinery .
Page 10 of 394

#VALUE!

Remarks/ Input
ref.

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Case Using concrete Mixer


I
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (H) Case I
d) formwork

e)

Add 11 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Add 1.4 per cent of cost of material, Labour and
machinery excluding formwork to cater for extra lift
Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

5297.00

11.00

582.67

1.40

74.16
1190.77
714.46

Rate perm (a+b+c+d+e+f)

7859.05
say

13.5 H
(q)

Case With Batching Plant, Transit Mixer and Concrete Pump


II
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (H) Case II
d) formwork

e)

Add 11 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Add 1.4 per cent of cost of material, Labour and
machinery excluding formwork to cater for extra lift
Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

#VALUE!

11.00

#VALUE!

1.40

#VALUE!
#VALUE!
#VALUE!

Rate perm (a+b+c+d+e+f)

#VALUE!
say

13.5 H

(r)

e)

Add 13 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Add 3 per cent of cost of material, Labour and
machinery excluding formwork to cater for extra lift
Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

5297.00

13.00

688.61

3.00

158.91
1228.90
737.34

Rate perm (a+b+c+d+e+f)

8110.77
say

Case With Batching Plant, Transit Mixer and Concrete Pump


II
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (H) Case II
d) formwork

e)

Add 13 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Add 3 per cent of cost of material, Labour and
machinery excluding formwork to cater for extra lift
Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

8111.00

#VALUE!

13.00

#VALUE!

3.00

#VALUE!
#VALUE!
#VALUE!

Rate perm (a+b+c+d+e+f)

#VALUE!
say

Note

#VALUE!

Height above 10m

For height, above 10m, add 3 per cent of cost as above


excluding formwork. For cost of formwork add 13 per cent of
cost of material, labour and machinery
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (H) Case I
d) formwork

13.5 H
(r)

7859.00

The basic components of this analysis are the same as


those of items 13.8 (A to H). The only changes are as under:
a)
Ramps/Stairs: Extra expenditure on structures which
are more than 5 m high @ 2 per cent of cost for height upto
10 m and 4 per cent for heights above 10 m will be involved
for approaching the work spot by providing higher ramp/stair
case for use by the working parties.

Page 11 of 394

#VALUE!

Remarks/ Input
ref.

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/ Input
ref.

b) The above mentioned percentages have been suitably


modified for different categories as cost for various
categories varies, whereas effort for access for same height
will be similar. As the cost of richer concrete is comparatively
more, the percentage to be added has been reduced to
maintain the same cost for extra efforts.
13.6

Section
1600 &
2200

Supplying, fitting and placing HYSD bar reinforcement in


sub-structure complete as per drawing and Technical
Specifications
Output: MT
Taking output = 1 MT
a) Material
HYSD bars including 5 per cent overlaps and wastage
Binding wire
b)
Labour for cutting, bending, shifting to site, tying
and placing in position
Mate

tonne

1.05

52100.00

54705.00

M-082

kg

6.00

87.00

522.00

M-072

day

0.34

673.00

228.82

L-12

Blacksmith

day

2.00

500.00

1000.00

L-02

Mazdoor

day

6.50

377.00

2450.50

L-13

c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

11781.26
7068.76

Rate for per MT (a+b+c+d)


13.7

1600 &
2200

77756.34
say

77756.00

Supplying, fitting and placing Mild steel reinforcement


complete in sub-structure as per drawing and Technical
Specification
Unit = MT
Taking output = 1 MT
a) Material
MS bars including 5 per cent overlaps and wastage
Binding wire
b) Labour for straightening, cutting, bending, shifting
to site, tying and placing in position
Mate

tonne

1.05

37100.00

38955.00

M-126

kg

6.00

87.00

522.00

M-072

day

0.28

673.00

188.44

L-12

Blacksmith

day

1.50

500.00

750.00

L-02

Mazdoor

day

5.50

377.00

2073.50

L-13

c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

8497.79
5098.67

Rate for per MT (a+b+c+d)


13.8

2706 &
2200

56085.40
say

56085.00

55.00

1732.50

Providing weep holes in Brick masonry/Plain/


Reinforced concrete abutment, wing wall/ return wall
with 100 mm dia AC pipe, extending through the full
width of the structure with slope of 1V :20H towards
drawing foce. Complete as per drawing and Technical
Specifications
Unit = Nos.
Taking output = 30 Nos.
a) Material
AC pipe 100 mm dia. (including wastage @ 5 per cent )

metre

31.50

Average length of weep hole is taken as one metre for the


purpose of estimating.
MS clamp

each.

30.00

input

#VALUE!

each.

10.00

5.50

55.00

M-056/10

cum

0.05

5916.00

295.80

Item 12.6 (A)

Mate

day

0.03

673.00

20.19

L-12

Mason

day

0.50

500.00

250.00

L-11

Mazdoor

day

0.25

377.00

94.25

L-13

collar for AC pipe (average) taking 10% of above pipe


rate
Cement mortar 1:3 (Rate as in Item 12.6)
b)

M-056

M-123

Labour

Page 12 of 394

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

c)

Overhead charges @ 0.2 on (a+b)

#VALUE!

d)

Contractor's profit @ 0.1 on (a+b+c)

#VALUE!

Cost for 30 m = a+b+c+d

#VALUE!

Rate per m (a+b+c+d)/30

#VALUE!
say

Note

Remarks/ Input
ref.

#VALUE!

1. In case of stone masonry, the size of the weep hole shall


be 150 mm x 80 mm or circular with 150 mm diameter.
2. For structure in stone masonry, the weep holes shall be
deemed to be included in the item of stone masonry work
and shall not be paid separately.

13.9

710.1.4.
of
IRC:78
& 2200

Back filling behind abutment, wing wall and return wall


complete as per drawing and Technical Specification

Unit = cum
Taking output = 10 cum
A

Granular material
a)

b)

Labour
Mate

day

0.28

673.00

188.44

L-12

Mazdoor

day

7.00

377.00

2639.00

L-13

cum

12.00

190.00

2280.00

M-009

Plate compactor/power rammer

hour

2.50

input

#VALUE!

P&M-086

Water Tanker

hour

0.05

233.00

11.65

P&M-060

Material
Granular material

c)

Machinery

d)

Overhead charges @ 0.2 on (a+b+c)

#VALUE!

e)

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!

Cost for 10 cum of granular backfill = a+b+c+d+e

#VALUE!

Rate per cum = (a+b+c+d+e)/10

#VALUE!
say

13.9

Sandy material
a)

b)

Labour
Mate

day

0.28

673.00

188.44

L-12

Mazdoor for filling, watering, ramming etc.

day

7.00

377.00

2639.00

L-13

cum

12.00

616.00

7392.00

M-006

Plate compactor/power rammer

hour

2.50

input

#VALUE!

P&M-086

Water Tanker

hour

0.06

233.00

13.98

P&M-060

Material
Sand

c)

Machinery

d)

Overhead charges @ 0.2 on (a+b+c)

#VALUE!

e)

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!

Cost for 10 cum of sandy backfill = a+b+c+d+e

#VALUE!

Rate per cum = (a+b+c+d+e)/10

#VALUE!
say

13.10

710.1.4.
of
IRC:78
and
2200

#VALUE!

#VALUE!

Providing and laying of Filter media with granular


materials/stone crushed aggregates satisfying the
requirements laid down in clause 2504.2.2. of MoRTH
specifications to a thickness of not less than 600 mm
with smaller size towards the soil and bigger size
towards the wall and provided over the entire surface
behind abutment, wing wall and return wall to the full
height compacted to a firm condition complete as per
drawing and Technical Specification.
Unit = cum
Taking output = 10 cum.
a) Labour
Mate

day

0.32

673.00

215.36

L-12

Mazdoor for filling, watering, ramming etc.

day

7.00

377.00

2639.00

L-13

Page 13 of 394

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Mazdoor (Skilled)

Quantity

Rate Rs

Cost Rs

day

1.00

408.00

408.00

L-15

Filter media of stone aggregate conforming to clause


2504.2.2. of MoRTH specifications.
Machinery

cum

12.00

725.00

8700.00

M-012

Water Tanker of 6 KL capacity

hour

0.06

233.00

b)

Material

c)
d)

Overhead charges @ 0.2 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

P&M-060

1437.16
15808.77

Rate per cum = (a+b+c+d+e)/10

1580.88
say

2000,
1000 &
2200

13.98
2395.27

cost for 10 cum of Fiter Media = a+b+c+d+e

13.11

Remarks/ Input
ref.

1581.00

Supplying, fitting and fixing in position true to line and


level cast steel rocker bearing conforming to IRC: 83(Pt.1) section IX and clause 2003 of MoRTH specifications
complete including all accessories as per drawing and
Technical Specifications.
Unit: one tonne capacity
Considering a 250 tonne capacity bearing for this analysis
a)

b)

Labour
Mate

day

0.06

673.00

40.38

L-12

Mazdoor (Skilled)

day

0.50

408.00

204.00

L-15

Mazdoor

day

1.00

377.00

377.00

L-13

each.

1.00

input

#VALUE!

M-065

Material
Cast steel rocker bearing assembly of 250 tonne
design load capacity duly painted complete with all its
components as per drawing and specifications

#VALUE!

c)

Add 1 per cent of cost of bearing assembly for


foundation anchorage bolts, lifting arrangements,
grease and other consumables.
Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

#VALUE!

#VALUE!

cost for 250 tonnes capacity bearing = a+b+c+d

#VALUE!

Rate per tonne capacity = (a+b+c+d)/250

#VALUE!
say

13.12

2000 ,
1000 &
2200

#VALUE!

Supplying, fitting and fixing in position true to line and


level forged steel roller bearing conforming to IRC:
83(Pt.-1) section IX and clause 2003 of MoRTH
specifications complete including all accessories as per
drawing and Technical Specifications.
Unit: one tonne capacity
Considering a 250 tonne capacity bearing for this analysis
a)

b)

Labour
Mate

day

0.06

673.00

40.38

L-12

Mazdoor

day

1.00

377.00

377.00

L-13

Mazdoor (Skilled)

day

0.50

408.00

204.00

L-15

each.

1.00

input

#VALUE!

M-067

Material
Forged steel roller bearing of 250 tonne design load
capacity duly painted complete with all its components
as per drawing and specifications
Add 1 per cent of cost of bearing assembly for
foundation anchorage bolts, lifting arrangements,
grease and other consumables.

#VALUE!

c)

Overhead charges @ 0.2 on (a+b)

#VALUE!

d)

Contractor's profit @ 0.1 on (a+b+c)

#VALUE!

cost for 250 tonnes capacity bearing = a+b+c+d

#VALUE!

Rate per tonne capacity = (a+b+c+d)/250

#VALUE!
say

Page 14 of 394

#VALUE!

Sr No
13.13

Ref. to
MoRTH
Spec.
2000 &
2200

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/ Input
ref.

Supplying, fitting and fixing in position true to line and


level sliding plate bearing with PTFE surface sliding on
stainless steel complete including all accessories as per
drawing and Technical Specifications and BS: 5400,
section 9.1 & 9.2 (for PTFE)
and clause 2004 of
MoRTH Specifications.
Unit: one tonne capacity
Considering a 80 tonne capacity bearing for this analysis
a)

b)

Labour
Mate

day

0.06

673.00

40.38

L-12

Mazdoor

day

1.00

377.00

377.00

L-13

Mazdoor (Skilled)

day

0.50

408.00

204.00

L-15

each.

1.00

input

#VALUE!

M-069

Material
PTFE sliding plate bearing assembly of 80 tonnes
design load capacity duly painted complete with all its
components as per drawing and Technical
Specifications

#VALUE!

c)

Add 1 per cent for foundation anchorage bolts and


consumables.
Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

#VALUE!

#VALUE!

cost for 80 tonnes capacity bearing = a+b+c+d

#VALUE!

Rate per tonne capacity = (a+b+c+d)/80

#VALUE!
say

13.14

2000 &
2200

#VALUE!

Supplying, fitting and fixing in position true to line and


level elastomeric bearing conforming to IRC: 83 (Part-II)
section IX and clause 2005 of MoRTH specifications
complete including all accessories as per drawing and
Technical Specifications.
Unit: one cubic centimetre
Considering an elastomeric bearing of size 500 x 400 x 96
mm for this analysis.
Overall volume - 19200 cu.cm
Volume of 6 nos. 488 x 388 x 4 mm size reinforcing steel
plates = 4545 cu.cm.
Hence volume of elastometer = 14655 cu.cm.
a)

b)

Labour
Mate

day

0.06

673.00

40.38

L-12

Mazdoor

day

1.00

377.00

377.00

L-13

Mazdoor (Skilled)

day

0.50

408.00

204.00

L-15

each.

1.00

input

#VALUE!

M-066

Material
Elastomeric bearing assembly consisting of 7 layers of
elastomer bonded to 6 nos. internal reinforcing steel
laminates by the process of vulcanisation, complete
with all components as per drawing and Technical
Specifications.

#VALUE!

c)

Add 1 per cent of cost of bearing assembly for


foundation anchorage bolts and consumables.
Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

#VALUE!

cost for 19200cc of elastomeric bearing = a+b+c+d

#VALUE!

Rate per cc of elastomeric bearing = (a+b+c+d)/19200

#VALUE!

#VALUE!

say
13.15

2000 &
2200

Supplying, fitting and fixing in position true to line and


level sliding plate bearing with stainless steel plate
sliding on stainless steel plate with mild steel matrix
complete including all accessories as per drawing and
Technical Specifications.
Unit: one tonne capacity
Considering the sliding bearing of 80 tonnes design capacity
for this analysis.
a) Labour
Page 15 of 394

#VALUE!

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/ Input
ref.

Mate

day

0.04

673.00

26.92

L-12

Mazdoor

day

0.75

377.00

282.75

L-13

Mazdoor (Skilled)

day

0.35

408.00

142.80

L-15

each.

1.00

input

#VALUE!

M-070

b)

Material

c)

Supply of sliding plate bearing of 80 tonne design


capacity complete as per drawings and Technical
Specifications.
Add 1 per cent of cost of bearing assembly for
foundation anchorage bolts and consumables.
Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

#VALUE!

cost for 80 tonnes of capacity bearing = a+b+c+d

#VALUE!

#VALUE!
#VALUE!

#VALUE!
say
13.16

2000 &
2200

#VALUE!

Supplying, fitting and fixing in position true to line and


level POT-PTFE bearing consisting of a metal piston
supported by a disc or unreinforced elastomer confined
within a metal cylinder, sealing rings, dust seals, PTFE
surface sliding against stainless steel mating surface,
complete assembly to be of cast steel/fabricated
structural steel, metal and elastomer elements to be as
per IRC: 83 part-I & II respectively and other parts
conforming to BS: 5400, section 9.1 & 9.2 and clause
2006 of MoRTH Specifications complete as per drawing
and approved Technical Specifications.

Unit: one tonne capacity

387.20

Considering a Pot bearing assembly of 250 tonne capacity


for this analysis.
a) Labour

b)

Mate

day

0.08

673.00

53.84

L-12

Mazdoor

day

1.50

377.00

565.50

L-13

Mazdoor (Skilled)

day

0.50

408.00

204.00

L-15

each.

1.00

input

#VALUE!

M-068

Material
Pot type bearing assembly consisting of a metal piston
supported by a disc, PTFE pads providing sliding
surfaces against stainless steel mating together with
cast steel assemblies/fabricated structural steel
assemblies duly painted with all components as per
clause 2006 and complete as per drawings and
Technical Specifications.

#VALUE!

c)

Add 1 per cent of cost of bearing assembly for


foundation anchorage bolts and consumables.
Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

#VALUE!

#VALUE!

cost for 250 tonnes capacity bearing = a+b+c+d

#VALUE!

Rate per tonne capacity = (a+b+c+d)/250

#VALUE!
say

Page 16 of 394

#VALUE!

CHAPTER-14
SUPER-STRUCTURE
Sr No
14.1

Ref. to
MoRTH
Spec.

Description

1500
&1600
1700

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Furnishing and Placing Reinforced/ Prestressed cement


concrete in super-structure as per drawing and
Technical Specification
RCC Grade M20

Case I Using Concrete Mixer


Unit = 1 cum
Taking output = 15 cum
a)

b)

c)

Material
Cement

tonne

5.12

5940.00

30412.80

M-081

Coarse sand

cum

6.75

2400.00

16200.00

M-005

20 mm Aggregate

cum

8.10

942.00

7630.20

M-053

10 mm Aggregate

cum

5.40

1063.00

5740.20

M-051

Mate

day

0.86

673.00

578.78

L-12

Mason

day

1.50

500.00

750.00

L-11

Mazdoor

day

20.00

377.00

7540.00

L-13

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

218.00

1308.00

P&M-009

Generator 33 KVA

hour

6.00

349.00

2094.00

P&M-079

Labour

Machinery

Basic Cost of Labour, Material & Machinery (a+b+c)


for 15 cum
For formwork and staging add the following:
14.1A
Case I

(i)

For solid slab super-structure, 20-30 per cent of (a+b+c)

(p)

Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
for
15 cum
d) Formwork and staging 20 per cent of (a+b+c)
e)

Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

72254.00

72254.00
20.00

14450.80
17340.96
10404.58

Cost for 15 cum = a+b+c+d+e+f

114450.34

Rate per cum = (a+b+c+d+e+f)/15

7630.02
say

14.1A
Case I (i)

(q)

Basic Cost of Labour, Material & Machinery (a+b+c)


for
15 cum
d) Formwork and staging 25 per cent of (a+b+c)
e)

Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

72254.00
25.00

18063.50
18063.50
10838.10

Cost for 15 cum = a+b+c+d+e+f

119219.10

Rate per cum = (a+b+c+d+e+f)/15

7947.94
say

14.1A
Case I (i)

(r)

7948.00

Height above 10m

Basic Cost of Labour, Material & Machinery (a+b+c)


for
15 cum
d) Formwork and staging 30 per cent of (a+b+c)
e)

Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

72254.00
30.00

21676.20
18786.04
11271.62

Cost for 15 cum = a+b+c+d+e+f

123987.86

Rate per cum = (a+b+c+d+e+f)/15

8265.86
say

14.1A
Case I

7630.00

Height 5m to 10m

(ii) For T-beam & slab, 25-35 per cent of (a+b+c)


(p)

Height upto 5m
Page 1 of 394

8266.00

Basic Cost of Labour, Material & Machinery (a+b+c)


for
15 cum
d) Formwork and staging 25 per cent of (a+b+c)
e)

Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

72254.00
25.00

18063.50
18063.50
10838.10

Cost for 15 cum = a+b+c+d+e+f

119219.10

Rate per cum = (a+b+c+d+e+f)/15

7947.94
say

14.1A
Case I
(ii)

(q)

Basic Cost of Labour, Material & Machinery (a+b+c)


for
15 cum
d) Formwork and staging 30 per cent of (a+b+c)
e)

Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

72254.00
30.00

21676.20
18786.04
11271.62

Cost for 15 cum = a+b+c+d+e+f

123987.86

Rate per cum = (a+b+c+d+e+f)/15

8265.86
say

14.1A
Case I
(ii)

(r)

8266.00

Height above 10m

Basic Cost of Labour, Material & Machinery (a+b+c)


for
15 cum
d) Formwork and staging 35 per cent of (a+b+c)
e)

Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

72254.00
35.00

25288.90
19508.58
11705.15

Cost for 15 cum = a+b+c+d+e+f

128756.63

Rate per cum = (a+b+c+d+e+f)/15


14.1A

7948.00

Height 5m to 10m

8583.78
say

8584.00

Case II Using Batching Plant, Transit Mixer and Concrete Pump


Unit = cum
Taking output = 120 cum
a)

b)

c)

Material
Cement

tonne

40.92

5940.00

243064.80

M-081

Coarse sand

cum

54.00

2400.00

129600.00

M-004

20 mm Aggregate

cum

64.80

942.00

61041.60

M-053

10 mm Aggregate

cum

43.20

1063.00

45921.60

M-051

Mate

day

0.84

673.00

565.32

Mason

day

3.00

500.00

1500.00

L-11

Mazdoor

day

18.00

377.00

6786.00

L-13

Batching Plant @ 20 cum/hour

hour

6.00

2094.00

12564.00

P&M-002

Generator 100 KVA

hour

6.00

654.00

3924.00

P&M-080

Loader

hour

6.00

756.00

4536.00

P&M-017

hour

15.00

873.00

13095.00

P&M-049

tonne.km

300L

input

#VALUE!

Lead =1
km & P&M050

6.00

240.00

1440.00

P&M-007

Labour
L-12

Machinery

Transit Mixer ( capacity 4.0 cu.m )


Transit Mixer 4 cum capacity lead upto1 Km
Lead beyond 1 Km, L - lead in Kilometer

Concrete Pump

hour

Basic Cost of Labour, Material & Machinery (a+b+c)


for 120 cum
For formwork and staging add the following:
14.1A
Case II

(i)

For solid slab super-structure, 20-30 per cent of (a+b+c)

(p)

Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
for
120 cum
d) Formwork and staging 20 per cent of (a+b+c)
e)

Overhead charges @ 0.2 on (a+b+c+d)


Page 2 of 394

#VALUE!

#VALUE!
20.00

#VALUE!
#VALUE!

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

#VALUE!

Cost for 120 cum = a+b+c+d+e+f

#VALUE!

Rate per cum = (a+b+c+d+e+f)/120

#VALUE!
say

14.1A
Case II
(i)

(q)

Height 5m to 10m

Basic Cost of Labour, Material & Machinery (a+b+c)


for
120 cum
d) Formwork and staging 25 per cent of (a+b+c)

#VALUE!
25.00

#VALUE!

e)

Overhead charges @ 0.2 on (a+b+c+d)

#VALUE!

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

#VALUE!

Cost for 120 cum = a+b+c+d+e+f

#VALUE!

Rate per cum = (a+b+c+d+e+f)/120

#VALUE!
say

14.1A
Case II
(i)

(r)

#VALUE!
30.00

#VALUE!

e)

Overhead charges @ 0.2 on (a+b+c+d)

#VALUE!

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

#VALUE!

Cost for 120 cum = a+b+c+d+e+f

#VALUE!

Rate per cum = (a+b+c+d+e+f)/120

#VALUE!
say

Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
for
120 cum
d) Formwork and staging 25 per cent of (a+b+c)

#VALUE!
25.00

#VALUE!

e)

Overhead charges @ 0.2 on (a+b+c+d)

#VALUE!

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

#VALUE!

Cost for 120 cum = a+b+c+d+e+f

#VALUE!

Rate per cum = (a+b+c+d+e+f)/120

#VALUE!
say

(q)

#VALUE!
30.00

#VALUE!

e)

Overhead charges @ 0.2 on (a+b+c+d)

#VALUE!

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

#VALUE!

Cost for 120 cum = a+b+c+d+e+f

#VALUE!

Rate per cum = (a+b+c+d+e+f)/120

#VALUE!
say

(r)

#VALUE!
35.00

#VALUE!

e)

Overhead charges @ 0.2 on (a+b+c+d)

#VALUE!

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

#VALUE!

Cost for 120 cum = a+b+c+d+e+f

#VALUE!

Rate per cum = (a+b+c+d+e+f)/120

#VALUE!
say

#VALUE!

Height above 10m

Basic Cost of Labour, Material & Machinery (a+b+c)


for
120 cum
d) Formwork and staging 35 per cent of (a+b+c)

14.1

#VALUE!

Height 5m to 10m

Basic Cost of Labour, Material & Machinery (a+b+c)


for
120 cum
d) Formwork and staging 30 per cent of (a+b+c)

14.1A
Case II
(ii)

#VALUE!

(ii) For T-beam & slab, 25-35 per cent of (a+b+c)


(p)

14.1A
Case II
(ii)

#VALUE!

Height above 10m

Basic Cost of Labour, Material & Machinery (a+b+c)


for
120 cum
d) Formwork and staging 30 per cent of (a+b+c)

14.1A
Case II

#VALUE!

