Академический Документы
Профессиональный Документы
Культура Документы
CONTENTS
Page
Contents
INTRODUCTION
1.
1.1
Management Responsibilities
1.2
1.3
2.
3.
4.
5.
2.1
Introduction
2.2
Project Manager
2.3
Appointed Person
2.4
Crane Supervisor
2.5
Crane Co-Ordinator
2.6
Operators
2.7
Slinger/Signallers
2.8
Fitters/Erectors
3.1
Tender Planning
3.2
Project Planning
3.3
Lift Planning
3.4
Contractual Considerations
10
3.5
Selection of Cranes
10
3.6
Siting of Cranes
11
3.7
11
3.8
12
3.9
12
13
SPECIALIST LIFTING
14
4.1
14
4.2
15
4.3
16
4.4
16
Page
Contents
6.
7.
8.
9.
TOWER CRANES
23
6.1
Introduction
23
6.2
Appointments
23
6.3
23
6.4
Foundation Design
25
6.5
27
6.6
28
6.7
Ties
28
6.8
Installation
28
6.9
Operation
30
33
35
35
36
7.1
Introduction
36
7.2
Daily Checks
36
7.3
Weekly Inspections
36
7.4
Maintenance
36
7.5
Thorough Examinations
36
7.6
Testing
36
7.7
Examination Schemes
37
7.8
37
7.9
Competent Person
37
RADIOS
38
8.1
Use of Radios
38
8.2
38
ELECTRICAL MATTERS
39
40
11. APPENDICES
41
Appendix 1 Bibliography
41
17
5.1
17
5.2
Visiting Mobiles
18
5.3
Excavators
18
5.4
19
Appendix 5 Glossary
52
5.5
Lorry Loaders
20
53
5.6
21
54
5.7
21
56
5.8
21
5.9
22
Foundations
45
47
INTRODUCTION
1.
1.1
MANAGEMENT RESPONSIBILITIES
1.3.1
1.2
1.3
1.3.2
Crane Co-ordinator
Appointed Person
(Lifting Operations)
Crane Co-ordinator
Tower Crane 1
Lifting Team
Tower Crane 2
Lifting Team
Mobile Crane 1
Lifting Team
Crane Supervisor
Operator
Slinger/Signaller(s)
Crane Supervisor
Operator
Slinger/Signaller(s)
Crane Supervisor
Operator
Slinger/Signaller(s)
Typical Organisation on a Multi Crane Site Structure (Derived from BS 7121 Pt 5 Fig 2)
1.3.3
1.3.4
2.
2.1
INTRODUCTION
2.2
PROJECT MANAGER
2.2.1
Duties
2.3
APPOINTED PERSON
2.3.1
Selection
2.3.2
Duties
2.4
CRANE SUPERVISOR
2.6
2.5
OPERATORS
CRANE CO-ORDINATOR
2.6.1
Operators must:
Check the crane before the start of each shift
2.8
2.7
SLINGER/SIGNALLERS
FITTERS/ERECTORS
3.
3.1
TENDER PLANNING
3.2.2
a.
PROJECT PLANNING
3.2.1
3.2
Briefing Sessions
b.
3.3
LIFT PLANNING
3.3.1
Basic Lifts
Bundles of rebar
Scaffold tubes
3.3.2
Standard Lifts
3.3.3
Complex Lifts
3.4.2
3.4
3.5
CONTRACTUAL CONSIDERATIONS
SELECTION OF CRANES
3.4.1
10
3.6.2
Proximity to Hazards
3.6
SITING OF CRANES
Airfields
3.6.1
Ground Conditions
3.7
11
5 Fresh Breeze
3.9
3.8
12
3.10
13
4.
SPECIALIST LIFTING
4.1
RAISING OR LOWERING
PERSONNEL (MAN RIDING)
Man riding can only be carried out on cranes: That preferably have a hydraulic or
electrical/electronic control system rather than a
mechanical/pneumatic one.
14
4.2
15
4.4
4.3
16
5.
