INGENIERIA CIVIL
25 cm.
1*4.25/2 = 2.125 m2
-Parapeto:
Peso propio = (1)(0.9)(0.25)(1800) = 405 Kg.
-Losa aligerada:
Peso propio
= 350 Kg/m 2
Peso de acabados
= 100 Kg/m 2
Tabiquera
= 100 Kg/m 2
Carga Muerta (CM) = 550 Kg/m 2
Peso de losa = (550 Kg/m 2 ) (2.125 m2) = 1168.75 Kg/m.
-Viga solera o principal:
Peso propio = (0.25) (0.25) (1.00) (2400) = 150 Kg/m.
-Muro de 2.30m:
Peso propio = (1800) (2.30) (0.25) (1.00) = 1035 Kg/m.
-Sobrecarga o carga viva = 200.00Kg/m 2 (2.125 m2) =425 Kg/m.
Peso total del segundo nivel:
1
P2 = 3183.75 Kg/m.
PRIMER NIVEL:
rea de Influencia:
1*4.25/2 = 2.125 m2
-Losa aligerada:
Peso propio
= 350 Kg/m 2
Peso de acabados
= 100 Kg/m 2
Tabiquera
= 100 Kg/m 2
Carga Muerta (CM) = 550 Kg/m 2
Peso de losa = (550 Kg/m 2 ) (2.125 m2) = 1168.75 Kg/m.
-Viga solera o principal:
Peso propio = (0.25) (0.25) (1.00) (2400) = 150 Kg/m.
-Muro de 3.75m:
Peso propio = (1800) (3.75) (0.25) (1.00) = 1687.5 Kg/m.
-Sobrecarga o carga viva = 500 Kg/m 2 (2.125 m2) = 1062.5 Kg/m.
Peso total del primer nivel:
P1 = 4068.75 Kg/m.
-Sobrecimiento:
Peso propio = (0.25)(0.30)(1)(2400) = 180 Kg/m.
PESO PARCIAL = 7432.5 kg/m.
-Cimiento:
Peso propio = (10%)(7432.5) = 743.25 Kg/m.
PESO TOTAL = 8175.75 Kg/m.
-Calculo de cimentacin:
A = b*1m = P /
b = 8175.75 / (0.8*10000)
b = 1.02m. 1m.(Zapata)
tramo 2-3:
SEGUNDO NIVEL:
rea de Influencia:
1*4.25/2 = 2.125 m2
-Parapeto:
Peso propio = (1m)(0.9m)(0.25m)(1800kg/m3) = 405 Kg./m
-Losa aligerada:
Peso propio
= 350 Kg/m 2
Peso de acabados
= 100 Kg/m 2
Tabiquera
= 100 Kg/m 2
Carga Muerta (CM) = 550 Kg/m 2
Peso de losa = (550 Kg/m 2 ) (2.125 m2) = 1168.75 Kg/m.
-Viga solera o principal:
Peso propio = (0.25) (0.25) (1.00) (2400) = 150 Kg/m.
-Muro de 2.30m:
Peso propio = (1800) (2.30) (0.25) (1.00) = 1035 Kg/m.
-Sobrecarga o carga viva = 200.00Kg/m 2 (2.125 m2) =425 Kg/m.
Peso total del segundo nivel:
P2 = 3183.75 Kg/m.
PRIMER NIVEL:
rea de Influencia:
1*4.25/2 = 2.125 m2
-Losa aligerada:
Peso propio
= 350 Kg/m 2
Peso de acabados
= 100 Kg/m 2
Tabiquera
= 100 Kg/m 2
Carga Muerta (CM) = 550 Kg/m 2
Peso de losa = (550 Kg/m 2 ) (2.125 m2) = 1168.75 Kg/m.
b = 8175.75 / (0.8*10000)
b = 1.02m. 1m. (zapata)
tramo 2-3:
SEGUNDO NIVEL:
rea de Influencia:
1*4.25/2 = 2.125 m2
-Parapeto:
Peso propio = (1)(0.9)(0.25)(1800) = 405 Kg.
-Losa aligerada:
Peso propio
= 350 Kg/m 2
Peso de acabados
= 100 Kg/m 2
Tabiquera
= 100 Kg/m 2
Carga Muerta (CM) = 550 Kg/m 2
Peso de losa = (550 Kg/m 2 ) (2.125 m2) = 1168.75 Kg/m.