RCC Grade M25

Case I Using Concrete Mixer


Unit = 1 cum
Taking output = 15 cum
Page 3 of 394

#VALUE!

a)

b)

c)

Material
Cement

tonne

5.99

5940.00

35580.60

M-081

Coarse sand

cum

6.75

2400.00

16200.00

M-005

20 mm Aggregate

cum

8.10

942.00

7630.20

M-053

10 mm Aggregate

cum

5.40

1063.00

5740.20

M-051

Mate

day

0.86

673.00

578.78

L-12

Mason

day

1.50

500.00

750.00

L-11

Mazdoor

day

20.00

377.00

7540.00

L-13

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

218.00

1308.00

P&M-009

Generator 33 KVA

hour

6.00

349.00

2094.00

P&M-079

Labour

Machinery

Basic Cost of Labour, Material & Machinery (a+b+c)


for 15 cum
For formwork and staging add the following:
14.1B
Case I

(i)

For solid slab super-structure, 20-30 per cent of (a+b+c)

(p)

Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
for
15 cum
d) Formwork and staging 20 per cent of (a+b+c)
e)

Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

77422.00

77422.00
20.00

15484.40
18581.28
11148.77

Cost for 15 cum = a+b+c+d+e+f

122636.45

Rate per cum = (a+b+c+d+e+f)/15

8175.76
say

14.1B
Case I (i)

(q)

Basic Cost of Labour, Material & Machinery (a+b+c)


for
15 cum
d) Formwork and staging 25 per cent of (a+b+c)
e)

Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

77422.00
25.00

19355.50
19355.50
11613.30

Cost for 15 cum = a+b+c+d+e+f

127746.30

Rate per cum = (a+b+c+d+e+f)/15

8516.42
say

14.1B
Case I (i)

(r)

e)

Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

77422.00
30.00

23226.60
20129.72
12077.83

Cost for 15 cum = a+b+c+d+e+f

132856.15

Rate per cum = (a+b+c+d+e+f)/15

8857.08
say

(ii)

For T-beam & slab, 25-35 per cent of (a+b+c)

(p)

Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
for
15 cum
d) Formwork and staging 25 per cent of (a+b+c)
e)

Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

25.00

19355.50
19355.50
11613.30
127746.30

Rate per cum = (a+b+c+d+e+f)/15

8516.42
say

(q)

8857.00

77422.00

Cost for 15 cum = a+b+c+d+e+f

14.1B
Case I
(ii)

8516.00

Height above 10m

Basic Cost of Labour, Material & Machinery (a+b+c)


for
15 cum
d) Formwork and staging 30 per cent of (a+b+c)

14.1B
Case I

8176.00

Height 5m to 10m

Height 5m to 10m

Page 4 of 394

8516.00

Basic Cost of Labour, Material & Machinery (a+b+c)


for
15 cum
d) Formwork and staging 30 per cent of (a+b+c)
e)

Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

77422.00
30.00

23226.60
20129.72
12077.83

Cost for 15 cum = a+b+c+d+e+f

132856.15

Rate per cum = (a+b+c+d+e+f)/15

8857.08
say

14.1B
Case I
(ii)

(r)

Basic Cost of Labour, Material & Machinery (a+b+c)


for
15 cum
d) Formwork and staging 35 per cent of (a+b+c)
e)

Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

77422.00
35.00

27097.70
20903.94
12542.36

Cost for 15 cum = a+b+c+d+e+f

137966.00

Rate per cum = (a+b+c+d+e+f)/15


14.1B

8857.00

Height above 10m

9197.73
say

9198.00

Case II Using Batching Plant, Transit Mixer and Concrete Pump


Unit = cum
Taking output = 120 cum
a)

b)

c)

Material
Cement

tonne

47.95

5940.00

284823.00

M-081

Coarse sand

cum

54.20

2400.00

130080.00

M-004

20 mm Aggregate

cum

64.80

942.00

61041.60

M-053

10 mm Aggregate

cum

43.20

1063.00

45921.60

M-051

Mate

day

0.84

673.00

565.32

Mason

day

3.00

500.00

1500.00

L-11

Mazdoor

day

18.00

377.00

6786.00

L-13

Batching Plant @ 20 cum/hour

hour

6.00

2094.00

12564.00

P&M-002

Generator 100 KVA

hour

6.00

654.00

3924.00

P&M-080

Loader

hour

6.00

756.00

4536.00

P&M-017

hour

15.00

873.00

13095.00

P&M-049

tonne.km

300L

input

#VALUE!

Lead =1
km & P&M050

6.00

240.00

1440.00

P&M-007

Labour
L-12

Machinery

Transit Mixer ( capacity 4.0 cu.m )


Transit Mixer 4 cum capacity lead upto1 Km
Lead beyond 1 Km, L - lead in Kilometer

Concrete Pump

hour

Basic Cost of Labour, Material & Machinery (a+b+c)


for 120 cum
For formwork and staging add the following:
14.1B
Case II

(i)

For solid slab super-structure, 20-30 per cent of (a+b+c)

(p)

Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
for
120 cum
d) Formwork and staging 20 per cent of (a+b+c)

#VALUE!

#VALUE!
20.00

#VALUE!

e)

Overhead charges @ 0.2 on (a+b+c+d)

#VALUE!

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

#VALUE!

Cost for 120 cum = a+b+c+d+e+f

#VALUE!

Rate per cum = (a+b+c+d+e+f)/120

#VALUE!
say

14.1B
Case II
(i)

(q)

#VALUE!

Height 5m to 10m

Basic Cost of Labour, Material & Machinery (a+b+c)


for
120 cum
d) Formwork and staging 25 per cent of (a+b+c)
e)

Overhead charges @ 0.2 on (a+b+c+d)


Page 5 of 394

#VALUE!
25.00

#VALUE!
#VALUE!

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

#VALUE!

Cost for 120 cum = a+b+c+d+e+f

#VALUE!

Rate per cum = (a+b+c+d+e+f)/120

#VALUE!
say

14.1B
Case II
(i)

(r)

Height above 10m

Basic Cost of Labour, Material & Machinery (a+b+c)


for
120 cum
d) Formwork and staging 30 per cent of (a+b+c)

#VALUE!
30.00

#VALUE!

e)

Overhead charges @ 0.2 on (a+b+c+d)

#VALUE!

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

#VALUE!

Cost for 120 cum = a+b+c+d+e+f

#VALUE!

Rate per cum = (a+b+c+d+e+f)/120

#VALUE!
say

14.1B
Case II

(ii)

For T-beam & slab, 25-35 per cent of (a+b+c)

(p)

Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
for
120 cum
d) Formwork and staging 25 per cent of (a+b+c)

25.00

#VALUE!

e)

Overhead charges @ 0.2 on (a+b+c+d)

#VALUE!

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

#VALUE!
#VALUE!

Rate per cum = (a+b+c+d+e+f)/120

#VALUE!
say

(q)

#VALUE!
30.00

#VALUE!

e)

Overhead charges @ 0.2 on (a+b+c+d)

#VALUE!

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

#VALUE!

Cost for 120 cum = a+b+c+d+e+f

#VALUE!

Rate per cum = (a+b+c+d+e+f)/120

#VALUE!
say

(r)

#VALUE!
35.00

#VALUE!

e)

Overhead charges @ 0.2 on (a+b+c+d)

#VALUE!

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

#VALUE!

Cost for 120 cum = a+b+c+d+e+f

#VALUE!

Rate per cum = (a+b+c+d+e+f)/120


C

#VALUE!

Height above 10m

Basic Cost of Labour, Material & Machinery (a+b+c)


for
120 cum
d) Formwork and staging 35 per cent of (a+b+c)

14.1

#VALUE!

Height 5m to 10m

Basic Cost of Labour, Material & Machinery (a+b+c)


for
120 cum
d) Formwork and staging 30 per cent of (a+b+c)

14.1B
Case II
(ii)

#VALUE!

#VALUE!

Cost for 120 cum = a+b+c+d+e+f

14.1B
Case II
(ii)

#VALUE!

#VALUE!
say

#VALUE!

RCC Grade M 30

Case I Using Concrete Mixer


Unit = 1 cum
Taking output = 15 cum
a)

b)

c)

Material
Cement

tonne

6.10

5940.00

36234.00

M-081

Coarse sand

cum

6.75

2400.00

16200.00

M-005

20 mm Aggregate

cum

8.10

942.00

7630.20

M-053

10 mm Aggregate

cum

5.40

1063.00

5740.20

M-051

Mate

day

0.90

673.00

605.70

L-12

Mason

day

1.50

500.00

750.00

L-11

Mazdoor

day

21.00

377.00

7917.00

L-13

Labour

Machinery
Page 6 of 394

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

218.00

1308.00

P&M-009

Generator 33 KVA

hour

6.00

349.00

2094.00

P&M-079

Basic Cost of Labour, Material & Machinery (a+b+c)


for 15 cum
For formwork and staging add the following:
14.1C
Case I

(i)

For solid slab super-structure, 20-30 per cent of (a+b+c)

(p)

Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
for
15 cum
d) Formwork and staging 20 per cent of (a+b+c)
e)

Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

78480.00

78480.00
20.00

15696.00
18835.20
11301.12

Cost for 15 cum = a+b+c+d+e+f

124312.32

Rate per cum = (a+b+c+d+e+f)/15

8287.49
say

14.1C
Case I (i)

(q)

Basic Cost of Labour, Material & Machinery (a+b+c)


for
15 cum
d) Formwork and staging 25 per cent of (a+b+c)
e)

Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

78480.00
25.00

19620.00
19620.00
11772.00

Cost for 15 cum = a+b+c+d+e+f

129492.00

Rate per cum = (a+b+c+d+e+f)/15

8632.80
say

14.1C
Case I (i)

(r)

78480.00
30.00

23544.00

e)

Overhead charges @ 0.2 on (a+b+c+d)

20404.80

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

12242.88

Cost for 15 cum = a+b+c+d+e+f

134671.68

Rate per cum = (a+b+c+d+e+f)/15

8978.11
say

(ii)

For T-beam & slab, 25-35 per cent of (a+b+c)

(p)

Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
for
15 cum
d) Formwork and staging 25 per cent of (a+b+c)

25.00

19620.00

e)

Overhead charges @ 0.2 on (a+b+c+d)

19620.00

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

11772.00
129492.00

Rate per cum = (a+b+c+d+e+f)/15

8632.80
say

(q)

e)

Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

78480.00
30.00

23544.00
20404.80
12242.88

Cost for 15 cum = a+b+c+d+e+f

134671.68

Rate per cum = (a+b+c+d+e+f)/15

8978.11
say

(r)

8633.00

Height 5m to 10m

Basic Cost of Labour, Material & Machinery (a+b+c)


for
15 cum
d) Formwork and staging 30 per cent of (a+b+c)

14.1C
Case I
(ii)

8978.00

78480.00

Cost for 15 cum = a+b+c+d+e+f

14.1C
Case I
(ii)

8633.00

Height above 10m

Basic Cost of Labour, Material & Machinery (a+b+c)


for
15 cum
d) Formwork and staging 30 per cent of (a+b+c)

14.1C
Case I

8287.00

Height 5m to 10m

Height above 10m

Page 7 of 394

8978.00

Basic Cost of Labour, Material & Machinery (a+b+c)


for
15 cum
d) Formwork and staging 35 per cent of (a+b+c)

78480.00
35.00

27468.00

e)

Overhead charges @ 0.2 on (a+b+c+d)

21189.60

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

12713.76

Cost for 15 cum = a+b+c+d+e+f

139851.36

Rate per cum = (a+b+c+d+e+f)/15


14.1C

9323.42
say

9323.00

Case II Using Batching Plant, Transit Mixer and Concrete Pump.


Unit = cum
Taking output = 120 cum
a)

b)

c)

Material
Cement

tonne

48.79

5940.00

289812.60

M-081

Coarse sand

cum

54.60

2400.00

131040.00

M-004

20 mm Aggregate

cum

64.80

942.00

61041.60

M-053

10 mm Aggregate

cum

43.20

1063.00

45921.60

M-051

Mate

day

0.88

673.00

592.24

Mason

day

3.00

500.00

1500.00

L-11

Mazdoor

day

19.00

377.00

7163.00

L-13

Batching Plant @ 20 cum/hour

hour

6.00

2094.00

12564.00

P&M-002

Generator 100 KVA

hour

6.00

654.00

3924.00

P&M-080

Loader

hour

6.00

756.00

4536.00

P&M-017

hour

15.00

873.00

13095.00

P&M-049

tonne.km

300L

input

#VALUE!

Lead =1
km & P&M050

6.00

240.00

1440.00

P&M-007

Labour
L-12

Machinery

Transit Mixer ( capacity 4.0 cu.m )


Transit Mixer 4 cum capacity lead upto1 Km
Lead beyond 1 Km, L - lead in Kilometer

Concrete Pump

hour

Basic Cost of Labour, Material & Machinery (a+b+c)


for 120 cum
For formwork and staging add the following:
14.1C
Case II

(i)

For solid slab super-structure, 20-30 per cent of (a+b+c)

(p)

Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
for
120 cum
d) Formwork and staging 20 per cent of (a+b+c)

#VALUE!

#VALUE!
20.00

#VALUE!

e)

Overhead charges @ 0.2 on (a+b+c+d)

#VALUE!

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

#VALUE!

Cost for 120 cum = a+b+c+d+e+f

#VALUE!

Rate per cum = (a+b+c+d+e+f)/120

#VALUE!
say

14.1C
Case II
(i)

(q)

Height 5m to 10m

Basic Cost of Labour, Material & Machinery (a+b+c)


for
120 cum
d) Formwork and staging 25 per cent of (a+b+c)

#VALUE!
25.00

#VALUE!

e)

Overhead charges @ 0.2 on (a+b+c+d)

#VALUE!

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

#VALUE!

Cost for 120 cum = a+b+c+d+e+f

#VALUE!

Rate per cum = (a+b+c+d+e+f)/120

#VALUE!
say

14.1C
Case II
(i)

(r)

#VALUE!

#VALUE!

Height above 10m

Basic Cost of Labour, Material & Machinery (a+b+c)


for
120 cum
d) Formwork and staging 30 per cent of (a+b+c)
e)

Overhead charges @ 0.2 on (a+b+c+d)


Page 8 of 394

#VALUE!
30.00

#VALUE!
#VALUE!

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

#VALUE!

Cost for 120 cum = a+b+c+d+e+f

#VALUE!

Rate per cum = (a+b+c+d+e+f)/120

#VALUE!
say

14.1C
Case II

(ii)

For T-beam & slab, 25-35 per cent of (a+b+c)

(p)

Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
for
120 cum
d) Formwork and staging 25 per cent of (a+b+c)

#VALUE!
25.00

#VALUE!

e)

Overhead charges @ 0.2 on (a+b+c+d)

#VALUE!

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

#VALUE!

Cost for 120 cum = a+b+c+d+e+f

#VALUE!

Rate per cum = (a+b+c+d+e+f)/120

#VALUE!
say

14.1C
Case II
(ii)

(q)

#VALUE!
30.00

#VALUE!

e)

Overhead charges @ 0.2 on (a+b+c+d)

#VALUE!

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

#VALUE!

Cost for 120 cum = a+b+c+d+e+f

#VALUE!

Rate per cum = (a+b+c+d+e+f)/120

#VALUE!
say

(r)

#VALUE!
35.00

#VALUE!

e)

Overhead charges @ 0.2 on (a+b+c+d)

#VALUE!

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

#VALUE!

Cost for 120 cum = a+b+c+d+e+f

#VALUE!

Rate per cum = (a+b+c+d+e+f)/120


D

#VALUE!

Height above 10m

Basic Cost of Labour, Material & Machinery (a+b+c)


for
120 cum
d) Formwork and staging 35 per cent of (a+b+c)

14.1

#VALUE!

Height 5m to 10m

Basic Cost of Labour, Material & Machinery (a+b+c)


for
120 cum
d) Formwork and staging 30 per cent of (a+b+c)

14.1C
Case II
(ii)

#VALUE!

#VALUE!
say

#VALUE!

RCC/PSC Grade M35

Case I Using Concrete Mixer.


Unit = 1 cum
Taking output = 15 cum
a)

b)

c)

Material
Cement

tonne

6.33

5940.00

37600.20

M-081

Coarse sand

cum

6.75

2400.00

16200.00

M-005

20 mm Aggregate

cum

8.10

942.00

7630.20

M-053

10 mm Aggregate

cum

5.40

1063.00

5740.20

M-051

Mate

day

0.90

673.00

605.70

L-12

Mason

day

1.50

500.00

750.00

L-11

Mazdoor

day

21.00

377.00

7917.00

L-13

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

218.00

1308.00

P&M-009

Generator 33 KVA

hour

6.00

349.00

2094.00

P&M-079

Labour

Machinery

Basic Cost of Labour, Material & Machinery (a+b+c)


for 15 cum
For formwork and staging add the following:
14.1D
Case I

(i)

For solid slab super-structure, 18-28 per cent of (a+b+c)

(p)

Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
for
15 cum
d) Formwork and staging 18 per cent of (a+b+c)

Page 9 of 394

79846.00

79846.00
18.00

14372.28

e)

Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

18843.66
11306.19

Cost for 15 cum = a+b+c+d+e+f

124368.13

Rate per cum = (a+b+c+d+e+f)/15

8291.21
say

14.1D
Case I (i)

(q)

Basic Cost of Labour, Material & Machinery (a+b+c)


for
15 cum
d) Formwork and staging 23 per cent of (a+b+c)
e)

Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

79846.00
23.00

18364.58
19642.12
11785.27

Cost for 15 cum = a+b+c+d+e+f

129637.97

Rate per cum = (a+b+c+d+e+f)/15

8642.53
say

14.1D
Case I (i)

(r)

e)

Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

79846.00
28.00

22356.88
20440.58
12264.35

Cost for 15 cum = a+b+c+d+e+f

134907.80

Rate per cum = (a+b+c+d+e+f)/15

8993.85
say

(ii)

For T-beam & slab, 23-33 per cent of (a+b+c)

(p)

Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
for
15 cum
d) Formwork and staging 23 per cent of (a+b+c)
e)

Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

23.00

18364.58
19642.12
11785.27
129637.97

Rate per cum = (a+b+c+d+e+f)/15

8642.53
say

(q)

e)

Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

79846.00
28.00

22356.88
20440.58
12264.35

Cost for 15 cum = a+b+c+d+e+f

134907.80

Rate per cum = (a+b+c+d+e+f)/15

8993.85
say

(r)

e)

Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

79846.00
33.00

26349.18
21239.04
12743.42

Cost for 15 cum = a+b+c+d+e+f

140177.64

Rate per cum = (a+b+c+d+e+f)/15

9345.18
say

(iii)
(p)

8994.00

Height above 10m

Basic Cost of Labour, Material & Machinery (a+b+c)


for
15 cum
d) Formwork and staging 33 per cent of (a+b+c)

14.1D
Case I

8643.00

Height 5m to 10m

Basic Cost of Labour, Material & Machinery (a+b+c)


for
15 cum
d) Formwork and staging 28 per cent of (a+b+c)

14.1D
Case I
(ii)

8994.00

79846.00

Cost for 15 cum = a+b+c+d+e+f

14.1D
Case I
(ii)

8643.00

Height above 10m

Basic Cost of Labour, Material & Machinery (a+b+c)


for
15 cum
d) Formwork and staging 28 per cent of (a+b+c)

14.1D
Case I

8291.00

Height 5m to 10m

For box girder and balanced cantilever, 38-58 per cent


of cost of concrete.
Height upto 5m

Page 10 of 394

9345.00

Basic Cost of Labour, Material & Machinery (a+b+c)


for
15 cum
d) Formwork and staging 38 per cent of (a+b+c)
e)

Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

79846.00
38.00

30341.48
22037.50
13222.50

Cost for 15 cum = a+b+c+d+e+f

145447.47

Rate per cum = (a+b+c+d+e+f)/15

9696.50
say

14.1D
Case I
(iii)

(q)

Basic Cost of Labour, Material & Machinery (a+b+c)


for
15 cum
d) Formwork and staging 48 per cent of (a+b+c)
e)

Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

79846.00
48.00

38326.08
23634.42
14180.65

Cost for 15 cum = a+b+c+d+e+f

155987.15

Rate per cum = (a+b+c+d+e+f)/15

10399.14
say

14.1D
Case I
(iii)

(r)

9696.00

Height 5m to 10m

10399.00

Height above 10m

Basic Cost of Labour, Material & Machinery (a+b+c)


for
15 cum
d) Formwork and staging 58 per cent of (a+b+c)
e)

Overhead charges @ 0.2 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

79846.00
58.00

46310.68
25231.34
15138.80

Cost for 15 cum = a+b+c+d+e+f

166526.82

Rate per cum = (a+b+c+d+e+f)/15

11101.79
say

11102.00

Case II Using Batching Plant, Transit Mixer and Concrete Pump


Unit = cum
Taking output = 120 cum
a)

b)

c)

Material
Cement

tonne

50.64

5940.00

300801.60

M-081

Coarse sand

cum

54.00

2400.00

129600.00

M-004

20 mm Aggregate

cum

64.80

942.00

61041.60

M-053

10 mm Aggregate

cum

43.20

1063.00

45921.60

M-051

Mate

day

0.88

673.00

592.24

Mason

day

3.00

500.00

1500.00

L-11

Mazdoor

day

19.00

377.00

7163.00

L-13

Batching Plant @ 20 cum/hour

hour

6.00

2094.00

12564.00

P&M-002

Generator 100 KVA

hour

6.00

654.00

3924.00

P&M-080

Loader

hour

6.00

756.00

4536.00

P&M-017

hour

15.00

873.00

13095.00

P&M-049

tonne.km

300L

input

#VALUE!

Lead =1
km & P&M050

6.00

240.00

1440.00

P&M-007

Labour
L-12

Machinery

Transit Mixer ( capacity 4.0 cu.m )


Transit Mixer 4 cum capacity lead upto1 Km
Lead beyond 1 Km, L - lead in Kilometer

Concrete Pump

hour

Basic Cost of Labour, Material & Machinery (a+b+c)


for 120 cum
For formwork and staging add the following:
14.1D
Case II

(i)

For solid slab super-structure, 18-28 per cent of (a+b+c)

(p)

Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
for
120 cum
d) Formwork and staging 18 per cent of (a+b+c)
e)

Overhead charges @ 0.2 on (a+b+c+d)


Page 11 of 394

#VALUE!

#VALUE!
18.00

#VALUE!
#VALUE!

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

#VALUE!

Cost for 120 cum = a+b+c+d+e+f

#VALUE!

Rate per cum = (a+b+c+d+e+f)/120

#VALUE!
say

14.1D
Case II
(i)

(q)

Height 5m to 10m

Basic Cost of Labour, Material & Machinery (a+b+c)


for
120 cum
d) Formwork and staging 23 per cent of (a+b+c)

#VALUE!
23.00

#VALUE!

e)

Overhead charges @ 0.2 on (a+b+c+d)

#VALUE!

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

#VALUE!

Cost for 120 cum = a+b+c+d+e+f

#VALUE!

Rate per cum = (a+b+c+d+e+f)/120

#VALUE!
say

14.1D
Case II
(i)

(r)

#VALUE!
28.00

#VALUE!

e)

Overhead charges @ 0.2 on (a+b+c+d)

#VALUE!

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

#VALUE!

Cost for 120 cum = a+b+c+d+e+f

#VALUE!

Rate per cum = (a+b+c+d+e+f)/120

#VALUE!
say

(ii)

For T-beam & slab, 23-33 per cent of (a+b+c)

(p)

Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
for
120 cum
d) Formwork and staging 23 per cent of (a+b+c)

23.00

#VALUE!

e)

Overhead charges @ 0.2 on (a+b+c+d)

#VALUE!

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

#VALUE!
#VALUE!

Rate per cum = (a+b+c+d+e+f)/120

#VALUE!
say

(q)

#VALUE!
28.00

#VALUE!

e)

Overhead charges @ 0.2 on (a+b+c+d)

#VALUE!

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

#VALUE!

Cost for 120 cum = a+b+c+d+e+f

#VALUE!

Rate per cum = (a+b+c+d+e+f)/120

#VALUE!
say

(r)

#VALUE!
33.00

#VALUE!

e)

Overhead charges @ 0.2 on (a+b+c+d)

#VALUE!

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

#VALUE!

Cost for 120 cum = a+b+c+d+e+f

#VALUE!

Rate per cum = (a+b+c+d+e+f)/120

#VALUE!
say

(iii)
(p)

#VALUE!

Height above 10m

Basic Cost of Labour, Material & Machinery (a+b+c)


for
120 cum
d) Formwork and staging 33 per cent of (a+b+c)

14.1D
Case II

#VALUE!

