Академический Документы
Профессиональный Документы
Культура Документы
NO.
TCE-4857A-C-
SHEET 1 OF 25
1.0
DESIGN REQUIREMENTS
General
1.1
1.2
The steam generator and its auxiliaries shall be designed for outdoor
installation.
1.3
1.4
1.5
1.6
The furnace shall be designed such that the heat release rates shall not
exceed the values specified in Data Sheet-A1 at 100% steam generator
maximum continuous rating (SGMCR) condition. The distance between
centre line of bottom most coal burner and furnace hopper working point
shall be not less than 3 metres. The configuration of the furnace shall be
such that flame impingement on any section of the furnace is avoided over
the entire load range.
1.7
The furnace shall have hopper bottom with stainless steel seal plates
suitable for connection to a water impounded ash hopper. A suitable sealing
arrangement for connecting to a water impounded ash hopper shall also be
provided. The clear width of the hopper throat shall not be less than
1100mm. The distance between furnace opening and the grade level shall
be 7.5 m.
1.8
Field welds in large diameter thick walled headers or pipes shall be avoided
to the extent possible.
1.9
Provision shall be made for the future installation of additional soot blowers
in the furnace.
ISSUE
R0
NO.
TCE-4857A-C-
SHEET 2 OF 25
1.10
1.11
A gas tight enclosure shall be designed for the entire steam generator from
the lower furnace to the economiser exit. In areas where welded wall
construction is used, no skin casing is required, but skin casing of steel
plates shall be used for all enclosures and behind all wide spaced tubes
where refractory is used. Frames shall be furnished around all openings in
the steam generator, designed to allow for expansion between the welded
wall or inner skin casing and an outer aluminum lagging. The aluminum
shall be of ribbed type and shall be minimum 1.2 mm thick.
Steam and Water System
1.12
The steam and water system shall be as per enclosed scheme no.
TCE.4857A-510-SK-001.The system shall be designed for a continuous
operating capability as specified in Data Sheet-A1. The Bidder shall clearly
bring out the design features to minimise the peak tube metal temperature,
unit temperature variation between adjacent enclosure tubes and prevent
departure from nucleate boiling.
Steam Generator Water Circulation
1.13
The circulation system shall ensure adequate circulation ratio during rapid
start-ups and load changes to prevent overheating of the water wall tubes
with maximum possible heat flux in the furnace. This shall be ensured by
suitable sizing the steam drum, down comers and water wall tubes. The
steam generator water circulation shall be natural circulation type.
1.14
1.15
The design of the drum internal shall be such as to guarantee the steam
quality required for the steam turbine (greater than or equal to 99.9 5), over
the entire load range.
1.16
All nozzles shall be of the long body type so that the same will extend
through the steam generator lagging. The ends of nozzles smaller than 50
mm shall have plane ends for socket welding and the nozzles 50 mm and
larger shall have beveled ends for butt-welding.
1.17
The distribution and placement of furnace water wall tube inlets to the drum ISSUE
shall be designed to permit uniform heating of the drum metal during start- R0
NO.
TCE-4857A-C-
SHEET 3 OF 25
up, shutdown and load changes. The CONTRACTOR shall specify in the
tender, the maximum permissible drum metal temperature differential and
the corresponding maximum permissible rate of pressure and temperature
changes during start-up, shutdown and load changes.
Superheater and Reheater
1.18
1.19
1.20
1.21
1.22
Auxiliary steam tap-off connection for soot blowing shall be either from
intermediate superheater header or from cold reheat line or from auxiliary
steam header. In case the steam is tapped off from the cold reheat line or
from auxiliary steam header, the CONTRACTOR shall furnish a list of
installation where such systems are in vogue and also the same shall be
reflected appropriately in the turbine cycle heat balance diagrams.
Suitable allowance shall be provided for the superheater and reheater
tubes to counter the erosion condition.
ISSUE
R0
NO.
TCE-4857A-C-
SHEET 4 OF 25
Economiser
1.23
It shall be ensured that the economiser design pressure exceeds the steam
generator design pressure by an amount of at least equal to the pressure
drop (friction and static) through the economiser at the 100% SGMCR
condition.