-Viga solera o principal:
4
1*4.25/2 = 2.125 m2
-Losa aligerada:
Peso propio
= 350 Kg/m 2
Peso de acabados
= 100 Kg/m 2
Tabiquera
= 100 Kg/m 2
Carga Muerta (CM) = 550 Kg/m 2
Peso de losa = (550 Kg/m 2 ) (2.125 m2) = 1168.75 Kg/m.
-Viga solera o principal:
Peso propio = (0.25) (0.25) (1.00) (2400) = 150 Kg/m.
-Muro de 3.75m:
Peso propio = (1800) (3.75) (0.25) (1.00) = 1687.5 Kg/m.
-Sobrecarga o carga viva = 500 Kg/m 2 (2.125 m2) = 1062.5 Kg/m.
Peso total del primer nivel:
P1 = 4068.75 Kg/m.
-Sobrecimiento:
Peso propio = (0.25)(0.30)(1)(2400) = 180 Kg/m.
PESO PARCIAL = 7432.5 kg/m.
-Cimiento:
Peso propio = (10%)(7432.5) = 743.25 Kg/m.
PESO TOTAL = 8175.75 Kg/m.
-Calculo de cimentacin:
A = b*1m = P /
5
b = 8175.75 / (0.8*10000)
b = 1.02m. 1m. (zapata)
tramo 3-4:
SEGUNDO NIVEL:
rea de Influencia:
1*4.25/2 = 2.125 m2
-Parapeto:
Peso propio = (1)(0.9)(0.25)(1800) = 405 Kg/m.
-Losa aligerada:
Peso propio
= 350 Kg/m 2
Peso de acabados
= 100 Kg/m 2
Tabiquera
= 100 Kg/m 2
Carga Muerta (CM) = 550 Kg/m 2
Peso de losa = (550 Kg/m 2 ) (2.125 m2) = 1168.75 Kg/m.
-Viga solera o principal:
Peso propio = (0.25) (0.25) (1.00) (2400) = 150 Kg/m.
-Muro de 2.30m:
Peso propio = (1800) (2.30) (0.25) (1.00) = 1035 Kg/m.
-Sobrecarga o carga viva = 200.00Kg/m 2 (2.125 m2) =425 Kg/m.
Peso total del segundo nivel:
P2 = 3183.75 Kg/m.
PRIMER NIVEL:
rea de Influencia:
1*4.25/2 = 2.125 m2
-Losa aligerada:
Peso propio
= 350 Kg/m 2
6
Peso de acabados
= 100 Kg/m 2
Tabiquera
= 100 Kg/m 2
Carga Muerta (CM) = 550 Kg/m 2
Peso de losa = (550 Kg/m 2 ) (2.125 m2) = 1168.75 Kg/m.
-Viga solera o principal:
Peso propio = (0.25) (0.25) (1.00) (2400) = 150 Kg/m.
-Muro de 3.75m:
Peso propio = (1800) (3.75) (0.25) (1.00) = 1687.5 Kg/m.
-Sobrecarga o carga viva = 500 Kg/m 2 (2.125 m2) = 1062.5 Kg/m.
Peso total del primer nivel:
P1 = 4068.75 Kg/m.
-Sobrecimiento:
Peso propio = (0.25)(0.30)(1)(2400) = 180 Kg/m.
PESO PARCIAL = 7432.5 kg/m.
-Cimiento:
Peso propio = (10%)(7432.5) = 743.25 Kg/m.
PESO TOTAL = 8175.75 Kg/m.
-Calculo de cimentacin:
A = b*1m = P /
b = 8175.75 / (0.8*10000)
b = 1.02m. 1m. (Zapata)
tramo 4-5:
SEGUNDO NIVEL:
rea de Influencia:
1*4.25/2 = 2.125 m2
-Parapeto:
Peso propio = (1)(0.9)(0.25)(1800) = 405 Kg.
-Losa aligerada:
Peso propio
= 350 Kg/m 2
7
Peso de acabados
= 100 Kg/m 2
Tabiquera
= 100 Kg/m 2
Carga Muerta (CM) = 550 Kg/m 2
Peso de losa = (550 Kg/m 2 ) (2.125 m2) = 1168.75 Kg/m.
-Viga solera o principal:
Peso propio = (0.25) (0.25) (1.00) (2400) = 150 Kg/m.