Height 5m to 10m

Basic Cost of Labour, Material & Machinery (a+b+c)


for
120 cum
d) Formwork and staging 28 per cent of (a+b+c)

14.1D
Case II
(ii)

#VALUE!

#VALUE!

Cost for 120 cum = a+b+c+d+e+f

14.1D
Case II
(ii)

#VALUE!

Height above 10m

Basic Cost of Labour, Material & Machinery (a+b+c)


for
120 cum
d) Formwork and staging 28 per cent of (a+b+c)

14.1D
Case II

#VALUE!

#VALUE!

For box girder and balanced cantilever, 38-58 per cent


of cost of concrete.
Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
120 cum
Page 12 of 394

for

#VALUE!

d)

Formwork and staging 38 per cent of (a+b+c)

e)

Overhead charges @ 0.2 on (a+b+c+d)

38.00

#VALUE!
#VALUE!

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

#VALUE!

Cost for 120 cum = a+b+c+d+e+f

#VALUE!

Rate per cum = (a+b+c+d+e+f)/120

#VALUE!
say

14.1D
Case II
(iii)

(q)

Height 5m to 10m

Basic Cost of Labour, Material & Machinery (a+b+c)


for
120 cum
d) Formwork and staging 48 per cent of (a+b+c)

#VALUE!
48.00

#VALUE!

e)

Overhead charges @ 0.2 on (a+b+c+d)

#VALUE!

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

#VALUE!

Cost for 120 cum = a+b+c+d+e+f

#VALUE!

Rate per cum = (a+b+c+d+e+f)/120

#VALUE!
say

14.1D
Case II
(iii)

(r)

#VALUE!
58.00

#VALUE!

e)

Overhead charges @ 0.2 on (a+b+c+d)

#VALUE!

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

#VALUE!

Cost for 120 cum = a+b+c+d+e+f

#VALUE!

Rate per cum = (a+b+c+d+e+f)/120


E

#VALUE!

Height above 10m

Basic Cost of Labour, Material & Machinery (a+b+c)


for
120 cum
d) Formwork and staging 58 per cent of (a+b+c)

14.1

#VALUE!

#VALUE!
say

#VALUE!

PSC Grade M-40

Case 1 Using concrete mixer.


Unit = 1 cum
Taking output = 15 cum
a)

Material
Cement

tonne

6.45

5940.00

38313.00

M-081

Coarse sand

cum

6.75

2400.00

16200.00

M-005

20 mm Aggregate

cum

8.10

942.00

7630.20

M-053

10 mm Aggregate

cum

5.40

1063.00

5740.20

M-051

kg

25.80

input

#VALUE!

M-180

Mate

day

0.96

673.00

646.08

L-12

Mason

day

2.00

500.00

1000.00

L-11

Mazdoor

day

22.00

377.00

8294.00

L-13

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

218.00

1308.00

P&M-009

Generator 33 KVA

hour

6.00

349.00

2094.00

P&M-079

Admixture @ 0.4 per cent of cement


b)

c)

Labour

Machinery

Basic Cost of Labour, Material & Machinery (a+b+c)


for 15 cum
For formwork and staging add the following:
14.1E
Case I

(i)

For solid slab super-structure, 20-30 per cent of (a+b+c)

(p)

Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
for
15 cum
d) Formwork and staging 20 per cent of (a+b+c)

#VALUE!

#VALUE!
20.00

#VALUE!

e)

Overhead charges @ 0.2 on (a+b+c+d)

#VALUE!

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

#VALUE!

Cost for 15 cum = a+b+c+d+e+f

#VALUE!

Rate per cum = (a+b+c+d+e+f)/15

#VALUE!
say

14.1E
Case I (i)

(q)

Height 5m to 10m

Page 13 of 394

#VALUE!

Basic Cost of Labour, Material & Machinery (a+b+c)


for
15 cum
d) Formwork and staging 25 per cent of (a+b+c)

#VALUE!
25.00

#VALUE!

e)

Overhead charges @ 0.2 on (a+b+c+d)

#VALUE!

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

#VALUE!

Cost for 15 cum = a+b+c+d+e+f

#VALUE!

Rate per cum = (a+b+c+d+e+f)/15

#VALUE!
say

14.1E
Case I (i)

(r)

Height above 10m

Basic Cost of Labour, Material & Machinery (a+b+c)


for
15 cum
d) Formwork and staging 30 per cent of (a+b+c)

#VALUE!
30.00

#VALUE!

e)

Overhead charges @ 0.2 on (a+b+c+d)

#VALUE!

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

#VALUE!

Cost for 15 cum = a+b+c+d+e+f

#VALUE!

Rate per cum = (a+b+c+d+e+f)/15

#VALUE!
say

14.1E
Case I

(ii)

For T-beam & slab, 25-35 per cent of (a+b+c)

(p)

Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
for
15 cum
d) Formwork and staging 25 per cent of (a+b+c)

25.00

#VALUE!

e)

Overhead charges @ 0.2 on (a+b+c+d)

#VALUE!

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

#VALUE!
#VALUE!

Rate per cum = (a+b+c+d+e+f)/15

#VALUE!
say

(q)

#VALUE!
30.00

#VALUE!

e)

Overhead charges @ 0.2 on (a+b+c+d)

#VALUE!

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

#VALUE!

Cost for 15 cum = a+b+c+d+e+f

#VALUE!

Rate per cum = (a+b+c+d+e+f)/15

#VALUE!
say

(r)

#VALUE!

Height above 10m

Basic Cost of Labour, Material & Machinery (a+b+c)


for
15 cum
d) Formwork and staging 35 per cent of (a+b+c)

#VALUE!
35.00

#VALUE!

e)

Overhead charges @ 0.2 on (a+b+c+d)

#VALUE!

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

#VALUE!

Cost for 15 cum = a+b+c+d+e+f

#VALUE!

Rate per cum = (a+b+c+d+e+f)/15


14.1E

#VALUE!

Height 5m to 10m

Basic Cost of Labour, Material & Machinery (a+b+c)


for
15 cum
d) Formwork and staging 30 per cent of (a+b+c)

14.1E
Case I
(ii)

#VALUE!

#VALUE!

Cost for 15 cum = a+b+c+d+e+f

14.1E
Case I
(ii)

#VALUE!

#VALUE!
say

#VALUE!

Case II Using Batching Plant, Transit Mixer and Concrete Pump


Unit = cum
Taking output = 120 cum
a)

Material
Cement

tonne

51.60

5940.00

306504.00

M-081

Coarse sand

cum

54.00

2400.00

129600.00

M-004

20 mm Aggregate

cum

64.80

942.00

61041.60

M-053

10 mm Aggregate

cum

43.20

1063.00

45921.60

M-051

kg

206.40

input

#VALUE!

M-180

Admixture @ 0.4 per cent of cement


b)

Labour
Page 14 of 394

c)

Mate

day

0.94

673.00

632.62

Mason

day

3.50

500.00

1750.00

L-12
L-11

Mazdoor

day

20.00

377.00

7540.00

L-13

Batching Plant @ 20 cum/hour

hour

6.00

2094.00

12564.00

P&M-002

Generator 100 KVA

hour

6.00

654.00

3924.00

P&M-080

Loader

hour

6.00

756.00

4536.00

P&M-017

hour

15.00

873.00

13095.00

P&M-049

tonne.km

300L

input

#VALUE!

Lead =1
km & P&M050

6.00

240.00

1440.00

P&M-007

Machinery

Transit Mixer ( capacity 4.0 cu.m )


Transit Mixer 4 cum capacity lead upto1 Km
Lead beyond 1 Km, L - lead in Kilometer

Concrete Pump

hour

Basic Cost of Labour, Material & Machinery (a+b+c) for


120 cum
For formwork and staging add the following:
14.1E
Case II

(i)
(p)

#VALUE!

For solid/voided slab super-structure, 18-28 per cent of


(a+b+c)
Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 120
cum
d) Formwork and staging 18 per cent of (a+b+c)

#VALUE!
18.00

#VALUE!

e)

Overhead charges @ 0.2 on (a+b+c+d)

#VALUE!

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

#VALUE!

Cost for 15 cum = a+b+c+d+e+f

#VALUE!

Rate per cum = (a+b+c+d+e+f)/120

#VALUE!
say

14.1E
Case II
(i)

(q)

Height 5m to 10m

Basic Cost of Labour, Material & Machinery (a+b+c)


for
120 cum
d) Formwork and staging 23 per cent of (a+b+c)

#VALUE!
23.00

#VALUE!

e)

Overhead charges @ 0.2 on (a+b+c+d)

#VALUE!

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

#VALUE!

Cost for 120 cum = a+b+c+d+e+f

#VALUE!

Rate per cum = (a+b+c+d+e+f)/120

#VALUE!
say

14.1E
Case II
(i)

(r)

#VALUE!
28.00

#VALUE!

e)

Overhead charges @ 0.2 on (a+b+c+d)

#VALUE!

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

#VALUE!

Cost for 120 cum = a+b+c+d+e+f

#VALUE!

Rate per cum = (a+b+c+d+e+f)/120

#VALUE!
say

(ii)

For T-beam & slab, 23-33 per cent of (a+b+c)

(p)

Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
for
120 cum
d) Formwork and staging 23 per cent of (a+b+c)

23.00

#VALUE!

e)

Overhead charges @ 0.2 on (a+b+c+d)

#VALUE!

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

#VALUE!
#VALUE!

Rate per cum = (a+b+c+d+e+f)/120

#VALUE!
say

(q)

#VALUE!

#VALUE!

Cost for 120 cum = a+b+c+d+e+f

14.1E
Case II
(ii)

#VALUE!

Height above 10m

Basic Cost of Labour, Material & Machinery (a+b+c)


for
120 cum
d) Formwork and staging 28 per cent of (a+b+c)

14.1E
Case II

#VALUE!

Height 5m to 10m

Page 15 of 394

#VALUE!

Basic Cost of Labour, Material & Machinery (a+b+c)


for
120 cum
d) Formwork and staging 28 per cent of (a+b+c)

#VALUE!
28.00

#VALUE!

e)

Overhead charges @ 0.2 on (a+b+c+d)

#VALUE!

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

#VALUE!

Cost for 120 cum = a+b+c+d+e+f

#VALUE!

Rate per cum = (a+b+c+d+e+f)/120

#VALUE!
say

14.1E
Case II
(ii)

(r)

Height above 10m

Basic Cost of Labour, Material & Machinery (a+b+c)


for
120 cum
d) Formwork and staging 33 per cent of (a+b+c)

#VALUE!
33.00

#VALUE!

e)

Overhead charges @ 0.2 on (a+b+c+d)

#VALUE!

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

#VALUE!

Cost for 120 cum = a+b+c+d+e+f

#VALUE!

Rate per cum = (a+b+c+d+e+f)/120

#VALUE!
say

14.1E
Case II

(iii)

For cast-in-situ box girder, segment construction and


balanced cantilever, 38-58 per cent of cost of concrete.

(p)

Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
for
120 cum
d) Formwork and staging 38 per cent of (a+b+c)

38.00

#VALUE!

e)

Overhead charges @ 0.2 on (a+b+c+d)

#VALUE!

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

#VALUE!
#VALUE!

Rate per cum = (a+b+c+d+e+f)/120

#VALUE!
say

(q)

#VALUE!
48.00

#VALUE!

e)

Overhead charges @ 0.2 on (a+b+c+d)

#VALUE!

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

#VALUE!

Cost for 120 cum = a+b+c+d+e+f

#VALUE!

Rate per cum = (a+b+c+d+e+f)/120

#VALUE!
say

(r)

#VALUE!
58.00

#VALUE!

e)

Overhead charges @ 0.2 on (a+b+c+d)

#VALUE!

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

#VALUE!

Cost for 120 cum = a+b+c+d+e+f

#VALUE!

Rate per cum = (a+b+c+d+e+f)/120


F

#VALUE!

Height above 10m

Basic Cost of Labour, Material & Machinery (a+b+c)


for
120 cum
d) Formwork and staging 58 per cent of (a+b+c)

14.1F

#VALUE!

Height 5m to 10m

Basic Cost of Labour, Material & Machinery (a+b+c)


for
120 cum
d) Formwork and staging 48 per cent of (a+b+c)

14.1E
Case II
(iii)

#VALUE!

#VALUE!

Cost for 120 cum = a+b+c+d+e+f

14.1E
Case II
(iii)

#VALUE!

#VALUE!
say

#VALUE!

PSC Grade M-45


Unit = 1 cum
Taking output = 120 cum
a)

Material
Cement

tonne

55.80

5940.00

331452.00

M-081

Coarse sand

cum

54.00

2400.00

129600.00

M-004

20 mm Aggregate

cum

64.80

942.00

61041.60

M-053

10 mm Aggregate

cum

43.20

1063.00

45921.60

M-051

kg

223.20

input

#VALUE!

M-180

Admixture @ 0.4 per cent of cement


b)

Labour
Page 16 of 394

c)

Mate

day

0.94

673.00

632.62

Mason

day

3.50

500.00

1750.00

L-12
L-11

Mazdoor

day

20.00

377.00

7540.00

L-13

Batching Plant @ 20 cum/hour

hour

6.00

2094.00

12564.00

P&M-002

Generator 100 KVA

hour

6.00

654.00

3924.00

P&M-080

Loader

hour

6.00

756.00

4536.00

P&M-017

hour

15.00

873.00

13095.00

P&M-049

tonne.km

300L

input

#VALUE!

Lead =1
km & P&M050

6.00

240.00

1440.00

P&M-007

Machinery

Transit Mixer ( capacity 4.0 cu.m )


Transit Mixer 4 cum capacity lead upto1 Km
Lead beyond 1 Km, L - lead in Kilometer

Concrete Pump

hour

Basic Cost of Labour, Material & Machinery (a+b+c)


for 120 cum
For formwork and staging add the following:
14.1F

(i)
(p)

#VALUE!

For solid slab/voided slab super-structure, 16-26 per


cent of cost of concrete (a+b+c)
Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
for
120 cum
d) Formwork and staging 16 per cent of (a+b+c)

#VALUE!
16.00

#VALUE!

e)

Overhead charges @ 0.2 on (a+b+c+d)

#VALUE!

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

#VALUE!

Cost for 120 cum = a+b+c+d+e+f

#VALUE!

Rate per cum = (a+b+c+d+e+f)/120

#VALUE!
say

14.1F
(i)

(q)

Height 5m to 10m
Basic Cost of Labour, Material & Machinery (a+b+c)
for
120 cum
d) Formwork and staging 21 per cent of (a+b+c)

#VALUE!
21.00

#VALUE!

e)

Overhead charges @ 0.2 on (a+b+c+d)

#VALUE!

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

#VALUE!

Cost for 120 cum = a+b+c+d+e+f

#VALUE!

Rate per cum = (a+b+c+d+e+f)/120

#VALUE!
say

14.1F
(i)

(r)

#VALUE!
26.00

#VALUE!

e)

Overhead charges @ 0.2 on (a+b+c+d)

#VALUE!

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

#VALUE!

Cost for 120 cum = a+b+c+d+e+f

#VALUE!

Rate per cum = (a+b+c+d+e+f)/120

#VALUE!
say

(ii)

For T-beam & slab including launching of precast


girders by launching truss upto 40 m span, 21-31 per
cent of cost of concrete.

(p)

Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
for
120 cum
d) Formwork and staging 21 per cent of (a+b+c)

21.00

#VALUE!

e)

Overhead charges @ 0.2 on (a+b+c+d)

#VALUE!

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

#VALUE!
#VALUE!

Rate per cum = (a+b+c+d+e+f)/120

#VALUE!
say

(q)

#VALUE!

#VALUE!

Cost for 120 cum = a+b+c+d+e+f

14.1F
(ii)

#VALUE!

Height above 10m


Basic Cost of Labour, Material & Machinery (a+b+c)
for
120 cum
d) Formwork and staging 26 per cent of (a+b+c)

14.1F

#VALUE!

#VALUE!

Height 5m to 10m
Basic Cost of Labour, Material & Machinery (a+b+c)
for
120 cum
d) Formwork and staging 26 per cent of (a+b+c)
Page 17 of 394

#VALUE!
26.00

#VALUE!

e)

Overhead charges @ 0.2 on (a+b+c+d)

#VALUE!

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

#VALUE!

Cost for 120 cum = a+b+c+d+e+f

#VALUE!

Rate per cum = (a+b+c+d+e+f)/120

#VALUE!
say

14.1F
(ii)

(r)

Height above 10m


Basic Cost of Labour, Material & Machinery (a+b+c)
for
120 cum
d) Formwork and staging 31 per cent of (a+b+c)

#VALUE!
31.00

#VALUE!

e)

Overhead charges @ 0.2 on (a+b+c+d)

#VALUE!

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

#VALUE!

Cost for 120 cum = a+b+c+d+e+f

#VALUE!

Rate per cum = (a+b+c+d+e+f)/120

#VALUE!
say

14.1F

(iii)

For cast-in-situ box girder, segmental construction and


balanced cantilever, 36-56 per cent of cost of concrete.

(p)

Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
for
120 cum
d) Formwork and staging 36 per cent of (a+b+c)

36.00

#VALUE!

e)

Overhead charges @ 0.2 on (a+b+c+d)

#VALUE!

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

#VALUE!
#VALUE!

Rate per cum = (a+b+c+d+e+f)/120

#VALUE!
say

(q)

#VALUE!
46.00

#VALUE!

e)

Overhead charges @ 0.2 on (a+b+c+d)

#VALUE!

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

#VALUE!

Cost for 120 cum = a+b+c+d+e+f

#VALUE!

Rate per cum = (a+b+c+d+e+f)/120

#VALUE!
say

(r)

#VALUE!
56.00

#VALUE!

e)

Overhead charges @ 0.2 on (a+b+c+d)

#VALUE!

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

#VALUE!

Cost for 120 cum = a+b+c+d+e+f

#VALUE!

Rate per cum = (a+b+c+d+e+f)/120


G

#VALUE!

Height above 10m


Basic Cost of Labour, Material & Machinery (a+b+c)
for
120 cum
d) Formwork and staging 56 per cent of (a+b+c)

14.1

#VALUE!

Height 5m to 10m
Basic Cost of Labour, Material & Machinery (a+b+c)
for
120 cum
d) Formwork and staging 46 per cent of (a+b+c)

14.1F
(iii)

#VALUE!

#VALUE!

Cost for 120 cum = a+b+c+d+e+f

14.1F
(iii)

#VALUE!

#VALUE!
say

#VALUE!

PSC Grade M-50


Unit = 1 cum
Taking output = 120 cum
a)

Material
Cement

tonne

58.80

5940.00

349272.00

M-081

Coarse sand

cum

54.00

2400.00

129600.00

M-004

20 mm Aggregate

cum

64.80

942.00

61041.60

M-053

10 mm Aggregate

cum

43.20

1063.00

45921.60

M-051

kg

235.20

input

#VALUE!

M-180

Mate

day

0.94

673.00

632.62

L-12

Mason

day

3.50

500.00

1750.00

L-11

Mazdoor

day

20.00

377.00

7540.00

L-13

hour

6.00

2094.00

12564.00

P&M-002

Admixture @ 0.4 per cent of cement


b)

c)

Labour

Machinery
Batching Plant @ 20 cum/hour
Page 18 of 394

Generator 100 KVA

hour

6.00

654.00

3924.00

P&M-080

Loader

hour

6.00

756.00

4536.00

P&M-017

hour

15.00

873.00

13095.00

P&M-049

tonne.km

300L

input

#VALUE!

Lead =1
km & P&M050

6.00

240.00

1440.00

P&M-007

Transit Mixer ( capacity 4.0 cu.m )


Transit Mixer 4 cum capacity lead upto1 Km
Lead beyond 1 Km, L - lead in Kilometer

Concrete Pump

hour

Basic Cost of Labour, Material & Machinery (a+b+c)


for 120 cum
For formwork and staging add the following:
14.1G

(i)

For cast-in-situ box girder, segmental construction and


balanced cantilever, 35-55 per cent of cost of concrete

(p)

Height upto 5m

#VALUE!

Basic Cost of Labour, Material & Machinery (a+b+c)


for
120 cum
d) Formwork and staging 35 per cent of (a+b+c)

#VALUE!
35.00

#VALUE!

e)

Overhead charges @ 0.2 on (a+b+c+d)

#VALUE!

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

#VALUE!

Cost for 120 cum = a+b+c+d+e+f

#VALUE!

Rate per cum = (a+b+c+d+e+f)/120

#VALUE!
say

14.1G
(i)

(q)

Height 5m to 10m
Basic Cost of Labour, Material & Machinery (a+b+c)
for
120 cum
d) Formwork and staging 45 per cent of (a+b+c)

#VALUE!
45.00

#VALUE!

e)

Overhead charges @ 0.2 on (a+b+c+d)

#VALUE!

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

#VALUE!

Cost for 120 cum = a+b+c+d+e+f

#VALUE!

Rate per cum = (a+b+c+d+e+f)/120

#VALUE!
say

14.1G
(i)

(r)

#VALUE!
55.00

#VALUE!

e)

Overhead charges @ 0.2 on (a+b+c+d)

#VALUE!

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

#VALUE!

Cost for 120 cum = a+b+c+d+e+f

#VALUE!

Rate per cum = (a+b+c+d+e+f)/120


H

#VALUE!

Height above 10m


Basic Cost of Labour, Material & Machinery (a+b+c)
for
120 cum
d) Formwork and staging 55 per cent of (a+b+c)

14.1

#VALUE!

#VALUE!
say

#VALUE!

PSC Grade M- 55
Unit = 1 cum
Taking output = 120 cum
a)

Material
Cement

tonne

63.50

5940.00

377190.00

M-081

Coarse sand

cum

54.00

2400.00

129600.00

M-004

20 mm Aggregate

cum

64.80

942.00

61041.60

M-053

10 mm Aggregate

cum

43.20

1063.00

45921.60

M-051

kg

254.00

input

#VALUE!

M-180

Mate

day

0.94

673.00

632.62

L-12

Mason

day

3.50

500.00

1750.00

L-11

Mazdoor

day

20.00

377.00

7540.00

L-13

Batching Plant @ 20 cum/hour

hour

6.00

2094.00

12564.00

P&M-002

Generator 100 KVA

hour

6.00

654.00

3924.00

P&M-080

Loader

hour

6.00

756.00

4536.00

P&M-017

hour

15.00

873.00

13095.00

P&M-049

Admixture @ 0.4 per cent of cement


b)

c)

Labour

Machinery

Transit Mixer ( capacity 4.0 cu.m )


Transit Mixer 4 cum capacity lead upto1 Km
Page 19 of 394

Lead beyond 1 Km, L - lead in Kilometer

Concrete Pump

tonne.km

hour

Basic Cost of Labour, Material & Machinery (a+b+c)


for 120 cum
For formwork and staging add the following:
14.1H

(i)

For cast-in-situ box girder, segmental construction and


balanced cantilever, 35-55 per cent of cost of concrete

(p)

Height upto 5m

300L

input

6.00

240.00

#VALUE!
35.00

#VALUE!

e)

Overhead charges @ 0.2 on (a+b+c+d)

#VALUE!

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

#VALUE!

Cost for 120 cum = a+b+c+d+e+f

#VALUE!

Rate per cum = (a+b+c+d+e+f)/120

#VALUE!
say

(q)

#VALUE!
45.00

#VALUE!

e)

Overhead charges @ 0.2 on (a+b+c+d)

#VALUE!

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

#VALUE!

Cost for 120 cum = a+b+c+d+e+f

#VALUE!

Rate per cum = (a+b+c+d+e+f)/120

#VALUE!
say

(r)

#VALUE!

Height above 10m


Basic Cost of Labour, Material & Machinery (a+b+c)
for
120 cum
d) Formwork and staging 55 per cent of (a+b+c)

#VALUE!
55.00

#VALUE!

e)

Overhead charges @ 0.2 on (a+b+c+d)

#VALUE!

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

#VALUE!

Cost for 120 cum = a+b+c+d+e+f

#VALUE!

Rate per cum = (a+b+c+d+e+f)/120


Note

#VALUE!

Height 5m to 10m
Basic Cost of Labour, Material & Machinery (a+b+c)
for
120 cum
d) Formwork and staging 45 per cent of (a+b+c)

14.1H
(i)

Lead =1
km & P&M050
1440.00 P&M-007

#VALUE!

