S/No.
Analysis and recommendation
1Technical Sanction (T.S) is required in advance for the
commencement of work and as per saying of the Sub
Divisional Officer of the C&W that technical sanction is
under process of approval this distinctly point that the
executing department is deliberately delaying the process
of T.S so as to cover the lapses in planning and
implementation of the scheme It is recommended that the
executing department should assure the process of T.S
without any further loss of time.
Replies
Technical sanction of the scheme has been
submitted to the Superintending Engineer C&W
Circle Mardan for approval and will be available
for verification in short time.