Peso de la reaccin de la escalera= 30.39kg/m
-Muro de 2.30m:
Peso propio = (1800) (2.30) (0.25) (1.00) = 1035 Kg/m.
-Sobrecarga o carga viva = 200.00Kg/m 2 (2.125 m2) =425 Kg/m.
Peso total del segundo nivel:
P2 = 3214.14 Kg/m.
PRIMER NIVEL:
rea de Influencia:
1*4.25/2 = 2.125 m2
-Losa aligerada:
Peso propio
= 350 Kg/m 2
Peso de acabados
= 100 Kg/m 2
Tabiquera
= 100 Kg/m 2
Carga Muerta (CM) = 550 Kg/m 2
Peso de losa = (550 Kg/m 2 ) (2.125 m2) = 1168.75 Kg/m.
-Viga solera o principal:
Peso propio = (0.25) (0.25) (1.00) (2400) = 150 Kg/m.
Peso de la reaccin Cde la escalera del primer nivel= 625.85 kg/m
Peso de la reaccin A de la escalera del segundo piso=2008.59 kg/m
-Muro de 3.75m:
Peso propio = (1800) (3.75) (0.25) (1.00) = 1687.5 Kg/m.
-Sobrecarga o carga viva = 500 Kg/m 2 (2.125 m2) = 1062.5 Kg/m.
Peso total del primer nivel:
P1 = 6703.19 Kg/m.
-Sobrecimiento:
8
b = 11107.06/ (0.8*10000)
b = 1.38m. 1.40m. (zapata)
2.2.- Metrado de cargas en el eje B-B
tramo 1-2:
SEGUNDO NIVEL:
rea de Influencia:
1*(4.25/2+4/2) = 4.125 m2
-Parapeto:
Peso propio = (1)(0.9)(0.25)(1800) = 405 Kg.
-Losa aligerada:
Peso propio
= 350 Kg/m 2
Peso de acabados
= 100 Kg/m 2
Tabiquera
= 100 Kg/m 2
Carga Muerta (CM) = 550 Kg/m 2
Peso de losa = (550 Kg/m 2 ) (4.125 m2) = 2268.75 Kg/m.
-Viga solera o principal:
Peso propio = (0.25) (0.25) (1.00) (2400) = 150 Kg/m.
-Muro de 2.30m:
Peso propio = (1800) (2.30) (0.25) (1) = 1035 Kg/m.
-Sobrecarga o carga viva = 200.00Kg/m 2 (4.125 m2) = 825 Kg/m.
Peso total del segundo nivel:
P2 = 4683.75 Kg/m.
PRIMER NIVEL:
rea de Influencia:
1*(4.25/2+4/2) = 4.125 m2
-Losa aligerada:
Peso propio
= 350 Kg/m 2
Peso de acabados
= 100 Kg/m 2
Tabiquera
= 100 Kg/m 2
Carga Muerta (CM) = 550 Kg/m 2
Peso de losa = (550 Kg/m 2 ) (4.125 m2) = 2268.75 Kg/m.
-Viga solera o principal:
Peso propio = (0.25) (0.25) (1.00) (2400) = 150 Kg/m.
-Muro de 3.75m:
Peso propio = (1800) (3.75) (0.25) (1.00) = 1687.5 Kg/m.
-Sobrecarga o carga viva = 500 Kg/m 2 (4.125 m2) = 2062.50 Kg/m.
Peso total del primer nivel:
P1 = 6168.50 Kg/m.
-Sobrecimiento:
Peso propio = (0.25)(0.30)(1)(2400) = 180 Kg/m.
PESO PARCIAL = 11032.25 kg/m.
-Cimiento:
Peso propio = (10%)(11032.25) = 1103.225 Kg/m.
PESO TOTAL = 12135.475 Kg/m.
-Calculo de cimentacin:
A = b*1m = P /
b = 12135.475/ (0.8*10000)
b = 1.52m. 1.50m. (zapata)
tramo 2-3:
10
SEGUNDO NIVEL:
rea de Influencia:
1*(4.25/2+4/2) = 4.125 m2
-Parapeto:
Peso propio = (1)(0.9)(0.25)(1800) = 405 Kg.
-Losa aligerada:
Peso propio
= 350 Kg/m 2
Peso de acabados
= 100 Kg/m 2
Tabiquera
= 100 Kg/m 2
Carga Muerta (CM) = 550 Kg/m 2
Peso de losa = (550 Kg/m 2 ) (4.125 m2) = 2268.75 Kg/m.
