Provinsi
Kota /
Kabupaten
: PAPUA
KABUPATEN
:
JAYAPURA
ELEMEN BANGUNAN
RUMAH
GEDUNG
BERTINGKAT
MENENGAH
MEWAH
MENENGAH
SEDERHANA
Spek 2 (dua)
lantai
Rp. / m
Rp. / m
Rp. / m
Rp. / m
GUDANG
Rp. / m
A. BIAYA LANGSUNG
Pondasi
935,831
713,582
419,373
724,746
508,171
Struktur
1,871,664
1,427,164
838,745
1,449,493
1,016,342
Rangka Atap
311,944
237,860
139,791
241,582
169,390
Penutup Atap
362,744
313,588
249,901
194,601
245,371
Plafon
508,639
136,564
117,878
301,536
1,171,436
609,996
541,432
284,657
402,368
502,045
261,427
232,043
121,995
172,444
Lantai
744,855
338,337
179,184
127,961
396,813
Utilitas
826,833
262,452
185,128
365,589
145,093
7,235,990
4,300,971
2,903,474
3,812,160
3,055,993
Professional Fee
217,080
129,029
87,104
114,365
91,680
Biaya Perijinan
108,539
64,515
43,552
57,183
45,839
Dinding
Keuntungan Kontraktor
723,599
430,097
290,347
381,216
305,599
1,049,218
623,641
421,003
552,764
443,118
8,285,208
4,924,612
3,324,477
4,364,924
3,499,111
828,521
492,461
332,448
436,492
349,911
9,113,729
5,417,073
3,656,925
4,801,417
3,849,022
PEMBULATAN
9,114,000
5,417,000
3,657,000
4,801,000
3,849,000
PPN 10%
: PAPUA BARAT
KABUPATEN
:
SORONG
ELEMEN BANGUNAN
RUMAH
GEDUNG
BERTINGKAT
MENENGAH
MEWAH
MENENGAH
SEDERHANA
Spek 2 (dua)
lantai
Rp. / m
Rp. / m
Rp. / m
Rp. / m
GUDANG
Rp. / m
A. BIAYA LANGSUNG
Pondasi
942,576
718,725
422,396
729,969
511,834
Struktur
1,885,154
1,437,450
844,790
1,459,940
1,023,667
Rangka Atap
314,193
239,575
140,799
243,323
170,611
Penutup Atap
365,358
315,848
251,702
196,004
247,139
Plafon
512,305
137,548
118,728
303,709
Dinding
1,179,879
614,392
545,334
286,709
405,268
505,663
263,311
233,715
122,875
173,687
Lantai
750,223
340,776
180,475
128,883
399,673
Utilitas
832,792
264,344
186,462
368,224
146,139
7,288,142
4,331,969
2,924,401
3,839,636
3,078,018
Professional Fee
218,645
129,959
87,731
115,190
92,341
Biaya Perijinan
109,322
64,980
43,866
57,595
46,170
Keuntungan Kontraktor
728,814
433,197
292,440
383,963
307,801
1,056,780
628,136
424,037
556,748
446,312
8,344,923
4,960,105
3,348,438
4,396,384
3,524,330
834,492
496,011
334,844
439,638
352,433
9,179,415
5,456,116
3,683,282
4,836,022
3,876,764
PEMBULATAN
9,179,000
5,456,000
3,683,000
4,836,000
3,877,000
PPN 10%
GEDUNG
BERTINGKAT
RUMAH
MENENGAH
-
MENENGAH
SEDERHANA
Spek 2 (dua)
GUDANG
MEWAH
Rp. / m
lantai
Rp. / m
Rp. / m
Rp. / m
Rp. / m
A. BIAYA LANGSUNG
Pondasi
603,629
460,274
270,504
467,475
327,780
Struktur
1,207,260
920,549
541,007
934,951
655,560
Rangka Atap
201,210
153,424
90,168
155,825
109,260
Penutup Atap
233,977
202,270
161,191
125,522
158,269
Plafon
328,082
88,086
76,034
194,496
Dinding
755,599
393,459
349,234
183,609
259,535
323,828
168,626
149,672
78,689
111,230
Lantai
480,446
218,234
115,577
82,537
255,952
Utilitas
533,323
169,287
119,411
235,812
93,588
4,667,354
2,774,209
1,872,797
2,458,917
1,971,175
140,021
83,226
56,183
73,768
59,135
70,010
41,614
28,092
36,884
29,567
466,735
277,421
187,279
245,892
197,117
676,766
402,261
271,555
356,543
285,820
5,344,120
3,176,470
2,144,352
2,815,461
2,256,994
534,412
317,647
214,435
281,546
225,699
5,878,532
3,494,117
2,358,787
3,097,007
2,482,694
PEMBULATAN
5,879,000
3,494,000
2,359,000
3,097,000
2,483,000
SULAWESI
UTARA
KOTA
:
MANADO
:
Kota /
Kabupaten
ELEMEN BANGUNAN
RUMAH
GEDUNG
BERTINGKAT
MENENGAH
MEWAH
MENENGAH
SEDERHANA
Spek 2 (dua)
lantai
Rp. / m
Rp. / m
Rp. / m
Rp. / m
GUDANG
Rp. / m
A. BIAYA LANGSUNG
Pondasi
721,984
550,521
323,542
559,134
392,049
Struktur
1,443,969
1,101,042
647,083
1,118,268
784,097
Rangka Atap
240,662
183,507
107,847
186,378
130,683
Penutup Atap
279,853
241,930
192,796
150,133
189,301
Plafon
392,409
105,357
90,942
232,632
Dinding
903,750
470,605
417,709
219,610
310,423
387,322
201,688
179,018
94,118
133,039
Lantai
574,648
261,023
138,238
98,720
306,137
Utilitas
637,893
202,479
142,824
282,048
111,938
5,582,489
3,318,153
2,239,999
2,941,041
2,357,666
Professional Fee
167,475
99,544
67,199
88,232
70,730
83,737
49,773
33,600
44,116
35,365
558,249
331,815
224,000
294,104
235,766
809,461
481,133
324,799
426,451
341,861
6,391,949
3,799,285
2,564,799
3,367,492
2,699,527
639,195
379,929
256,480
336,749
269,953
7,031,144
4,179,214
2,821,278
3,704,241
2,969,479
PEMBULATAN
7,031,000
4,179,000
2,821,000
3,704,000
2,969,000
Biaya Perijinan
Keuntungan Kontraktor
TOTAL BIAYA TIDAK LANGSUNG ( B )
TOTAL BIAYA PEMBANGUNAN BARU ( A + B )
PPN 10%
: PAPUA
KABUPATEN
:
JAYAWIJAYA
ELEMEN BANGUNAN
RUMAH
GEDUNG
BERTINGKAT
MENENGAH
MEWAH
MENENGAH
SEDERHANA
Spek 2 (dua)
lantai
Rp. / m
Rp. / m
Rp. / m
Rp. / m
GUDANG
Rp. / m
A. BIAYA LANGSUNG
Pondasi
2,119,376
1,616,049
949,754
1,641,331
1,150,855
Struktur
4,238,756
3,232,098
1,899,505
3,282,666
2,301,710
Rangka Atap
706,460
538,682
316,585
547,110
383,618
Penutup Atap
821,505
710,183
565,951
440,713
555,692
1,151,913
309,275
266,958
682,888
Plafon
Dinding
2,652,949
1,381,457
1,226,180
644,663
911,242
1,136,980
592,054
525,507
276,283
390,533
Lantai
1,686,872
766,232
405,797
289,792
898,662
Utilitas
1,872,528
594,375
419,259
827,950
328,593
16,387,341
9,740,404
6,575,496
8,633,396
6,920,905
Professional Fee
491,621
292,212
197,263
259,003
207,628
Biaya Perijinan
245,809
146,107
98,633
129,502
103,812
1,638,734
974,041
657,549
863,339
692,089
2,376,164
1,412,360
953,445
1,251,844
1,003,530
18,763,504
11,152,765
7,528,941
9,885,240
7,924,434
1,876,350
1,115,276
752,894
988,524
792,443
20,639,855
12,268,041
8,281,835
10,873,764
8,716,878
PEMBULATAN
20,640,000
12,268,000
8,282,000
10,874,000
8,717,000
Keuntungan Kontraktor
TOTAL BIAYA TIDAK LANGSUNG ( B )
TOTAL BIAYA PEMBANGUNAN BARU ( A + B )
PPN 10%
RUMAH
GEDUNG
BERTINGKAT
GUDANG
MENENGAH
MEWAH
MENENGAH
SEDERHANA
Spek 2 (dua)
lantai
Rp. / m
Rp. / m
Rp. / m
Rp. / m
Rp. / m
A. BIAYA LANGSUNG
Pondasi
927,312
707,086
415,555
718,148
503,545
Struktur
1,854,624
1,414,171
831,109
1,436,297
1,007,089
Rangka Atap
309,104
235,695
138,518
239,383
167,848
Penutup Atap
359,441
310,733
247,626
192,830
243,137
Plafon
504,008
135,320
116,805
298,791
1,160,771
604,442
536,503
282,066
398,705
497,474
259,047
229,930
120,885
170,874
Lantai
738,074
335,257
177,553
126,796
393,200
Utilitas
819,305
260,063
183,442
362,261
143,773
7,170,113
4,261,814
2,877,041
3,777,454
3,028,171
Professional Fee
215,104
127,854
86,311
113,324
90,846
Biaya Perijinan
107,551
63,928
43,156
56,662
45,422
Keuntungan Kontraktor
717,011
426,182
287,704
377,745
302,817
1,039,666
617,964
417,170
547,732
439,084
8,209,780
4,879,778
3,294,211
4,325,186
3,467,255
820,978
487,978
329,421
432,519
346,726
Dinding
PPN 10%
9,030,758
5,367,756
3,623,632
4,757,704
3,813,981
PEMBULATAN
9,031,000
5,368,000
3,624,000
4,758,000
3,814,000
: PAPUA
KABUPATEN KEPULAUAN
:
YAPEN
ELEMEN BANGUNAN
RUMAH
GEDUNG
BERTINGKAT
MENENGAH
MEWAH
MENENGAH
SEDERHANA
Spek 2 (dua)
lantai
Rp. / m
Rp. / m
Rp. / m
Rp. / m
GUDANG
Rp. / m
A. BIAYA LANGSUNG
Pondasi
878,465
669,839
393,665
680,319
477,020
Struktur
1,756,930
1,339,679
787,329
1,360,639
954,040
Rangka Atap
292,822
223,279
131,222
226,773
159,007
Penutup Atap
340,507
294,365
234,582
182,672
230,330
Plafon
477,459
128,192
110,652
283,052
1,099,626
572,603
508,242
267,208
377,703
471,269
245,402
217,818
114,517
161,873
Lantai
699,195
317,597
168,200
120,117
372,488
Utilitas
776,148
246,364
173,779
343,178
136,199
Dinding
6,792,421
4,037,320
2,725,490
3,578,473
2,868,659
Professional Fee
203,773
121,119
81,764
107,355
86,060
Biaya Perijinan
101,886
60,560
40,883
53,677
43,029
Keuntungan Kontraktor
679,242
403,732
272,549
357,847
286,865
984,901
585,412
395,195
518,879
415,955
7,777,322
4,622,731
3,120,686
4,097,353
3,284,614
777,732
462,273
312,069
409,735
328,461
8,555,054
5,085,005
3,432,754
4,507,088
3,613,076
PEMBULATAN
8,555,000
5,085,000
3,433,000
4,507,000
3,613,000
: PAPUA
KABUPATEN BIAK
:
NUMFOR
ELEMEN BANGUNAN
RUMAH
GEDUNG
BERTINGKAT
MENENGAH
MEWAH
MENENGAH
SEDERHANA
Spek 2 (dua)
lantai
Rp. / m
Rp. / m
Rp. / m
Rp. / m
GUDANG
Rp. / m
A. BIAYA LANGSUNG
Pondasi
1,016,415
775,028
455,485
787,153
551,929
Struktur
2,032,831
1,550,056
910,968
1,574,307
1,103,858
Rangka Atap
338,805
258,342
151,828
262,384
183,976
Penutup Atap
393,979
340,591
271,420
211,358
266,500
Plafon
552,437
148,323
128,028
327,501
1,272,306
662,522
588,054
309,169
437,015
545,275
283,938
252,024
132,500
187,293
Lantai
808,994
367,471
194,613
138,979
430,982
Utilitas
898,031
285,051
201,069
397,070
157,587
7,859,072
4,671,322
3,153,489
4,140,421
3,319,141
Professional Fee
235,773
140,139
94,604
124,213
99,575
Biaya Perijinan
117,886
70,070
47,303
62,107
49,787
Keuntungan Kontraktor
785,907