Basic Cost of Labour, Material & Machinery (a+b+c)


for
120 cum
d) Formwork and staging 35 per cent of (a+b+c)

14.1H
(i)

#VALUE!

#VALUE!
say

#VALUE!

1.Where ever concrete is carried out using batching plant,


transit mixer, concrete pump, admixers conforming IS: 9103
@ 0.4 per cent of weight of cement may be added for
achieving desired slump of concrete.
2. Cement provided for various components of the super
structure is for estimating purpose only. Actual quantity of
cement will be as per approved mix design. Similarly, the
provision for coarse and fine aggregates is for estimating
purpose and the exact quantity shall be as per the mix
design.
3. The items like needle and surface vibrators are part of
minor T & P which is already covered under the overhead
charges. As such these items have not been added
separately in the rate analysis.

14.2

1600

Supplying, fitting and placing HYSD bar reinforcement in


super-structure complete as per drawing and technical
specifications
Unit = 1 MT
Taking output = 1 MT
a)

Material
HYSD bars including 5 per cent for laps and wastage
Binding wire

b)
Labour for cutting, bending, tying and placing in
position
Mate
Blacksmith
Page 20 of 394

tonne

1.05

52100.00

54705.00

M-082

Kg

8.00

87.00

696.00

M-072

day

0.44

673.00

296.12

L-12

day

3.00

500.00

1500.00

L-02

Mazdoor

day
Basic Cost of Labour & Material (a+b)

c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

8.00

377.00

L-13

12042.62
7225.57

Rate per MT = a+b+c+d


14.3

3016.00

60214.00

79481.32
say

79481.00

High tensile steel wires/strands including all


accessories for stressing, stressing operations and
grouting complete as per drawing and Technical
Specifications

1800

Unit = 1 MT
Taking output = 0.377 MT
Details of cost for 12T13 strand 40 m long cable (weight =
0.377 MT)
a) Material
H.T. Strand @ 9.42 kg/m including 2 per cent for
wastage and extra length for jacking
Sheathing duct ID 66 mm along with 5 per cent extra
length 40 x 1.05 = 42 m.
Tube anchorage set complete with bearing plate,
permanent wedges etc
Cement for grouting including 3 per cent wastage @
3.00 kg/m = 3 x 1.03 x 40 = 123.60 kg (say, = 125 kg)

b)

tonne

0.39

input

#VALUE!

M-119

metre

42.00

input

#VALUE!

M-165

each

2.00

input

#VALUE!

M-187

tonne

0.125

5940.00

742.50

M-081

Add 0.50 per cent cost of material for Spacers,


Insulation tape and miscellaneous items
Labour

#VALUE!

i) For making and fixing cables, anchorages


Mate

day

0.16

673.00

107.68

L-12

Blacksmith

day

1.00

500.00

500.00

L-02

Mazdoor

day

3.00

377.00

1131.00

L-13

ii) For prestressing


Mate/Supervisor

day

0.05

673.00

33.65

L-12

Prestressing operator / Fitter

day

0.25

456.00

114.00

L-08

Mazdoor

day

1.00

377.00

377.00

L-13

Mate/Supervisor

day

0.05

673.00

33.65

L-12

Mason

day

0.25

500.00

125.00

L-11

Mazdoor

day

1.00

377.00

377.00

L-13

Stressing jack with pump

hour

2.50

121.00

302.50

P&M-040

Grouting pump with agitator

hour

1.00

input

#VALUE!

M-111

Generator 33 KVA.

hour

3.50

349.00

1221.50

P&M-079

iii) For grouting

c)

Machinery

d)

Overhead charges @ 0.2 on (a+b+c)

#VALUE!

e)

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!

Cost for 0.377 MT (a+b+c+d+e)

#VALUE!

Rate per MT = (a+b+c+d+e)/0.377


Note
14.4

2702

#VALUE!
say

#VALUE!

59776.00

Cost of HT steel has been taken for delivery at site. Hence


carriage has not been considered.
Providing and laying Cement concrete wearing coat M30 grade including reinforcement complete as per
drawing and Technical Specifications
Unit = 1 cum
Taking output = 1 cum
a)

Material

b)

Cement concrete M30 Grade Refer relevant item of


concrete in Item 14.1 excluding formwork
HYSD bar reinforcement Rate as per item No
14.2(Excluding OH & CP)
Labour
Mazdoor for cleaning deck slab concrete surface.

c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)


Page 21 of 394

cum

1.00

59776.00

tonne

0.075

60214.00

day

0.15

377.00

Item
14.1(C)
4516.05 Item 14.2 A

56.55
12869.72
7721.83

L-13

Rate per cum (a+b+c+d)

84940.15
say

14.5

515 &
2702

84940.00

Mastic Asphalt
Providing and laying 12 mm thick mastic asphalt
wearing course on top of deck slab excluding prime
coat with paving grade bitumen meeting the
requirements given in table 500-29, prepared by using
mastic cooker and laid to required level and slope after
cleaning the surface, including providing antiskid
surface with bitumen precoated fine grained hard stone
chipping of 9.5 mm nominal size at the rate of 0.005cum
per 10 sqm and at an approximate spacing of 10 cm
center to center in both directions, pressed into surface
when the temperature of surfaces not less than 100 deg.
C, protruding 1 mm to 4 mm over mastic surface, all
complete as per clause 515.

Unit = sqm
Taking output = 72.46 sqm (2 tonnes)(0.869 cum)
assuming a density of 2.3 tonnes/cum.
a) Labour

b)

c)

Mate

day

0.49

673.00

329.77

L-12

Mazdoor

day

11.00

377.00

4147.00

L-13

Mazdoor (Skilled)

day

1.25

408.00

510.00

L-15

Mechanical broom @ 1250 sqm per hour

hour

0.06

334.00

20.04

P&M-031

Air compressor 250 cfm

hour

0.06

300.00

18.00

P&M-001

Mastic cooker 1 tonne capacity

hour

6.00

58.00

348.00

P&M-030

Bitumen boiler 1500 litres capacity

hour

6.00

186.00

1116.00

P&M-005

Tractor for towing and positioning of mastic cooker and


bitumen boiler
Material

hour

1.00

340.00

340.00

P&M-053

tonne

0.204

41320.00

8429.28

M-074

cum

0.39

137.00

53.43

M-021

tonne

0.36

3200.00

1152.00

M-188

cum

0.55

1063.00

584.65

M-051

cum

0.036

input

#VALUE!

M-142

kg

1.05

41.32

43.39

Machinery

Base mastic (without coarse aggregates) = 60 per cent


Coarse aggregate(3.35mm to 9.5 mm size) = 40 per cent .
Proportion of material required for mastic asphalt with coarse
aggregates (based on mix design done by CRRI for a
specific case)
i) Bitumen 80/100 or 60/70 or 30/40 @ 10.2 per cent
by weight of mix. 2 x 10.2/100 = 0.204
ii) Crusher stone dust @ 31.9 per cent by weight of
mix = 2 x 31.9/100 = 0.638 tonnes = 0.638/1.625 =
0.39
iii) Lime stone dust filler with calcium carbonate
content not less than 80 per cent by weight @ 17.92
per cent by weight of mix = 2 x 17.92/100 = 0.36
iv) Coarse aggregates 9.5 mm to 3.35 mm size @ 40
per cent by weight of mix = 2 x 40/100 = 0.8 MT =
0.8/1.456 = 0.55
v) Pre-coated stone chips of 9.5 mm nominal size for
skid resistance = 72.46x0.005/10 = 0.036
vi) Bitumen for coating of chips @ 2 per cent by
weight = 0.036 x 1.456 x 2/100 = 0.001048MT =
1.05kg
d)

Overhead charges @ 0.2 on (a+b+c)

#VALUE!

e)

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!

Cost for 72.46 sqm = a+b+c+d+e

#VALUE!

Rate per sqm = (a+b+c+d+e)/72.46

#VALUE!
say

Note

1.The rates for 6 mm or any other thickness may be worked


out on pro-rata basis.
2. Where tack coat is required to be provided before laying
mastic asphalt, the same is required to be measured and
paid separately.
3.The quantities of binder, filler and aggregates are for
estimating purpose. Exact quantities shall be as per mix
design.

Page 22 of 394

#VALUE!

M074/1000

14.6

4.This rate analysis is based on design made by CRRI for a


specific case and is meant for estimating purposes only.
Actual design is required to be done for each case.
5.The quantity of bitumen works out 17 per cent of the
mastic asphalt blocks without aggregates and falls within the
standards laid down by MoRTH Specifications.
Construction of precast RCC railing of M30 Grade,
aggregate size not exceeding 12 mm, true to line and
grade, tolerance of vertical RCC post not to exceed 1 in
500, centre to centre spacing between vertical post not
to exceed 2000 mm, leaving adequate space between
vertical post for expansion, complete as per approved
drawings and technical specifications.

2703,
1500,
1600 &
1700

Unit = 1 RM
Taking output = 2 x 24 m span = 48 m
a)

Material
Cement concreteM30 Grade Refer relevant item of
concrete in Item 14.1(C) by using batching plant,
excluding formwork i.e. per cum basic cost (a+b+c)

cum

4.09

#VALUE!

#VALUE!

Item
14.1(C)

No. of vertical posts = (12 + 2)2 = 28 Nos., External


area of vertical post 0.25x0.275 = 0.069sqm, Concrete
in Vertical posts = 0.069 x 28 = 1.932 cum, Hand rail in
3 tiers = 3 x 24 = 72 m, External area = 0.170 x 0.175
= 0.03 sqm, Concrete in hand rails = 0.03 x 72 = 2.16
cum, Total Concrete = 1.932 + 2.16 = 4.092 cum.
(Refer MoRTH SD / 202).
Add 5 per cent of above cost for form work for casting
in casting yard.
HYSD bar reinforcement Rate as per item No
14.2(Excluding OH & CP)
Refer MoRTH SD / 202.

#VALUE!
tonne

0.87

60214.00

#VALUE!

b)

Add 5 per cent of (a) for handling and fixing of


precast panels in position
Overhead charges @ 0.2 on (a)

c)

Contractor's profit @ 0.1 on (a+b)

#VALUE!

#VALUE!

Rate for 48 m (a+b+c)

#VALUE!

Rate per metre (a+b+c)/48


Note

14.7

2703,
1500,
1600 &
1700

52085.11 Item 14.2 A

#VALUE!
say

#VALUE!

#VALUE!

1.Quantities of material have been adopted from standard


plans of MoRTH vide drawing no. SD/202.
2.48 m length is the total linear length adding both sides of
24 m span.
Construction of RCC railing of M30 Grade in-situ with 20
mm nominal size aggregate, true to line and grade,
tolerance of vertical RCC post not to exceed 1 in 500,
centre to centre spacing between vertical post not to
exceed 2000 mm, leaving adequate space between
vertical post for expansion, complete as per approved
drawings and technical specifications.
Unit = 1 RM
Taking output = 2 x 24 m span = 48 m.
a)

Material
Cement concreteM30 Grade Refer relevant item of
concrete in Item 14.1(C) by using batching plant,
excluding formwork i.e. per cum basic cost (a+b+c)
No. of vertical posts = (12 + 2)2 = 28 Nos., External
area of vertical post 0.25x0.275 = 0.069sqm, Concrete
in vehicle posts = 0.069 x 28 = 1.932 cum, Hand rail in
3 tiers = 3 x 24 = 72 m, External area = 0.170 x 0.175
= 0.03 sqm, Concrete in hand rails = 0.03 x 72 = 2.16
cum, Total Concrete = 1.932 + 2.16 = 4.092 cum.
(Refer MoRTH SD / 202).

cum

4.092

#VALUE!

tonne

0.87

60214.00

Add 12 per cent of above cost for form work.


HYSD bar reinforcement Rate as per item No
14.2(Excluding OH & CP)
refer MoRTH SD / 202.
b)

Overhead charges @ 0.2 on (a)

#VALUE!
52085.11 Item 14.2 A

#VALUE!
Page 23 of 394

Item
14.1(C)

c)

Contractor's profit @ 0.1 on (a+b)

#VALUE!

Rate for 48 m (a+b+c)

#VALUE!

Rate per metre (a+b+c)/48


Note

14.8

2703.2 &
1900

#VALUE!
say

#VALUE!

1. Quantities of material have been adopted from standard


plans of MoRTH vide drawing no. SD/202.
2. 48 m length is the total linear length adding both sides of
24 m span.
Providing, fitting and fixing mild steel railing complete
as per drawing and Technical Specification
Unit = 1 RM
Taking output = 2 x 50 m span = 100 m
a)

b)

Material:
1) ISMC 100 = 2.806 x 1.05 = 2.946 MT

tonne

2.95

44100.00

129918.60

M-179

2) MS Flat = 0.964 x 1.05 = 1.012 MT

tonne

1.01

44100.00

44629.20

M-179

3) MS bars = 0.17 x 1.05 = 0.180 MT

tonne

0.18

44100.00

7938.00

M-179

4) MS bolts, nuts and washers

tonne

0.15

81000.00

12150.00

M130*1000

Add @ 5 per cent of cost of material for painting one


shop coat with red oxide primer and three coats of
synthetic enamel paint and consumables to safeguard
against weathering and corrosion.

9731.79

Add for cost of concrete for fixing vertical posts in the


performed recess @ 1 per cent of cost of material.
Add for electricity charges, welding and drilling
equipment, electrodes and other consumables @ 1 per
cent of cost of material.

1946.36
1946.36

Labour
Mate

day

2.80

673.00

1884.40

L-12

Mazdoor (Skilled)

day

30.00

408.00

12240.00

L-15

Mazdoor

day

40.00

377.00

15080.00

L-13

c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

47492.94
28495.76

Cost for 100 m steel railing = a+b+c+d

313453.41

Rate per metre (a+b+c+d)/100


14.9

2705

3134.53
say

3135.00

#VALUE!

Drainage Spouts complete as per drawing and Technical


specification
Unit = 1 No.
Taking output = 1 No.
a)

b)

Material
Corrosion resistant Structural steel including 5 per cent
wastage
GI pipe 100mm dia

Kg

4.00

#VALUE!

M087/1000
M-056

metre

6.00

55.00

330.00

GI bolt 10 mm Dia

each

6.00

input

#VALUE!

M-110

Galvanised MS flat clamp

each

2.00

input

#VALUE!

M-101

Mate

day

0.02

673.00

13.46

L-12

Skilled (Blacksmith, welder etc.)

day

0.02

500.00

10.00

L-02

Mazdoor

day

0.02

377.00

7.54

L-13

Mate

day

0.01

673.00

6.73

L-12

Mason

day

0.01

500.00

5.00

L-11

Mazdoor

day

0.20

377.00

75.40

L-13

Labour

For fabrication

For fixing in position

Add @ 5 per cent of cost of material and labour for


electrodes, cutting gas, sealant, anti-corrosive
bituminous paint, mild steel grating etc.

#VALUE!

c)

Overhead charges @ 0.2 on (a+b)

#VALUE!

d)

Contractor's profit @ 0.1 on (a+b+c)

#VALUE!

Rate per metre (a+b+c+d)

#VALUE!
say

Page 24 of 394

#VALUE!

Note

14.10

1. In case of viaducts in urban areas, the drainage spouts


should be connected with suitably located pipelines to
discharge the surface run-off to drains provided at ground
level.
2. In case of bridges, sufficient length of G.I Pipe shall be
provided to ensure that there is no splashing of water from
the drainage spout on the structure.
PCC M15 Grade leveling course below approach slab
complete as per drawing and Technical specification

2700

Unit = 1 cum
Taking output = 1 cum
Material
Concrete, Rate as per item No. 12.8 (A) excluding
formworks
Rate per cum
14.11

1500,16
00,1700
& 2704

cum

1.00

5597.00

5597.00

say

5597.00

Item 12.8
(A)

Reinforced cement concrete approach slab including


reinforcement and formwork complete as per drawing
and Technical specification
Unit = 1 cum
Taking output = 1 cum
a)

Material
Cement concreteM30 Grade Refer relevant item of
concrete in item 12.8(G)by using batching plant,
excluding formwork i.e. per cum basic cost (a+b+c)
(Excluding OH & CP)

cum

1.00

#VALUE!

( Refer relevant item of concrete in item No. 13.8 (G)


except that form work may be added at the rate of 2
per cent of cost against 3.5 per cent provided in the
foundation concrete.

b)

HYSD bar reinforcement Rate as per item No


14.2(Excluding OH & CP)
Overhead charges @ 0.2 on (a)

c)

Contractor's profit @ 0.1 on(a+b)

#VALUE!

tonne

0.05

60214.00

14.12

1600

3010.70 Item 14.2 A


#VALUE!
#VALUE!

Rate per cum (a+b+c)


Note

#VALUE! Item 12.8


(G)

#VALUE!
say

#VALUE!

The grade of reinforced cement concrete may be adopted as


M30 for severe conditions and M25 for moderate conditions.
Providing anti-corrosive treatment to HYSD
reinforcement with Fusion Bonded Epoxy Coating
(FBEC)
Unit = 1 MT
Taking output = 1 MT
To be taken as per the prevailing market rates.

Note

14.13

1800 &
2300

Contractors generally do not have expertise for this item .


The job is therefore, got done from specialised firms who
have the expertise in the field of construction chemicals. The
prevailing rate in the market is required to be ascertained
from the market and added in the cost estimate. Detailed
guidelines in this regard have been issued by MoRTH vide
their circular no. RW/NH-34041/44/91-S&R dated 21.3.2000.
Precast - pretensioned Girders
Providing, precasting, transportation and placing in
position precast pretensioned concrete girders as per
drawing and technical specifications
Unit = 1 cum
Taking output = 1 cum
Grade of concrete - M40
a)

Material
Cement

tonne

0.47

5940.00

2791.80

M-081

Coarse sand

cum

0.45

2400.00

1080.00

M-004

20 mm Aggregate

cum

0.54

942.00

508.68

M-053

10 mm Aggregate

cum

0.36

1063.00

382.68

M-051

Admixture @ 0.4 per cent of cement

Kg

1.88

input

#VALUE!

M-180

Page 25 of 394

HYSD steel .

tonne

0.10

52100.00

5210.00

M-082

HT strand with 5 per cent as wastage and extra length


for anchoring
LDO for steam curing

tonne

0.06

input

#VALUE!

M-119

Litre

37.00

input

#VALUE!

M-122

Add consumables such as binding wire, foam, packing


tape, shuttering oil, HDPE pipe for unbonding of
strand, bolt & nuts etc @ 1 per cent of material cost
b)

#VALUE!

Labour

(i) Cutting, bending, making reinforcement cage, placing


in position, binding etc. complete
Taking quantity of steel 100 Kg/cum of concrete
including laps and wastage
Mate

day

0.06

673.00

40.38

L-12

Mazdoor (Skilled)

day

0.35

408.00

142.80

L-15

Mazdoor

day

1.40

377.00

527.80

L-13

Mate

day

0.02

673.00

13.46

L-12

Mazdoor (Skilled)

day

0.14

408.00

57.12

L-15

Mazdoor

day

0.50

377.00

188.50

L-13

Mate

day

0.12

673.00

80.76

L-12

Mazdoor (Skilled)

day

1.00

408.00

408.00

L-15

Mazdoor

day

2.00

377.00

754.00

L-13

(ii) Cable cutting and threading in position including


binding by insulation tape with HDPE pipes etc.,
prestessing and cutting of extra length of HT strand
after de-stressing.
Taking quantity of HT strand 60 Kg/cum

(iii) Erection and dismantling of shuttering


Taking shuttering area 10 sqm/cum of concrete

(iv) Concreting by Batching plant and stationary


concrete pump
Mate

day

0.03

673.00

20.19

L-12

Mazdoor (Skilled)

day

0.05

408.00

20.40

L-15

Mazdoor

day

0.60

377.00

226.20

L-13

Mate

day

0.01

673.00

6.73

L-12

Mazdoor

day

0.35

377.00

131.95

L-13

day

0.01

673.00

6.73

L-12

day

0.25

377.00

94.25

L-13

Mate

day

0.01

673.00

6.73

L-12

Mazdoor (Skilled)

day

0.06

408.00

24.48

L-15

Mazdoor

day

0.24

377.00

90.48

L-13

Generator 100 KVA

hour

0.05

654.00

32.70

P&M-080

Batching Plant @ 20 cum/hour

hour

0.05

2094.00

104.70

P&M-002

Transit Mixer 4 cum capacity

hour

0.10

873.00

87.30

P&M-049

Concrete Pump stationary

hour

0.05

240.00

12.00

P&M-007

Crane 35 tonne capacity

hour

0.10

800.00

80.00

P&M-012

Trailor 30 tonne capacity

hour

0.10

input

Loader

hour

0.05

756.00

(v) Steam curing and manual curing

(vi) Handling of precast girder, stacking in stockyard


and again loading in trailor
Mate
Mazdoor
(vii) Placement of girders in position over pier caps
including placement of sand jacks, channel, levelling
etc.

c)

Machinery

i) At casting yard

#VALUE! P&M-089
37.80

P&M-017

ii) For transportation and placement at site


Crane 35 tonne capacity
Trailer 30 tonne capacity for transporting to site.

hour

0.15

800.00

120.00

P&M-012

tonne.km

2.5xL

input

#VALUE!

Lead =1
km & P&M090

hour

0.15

input

#VALUE! P&M-089

(L - Lead in Kilometer)
Trailor 30 tonne capacity during placement.
Page 26 of 394

#VALUE!

d)

Cost of formwork, steam curing arrangement,


pretensioning arrangement etc @ 5 per cent of cost
material, labour and machinery
Overhead charges @ 0.2 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!

#VALUE!

Rate per cum = (a+b+c+d+e)


14.14

1700 &
1800

#VALUE!
say

#VALUE!

Providing and fixing Helical pipes in voided concrete


slabs
Unit = 1 RM
Taking output = 1 RM
a)

Material
Helical pipes 600mm diameter

metre

1.00

input

#VALUE!

M-117

Tie rods 20mm diameter

each

1.00

input

#VALUE!

M-183

Consumables for sealing joints etc.@ 5 per cent of cost of


material
b) Labour

#VALUE!

Mate

day

0.01

673.00

6.73

L-12

Fitter

day

0.05

456.00

22.80

L-08

Mazdoor

day

0.20

377.00

75.40

L-13

c)

Overhead charges @ 0.2 on (a+b)

#VALUE!

d)

Contractor's profit @ 0.1 on (a+b+c)

#VALUE!

Rate per cum (a+b+c+d)

#VALUE!
say

14.15

800

#VALUE!

Crash Barriers
The rate analysis for rigid crash barrier in reinforced cement
concrete, semi-rigid crash barrier with metal beam and
flexible crash barrier with wire ropes have been made and
included in chapter-8 on Traffic and Transportation.

14.16

800

Painting on concrete surface


Providing and applying 2 coats of water based cement
paint to unplastered concrete surface after cleaning the
surface of dirt, dust, oil, grease, efflorescence and
applying paint @ of 1 litre for 2 sqm.
Unit = sqm
Taking output = 10 sqm
a)

Labour
Mate

day

0.01

673.00

6.73

L-12

Painter

day

0.25

396.00

99.00

L-18

Mazdoor (Skilled)

day

0.25

408.00

102.00

L-15

Litres

5.00

input

#VALUE!

M-190

b)

Material

c)

Water based paint of approved quality for cement


concrete surface
Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

#VALUE!
#VALUE!

Cost for 10 sqm (a+b+c+d)

#VALUE!

Rate per sqm (a+b+c+d)/10


14.17

2604

#VALUE!
say

#VALUE!