-Viga solera o principal:
Peso propio = (0.25) (0.25) (1.00) (2400) = 150 Kg/m.
-Muro de 2.30m:
Peso propio = (1800) (2.30) (0.25) (1) = 1035 Kg/m.
-Sobrecarga o carga viva = 200.00Kg/m 2 (4.125 m2) = 825 Kg/m.
Peso total del segundo nivel:
P2 = 4683.75 Kg/m.
PRIMER NIVEL:
rea de Influencia:
1*(4.25/2+4/2) = 4.125 m2
-Losa aligerada:
Peso propio
= 350 Kg/m 2
Peso de acabados
= 100 Kg/m 2
Tabiquera
= 100 Kg/m 2
Carga Muerta (CM) = 550 Kg/m 2
Peso de losa = (550 Kg/m 2 ) (4.125 m2) = 2268.75 Kg/m.
-Viga solera o principal:
Peso propio = (0.25) (0.25) (1.00) (2400) = 150 Kg/m.
-Muro de 3.75m:
Peso propio = (1800) (3.75) (0.25) (1.00) = 1687.5 Kg/m.
-Sobrecarga o carga viva = 500 Kg/m 2 (4.125 m2) = 2062.50 Kg/m.
Peso total del primer nivel:
11
P1 = 6168.50 Kg/m.
-Sobrecimiento:
Peso propio = (0.25)(0.30)(1)(2400) = 180 Kg/m.
PESO PARCIAL = 11032.25 kg/m.
-Cimiento:
Peso propio = (10%)(11032.25) = 1103.225 Kg/m.
PESO TOTAL = 12135.475 Kg/m.
-Calculo de cimentacin:
A = b*1m = P /
b = 12135.475/ (0.8*10000)
b = 1.52m. 1.50m. (Zapata)
tramo 3-4:
SEGUNDO NIVEL:
rea de Influencia:
1*(4.25/2+4/2) = 4.125 m2
-Parapeto:
Peso propio = (1)(0.9)(0.25)(1800) = 405 Kg.
-Losa aligerada:
Peso propio
= 350 Kg/m 2
Peso de acabados
= 100 Kg/m 2
Tabiquera
= 100 Kg/m 2
Carga Muerta (CM) = 550 Kg/m 2
Peso de losa = (550 Kg/m 2 ) (4.125 m2) = 2268.75 Kg/m.
-Viga solera o principal:
Peso propio = (0.25) (0.25) (1.00) (2400) = 150 Kg/m.
-Muro de 2.30m:
Peso propio = (1800) (2.30) (0.25) (1) = 1035 Kg/m.
-Sobrecarga o carga viva = 200.00Kg/m 2 (4.125 m2) = 825 Kg/m.
12
PRIMER NIVEL:
rea de Influencia:
1*(4.25/2+4/2) = 4.125 m2
-Losa aligerada:
Peso propio
= 350 Kg/m 2
Peso de acabados
= 100 Kg/m 2
Tabiquera
= 100 Kg/m 2
Carga Muerta (CM) = 550 Kg/m 2
Peso de losa = (550 Kg/m 2 ) (4.125 m2) = 2268.75 Kg/m.
-Viga solera o principal:
Peso propio = (0.25) (0.25) (1.00) (2400) = 150 Kg/m.
-Muro de 3.75m:
Peso propio = (1800) (3.75) (0.25) (1.00) = 1687.5 Kg/m.
-Sobrecarga o carga viva = 500 Kg/m 2 (4.125 m2) = 2062.50 Kg/m.
Peso total del primer nivel:
P1 = 6168.50 Kg/m.
-Sobrecimiento:
Peso propio = (0.25)(0.30)(1)(2400) = 180 Kg/m.
PESO PARCIAL = 11032.25 kg/m.
-Cimiento:
Peso propio = (10%)(11032.25) = 1103.225 Kg/m.
PESO TOTAL = 12135.475 Kg/m.
-Calculo de cimentacin:
A = b*1m = P /
b = 12135.475/ (0.8*10000)
b = 1.52m.
1.50m. (zapata)
13
tramo 4-5:
SEGUNDO NIVEL:
rea de Influencia:
1*(4.25/2+4/2) = 4.125 m2
-Parapeto:
Peso propio = (1)(0.9)(0.25)(1800) = 405 Kg.