467,132
315,348
414,042
331,913
1,139,565
677,342
457,255
600,362
481,275
8,998,637
5,348,664
3,610,744
4,740,783
3,800,415
899,864
534,866
361,074
474,078
380,042
9,898,501
5,883,531
3,971,818
5,214,861
4,180,457
PEMBULATAN
9,899,000
5,884,000
3,972,000
5,215,000
4,180,000
Dinding
PPN 10%
: PAPUA
KABUPATEN
:
MERAUKE
ELEMEN BANGUNAN
RUMAH
GEDUNG
BERTINGKAT
MENENGAH
MEWAH
MENENGAH
SEDERHANA
Spek 2 (dua)
lantai
Rp. / m
Rp. / m
Rp. / m
Rp. / m
GUDANG
Rp. / m
A. BIAYA LANGSUNG
Pondasi
1,847,665
1,408,866
827,992
1,430,907
1,003,311
Struktur
3,695,333
2,817,732
1,655,982
2,861,817
2,006,623
Rangka Atap
615,889
469,621
275,997
476,969
334,437
Penutup Atap
716,185
619,135
493,394
384,212
484,450
Plafon
1,004,234
269,625
232,733
595,340
Dinding
2,312,832
1,204,349
1,068,980
562,015
794,418
991,215
516,151
458,135
240,863
340,466
Lantai
1,470,610
667,998
353,773
252,640
783,450
Utilitas
1,632,463
518,174
365,508
721,804
286,466
14,286,428
8,491,651
5,732,495
7,526,565
6,033,621
Professional Fee
428,594
254,749
171,973
225,798
181,009
Biaya Perijinan
214,295
127,376
85,988
112,899
90,503
1,428,642
849,166
573,249
752,656
603,361
2,071,531
1,231,291
831,210
1,091,353
874,874
16,357,959
9,722,942
6,563,705
8,617,919
6,908,495
Keuntungan Kontraktor
TOTAL BIAYA TIDAK LANGSUNG ( B )
TOTAL BIAYA PEMBANGUNAN BARU ( A + B )
PPN 10%
1,635,796
972,294
656,371
861,792
690,849
17,993,755
10,695,236
7,220,076
9,479,711
7,599,344
PEMBULATAN
17,994,000
10,695,000
7,220,000
9,480,000
7,599,000
: PAPUA
KABUPATEN
:
PANIAI
ELEMEN BANGUNAN
RUMAH
GEDUNG
BERTINGKAT
MENENGAH
MEWAH
MENENGAH
SEDERHANA
Spek 2 (dua)
lantai
Rp. / m
Rp. / m
Rp. / m
Rp. / m
GUDANG
Rp. / m
A. BIAYA LANGSUNG
Pondasi
1,528,030
1,165,140
684,754
1,183,368
829,744
Struktur
3,056,062
2,330,281
1,369,507
2,366,739
1,659,489
Rangka Atap
509,344
388,379
228,251
394,456
276,581
Penutup Atap
592,289
512,028
408,040
317,746
400,643
Plafon
830,508
222,982
192,472
492,349
1,912,726
996,004
884,052
464,789
656,988
819,741
426,859
378,880
199,195
281,567
1,216,203
552,438
292,572
208,935
647,918
Dinding
Pintu dan Jendela
Lantai
Utilitas
1,350,057
428,533
302,278
596,936
236,909
11,814,959
7,022,645
4,740,807
6,224,514
4,989,840
Professional Fee
354,449
210,679
142,223
186,736
149,696
Biaya Perijinan
177,224
105,341
71,113
93,368
74,847
1,181,496
702,265
474,080
622,451
498,983
1,713,169
1,018,285
687,416
902,556
723,526
13,528,128
8,040,930
5,428,223
7,127,069
5,713,366
1,352,813
804,093
542,822
712,707
571,337
14,880,941
8,845,023
5,971,045
7,839,776
6,284,702
PEMBULATAN
14,881,000
8,845,000
5,971,000
7,840,000
6,285,000
Keuntungan Kontraktor
TOTAL BIAYA TIDAK LANGSUNG ( B )
TOTAL BIAYA PEMBANGUNAN BARU ( A + B )
PPN 10%
: PAPUA
KABUPATEN PUNCAK
:
JAYA
ELEMEN BANGUNAN
A. BIAYA LANGSUNG
RUMAH
GEDUNG
BERTINGKAT
MENENGAH
MEWAH
MENENGAH
SEDERHANA
Spek 2 (dua)
lantai
Rp. / m
Rp. / m
Rp. / m
Rp. / m
GUDANG
Rp. / m
Pondasi
2,669,757
2,035,720
1,196,395
2,067,568
1,449,720
Struktur
5,339,518
4,071,441
2,392,787
4,135,141
2,899,440
Rangka Atap
889,920
678,572
398,798
689,189
483,240
Penutup Atap
1,034,841
894,610
712,923
555,162
699,999
Plafon
1,451,054
389,591
336,284
860,227
Dinding
3,341,893
1,740,207
1,544,607
812,075
1,147,883
1,432,242
745,804
661,975
348,031
491,951
Lantai
2,124,936
965,214
511,179
365,048
1,132,035
Utilitas
2,358,804
748,728
528,136
1,042,960
413,925
20,642,966
12,269,888
8,283,085
10,875,401
8,718,193
Professional Fee
619,290
368,096
248,491
326,264
261,547
Biaya Perijinan
309,643
184,050
124,247
163,132
130,771
2,064,296
1,226,990
828,307
1,087,539
871,818
2,993,229
1,779,136
1,201,045
1,576,935
1,264,136
23,636,195
14,049,024
9,484,130
12,452,336
9,982,329
2,363,619
1,404,902
948,413
1,245,234
998,233
25,999,814
15,453,926
10,432,543
13,697,570
10,980,562
PEMBULATAN
26,000,000
15,454,000
10,433,000
13,698,000
10,981,000
Keuntungan Kontraktor
TOTAL BIAYA TIDAK LANGSUNG ( B )
TOTAL BIAYA PEMBANGUNAN BARU ( A + B )
PPN 10%
: PAPUA
Kota /
Kabupaten
KABUPATEN PUNCAK
JAYA
ELEMEN BANGUNAN
RUMAH
GEDUNG
BERTINGKAT
MENENGAH
MEWAH
MENENGAH
SEDERHANA
Spek 2 (dua)
lantai
Rp. / m
Rp. / m
Rp. / m
Rp. / m
GUDANG
Rp. / m
A. BIAYA LANGSUNG
Pondasi
2,669,757
2,035,720
1,196,395
2,067,568
1,449,720
Struktur
5,339,518
4,071,441
2,392,787
4,135,141
2,899,440
Rangka Atap
889,920
678,572
398,798
689,189
483,240
Penutup Atap
1,034,841
894,610
712,923
555,162
699,999
Plafon
1,451,054
389,591
336,284
860,227
Dinding
3,341,893
1,740,207
1,544,607
812,075
1,147,883
1,432,242
745,804
661,975
348,031
491,951
Lantai
2,124,936
965,214
511,179
365,048
1,132,035
Utilitas
2,358,804
748,728
528,136
1,042,960
413,925
20,642,966
12,269,888
8,283,085
10,875,401
8,718,193
Professional Fee
619,290
368,096
248,491
326,264
261,547
Biaya Perijinan
309,643
184,050
124,247
163,132
130,771
2,064,296
1,226,990
828,307
1,087,539
871,818
Keuntungan Kontraktor
2,993,229
1,779,136
1,201,045
1,576,935
1,264,136
23,636,195
14,049,024
9,484,130
12,452,336
9,982,329
2,363,619
1,404,902
948,413
1,245,234
998,233
25,999,814
15,453,926
10,432,543
13,697,570
10,980,562
PEMBULATAN
26,000,000
15,454,000
10,433,000
13,698,000
10,981,000
: PAPUA
KABUPATEN
:
MIMIKA
ELEMEN BANGUNAN
RUMAH
GEDUNG
BERTINGKAT
MENENGAH
MEWAH
MENENGAH
SEDERHANA
Spek 2 (dua)
lantai
Rp. / m
Rp. / m
Rp. / m
Rp. / m
GUDANG
Rp. / m
A. BIAYA LANGSUNG
Pondasi
1,373,892
1,047,609
615,681
1,063,998
746,045
Struktur
2,747,786
2,095,217
1,231,360
2,127,998
1,492,090
Rangka Atap
457,965
349,202
205,227
354,666
248,682
Penutup Atap
532,543
460,378
366,880
285,694
360,229
Plafon
746,731
200,489
173,056
442,684
1,719,782
895,534
794,875
417,905
590,716
737,051
383,801
340,661
179,101
253,164
Dinding
Pintu dan Jendela
Lantai
1,093,520
496,712
263,059
187,859
582,560
Utilitas
1,213,872
385,305
271,786
536,721
213,011
10,623,143
6,314,246
4,262,585
5,596,625
4,486,497
Professional Fee
318,695
189,427
127,877
167,900
134,595
Biaya Perijinan
159,346
94,715
63,939
83,950
67,297
1,062,314
631,425
426,258
559,662
448,649
1,540,355
915,567
618,074
811,512
650,541
12,163,498
7,229,813
4,880,659
6,408,137
5,137,038
1,216,350
722,981
488,066
640,814
513,704
13,379,848
7,952,794
5,368,724
7,048,950
5,650,742
PEMBULATAN
13,380,000
7,953,000
5,369,000
7,049,000
5,651,000
Keuntungan Kontraktor
TOTAL BIAYA TIDAK LANGSUNG ( B )
TOTAL BIAYA PEMBANGUNAN BARU ( A + B )
PPN 10%
: PAPUA
KABUPATEN BOVEN
:
DIGOEL
ELEMEN BANGUNAN
RUMAH
GEDUNG
BERTINGKAT
MENENGAH
MEWAH
MENENGAH
SEDERHANA
Spek 2 (dua)
lantai
Rp. / m
Rp. / m
Rp. / m
Rp. / m
GUDANG
Rp. / m
A. BIAYA LANGSUNG
Pondasi
1,287,558
981,778
576,992
997,137
699,164
Struktur
2,575,118
1,963,556
1,153,982
1,994,276
1,398,328
Rangka Atap
429,187
327,259
192,331
332,379
233,055
Penutup Atap
499,079
431,448
343,825
267,741
337,592
Plafon
699,807
187,890
162,182
414,866
1,611,713
839,259
744,926
391,644
553,596
690,735
359,683
319,254
167,847
237,256
Lantai
1,024,804
465,499
246,529
176,054
545,953
Utilitas
1,137,593
361,093
254,707
502,994
199,626
9,955,593
5,917,465
3,994,728
5,244,938
4,204,570
Professional Fee
298,668
177,524
119,841
157,349
126,138
Biaya Perijinan
149,333
88,763
59,921
78,674
63,068
Keuntungan Kontraktor
995,559
591,747
399,472
524,493
420,456
1,443,561
858,033
579,234
760,517
609,662
11,399,154
6,775,498
4,573,962
6,005,455
4,814,231
1,139,915
677,550
457,396
600,545
481,423
12,539,070
7,453,048
5,031,358
6,606,000
5,295,654
PEMBULATAN
12,539,000
7,453,000
5,031,000
6,606,000
5,296,000
Dinding
Pintu dan Jendela
Provinsi
Kota /
Kabupaten
: PAPUA
KABUPATEN
:
MAPPI
ELEMEN BANGUNAN
RUMAH
GEDUNG
BERTINGKAT
MENENGAH
MEWAH
MENENGAH
SEDERHANA
Spek 2 (dua)
lantai
Rp. / m
Rp. / m
Rp. / m
Rp. / m
GUDANG
Rp. / m
A. BIAYA LANGSUNG
Pondasi
1,503,393
1,146,355
673,714
1,164,289
816,366
Struktur
3,006,789
2,292,710
1,347,426
2,328,580
1,632,733
Rangka Atap
501,132
382,118
224,571
388,096
272,122
Penutup Atap
582,740
503,773
401,461
312,623
394,183
Plafon
817,117
219,386
189,368
484,411
1,881,887
979,945
869,799
457,296
646,396
806,524
419,977
372,772
195,983
277,027
Lantai
1,196,594
543,532
287,855
205,566
637,471
Utilitas
1,328,290
421,624
297,404
587,311
233,090
11,624,466
6,909,419
4,664,371
6,124,156
4,909,388
Professional Fee
348,735
207,282
139,930
183,726
147,282
Biaya Perijinan
174,366
103,642
69,966
91,863
73,640
1,162,446
690,942
466,436
612,415
490,938
Dinding
Pintu dan Jendela
Keuntungan Kontraktor
1,685,547
1,001,867
676,333
888,004
711,860
13,310,013
7,911,286
5,340,703
7,012,159
5,621,249
1,331,001
791,129
534,070
701,216
562,125
14,641,015
8,702,414
5,874,773