673.00

13.46

Burried Joint
Providing and laying a burried expansion joint,
expansion gap being 20 mm, covered with 12 mm thick,
200 mm wide galvanised weldable structural steel plate
as per IS: 2062, placed symmetrical to centre line of the
joint, resting freely over the top surface of the deck
concrete, welding of 8 mm dia. 100 mm long galvanised
nails spaced 300 mm c/c along the centre line of the
plate, all as specified in clause 2604.
Unit = Running meter
Taking output = 12 m
a)

Labour
Mate

day
Page 27 of 394

0.02

L-12

Mazdoor

day

0.40

377.00

150.80

L-13

Mazdoor (Skilled)

day

0.20

408.00

81.60

L-15

kg

237.50

57.96

13765.50

b)

Material

c)

Galvanised M.S plate 200 mm wide,12 mm thick @


94.20 kg/sqm including 5 per cent wastage
Add 1 per cent of cost of steel plate cutting, welding
consumables and galvanised nails.
Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

137.66
2829.80
1697.88

Cost for 12 m = (a+b+c+d)

18676.70

Rate per m = (a+b+c+d)/12

1556.39
say

Note

14.18

2605

M060/1000

1556.00

Guidelines laid down vide the MoRTH circular No. RW/NH34059/1/96-S&R dated 30.11.2000 and subsequent
corrigendum dated 25.01.2001 may be reffered for
expansion joints.
Filler joint

(i)

Providing & fixing 2 mm thick corrugated copper plate in


expansion joint complete as per drawing & Technical
Specification.
Unit = Running meter
Taking output = 12 m
a)

Labour

Cutting, bending, carrying & fixing etc.

b)

Mate

day

0.04

673.00

26.92

L-12

Mazdoor

day

0.50

377.00

188.50

L-13

Mazdoor (Skilled)

day

0.50

408.00

204.00

L-15

kg

55.00

522.00

28710.00

Material
Copper plate - 12m long x 250 mm wide

M-086

Area = 12 x 0.25 = 3 sqm


Weight = 3 x 0.002 x 8900 = 53.4 kg
Wastage @ 2.5 per cent = 1.33 kg/54.73 kg say = 55 kg.
c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

5825.88
3495.53

Cost for 12 m = (a+b+c+d)

38450.83

Rate per m = (a+b+c+d)/12

3204.24
say

14.18

(ii)

3204.00

Providing & fixing 20 mm thick compressible fibre board


in expansion joint complete as per drawing & Technical
Specification.
Unit = Running meter
Taking output = 12 m
a)

Labour

For carrying, placing & fixing.

b)

Mate

day

0.008

673.00

5.38

L-12

Mazdoor

day

0.10

377.00

37.70

L-13

Mazdoor (Skilled)

day

0.10

408.00

40.80

L-15

sqm

3.00

603.00

1809.00

Material

20 mm thick compressible fibre board 12 m long x 25


cm deep.
Area = 12 x 0.25 = 3 sqm
c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

378.58
227.15

Cost for 12 m = (a+b+c+d)

2498.61

Rate per m = (a+b+c+d)/12

208.22
say

14.18

(iii)

Providing and fixing in position 20 mm thick


premoulded joint filler in expansion joint for fixed ends
of simply supported spans not exceeding 10 m to cater
for a horizontal movement upto 20 mm, covered with
sealant complete as per drawing and technical
specifications.
Unit = Running meter
Page 28 of 394

208.00

M-084

Taking output = 12 m
a)

Labour
Mate

day

0.01

673.00

6.73

L-12

Mazdoor

day

0.20

377.00

75.40

L-13

Mazdoor (Skilled)

day

0.10

408.00

40.80

L-15

sqm

3.60

992.00

3571.20

b)

Material

c)

Premoulded joint filler 12 m long,20 mm thick and 300


mm deep.
Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

738.83
443.30

Cost for 12 m = (a+b+c+d)

4876.25

Rate per m = (a+b+c+d)/12

406.35
say

14.18

(iv)

M-141

406.00

Providing and filling joint sealing compound as per


drawings and technical specifications with coarse sand
and 6 per cent bitumen by weight
Unit = Running meter
Taking output = 12 m
12m long x 100 mm wide x 10mm deep recess
a)

b)

Labour
Mate

day

0.02

673.00

13.46

L-12

Mazdoor

day

0.50

377.00

188.50

L-13

Mazdoor (Skilled)

day

0.10

408.00

40.80

L-15

cum

0.012

2400.00

28.80

M-005

cum

0.001

41320.00

41.32

M-074

Material
Sand

Volume 12 x 0.1 x 0.01 = 0.012 cum


Weight 0.012 x 1400 = 16.8kg
Bitumen
16.8 x 0.06 = 1 kg
c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

62.58
37.55

Cost for 12 m = (a+b+c+d)

413.00

Rate per m = (a+b+c+d)/12

34.42
say

Note

34.00

For arriving at the final rate of filler joints per m


length and per cm depth of joint filling compound,
the rates at Sl. No. i), ii), iii) & iv) shall be added

14.19

2600

Asphaltic Plug joint


Providing and laying of asphaltic plug joint to provide
for horizontal movement of 25 mm and vertical
movement of 2 mm, depth of joint varying from 75 mm to
100 mm, width varying from 500 mm to 750 mm (in
traffic direction), covered with a closure plate of 200mm
x 6mm of weldable structural steel conforming to IS:
2062, asphaltic plug to consist of polymer modified
bitumen binder, carefully selected single size aggregate
of 12.5 mm nominal size and a heat resistant foam
caulking/backer rod, all as per approved drawings and
specifications.

Unit = Running meter


Taking output = 12 m
a)

b)

Labour
Mate

day

0.052

673.00

35.00

L-12

Mazdoor

day

1.00

377.00

377.00

L-13

Mazdoor (Skilled)

day

0.30

408.00

122.40

L-15

Material
Crushed stone aggregate 12.5 mm nominal size

2.4

cum

0.75

928.00

696.00

M-052

Polymer modified bitumen

kg

77.50

42.68

3307.47

Galvanised structural steel plate 200 mm wide,6 mm


thick, 12 m long (2.4 sqm) @ 47.10 kg/sqm including 5
per cent wastage

kg

113.00

input

#VALUE!

M-078/
1000
M-103

Page 29 of 394

c)

Add 1 per cent for welding and foam caulking/backer


rod and other incidentals.
Machinery

#VALUE!

Mastic cooker 1 tonne capacity

hour

1.00

58.00

58.00

P&M-030

Smooth 3-wheeled steel roller 8-10 capacity

hour

0.50

432.00

216.00

P&M-044

d)

Overhead charges @ 0.2 on (a+b+c)

#VALUE!

e)

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!

Cost for 12 m asphalt plug joint = (a+b+c+d+e)

#VALUE!

Rate per m = (a+b+c+d+e)/12

#VALUE!
say

Note

14.20

2606

#VALUE!

The nominal size of aggregates shall be 12.5 mm for depth


of joint upto 75 mm and 20 mm for joints of depth more than
75 mm.
Elastomeric Slab Steel Expansion Joint
Providing and laying of an elastomeric slab steel
expansion joint, catering to right or skew (less than 20
deg., moderately curved with maximum horizontal
movement upto 50 mm, complete as per approved
drawings and standard specifications to be installed by
the manufacturer/supplier or their authorised
representative ensuring compliance to the
manufacturer's instructions for installation and clause
2606 of MoRTH specifications for road & bridge works.
Unit = Running meter
Taking output = 12 m
a)

b)

Labour
Mate

day

0.06

673.00

40.38

L-12

Mazdoor

day

1.00

377.00

377.00

L-13

Mazdoor (Skilled)

day

0.50

408.00

204.00

L-15

metre

12.00

input

#VALUE!

M-093

Material
Supply of elastomeric slab seal expansion joint
assembly manufactured by using chloroprene,
elastomer for elastomeric slab unit conforming to
clause 915.1 of IRC: 83 (part II), complete as per
approved drawings and standard specification
conforming to clause 2606 of MoRT&H Specification

#VALUE!

c)

Add 5 per cent of cost of material for anchorage


reinforcement, welding and other incidentals.
Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

#VALUE!

#VALUE!

Cost for 12 m = (a+b+c+d)

#VALUE!

Rate per m = (a+b+c+d)/12


14.21

2600

#VALUE!
say

#VALUE!

Compression Seal Joint


Providing and laying of compression seal joint
consisting of steel armoured nosing at two edges of the
joint gap suitably anchored to the deck concrete and a
preformed chloroprene elastomer or closed cell foam
joint sealer compressed and fixed into the joint gap with
special adhesive binder to cater for a horizontal
movement upto 40 mm and vertical movement of 3 mm.
Unit = Running meter
Taking output = 12 m
a)

b)

Labour
Mate

day

0.036

673.00

24.23

L-12

Mazdoor

day

0.60

377.00

226.20

L-13

Mazdoor (Skilled)

day

0.30

408.00

122.40

L-15

kg

446.00

input

#VALUE!

M-103

Material
1. Galvanised angle sections 100mm x 100mm of
12mm thickness weldable structural steel as per IS:
2062, 2 nos. of 12 m length each @ 17.7 kg/m and 5
per cent wastage.
Add 5 per cent of cost of above for structural steel for
anchorage, welding and other incidentals.
Page 30 of 394

#VALUE!

Preformed continuous chloroprene elastomer or closed


cell foam sealing element with high tear strength,
vulcanised in a single operation for the full length of a
joint to ensure water tightness.

metre

12.00

input

#VALUE!

c)

Add 1 per cent of cost of sealing element for lubricantcum-adhesive and other consumables.
Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

#VALUE!
#VALUE!

Rate per m = (a+b+c+d)/12

14.22

M-143

#VALUE!

Cost for 12 m = (a+b+c+d)

Note

#VALUE!

#VALUE!
say

#VALUE!

1. The installation shall be done by the manufacturer or his


authorised representative to the satisfaction of the Engineer.
2. The concreting for joining the expansion joint assembly
with the deck has not been included in this analysis as the
same is catered in the quantities of RCC deck.
3. The anchoring bars of the expansion joint assembly shall
be welded to the main reinforcement of the deck.
Strip Seal Expansion Joint

2607

Providing and laying of a strip seal expansion joint


catering to maximum horizontal movement upto 70 mm,
complete as per approved drawings and standard
specifications to be installed by the
manufacturer/supplier or their authorised representative
ensuring compliance to the manufacturer's instructions
for installation.
Unit = Running meter
Taking output = 12 m
a)

b)

Labour
Mate

day

0.05

673.00

33.65

L-12

Mazdoor

day

1.00

377.00

377.00

L-13

Mazdoor (Skilled)

day

0.25

408.00

102.00

L-15

metre

12.00

input

#VALUE!

M-178

Material
Supply of complete assembly of strip seal expansion
joint comprising of edge beams, anchorage, strip seal
element and complete accessories as per approved
specifications and drawings.

#VALUE!

c)

Add 5 per cent of cost of material for anchorage


reinforcement, welding and other incidentals.
Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

#VALUE!

#VALUE!

Cost for 12 m = (a+b+c+d)

#VALUE!

Rate per m = (a+b+c+d)/12

#VALUE!
say

Note

14.23

2600

#VALUE!

1. The installation shall be done by the manufacturer or his


authorised representative to the satisfaction of the Engineer.
2. The concreting for joining the expansion joint assembly
with the deck has not been included in this analysis as the
same is catered in the quantities of RCC deck.
Modular Strip / Box Seal Joint
Providing and laying of a modular strip Box seal
expansion joint including anchorage catering to a
horizontal movement beyond 70 mm and upto 140mm,
complete as per approved drawings and standard
specifications to be installed by the
manufacturer/supplier or their authorised representative
ensuring compliance to the manufacturer's instructions
for installation.
Unit = Running meter
Taking output = 12 m
a)

Labour
Mate

day

0.056

673.00

37.69

L-12

Mazdoor

day

1.00

377.00

377.00

L-13

Mazdoor (Skilled)

day

0.40

408.00

163.20

L-15

Page 31 of 394

b)

Material
Supply of a modular strip/box seal joint assembly
comprising of edge beams, central beam,2 modules
chloroprene seal, anchorage elements, support and
control system, all steel sections protected against
corrosion and installed by the manufacturer or his
authorised representative.

metre

12.00

input

c)

Overhead charges @ 0.2 on (a+b)

#VALUE!

d)

Contractor's profit @ 0.1 on (a+b+c)

#VALUE!

Cost for 12 m Modular strip/box seal joint = (a+b+c+d)

#VALUE!
say

14.24

M-127

#VALUE!

Rate per m = (a+b+c+d)/12


Note

#VALUE!

#VALUE!

1. The installation shall be done by the manufacturer or his


authorised representative to the satisfaction of the Engineer.
2. The concreting for joining the expansion joint assembly
with the deck has not been included in this analysis as the
same is catered in the quantities of RCC deck.
3. The anchoring bars of the expansion joint assembly shall
be welded to the main reinforcement of the deck.
Modular Strip / Box Seal Joint

2600

Providing and laying of a modular strip box seal


expansion joint catering to a horizontal movement
beyond 140mm and upto 210mm, complete as per
approved drawings and standard specifications to be
installed by the manufacturer/supplier or their
authorised representative ensuring compliance to the
manufacturer's instructions for installation.
Unit = Running meter
Taking output = 12 m
a)

b)

Labour
Mate

day

0.07

673.00

47.11

L-12

Mazdoor

day

1.25

377.00

471.25

L-13

Mazdoor (Skilled)

day

0.50

408.00

204.00

L-15

metre

12.00

input

#VALUE!

M-128

Material
Supply of a modular box/box seal joint assembly
containing 3 modules/cells and comprising of edge
beams, two central beams, chloroprene seal,
anchorage elements, support and control system, all
steel sections protected against corrosion and installed
by the manufacturer or his authorised representative.

c)

Overhead charges @ 0.2 on (a+b)

#VALUE!

d)

Contractor's profit @ 0.1 on (a+b+c)

#VALUE!

Cost for 12 m Modular strip/box seal joint = (a+b+c+d)

#VALUE!

Rate per m = (a+b+c+d)/12

#VALUE!
say

Note

1. The installation shall be done by the manufacturer or his


authorised representative to the satisfaction of the Engineer.
2. The concreting for joining the expansion joint assembly
with the deck has not been included in this analysis as the
same is catered in the quantities of RCC deck.
3. The anchoring bars of the expansion joint assembly shall
be welded to the main reinforcement of the deck.

Page 32 of 394

#VALUE!

CHAPTER - 15
RIVER TRAINING AND PROTECTION WORKS
Sr No

Ref. to
MoRTH
Spec.

15.1

2503

Description

Unit

*
Note
2503

Remarks/
Input ref.

*
Note

cum
cum

1.00
0.20

240.00
175.00

240.00
35.00

M-003
M-008

day
day
day

0.04
0.35
0.75

673.00
500.00
377.00

L-12
L-11
L-13

say

26.92
175.00
282.75
151.93
91.16
1002.76
1003.00

Including excavation for trimming for preparation of bed.


Nominal excavation required for preparation of bed has been
taken into account while making provision for labour.
Boulder Apron Laid in Wire Crates
Providing and laying of boulder apron laid in wire crates
made with 4mm dia GI wire conforming to IS: 280 & IS:4826
in 100mm x 100mm mesh (weaved diagonally) including 10
per cent extra for laps and joints laid with stone boulders
weighing not less than 40 kg each.
Unit = cum
Taking output = 3 mx1.5mx1.25m = 5.63 cum
a) Material
4mm GI wire crates woven in mesh size of 100 mm x
100 mm.
Stone
Stone Spalls
b) Labour
Mate
Mazdoor (Skilled)
Mazdoor
c) Overhead charges @ 0.2 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Cost for 5.63 cum = a+b+c+d
Rate per cum = (a+b+c+d)/5.63

2503

Cost Rs

Boulder Laid Dry Without Wire Crates.


Unit = cum
Taking output = 1 cum
a) Material
Stone
Stone Spalls
b) Labour
Mate
Mason
Mazdoor *
c) Overhead charges @ 0.2 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Rate per cum = (a+b+c+d)

15.3

Rate Rs

Providing and laying boulders apron on river bed for


protection against scour with stone boulders weighing
not less than 40 kg each complete as per drawing and
Technical specification.
A

15.2

Quantity

sqm

22.00

input

#VALUE!

M-102

cum
cum

5.63
1.13

240.00
175.00

1351.20
197.75

M-003
M-008

day
day
day

0.18
1.50
*3.00

673.00
408.00
377.00

L-12
L-15
L-13

say

121.14
612.00
1131.0
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

5820.00

5820.00

Item 12.8
(A)

Including excavation for trimming for preparation of bed.


Readymade woven wire crate rolls have been considered in
the rate analysis. In case readymade rolls are not available,
GI wire 4mm dia. @ 32 kg per 10 sqm may be provided. In
that case 2 per cent of the cost of GI wire may be added for
weaving the wire crates.
Cement Concrete Blocks (size 0.5 x 0.5 x 0.5 m)
Providing and laying of apron with cement concrete blocks of
size 0.5x0.5x0.5 m cast in-situ and made with nominal mix of
M-15 grade cement concrete with a minimum cement
content of 250 kg/cum as per IRC: 21-2000.
Unit = cum
Taking out put = 1 cum
Concrete Grade M15 Rate as per item No. 12.8 (A)
including OH & CP
Add 2 per cent of cost to account for excavation for
preparation of bed, nominal surface reinforcement and
filling of granular material in recesses between blocks.

cum

1.00

116.40

Rate per cum


say

Page 1 of 394

5936.40
5936.00

Sr No

Ref. to
MoRTH
Spec.

15.4

2504

Description

Unit

Rate Rs

Cost Rs

Remarks/
Input ref.

Providing and laying Pitching on slopes laid over


prepared filter media including boulder apron laid dry in
front of toe of embankment complete as per drawing and
Technical specifications
A

Stone/Boulder
Unit = cum
Taking output = 1 cum
a) Material
Stone weighing not less than 40kg
Stone spalls of minimum 25 mm size
b) Labour
Mate
Mason
Mazdoor
c) Overhead charges @ 0.2 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Rate per cum = (a+b+c+d)

15.4

Quantity

cum
cum

1.00
0.20

240.00
175.00

240.00
35.00

M-003
M-008

day
day
day

0.04
0.35
0.75

673.00
500.00
377.00

L-12
L-11
L-13

say

26.92
175.00
282.75
151.93
91.16
1002.76
1003.00

5820.00

5820.00

Item 12.8
(A)

Cement Concrete Blocks of size 0.3x0.3 x0.3 m cast in


cement concrete of Grade M15
Unit = cum
Taking output = 1 cum
Concrete Grade M15 Rate as per item No. 12.8 (A)

cum

1.00

Add 2 per cent of cost to account for nominal surface


reinforcement and filling of granular material in
recesses between blocks.
Rate per cum
15.5

2504

116.40

5936.40
say

5936.00

870.00

M-012

Providing and laying Filter material underneath pitching


in slopes complete as per drawing and Technical
specification
Unit = cum
Taking output = 1 cum
a)

Material
Graded stone aggregate of required size

b)

cum

1.20

725.00

Mate

day

0.05

673.00

33.65

L-12

Mazdoor (Skilled)

day

0.25

408.00

102.00

L-15

Mazdoor *

day

1.00

377.00

377.00

L-13

Labour

c)

Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

276.53
165.92

Rate per cum = (a+b+c+d)

1825.10
say

15.6

700 &
2504

1825.00

Includes Mazdoor required for trimming of slope to proper


profile and preparation of bed.
Geotextile Filter
Laying of a geotextile filter between pitching and
embankment slopes on which pitching is laid to prevent
escape of the embankment material through the voids of the
stone pitching/cement concrete blocks as well as to allow
free movement of water without creating any uplift head on
the pitching.
Unit = sqm
Taking output = 10 sqm.
a)

Labour
Mate

day

0.02

673.00

13.46

L-12

Mazdoor

day

0.30

377.00

113.10

L-13

Mazdoor (Skilled)

day

0.10

408.00

40.80

L-15

sqm

11.00

404.00

4444.00

b)

Material

c)

Permeable synthetic geotextile including 5 per cent for


overlap and wastage
Overhead charges @ 0.2 on (a+b)
Page 2 of 394

922.27

M-181

Sr No

Ref. to
MoRTH
Spec.

Description
d)

Unit

Quantity

Rate Rs

Cost Rs

Contractor's profit @ 0.1 on (a+b+c)

553.36

Cost for 10 sqm = a+b+c+d

6087.00

Rate per sqm = (a+b+c+d)/10


15.7

2504.4

Remarks/
Input ref.

608.70
say

609.00

Toe protection
A toe wall for toe protection can either be in dry rubble
masonry in case of dry rubble pitching or pitching with
stones in wire crates or it can be in PCC M15 nominal mix if
cement concert block have been used for pitching . Rates for
toe wall can be adopted from respective clauses depending
upon approved design. The rate for excavation for
foundation, dry rubble masonry and PCC M15 have been
analysed and given in respective chapters.

15.8

2505

Providing and laying Flooring complete as per drawing


and Technical specifications laid over cement concert
bedding.
Rubble stone laid in cement mortar 1:3
Unit = cum
Taking output = 1 cum
a) Cement mortor 1:3 (Rate as in Item 12.6 sub-analysis)
excluding OH & CP
b) Add for cement concrete bedding (M15 Nominal
mix) vide Item 12.8 (A) excluding OH & CP . Quantity
shall be adopted as per design ( Assume Rubble stone
Flooring thickness 300mm and cement concrete
bedding thickness 100mm)

c)

d)

cum

0.33

5916.00

1952.28

cum

0.33

4240.00

1399.20

Add 1 per cent of cost to account for excavation for


preparation of bed.
Material

33.51

Stone

cum

1.00

240.00

240.00

M-003

Stone Spalls

cum

0.20

175.00

35.00

M-008

Mate

day

0.08

673.00

53.84

L-12

Mason

day

0.50

500.00

250.00

L-11

Mazdoor (for laying stones, filling of quarry spalls)

day

1.50

377.00

565.50

L-13

Labour

e)

Overhead charges @ 0.2 on (a+c+d)

f)

Contractor's profit @ 0.1 on (a+c+d+e)

619.32
371.59

Rate per cum = (a+b+c+d+e+f)

15.8

5520.25

Includes cement mortar for laying and filling of joints.

Cement Concrete blocks Grade M15


Concrete Grade M15 block. (Rate as per item No. 12.8
(A) including OH & CP.
Add for cement concrete bedding (M15 Nominal mix)
vide Item 12.8 (A) including OH & CP. Quantity shall be
adopted as per design ( Assume Cement Concrete
blocks thickness 300mm and cement concrete bedding
thickness 100mm)

say

5520.00

cum

1.00

5820.00

5820.00

cum

0.33

5820.00

1920.60

Add 1 per cent of cost to account for excavation for


preparation of bed.
Rate per cum
15.9

2506

Item 12.6
(A)
Item 12.8
(A)

Item 12.8
(A)
Item 12.8
(A)

77.41
7818.01
say

7818.00

Dry Rubble Flooring


Construction of dry rubble flooring at cross drainage works
for relatively less important works.
Unit = cum
Taking output = 1 cum
a)

b)

Material
Stone

cum

1.00

240.00

240.00

M-003

Stone Spalls

cum

0.20

175.00

35.00

M-008

Labour
Page 3 of 394

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Mate

day

0.10

673.00

67.30

Mason

day

0.50

500.00

250.00

L-11

mazdoor

day

1.50

377.00

565.50

L-13

c)

Add 1 per cent of (b) for trimming and preparation of


base.
Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

2507.2
A

L-12

8.83
233.33
140.00

Rate per cum = (a+b+c+d)


15.10

Remarks/
Input ref.

1539.95
say

1540.00

5568.00

5568.00

say

5568.00

5820.00

5820.00

say

5820.00

Curtain wall complete as per drawing and Technical


specification
Stone masonry in cement mortar (1:3)
Coursed rubble masonry (1st sort)
Rate same as per item No. 12.7 (A)

cum

1.00

Item 12.7
(A )

including OH & CP

Rate per cum


or
15.10

Cement concrete Grade M15


Concrete Grade M15 Rate as per item No. 12.8 (A)
including OH & CP
Rate per cum

Note

15.11

2507.2

cum

1.00

Item 12.8
(A)

Other items like excavation for foundation, filling behind wall,


filter media, weep holes etc. shall be added separately as
per approved design.
Flexible Apron :Construction of flexible apron 1 m thick
comprising of loose stone boulders weighing not less
than 40 kg beyond curtain wall.
Unit = cum
Taking Output = 1 cum
a)

b)

Material
Stone

cum

1.00

240.00

240.00

M-003

Stone Spalls

cum

0.20

175.00

35.00

M-008

Mate

day

0.05

673.00

33.65

L-12

Mason

day

0.25

500.00

125.00

L-11

Mazdoor

day

1.00

377.00

377.00

L-13

Labour

c)

Add 1 per cent of cost of (a+b) for trimming and


preparation of bed.
Overhead charges @ 0.2 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

8.11
163.75
98.25

Rate per cum = (a+b+c+d)

1080.76
say

15.12

2503.3

1081.00

Gabian Structure for Retaining Earth


Providing and construction of a gabian structure for retaining
earth with segments of wire crates of size 7 m x 3 m x 0.6 m
each divided into 1.5 m compartments by cross netting,
made from 4 mm galvanised steel wire @ 32 kg per 10 sqm
having minimum tensile strength of 300 Mpa conforming to
IS:280 and galvanizing coating conforming to IS:4826,
woven into mesh with double twist, mesh size not exceeding
100 x 100 mm, filled with boulders with least dimension of
200 mm, all loose ends to be tied with 4 mm galvanised
steel wire
Unit = cum
Taking output = 7 x 3 x 0.6 = 12.60 cum
a)

b)

Labour
Mate

day

0.28

673.00

188.44

L-12

Mazdoor

day

5.00

377.00

1885.00

L-13

Mazdoor (Skilled)

day

2.00

408.00

816.00

L-15

Material

Page 4 of 394

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Galvanised steel wire crates of mesh size 100 mm x


100 mm woven with 4mm dia. GI wire in rolls of
required size.

sqm

61.00

input

#VALUE!