-Losa aligerada:
Peso propio
= 350 Kg/m 2
Peso de acabados
= 100 Kg/m 2
Tabiquera
= 100 Kg/m 2
Carga Muerta (CM) = 550 Kg/m 2
Peso de losa = (550 Kg/m 2 ) (4.125 m2) = 2268.75 Kg/m.
-Viga solera o principal:
Peso propio = (0.25) (0.25) (1.00) (2400) = 150 Kg/m.
-Muro de 2.30m:
Peso propio = (1800) (2.30) (0.25) (1) = 1035 Kg/m.
-Sobrecarga o carga viva = 200.00Kg/m 2 (4.125 m2) = 825 Kg/m.
Peso total del segundo nivel:
P2 = 4683.75 Kg/m.
PRIMER NIVEL:
rea de Influencia:
1*(4.25/2+4/2) = 4.125 m2
-Losa aligerada:
Peso propio
= 350 Kg/m 2
Peso de acabados
= 100 Kg/m 2
Tabiquera
= 100 Kg/m 2
Carga Muerta (CM) = 550 Kg/m 2
Peso de losa = (550 Kg/m 2 ) (4.125 m2) = 2268.75 Kg/m.
-Viga solera o principal:
14
b = 12135.475/ (0.8*10000)
b = 1.52m.
1.50m. (zapata)
1*(4/2) = 2 m2
-Parapeto:
Peso propio = (1)(0.9)(0.25)(1800) = 405 Kg.
-Losa aligerada:
Peso propio
= 350 Kg/m 2
Peso de acabados
= 100 Kg/m 2
Tabiquera
= 100 Kg/m 2
Carga Muerta (CM) = 550 Kg/m 2
Peso de losa = (550 Kg/m 2 ) ( m2) = 1100 Kg/m.
15
1*(4/2) = 2 m2
-Losa aligerada:
Peso propio
= 350 Kg/m 2
Peso de acabados
= 100 Kg/m 2
Tabiquera
= 100 Kg/m 2
Carga Muerta (CM) = 550 Kg/m 2
Peso de losa = (550 Kg/m 2 ) (2 m2) = 1100 Kg/m.
-Viga solera o principal:
Peso propio = (0.25) (0.25) (1.00) (2400) = 150 Kg/m.
-Muro de 3.75m:
Peso propio = (1800) (3.75) (0.25) (1.00) = 1687.5 Kg/m.
-Sobrecarga o carga viva = 500 Kg/m 2 (2 m2) = 1000 Kg/m.
Peso total del primer nivel:
P1 = 3937.5 Kg/m.
-Sobrecimiento:
Peso propio = (0.25)(0.30)(1)(2400) = 180 Kg/m.
PESO PARCIAL = 7207.5 kg/m.
-Cimiento:
Peso propio = (10%)(7207.5) = 720.75 Kg/m.
PESO TOTAL = 7928.25 Kg/m.
-Calculo de cimentacin:
16
A = b*1m = P /
b = 7928.25/ (0.8*10000)
b = 0.99 1m.(zapata)
tramo 2-3:
SEGUNDO NIVEL:
rea de Influencia:
1*(4/2) = 2 m2
-Parapeto:
Peso propio = (1)(0.9)(0.25)(1800) = 405 Kg.
-Losa aligerada:
Peso propio
= 350 Kg/m 2
Peso de acabados
= 100 Kg/m 2
Tabiquera
= 100 Kg/m 2
Carga Muerta (CM) = 550 Kg/m 2
Peso de losa = (550 Kg/m 2 ) ( m2) = 1100 Kg/m.
-Viga solera o principal:
Peso propio = (0.25) (0.25) (1.00) (2400) = 150 Kg/m.
-Muro de 2.30m:
Peso propio = (1800) (2.30) (0.25) (1) = 1035 Kg/m.
-Sobrecarga o carga viva = 200.00Kg/m 2 (2 m2) = 400 Kg/m.
Peso total del segundo nivel:
P2 = 3090 Kg/m.
PRIMER NIVEL:
rea de Influencia:
1*(4/2) = 2 m2
-Losa aligerada:
Peso propio
= 350 Kg/m 2
Peso de acabados
= 100 Kg/m 2
Tabiquera
= 100 Kg/m 2
Carga Muerta (CM) = 550 Kg/m 2
Peso de losa = (550 Kg/m 2 ) (2 m2) = 1100 Kg/m.