7,713,375
6,183,374
PEMBULATAN
14,641,000
8,702,000
5,875,000
7,713,000
6,183,000
: PAPUA
KABUPATEN
:
ASMAT
ELEMEN BANGUNAN
RUMAH
GEDUNG
BERTINGKAT
MENENGAH
MEWAH
MENENGAH
SEDERHANA
Spek 2 (dua)
lantai
Rp. / m
Rp. / m
Rp. / m
Rp. / m
GUDANG
Rp. / m
A. BIAYA LANGSUNG
Pondasi
1,695,657
1,292,958
759,873
1,313,186
920,769
Struktur
3,391,317
2,585,917
1,519,744
2,626,375
1,841,537
Rangka Atap
565,220
430,985
253,291
437,729
306,923
Penutup Atap
657,265
568,199
452,803
352,603
444,594
Plafon
921,616
247,443
213,586
546,361
2,122,555
1,105,267
981,034
515,778
729,061
Dinding
909,668
473,687
420,444
221,047
312,455
Lantai
1,349,622
613,042
324,668
231,855
718,996
Utilitas
1,498,160
475,544
335,438
662,421
262,899
13,111,080
7,793,041
5,260,881
6,907,353
5,537,234
Professional Fee
393,333
233,791
157,825
207,222
166,118
Biaya Perijinan
196,665
116,897
78,914
103,611
83,058
1,311,108
779,305
526,087
690,735
553,722
1,901,106
1,129,992
762,826
1,001,567
802,898
15,012,186
8,923,034
6,023,708
7,908,921
6,340,131
1,501,219
892,303
602,371
790,892
634,013
16,513,405
9,815,337
6,626,079
8,699,813
6,974,145
PEMBULATAN
16,513,000
9,815,000
6,626,000
8,700,000
6,974,000
Keuntungan Kontraktor
TOTAL BIAYA TIDAK LANGSUNG ( B )
TOTAL BIAYA PEMBANGUNAN BARU ( A + B )
PPN 10%
GEDUNG
BERTINGKAT
RUMAH
MENENGAH
MEWAH
MENENGAH
SEDERHANA
Spek 2 (dua)
lantai
GUDANG
Rp. / m
Rp. / m
Rp. / m
Rp. / m
Rp. / m
A. BIAYA LANGSUNG
Pondasi
1,555,080
1,185,767
696,877
1,204,317
844,433
Struktur
3,110,163
2,371,533
1,393,751
2,408,637
1,688,866
Rangka Atap
518,361
395,255
232,292
401,439
281,478
Penutup Atap
602,775
521,093
415,264
323,371
407,735
Plafon
845,210
226,929
195,879
501,065
1,946,586
1,013,636
899,703
473,018
668,619
834,253
434,416
385,588
202,721
286,552
Lantai
1,237,733
562,218
297,752
212,633
659,388
Utilitas
1,373,957
436,119
307,629
607,503
241,103
12,024,117
7,146,966
4,824,732
6,334,705
5,078,174
Professional Fee
360,724
214,409
144,741
190,042
152,346
Biaya Perijinan
180,361
107,205
72,372
95,021
76,172
1,202,411
714,697
482,473
633,470
507,816
1,743,497
1,036,311
699,585
918,533
736,334
13,767,614
8,183,277
5,524,317
7,253,238
5,814,508
1,376,761
818,328
552,432
725,324
581,451
15,144,375
9,001,605
6,076,749
7,978,562
6,395,959
PEMBULATAN
15,144,000
9,002,000
6,077,000
7,979,000
6,396,000
Dinding
Pintu dan Jendela
Keuntungan Kontraktor
TOTAL BIAYA TIDAK LANGSUNG ( B )
TOTAL BIAYA PEMBANGUNAN BARU ( A + B )
PPN 10%
: PAPUA
KABUPATEN PEGUNUNGAN
:
BINTANG
ELEMEN BANGUNAN
RUMAH
GEDUNG
BERTINGKAT
MENENGAH
MEWAH
MENENGAH
SEDERHANA
Spek 2 (dua)
lantai
Rp. / m
Rp. / m
Rp. / m
Rp. / m
GUDANG
Rp. / m
A. BIAYA LANGSUNG
Pondasi
2,754,884
2,100,631
1,234,543
2,133,494
1,495,945
Struktur
5,509,772
4,201,262
2,469,083
4,266,993
2,991,891
Rangka Atap
918,296
700,209
411,514
711,165
498,648
Penutup Atap
1,067,838
923,135
735,655
572,864
722,319
Plafon
1,497,322
402,013
347,007
887,656
Dinding
3,448,452
1,795,695
1,593,858
837,969
1,184,484
1,477,910
769,585
683,083
359,128
507,637
Lantai
2,192,691
995,991
527,478
376,688
1,168,131
Utilitas
2,434,017
772,602
544,976
1,076,215
427,124
21,301,182
12,661,123
8,547,197
11,222,172
8,996,179
Professional Fee
639,037
379,833
256,414
336,667
269,887
Biaya Perijinan
319,516
189,919
128,209
168,333
134,941
Keuntungan Kontraktor
2,130,118
1,266,113
854,719
1,122,216
899,616
3,088,671
1,835,865
1,239,341
1,627,217
1,304,444
24,389,853
14,496,988
9,786,539
12,849,388
10,300,623
2,438,985
1,449,699
978,654
1,284,939
1,030,062
26,828,838
15,946,686
10,765,193
14,134,327
11,330,685
PEMBULATAN
26,829,000
15,947,000
10,765,000
14,134,000
11,331,000
: PAPUA
KABUPATEN
:
TOLIKARA
ELEMEN BANGUNAN
RUMAH
GEDUNG
BERTINGKAT
MENENGAH
MEWAH
MENENGAH
SEDERHANA
Spek 2 (dua)
lantai
Rp. / m
Rp. / m
Rp. / m
Rp. / m
GUDANG
Rp. / m
A. BIAYA LANGSUNG
Pondasi
2,145,930
1,636,296
961,653
1,661,895
1,165,274
Struktur
4,291,863
3,272,593
1,923,303
3,323,794
2,330,547
Rangka Atap
715,311
545,431
320,551
553,965
388,425
Penutup Atap
831,798
719,081
573,042
446,235
562,654
1,166,346
313,150
270,303
691,444
Plafon
Dinding
2,686,188
1,398,765
1,241,543
652,740
922,659
1,151,225
599,472
532,091
279,745
395,426
Lantai
1,708,007
775,832
410,882
293,423
909,921
Utilitas
1,895,989
601,822
424,512
838,323
332,710
16,592,656
9,862,441
6,657,880
8,741,563
7,007,616
Professional Fee
497,781
295,873
199,735
262,248
210,229
Biaya Perijinan
248,889
147,938
99,869
131,124
105,113
1,659,265
986,245
665,787
874,156
700,760
2,405,934
1,430,056
965,391
1,267,528
1,016,103
18,998,590
11,292,497
7,623,270
10,009,091
8,023,719
1,899,859
1,129,250
762,327
1,000,909
802,372
20,898,449
12,421,746
8,385,597
11,010,000
8,826,090
PEMBULATAN
20,898,000
12,422,000
8,386,000
11,010,000
8,826,000
Keuntungan Kontraktor
TOTAL BIAYA TIDAK LANGSUNG ( B )
TOTAL BIAYA PEMBANGUNAN BARU ( A + B )
PPN 10%
GEDUNG
BERTINGKAT
RUMAH
MENENGAH
-
MENENGAH
SEDERHANA
Spek 2 (dua)
GUDANG
MEWAH
Rp. / m
lantai
Rp. / m
Rp. / m
Rp. / m
Rp. / m
A. BIAYA LANGSUNG
Pondasi
1,528,385
1,165,411
684,914
1,183,643
829,937
Struktur
3,056,772
2,330,822
1,369,825
2,367,289
1,659,874
Rangka Atap
509,462
388,470
228,305
394,548
276,646
Penutup Atap
592,427
512,147
408,135
317,820
400,736
Plafon
830,701
223,033
192,516
492,464
1,913,170
996,235
884,258
464,897
657,141
819,931
426,959
378,968
199,241
281,632
Lantai
1,216,485
552,567
292,640
208,983
648,068
Utilitas
1,350,370
428,632
302,348
597,074
236,964
11,817,704
7,024,277
4,741,908
6,225,960
4,990,999
Professional Fee
354,532
210,728
142,256
186,780
149,731
Biaya Perijinan
177,265
105,365
71,129
93,390
74,864
1,181,770
702,428
474,190
622,596
499,099
1,713,567
1,018,521
687,575
902,765
723,694
13,531,271
8,042,798
5,429,484
7,128,725
5,714,693
1,353,127
804,280
542,948
712,872
571,469
14,884,398
8,847,078
5,972,432
7,841,597
6,286,162
Dinding
Pintu dan Jendela
Keuntungan Kontraktor
TOTAL BIAYA TIDAK LANGSUNG ( B )
TOTAL BIAYA PEMBANGUNAN BARU ( A + B )
PPN 10%
TOTAL BIAYA PEMB. BARU SETELAH PPN
PEMBULATAN
14,884,000
8,847,000
5,972,000
7,842,000
6,286,000
: PAPUA
KABUPATEN
:
KEEROM
ELEMEN BANGUNAN
RUMAH
GEDUNG
BERTINGKAT
MENENGAH
MEWAH
MENENGAH
SEDERHANA
Spek 2 (dua)
lantai
Rp. / m
Rp. / m
Rp. / m
Rp. / m
GUDANG
Rp. / m
A. BIAYA LANGSUNG
Pondasi
1,171,262
893,101
524,877
907,073
636,014
Struktur
2,342,527
1,786,202
1,049,751
1,814,148
1,272,028
Rangka Atap
390,421
297,700
174,959
302,358
212,005
Penutup Atap
454,000
392,479
312,770
243,558
307,100
Plafon
636,599
170,919
147,533
377,395
1,466,139
763,455
677,642
356,269
503,593
628,346
327,195
290,419
152,686
215,826
Lantai
932,241
423,454
224,262
160,152
496,641
Utilitas
1,034,843
328,478
231,701
457,562
181,595
9,056,379
5,382,984
3,633,914
4,771,202
3,824,802
Dinding
Professional Fee
271,692
161,489
109,017
143,137
114,745
Biaya Perijinan
135,845
80,746
54,509
71,568
57,371
Keuntungan Kontraktor
905,638
538,299
363,391
477,120
382,479
1,313,175
780,534
526,917
691,825
554,595
10,369,553
6,163,517
4,160,830
5,463,027
4,379,397
1,036,955
616,352
416,083
546,303
437,940
11,406,508
6,779,869
4,576,913
6,009,329
4,817,337
PEMBULATAN
11,407,000
6,780,000
4,577,000
6,009,000
4,817,000
: PAPUA
KABUPATEN
:
WAROPEN
ELEMEN BANGUNAN
RUMAH
GEDUNG
BERTINGKAT
MENENGAH
MEWAH
MENENGAH
SEDERHANA
Spek 2 (dua)
lantai
Rp. / m
Rp. / m
Rp. / m
Rp. / m
GUDANG
Rp. / m
A. BIAYA LANGSUNG
Pondasi
1,103,459
841,400
494,492
854,563
599,195
Struktur
2,206,919
1,682,800
988,982
1,709,128
1,198,391
Rangka Atap
367,820
280,466
164,831
284,854
199,732
Penutup Atap
427,719
369,759
294,664
229,458
289,322
Plafon
599,747
161,025
138,992
355,547
1,381,265
719,259
638,414
335,645
474,441
591,972
308,254
273,606
143,848
203,332
Lantai
878,274
398,941
211,279
150,881
467,891
Utilitas
974,936
309,463
218,288
431,074
171,083
8,532,111
5,071,367
3,423,549
4,495,000
3,603,387
Professional Fee
255,964
152,141
102,706
134,851
108,102
Biaya Perijinan
127,981
76,071
51,354
67,425
54,050
Keuntungan Kontraktor
853,211
507,137
342,354
449,500
360,338
1,237,156
735,349
496,414
651,776
522,490
9,769,267
5,806,716
3,919,963
5,146,776
4,125,877
976,927
580,672
391,996
514,678
412,588
10,746,194
6,387,387
4,311,959
5,661,453
4,538,465
PEMBULATAN
10,746,000
6,387,000
4,312,000
5,661,000
4,538,000
Dinding
PPN 10%
GEDUNG
BERTINGKAT
RUMAH
MENENGAH
-
MENENGAH
SEDERHANA
Spek 2 (dua)
lantai
GUDANG
MEWAH
Rp. / m
Rp. / m
Rp. / m
Rp. / m
Rp. / m
A. BIAYA LANGSUNG
Pondasi
1,374,176
1,047,825
615,808
1,064,218
746,199
Struktur
2,748,354
2,095,650
1,231,614
2,128,438
1,492,399
Rangka Atap
458,059
349,274