1.24
The economiser shall be of non-steaming type and shall have provision for
recirculation of water while starting the unit. The economiser tube banks
shall be of in line design. The design of the economiser shall be such that
the tube elements can be easily replaced when necessary. Suitable
allowance shall be provided for the economiser tubes to counter the
erosion.
Headers
1.25
All headers in high temperature gas path shall be located outside the gas
path. The handhole openings in headers shall be so located as to provide
suitable access to maintenance and inspection. All handhole plates shall be
designed for seal welding.
1.26
The header vents, drains, pressure gauges, steam and safety valve
connections shall be of weld-end type. Instrument as required including test
connections shall be provided.
1.27
1.28
All valves that require operation during start-up or shutdown of the steam
generator shall be electric motor operated, except as specifically stated
otherwise. All motor actuators shall be designed to meet the torque
requirement due to maximum differential pressure. In addition to these
motorised valves, any other service, which calls for motor operation, shall
be motorised and those motorised valves shall be listed in the bid.
1.29
1.30
Facility for draining the steam drum during emergency when the steam
generator is in operation shall be provided. The valves shall be furnished
with motor drive. The drain shall be led to IBD through a drain collection
header. The tap off point for emergency drain should be at normal drum
level. All blowdown valves shall be suitable for passage of acid wash during
acid cleaning.
ISSUE
R0
NO.
TCE-4857A-C-
SHEET 5 OF 25
1.31
The drain valve capacity shall be sufficient to permit draining of the unit
under atmospheric pressure in one (1) hour.
1.32
1.33
The air and flue gas system shall be as per enclosed scheme no.
TCE.4857A-510-SK-0003
1.34
The air and flue gas system shall be designed to meet the requirements of
100% SG MCR conditions and for using the coals specified. The system
shall also be suitably designed for burning heavy furnace oil (HFO) and
light diesel oil (LDO) as specified.
1.35
The air and flue gas system shall consist of two (2) 60% capacity FD fans
of axial blade pitch controlled, two (2) 60% capacity PA fans of axial blade
pitch controlled (the Bidder can offer centrifugal fans with techno economic
justification), two (2) 60% capacity centrifugal ID fans with variable
frequency drives and inlet guide vane control 2 x 60% capacity trisector
regenerative air preheater (RAPH), with associated drive motors, cold air,
hot air, tempering and flue gas ducting and dampers to handle the steam
generator requirements.
1.36
1.36.1
The rotor shall be over-speed tested to at least 10% above the maximum
operating speed and shall be dynamically balanced. The fan shafts are to
be supported in bearings on either side independent of the casings.
Overhung impellers will not be acceptable.
1.36.2
1.36.3
Forced oil lubrication system for the fans and motors shall consist of 2 x
100% oil pumps each with motor, 2 x 100% oil coolers and filters; one (1) oil
tank and electric heater with thermostat etc.
1.36.4
1.36.5
1.37
Each bearing is to be provided with oil level indicator and a screwed drain
plug. Adequate sealing arrangement shall be provided at each end of the
bearing housing to prevent leakage of lubricating oil.
ISSUE
R0
NO.
TCE-4857A-C-
SHEET 6 OF 25
1.38
Silencer shall be provided at the inlet of FD and PA fans with weather hood
and inlet screen.
1.39
1.40
1.41
The gas and air ducts shall be designed for wind loads as specified for the
steam generating unit proper and their own weight including fly ash load
which may get deposited at the duct bottom, insulation and lining. The top
of the ducts shall be crowned to ensure proper drainage.
1.42
The ductwork shall be free to expand, but it shall be rigid against wind and
seismic disturbances. Adequate provision shall be made for all expected
expansion or contraction.
1.43
All gas and air ducts shall be designed to ensure uniform distribution of gas
and airflow to the various portions of the unit. These ducts shall consist of
turning vanes / baffle plates, stiffening devices, expansion joints, interior
bracings, access doors and brackets, support structures and hangers as
necessary.
1.44
Aerofoils shall be provided in the air ducts for the measurement of total
airflow.
1.45
1.46
Electrical operated guillotine type isolation dampers along with drives shall
be provided as specified in Data sheet-A1. The inlet dampers for ID fans
shall be located in horizontal duct of main inlet duct to avoid fly ash build up
when in closed position(the same will be take care suitably during detailed
engineering by SEC).
