Академический Документы
Профессиональный Документы
Культура Документы
3. HIGHWAY PROJECT
Introduction
Transportation is a vital infrastructure for the speedy economic growth of a
developing country. Road transportation is one of the important modes of transport
having many desirable characteristics. Such as flexibility, door to door service and
accessibility to remote area.
Road networks are rightly called the arteries of a country. Road system influences all
the aspects of human life. Road systems are very necessary for economic
development, spreading of human habitation, meet strategic purposes, etc.
In the present era planning is considered as pre-requisite and basic need for any new
project or an expansion program. Thus highway planning is also a basic need for any
highway development. Since, we have undertaken HIGHWAY PROJECT as our
project work; we have considered the following objectives.
i.
ii.
iii.
iv.
v.
vi.
Proposal
This project deals with the design of road and can be executed in following manners.
i.
A road was selected and detailed surveys including cross section and
ii.
iii.
Page 1
HIGHWAY PROJECT
The geometric design of a highway deals with the dimensions and layout of visible
features of highway such as alignment, sight distance, curves, super elevation and
intersections etc. the geometrics of highway should be designed to provide optimum
efficiency in traffic operation with maximum safety at reasonable cost. The designed
may be exposed to planning of new highway network to meet the requirement of the
anticipated traffic. The design is also includes the sizes of drainage, aggregate, cross
slopes, super elevation etc.
Obligatory Points
These are divided into two types
a. Obligatory points through which the alignment should pass
b. Points through which the alignment should not pass. These will cause the
alignment often deviated from the shortest or easiest path.
Traffic
The proposed alignment should suit the traffic requirement. Origin and destination
study should be carried out in the area and desire lines be drawn showing the trend of
traffic flow. The new road to be aligned should keep in view traffic flow pattern and
future trends.
Geometric Design
Geometric design factors such as gradients, Radius of the curve and sight distance
also would govern final alignment of highway. If straight alignment is aimed at, often
it may be necessary to provide very steep gradients. As for as possible while aligning
a new road, the gradient should be flat and less than the ruling or design gradient.
Thus it may be necessary to change the alignment in view of design sped, maximum
allowable super elevation and coefficient of lateral friction. It may be necessary to
make the adjustment in the horizontal alignment of road keeping view the minimum
radius of the curve and the transition curve.
Page 2
HIGHWAY PROJECT
Economy
The alignment should be economical. The initial cost, maintenance cost and vehicle
operation cost should be minimum, high embankment or deep cutting are avoided and
choose the balance cutting and filling sight. These factors also control the alignment
of road.
Map Study
Map study gives a guidance of routes to be surveyed in the field. The main features
like river, hills and valleys, etc. are known by map study. B y careful study of maps,
the idea of aligning a new highway can be obtained.
Reconnaissance Survey
In this survey, the land along the various proposed highway routes are inspected. All
the relevant details not available in the map are collected and noted down
Preliminary Survey
This is carried out to collect all the physical informations, which is necessary in
connections with the proposed highway alignment. The quantity of earth work and
cost of construction are worked out. The best proposal is selected after preliminary
survey.
Detailed Survey
After preliminary survey, a detailed survey is carried out. Here temporary bench
marks are fixed and leveling works are performed. Here an elaborate and complete
data are collected for preparing detailed plan and estimate the project.
Page 3
HIGHWAY PROJECT
i.
ii.
iii.
Horizontal curves
Vertical curves
Transition curves
Horizontal Curve
A horizontal highway curve is a curve in plan to provide change in direction to the
central line of a road. Horizontal curves are further divided into following.
i.
ii.
iii.
Vertical Curve
In order to have smooth vehicle movement on the roads, the changes in the grade
should be smoothened out by the vertical curves.
Vertical curves may be classified as
i.
ii.
Transition Curves
A transition curve has a radius which decreases from infinity at the tangent point to a
designed radius of the circular curve. When a transition curve is introduced between a
straight and circular curve, the radius of the circular curve decreases, becomes
minimum at the beginning of the circular curve.
Different types of transition curves are
i.
ii.
iii.
Spiral
Lemniscates
Cubic parabola
Surveying Details
Introduction
In a road survey the first step is leveling. The leveling work is carried out using
instruments such as dumpy level, cross staff and leveling staff. Other instruments such
Page 4
HIGHWAY PROJECT
as prismatic compass to find the bearings of alignments, arrows and ranging roads to
mark the points on the field are also used.
The road is aligned by two operations
i.
ii.