205,269
354,739
248,733
Penutup Atap
532,653
460,473
366,955
285,753
360,303
Plafon
746,886
200,530
173,092
442,776
1,720,138
895,719
795,039
417,991
590,838
737,203
383,880
340,732
179,138
253,217
Lantai
1,093,746
496,815
263,114
187,897
582,681
Utilitas
1,214,123
385,385
271,842
536,832
213,055
10,625,338
6,315,552
4,263,466
5,597,782
4,487,424
Professional Fee
318,761
189,466
127,903
167,934
134,623
Biaya Perijinan
159,379
94,734
63,953
83,967
67,311
1,062,534
631,556
426,346
559,778
448,742
1,540,674
915,756
618,201
811,679
650,676
12,166,012
7,231,308
4,881,667
6,409,461
5,138,100
1,216,601
723,131
488,167
640,946
513,810
13,382,613
7,954,438
5,369,834
7,050,407
5,651,910
Dinding
Pintu dan Jendela
Keuntungan Kontraktor
TOTAL BIAYA TIDAK LANGSUNG ( B )
TOTAL BIAYA PEMBANGUNAN BARU ( A + B )
PPN 10%
TOTAL BIAYA PEMB. BARU SETELAH PPN
PEMBULATAN
13,383,000
7,954,000
5,370,000
7,050,000
5,652,000
: PAPUA
KABUPATEN MAMBERAMO
:
RAYA
ELEMEN BANGUNAN
RUMAH
GEDUNG
BERTINGKAT
MENENGAH
MEWAH
MENENGAH
SEDERHANA
Spek 2 (dua)
lantai
Rp. / m
Rp. / m
Rp. / m
Rp. / m
GUDANG
Rp. / m
A. BIAYA LANGSUNG
Pondasi
1,519,723
1,158,806
681,032
1,176,935
825,234
Struktur
3,039,448
2,317,613
1,362,062
2,353,873
1,650,467
Rangka Atap
506,575
386,268
227,011
392,312
275,078
Penutup Atap
589,070
509,245
405,822
316,018
398,465
Plafon
825,993
221,769
191,425
489,673
1,902,327
990,589
879,246
462,263
653,417
815,285
424,539
376,821
198,112
280,036
Lantai
1,209,591
549,435
290,982
207,799
644,396
Utilitas
1,342,717
426,203
300,634
593,691
235,621
11,750,729
6,984,468
4,715,034
6,190,675
4,962,714
Dinding
Pintu dan Jendela
Professional Fee
352,522
209,534
141,450
185,721
148,882
Biaya Perijinan
176,260
104,768
70,726
92,861
74,440
1,175,073
698,447
471,503
619,067
496,270
1,703,855
1,012,749
683,679
897,649
719,592
13,454,585
7,997,217
5,398,713
7,088,324
5,682,306
1,345,458
799,722
539,871
708,832
568,231
14,800,043
8,796,939
5,938,584
7,797,157
6,250,537
PEMBULATAN
14,800,000
8,797,000
5,939,000
7,797,000
6,251,000
Keuntungan Kontraktor
TOTAL BIAYA TIDAK LANGSUNG ( B )
TOTAL BIAYA PEMBANGUNAN BARU ( A + B )
PPN 10%
: PAPUA
KABUPATEN
:
NDUGA
ELEMEN BANGUNAN
RUMAH
GEDUNG
BERTINGKAT
MENENGAH
MEWAH
MENENGAH
SEDERHANA
Spek 2 (dua)
lantai
Rp. / m
Rp. / m
Rp. / m
Rp. / m
GUDANG
Rp. / m
A. BIAYA LANGSUNG
Pondasi
2,302,695
1,755,831
1,031,904
1,783,300
1,250,399
Struktur
4,605,393
3,511,662
2,063,805
3,566,604
2,500,799
Rangka Atap
767,566
585,276
343,968
594,433
416,800
Penutup Atap
892,562
771,611
614,904
478,833
603,757
Plafon
1,251,550
336,026
290,049
741,955
Dinding
2,882,419
1,500,948
1,332,240
700,424
990,061
1,235,325
643,264
570,961
300,181
424,313
Lantai
1,832,781
832,508
440,897
314,858
976,393
Utilitas
2,034,495
645,786
455,523
899,564
357,015
17,804,784
10,582,913
7,144,252
9,380,153
7,519,537
Professional Fee
534,144
317,487
214,326
281,406
225,587
Biaya Perijinan
267,071
158,745
107,165
140,703
112,792
1,780,478
1,058,292
714,424
938,015
751,952
2,581,693
1,534,524
1,035,915
1,360,124
1,090,331
20,386,477
12,117,437
8,180,166
10,740,277
8,609,868
2,038,648
1,211,744
818,017
1,074,028
860,987
22,425,125
13,329,181
8,998,183
11,814,304
9,470,855
PEMBULATAN
22,425,000
13,329,000
8,998,000
11,814,000
9,471,000
Keuntungan Kontraktor
TOTAL BIAYA TIDAK LANGSUNG ( B )
TOTAL BIAYA PEMBANGUNAN BARU ( A + B )
PPN 10%
GEDUNG
BERTINGKAT
RUMAH
MENENGAH
-
MENENGAH
SEDERHANA
Spek 2 (dua)
lantai
GUDANG
MEWAH
Rp. / m
Rp. / m
Rp. / m
Rp. / m
Rp. / m
A. BIAYA LANGSUNG
Pondasi
2,594,357
1,978,227
1,162,606
2,009,175
1,408,776
Struktur
5,188,717
3,956,454
2,325,209
4,018,354
2,817,553
Rangka Atap
864,787
659,408
387,535
669,725
469,592
Penutup Atap
1,005,615
869,344
692,788
539,483
680,229
Plafon
1,410,072
378,588
326,787
835,932
Dinding
3,247,510
1,691,059
1,500,983
789,140
1,115,464
1,391,792
724,741
643,280
338,202
478,057
Lantai
2,064,923
937,954
496,742
354,738
1,100,064
Utilitas
2,292,186
727,582
513,220
1,013,504
402,235
20,059,958
11,923,357
8,049,151
10,568,253
8,471,970
Professional Fee
601,800
357,700
241,473
317,049
254,160
Biaya Perijinan
300,898
178,852
120,738
158,525
127,078
2,005,995
1,192,336
804,914
1,056,825
847,195
2,908,693
1,728,889
1,167,125
1,532,399
1,228,434
22,968,651
13,652,245
9,216,275
12,100,652
9,700,404
2,296,865
1,365,225
921,628
1,210,065
970,040
25,265,517
15,017,470
10,137,903
13,310,717
10,670,444
Keuntungan Kontraktor
TOTAL BIAYA TIDAK LANGSUNG ( B )
TOTAL BIAYA PEMBANGUNAN BARU ( A + B )
PPN 10%
TOTAL BIAYA PEMB. BARU SETELAH PPN
PEMBULATAN
25,266,000
15,017,000
10,138,000
13,311,000
10,670,000
: PAPUA
KABUPATEN MAMBERAMO
:
TENGAH
ELEMEN BANGUNAN
RUMAH
GEDUNG
BERTINGKAT
MENENGAH
MEWAH
MENENGAH
SEDERHANA
Spek 2 (dua)
lantai
Rp. / m
Rp. / m
Rp. / m
Rp. / m
GUDANG
Rp. / m
A. BIAYA LANGSUNG
Pondasi
2,858,471
2,179,617
1,280,964
2,213,716
1,552,195
Struktur
5,716,946
4,359,234
2,561,923
4,427,436
3,104,389
Rangka Atap
952,825
726,538
426,988
737,905
517,398
Penutup Atap
1,107,990
957,846
763,317
594,404
749,479
Plafon
1,553,623
417,130
360,055
921,033
Dinding
3,578,118
1,863,215
1,653,788
869,477
1,229,022
1,533,481
798,522
708,768
372,632
526,725
Lantai
2,275,139
1,033,441
547,312
390,852
1,212,054
Utilitas
2,525,538
801,652
565,468
1,116,682
443,184
22,102,131
13,137,196
8,868,582
11,644,138
9,334,446
Professional Fee
663,065
394,115
266,055
349,326
280,035
Biaya Perijinan
331,530
197,060
133,030
174,663
140,015
2,210,213
1,313,720
886,857
1,164,413
933,443
3,204,808
1,904,895
1,285,942
1,688,402
1,353,493
25,306,939
15,042,091
10,154,524
13,332,540
10,687,938
2,530,694
1,504,209
1,015,452
1,333,254
1,068,794
27,837,633
16,546,300
11,169,976
14,665,794
11,756,732
PEMBULATAN
27,838,000
16,546,000
11,170,000
14,666,000
11,757,000
Keuntungan Kontraktor
TOTAL BIAYA TIDAK LANGSUNG ( B )
TOTAL BIAYA PEMBANGUNAN BARU ( A + B )
PPN 10%
: PAPUA
KABUPATEN
:
YALIMO
ELEMEN BANGUNAN
RUMAH
GEDUNG
BERTINGKAT
MENENGAH
MEWAH
MENENGAH
SEDERHANA
Spek 2 (dua)
lantai
Rp. / m
Rp. / m
Rp. / m
Rp. / m
GUDANG
Rp. / m
A. BIAYA LANGSUNG
Pondasi
2,774,196
2,115,356
1,243,197
2,148,450
1,506,432
Struktur
5,548,396
4,230,712
2,486,391
4,296,904
3,012,864
Rangka Atap
924,733
705,117
414,399
716,150
502,144
Penutup Atap
1,075,324
929,607
740,812
576,879
727,382
Plafon
1,507,818
404,831
349,440
893,879
Dinding
3,472,625
1,808,283
1,605,030
843,843
1,192,787
1,488,270
774,979
687,871
361,646
511,196
Lantai
2,208,062
1,002,973
531,176
379,329
1,176,319
Utilitas
2,451,079
778,017
548,796
1,083,759
430,118
21,450,502
12,749,877
8,607,113
11,300,838
9,059,242
Professional Fee
643,516
382,496
258,211
339,027
271,778
Biaya Perijinan
321,756
191,250
129,108
169,513
135,887
2,145,050
1,274,988
860,710
1,130,083
905,923
3,110,322
1,848,734
1,248,029
1,638,623
1,313,588
24,560,824
14,598,611
9,855,142
12,939,462
10,372,830
2,456,082
1,459,861
985,514
1,293,946
1,037,283
27,016,907
16,058,472
10,840,656
14,233,408
11,410,113
PEMBULATAN
27,017,000
16,058,000
10,841,000
14,233,000
11,410,000
Keuntungan Kontraktor
TOTAL BIAYA TIDAK LANGSUNG ( B )
TOTAL BIAYA PEMBANGUNAN BARU ( A + B )
PPN 10%
GEDUNG
BERTINGKAT
RUMAH
MENENGAH
-
MENENGAH
SEDERHANA
Spek 2 (dua)
lantai
GUDANG
MEWAH
Rp. / m
Rp. / m
Rp. / m
Rp. / m
Rp. / m
A. BIAYA LANGSUNG
Pondasi
3,276,723
2,498,539
1,468,395
2,537,628
1,779,312
Struktur
6,553,451
4,997,078
2,936,784
5,075,260
3,558,624
Rangka Atap
1,092,243
832,845
489,465
845,876
593,104
Penutup Atap
1,270,111
1,097,999
875,005
681,377
859,143
Plafon
1,780,949
478,164
412,738
1,055,799
Dinding
4,101,669
2,135,841
1,895,771
996,699
1,408,853
1,757,861
915,362
812,475
427,155
603,795
Lantai
2,608,038
1,184,655
627,395
448,042
1,389,402
Utilitas
2,895,076
918,950
648,207
1,280,075
508,031
25,336,121
15,059,433
10,166,235
13,347,911
10,700,264
Professional Fee
760,085
451,782
304,985
400,440
321,009
Biaya Perijinan
380,040
225,894
152,495
200,220
160,502
2,533,612
1,505,944
1,016,622
1,334,790
1,070,024
3,673,737
2,183,620
1,474,101
1,935,449
1,551,536
29,009,857
17,243,054
11,640,337
15,283,361
12,251,800
2,900,986
1,724,305
1,164,034
1,528,336
1,225,180
31,910,843
18,967,359
12,804,370
16,811,697
13,476,980
Keuntungan Kontraktor
TOTAL BIAYA TIDAK LANGSUNG ( B )
TOTAL BIAYA PEMBANGUNAN BARU ( A + B )
PPN 10%
TOTAL BIAYA PEMB. BARU SETELAH PPN
PEMBULATAN
31,911,000
18,967,000
12,804,000
16,812,000
13,477,000
: PAPUA
KABUPATEN
:
DOGIYAI
ELEMEN BANGUNAN
RUMAH
GEDUNG
BERTINGKAT
MENENGAH
MEWAH
MENENGAH
SEDERHANA
Spek 2 (dua)
lantai
Rp. / m
Rp. / m
Rp. / m
Rp. / m
GUDANG
Rp. / m
A. BIAYA LANGSUNG