M-102

Stone boulders with least dimension of 200 mm

cum

12.60

240.00

3024.00

M-003

Stone spalls of minimum size 25 mm

cum

2.52

175.00

441.00

M-008

c)

Overhead charges @ 0.2 on (a+b)

#VALUE!

d)

Contractor's profit @ 0.1 on (a+b+c)

#VALUE!

Cost for 12.60 cum (a+b+c+d)

#VALUE!

Rate per cum (a+b+c+d)/12.60

#VALUE!
say

Note

15.13

Remarks/
Input ref.

#VALUE!

Readymade woven wire crate rolls have been considered in


the rate analysis. In case readymade rolls are not available,
GI wire 4mm dia. @ 32 kg per 10 sqm may be provided. In
that case 2 per cent of the cost of GI wire may be added for
weaving the wire crates.
Gabian Structure for Erosion Control, River Training
Works and Protection works
Providing and constructing gabian structures for erosion
control, river training works and protection works with wire
crates of size 2 m x 1 m x 0.3 m each divided into 1m
compartments by cross netting, made from 4 mm galvanised
steel wire @ 32 kg per 10 sqm having minimum tensile
strength of 300 Mpa conforming to IS:280 and galvanizing
coating conforming to IS:4826, woven into mesh with double
twist, mesh size not exceeding 100 mm x 100 mm, filled with
boulders with least dimension of 200 mm, all loose ends to
be securely tied with 4 mm galvanised steel wire.

2503.3

Unit = cum
Taking output = 2 x 1 x 0.3 x 10 Nos. = 6.00 cum
a)

b)

Labour
Mate

day

0.14

673.00

94.22

L-12

Mazdoor

day

2.50

377.00

942.50

L-13

Mazdoor (Skilled)

day

1.00

408.00

408.00

L-15

Galvanised steel wire crates of mesh size 100 mm x


100 mm woven with 4mm dia. GI wire in rolls of
required size to cover 6.00 cum.

sqm

65.00

input

#VALUE!

M-102

Stone boulders with least dimension of 200 mm

cum

6.00

240.00

1440.00

M-003

Stone spalls of minimum size 25 mm

cum

1.20

175.00

210.00

M-008

Material

c)

Overhead charges @ 0.2 on (a+b)

#VALUE!

d)

Contractor's profit @ 0.1 on (a+b+c)

#VALUE!

Cost for 6.00 cum (a+b+c+d)

#VALUE!

Rate per cum (a+b+c+d)/6.00

#VALUE!
say

Note

Readymade woven wire crate rolls have been considered in


the rate analysis. In case readymade rolls are not available,
GI wire 4mm dia. @ 32 kg per 10 sqm may be provided. In
that case 2 per cent of the cost of GI wire may be added for
weaving the wire crates.

Page 5 of 394

#VALUE!

CHAPTER-16
REPAIR AND REHABILITATION
Sr No

Ref. to
MoRTH
Spec.

16.1

2809

Description

Unit

2809

2807

Cost Rs

Remarks/
Input ref.

day
day

0.06
1.00

673.00
377.00

40.38
377.00

L-12
L-13

hour

1.00

300.00

300.00

P&M-001

hour

0.50

340.00

P&M-053

say

170.00
266.21
115.36
1268.95
126.90
127.00

Removal of existing asphaltic wearing coat comprising


of 50 mm thick asphaltic concert laid over 12 mm thick
mastic asphalt including disposal with all lift and lead
upto 1000 m.
Unit = Sq m
Taking output = 10 sqm
a) Labour
Mate
Mazdoor
b) Machinery
Air Compressor 250 cfm with pneumatic breaker.
Tractor-trolley.
c) Overhead charges @ 0.3 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Cost for 10 sqm = (a+d+c+d)
Rate per sqm = (a+b+c+d)/10

16.3

Rate Rs

Removal of existing cement concrete wearing coat


including its disposal complete as per Technical
Specification without causing any detrimental effect to
any part of the bridge structure and removal of
dismantled material with all lifts and lead upto 1000 m
Unit = Sq m ( Thickness 75 mm)
Taking output = 10 sqm
a) Labour
Mate
Mazdoor
b) Machinery
Air Compressor 250 cfm with pneumatic breaker/jack
hammer along with accessories.
Tractor-trolley.
c) Overhead charges @ 0.3 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Cost for 10 sqm = (a+d+c+d)
Rate per sqm = (a+b+c+d)/10

16.2

Quantity

day
day

0.03
0.75

673.00
377.00

20.19
282.75

L-12
L-13

hour
hour

0.75
0.40

300.00
340.00

P&M-001
P&M-053

say

225.00
136.00
199.18
86.31
949.43
94.94
95.00

95.04

Guniting concrete surface with cement mortar applied


with compressor after cleaning surface and spraying
with epoxy complete as per Technical Specification
Unit = Sq m
Taking output = 1 sqm
Assuming thickness 25 mm
a) Material
Cement
Graded sand
Wire mesh 50mm x 50mm size of 3mm wire
Epoxy
Accelerator compound for guniting @ 4 per cent of
weight of cement
Add 2 per cent of cost of material for miscellaneous
consumables like nozzles, wire brush, cotton waste
etc.
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Compressor with guniting equipment along with
accessories
d) Overhead charges @ 0.3 on (a+b+c)
e) Contractor's profit @ 0.1 on (a+b+c+d)
Rate per sqm = (a+b+c+d+e)

Page 1 of 394

kg

16.00

5.94

cum
kg
kg
kg

0.04
2.00
0.67
0.64

2400.00
52.00
input
input

M081/1000
96.00
M-005
104.00
M-192
#VALUE! M-095
#VALUE! M-180
#VALUE!

day
day
day

0.01
0.04
0.14

673.00
500.00
377.00

6.73
20.00
52.78

L-12
L-11
L-13

hour

0.10

300.00

30.00

P&M-076

say

#VALUE!
#VALUE!
#VALUE!
#VALUE!

Sr No

Ref. to
MoRTH
Spec.

16.4

2800

Description

Unit

Quantity

Rate Rs

Cost Rs

Providing and inserting nipples with approved fixing


compound after drilling holes for grouting as per
Technical
Specifications
including
subsequent
cutting/removal and sealing of the hole as necessary of
nipples after completion of grouting with Cement/Epoxy
Unit = Number
Taking output = 1 No.
a) Material
Nipples
Cement, fixing compound and consumables @ 15 per
cent of cost of nipple
b) Labour
Mate
Mazdoor (Skilled) labour for drilling
Mazdoor (Skilled) labour for fixing nipple and sealing
inlets
Mazdoor for cutting and removing of nipples

each

1.00

15.00

15.00
2.25

M-129

day
day
day

0.01
0.08
0.08

673.00
408.00
408.00

6.73
32.64
32.64

L-12
L-15
L-15

day

0.04

377.00

15.08

L-13

Add 10 per cent of labour cost for drilling holes etc


c)

Overhead charges @ 0.3 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

8.71
33.91
14.70

Rate per No. = (a+b+c+d)


16.5

Remarks/
Input ref.

161.66
say

162.00

5.94

6.53

Sealing of cracks/porous concrete by injection process


through nipples/Grouting complete as per Technical
Specification.

2806

Cement Grout
Unit = kg
Taking output = 1 kg
a)

Material
Cement including 10 per cent wastage

b)

c)

Admixtures (anti shrinkage compound)


cent of cost of cement
Labour

kg

1.10

@ 20 per

1.31

Mate

day

0.08

673.00

53.84

L-12

Mazdoor (Skilled)

day

0.10

408.00

40.80

L-15

Mazdoor

day

0.10

377.00

37.70

L-13

hour

0.10

input

#VALUE!

M-111

Machinery
Grout pump with agitator and accessories

d)

Overhead charges @ 0.3 on (a+b+c)

#VALUE!

e)

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!

Rate per kg = (a+b+c+d+e)


B

M081/1000

#VALUE!
say

#VALUE!

Cement Mortar (1:1) Grouting


Unit = kg
Taking output = 1 kg
a)

b)

c)

Material
Cement including 10 per cent wastage

kg

0.55

5.94

3.27

Sand including 10 per cent wastage

kg

0.55

1.60

0.88

Admixtures (anti shrinkage compound)


cent of cost of cement
Labour

@ 20 per

M081/1000
M005/1500

0.65

Mate

day

0.08

673.00

53.84

L-12

Mazdoor (Skilled)

day

0.10

408.00

40.80

L-15

Mazdoor

day

0.10

377.00

37.70

L-13

hour

0.10

input

#VALUE!

M-111

Machinery
Grout pump with agitator and accessories

d)

Overhead charges @ 0.3 on (a+b+c)

#VALUE!

e)

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!

Page 2 of 394

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Rate per kg = (a+b+c+d+e)

#VALUE!
say

16.6

Remarks/
Input ref.

#VALUE!

Patching of damaged concrete surface with polymer


concrete and curing compounds, initiator and promoter,
available in present formulations, to be applied as per
instructions of manufacturer and as approved by the
Engineer.

2800

Unit = sqm
Taking output = 10 sqm for an average thickness of
25mm.
a) Labour

b)

Mate

day

0.06

673.00

40.38

L-12

Mazdoor (Skilled)

day

0.75

408.00

306.00

L-15

Mazdoor

day

0.75

377.00

282.75

L-13

kg

315.00

input

#VALUE!

M-145

2.00

input

#VALUE!

M-111

Material
Pre-packed polymer concrete based on epoxy system
complete with curing compound, intiator and promoter
including 5 per cent wastage.

c)

Machinery
Grout pump with agitator and accessories

hour

d)

Overhead charges @ 0.3 on (a+b+c)

#VALUE!

e)

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!

Cost for 10 sqm = a+b+c+d+e

#VALUE!

Rate per sqm = (a+b+c+d+e)/10


Note

16.7

2803

#VALUE!
say

#VALUE!

This item is a proprietory item available in market as prepacked polymer concrete and is required to be applied as
per instructions of the manufacturer.
Sealing of crack / porous concrete with Epoxy Grout by
injection through nipples complete as per clause 2803.1.
Unit = kg
Taking output = 1 kg
a)

Material
Epoxy including 10 per cent wastage

b)

c)

kg

1.10

input

#VALUE!

Mate

day

0.08

673.00

53.84

L-12

Mazdoor (Skilled)

day

0.10

408.00

40.80

L-15

Mazdoor

day

0.10

377.00

37.70

L-13

hour

0.10

input

Machinery
Epoxy Injection gun

2804

#VALUE! P&M-078

d)

Overhead charges @ 0.3 on (a+b+c)

#VALUE!

e)

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!

Rate per kg = (a+b+c+d+e)


16.8

M-095

Labour

#VALUE!
say

#VALUE!

Applying epoxy mortar over leached, honey combed and


spalled concrete surface and exposed steel
reinforcement complete as per Technical Specification
Unit = sqm
Taking output = 10 sqm
Assume average 10mm thickness of epoxy mortar
a)

b)

Material
Epoxy resin-hardener mix for prime coat

kg

2.50

input

#VALUE!

M-098

Epoxy mortar

kg

2.20

input

#VALUE!

M-096

Epoxy resin -hardener mix for seal coat.

kg

2.00

input

#VALUE!

M-098

Add 3 per cent cost of material for other consumables


like acetone etc and to cover wastage.
Labour
Mate

#VALUE!

day

Page 3 of 394

0.04

673.00

26.92

L-12

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Mazdoor (Skilled)

day

0.50

408.00

204.00

L-15

Mazdoor

day

0.50

377.00

188.50

L-13

c)

Overhead charges @ 0.3 on (a+b)

#VALUE!

d)

Contractor's profit @ 0.1 on (a+b+c)

#VALUE!

Cost for 10 sqm = a+b+c+d

#VALUE!

Rate per sqm = (a+b+c+d)/10

#VALUE!
say

16.9

2807

Remarks/
Input ref.

#VALUE!

Removal of defective concrete, cleaning the surface


thoroughly, applying the shotcrete mixture mechanically
with compressed air under pressure, comprising of
cement, sand, coarse aggregates, water and quick
setting compound in the proportion as per clause
2807.1., sand and coarse aggregates conforming to IS:
383 and table 1 of IS: 9012 respectively, water cement
ratio ranging from 0.35 to 0.50, density of gunite not less
than 2000 kg/cum, strength not less than 25 Mpa and
workmanship conforming to clause 2807.6.
unit: sqm
Taking output = 10 sqm, 40 mm average thickness.
a) Labour

b)

c)

Mate

day

0.04

673.00

26.92

L-12

Mazdoor

day

0.50

377.00

188.50

L-13

Mazdoor (Skilled)

day

0.50

408.00

204.00

L-15

Air compressor 250 cfm

hour

1.00

300.00

300.00

P&M-001

Shotcreteing equipment

hour

1.00

300.00

300.00

P&M-076

water tanker 6 KL capacity

hour

0.02

233.00

4.66

P&M-060

120.00

5.94

712.80
360.00

M081/1000
M-005

Machinery

Material
Cement

kg

Sand

cum

0.15

2400.00

Coarse aggregate of size 4.75mm

cum

0.15

137.00

20.55

M-024

Quick setting compound

kg

2.50

input

#VALUE!

M-147

Water

KL

0.10

13.00

1.30

M-189

d)

Overhead charges @ 0.3 on (a+b+c)

#VALUE!

e)

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!

Cost for 10 sqm = a+b+c+d+e

#VALUE!

Rate per sqm = (a+b+c+d+e)/10

#VALUE!
say

16.10

2800

#VALUE!

Applying pre-packed cement based polymer mortar of


strength 45 Mpa at 28 days for replacement of spalled
concrete
Unit = sqm
Taking output = 10 sqm
Assumed thickness - 10 mm
a)

Material
Acrylic polymer bonding coat
pre-packed cement based polymer mortar of strength
45 Mpa at 28 days
Add 3 per cent of (a ) above for wastage.

b)

Litre

1.40

457.00

639.80

M-057

kg

12.00

input

#VALUE!

M-145

#VALUE!

Labour
Mate

day

0.04

673.00

26.92

L-12

Mazdoor (Skilled)

day

0.50

408.00

204.00

L-15

Mazdoor

day

0.50

377.00

188.50

L-13

c)

Overhead charges @ 0.3 on (a+b)

#VALUE!

d)

Contractor's profit @ 0.1 on (a+b+c)

#VALUE!

Cost for 10 sqm = a+b+c+d

#VALUE!

Rate per sqm = (a+b+c+d)/10

#VALUE!
say
Page 4 of 394

#VALUE!

Sr No

Ref. to
MoRTH
Spec.

16.11

2805

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Eproxy bonding of new concrete to old concrete


Unit = sqm
Taking output = 10 sqm
a)

Material

Epoxy resin with pot life not less than 60-90 minutes
and satisfying testing as per clause 2803.9
Add 3 per cent of (a ) above for wastage.
b)

kg

8.00

input

#VALUE!

Mate

day

0.04

673.00

26.92

L-12

Mazdoor (Skilled)

day

0.50

408.00

204.00

L-15

Mazdoor

day

0.50

377.00

188.50

L-13

c)

Overhead charges @ 0.3 on (a+b)

#VALUE!

d)

Contractor's profit @ 0.1 on (a+b+c)

#VALUE!
#VALUE!

Rate per sqm = (a+b+c+d)/10


2810

M-098

Labour

Cost for 10 sqm = a+b+c+d

16.12

#VALUE!

#VALUE!
say

#VALUE!

input

#VALUE!

M-119
M-114

Providing external prestressing with high tensile steel


wires/strands including drilling for passage of
prestessing steel, all accessories for stressing and
stressing operation and grouting complete as per
drawing and Technical Specification
Span assumed: 25 m
No. of cables: 4 no.
No. of anchorages : 8 no.
Unit = MT
Taking output = 1 MT
Assume 12.7mm dia. Strand in 12T13 system. Weight-9.42
kg/m of cable.
a) Material
HTS strand including 5 per cent wastage and extra
length for jacking
HDPE pipes 75mm dia including 5 per cent wastage
Cement for grouting

b)

tonne

1.05

metre

112.00

input

#VALUE!

kg

400.00

5.94

2376.00

input

M081/1000
#VALUE! M-187

Tube anchorage set complete with bearing plate,


permanent wedges etc
Epoxy

each

8.00

kg

6.00

input

#VALUE!

M-095

MS plates for deviator (where deviator blocks are not


provided)
Add 20 per cent cost of material for other materials
like lead sheet, sleeves, deviator fixtures etc.
Labour

tonne

2.10

44100.00

92610.00

M-179

#VALUE!

i) For making holes in the structure .


Mate

day

0.24

673.00

161.52

L-12

Mazdoor Semi-skilled)

day

3.00

377.00

1131.00

L-14

Mazdoor

day

3.00

377.00

1131.00

L-13

ii) For making and fixing anchorages for cables and


placement of cables .
Mate

day

0.44

673.00

296.12

L-12

Blacksmith

day

3.00

500.00

1500.00

L-02

Mazdoor

day

8.00

377.00

3016.00

L-13

Mate/Supervisor

day

0.13

673.00

87.49

L-12

Fitter

day

0.70

456.00

319.20

L-08

Mazdoor

day

2.65

377.00

999.05

L-13

Mate/Supervisor

day

0.13

673.00

87.49

L-12

Mason

day

0.70

500.00

350.00

L-11

Mazdoor

day

2.65

377.00

999.05

L-13

iii) For prestressing

iv) For grouting

c)

Machinery
Page 5 of 394

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Stressing jack with pump

hour

4.00

121.00

484.00

P&M-040

Grouting pump with agitator

hour

1.35

input

#VALUE!

M-111

d)

Overhead charges @ 0.3 on (a+b+c)

#VALUE!

e)

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!

Rate per MT = (a+b+c+d+e)


16.13

2810

Remarks/
Input ref.

#VALUE!
say

#VALUE!

Providing external prestressing with high tensile steel


wires/strands including drilling for passage of
prestessing steel, all accessories for stressing and
stressing operation and grouting complete as per
drawing and Technical Specification
Span assumed: 50 m
No. of cables: 4 no.
No. of anchorages : 8 no.
Unit = MT
Taking output = 3.10 MT
Assume 12.7mm dia. Strand in 19T13 system. Weight-14.73
kg/m of cable.
a) Material

b)

HTS strand including 5 per cent wastage and extra


length for jacking
HDPE pipes 90mm dia including 5 per cent wastage

tonne

3.10

input

#VALUE!

M-119

metre

224.00

input

#VALUE!

M-115

Cement for grouting

tonne

1.01

5940.00

5999.40

M-081

Tube anchorage set complete with bearing plate,


permanent wedges etc
Epoxy

each

8.00

input

#VALUE!

M-187

kg

10.00

input

#VALUE!

M-095

MS plates for deviator (where deviator blocks are not


provided)
Add 20 per cent cost of material for other materials
like lead sheet, sleeves, deviator fixtures etc.
Labour

tonne

7.00

44100.00

308700.00

M-179

#VALUE!

i) For making holes in the structure .


Mate

day

0.08

673.00

53.84

L-12

Mazdoor Semi-skilled)

day

8.00

377.00

3016.00

L-14

Mazdoor

day

8.00

377.00

3016.00

L-13

ii) For making and fixing anchorages for cables and


placement of cables .
Mate

day

1.28

673.00

861.44

L-12

Blacksmith

day

7.00

500.00

3500.00

L-02

Mazdoor

day

25.00

377.00

9425.00

L-13

Mate/Supervisor

day

0.20

673.00

134.60

L-12

Fitter

day

1.00

456.00

456.00

L-08

Mazdoor

day

4.00

377.00

1508.00

L-13

Mate/Supervisor

day

0.26

673.00

174.98

L-12

Mason

day

1.50

500.00

750.00

L-11

Mazdoor

day

5.00

377.00

1885.00

L-13

Stressing jack with pump

hour

7.00

121.00

847.00

P&M-040

Grouting pump with agitator

hour

3.00

input

#VALUE!

M-111

iii) For prestressing

iv) For grouting

c)

Machinery

d)

Overhead charges @ 0.3 on (a+b+c)

#VALUE!

e)

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!

Cost for 3.10 MT = a+b+c+d+e

#VALUE!

Rate per MT = (a+b+c+d+e)/3.10

#VALUE!
say

Page 6 of 394

#VALUE!

Sr No

Ref. to
MoRTH
Spec.

16.14

2810

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Providing external prestressing with high tensile steel


wires/strands including drilling for passage of
prestessing steel, all accessories for stressing and
stressing operation and grouting complete as per
drawing and Technical Specification
Span assumed: 100 m
No. of cables: 6 no.
No. of anchorages : 12 no.
Unit = MT
Taking output = 9.28 MT
Assume 12.7mm dia. Strand in 19T13 system. Weight-14.73
kg/m of cable.
a) Material

b)

HTS strand including 5 per cent wastage and extra


length for jacking
HDPE pipes 90 mm dia including 5 per cent wastage

tonne

9.28

input

#VALUE!

M-119

metre

672.00

input

#VALUE!

M-115

Cement for grouting

tonne

3.04

5940.00

18057.60

M-081

Tube anchorage set complete with bearing plate,


permanent wedges etc
Epoxy

each

12.00

input

#VALUE!

M-187

kg

14.00

input

#VALUE!

M-095

MS plates for deviator (where deviator blocks are not


provided)
Add 20 per cent cost of material for other materials
like lead sheet, sleeves, deviator fixtures etc.
Labour

tonne

20.00

44100.00

882000.00

M-179

#VALUE!

i) For making holes in the structure .


Mate

day

1.72

673.00

1157.56

L-12

Mazdoor Semi-skilled)

day

18.00

377.00

6786.00

L-14

Mazdoor

day

25.00

377.00

9425.00

L-13

ii) For making and fixing anchorages for cables and


placement of cables .
Mate

day

4.00

673.00

2692.00

L-12

Blacksmith

day

20.00

500.00

10000.00

L-02

Mazdoor

day

80.00

377.00

30160.00

L-13

Mate/Supervisor

day

0.30

673.00

201.90

L-12

Fitter

day

1.50

456.00

684.00

L-08

Mazdoor

day

6.00

377.00

2262.00

L-13

Mate/Supervisor

day

1.00

673.00

673.00

L-12

Mason

day

5.00

500.00

2500.00

L-11

Mazdoor

day

20.00

377.00

7540.00

L-13

Stressing jack with pump

hour

10.00

121.00

1210.00

P&M-040

Grouting pump with agitator

hour

10.00

input

#VALUE!

M-111

iii) For prestressing

iv) For grouting

c)

Machinery

d)

Overhead charges @ 0.3 on (a+b+c)

#VALUE!

e)

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!

Cost for 9.28 MT = a+b+c+d+e

#VALUE!

Rate per MT = (a+b+c+d+e)/9.28

#VALUE!
say

16.15

2808

#VALUE!

Replacement of Bearings complete as per Technical


Specification
Unit = No
Taking output = 3 No.
Lifting of superstructure span by jacking up from below i.e.
by placing the jacks on pier/abutment caps for span length of
30m.
a)

Lifting of span
i) Hire charges for jack of 40 tonne lifting capacity.