Longitudinal sectioning
Cross sectioning
Wherever there is necessity of providing a culvert, block leveling of the area is carried
out.
Cross Sectioning
Cross sections are run at right angles to the horizontal profile and at either side of it
for the purpose of lateral outline of the road surface.
Contouring
On a plan, the relative altitudes of the points can be represented by contour lines as
they indicate the elevators directly. The area to be surveyed is divided into a number
of squares. The levels on the corner of these squares are determined using direct
leveling. The contour interpolation is done by graphical methods.
EXTENSIVE SURVEY PROJECT REPORT - 2016
Page 5
HIGHWAY PROJECT
ii.
longitudinal direction.
Skid - It occurs when the wheel slide without revolving. Skid is of two
iii.
iv.
Classification of Terrain
The classification of terrain is normally done by means of the cross slope of the
country, viz the slope approximately perpendicular to the centerline of the highway
location. The following classification is generally followed.
Table 1.
Sl. No
Terrain classification
Page 6
Percent
country
cross
slope
of
HIGHWAY PROJECT
Level
0-10
Rolling
10-25
Mountainous
25-60
Steep
Greater than 60
An extensive survey of 42000km of roads India as part of the Road User Cost Study
has enabled the development of the following system of terrain classification:
Table 2. Terrain classification suggested in Road User Cost Study
Sl.No
Curvature
(m/km)
(deg/km)
a)low curvature
0-15
0-50
b)high curvature
Rolling
0-15
Above 51
16-30
0-100
16-30
Above 101
a)low curvature
Over 31
0-200
b)high curvature
Over 31
Above 201
Terrain classification
Plain
a)low curvature
b)high curvature
Hilly
1 +2 +3 ++n +
Average Curvature of section AB, CV= DISTANCEAB ( KM ) , Expressed in
m
Degrees/km
h1 +h2 +h
3+ + hn+h
Page 7
, Expressed in
HIGHWAY PROJECT
616 0
Therefore, average curvature of section AB, CV= 1.5
Therefore, average Rise and fall of section AB, RF=
=410 Degrees/km
60.94
1.01
= 60.33meter/km
iv.
Cement
concrete
of rainfall range
Heavy
Low
and
high
type
bituminous surface
2
pavement
Earth
1 in 50
1 in 60
1 in 40
1 in 50
1 in 33
1 in 40
1 in 25
Page 8
in 33
HIGHWAY PROJECT
Roadway wi
Sl.no.
Road classification
12.0
7.5
12.0
Design Speed
The design speed is the main factor on which geometric design elements depends. The
sight distances, radius of horizontal curve, super elevation, extra widening of
pavement, length of horizontal transition curve and the length of summit and valley
curve are all dependent on design speed. The design speed of roads depends on class
of the road and terrain.
Table 5.Design Speed on Highway
Design speed in mph for various terrains
Road
classification
Plain
Ruling
Rolling
Min.
Ruling
Min.
Page 9
Mountainous
Steep
Ruling
Ruling
Min.
Min.
HIGHWAY PROJECT
National and
100
state highway
80
80
65
50
40
40
30
Gradient
The slope of the road pavement in the longitudinal direction is called grade or
gradient. It may be expressed either as a ratio or rise or fall in a specified horizontal
distance, or as percentage of rise or fall.
Depending on the steepness of the road pavement, the gradients are categorized as
follows:
i.
ii.
iii.
iv.
Ruling gradient
Limiting gradient
Exceptional gradient
Minimum gradient
Ruling gradient
Limiting gradient
Exceptional gradient
3.3%(1 in 30)
5%(1 in 20)
6.7%(1 in 15)
6%(1 in 16.7)
7%(1 in 14.3)
7%(1 in 14.3)
8%(1 in 25)
having
6%(1 in 16.7)
Right of Way:
Right of Way is the area of land required for the road, along its alignment.
The land width is governed by following factor Width of formation depending on the
category of highway and width of roadway and road margins.
1. Height of embankment, side slopes, drainage system and sight distances.
Table 7.Recommended land width of different roads:
EXTENSIVE SURVEY PROJECT REPORT - 2016
Page 10
HIGHWAY PROJECT
SL.NO. Road
Mountains
Classification
Steep terrain
Open areas
Normal
1.
and
Built areas
Open
Built
areas
areas
Range Normal
Range Normal
Range
30-60
30
30-60
24
20
district 25
25-30
20
15-25
18
15
district 15
15-5
15
15-20
15
12
12-18
10
12-15
National
and 45
State highways
2.