Pondasi
1,509,002
1,150,632
676,228
1,168,633
819,412
Struktur
3,018,007
2,301,263
1,352,453
2,337,268
1,638,824
Rangka Atap
503,002
383,543
225,409
389,544
273,137
Penutup Atap
584,914
505,652
402,959
313,789
395,654
Plafon
820,166
220,205
190,075
486,218
1,888,908
983,601
873,044
459,002
648,807
809,533
421,544
374,162
196,714
278,061
Lantai
1,201,058
545,559
288,929
206,333
639,850
Utilitas
1,333,245
423,197
298,514
589,503
233,959
11,667,835
6,935,197
4,681,772
6,147,004
4,927,704
Dinding
Pintu dan Jendela
Professional Fee
350,036
208,056
140,452
184,411
147,832
Biaya Perijinan
175,017
104,029
70,227
92,206
73,915
1,166,783
693,520
468,177
614,700
492,770
1,691,836
1,005,605
678,856
891,317
714,516
13,359,670
7,940,801
5,360,628
7,038,320
5,642,221
1,335,967
794,080
536,063
703,832
564,222
14,695,637
8,734,882
5,896,691
7,742,152
6,206,443
PEMBULATAN
14,696,000
8,735,000
5,897,000
7,742,000
6,206,000
Keuntungan Kontraktor
TOTAL BIAYA TIDAK LANGSUNG ( B )
TOTAL BIAYA PEMBANGUNAN BARU ( A + B )
PPN 10%
: PAPUA
KABUPATEN INTAN
:
JAYA
ELEMEN BANGUNAN
RUMAH
GEDUNG
BERTINGKAT
MENENGAH
MEWAH
MENENGAH
SEDERHANA
Spek 2 (dua)
lantai
Rp. / m
Rp. / m
Rp. / m
Rp. / m
GUDANG
Rp. / m
A. BIAYA LANGSUNG
Pondasi
3,074,448
2,344,302
1,377,749
2,380,978
1,669,474
Struktur
6,148,901
4,688,605
2,755,494
4,761,960
3,338,948
Rangka Atap
1,024,818
781,433
459,250
793,659
556,491
Penutup Atap
1,191,706
1,030,218
820,991
639,315
806,107
Plafon
1,671,010
448,647
387,260
990,624
Dinding
3,848,469
2,003,994
1,778,744
935,172
1,321,883
1,649,347
858,856
762,320
400,787
566,523
Lantai
2,447,042
1,111,525
588,665
420,384
1,303,633
Utilitas
2,716,360
862,223
608,193
1,201,055
476,670
23,772,102
14,129,803
9,538,665
12,523,934
10,039,728
Professional Fee
713,164
423,893
286,158
375,720
301,193
Biaya Perijinan
356,580
211,949
143,081
187,860
150,594
2,377,210
1,412,981
953,865
1,252,392
1,003,971
3,446,954
2,048,824
1,383,104
1,815,973
1,455,758
27,219,056
16,178,626
10,921,769
14,339,907
11,495,487
2,721,906
1,617,863
1,092,177
1,433,991
1,149,549
29,940,961
17,796,489
12,013,946
15,773,897
12,645,035
PEMBULATAN
29,941,000
17,796,000
12,014,000
15,774,000
12,645,000
Keuntungan Kontraktor
TOTAL BIAYA TIDAK LANGSUNG ( B )
TOTAL BIAYA PEMBANGUNAN BARU ( A + B )
PPN 10%
GEDUNG
BERTINGKAT
RUMAH
MENENGAH
-
MENENGAH
SEDERHANA
Spek 2 (dua)
lantai
GUDANG
MEWAH
Rp. / m
Rp. / m
Rp. / m
Rp. / m
Rp. / m
A. BIAYA LANGSUNG
Pondasi
1,569,706
1,196,919
703,431
1,215,644
852,375
Struktur
3,139,414
2,393,838
1,406,859
2,431,291
1,704,750
Rangka Atap
523,236
398,972
234,477
405,215
284,125
Penutup Atap
608,444
525,994
419,169
326,412
411,570
Plafon
853,159
229,063
197,721
505,778
1,964,894
1,023,169
908,164
477,466
674,907
842,099
438,502
389,214
204,628
289,247
Lantai
1,249,374
567,506
300,552
214,633
665,589
Utilitas
1,386,879
440,221
310,522
613,217
243,371
12,137,205
7,214,184
4,870,109
6,394,284
5,125,935
Professional Fee
364,117
216,425
146,102
191,830
153,779
Biaya Perijinan
182,057
108,214
73,052
95,915
76,888
1,213,720
721,419
487,010
639,428
512,593
1,759,894
1,046,058
706,165
927,172
743,259
13,897,100
8,260,242
5,576,274
7,321,456
5,869,194
1,389,710
826,024
557,627
732,146
586,919
15,286,809
9,086,266
6,133,902
8,053,601
6,456,114
Dinding
Pintu dan Jendela
Keuntungan Kontraktor
TOTAL BIAYA TIDAK LANGSUNG ( B )
TOTAL BIAYA PEMBANGUNAN BARU ( A + B )
PPN 10%
TOTAL BIAYA PEMB. BARU SETELAH PPN
PEMBULATAN
15,287,000
9,086,000
6,134,000
8,054,000
6,456,000
: PAPUA
KABUPATEN
:
DEIYAI
ELEMEN BANGUNAN
RUMAH
GEDUNG
BERTINGKAT
MENENGAH
MEWAH
MENENGAH
SEDERHANA
Spek 2 (dua)
lantai
Rp. / m
Rp. / m
Rp. / m
Rp. / m
GUDANG
Rp. / m
A. BIAYA LANGSUNG
Pondasi
1,569,706
1,196,919
703,431
1,215,644
852,375
Struktur
3,139,414
2,393,838
1,406,859
2,431,291
1,704,750
Rangka Atap
523,236
398,972
234,477
405,215
284,125
Penutup Atap
608,444
525,994
419,169
326,412
411,570
Plafon
853,159
229,063
197,721
505,778
1,964,894
1,023,169
908,164
477,466
674,907
842,099
438,502
389,214
204,628
289,247
Lantai
1,249,374
567,506
300,552
214,633
665,589
Utilitas
1,386,879
440,221
310,522
613,217
243,371
12,137,205
7,214,184
4,870,109
6,394,284
5,125,935
Dinding
Pintu dan Jendela
Professional Fee
364,117
216,425
146,102
191,830
153,779
Biaya Perijinan
182,057
108,214
73,052
95,915
76,888
1,213,720
721,419
487,010
639,428
512,593
1,759,894
1,046,058
706,165
927,172
743,259
13,897,100
8,260,242
5,576,274
7,321,456
5,869,194
1,389,710
826,024
557,627
732,146
586,919
15,286,809
9,086,266
6,133,902
8,053,601
6,456,114
PEMBULATAN
15,287,000
9,086,000
6,134,000
8,054,000
6,456,000
Keuntungan Kontraktor
TOTAL BIAYA TIDAK LANGSUNG ( B )
TOTAL BIAYA PEMBANGUNAN BARU ( A + B )
PPN 10%
: PAPUA
KOTA
:
JAYAPURA
ELEMEN BANGUNAN
RUMAH
GEDUNG
BERTINGKAT
MENENGAH
MEWAH
MENENGAH
SEDERHANA
Spek 2 (dua)
lantai
Rp. / m
Rp. / m
Rp. / m
Rp. / m
GUDANG
Rp. / m
A. BIAYA LANGSUNG
Pondasi
1,403,712
1,070,346
629,044
1,087,091
762,237
Struktur
2,807,425
2,140,692
1,258,085
2,174,185
1,524,475
Rangka Atap
467,905
356,781
209,681
362,364
254,079
Penutup Atap
544,102
470,370
374,842
291,894
368,047
Plafon
762,939
204,840
176,812
452,292
Dinding
1,757,109
914,970
812,127
426,975
603,537
753,048
392,131
348,055
182,989
258,659
Lantai
1,117,254
507,493
268,769
191,936
595,204
Utilitas
1,240,218
393,668
277,685
548,370
217,635
10,853,710
6,451,293
4,355,101
5,718,096
4,583,873
Professional Fee
325,612
193,538
130,652
171,544
137,517
Biaya Perijinan
162,805
96,770
65,327
85,772
68,757
1,085,371
645,130
435,509
571,809
458,386
1,573,788
935,438
631,489
829,125
664,661
12,427,498
7,386,731
4,986,590
6,547,221
5,248,534
1,242,750
738,673
498,659
654,722
524,853
13,670,248
8,125,404
5,485,249
7,201,943
5,773,387
PEMBULATAN
13,670,000
8,125,000
5,485,000
7,202,000
5,773,000
Keuntungan Kontraktor
TOTAL BIAYA TIDAK LANGSUNG ( B )
TOTAL BIAYA PEMBANGUNAN BARU ( A + B )
PPN 10%
GEDUNG
BERTINGKAT
RUMAH
MENENGAH
MENENGAH
SEDERHANA
Spek 2 (dua)
GUDANG
MEWAH
Rp. / m
lantai
Rp. / m
Rp. / m
Rp. / m
Rp. / m
A. BIAYA LANGSUNG
Pondasi
1,062,564
810,217
476,166
822,892
576,989
Struktur
2,125,129
1,620,434
952,330
1,645,787
1,153,978
Rangka Atap
354,188
270,072
158,722
274,297
192,330
Penutup Atap
411,867
356,055
283,744
220,955
278,600
Plafon
577,520
155,057
133,841
342,371
1,330,074
692,603
614,754
323,206
456,858
570,033
296,830
263,466
138,516
195,797
Lantai
845,725
384,155
203,449
145,289
450,550
Utilitas
938,804
297,994
210,198
415,098
164,742
8,215,904
4,883,417
3,296,669
4,328,411
3,469,842
Professional Fee
246,478
146,502
98,899
129,853
104,096
Biaya Perijinan
123,238
73,252
49,450
64,927
52,047
Keuntungan Kontraktor
821,590
488,342
329,666
432,841
346,984
1,191,306
708,096
478,016
627,620
503,126
9,407,209
5,591,514
3,774,685
4,956,032
3,972,968
940,721
559,151
377,469
495,603
397,297
10,347,930
6,150,665
4,152,154
5,451,635
4,370,265
Dinding
PPN 10%
TOTAL BIAYA PEMB. BARU SETELAH PPN
PEMBULATAN
Provinsi
Kota /
Kabupaten
10,348,000
6,151,000
4,152,000
5,452,000
4,370,000
: PAPUA BARAT
KABUPATEN
:
FAKFAK
ELEMEN BANGUNAN
RUMAH
GEDUNG
BERTINGKAT
MENENGAH
MEWAH
MENENGAH
SEDERHANA
Spek 2 (dua)
lantai
Rp. / m
Rp. / m
Rp. / m
Rp. / m
GUDANG
Rp. / m
A. BIAYA LANGSUNG
Pondasi
1,047,796
798,957
469,548
811,456
568,970
Struktur
2,095,594
1,597,913
939,094
1,622,913
1,137,939
Rangka Atap
349,266
266,318
156,516
270,485
189,657
Penutup Atap
406,143
351,106
279,800
217,884
274,728
Plafon
569,493
152,902
131,981
337,612
1,311,588
682,977
606,210
318,714
450,508
562,110
292,705
259,805
136,591
193,075
Lantai
833,971
378,816
200,622
143,270
444,288
Utilitas
925,757
293,852
207,277
409,329
162,453
8,101,718
4,815,547
3,250,852
4,268,254
3,421,618
Dinding
Professional Fee
243,052
144,466
97,525
128,048
102,649
Biaya Perijinan
121,525
72,234
48,763
64,024
51,324
Keuntungan Kontraktor
810,172
481,555
325,085
426,825
342,161
1,174,749
698,255
471,373
618,898
496,134
9,276,466
5,513,802
3,722,224
4,887,152
3,917,752
927,647
551,380
372,222
488,715
391,775
10,204,113
6,065,182
4,094,447
5,375,867
4,309,527
PEMBULATAN
10,204,000
6,065,000
4,094,000
5,376,000
4,310,000
PPN 10%
: PAPUA BARAT
KABUPATEN TELUK
:
WONDAMA
ELEMEN BANGUNAN
RUMAH
GEDUNG
BERTINGKAT
MENENGAH
MEWAH
MENENGAH
SEDERHANA
Spek 2 (dua)
lantai
Rp. / m
Rp. / m
Rp. / m
Rp. / m
GUDANG
Rp. / m
A. BIAYA LANGSUNG
Pondasi
983,045
749,583
440,531
761,310
533,809
Struktur
1,966,092
1,499,167
881,061
1,522,622
1,067,618
Rangka Atap
327,682
249,861
146,844
253,770
177,936
Penutup Atap
381,044
329,409
262,509
204,419
257,750
Plafon
534,300