1.47
The flue gas duct layout shall be designed considering the following
aspects:
The change of direction of flue gas duct shall be gradual to avoid
ash collection at the bottom of the duct and also to prevent erosion
by local concentration of fly ash.
ISSUE
R0
NO.
TCE-4857A-C-
SHEET 7 OF 25
1.49
1.50
1.51
1.52
1.53
NO.
TCE-4857A-C-
SHEET 8 OF 25
1.56
1.56.1
1.56.2
1.56.3
Each output leg of each transformer-rectifier set shall serve one bus
section and both bus sections served by each transformer-rectifier set shall
be in the same field.
1.56.4
1.56.5
NO.
TCE-4857A-C-
SHEET 9 OF 25
All silicon rectifier cells shall be conservatively rated for compatibility with
maximum circuit load and demands requirements.
1.56.7
1.56.8
1.56.9
1.56.10 In the event of arcing, the filter voltage shall be switched off for several half
cycles to ensure a satisfactory extinction of the arc. If dust bridging or metal
short circuits occur in the precipitator, the precipitator short circuit current
shall be limited to the rated current of the installation and disconnected
completely after the expiration of a given time.
1.56.11 Supporting insulators shall be located in heated compartments that are
maintained above the dew point of the flue gas. They shall be located out
of the dirty gas stream. These shall be protected from weather by either a
common top housing or individual compartments. A steel shroud below the
insulator may be provided which will further inhibit dust diffusion. Each
compartment shall be pressurised and ventilated by heated filtered air
furnished by one or motor driven blowers. Contactors and strip heaters with
control thermostats for heating the air, blower motors, and blower motor
contactors and control for each compartment as required, for complete
hand automatic operation with alarm contacts for high and low
temperatures and loss of pressure shall be provided. The filters shall be of
the washable type, adequately sized for use in dusty atmosphere.
1.56.12 If strip heaters are used, the wiring to the strip heater terminals shall be
nickel-plated copper with 600-volt teflon-glass insulation.
Control Cubicles
1.56.13 Automatic control cubicles shall be furnished for indoor mounting. Units
shall be of the high-speed silicon controlled rectifier or magnetic-amplifier
type designed to maintain the optimum Precipitator voltage and current for ISSUE
R0
NO.
TCE-4857A-C-
SHEET 10 OF 25
variations in rate of gas flow and particle content and with simultaneous
supply voltage variations of plus or minus 10%. The automatic controls
shall have full control from 10% of the power set rating to full rating.
The control system should be capable of:
a)
b)
c)
Break a power arc within around ten- (10) milli sec of its occurrence.
d)
e)
Modify the current wave shape permitting greater power input prior to
reaching spark over threshold.
b)
ISSUE
R0
NO.
TCE-4857A-C-
SHEET 11 OF 25
Motors
1.56.19 Drive motors of the rapping mechanism for collecting and discharge
electrodes and fans shall comprise 415V, 3 phase, 50 Hz, rated direct-online induction motors with IP-55 enclosure.
In general, motors shall conform to Specification as specified.
1.56.20 Each motor shall be connected to its supply by means of a full voltage
combination magnetic starter which shall include a moulded case circuit
breaker or switch & HRC cartridge link type fuses for the over-current and
short circuit protection. All motor starters, heater contactors, etc. shall be
mounted in their respective control cabinets. Location of motors shall be
such that they are easily accessible for any repair or maintenance.
1.57
1.58
The CONTRACTOR shall optimise gas flow pattern and distribution in the
precipitator sections.
1.59
The storm water drain piping shall be provided up to the grade levels for
ESP.
Start-up/Warm-up Oil System
1.60
The start-up/warm-up oil system shall be as per the enclosed scheme no.
TCE.4857A-SK-510-0004
1.61
Warm up oil system shall be designed for burning light diesel oil (LDO) as
specified in Section C-2. This system design capacity should be sufficient to
raise steam parameters of the steam generator to meet auxiliary steam for
fuel oil heating and atomising in the shortest possible time to enable quick
changeover to HFO firing. However, this system shall have minimum
capacity of 10% of MCR rating of one steam generator. LDO will also be
utilised as flushing medium for flushing out fuel oil pipelines and headers
during long unit outages.