Day

3.00

input

Mate

day

0.64

673.00

Page 7 of 394

#VALUE! P&M-084
430.72

L-12

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Mazdoor (Skilled)

day

4.00

408.00

1632.00

Mazdoor

day

12.00

377.00

4524.00

L-13

v) Wooden packing

cum

0.15

input

#VALUE!

M-195

each

3.00

input

#VALUE!

M-065

b)

Replacement of bearing

c)

Overhead charges @ 0.3 on (a+b)

#VALUE!

d)

Contractor's profit @ 0.1 on (a+b+c)

#VALUE!

Cost of bearing.

Cost of repair of 3 bearings = a+b+c+d

#VALUE!
say

16.16

L-15

#VALUE!

Rate of repair per bearing = (a+b+c+d)/3


Note

Remarks/
Input ref.

#VALUE!

The work entails replacement of all the bearings on one side


of the span.
Rectification of Bearings as per Technical Specifications

2808

Unit = 1 No
Taking output = 3 No.
a)
Lifting of superstructure span by jacking up from
below i.e. by placing the jacks on pier/abutment caps for
span length of 30m.
i) Hire charges for jack of 40 tonne lifting capacity.

each

3.00

input

ii) Mate

day

0.64

673.00

430.72

L-12

iii) Mazdoor (Skilled)

day

4.00

408.00

1632.00

L-15

iv) Mazdoor

day

12.00

377.00

4524.00

L-13

v) Wooden packing

cum

0.15

input

#VALUE!

M-195

b)

Cost of parts to be replaced for 3 bearings.

each

3.00

input

#VALUE!

M-064

c)

Overhead charges @ 0.3 on (a+b)

#VALUE!

d)

Contractor's profit @ 0.1 on (a+b+c)

#VALUE!

Cost of repair of 3 bearings = a+b+c+d

#VALUE!

Rate of repair per bearing = (a+b+c+d)/3


Note
16.17

#VALUE! P&M-084

#VALUE!
say

#VALUE!

The rectification of 3 bearings included in this analysis are


on the same side of the span.
Replacement of Expansion Joints complete as per
drawings
Unit -1 RM
Taking output = 12 RM
a)

Material

b)

Epoxy for bonding new concrete to old concrete @ 0.8


kg/sqm
M-30 grade cement concrete excluding OH & CP (Rate
as per items 14.1 C (i)
Labour

Removal of old expansion joint including breaking of


concrete, cutting of lugs and shifting of broken material etc.
Mate

kg

9.60

input

#VALUE!

M-095

cum

3.60

59776.00

215193.60

Item
14.1(C)

day

0.26

673.00

174.98

L-12

Mazdoor

day

6.00

377.00

2262.00

L-13

Mazdoor (Skilled)

day

0.50

408.00

204.00

L-15

c)

Overhead charges @ 0.3 on (a+b)

#VALUE!

d)

Contractor's profit @ 0.1 on (a+b+c)

#VALUE!
#VALUE!

Cost for replacement of 12 RM = a+b+c+d


Rate per RM = (a+b+c+d)/12

#VALUE!
say

Note

16.18

The rate for the installation of new expansion joints may be


taken from the chapter on superstructure. Broken concrete
will have to be replaced which has been included in this
analysis.
Replacement of Damaged Concrete Railing.
Unit = RM
Taking output = 10 RM
a)

Labour
Page 8 of 394

#VALUE!

Sr No

Ref. to
MoRTH
Spec.

Unit

Labour for dismantling old railing and disposal of dismantled


material.
Mate

day

0.20

673.00

134.60

L-12

day

5.00

377.00

1885.00

L-13

hour

1.00

340.00

340.00

P&M-053

Mazdoor
b)

Quantity

Rate Rs

Cost Rs

Machinery
Tractor-trolley for disposal of dismantled material

c)

Overhead charges @ 0.3 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

707.88
306.75

Cost for 10 m = a+b+c+d

3374.23

Rate per metre = (a+b+c+d)/10

337.42
say

Note
16.19

Remarks/
Input ref.

Description

337.00

The rate for the provision of new railing may be adopted


from the chapter on superstructure.
Replacement of Crash Barrier.
Unit = RM
Taking output = 10 M
a)

Labour

Labour for dismantling old railing and disposal of dismantled


material.
Mate
Mazdoor
b)

day

0.40

673.00

269.20

L-12

day

10.00

377.00

3770.00

L-13

hour

1.00

340.00

340.00

P&M-053

Machinery
Tractor-trolley for disposal of dismantled material

c)

Overhead charges @ 0.3 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

1313.76
569.30

Cost for 10 m = a+b+c+d

6262.26

Rate per metre = (a+b+c+d)/10

626.23
say

Note
16.20

626.00

The rate for the construction of new crash barrier may be


adopted from chapter 8 on Traffic and Transportation.
Replacement of Damaged Mild Steel Railing
Unit = RM
Taking output = 10 M
a)

Labour

Labour for dismantling old railing and disposal of dismantled


material.
Mate
Mazdoor
b)

day

0.16

673.00

107.68

L-12

day

4.00

377.00

1508.00

L-13

hour

1.00

340.00

340.00

P&M-053

Machinery
Tractor-trolley for disposal of dismantled material

c)

Overhead charges @ 0.3 on (a+b)

586.70

d)

Contractor's profit @ 0.1 on (a+b+c)

254.24

Cost for 10 m = a+b+c+d

2796.62

Rate per metre = (a+b+c+d)/10

279.66
say

16.21

280.00

Repair of Crash Barrier


Repair of concrete crash barrier with cement concert of M-30
grade by cutting and trimming the damaged portion to a
regular shape, cleaning the area to be repaired thoroughly,
applying cement concert after erection of proper form work.
Unit = Running meter.
Taking output = 10 M.
It is assumed that damage is to the extent of 10 per cent of
the volume of concrete .This will require 0.30 cum of
concrete.
a)

Manpower*
Mate

day

0.04

673.00

26.92

L-12

Mazdoor

day

1.00

377.00

377.00

L-13

Page 9 of 394

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

* For dismantling and trimming the surface to a regular shape


and removal of damaged material.
b) Material
M-30 grade cement concrete excluding OH & CP (Rate
as per items 14.1 C (i)
This may be priced based on the rate given the chapter of
superstructure.
c) Overhead charges @ 0.3 on (a)
d)

cum

0.30

59776.00

Item
14.1(C)

121.18

Contractor's profit @ 0.1 on (a+c)

52.51

Cost for 10 m = a+b+c+d

18510.41

Rate per m = (a+b+c+d)/10


16.22

17932.80

1851.04
say

1851.00

5977.60

Repair of RCC Railing


Carrying out repair of RCC M30 railing to bring it to the
original shape.
Unit = Running meter.
Taking output = 10 M.
It is assumed that damage is to the extent of 10 per cent .
a)

Material

b)

M-30 grade cement concrete excluding OH & CP (Rate


as per items 14.1 C (i)
HYSD bar reinforcement Rate as per item No
14.2(Excluding OH & CP)
Labour*

cum

0.10

59776.00

tonne

0.01

60214.00

Mate

day

0.016

673.00

10.77

L-12

mazdoor

day

0.20

377.00

75.40

L-13

* For dismantling and trimming the surface to a regular shape


and removal of damaged material.
c) Overhead charges @ 0.3 on (b)
d)

25.85

Contractor's profit @ 0.1 on (b+c)

11.20

Cost for 10 m = a+b+c+d

6883.60

Rate per m = (a+b+c+d)/10


16.23

Item
14.1(C)
782.78 Item 14.2 A

688.36
say

688.00

Repair of Steel Railing


Repair of steel railing to bring it to the original shape
It is assumed that the damage to the steel railing is to the
extent of 10 per cent .
Unit = Running meter.
Taking output = 10 M.
a)

Material
Mild steel ISMC series

kg

29.00

44.10

1278.90

Flat iron

kg

10.00

44.10

441.00

MS Bolt and nuts

kg

1.00

81.00

81.00

Add 5 per cent of cost of material for painting.


b)

M179/1000
M179/1000
M-130

90.05

Labour
Mate

day

0.016

673.00

10.77

L-12

Mazdoor (Skilled)

day

0.20

408.00

81.60

L-15

Mazdoor

day

0.20

377.00

75.40

L-13

c)

Overhead charges @ 0.3 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

617.61
267.63

Cost of repair for10m = a+b+c+d

2943.96

Cost of meter = (a+b+c+d)/10

294.40
say

Page 10 of 394

294.00

Materials
Sl.
No.

Description

Unit

Rate
Arrived

Rate as per KSOR


Rate

Item No

Item

M-001 Stone Boulder of size 150 mm and below at Cruser Plant

cum

210

210

32 of PartII

Latrite rough stone 150mm

M-002 Supply of quarried stone 150 - 200 mm size for Hand Broken at site

cum

240

240

33 of PartII

Laterite boulders

M-003 Boulder with minimum size of 300 mm for Pitching at Site

cum

240

240

33 of PartII

Laterite boulders

M-004 Coarse sand at Mixing Plant

cum

2400

2400

62 of PartII

River sand

M-005 Coarse sand at Site

cum

2400

2400

62 of PartII

River sand

M-006 Fine sand at Site

cum

616

616

64 of part II

Sand for filling

M-007 Moorum at Site

cum

450

450

61 of partII

Cut gravel

M-008 Gravel/Quarry spall at Site

Cum

175

175

60 of part II

Gravel (Silted Silicious)

M-009 Granular Material or hard murrum for GSB works at Site

Cum

190

190

60 of part II

Gravel (Silted Silicious

M-010 Granular Material or hard murrum for GSB works at Mixing Plant

Cum

190

190

60 of part II

Gravel (Silted Silicious

Cum

Nil

Nil

646

51 of part II

45mm Broken stone for


road works

875

45 of part II

22-24mm

40 of part II

11-12mm

73of part II

Quarry dust

M-011

Fly ash conforming to IS: 3812 ( Part II & I) atHMP Plant / Batching
Plant / Crushing Plant
Filter media/Filter Material as per Table 300-3 (MoRT&H Specification)

45 mm

3%

646

19.38

M-012 22.4

40%

875

350.00

11.2

30%

996

298.80

996

5.6 &2.8mm

27%

137

36.99

137

Cum

705.17

M-012
Sl.
No.

Description

Cum

705.17

Unit

Rate
Arrived

Rate as per KSOR


Rate

Item No
73of part II

Item
Quarry dust

619
713
1063
137

52 of part II
47 of part II
39 of part II
73 of part II

48mm
26-27mm
9mm-11mm
quarrydust

705.17
Close graded Granular sub-base Material 53 mm to 9.5 mm
56mm
26.5
9.5
4.75&2.36

123.80
178.25
M-013
318.90
34.25
655.20
Close graded Granular sub-base Material 37.5 mm to 9.5 mm
M-014 26.5mm
9.5mm

20%
25%
30%
25%

40%
60%

619
713
1063
137

713
1063

285.2
637.8
923

cum

655.20

cum

923

713
1063

47 of part II
39 of part II

26-27mm
9mm-11mm

cum

923

713

47 of part II

26-27mm

1063

39 of part II

9mm-11mm

Close graded Granular sub-base Material 26.5 mm to 9.5 mm


M-015 26.5mm
9.5mm

40%

713

60%

1063

285.2

637.8
923
Close graded Granular sub-base Material 9.5 mm to 4.75 mm
M-016

9.5
4.75

60%
40%

1063
137

637.8
54.8
692.6

cum

692.6

1063
137

39 of part II
73 of part II

9mm-11mm
quarrydust

cum

692.6

1063

39 of part II

9mm-11mm

73 of part II

quarrydust

73 of part II

quarrydust

Close graded Granular sub-base Material 9.5 mm to 2.36 mm


M-017

9.5mm

60%

1063

4.75&2.36

40%

137

4.75&2.36

100%

137

637.8

54.8
692.6
Close graded Granular sub-base Material 4.75mm to 2.36 mm
M-018

137

137
cum

137

137

Sl.
No.

Description

Unit

Rate
Arrived

Close graded Granular sub-base Material 4.75mm to 75 micron mm


M-019

Rate as per KSOR


Rate

Item No

Item

cum

137

137

73 of part II

quarrydust

cum

137

137

73 of part II

quarrydust

4.75&Msand 100%
137
137
Close graded Granular sub-base Material 2.36 mm
M-020

M Sand

100%

137

137

M-021

Stone crusher dust finer than 3mm with not more than 10% passing
0.075 sieve.Quarry dust- 100%

cum

137

137

73 of part II

quarrydust

M-022

Coarse graded Granular sub-base Material 2.36 mm & below


Msand - 100%

cum

137

137

73 of part II

quarrydust

Coarse graded Granular sub-base Material 4.75mm to 75 micron


M-023 4.75mm -30 %& Msand -70 %

cum

137

137

73 of part II

quarrydust

Coarse graded Granular sub-base Material 4.75 mm to 2.36 mm


M-024 4.75mm- 30 % & Msand -70 %

cum

137

137

73 of part II

quarrydust

Coarse graded Granular sub-base Material 9.5 mm to 4.75 mm


M-025 4.75mm- 30 % & Msand -70 %

cum

137

137

73 of part II

quarrydust

cum

511.4

713

47of part II

26-27mm

980

137

73 of part II

quarrydust

800

Coarse graded Granular sub-base Material 26.5 mm to 4.75 mm


M-026

26.5mm

65%

713

463.45

4.75mm

35%

137

47.95
511.4

Sl.
No.

Description

Unit

Rate
Arrived

Rate as per KSOR


Rate

Item No

Item

M-027

Coarse graded Granular sub-base Material 26.5 mm to 9.5 mm


26.5mm - 100 %

cum

713

713

47of part II

26-27mm

M-028

Coarse graded Granular sub-base Material 37.5 mm to 9.5 mm


26.5mm -100%

cum

713

713

47of part II

26-27mm

M-029

Coarse graded Granular sub-base Material 53 mm to 26 .5mm


26.5mm -100%

cum

713

713

47of part II

26-27mm

700

38of part II

6-7mm

950

2314

(63)of part II

Msand

2150

875

45of part II

22-24mm

1170

996

40of part II

11-12mm

1350

137

73of part II

Quarry dust

800

928

41of part II

13-14mm

700
137

38of part II
73of part II

6-7mm
Quarry dust

Aggregates below 5.6 mm

M-030

5.6mm

50%

700

350

Msand

50%

2314

1157

cum

1507

1507
Aggregates 22.4 mm to 2.36 mm
(a) Wet Mix Macadam 22.4mm

35%

875

306.25

11.2mm

30%

996

298.8

4.75mm &
2.36mm

35%

137

47.95

cum

653

653
Aggregates 22.4 mm to 2.36 mm
(b) Bituminous Penetration Macadam -

M-031

22.4mm

0%

13.2mm

40%

928

371.2

5.6mm
2.8mm

40%
20%

700
137

280
27.4
678.6

cum

678.6

M-031
Sl.
No.

Description

Unit

Rate
Arrived

Aggregates 22.4 mm to 2.36 mm


(c) Built up Spray Grout
22.4mm

M032

M033

Item

757.7

928

41of part II

13-14mm

1300

50%

928

464

5.6mm

40%

700

280

700

38of part II

6-7mm

950

2.8mm

10%

137

13.7
757.7

137

73of part II

Quarry dust

800

Aggregates 22.4 mm to 5.6 mm


4.75mm - 100%
Aggregates 45 mm to 2.8 mm
45mm
26.5mm
13.2mm
2.8mm

0%
50%
45%
5%

713
928
2777

45mm
22.4mm

5%
95%

646
875

cum

137

137

73of part II

Quarry dust

356.5
417.6
138.85
912.95

cum

912.95

713
928
2777

47of part II
41of part II
62of part II

26-27
13-14
Riversand

32.3
831.25
863.55

cum

863.55

646
875

51of part II
45of part II

45mm
22-24

713

713

47of part II

26-27mm

713

47of part II

26-27mm

980

928

41of part II

13-14mm

1300

2314

(63)of part II

Msand

2150

619

52of part II

48mm

53mm
26.5mm

0%
45%

713

320.85

13.2mm

50%

928

464

2.8mm

5%

2314

115.7
900.55

Aggregates 53 mm to 22.4 mm
M-035

Item No

13.2mm

(b) Crusher Run Maccadam Base


26.5mm -100%
Aggregates 53 mm to 2.8 mm

M-035

Rate

0%

Aggregates 45 mm to 22.4 mm
(a)Wet Mix Macadam

M-034

Rate as per KSOR

53mm

5%

619

30.95

cum

cum

900.55

793.5

895
1170

Sl.
No.
M-035

Description
45mm
22.4mm

30%
65%

646
875

193.8
568.75
793.5

Unit

Rate
Arrived

cum

793.5

cum

1010.7

Rate as per KSOR


Rate
646
875

Item No
51of part II
45of part II

Item
45mm
22-24mm

646

51of part II

45mm

875

45of part II

22-24mm

2314

63of part II

Msand

511

56of part II

63mm-65mm

572

54of part II

53mm

Aggregates 63 mm to 2.8 mm

M-037

63mm

0%

45mm

35%

646

226.1

22.4mm

50%

875

437.5

2.8mm

15%

2314

347.1
1010.7

Aggregates 63 mm to 45 mm

M-038

63mm

10%

511

51.1

53mm

45%

572

257.4

45mm

45%

646

290.7
599.2

646

51of part II

45mm

40.4
314.6
226.1
581.1

59of part II
54of part II
51of part II

90mm
53mm
45mm

Aggregates 90 mm to 45 mm
M-039

M-040

90mm
53mm
45mm-

10%
55%
35%

599.2

cum

581.1

404
572
646

Aggregates 10 mm to 5 mm
(a) Bituminous Macadam
5.6 -100%

cum

700

700

38of part II

6-7mm

(b) Dense graded Bituminous Macadam


4.75 & 2.36 - 100%

cum

2314

2314

63of part II

Msand

( c) Semi Dense Bituminous Macadam Concrete


Grade I&II 5.6mm -100%

cum

700

700

38of part II

6-7mm

1063

1063

39 of part II

9mm

(d)Bituminous Concrete
9.5mm - 100%

404
572
646

cum

950

Sl.
No.

Description

Unit

Rate
Arrived

Aggregates 11.2 mm to 0.09 mm


M-041

11.2mm
5.6mm
2.8mm

0%
35%
65%

700
2314

Aggregates 13.2 mm to 0.09 mm

M-042

cum

1749.1

cum

1375.2

Rate

Item No

Item

700
2314

38of part II
63of part II

6-7mm
Msand

996

40of part II

11-12mm

700

38of part II

6-7mm

13.2mm

0%

11.2mm

10%

996

99.6

5.6mm

50%

700

350

2.8mm

40%

2314

925.6
1375.2

2314

63of part II

Msand

928
1063
996

41of part II
39 of part II
40of part II

13-14mm
9mm
11-12mm

700

38of part II

6-7mm

Aggregates 13.2 mm to 5.6 mm

M-043

245
1504.1
1749.1

Rate as per KSOR

13.2 mm
9.5mm
11.2mm

35%
20%
30%

928
1063
996

324.8
212.6
298.8

6-7mm

15%

700

105
941.2

cum

941.2

Aggregates 13.2 mm to 10 mm
(a)Semi Dense Bituminous Concrete
M-044

13.2mm
11.2mm

10%
90%

928
996

92.8
896.4
989.2

(b) Bituminous Concrete


9.5mm - 100%
Aggregates 20 mm to 10 mm
M-045

19mm

20%

875

175

9.5mm

80%

1063

850.4
1025.4

cum

989.2

928
996

41of part II
40of part II

13-14mm
11-12mm

cum

1063

1063

39 of part II

9mm

cum

1025.4

875

45of part II

22-24mm

1063

39 of part II

9mm

1350

Sl.
No.

Description

Unit

Rate
Arrived

Rate as per KSOR


Rate

Item No

Item

875

45of part II

22-23mm

1170

996

40of part II

11-12mm

1350

928

928

41of part II

13-14mm

cum

713

713

47of part II

26-27

cum

711

673

49 of part II

37.5mm

713

47of part II

26-27

Aggregates 25 mm to 10 mm
(a)Bituminous Macadam

M-046

22.4

25%

875

218.75

11.2mm

75%

996

747
965.75

cum

(b)Dense Graded Bituminous Macadam


13.2mm-100%
M-047 Aggregates 19 mm to 6 mm

cum

M-048 Aggregates 37.5 mm to 19 mm

cum

Aggregates 37.5 mm to 25 mm
(a) Bituminous Macadam
26.5mm- 100%

965.75

(b) Dense graded Bituminous Macadam


37.5mm-0%& 26.5mm-100%
M-049
37.5

5%

673

33.65

26.5

95%

713

677.35
711

M-050 Aggregates 6 mm nominal size

cum

700

700

38 of Part II

6mm

M-051 Aggregates 10 mm nominal size

cum

1063

1063

39 of Part II

11-12mm

M-052 Aggregates 13.2/12.5 mm nominal size

cum

928

928

41 of Part II

13-14mm

M-053 Aggregates 20 mm nominal size

cum

942

942

44 of Part II

20mm

M-054 Aggregates 25 mm nominal size

cum

767

767

46 of Part II

25mm

M-055 Aggregates 40 mm nominal size

cum

659

659

50 of Part II

40mm

M-056 AC pipe 100 mm dia

metre

55

55

AC pipe fittings of
PartIII

Sl.
No.

Description

Unit

Rate
Arrived

Rate as per KSOR


Rate

Item No

Item

M-057 Acrylic polymer bonding coat

litre

457

457

360 of part II

M-058 Alluminium Paint

litre

195

195

145 of PartII

M-059 Aluminium alloy plate 2mm Thick

sqm

926

926

597 of PartII

M-060 Aluminium alloy/galvanised steel

tonne

57960

57960

272-275 of part II

G.I Plain Sheet 0.8mm to


1.6mm

Aluminium sheeting fixed with encapsulated lens type reflective sheeting


M-061 including 2% towards lettering, cost of angle iron, cost of drilling holes,
nuts, bolts etc.and signs as applicable

sqm

Nil

Nil

M-062 Aluminium studs 100 x 100 mm fitted with lense reflectors

nos

Nil

Nil

M-063 Barbed wire


M-064 Bearing (Cost of parts)

kg
nos

49.68
Nil

49.68
Nil

256 of part II

G.I Barbed wire

M-065 Bearing (Cast steel rocker bearing assembly of 250 tonne )

nos

Nil

Nil

Bearing (Elastomeric bearing assembly consisting of 7 internal layers of


M-066 elastomer bonded to 6 nos. internal reinforcing steel laminates by the
process of vulcanisation,)

nos

Nil

Nil

M-067 Bearing (Forged steel roller bearing of 250 tonne

nos

Nil

Nil

Bearing (Pot type bearing assembly consisting of a metal piston


supported by a disc, PTFE pads providing sliding surfaces against
M-068
stainless steel mating together with cast steel assemblies/fabricated
structural steel assemblies duly painted with all comp

nos

Nil

Nil

M-070 Bearing (Supply of sliding plate bearing of 80 tonne)

nos

Nil

Nil

M-071 Bentonite

kg

6.35

6.35

575of partII

Sl.
No.

Description

M-072 Binding wire

Unit

Rate
Arrived

Rate as per KSOR


Rate

Item No

Item

kg

87

87

237&238 of partII

Iron wire for tying grills

M-073 Bitumen ( Cationic Emulsion )

tonne

34975

34975

370 of partII

Bitumen emulsion (without


Container)

M-074 Bitumen (60-70 grade)

tonne

41320

41320

368 of partII

Bitumen (60-70 grade)


(without Container)

M-075 Bitumen (80-100 grade )

tonne

40367

40367

367 of partII

M-076 Bitumen (Cutback )

tonne

40367

40367

367 of partII

M-077 Bitumen (emulsion)

tonne

34975

34975

369 of partII

M-078 Bitumen (modified graded)

tonne

42677

42677

366 of partII

M-079 Brick

each

3.8

3.8

5 of part II

M-080 C.I.shoes for the pile


M-081 Cement

kg
tonne

53
5940

53
5940

595 of partII
75 of part II

M-082 Cold twisted bars (HYSD Bars)

tonne

52100

52100

129 of partII

M-083 Coller for joints 300 mm dia


M-084 Compressible Fibre Board(20mm thick)
M-085 Connectors/ Staples

nos
sqm
each

Nil
603
7

Nil
603
7

530 of part II
592 of part II

M-086 Copper Plate(12m long x 250mmwide)

kg

522

522

270 of part II

Copper Sheet

tonne

Nil

Nil

kg

53.4

53.4

276 to 278 of
part II

M-089 Credit for excavated rock found suitable for use

cum

391

391

35 of part II

Corrugated Sheet 1mm to


0.63mm
Blasted rubble at quarry
above 40 dm3

M-090 Curing compound

liter

727

727

591 of part II

M-087 Corrosion resistant Structural steel


M-088 Corrugated sheet, 3 mm thick, "Thrie" beam section railing

Bitumen (80-100 grade)


(without Container)
Bitumen (80-100 grade)
(without Container)
Bitumen emulsion (without
Container)
Natural
rubbermodifiedbitumen
(without Container)
Country burnt traditional
bricks 22.9x11.2x7 cm

Twisted bar
Steel ISI)

(tor

Sl.
No.