Major
Roads
3.
Other
Roads
4.
Village Roads
12
Super elevation
In order to counteract the effect of centrifugal force and to reduce the tendency of the
vehicle to overturn or skid, the outer edge of pavement is raised with respect to the
inner edge, thus providing a transverse slope throughout the length of the horizontal
curve. This transverse inclination to the pavement surface is known as super
elevation.
Super Elevation
To counter act the effect of centrifugal force and to reduce the tendency of vehicle to
overturn of skid the outer edge of pavement is raised with respect to inner edge. Such
provision of transverse slope is provided on horizontal curves. The design of super
elevation is illustrated as below.
Extra Widening
EXTENSIVE SURVEY PROJECT REPORT - 2016
Page 11
HIGHWAY PROJECT
Extra widening is provided to provide extra space required for mechanical and
psychological reasons along the horizontal curves, which is provided as per the table
below:
Vertical Alignment
When two different or contrary gradients meet, they are connected by a curve in the
vertical plane known as vertical curve. These ar4e needed to secure a gradient change
in grade so that abrupt change in grade at the apex is not allowed. The vertical curves
used in highway may be classified into two categories.
i.
ii.
Summit curve
Valley curve
Summit Curve
A curve with convexity upwards is called a summit curve. This occurs when an
ascending intersect a descending gradient or when an ascending meets on other
ascending gradient or an ascending gradient meeting a horizontal a summit curve is
Page 12
Ext
1.5
1.5
1.2
0.9
0.6
Nil
HIGHWAY PROJECT
Valley Curve
A vertical curve, concave upwards is called as valley curve. This is formed when
descending gradient intersect an ascending gradient or when a descending gradient
meets another descending gradient or when a descending gradient gains a horizontal
path, they should be designed for:
i. Comfort
ii. Head light sight distance condition
Pavement Design
For the safety and comfort ability of fast vehicles road surface should be even along
the longitudinal profile. The surface should also so be stable and unyielding in
different conditions and it should allow the heavy load of traffic to move with least
possible resistance. In order to provide a stable and even surface for traffic the road
way is provided with a suitably designed and constructed pavement structure.
Pavement is designed and to distribute wheel load in larger area and elastic
deformation caused by the load to fall within the permissible limit.
Page 13
HIGHWAY PROJECT
13 . 89
SSD = (13.89X2.5) + 2 x 9. 81 x 0 . 35
SSD = 62.205m
OSD Calculation
Here, overtaking
V= 50.0kmph
V = (50/3.6) = 13.89 m/s (overtaking)
Vb= V-16
= 50.00-16 = 34kmph
V = (34/3.6) = 9.44 m/s
t= 2.5 sec
A= 4 kmph
f= 0.35
d1=0.278 x Vb+ t
= (0.278x34.00+6) = 15.452m
S=0.2 x Vb+ 6
=0.2x34+6
=12.8 m
T=
14 . 4 + S
A
T=
14.4+ 12.8
4
= 2.607 sec
b= 0.278xVbxT
Page 14
HIGHWAY PROJECT
= 0.278x34x2.607
= 24.641 m
d2=b+2s
=24.641+2x12.8
=50.241 m
OSD = for one way (means two lane)
OSD = d1+ d2
=15.452+50.241
OSD = 65.693 m
R=
V2
127 ( e+ f )
As per IRC the design speed for mountainous terrain is taken as 50kmph, e=7% and
f=0.15
R=
502
127 ( 0.07 +0.15 )
R = 89.477m
Therefore, take R = 90m
2
V
225 R
e=
50
225 X 90
e = 0.123
Obtained value of e is more than the permissible value 0.07. Therefore adopt
e = 0.07 and check for lateral coefficient of friction,
Page 15
HIGHWAY PROJECT
f=
V
127 R
f=
50
(127 X 90)
-e
2
0.07
f = 0.148
Obtained value of f is less than the permissible value 0.15. Therefore, e = 0.07 is safe
for design speed of 50kmph.
80
75+ V
C=
80
75+ 50
3
C = 0.64 m/ sec
Obtained value of c should lie between 0.5 and 0.8 as recommended by IRC.
Therefore
3
c = 0.64 m/ sec
is adopted.
LS
V3
46 .5 xCxR
Page 16
HIGHWAY PROJECT
LS
50
0.64 X 90 X 46.5
LS =46.669M
B=W+
We
1 X 62
2 X 90
We
n l2
2R
V
9. 5 R
50
9.5 90
W e =0.755m
B=3.75+0.755
B=4.505m
Allowable rate of introduction of super elevation = 1 in 60, pavement to be rotated
about the inner edge to effect better drainage.