143,453
123,825
316,749
1,230,536
640,771
568,748
299,018
422,668
527,373
274,617
243,749
128,150
181,144
Lantai
782,434
355,407
188,224
134,416
416,833
Utilitas
868,548
275,693
194,468
384,034
152,414
7,601,056
4,517,961
3,049,959
4,004,489
3,210,172
Professional Fee
228,032
135,539
91,498
120,135
96,306
Biaya Perijinan
114,015
67,770
45,750
60,068
48,152
Keuntungan Kontraktor
760,105
451,796
304,995
400,449
321,017
1,102,153
655,105
442,243
580,652
465,474
8,703,209
5,173,066
3,492,202
4,585,141
3,675,646
870,321
517,307
349,220
458,514
367,565
9,573,529
5,690,372
3,841,422
5,043,655
4,043,211
PEMBULATAN
9,574,000
5,690,000
3,841,000
5,044,000
4,043,000
Dinding
PPN 10%
GEDUNG
BERTINGKAT
RUMAH
MENENGAH
-
MENENGAH
SEDERHANA
Spek 2 (dua)
lantai
GUDANG
MEWAH
Rp. / m
Rp. / m
Rp. / m
Rp. / m
Rp. / m
A. BIAYA LANGSUNG
Pondasi
1,367,360
1,042,628
612,754
1,058,939
742,498
Struktur
2,734,723
2,085,256
1,225,505
2,117,881
1,484,996
Rangka Atap
455,787
347,542
204,251
352,980
247,499
Penutup Atap
530,011
458,189
365,135
284,335
358,516
Plafon
743,181
199,535
172,234
440,580
1,711,606
891,276
791,096
415,918
587,907
733,547
381,976
339,042
178,250
251,961
Lantai
1,088,321
494,351
261,809
186,966
579,790
Utilitas
1,208,101
383,473
270,494
534,169
211,999
10,572,637
6,284,227
4,242,319
5,570,017
4,465,167
Professional Fee
317,180
188,527
127,269
167,101
133,956
Biaya Perijinan
158,589
94,264
63,635
83,551
66,977
1,057,264
628,423
424,231
557,001
446,516
1,533,032
911,214
615,135
807,653
647,448
12,105,669
7,195,441
4,857,455
6,377,670
5,112,615
1,210,567
719,544
485,745
637,767
511,262
13,316,236
7,914,985
5,343,200
7,015,438
5,623,877
Dinding
Pintu dan Jendela
Keuntungan Kontraktor
TOTAL BIAYA TIDAK LANGSUNG ( B )
TOTAL BIAYA PEMBANGUNAN BARU ( A + B )
PPN 10%
TOTAL BIAYA PEMB. BARU SETELAH PPN
PEMBULATAN
13,316,000
7,915,000
5,343,000
7,015,000
5,624,000
: PAPUA BARAT
KABUPATEN
:
MANOKWARI
ELEMEN BANGUNAN
RUMAH
GEDUNG
BERTINGKAT
MENENGAH
MEWAH
MENENGAH
SEDERHANA
Spek 2 (dua)
lantai
Rp. / m
Rp. / m
Rp. / m
Rp. / m
GUDANG
Rp. / m
A. BIAYA LANGSUNG
Pondasi
916,946
699,182
410,910
710,120
497,916
Struktur
1,833,893
1,398,363
821,818
1,420,241
995,832
Rangka Atap
305,649
233,060
136,970
236,707
165,972
Penutup Atap
355,423
307,260
244,858
190,674
240,419
Plafon
498,374
133,808
115,499
295,451
1,147,795
597,686
530,505
278,913
394,248
491,913
256,151
227,360
119,534
168,964
Lantai
729,823
331,509
175,568
125,378
388,805
Utilitas
810,147
257,156
181,392
358,211
142,165
7,089,964
4,214,175
2,844,881
3,735,229
2,994,321
Dinding
Professional Fee
212,699
126,425
85,346
112,057
89,830
Biaya Perijinan
106,349
63,213
42,674
56,029
44,914
Keuntungan Kontraktor
708,996
421,418
284,488
373,523
299,432
1,028,044
611,056
412,507
541,609
434,176
8,118,008
4,825,231
3,257,387
4,276,838
3,428,497
811,801
482,523
325,739
427,684
342,850
8,929,809
5,307,754
3,583,126
4,704,521
3,771,347
PEMBULATAN
8,930,000
5,308,000
3,583,000
4,705,000
3,771,000
PPN 10%
: PAPUA BARAT
KABUPATEN SORONG
:
SELATAN
ELEMEN BANGUNAN
RUMAH
GEDUNG
BERTINGKAT
MENENGAH
MEWAH
MENENGAH
SEDERHANA
Spek 2 (dua)
lantai
Rp. / m
Rp. / m
Rp. / m
Rp. / m
GUDANG
Rp. / m
A. BIAYA LANGSUNG
Pondasi
1,057,097
806,048
473,716
818,659
574,020
Struktur
2,114,195
1,612,097
947,430
1,637,319
1,148,040
Rangka Atap
352,366
268,682
157,905
272,886
191,340
Penutup Atap
409,748
354,223
282,284
219,818
277,166
Plafon
574,548
154,259
133,153
340,609
1,323,231
689,039
611,591
321,543
454,507
567,100
295,303
262,111
137,804
194,789
Lantai
841,374
382,179
202,403
144,542
448,232
Utilitas
933,974
296,461
209,117
412,962
163,895
8,173,633
4,858,292
3,279,708
4,306,142
3,451,990
Professional Fee
245,209
145,749
98,390
129,185
103,560
Biaya Perijinan
122,604
72,875
49,196
64,592
51,779
Keuntungan Kontraktor
817,363
485,830
327,970
430,614
345,198
1,185,176
704,453
475,557
624,391
500,538
9,358,809
5,562,745
3,755,265
4,930,533
3,952,528
935,881
556,275
375,526
493,053
395,253
10,294,690
6,119,020
4,130,791
5,423,586
4,347,780
PEMBULATAN
10,295,000
6,119,000
4,131,000
5,424,000
4,348,000
Dinding
PPN 10%
GEDUNG
BERTINGKAT
RUMAH
MENENGAH
-
MENENGAH
SEDERHANA
Spek 2 (dua)
lantai
GUDANG
MEWAH
Rp. / m
Rp. / m
Rp. / m
Rp. / m
Rp. / m
A. BIAYA LANGSUNG
Pondasi
942,576
718,725
422,396
729,969
511,834
Struktur
1,885,154
1,437,450
844,790
1,459,940
1,023,667
Rangka Atap
314,193
239,575
140,799
243,323
170,611
Penutup Atap
365,358
315,848
251,702
196,004
247,139
Plafon
512,305
137,548
118,728
303,709
1,179,879
614,392
545,334
286,709
405,268
505,663
263,311
233,715
122,875
173,687
Lantai
750,223
340,776
180,475
128,883
399,673
Utilitas
832,792
264,344
186,462
368,224
146,139
7,288,142
4,331,969
2,924,401
3,839,636
3,078,018
Professional Fee
218,645
129,959
87,731
115,190
92,341
Biaya Perijinan
109,322
64,980
43,866
57,595
46,170
Keuntungan Kontraktor
728,814
433,197
292,440
383,963
307,801
1,056,780
628,136
424,037
556,748
446,312
8,344,923
4,960,105
3,348,438
4,396,384
3,524,330
834,492
496,011
334,844
439,638
352,433
9,179,415
5,456,116
3,683,282
4,836,022
3,876,764
Dinding
PPN 10%
TOTAL BIAYA PEMB. BARU SETELAH PPN
PEMBULATAN
9,179,000
5,456,000
3,683,000
4,836,000
3,877,000
: PAPUA BARAT
KABUPATEN RAJA
:
AMPAT
ELEMEN BANGUNAN
RUMAH
GEDUNG
BERTINGKAT
MENENGAH
MEWAH
MENENGAH
SEDERHANA
Spek 2 (dua)
lantai
Rp. / m
Rp. / m
Rp. / m
Rp. / m
GUDANG
Rp. / m
A. BIAYA LANGSUNG
Pondasi
1,041,761
794,355
466,843
806,782
565,693
Struktur
2,083,524
1,588,710
933,685
1,613,566
1,131,385
Rangka Atap
347,254
264,784
155,614
268,927
188,564
Penutup Atap
403,804
349,084
278,188
216,629
273,145
Plafon
566,213
152,022
131,221
335,668
1,304,034
679,043
602,718
316,878
447,913
558,873
291,019
258,308
135,805
191,963
Lantai
829,167
376,635
199,466
142,445
441,729
Utilitas
920,425
292,160
206,083
406,971
161,517
8,055,055
4,787,811
3,232,128
4,243,671
3,401,911
241,652
143,634
96,963
127,311
102,058
Dinding
Biaya Perijinan
120,825
71,818
48,482
63,655
51,028
Keuntungan Kontraktor
805,505
478,781
323,212
424,367
340,190
1,167,983
694,233
468,658
615,333
493,276
9,223,038
5,482,045
3,700,786
4,859,004
3,895,187
922,304
548,204
370,079
485,900
389,519
10,145,342
6,030,249
4,070,864
5,344,904
4,284,706
PEMBULATAN
10,145,000
6,030,000
4,071,000
5,345,000
4,285,000
PPN 10%
: PAPUA BARAT
KABUPATEN
:
TAMBRAUW
ELEMEN BANGUNAN
RUMAH
GEDUNG
BERTINGKAT
MENENGAH
MEWAH
MENENGAH
SEDERHANA
Spek 2 (dua)
lantai
Rp. / m
Rp. / m
Rp. / m
Rp. / m
GUDANG
Rp. / m
A. BIAYA LANGSUNG
Pondasi
1,400,588
1,067,964
627,644
1,084,672
760,541
Struktur
2,801,177
2,135,928
1,255,286
2,169,346
1,521,082
466,863
355,987
209,215
361,557
253,514
Rangka Atap
Penutup Atap
542,891
469,324
374,008
291,245
367,228
Plafon
761,241
204,384
176,419
451,286
1,753,199
912,934
810,320
426,025
602,194
751,372
391,258
347,281
182,581
258,084
Lantai
1,114,768
506,363
268,171
191,509
593,880
Utilitas
1,237,458
392,792
277,067
547,150
217,150
10,829,556
6,436,935
4,345,409
5,705,370
4,573,672
Professional Fee
324,887
193,108
130,361
171,162
137,211
Biaya Perijinan
162,443
96,555
65,182
85,581
68,604
1,082,955
643,694
434,540
570,537
457,366
1,570,285
933,357
630,083
827,280
663,181
12,399,841
7,370,292
4,975,492
6,532,650
5,236,854
1,239,984
737,029
497,549
653,265
523,685
13,639,825
8,107,321
5,473,042
7,185,915
5,760,539
PEMBULATAN
13,640,000
8,107,000
5,473,000
7,186,000
5,761,000
Dinding
Pintu dan Jendela
Keuntungan Kontraktor
TOTAL BIAYA TIDAK LANGSUNG ( B )
TOTAL BIAYA PEMBANGUNAN BARU ( A + B )
PPN 10%
RUMAH
GEDUNG
BERTINGKAT
GUDANG
MENENGAH
MEWAH
MENENGAH
SEDERHANA
Spek 2 (dua)
lantai
Rp. / m
Rp. / m
Rp. / m
Rp. / m
Rp. / m
A. BIAYA LANGSUNG
Pondasi
1,489,975
1,136,123
667,701
1,153,897
809,080
Struktur
2,979,952
2,272,246
1,335,399
2,307,796
1,618,159
Rangka Atap
496,659
378,707
222,567
384,632
269,693
Penutup Atap
577,539
499,276
397,878
309,832
390,665
Plafon
809,824
217,428
187,678
480,087
1,865,090
971,199
862,035
453,214
640,626
799,325
416,229
369,444
194,234
274,555
Lantai
1,185,914
538,680
285,286
203,731
631,782
Utilitas
1,316,434
417,860
294,749
582,069
231,009
11,520,710
6,847,748
4,622,738
6,069,494
4,865,569
Professional Fee
345,622
205,432
138,681
182,086
145,968
Biaya Perijinan
172,810
102,717
69,342
91,043
72,983
1,152,071
684,775
462,273
606,949
486,556
1,670,503
992,925
670,296
880,078
705,506
13,191,213
7,840,673
5,293,034
6,949,571
5,571,076
1,319,121
784,067
529,303
694,957
557,108
Dinding
Pintu dan Jendela
Keuntungan Kontraktor
TOTAL BIAYA TIDAK LANGSUNG ( B )
TOTAL BIAYA PEMBANGUNAN BARU ( A + B )
PPN 10%