5.1
5.1.3
5.1.4
5.1.1
5.1.2
Overloading
17
5.3
5.1.5
5.2
EXCAVATORS
VISITING MOBILES
18
Excavators used as
Excavators used as
as cranes
1 tonne or an
rated capacity of 1
overturning moment
tonne or less or an
overturning moment of
40,000 Nm or less
5.4
FORKLIFTS AND
TELESCOPIC HANDLERS
19
5.5
LORRY LOADERS
20
5.7.1
5.6
5.8
5.8.1
5.8.2
5.8.3
Side Booms
5.8.4
Drilling Derricks
5.7
5.8.5
Piling Rigs
21
5.8.6
In Summary
5.9
22
6.
TOWER CRANES
6.1
INTRODUCTION
6.2
APPOINTMENTS
6.3
TOWER CRANE
PLANNING PROCEDURE
The Location
Coverage
Capacity
Site Plan
Sections
23
6.3.2
Contract Stage
24
Ground conditions
Space available
Lifting capacities
Imposed foundation and tie-in forces for in-service,
out-of-service and erection/dismantling conditions
6.4
FOUNDATION DESIGN
6.4.1
Designer Qualifications
6.4.2
25
6.4.7
6.4.3
Standards
6.4.4
6.4.5
Design Certificate
6.4.6
26
6.5
6.5.1
Design Checker
6.4.8
Expendable Anchors
6.5.2
6.5.3
27
6.5.4
6.8.1
The Foundation
weld quality
6.7
INSTALLATION
6.6
6.8
TIES
6.8.1.1 Tower Crane Foundation/Grillage
Verification Form
6.8.2
28
6.8.3
6.8.3.1 General
Security
First aid
Welfare
Emergency services
29
6.8.4
6.9
OPERATION
6.9.1
6.9.2
30
6.9.3
6 hours
1 hour
10 hours
14 hours
2 hour
No. of Operators
31
6.9.5
6.9.4
32
6.9.6
6.10
33
34
6.11
6.12
35
7.
7.1
INTRODUCTION
7.5
7.2
DAILY CHECKS
7.3
WEEKLY INSPECTIONS
7.4
THOROUGH EXAMINATIONS
7.6
TESTING
MAINTENANCE
36
7.9
7.7
EXAMINATION SCHEMES
7.8
COMPETENT PERSON
37
RADIOS
8.1
USE OF RADIOS
8.2
38
ELECTRICAL MATTERS
9.
ELECTRICAL MATTERS
39
10
10.
c) Select Plant
Barford Road
Little Barford
St. Neots PE19 6WB
Telephone: 01480 407080
Fax: 01480 407899
Hire and installation of Tower Cranes, Crawler Cranes,
Mobile Cranes; Hire of Fire Extinguishers and
Surveying Instruments.
40
11
APPENDICES
APPENDIX 1 BIBLIOGRAPHY
Before using any document, check that it is the latest issue and includes any current amendments.
This list was reviewed in August 2007.
Regulations
The Lifting Operations and Lifting Equipment Regulations 1998 (LOLER)
The Construction (Design and Management) Regulations 2007
The Provision and Use of Work Equipment Regulations 1998 (PUWER)
Standards
BS 7121: Part 1:
BS 7121: Part 2:
BS 7121: Part 3:
BS 7121: Part 4:
BS 7121: Part 5:
CP 3010: 1972
2006
2003
2000
1997
2006
BS 1757:1986
BS 5744: 1979
BS 7262: 1990
BS 2573: Part 1: 1983
BS 8004: 1986
BS 8110:
I. Struct. E.: 1991
BS
BS
BS
BS
5950:
449: Part 2: 1969
6399: Part 2: 1997
7671:1992
CIRIA Guides
Special Publication 131
Special Publication 146
41
APPENDICES (cont)
Part 1
Part 2
42
43
APPENDICES (cont)
44
Where is it to be done?
Precise location.
Details of site features, layout and access, with notes on how these may affect
proposed arrangements and methods of working.
When is it to be done?
A detailed programme giving each stage of the operation and the dates on
which they will be carried out.
Who is to do it?
How is it to be done?
Arrangements for management of the erection/dismantling, including coordination with site and the responsibilities and authority of supervisory
personnel at all levels.