17
b = 7928.25/ (0.8*10000)
b = 0.99 1m.(zapata)
tramo 3-4:
SEGUNDO NIVEL:
rea de Influencia:
1*(4/2) = 2 m2
-Parapeto:
Peso propio = (1)(0.9)(0.25)(1800) = 405 Kg.
-Losa aligerada:
Peso propio
= 350 Kg/m 2
18
Peso de acabados
= 100 Kg/m 2
Tabiquera
= 100 Kg/m 2
Carga Muerta (CM) = 550 Kg/m 2
Peso de losa = (550 Kg/m 2 ) ( m2) = 1100 Kg/m.
-Viga solera o principal:
Peso propio = (0.25) (0.25) (1.00) (2400) = 150 Kg/m.
-Muro de 2.30m:
Peso propio = (1800) (2.30) (0.25) (1) = 1035 Kg/m.
-Sobrecarga o carga viva = 200.00Kg/m 2 (2 m2) = 400 Kg/m.
Peso total del segundo nivel:
P2 = 3090 Kg/m.
PRIMER NIVEL:
rea de Influencia:
1*(4/2) = 2 m2
-Losa aligerada:
Peso propio
= 350 Kg/m 2
Peso de acabados
= 100 Kg/m 2
Tabiquera
= 100 Kg/m 2
Carga Muerta (CM) = 550 Kg/m 2
Peso de losa = (550 Kg/m 2 ) (2 m2) = 1100 Kg/m.
-Viga solera o principal:
Peso propio = (0.25) (0.25) (1.00) (2400) = 150 Kg/m.
-Muro de 3.75m:
Peso propio = (1800) (3.75) (0.25) (1.00) = 1687.5 Kg/m.
-Sobrecarga o carga viva = 500 Kg/m 2 (2 m2) = 1000 Kg/m.
Peso total del primer nivel:
P1 = 3937.5 Kg/m.
-Sobrecimiento:
Peso propio = (0.25)(0.30)(1)(2400) = 180 Kg/m.
PESO PARCIAL = 7207.5 kg/m.
-Cimiento:
19
b = 7928.25/ (0.8*10000)
b = 0.99 1m.(zapata)
tramo 4-5:
SEGUNDO NIVEL:
rea de Influencia:
1*(4/2) = 2 m2
-Parapeto:
Peso propio = (1)(0.9)(0.25)(1800) = 405 Kg.
-Losa aligerada:
Peso propio
= 350 Kg/m 2
Peso de acabados
= 100 Kg/m 2
Tabiquera
= 100 Kg/m 2
Carga Muerta (CM) = 550 Kg/m 2
Peso de losa = (550 Kg/m 2 ) ( m2) = 1100 Kg/m.
-Viga solera o principal:
Peso propio = (0.25) (0.25) (1.00) (2400) = 150 Kg/m.
-Muro de 2.30m:
Peso propio = (1800) (2.30) (0.25) (1) = 1035 Kg/m.
-Sobrecarga o carga viva = 200.00Kg/m 2 (2 m2) = 400 Kg/m.
Peso total del segundo nivel:
P2 = 3090 Kg/m.
PRIMER NIVEL:
rea de Influencia:
1*(4/2) = 2 m2
-Losa aligerada:
20
Peso propio
= 350 Kg/m 2
Peso de acabados
= 100 Kg/m 2
Tabiquera
= 100 Kg/m 2
Carga Muerta (CM) = 550 Kg/m 2
Peso de losa = (550 Kg/m 2 ) (2 m2) = 1100 Kg/m.
-Viga solera o principal:
Peso propio = (0.25) (0.25) (1.00) (2400) = 150 Kg/m.
-Muro de 3.75m:
Peso propio = (1800) (3.75) (0.25) (1.00) = 1687.5 Kg/m.
-Sobrecarga o carga viva = 500 Kg/m 2 (2 m2) = 1000 Kg/m.
Peso total del primer nivel:
P1 = 3937.5 Kg/m.
-Sobrecimiento:
Peso propio = (0.25)(0.30)(1)(2400) = 180 Kg/m.
PESO PARCIAL = 7207.5 kg/m.
-Cimiento:
Peso propio = (10%)(7207.5) = 720.75 Kg/m.
PESO TOTAL = 7928.25 Kg/m.
