Академический Документы
Профессиональный Документы
Культура Документы
Picture 2: Probability Distributions: left side a normal distribution, right side a yes-no distribution.
In the example of the upgrade, a task of exporting all data from databases might take 20 hours or
somewhere between 18 and 25 hours, with the most likely value of 20 hours. This probability
distribution would look likely like Picture 3.
Probability is the likelihood of an event. Coin flipping - 50% probability the guess is correct - two possible and
equally likely outcomes.
2
Risk is the uncertainty or variability in the outcome of an event; often related to a possible undesired effect
or significant loss. Almost any change, good or bad, poses some risk.
When the model is ready, the input values do not vary need to be identified because those that do
not change cannot be modeled. For example, fixed values such as VAT% do not change, so we cant
model a 10% in trail 1 and a 12% in trail 2. That does not make sense.
Assumptions
In the next step, the input values become assumptions. In this example, a triangular distribution type
is taken and the minimum and maximum duration given per task.
Task
Duration in hours
Most likely
Minimum
Maximum
Installation on new hardware 60
40
80
Transfer of repositories
10
8
12
Export data
20
18
25
Import data
10
9
12
Testing
10
5
12
Total hours
110
80
141
Table 3: Application upgrade model with variables
Distribution type
Triangular
Triangular
Triangular
Triangular
Triangular
With a different distribution type, the assumption on the task export data looks different and will
give different results. Crystal Ball has more than 40 different distribution types and with data,
specific distribution types can be created as well.
Forecast value
The forecast value or values are those cells in the model that contain a formula and are derived from
a calculation. In our example, total hours is the forecast value and a sum of all tasks. As we see,
this value is somewhere between 80 and 141 hours. The most likely value is 110 hours. What will the
simulation show? What will be the likelihood of spending more than, lets say, 120 hours on the
upgrade project?
Simulation
The simulation is set to run 10.000 trails. In each trail, CB will pick random one value for each
assumption from their distribution. When this placed into the Excel model, the total hours are
calculated. The result is captured into the result set. Then the next trail starts, and again CB will pick
one random value for each assumption from their distribution.
This will be done until 10.000 trails have been executed and 10.000 results are in the result set. Then
these data values of the result set are displayed and statistical logics applied.
The result is shown in Picture 5 and shows a probability of 14.45% the upgrade will take more than
120 hours.
And now?
A given spreadsheet model could maybe further be extended into areas in which modelling makes
sense. Another option is to make the model and assumptions dynamic. This makes it better readable
and adjustments are easier.
Because the assumptions are the backbone of the model, improving them is likely possible,
especially when actuals become available or new insights are gathered.