Inward:
Proposed process (Flow Chart) at Security level check:
No
Yes
Reports to Purchase /
Updates in the MIS of Bills
pending at Gate
NO
YES
YES
1. Separate stock storage for different plants is something which is in our scope
but at least in SAP should be implemented something similar as fig.1
FIG-1
Bearings 6309-----4
Central Store
Power Plant
Bearings 6309----2
Bearings 6309----0
Pellet Plant
Bearings 6309----2
IOBP
SID
Bearings 6309----0
2. If the material is required by the other dept then we could have a inter plant
transaction with a foolproof technique(Approval and remaining necessary
action) Which could help in having a check against the Inventory level(A dept
raising a Purchase indent even if there is stock in the other dept stock)
3. We shall have a technique that the material Stock shall be reflected at user
Material type,bin,dept level ,Central Store Level and also cost center
basis(like differentiation between a capital good and revenue).