1.62
This system shall consist of two (2) 100% capacity LDO (1 working + 1
standby) pressurising pumps, suction strainers, compressed air atomised
burners, LDO and air piping valves and fittings, instrumentation, safety and
control systems in line with the sketch enclosed.
ISSUE
R0
NO.
TCE-4857A-C-
SHEET 12 OF 25
The support oil system shall be as per the enclosed scheme no.
TCE.4857A-510-SK-0005
1.64
This system shall use heavy fuel oil (HFO) as specified for start up/flame
stabilisation.
1.65 The fuel oil burning system shall consist of filtration and pressurising unit
having 2 x 100% capacity (one working one standby) pumps with matching
suction strainers, heating and filtration units consisting of (2 x 100%
capacity steam oil heaters) and two (2) matching pressure filters, fuel oil
safety and burner shut off valves, fuel oil pressure and temperature control
valves, fuel oil metering units, fuel oil atomising and blow-off steam headers
at burners, atomising steam pressure control valves, piping and valving
necessary for bypass and isolation, fuel oil burner header recirculation
control valve, recirculation piping with valves fuel oil atomizing burners, as
identified in the enclosed sketch.
1.66
The oil burning system shall be designed for 30 % SG MCR rating. The fuel
oil burners shall be positioned to provide support to any of the coal burners
at low loads for flame stabilisation as and when required.
1.67
All pumps, strainers and/or pump strainer assembly units shall be provided
with drip pans.
1.68
1.69
The suction and discharge filters, the fuel oil pumps and the fuel oil pipes
shall be equipped with electric heat tracing. The atomising / blow off steam
system and steam oil heaters will be supplied with auxiliary steam from
auxiliary steam system.
1.70
The screw/gear type pressurising pumps shall be provided with a springloaded relief valve and it shall be built-in with the pump, the discharge end
of the valve being connected to the pumps suction side. The relief valve
shall be capable of allowing the full discharge of the pump through it. The
relief valve set pressure shall be adjustable.
Coal Pulverising and Firing System
ISSUE
R0
NO.
TCE-4857A-C-
SHEET 13 OF 25
1.71
The coal firing system shall be designed to meet the requirement of steam
generator at 100% SG MCR condition, with worst coal as indicated in the
specification.
1.72
The coal pulverising and firing system shall consists of medium speed coal
mills with drives, coal feeders with drives, coal isolation gates at bunker
outlet, feeder inlet, coal piping with flexible couplings from mill outlets to
coal burners, coal burners with shut-off gates and drives, air registers with
drives, coal mill hot air and coal / air discharge isolation gates and drives,
two (2) x 100% seal air (SA) fans complete with air ducting to all coal
mills/feeders, isolation, interconnecting and control dampers on seal air
ducting as required, insulation, supports and hangers etc.
1.73
Forced oil lubrication system for the coal mills and motors shall consist of 2
x 100% oil pumps each with motor, 2 x 100% oil coolers and filters etc. with
necessary piping and valves.
1.74
(b)
(c)
selected
With one mill as standby and other mills running at 85% of their MCR,
the system shall be able to meet 100% coal firing rate using worst
coal. Also, with two mills as standby, 100%SGMCR shall be met using
design coal.
Minimum three mills shall be in operation for load range of 60%
TGMCR to 100% SGMCR.
Each coal mill shall be provided with a separate gravimetric coal
feeder and its capacity shall not be less than the capacity of the coal
mill
1.75
Dampers shall be provided on coal pipes at mill outlet, on cold air and seal
air ducts and gates on hot air to coal mills. These gates / dampers shall be
of manually operated type.
1.76
1.77
Sealing Air (SA) fans shall deliver air into a common seal air header from
where each coal mill and feeder set shall be supplied with the seal air.
1.78
For drawing coal samples (iso kinetic sampling of coal) for testing the
fineness of the ground coal, a minimum of four tapping points at right
angles to each other shall be provided on the straight length of pipe at each
coal mill outlet. Compressed air purging connections shall be provided at
the tapping points to clear the opening prior to sample collection.