14,510,334
8,624,740
5,822,337
7,644,528
6,128,183
PEMBULATAN
14,510,000
8,625,000
5,822,000
7,645,000
6,128,000
PAPUA
BARAT
KOTA
:
SORONG
:
Kota /
Kabupaten
ELEMEN BANGUNAN
RUMAH
GEDUNG
BERTINGKAT
MENENGAH
MEWAH
MENENGAH
SEDERHANA
Spek 2 (dua)
lantai
Rp. / m
Rp. / m
Rp. / m
Rp. / m
GUDANG
Rp. / m
A. BIAYA LANGSUNG
Pondasi
910,343
694,147
407,951
705,007
494,331
Struktur
1,820,687
1,388,294
815,901
1,410,014
988,661
Rangka Atap
303,448
231,382
135,984
235,002
164,777
Penutup Atap
352,864
305,047
243,095
189,301
238,688
Plafon
494,785
132,844
114,667
293,323
1,139,530
593,382
526,685
276,904
391,409
488,371
254,307
225,723
118,673
167,747
Lantai
724,568
329,122
174,304
124,475
386,005
Utilitas
804,313
255,304
180,086
355,632
141,142
Dinding
7,038,909
4,183,829
2,824,395
3,708,332
2,972,759
Professional Fee
211,168
125,515
84,731
111,251
89,183
Biaya Perijinan
105,583
62,758
42,366
55,625
44,591
Keuntungan Kontraktor
703,891
418,383
282,439
370,833
297,275
1,020,642
606,656
409,537
537,709
431,049
8,059,551
4,790,484
3,233,931
4,246,040
3,403,809
805,955
479,048
323,393
424,604
340,381
8,865,506
5,269,533
3,557,324
4,670,644
3,744,190
PEMBULATAN
8,866,000
5,270,000
3,557,000
4,671,000
3,744,000
PPN 10%
: PAPUA BARAT
KABUPATEN
:
SORONG
ELEMEN BANGUNAN
RUMAH
GEDUNG
BERTINGKAT
MENENGAH
MENENGAH SEDERHANA
MEWAH
Spek 2 (dua)
lantai
Rp. / m
Rp. / m
Rp. / m
Rp. / m
GUDANG
Rp. / m
A. BIAYA LANGSUNG
Pondasi
942,576
718,725
422,396
729,969
511,834
Struktur
1,885,154
1,437,450
844,790
1,459,940
1,023,667
Rangka Atap
314,193
239,575
140,799
243,323
170,611
Penutup Atap
365,358
315,848
251,702
196,004
247,139
Plafon
512,305
137,548
118,728
303,709
1,179,879
614,392
545,334
286,709
405,268
505,663
263,311
233,715
122,875
173,687
Lantai
750,223
340,776
180,475
128,883
399,673
Utilitas
832,792
264,344
186,462
368,224
146,139
7,288,142
4,331,969
2,924,401
3,839,636
3,078,018
Professional Fee
218,645
129,959
87,731
115,190
92,341
Biaya Perijinan
109,322
64,980
43,866
57,595
46,170
Keuntungan Kontraktor
728,814
433,197
292,440
383,963
307,801
1,056,780
628,136
424,037
556,748
446,312
Dinding
RUMAH
GEDUNG
GUDANG
BERTINGKAT
MENENGAH
MEWAH
MENENGAH
SEDERHANA
Spek 2 (dua)
lantai
Rp. / m
Rp. / m
Rp. / m
Rp. / m
Rp. / m
A. BIAYA LANGSUNG
Pondasi
590,353
450,151
264,554
457,193
320,571
Struktur
1,180,706
900,301
529,107
914,387
641,141
Rangka Atap
196,784
150,050
88,185
152,398
106,857
Penutup Atap
228,830
197,822
157,646
122,761
154,788
Plafon
320,866
86,149
74,361
190,219
Dinding
738,979
384,805
341,553
179,571
253,827
316,706
164,917
146,380
76,959
108,783
Lantai
469,879
213,434
113,035
80,722
250,322
Utilitas
521,593
165,563
116,785
230,625
91,530
4,564,696
2,713,191
1,831,605
2,404,834
1,927,819
136,941
81,396
54,948
72,145
57,835
68,470
40,698
27,474
36,073
28,917
456,469
271,319
183,160
240,483
192,782
661,881
393,413
265,582
348,701
279,533
5,226,577
3,106,604
2,097,188
2,753,535
2,207,352
PPN 10%
522,658
310,660
209,719
275,353
220,735
5,749,234
3,417,264
2,306,906
3,028,888
2,428,087
PEMBULATAN
5,749,000
3,417,000
2,307,000
3,029,000
2,428,000
: JAWA TENGAH
KOTA
:
SURAKARTA
ELEMEN BANGUNAN
RUMAH
GEDUNG
BERTINGKAT
MENENGAH
MEWAH
MENENGAH
SEDERHANA
Spek 2 (dua)
lantai
Rp. / m
Rp. / m
Rp. / m
Rp. / m
GUDANG
Rp. / m
A. BIAYA LANGSUNG
Pondasi
601,570
458,704
269,581
465,881
326,662
Struktur
1,203,142
917,409
539,161
931,762
653,324
Rangka Atap
200,524
152,901
89,860
155,294
108,887
Penutup Atap
233,179
201,581
160,641
125,093
157,729
Plafon
326,963
87,786
75,774
193,833
Dinding
753,021
392,117
348,043
182,983
258,650
322,724
168,050
149,161
78,421
110,850
Lantai
478,807
217,490
115,183
82,256
255,079
Utilitas
531,504
168,709
119,004
235,008
93,269
4,651,433
2,764,746
1,866,409
2,450,530
1,964,451
139,543
82,942
55,992
73,516
58,934
69,771
41,472
27,996
36,758
29,466
465,143
276,475
186,641
245,053
196,445
674,458
400,889
270,629
355,327
284,845
5,325,891
3,165,635
2,137,038
2,805,857
2,249,296
532,589
316,564
213,704
280,586
224,930
5,858,480
3,482,199
2,350,742
3,086,443
2,474,225
PEMBULATAN
5,858,000
3,482,000
2,351,000
3,086,000
2,474,000
: JAWA TENGAH
KABUPATEN
:
SEMARANG
ELEMEN BANGUNAN
RUMAH
GEDUNG
BERTINGKAT
MENENGAH
MEWAH
MENENGAH
SEDERHANA
Spek 2 (dua)
lantai
Rp. / m
Rp. / m
Rp. / m
Rp. / m
GUDANG
Rp. / m
A. BIAYA LANGSUNG
Pondasi
604,197
460,707
270,758
467,915
328,089
Struktur
1,208,396
921,415
541,516
935,831
656,177
Rangka Atap
201,399
153,569
90,253
155,972
109,363
Penutup Atap
234,197
202,461
161,343
125,640
158,418
Plafon
328,390
88,169
76,105
194,680
Dinding
756,310
393,829
349,563
183,782
259,779
324,133
168,784
149,813
78,763
111,334
Lantai
480,898
218,439
115,686
82,615
256,193
Utilitas
533,825
169,446
119,523
236,034
93,676
4,671,745
2,776,820
1,874,559
2,461,231
1,973,029
140,153
83,304
56,236
73,837
59,191
70,076
41,653
28,119
36,919
29,595
467,174
277,682
187,456
246,123
197,303
677,403
402,639
271,811
356,879
286,089
5,349,148
3,179,459
2,146,370
2,818,110
2,259,118
534,915
317,946
214,637
281,811
225,912
5,884,063
3,497,405
2,361,007
3,099,921
2,485,030
PEMBULATAN
5,884,000
3,497,000
2,361,000
3,100,000
2,485,000
RUMAH
GEDUNG
GUDANG
BERTINGKAT
MENENGAH
MEWAH
MENENGAH
SEDERHANA
Spek 2 (dua)
lantai
Rp. / m
Rp. / m
Rp. / m
Rp. / m
Rp. / m
A. BIAYA LANGSUNG
Pondasi
651,198
496,546
291,821
504,314
353,611
Struktur
1,302,398
993,092
583,641
1,008,630
707,222
Rangka Atap
217,066
165,515
97,274
168,105
117,870
Penutup Atap
252,415
218,210
173,894
135,413
170,741
Plafon
353,936
95,028
82,025
209,824
Dinding
815,144
424,466
376,755
198,079
279,988
349,348
181,914
161,467
84,891
119,995
Lantai
518,307
235,432
124,685
89,041
276,122
Utilitas
575,352
182,627
128,821
254,395
100,963
5,035,164
2,992,831
2,020,383
2,652,692
2,126,513
151,055
89,785
60,611
79,581
63,796
75,527
44,893
30,306
39,791
31,897
503,516
299,283
202,038
265,269
212,651
730,099
433,961
292,955
384,641
308,344
5,765,263
3,426,792
2,313,338
3,037,333
2,434,857
PPN 10%
576,526
342,679
231,334
303,733
243,486
6,341,789
3,769,471
2,544,672
3,341,066
2,678,343
PEMBULATAN
6,342,000
3,769,000
2,545,000
3,341,000
2,678,000
: JAWA TIMUR
KOTA
:
MALANG
ELEMEN BANGUNAN
RUMAH
GEDUNG
BERTINGKAT
MENENGAH
MEWAH
MENENGAH
SEDERHANA
Spek 2 (dua)
lantai
Rp. / m
Rp. / m
Rp. / m
Rp. / m
GUDANG
Rp. / m
A. BIAYA LANGSUNG
Pondasi
597,381
455,510
267,704
462,636
324,388
Struktur
1,194,764
911,021
535,407
925,274
648,775
Rangka Atap
199,127
151,836
89,235
154,212
108,129
Penutup Atap
231,555
200,177
159,523
124,222
156,631
Plafon
324,686
87,174
75,247
192,483
Dinding
747,778
389,387
345,619
181,709
256,849
320,477
166,880
148,123
77,875
110,078
Lantai
475,473
215,975
114,381
81,683
253,303
Utilitas
527,803
167,534
118,175
233,371
92,619
4,619,044
2,745,495
1,853,413
2,433,466
1,950,772
138,572
82,365
55,602
73,004
58,523
69,285
41,183
27,801
36,502
29,261
461,904
274,550
185,341
243,346
195,077
669,761
398,097
268,744
352,853
282,861
5,288,805
3,143,592
2,122,157
2,786,319
2,233,633
528,881
314,359
212,216
278,632
223,363
5,817,686
3,457,951
2,334,373
3,064,951
2,456,997
PEMBULATAN
5,818,000
3,458,000
2,334,000
3,065,000
2,457,000
Provinsi
Kota /
Kabupaten
: KOTA YOGYAKARTA
ELEMEN BANGUNAN
RUMAH
GEDUNG
BERTINGKAT
MENENGAH
MEWAH
MENENGAH
SEDERHANA
Spek 2 (dua)
lantai
Rp. / m
Rp. / m
Rp. / m
Rp. / m
GUDANG
Rp. / m
A. BIAYA LANGSUNG
Pondasi
593,477
452,533
265,954
459,612
322,267
Struktur
1,186,954
905,065
531,907
919,226
644,534
Rangka Atap
197,826
150,844
88,651
153,204
107,422
Penutup Atap
230,041
198,868
158,480
123,410
155,607
Plafon
322,564
86,605
74,755
191,225
Dinding
742,890
386,841
343,360
180,521
255,170
318,382
165,789
147,155
77,366
109,359
Lantai
472,365
214,563
113,633
81,149
251,647
Utilitas
524,353
166,439
117,403
231,846
92,014
4,588,851
2,727,548
1,841,297
2,417,559
1,938,020
137,666
81,826
55,238
72,527
58,141
68,832
40,914
27,620
36,264
29,070
458,885
272,755
184,129
241,756
193,802
665,383
395,495
266,988
350,546
281,013
5,254,234
3,123,043
2,108,285
2,768,106
2,219,033
525,423
312,304
210,829
276,811
221,903
5,779,657
3,435,347
2,319,114
3,044,916
2,440,936
PEMBULATAN
5,780,000
3,435,000
2,319,000
3,045,000
2,441,000
DAERAH ISTIMEWA
YOGYAKARTA
: KABUPATEN SLEMAN
:
Kabupaten
ELEMEN BANGUNAN
RUMAH
GEDUNG
BERTINGKAT
MENENGAH
MEWAH
MENENGAH
SEDERHANA
Spek 2 (dua)
lantai
Rp. / m
Rp. / m
Rp. / m
Rp. / m
GUDANG
Rp. / m
A. BIAYA LANGSUNG
Pondasi
565,929
431,527
253,609
438,279
307,308
Struktur
1,131,859
863,055
507,218
876,558
614,617
Rangka Atap
188,643
143,842
84,536
146,093
102,436
Penutup Atap
219,363
