VARIATION ORDER EVALUATION REPORT
January 28, 2016
(Date)
Project and Location

Contracting Parties

Contract Amount
Contract Duration
Date of
Bidding/Negotiation
Date of Effectivity of
Contract
Technical Description
of
Project

:
:
:

Repair /Completion of DOH-National Children


Hospital Bldg. (Phase II), E. Rodriguez Sr. Ave.,
Quezon City
DPWH-Quezon City Second Engineering
District
13,655,569.49
150 calendar days
September 19, 2013

September 30, 2013

The following are the Scope of Works:


a. Masonry Works
b. Cement Plaster Finish
c. Accoustical/Gypsum/C-Shape Aluminum
Stripe Ceiling
d. Gypsum/Ficem Board Panel
e. Cement Floor Finish
f. Tile Works
g. Vinyl Floor Tiles
h. Metal Structures
i. Finishing Hardware
j. Wooden Door & Partition
k. Steel Door
l. Aluminum Glass Window
m. Aluminum Glass Door
n. Plumbing Works
o. Power Load Center, Switchgear & Panel
Board
p. Wire & Wiring Devices
q. Conduits, Boxes & Fittings
r. Automatic Water Sprinkler System
s. Electric Elevator
t. Airconditioning System
u. Wall Guard Handrail
v. Delivered Items: Supply of conference

table with chair


w. Project Signboard
x. Construction Safety & Health
Subject of this Review:

Reason(s) for Change

:
Amount Involved
Extension of Contract :
:
Time
Revised Contract Cost

CO# _1_/ EWO# ____/ SA ___/


Recapitulation____
To accommodate the request of the end-user
for additional supply and installation of fire
alarm and fire sprinkler system at 4th & 5th
Floors. Installation of exterior wall lights &
installation /supply of fire alarm system at 6th
Floor.
1,339,063.16
15 days
P14,994,632.65

__ Yes___No
1. Is the change or additional work necessary? If
YES, state reason(s)
why and proceed with the review.
As per request of the end-user for additional supply and
installation of fire alarm and fire sprinkler system at 4th
& 5th Floors. Installation of exterior wall lights &
installation /supply of fire alarm system at 6th Floor.
__Yes____No

2. Does the manner of issuance conforms with RA


9184? If NO, describe
the manner of issuance adopted by
management :
As per evaluation by the COA-Audit Team Leader,
DPWH-QCSED, the
supporting documents are complete and the contract
has been found in order as to the legal and auditorial
review.

___ Yes__No

3. Are the work quantities accurate take-offs from


the Approved Plans
and Specifications? If NO,
discuss briefly the discrepancy ;
For Items 1008 & 1202, there are discrepancies in
quantities:

Particular

Quantity
ABC/CO
#1

As-Built
Plans

COA
Evaluation

Differen
ce

Item 1008

16.35
s.m.
338 sets

Item 1202

__Yes___No

10.01 s.m.

10.01 s.m.

3.07 s.m.

308 sets

308 sets

30 sets

4.
Is/Are the Unit Cost(s) reasonable? If NO,
discuss briefly the discrepancy ;
The unit costs of the contract cost was used in cost
estimate of the variation order (CO#1).

5. Reasonableness of Variation Order


% Difference

14,994,632.65 14,091,676.60

100
14,091,676.60
= 6.40%
6. Summary of Findings and Recommendations:

The Revised Contract Cost of P14,994,632.65 was found


to be 0.79% higher than the COA Estimated Cost of
P14,876,618.83, having a difference of P118,013.82. The
discrepancy was due to excessive quantity of Item No.1008Aluminum Glass Windows and Item No. 1202 - Automatic Water
Sprinkler System (see attached Cost Comparison Sheet).
Therefore, the revised Contract Cost
was
found
to
be
excessive per COA Resolution No. 2015 - 014, dated April 15,
2015.
Prepared by:
PHIMILOU P. CARPINA
TAS II

Reviewed by:

ZALDY B. LAVARRO
Sr. TAS

MARIA ROSARIO P. SABELLINA


Chief TAS
Acting Technical Service Chief