1.79
Coal isolation gates shall be provided at each bunker outlet. The gates
shall be of dust-proof, rack and self-cleaning type pinion with all parts in ISSUE
R0
NO.
TCE-4857A-C-
SHEET 14 OF 25
contact with coal of minimum type 410 weldable stainless steel. The gates
shall be provided with chains for hand operation.
1.78
Manual isolation gates shall also be furnished in each coal burner pipe at
the wind-box for facilitating on-line maintenance work of coal piping/coal
mill.
1.79
The coal feed pipe from the coal mills to the coal burners shall be of wear
resistant, weldable steel and of minimum thickness not less than 12 mm on
straight length and 20 mm (but not less than one and a half times the
straight pipe thickness) at outer radius of bends. The bends shall be basalt
lined or ceramic lined to prevent erosion.
1.80
Each pipe between bunker outlet and feeder inlet shall be provided with a
flanged filler piece for connection of an angle type divertor chute to permit
emergency dumping of coal from the bunkers. One carbon steel divertor
chute connection piece with flanged outlet shall be furnished.
1.81
1.87
Adequate and suitably located poke holes shall be provided to clear the
feed pipes to the mills when they get choked.
1.82
The Bidder shall also quote for slow speed ball and tube mills option. The
Bidder shall furnish the details of this option in his bid.
Mill reject hopper
1.83 The Mills rejects (Pyrites) discharged by the Mills shall be collected in the
respective Mills pyrites hopper. The pyrites hopper shall be provided with
isolation valves / dampers such that the valve will open automatically after a
pre-set weight of the rejects for further conveyance. The arrangement of the
mill reject hopper gates shall be such that at all times atmospheric air shall
not be ingressed into the system.
Ignition System
1.84
High Energy Arc (HEA) ignitors shall be provided to ignite LDO and HFO.
One HEA ignitor for each fuel oil gun shall be provided. The ignitor system
offered shall be of well-proven design of reputed make.
1.85
NO.
TCE-4857A-C-
SHEET 15 OF 25
1.86
Adequate number of flame scanners shall be provided for fuel oil and coal
firing. Two (2) 100% one AC and one DC motor driven scanner air fans
shall also be provided for the flame scanner cooling.
Blow Down System
1.87
The blow down system shall consist of continuous blowdown (CBD) tank
and intermittent blowdown (IBD) tank, all piping, headers, valves, supports
and hangers, insulation, etc. From steam drum to CBD tank, all piping,
headers, valves, supports and hangers, insulation etc., from CBD tank to
IBD tank and CBD tank level control system and instrumentation. The CBD
level control system shall be complete with drain control valve. All piping,
header, valves, supports and hangers, insulation etc., for emergency blow
down from steam drum to IBD tank shall also be included.
1.88
The CBD tank shall be designed to accept the continuous drain from the
steam drum for the purpose of controlling the dissolved solids in drum
water. The CBD tank shall have extra thickness at and around the point of
entry of drum water.
Soot Blowing System
1.89
The soot blowing system shall consist of motor operated steam soot
blowers of the rotary and retractable type, with drives, pressure reducing,
isolation and relief valves, steam traps, thermal drain valves, complete
piping, supports and hangers, insulation, motor control centers and soot
blower instrumentation and control system. The system shall be of selfdraining type. The Bidder can consider conventional type of soot blowing
system. The Bidder shall quote for alternative of Smart soot blowing
system (lower consumption of steam & less erosion, software based,
selective soot blowing) and furnish details of the same along with his bid.
1.90
ISSUE
R0
NO.
TCE-4857A-C-
SHEET 16 OF 25
Auxiliary steam system shall consist of one (1) auxiliary pressure reducing
station (PRS) and a desuperheater on the steam line tapped off from the
main steam line (MSL) as shown in the enclosed flow diagram
no.TCE.4857A-SK-510-0001. The system shall be complete with the
pressure reducing valves, bypass valve and isolation valves; safety relief
valves, drains, steam traps; quick closing block spray valve; desuperheater;
steam temperature control valves, bypass valve and isolation valves;
complete piping, supports with hangers, insulation and instrumentation &
control. Pressure control valves shall be selected in such a way that it
would be possible to regulate the steam flow based on demand under all
operating regimes. CONTRACTOR shall furnish the basis of the same
during detailed engineering for approval.