Description

Unit

Rate
Arrived

Rate as per KSOR


Rate

M-091

Delineators from ISI certified firm as per the standard drawing given in
IRC - 79

each

Nil

Nil

cum

137

137

Elastomeric slab seal expansion joint assembly manufactured by using


M-093 chloroprene, elastomer for elastomeric slab unit conforming to clause
915.1 of IRC: 83 (part II),

metre

Nil

Nil

M-094 Electric Detonators @ 1 detonator for 1/2 gelatin stick of 125 gms each

100 nos

1100

1100

kg

Nil

Nil

kg
kg
kg
each
each
nos

Nil
Nil
Nil
Nil
Nil
Nil

Nil
Nil
Nil
Nil
Nil
Nil

sqm

Nil

Nil

kg

Nil

Nil

M-092 Earth Cost or compensation for earth taken from private land

M-095 Epoxy compound with accessories for preparing epoxy mortar


M-096
M-097
M-098
M-099
M-100
M-101
M-102

Epoxy mortar
Epoxy primer
Epoxy resin-hardner mix for prime coat
Flag of red color cloth 600 x 600 mm
Flowering Plants
Galvanised MS flat clamp
Galvanised steel wire crates of mesh size 100 mm x 100 mm woven
with 4mm dia. GI wire in rolls of required size.

M-103 Galvanised structural steel plate 200 mm wide, 6 mm thick, 24 m long

M-104 Gelatin 80%


M-105 Geo grids
M-106 Geomembrane
M-107 Geonets

Item No

Item

61 of partII of
KSOR

Cut gravel

576of partII

kg

74.08

74.08

573 of partII

sqm
sqm
sqm

404
Nil
Nil

404
Nil
Nil

417 of partII

Gelatin 80 % ordinary
detonator with water proof
(case of 25 Kg) is Rs 1400

Sl.
No.

Description

Unit

Rate
Arrived

Rate as per KSOR

kg
kg
metre
metre
each
metre
litre
tonne
kg

79
Nil
Nil
Nil
Nil
Nil
Nil
Nil
Nil
Nil
137
Nil
Nil

Rate
79
Nil
Nil
Nil
Nil
Nil
Nil
Nil
Nil
Nil
137
Nil
Nil

sqm

Nil

Nil

M-122 LDO for steam curing


M-123 M.S. Clamps

litre
nos

Nil
Nil

Nil
Nil

M-124 M.S. Clamps

kg

55

55

128of partII

M-125 M.S.shoes @ 35 Kg per pile of 15 m

kg

53

53

595of partII

M-126 Mild Steel bars

tonne

37100

37100

125 of partII

Modular strip/box seal expansion joint including anchorage catering to a


horizontal movement beyond 70 mm and upto 140mm assembly
M-127
comprising of edge beams, central beam,2 modules chloroprene seal,
anchorage elements, support and control system, all steel

metre

Nil

Nil

M-108
M-109
M-110
M-111
M-112
M-113
M-114
M-115
M-116
M-117
M-118
M-119
M-120

Geotextile
Geotextile filter fabric
GI bolt 10 mm Dia
Grouting pump with agitator
Grass (Doob)
Grass (Fine)
HDPE pipes 75mm dia
HDPE pipes 90mm dia
Hedge plants
Helical pipes 600mm diameter
Hot applied thermoplastic compound
HTS strand
Joint Sealant Compound

M-121

Jute netting, open weave, 2.5 cm square opening for seeding and
Mulching

sqm
sqm
nos
hour

Item No
416 of part II

Item

598 of part II

Geotextile

M.s Angles/flats/joist

M.s Rounds / Squares

Sl.
No.

Description

Unit

Rate
Arrived

Rate as per KSOR


Rate

Modular strip/box seal expansion joint catering to a horizontal


movement beyond 140mm and upto 210mm box/box seal joint
M-128
assembly containing 3 modules/cells and comprising of edge beams,
two central beams, chloroprene seal, anchorage elements, support and

Item No

Item

metre

Nil

Nil

M-129 Nipples 12mm

nos

15

15

M-130 Nuts and bolts

kg

81

81

134 to 141 of
Part II

M-131 Paint

litre

211

211

330 of Part II

Sythentic Enamel

M-132 Pavement Marking Paint

litre

211

211

330 of Part II

Sythentic Enamel

M-133 Paving Fabric

sqm

Nil

Nil

M-134 Perforated geosynthetic pipe 150 mm dia

metre

Nil

Nil

M-135 Perforated pipe of cement concrete, internal dia 100 mm

metre

54

54

AC pipe fittings of
PartIII

kg

463

463

588 of partII

100mm dia or nearest


A.C.Pipe
antitermite treatment
chemical

M-137 Pipes 200 mm dia, 2.5 m long for drainage

metre

Nil

Nil

M-138 Plastic sheath, 1.25 mm thick for dowel bars

sqm

Nil

Nil

M-139 Plastic tubes 50 cm dia, 1.2 m high

nos

Nil

Nil

M-140 Polymer braids

metre

Nil

Nil

M-141 Pre moulded Joint filler,25 mm thick for expansion joint.

sqm

992

992

M-142 Pre-coated stone chips of 13.2 mm nominal size

cum

Nil

Nil

M-136 Pesticide

GI Pipes &fittings G.I Hex Nipples 15mm dioa


part III
or nearest size

584of partII

Machine pressed bitumen


pad 25mm for expansion
joint

Sl.
No.

Description

Unit

Rate
Arrived

Rate as per KSOR


Rate

Preformed continuous chloroprene elastomer or closed cell foam sealing


metre
M-143 element with high tear strength, vulcanised in a single operation for the
full length of a joint to ensure water tightness.

Nil

Nil

M-144 Pre-moulded asphalt filler board

sqm

Nil

Nil

kg

Nil

Nil

M-146 Primer

kg

Nil

Nil

M-147 Quick setting compound

kg

Nil

Nil

M-148 Random Rubble Stone

cum

391

391

M-149 RCC Pipe NP 4 heavy duty non presure pipe 1000 mm dia

metre

Nil

Nil

M-150 RCC Pipe NP 4 heavy duty non presure pipe 1200 mm dia

metre

Nil

Nil

M-151 RCC Pipe NP 4 heavy duty non presure pipe 300 mm dia

metre

Nil

Nil

kg

61

61

M-145

Pre-packed cement based polymer concrete of strength 45 Mpa at 28


days

M-152 Reflectorising glass beads


M-153

Reinforcement strips 60 mm wide 5 mm thick as per clause 3102.


(Copper Strips)

metre

Nil

Nil

M-154

Reinforcement strips 60 mm wide 5 mm thick as per clause 3102.


(Galvanised carbon steel strips)

metre

Nil

Nil

M-155

Reinforcement strips 60 mm wide 5 mm thick as per clause 3102.


(Glass reinforced polymer/fibre reinforced polymer/polymeric strips)

metre

Nil

Nil

M-156

Reinforcement strips 60 mm wide 5 mm thick as per clause 3102.


(Stainless steel strips)

metre

Nil

Nil

Item No

Item

34 of part II

Blasted rubble at quarry


above 40 dm3

Sl.
No.

Description

Unit

Rate
Arrived

Rate as per KSOR


Rate

M-157

Reinforcement strips 60 mm wide 5 mm thick as per clause 3102.


Aluminium strips)

M-158 Rivets

metre

Nil

Nil

each

0.65

0.65

M-159 Sand bags (Cost of sand and Empty cement bag)

nos

22

22

M-160 Sapling 2 m high 25 mm dia

each

Nil

Nil

M-161 Scrap tyres of size 900 x 20

nos

Nil

Nil

M-162 Seeds

kg

Nil

Nil

M-163 Selected earth

cum

137

137

M-164 Separation Membrane of impermeable plastic sheeting 125 micron thick

sqm

Nil

Nil

M-165 Sheathing duct

metre

Nil

Nil

M-166 Shrubs

each

Nil

Nil

cum

Nil

Nil

M-168 Sodium vapour lamp

each

Nil

Nil

M-169 Square Rubble Coursed Stone

cum

753

753

each

Nil

Nil

M-167

M-170

Sludge / Farm yard manure @ 0.18 cum per 100 sqm at site of work for
turfing

Steel circular hollow pole of standard specification for street lighting to


mount light at 5 m height above deck level

Item No

Item

382 of part II

Rivet Rs 50/Kg

600of partII

61 of partII

1m3 Sand=Rs 450(35.3147


Cu.feet) 1Cu.feet sand=
450/35.3147=12.74 cement
bag+sand= 3+12.74=15.74

Cut gravel

Assumed

36 of Part II

Coursed rubble stone for


Ist sort work

Sl.
No.

Description

Unit

Rate
Arrived

Rate as per KSOR


Rate

M-171

Steel circular hollow pole of standard specification for street lighting to


mount light at 9 m height above road level

each

Nil

Nil

M-172 Steel drum 300 mm dia 1.2 m high/empty bitumen drum

nos

238

238

M-173 Steel helmet and cushion block on top of pile head during driving.

kg

Nil

Nil

Item No

Item

601ofpartII

M-174 Steel pipe 25 mm external dia as per

IS:1239

metre

66

66

G.Ipipe & Fittings

G.I Pipe - 15mm dia or


nearest size B class

M-175 Steel pipe 50 mm external dia as per

IS:1239

metre

245

245

G.Ipipe & Fittings

G.I Pipe - 15 mm Dia or


nearest size

M-176 Steel wire rope 20 mm

kg

Nil

Nil

M-177 Steel wire rope 40 mm

kg

Nil

Nil

M-178 Strip seal expansion join

metre

Nil

Nil

M-179 Structural Steel

tonne

44100

44100

126 of partII

M.s Angles/flats/joist

kg

Nil

Nil

sqm

404

404

417 of partII

M-182 Through and bond stone

each

14

14

36 of Part II

M-183 Tie rods 20mm diameter

nos

Nil

Nil

M-184 Tiles size 300 x 300 mm and 25 mm thick

each

Nil

Nil

M-185 Timber

cum

Nil

Nil

M-186 Traffic cones with 150 mm reflective sleeve

nos

Nil

Nil

M-187 Tube anchorage set complete with bearing plate, permanent wedges etc

nos

Nil

Nil

M-180 Super plastisizer admixture IS marked as per 9103-1999


M-181

Synthetic Geogrids as per clause 3102.8 and approved design and


specifications.

Previous data

Through and bond stone0.24x0.24x0.39=0.02m3


0.02x520=10.4

Sl.
No.

Description

Unit

Rate
Arrived

Rate as per KSOR


Rate

M-188 Unslaked lime

Item No

Item

65 of Part II

Shell lime as Sl. No. 54 of


Part II density of lime
slacked = 600 Kg/m3. For
tonne=
1800/600x1000=3000

tonne

3200

3200

KL

13

13

litre

Nil

Nil

M-191 Welded steel wire fabric

kg

Nil

Nil

M-192 Wire mesh 50mm x 50mm size of 3mm wire

kg

52

52

256 of part II

G.I fencing wire/G I barbed


wire

M-193 Wooden ballies 2" Dia for bracing

each

M-194 Wooden ballies 8" Dia and 9 m long

each

337

337

123 of part II

Casurina poles 25 to 40 cm
girth 6m long is Rs170/E
(170/6)x9=255

M-195 Wooden packing

cum

M-196 Wooden staff for fastening of flag 25 mm dia, one m long

each

594of part II

M-189 Water
M-190 Water based cement paint

Previous data

Chief Engineer

637
280

917

475
1075

1550

409.5
405
280

1094.5

650
380
80

1110

44.75
1111.5

1156.25

441
650
107.5

1198.5

292.5
1012.5
1305

56

Machinery
Sl. No.

Description of Machine

P&M-001 Air Compressor

Activity

General Purpose

Output of
Machine

Output

Unit

Rate

capacity in cfm

170/250

hour

300

P&M-002

Batching and Mixing Plant (a) 30 cum


Concrete Mixing
capacity

cum/hour

20

hour

2094

P&M-003

Batching and Mixing Plant (b) 15 - 20


Concrete Mixing
cum capacity

cum/hour

13

hour

1745

sqm/hour

1750

hour

1006

capacity in litre

1500

hour

186

Paving of concrete surface

cum / hour

20

hour

2690

Pumping of concrete

cum / hour

33 / 22

hour

240

P&M-008 Concrete Bucket

For Pouring concrete

capacity in cum

hour

15

P&M-009 Concrete Mixer (a) 0.4/0.28 cum

Concrete Mixing

cum/hour

2.5

hour

218

P&M-010 Concrete Mixer (b) 1 cum

Concrete Mixing

cum/hour

7.5

hour

218

P&M-011 Crane (a) 80 tonnes

Lifting Purpose

hour

1200

P&M-012 Cranes b) 35 tonnes

Lifting Purpose

hour

800

P&M-013 Cranes c) 3 tonnes

Lifting Purpose

hour

334

P&M-014 Dozer D - 80 - A 12

Spreading /Cutting / Clearing

hour

3490

P&M-004 Bitumen Pressure Distributor

Applying bitumen tack coat

P&M-005 Bitumen Boiler oil fired

Bitumen Spraying

Concrete Paver Finisher with 40 HP


Motor
Concrete Pump of 45 & 30 cum
P&M-007
capacity
P&M-006

cum/hour

300/
150/250

Activity

Output of
Machine

Output

Unit

Rate

P&M-015 Dozer D - 50 - A 15

Spreading /Cutting / Clearing

cum/hour

200/
120/150

hour

2069

P&M-016 Emulsion Pressure Distributor

Applying emulsion tack coat

sqm/hour

1750

hour

750

Soil loading / Aggregate


loading

cum/hour

60 /25

hour

756

Sl. No.

P&M-017

Description of Machine

Front End loader 1 cum bucket


capacity

P&M-018 Generator (a) 125 KVA

Genration of electric Energy

KVA

100

hour

654

P&M-019 Generator( b) 63 KVA

Genration of electric Energy

KVA

50

hour

349

P&M-020 GSB Plant 50 cum

Producing GSB

cum/hour

40

hour

974

P&M-021 Hotmix Plant - 120 TPH capacity

DBM/BM/SDC/ Premix

cum/hour

40

hour

15906

P&M-022 Hotmix Plant - 100 TPH capacity

DBM/BM/SDC/ Premix

cum/hour

30

hour

12360

P&M-023 Hotmix Plant - 60 to 90 TPH capacity

DBM/BM/SDC/ Premix

cum/hour

25

hour

10256

P&M-024 Hotmix Plant - 40 to 60 TPH capacity

DBM/BM/SDC/ Premix

cum/hour

17

hour

7339

P&M-025 Hydraulic Chip Spreader

Surface Dressing

sqm/hour

1500

hour

2472

P&M-026 Hydraulic Excavator of 1 cum bucket

Soil Ordinary/Soil Marshy /


Soil Unsuitable

cum/hour

60 /60 /60

hour

1222

P&M-027 Integrated Stone Crusher 100THP

Crushing of Spalls

TPH

100

hour

8130

P&M-028 Integrated Stone Crusher 200 HP

Crushing of Spalls

TPH

200

hour

17103

P&M-029 Kerb Casting Machine

Kerb Making

Rm/hour

80

hour

291

Sl. No.

Description of Machine

Activity

Output of
Machine

Output

Unit

Rate

capacity in tonne

hour

58

P&M-030 Mastic Cooker

Mastic Wearing coat

P&M-031 Mechanical Broom Hydraulic

Surface Cleaning

sqm/hour

1250

hour

334

P&M-032 Motor Grader 3.35 mtr blade

Clearing /Spreading /GSB


/WBM

cum/hour

200/200/5
0/50

hour

2247

P&M-033 Mobile slurry seal equipment

Mixing and laying slurry seal

sqm/hour

2700

hour

945

cum/hour

40

hour

2509

cum/hour

40/30

hour

915

Rm/hour

2 to 3

hour

5126

Paver Finisher Hydrostatic with sensor Paving of DBM/ BM/SDC/


control 100 TPH
Premix
Paving of WMM /Paving of
P&M-035 Paver Finisher Mechanical 100 TPH
DLC
0.75 m dia to 1.2 m dia Boring
P&M-036 Piling Rig with Bantonite Pump
attachment
P&M-034

P&M-037 Pneumatic Road Roller

Rolling of Asphalt Surface

cum/hour

25

hour

1166

P&M-038 Pneumatic Sinking Plant

Pneumatic Sinking of wells

cum/hour

1.5 to 2.00

hour

3912

P&M-039 Pot Hole Repair Machine

Repair of potholes

cum/hour

hour

851

P&M-040 Prestressing Jack with Pump & access

Stressing of steel
wires/stands

hour

121

P&M-041 Ripper

Scarifying

cum/hour

60

hour

26

P&M-042 Rotavator

Scarifying

cum/hour

25

hour

16

P&M-043 Road marking machine

Road marking

Sqm/hour

100

hour

87

Sl. No.

Description of Machine

Activity

Output of
Machine

Output

Unit

Rate

P&M-044 Smooth Wheeled Roller 8 tonne

Soil Compaction /BM


Compaction

cum/hour

70/25

hour

432

P&M-045 Tandem Road Roller

Rolling of Aspalt Surface

cum/hour

30

hour

1073

P&M-046 Tipper - 5 cum

Transportation of soil, GSB,


WMM, Hotmix etc.

Capacity in cum

5.5

km

227

P&M-047 Tipper - 5 cum

Transportation of soil, GSB,


WMM, Hotmix etc.

Capacity in cum

5.5

tonne.k
m

P&M-048 Tipper - 5 cum

Transportation of soil, GSB,


WMM, Hotmix etc.

Capacity in cum

5.5

hour

291

P&M-049 Transit Mixer 4.0/4.5 cum

Transportation of Concrete
Mix to site

cum/hour

4.5

hour

873

P&M-050 Transit Mixer 4/4.5 cum

Transportation of Concrete
Mix to site

cum/hour

4.5

tonne.k
m

input

P&M-051 Transit Mixer 3.0 cum

Transportation of Concrete
Mix to site

cum/hour

hour

800

P&M-052 Transit Mixer 3.0 cum

Transportation of Concrete
Mix to site

cum/hour

tonne.k
m

input

P&M-053 Tractor

Pulling

capacity in HP

50

hour

340

P&M-054 Tractor with Rotevator

Rate of Tractor + Rotevator

hour

356

P&M-055 Tractor with Ripper

Rate of Tractor 6+ Ripper

hour

366

Sl. No.

Description of Machine

Activity

Output of
Machine

Output

Unit

Rate

P&M-056 Truck 5.5 cum per 10 tonnes

Material Transport

capacity/cum

4.5

km

21

P&M-057 Truck 5.5 cum per 10 tonnes

Material Transport

capacity/cum

4.5

hour

291

P&M-058 Truck 5.5 cum per 10 tonnes

Material Transport

capacity/cum

4.5

tonne.k
m

P&M-059 Vibratory Roller 8 tonne

Earth or soil / GSB / WBM

cum/hour

100/60/60

hour

1446

P&M-060 Water Tanker

Water Transport

capacity in KL

hour

233

P&M-061 Water Tanker

Water Transport

capacity in KL

km

23

P&M-062 Wet Mix Plant 60 TPH

Wet Mix

cum/hour

25

hour

1130

Sl. No. Description of Machine

Unit

Rate

P&M-063 Air compressor with pneumatic chisel attachment for cutting hard clay.

hour

300

P&M-064 Batch type cold mixing plant 100-120 TPH capacity producing an average output of 75 tonne per hour

hour

input

P&M-065 Belt conveyor system

hour

input

P&M-066 Boat to carry atleast 20 persons

hour

input

P&M-067 Cement concrete batch mix plant @ 175 cum per hour (effective output)

hour

input

P&M-068 Cement concrete batch mix plant @ 75 cum per hour

hour

input

Sl. No.

Activity

Output of
Machine

Unit

Rate

P&M-069 Cold milling machine @ 20 cum per hour

hour

input

P&M-070 Crane 5 tonne capacity

hour

334

P&M-071 Crane 10 tonne capacity

hour

input

P&M-072 Crane 15 tonne capacity

hour

input

P&M-073 Crane 20 tonne capacity

hour

input

P&M-074 Crane 40 T capacity

hour

800

P&M-075 Crane with grab 0.75 cum capacity

hour

349

P&M-076 Compressor with guniting equipment along with accessories

hour

300

P&M-077 Drum mix plant for cold mixes of appropriate capacity but not less than 75 tonnes/hour.

hour

input

P&M-078 Epoxy Injection gun

hour

input

P&M-079 Generator 33 KVA

hour

349

P&M-080 Generator 100 KVA

hour

654

P&M-081 Generator 250 KVA

hour

700

hour

input

hour

input

P&M-082

Description of Machine

Output

Induction, deinduction and erection of plant and equipment including all components and accessories
for pneumatic method of well sinking.

P&M-083 Joint Cutting Machine with 2-3 blades (for rigid pavement)

Sl. No.

Description of Machine

Activity

Output of
Machine

Output

Unit

Rate

P&M-084 Jack for Lifting 40 tonne lifting capacity.

day

input

P&M-085 Piling rig Including double acting pile driving hammer (Hydraulic rig)

hrs

input

P&M-086 Plate compactor

hour

input

P&M-087 Snow blower equipment 140 HP @ 600 cum per hour

hour

input

P&M-088 Texturing machine (for rigid pavement)

hour

input

P&M-089 Truck Trailor 30 tonne capacity

hour

input

P&M-090 Truck Trailor 30 tonne capacity

t.km

input

P&M-091 Tunnel Boring machine

hour

input

P&M-092 Vibrating Pile driving hammer complete with power unit and accessories.

hour

input

P&M-093 Wet Mix Plant 100 TPH

hour

1130

P&M-094 Wet Mix Plant 75 TPH

hour

1130

Chief Engineer

(B) Labour
Sl. No.

Description of Labour

Unit

Rate

Remarks

Rate
arrived

Rate as
per SOR

L-01

Blacksmith (IInd class)

day

450

450

Blacksmith as Sl No.1 of partI of KSOR

L-02

Blacksmith (Ist class)/ Welder/ Plumber/ Electrician

day

500

500

ExcludingElectrician.
Blacksmith/Plumber/welder

L-03
L-04
L-05
L-06

Blaster (Stone cutter)


Carpenter I Class
Chiseller (Head Mazdoor)
Driller (Jumper)

day
day
day
day

396
500
400
400

396

L-07

Diver

day

L-08
L-09
L-10
L-11
L-12
L-13

Fitter
Mali
Mason (IInd class)
Mason (Ist class)
Mate / Supervisor
Mazdoor

L-14

500

for all classes

400
400

Rate for jumper-

471

471

Well sinker -Diver without diving set

day
day
day
day
325
day

456
377
471
500
673
377

456

Mazdoor/Dresser (Semi Skilled)

day

377

377

L-15

Mazdoor/Dresser/Sinker (Skilled)

day

408

408

L-16

Medical Officer

day

852

852

Well Sinker ordinary


Skilled Assistant (Engineering Degree
Holder)

L-17
L-18

Operator(grouting)
Painter I class

day
day

450
396

450

Mechanic II

L-19

Para medical personnel

day

852

Rate for jumper

377
471

Man Mazdoor

500

Brick Mason &Rubble Mason

673

Skilled Assistant (Diploma Holder) -

Brick Mason &Rubble Mason

377
Special mazdoor for surveying thatching
white washing etc

396
852

Skilled Assistant (Engineering Degree


Holder)

Chief Engineer

Вам также может понравиться