Академический Документы
Профессиональный Документы
Культура Документы
of Head Office
Overheads
by
Terminology Contd
- idle/abortive/de-mob./etc.
- financing charges due to
reduced revenue.
- loss of productivity.
- Subcontractors claims.
= 100,000
=
=
=
20,000
50,000
90,000
10,000
= 300,000
= 30,000
OH & P
600,000
10% = 60,000
OH & P
Gross Profit
Site Overheads
Preliminaries etc.
HOOH
FOOH
= 660,000
If, on the issue of the Taking-Over Certificate for the whole of the
Works, it is found that as a result of:
(a) all varied work valued under Sub-Clauses 52.1 and 52.2, and
(b) all adjustments upon measurement of the estimated quantities set out
in the Bill of Quantities, excluding Provisional Sums, dayworks and
adjustments of price made under Clause 70,
but not from any other cause, there have been additions to or deductions
from the Contract Price which taken together are in excess of 15 per cent
of the Effective Contract Price ( which for the purposes of this SubClause shall mean the Contract Price, excluding Provisional Sums and
allowance for dayworks, if any) then and in such event ( subject to any
action already taken under any other Sub-Clause of this Clause),
..... there shall be added to or deducted from the Contract Price
such further sum . having regard to the Contractors Site and
general overhead costs of the Contract ... Such sum shall
be based only on the amount by which such additions or deductions
shall be in excess of 15 per cent of the Effective Contract Price.
x 12
= 12,000,000
12
= 240,000,000
0
3
= 48,000,000 x 5
10
5%
Original
Completion
4,000,000
X Period of Delay
Alfred Hudson
1891
2nd
3rd
4th
5th
6th
FINISH
7th
300,000
400 d
1st
CP
40 M
30 d
40,000,000
X 10%
8th
9th
X 30 d
400 d
HUDSON FORMULA
H.O.&Profit%
Contract Sum
x Period of Delay (Weeks) =
x
100
Contract Period (Weeks)
HUDSON FORMULA
Additional
Payment due
H.O.&Profit%
Contract Sum
x Period of Delay (Weeks) =
x
100
Contract Period (Weeks)
Additional
Payment due
(where :
(where :
Notes :-
Notes :-
EMDEN FORMULA
h
100
EICHLEAY FORMULA
Contract Sum
x Period of Delay (Weeks) =
Contract Period (Weeks)
Additional
Payment due
Step 1.
Contract Billings
Total Contract Billings
Notes :-
Step 2.
Allocable Overhead
Days of Performance
Step 3.
Daily Contract
Head Office Overhead
Days of Compensabl e
Delay
Additional
Payment due
Notes :
Other Formulae
Additional
Payment due
Notes :
a)
Hx
CP
SCP
Additional
Payment due
where :
Actual
Date of
Completion
Original
Date for
Completion
20 days
20 M
20 M
CP
SCP
Commenc-ement
Date
SAMARATUNGA FORMULA
10 M
40 M 80 days
40 M 80 days
2M
4 days
50 M 25 days
12 M
6 days
640,000/=
64 M
20 M
64 M
= 200,000/=