1.92
The spray water for desuperheating station shall be supplied from boiler
feed pump discharge or inter-stage tap-off. The CONTRACTOR shall
provide pressure and temperature control valves to meet the requirements
of auxiliary steam system.
1.93
1.93.1
1.93.2
Thermal insulation and cladding shall be provided for the entire steam
generator, flue gas / air ducting, ESP, etc. The insulation selected shall
meet the requirement specified.
Chemical Dosing System
1.94
The phosphate dosing system shall be supplied for SG unit to maintain the
drum water chemistry. The system shall consist of one solution preparation
tank, one solution dilution tank, 2 x 100% dosing pumps complete with
suction / discharge valves, Y-type suction strainers, pressure guages, etc.,
dosing pump discharge header sectionalising valves and complete piping
with isolating and non-return valves as required.
1.95
Each tank shall be complete with motorised agitator, overflow and drain
connections, inlet / outlet isolating valves and side mounted level gauge /
level switch with connecting isolating valves.
ISSUE
R0
NO.
TCE-4857A-C-
SHEET 17 OF 25
An auxiliary cooling water system shall be supplied for the SG unit. The
system shall consist of complete piping to all equipment requiring cooling
water. Each cooler / bearing shall be supplied with isolating valves at the
inlet and throttling type valves at the outlet.
SG Fill Pump
1.97
One (1) SG fill pump shall be supplied. The SG fill pump shall draw water
from the condensate storage tank (CST) and fill the SG unit before start-up.
The CONTRACTOR shall provide SG fills connection to the SG unit at
economiser, and superheater drain headers. In addition, the fill pump
discharge shall be connected to deaerator feed storage tank and ACW
storage tank also. The capacity of the fill pump shall be enough to fill the
SG unit in about 11/2 hours time.
Vibration and Noise Levels
1.96
The design of steam generator and its auxiliaries shall ensure maintenance
of vibration and noise levels within the limits specified
in the following paragraphs over the entire operating range and during load
fluctuations.
1.97
The gas path design shall prevent the generation of excitation forces
conducive to resonant vibration.
1.98
FD, ID, PA and coal mills shall be provided with vibration isolation system
(spring mounted) or conventional block/frame type RCC foundation can be
provided.
1.99
Vibration at the bearings of FD, ID, PA and coal mills shall meet the
requirements of VDI-2056, Machine Group `G, quality class `Good.
1.100
1.101
1.102
The measured noise level produced by any rotating equipment shall not
exceed 85 dBA at a distance of 1.0 m from its boundary in any direction
under any load condition.
1.103
NO.
TCE-4857A-C-
SHEET 18 OF 25
1.105
1.106
1.107
1.108
The minimum width of staircase shall be 1000 mm and the minimum width
of platforms shall be 750 mm. The minimum width of interconnecting
walkway between mill maintenance platform and the steam generator
gallery shall be 1200 mm. All platforms and staircases shall be provided
with gratings and only operating floor shall be provided with chequered
plates.
1.109
Actuators for remote operation of shut-off gates at the air inlets to coal mills
and cold air and hot air shut off gates at outlet of coal mills shall be
provided to allow positive shut-off in the event of fire in the mills.
Control Valves For System
1.110
All control valves shall be sized such that the valves are controllable over
entire operating regime viz. low load to full load. Those control valves which
require to be operated during cold, warm and hot start conditions shall also
be controllable during this mode of operation. To meet the above ISSUE
R0
NO.
TCE-4857A-C-
SHEET 19 OF 25
PERFORMANCE REQUIREMENTS
2.1
General
As the steam generator will operate generally base loaded, it shall be
designed to perform in the most efficient manner at 100% turbine generator
maximum continuous rating (TGMCR) condition.
2.2
2.3
2.4
2.5
NO.
TCE-4857A-C-
SHEET 20 OF 25
The CONTRACTOR shall indicate the minimum coal mill load (a) at which
point a coal mill must be removed from service when two other coal mills
are also in operation each sharing equal load (b) at which point stabilising
fuel oil is to be introduced before taking out the second mill (c) when one
mill is in operation and stabilising fuel oil is in use. CONTRACTOR shall
note that the minimum stable load without fuel oil support for pulverised fuel
flame stabilization shall not be more than 30% of steam generator MCR
(SGMCR) load.