-Calculo de cimentacin:
A = b*1m = P /
b = 7928.25/ (0.8*10000)
b = 0.99 1m. (Zapata)
21
1.-TRAMO A:
ln
ln
( promedio )
25 20
375
15cm 0.15m
25
375
18.75cm 0.1875m .
20
t 17cm 0.17 m
Entonces:
Wpp =
Wpp = 2400
Cp / 2 t
1 cp / p
Wpp = 697.39 kg / m 2
Acabados = 100 kg / m 2
Por lo tanto: CM = 797.39 kg / m 2
22
CARGA ULTIMA:
W U = 1.5CM 1.8CV
W U = 1.5 (797.39)+1.8 (500)
W U = 2096.09 Kg/m2
CARGA ULTIMA DISTRIBUIDA POR METRO LINEAL:
Cd = (2096.09 Kg/m2)(1m)
Cd = 2096.09 Kg/m.
= 0.17m.
Entonces:
Wpp = * t
Wpp = 408
kg / m 2
Acabados = 100 kg / m 2
23
CARGA ULTIMA:
W U = 1.5CM 1.8CV
W U = 1.5 (508)+1.8 (500)
W U = 1662 Kg/m2
CARGA ULTIMA DISTRIBUIDA POR METRO LINEAL:
Cd = (1662 Kg/m2)(2.1m)
Cd = 3490.2 Kg/m.
3. - TRAMO B:
= 0.17m.
Wpp =
Wpp = 2400
Cp / 2 t
1 cp / p
Wpp = 697.39 kg / m 2
Acabados = 100 kg / m 2
Por lo tanto: CM = 797.39 kg / m 2
CARGA ULTIMA:
W U = 1.5CM 1.8CV
W U = 1.5 (797.39)+1.8 (500)
W U = 2096.09 Kg/m2
CARGA ULTIMA DISTRIBUIDA POR METRO LINEAL:
Cd = (2096.09 Kg/m2)(1m)
Cd = 2096.09 Kg/m.
CALCULO DE REACCIONES:
Primera Idealizacin:
25
R A 4116 .05 Kg
Segunda idealizacin:
26
0 RC 5764.25 5138.40
Rc 625.85 Kg
4116.05 Kg.
SEGUNDO NIVEL:
1.-TRAMO A:
Calculo de garganta
t=
t
ln
ln
( promedio )
25 20
275
11cm 0.11m
25
275
13.75cm 0.1875m .
20
t 13cm 0.13m
Entonces:
Wpp =
Wpp = 2400
Cp / 2 t
1 cp / p
Wpp = 581.3 kg / m 2
Acabados = 100 kg / m 2
Por lo tanto: CM = 681.3 kg / m 2
CARGA ULTIMA:
W U = 1.5CM 1.8CV
W U = 1.5 (681.3)+1.8 (200)
W U = 1381.95 Kg/m2
CARGA ULTIMA DISTRIBUIDA POR METRO LINEAL:
Cd = (1381.95 Kg/m2)(1m)
Cd = 1381.95 Kg/m.
2.- DESCANSO (losa)
28
= 0.13m.
Entonces:
Wpp = * t
kg / m 2
Acabados = 100 kg / m 2
Por lo tanto: CM = 388 kg / m 2
CARGA ULTIMA:
W U = 1.5CM 1.8CV
W U = 1.5 (388)+1.8 (200)
W U = 942 Kg/m2
CARGA ULTIMA DISTRIBUIDA POR METRO LINEAL:
Cd = (942 Kg/m2)(2.1m)
Cd = 1978.2Kg/m.
29
3. - TRAMO B:
Wpp = 2400
Cp / 2 t
1 cp / p
Wpp = 581.3 kg / m 2
Acabados = 100 kg / m 2
Por lo tanto: CM = 681.3 kg / m 2
CARGA ULTIMA:
W U = 1.5CM 1.8CV
W U = 1.5 (681.3)+1.8 (200)
W U = 1381.95 Kg/m2
CARGA ULTIMA DISTRIBUIDA POR METRO LINEAL:
Cd = (1381.95 Kg/m2)(1m)
30
Cd = 1381.95 Kg/m.
CALCULO DE REACCIONES:
Primera Idealizacin:
R A 2008.59 Kg
31
Segunda idealizacin:
0 RC 2418.41 2388.02
Rc 30.39 Kg
32