The detailed method of erecting/dismantling the crane (the erection scheme
should be devised to ensure that activities such as slinging, lifting, unslinging,
initial connection, alignment and final connecting can be carried out safely).
The scheme may be detailed by reference to the appropriate sections of the
manufacturers manual.
The provision of suitable cranage to assist in the operations including
arrangements for access, adequate siting and outrigger foundations.
Arrangements for delivery, stocking, storing and movement of components
on site.
Arrangements for examination and testing following erection.
List the identified hazards, who might be harmed and the precautions to
be taken including:
Measures to avoid interface problems with other site operations
(see Section 6.8.3).
Provisions to aid the prevention of falls from height including safe means of
access and safe places of work.
Protection from falls of materials, tools and debris.
Contingency arrangements should there be, for instance, high winds, a
breakdown of plant or components delivered out of sequence.
In order to highlight the hazards identified and draw together all of the control
measures specified within the Method Statement, a Site-specific Risk
Assessment must be completed.
References
The Method Statements should include a site layout showing the position of
the tower crane and mobile crane. It should also include any cross-references
to specific drawings, standard procedures, generic risk assessments, and
manufacturers manuals etc.
45
APPENDICES (cont)
The Method Statement must be dated, signed by the originator, and each page
numbered as page x of y.
Communications
The Method Statement must contain a distribution list of all parties to whom
the contents of the Method Statement must be communicated and must also
detail the arrangements for briefing those carrying out the work on site.
Approval
All tower crane Method Statements must be approved by CPES before the
commencement of work on site. At least five working days must be allowed
for this approval process. Additional time may be needed to allow site to carry
out their own approval process.
Amendments
46
A4.1
A4.3
PRE-ERECTION INSPECTION
SCOPE OF INSPECTION
All foundations
Cast-in Items
(foundation
anchors etc.)
Reinforced
Concrete
Piles
Steelwork
Rails
A4.2
RESPONSIBILITY
A4.4
REGULAR MONITORING
All Foundations
Level checks
Reinforced
Concrete
Steelwork
Rails
47
APPENDICES (cont)
A4.5
FREQUENCY
A4.6
RECORDS
Pre-erection inspection
A4.7
CERTIFICATION
48
49
APPENDICES (cont)
50
51
APPENDICES (cont)
APPENDIX 5 - GLOSSARY
Appointed Person
Oversail
Crane Driver/Operator
Owner
Crane Supervisor
Project Manager
Hirer
Slinger/Signaller
Lifting Accessories
LOLER refers to the commonly used term Lifting
Tackle as accessories for lifting and defines them as
52
UKAS/BSI
The United Kingdom Accreditation Service (UKAS)
and British Standards Institute (BSI) are recognized by
the British Government as the UK national bodies
responsible for assessing and accrediting the
competence of organisations in the fields of
calibration, measurement, testing, inspection, and the
certification of systems, personnel and products.
53
APPENDICES (cont)
Draft Letter to a Crane Supplier - Rigging of Large Mobile Cranes before Starting Lifting
We have recently placed an order with you for the provision of a (type) mobile crane at our (name)
site on (date). As you are aware, before starting lifting the crane will require rigging in (name of road).
(Crane suppliers name) are responsible for the safe execution of this work which includes
responsibility for:
1. Provision of a safe system of work to protect both your employees and others not employed by
you. This should include a risk assessment to identify all hazards associated with the work and
the provision of appropriate measures to reduce any risks identified to an acceptable level.
2. Provision of suitably trained and briefed personnel, adequately supervised to ensure that the
safe system of work is carried out effectively.
3. Arrangements for the protection of the public.
Yours, etc.
A7.1
A7.4
PURPOSE
A7.2
SCOPE
A7.3
DEFINITIONS
A7.5
PROCEDURES
A7.5.1 Acquisition
When a Project Manager requires an item of lifting
accessories he should consult with either Select Plant
Technical Services or the Engineering & Temporary
Works Office (ETWO) or other specialist, to draw up a
specification for the equipment.
LEGAL REQUIREMENTS
54
or
55
APPENDICES (cont)
22. Ensure the load and the pads are cleaned correctly
prior to applying the lifter. Failure to do so
increases the chances of load slippage and rapidly
degrades the vacuum system
56
57