2.6
2.7
Rate of Loading
The steam generator shall be loaded as fast as practicable subsequent to
synchronisation after cold/warm/hot start-up with 60% capacity bypass
system in service. The CONTRACTOR shall indicate the criteria that will
govern the rate of loading of the steam generator. Specific reference shall
be made to thermocouples and their locations on the steam generator,
which will be used to establish steam generator loading schedules with
reference to the loading criteria. The thermo couple shall have minimum life
of ten (10) years.
2.8
2.9
2.10
Oxides of Nitrogen
The steam generator unit shall incorporate provisions necessary to restrict
the emission of oxide of nitrogen. The CONTRACTOR shall furnish details
on NOx control systems.
2.11
NO.
TCE-4857A-C-
SHEET 21 OF 25
2.12
(a)
(b)
(c)
2.13
The expected normal load range of the unit shall be from 40% TG MCR to
100% SG MCR.
2.13.1
Item
Particulars
(a)
Steady state
Superheater
Superheater
Outlet Pressure Outlet
Deviation
Temperature
Deviation
2
+ 0.2 kg/cm
+ 2.00C
Drum Level
Deviation (if
applicable)
+ 15mm
ISSUE
R0
NO.
TCE-4857A-C-
SHEET 22 OF 25
(b)
(c)
kg/cm2
kg/cm2
kg/cm2
kg/cm2
+ 30C
+ 50C
+ 80C
+ 100C
+ 15 mm
+ 20 mm
+ 25 mm
+ 50mm
+ 5.0 kg/cm2
+ 200C
+ 100 mm
+ 0.3
+ 0.5
+ 1.0
+ 1.5
3.0
MAINTENANCE REQUIREMENTS
3.1
The CONTRACTOR shall provide facilities for carrying out on-load and offload maintenance of the steam generators and its ancillaries. In general,
this should include adequate handling equipment, working space, platforms
and safety devices.
3.2
3.3
3.4
3.5
3.6
NO.
TCE-4857A-C-
SHEET 23 OF 25
provided. Access platforms, staircases and walkways with toe boards shall
be provided for all the critical equipment viz. soot blowers, air preheaters,
ID, FD, PA fans, valves of critical services, transmitter racks, junction boxes,
etc.
3.7
3.8
3.9
A pent house shall be formed above the roof of the steam generator for
attending to tubes and headers and thermocouples in this area. It shall be
of a hot design having the insulation on the outside of the casing to permit
it to expand and contact with the furnace walls. In order to avoid fly ash
infiltration, through the space around the tubes coming out from the furnace
in this area, all welded seals between furnace gas pass and pent house
shall be provided. Opening in the steam generator roof for introduction of
cables shall be extended through the pent house in the form of pipe
sleeves so that cables could be introduced without entering the pent house.
3.10
Pent house roof, enclosures at firing aisle platforms and at drum level shall
be covered with pre coated metal sheet.
3.11
Separate ventilation fans shall do the pent house cooling with air inlet
openings at opposite ends. The capacity of the fan shall be optimum for
safe and fast cooling of the pent house.
3.12
ISSUE
R0
NO.
TCE-4857A-C-
SHEET 24 OF 25
FANS
(a)
(b)
2 each
1
5
20
5 kg.m
35 kg.m
50 kg.m
Bearing pullers
(b)
2 sets
(c)
(d)
GRAVIMETRIC FEEDERS
(a)
Checking bar
2 Nos.
(b)
1 No.
(c)
1 No.
(d)
1 No.
ISSUE
R0
NO.
TCE-4857A-C-
SHEET 25 OF 25
(e)
Digital tachometer
1 No.
(f)
6 Nos.
SOOT BLOWERS
(a)
FUEL BURNERS
(a)
2 sets
2 sets
2 sets
(b)
(c)
4 nos.
(d)
1 no.
(e)
2 nos.
SAFETY VALVES
On line testing/setting device for safety
valves
OTHER ITEMS
(a)
Inclined manometer
(b)
Introscope
(c)
1 no.
ISSUE
R0