Now, E=B x e Where B=4.505m, e=0.07
E=4.505 x .07
E=0.315
Now length of the transition curve is given by
LS
Page 17
= E xN
HIGHWAY PROJECT
LS = 0.315X60
LS = 18.921 m
LS
is given by
LS
2.7 X 50 2
=
90
LS
2.7V
=
R
as per IRC.
LS = 75.0m
Therefore adopt length of transition curve= 75.0m
Design of Culvert
To design the culvert the discharge and velocity are assumed to be 1.2 m
m/sec.
To find the diameter of the pipe,
Q
A= V
1.2
A= 2
2
A= 0.6 m
But A=
d
4
Page 18
/sec and 2
HIGHWAY PROJECT
d
4
d = 0.874m
=0.6
Therefore adopt internal diameter=0.900m.To find the external diameter of the pipe
add 0.1m to internal diameter. Therefore D=1.000m.
Assume length of each pipe=3m, but road width=12m. Therefore four numbers of
pipes are required.
Extra Widening:
Assume
L= 6.0m
n= 1 lane
Extra widening is given by
We
1 X 62
2 X 90
We
n L2
2R
V
9. 5 R
50
9.5 90
= 0.775m
Therefore, total pavement width on curve
W+We = 3.75+0.775
= 4.525m
Page 19
HIGHWAY PROJECT
Road length
Design speed
Width of pavement
Width of roadway
Width of shoulder
Right of way
Soil type throughout the route
Pavement
Culvert (diameter of pipe)
Length of transition curve
: 1100m
: 50Kmph
: 3.75m
: 12.0m
: 1.0m
: 24m
: Gravelly soil
: Flexible
: 1.00m
: 75.00m
Chainage
Length
Area
(m)
(m)
Quantity=A*L
(m3)
(m2)
Cutting
Filling
Cutting
Filling
2.651
0.970
2.651
0.970
30
30
0.176
5.332
5.28
159.96
40
10
6.332
------
63.32
------
60
20
9.419
------
188.38
------
80
20
10.187
------
203.74
------
90
30
10.946
------
328.38
------
120
30
17.996
------
539.88
------
140
20
36.500
-----
730
------
Page 20
HIGHWAY PROJECT
150
10
36.220
------
362.2
------
10
180
30
44.312
------
1329.36
------
11
210
30
53.615
------
1608.45
------
12
230
20
37.665
------
753.3
------
13
240
10
41.574
------
415.74
------
14
270
30
40.271
------
1208.13
------
15
280
10
24.858
------
248.58
------
16
300
20
25.89
------
507.78
------
17
330
30
13.168
------
395.04
------
18
340
10
1.515
0.031
15.15
0.31
19
360
20
0.176
5.332
3.52
106.64
20
390
30
------
70.333
------
2109.99
21
410
20
------
124.046
------
2480.92
22
420
10
------
161.674
------
1616.74
23
430
10
------
120.837
------
1208.37
24
450
20
------
74.142
------
1482.84
25
480
30
------
61.599
------
1847.97
26
490
10
------
81.167
------
811.67
27
510
20
------
65.492
------
1309.84
28
540
30
------
90.328
------
2709.84
29
570
30
------
94.892
------
2846.76
30
590
20
------
100.169
------
2003.38
31
600
10
------
105.553
------
1055.53
32
630
30
------
138.348
------
4150.44
33
640
10
------
135.211
------
1352.11
34
660
20
------
92.556
------
1851
Page 21
HIGHWAY PROJECT
35
690
30
0.721
15.125
21.63
453.75
36
720
30
38.987
------
1169.61
------
37
750
30
95.429
------
2862.87
------
38
760
10
111.47
------
1114.47
------
39
780
20
92.430
------
1848.6
------
40
810
30
87.617
------
2628.51
-----
41
830
20
85.630
------
1712.6
------
42
840
10
67.088
------
670.88
------
43
870
30
53.644
------
1609.32
------
44
900
30
49.318
------
1479.54
------
45
930
30
57.327
------
1719.81
------
46
960
30
67.681
------
2030.43
------
47
990
30
77.072
------
2312.16
------
48
1000
10
70.093
------
700.93
------
49
1030
30
69.377
------
2081.31
------
50
1050
20
85.327
------
1706.54
------
51
1080
30
87.730
-------
2631.9
------
Page 22