189,637
151,124
117,682
148,384
Plafon
307,591
82,585
71,285
182,349
Dinding
708,407
368,885
327,422
172,142
243,326
303,603
158,094
140,324
73,775
104,283
Lantai
450,439
204,604
108,359
77,382
239,966
Utilitas
500,014
158,714
111,953
221,084
87,743
4,375,850
2,600,943
1,755,830
2,305,343
1,848,063
131,276
78,028
52,674
69,161
55,442
65,637
39,015
26,338
34,580
27,721
437,585
260,095
175,583
230,534
184,806
634,498
377,137
254,595
334,275
267,969
5,010,348
2,978,081
2,010,425
2,639,618
2,116,032
501,035
297,808
201,042
263,962
211,603
5,511,383
3,275,889
2,211,467
2,903,580
2,327,635
PEMBULATAN
5,511,000
3,276,000
2,211,000
2,904,000
2,328,000
PPN 10%
: BALI
KOTA
:
DENPASAR
ELEMEN BANGUNAN
RUMAH
GEDUNG
BERTINGKAT
MENENGAH
MEWAH
MENENGAH
SEDERHANA
Spek 2 (dua)
lantai
Rp. / m
Rp. / m
Rp. / m
Rp. / m
GUDANG
Rp. / m
A. BIAYA LANGSUNG
Pondasi
700,187
533,901
313,774
542,253
380,213
Struktur
1,400,376
1,067,802
627,547
1,084,508
760,425
Rangka Atap
233,396
177,967
104,591
180,751
126,738
Penutup Atap
271,404
234,626
186,976
145,600
183,586
Plafon
380,562
102,177
88,196
225,609
Dinding
876,466
456,398
405,098
212,980
301,051
375,629
195,599
173,614
91,277
129,022
Lantai
557,299
253,143
134,065
95,740
296,895
Utilitas
618,635
196,366
138,512
273,533
108,559
5,413,954
3,217,978
2,172,374
2,852,251
2,286,488
162,419
96,539
65,171
85,568
68,595
81,209
48,270
32,586
42,784
34,297
541,395
321,798
217,237
285,225
228,648
785,023
466,607
314,994
413,577
331,540
6,198,978
3,684,586
2,487,368
3,265,828
2,618,029
619,898
368,459
248,737
326,583
261,803
6,818,875
4,053,044
2,736,105
3,592,411
2,879,831
PEMBULATAN
6,819,000
4,053,000
2,736,000
3,592,000
2,880,000
: BALI
KABUPATEN
:
BADUNG
ELEMEN BANGUNAN
RUMAH
GEDUNG
BERTINGKAT
MENENGAH
MEWAH
MENENGAH
SEDERHANA
Spek 2 (dua)
lantai
Rp. / m
Rp. / m
Rp. / m
Rp. / m
GUDANG
Rp. / m
A. BIAYA LANGSUNG
Pondasi
672,285
512,625
301,270
520,645
365,061
Struktur
1,344,571
1,025,250
602,540
1,041,290
730,123
Rangka Atap
224,095
170,875
100,423
173,548
121,687
Penutup Atap
260,589
225,276
179,525
139,798
176,270
Plafon
365,397
98,105
84,681
216,618
Dinding
841,539
438,210
388,955
204,493
289,054
360,660
187,805
166,695
87,639
123,881
Lantai
535,091
243,055
128,723
91,925
285,063
Utilitas
593,982
188,541
132,993
262,633
104,233
5,198,209
3,089,742
2,085,805
2,738,589
2,195,372
155,947
92,692
62,574
82,158
65,861
77,973
46,347
31,287
41,079
32,930
519,821
308,974
208,580
273,859
219,537
753,740
448,013
302,441
397,096
318,328
5,951,949
3,537,755
2,388,246
3,135,685
2,513,700
595,195
353,776
238,825
313,569
251,370
6,547,144
3,891,531
2,627,071
3,449,254
2,765,070
PEMBULATAN
6,547,000
3,892,000
2,627,000
3,449,000
2,765,000
: SULAWESI SELATAN
KABUPATEN TANA
:
TORAJA
ELEMEN BANGUNAN
RUMAH
GEDUNG
BERTINGKAT
MENENGAH
MEWAH
MENENGAH
SEDERHANA
Spek 2 (dua)
lantai
Rp. / m
Rp. / m
Rp. / m
Rp. / m
GUDANG
Rp. / m
A. BIAYA LANGSUNG
Pondasi
752,229
573,583
337,096
582,557
408,472
Struktur
1,504,460
1,147,167
674,190
1,165,115
816,945
Rangka Atap
250,743
191,194
112,365
194,186
136,157
Penutup Atap
291,576
252,065
200,873
156,422
197,231
Plafon
408,848
109,771
94,751
242,377
Dinding
941,610
490,320
435,207
228,810
323,427
403,548
210,137
186,518
98,061
138,612
Lantai
598,721
271,958
144,029
102,856
318,962
Utilitas
664,615
210,961
148,807
293,864
116,627
5,816,350
3,457,157
2,333,837
3,064,247
2,456,433
174,491
103,715
70,015
91,928
73,693
87,245
51,858
35,008
45,964
36,846
581,635
345,716
233,383
306,424
245,643
843,371
501,288
338,406
444,316
356,182
6,659,721
3,958,445
2,672,243
3,508,563
2,812,615
PPN 10%
665,972
395,845
267,224
350,856
281,262
7,325,693
4,354,290
2,939,467
3,859,420
3,093,877
PEMBULATAN
7,326,000
4,354,000
2,939,000
3,859,000
3,094,000
SULAWESI
SELATAN
KOTA
:
MAKASSAR
:
Kota /
Kabupaten
ELEMEN BANGUNAN
RUMAH
GEDUNG
BERTINGKAT
MENENGAH
MEWAH
MENENGAH
SEDERHANA
Spek 2 (dua)
lantai
Rp. / m
Rp. / m
Rp. / m
Rp. / m
GUDANG
Rp. / m
A. BIAYA LANGSUNG
Pondasi
603,629
460,274
270,504
467,475
327,780
Struktur
1,207,260
920,549
541,007
934,951
655,560
Rangka Atap
201,210
153,424
90,168
155,825
109,260
Penutup Atap
233,977
202,270
161,191
125,522
158,269
Plafon
328,082
88,086
76,034
194,496
Dinding
755,599
393,459
349,234
183,609
259,535
323,828
168,626
149,672
78,689
111,230
Lantai
480,446
218,234
115,577
82,537
255,952
Utilitas
533,323
169,287
119,411
235,812
93,588
4,667,354
2,774,209
1,872,797
2,458,917
1,971,175
140,021
83,226
56,183
73,768
59,135
70,010
41,614
28,092
36,884
29,567
466,735
277,421
187,279
245,892
197,117
676,766
402,261
271,555
356,543
285,820
5,344,120
3,176,470
2,144,352
2,815,461
2,256,994
534,412
317,647
214,435
281,546
225,699
5,878,532
3,494,117
2,358,787
3,097,007
2,482,694
PEMBULATAN
5,879,000
3,494,000
2,359,000
3,097,000
2,483,000
SULAWESI
SELATAN
KABUPATEN
:
MAROS
:
Kota /
Kabupaten
ELEMEN BANGUNAN
RUMAH
GEDUNG
BERTINGKAT
MENENGAH
MEWAH
MENENGAH
SEDERHANA
Spek 2 (dua)
lantai
Rp. / m
Rp. / m
Rp. / m
Rp. / m
GUDANG
Rp. / m
A. BIAYA LANGSUNG
Pondasi
630,112
480,467
282,371
487,984
342,161
Struktur
1,260,224
960,935
564,742
975,969
684,321
Rangka Atap
210,038
160,156
94,124
162,661
114,054
Penutup Atap
244,242
211,144
168,263
131,028
165,213
Plafon
342,475
91,951
79,369
203,029
Dinding
788,748
410,721
364,556
191,665
270,921
338,036
176,024
156,238
82,142
116,109
Lantai
501,524
227,808
120,648
86,158
267,181
Utilitas
556,721
176,714
124,650
246,158
97,694
4,872,120
2,895,919
1,954,961
2,566,795
2,057,654
146,164
86,877
58,648
77,004
61,730
73,081
43,439
29,325
38,502
30,864
487,212
289,592
195,496
256,679
205,765
706,457
419,909
283,469
372,186
298,359
5,578,577
3,315,828
2,238,429
2,938,981
2,356,013
557,858
331,583
223,843
293,898
235,601
6,136,435
3,647,411
2,462,272
3,232,879
2,591,615
PEMBULATAN
6,136,000
3,647,000
2,462,000
3,233,000
2,592,000
Provinsi
SULAWESI
UTARA
KOTA
:
MANADO
:
Kota /
Kabupaten
ELEMEN BANGUNAN
RUMAH
GEDUNG
BERTINGKAT
MENENGAH
MEWAH
MENENGAH
SEDERHANA
Spek 2 (dua)
lantai
Rp. / m
Rp. / m
Rp. / m
Rp. / m
GUDANG
Rp. / m
A. BIAYA LANGSUNG
Pondasi
721,984
550,521
323,542
559,134
392,049
Struktur
1,443,969
1,101,042
647,083
1,118,268
784,097
Rangka Atap
240,662
183,507
107,847
186,378
130,683
Penutup Atap
279,853
241,930
192,796
150,133
189,301
Plafon
392,409
105,357
90,942
232,632
Dinding
903,750
470,605
417,709
219,610
310,423
387,322
201,688
179,018
94,118
133,039
Lantai
574,648
261,023
138,238
98,720
306,137
Utilitas
637,893
202,479
142,824
282,048
111,938
5,582,489
3,318,153
2,239,999
2,941,041
2,357,666
167,475
99,544
67,199
88,232
70,730
83,737
49,773
33,600
44,116
35,365
Keuntungan Kontraktor
558,249
331,815
224,000
294,104
235,766
809,461
481,133
324,799
426,451
341,861
6,391,949
3,799,285
2,564,799
3,367,492
2,699,527
639,195
379,929
256,480
336,749
269,953
7,031,144
4,179,214
2,821,278
3,704,241
2,969,479
PEMBULATAN
7,031,000
4,179,000
2,821,000
3,704,000
2,969,000
Provinsi
Kota /
Kabupaten
: KOTA BITUNG
ELEMEN BANGUNAN
RUMAH
GEDUNG
BERTINGKAT
MENENGAH
MEWAH
MENENGAH
SEDERHANA
Spek 2 (dua)
lantai
Rp. / m
Rp. / m
Rp. / m
Rp. / m
GUDANG
Rp. / m
A. BIAYA LANGSUNG
Pondasi
672,569
512,842
301,398
520,865
365,215
Struktur
1,345,139
1,025,683
602,794
1,041,730
730,431
Rangka Atap
224,190
170,947
100,466
173,622
121,738
Penutup Atap
260,699
225,371
179,601
139,857
176,345
Plafon
365,551
98,146
84,717
216,710
Dinding
841,894
438,395
389,119
204,579
289,176
360,812
187,884
166,766
87,676
123,933
Lantai
535,317
243,158
128,777
91,963
285,184
Utilitas
594,233
188,621
133,049
262,744
104,277
5,200,405
3,091,047
2,086,686
2,739,746
2,196,299
156,012
92,731
62,600
82,193
65,889
78,006
46,366
31,301
41,096
32,944
520,040
309,105
208,668
273,974
219,630
754,058
448,202
302,569
397,264
318,463
5,954,463
3,539,250
2,389,255
3,137,010
2,514,762
595,446
353,925
238,926
313,701
251,476
6,549,909
3,893,175
2,628,181
3,450,711
2,766,238
PEMBULATAN
6,550,000
3,893,000
2,628,000
3,451,000
2,766,000
GEDUNG
BERTINGKAT
RUMAH
MENENGAH
MEWAH
MENENGAH
SEDERHANA
Spek 2 (dua)
lantai
GUDANG
Rp. / m
Rp. / m
Rp. / m
Rp. / m
Rp. / m
A. BIAYA LANGSUNG
Pondasi
662,771
505,371
297,007
513,277
359,895
Struktur
1,325,543
1,010,741
594,013
1,026,555
719,790
Rangka Atap
220,924
168,457
99,002
171,092
119,965
Penutup Atap
256,901
222,088
176,984
137,820
173,776
Plafon
360,226
96,717
83,483
213,553
Dinding
829,630
432,009
383,451
201,599
284,964
355,556
185,147
164,336
86,399
122,128
Lantai
527,518
239,616
126,901
90,624
281,029
Utilitas
585,577
185,873
131,111
258,916
102,758
5,124,647
3,046,018
2,056,288
2,699,834
2,164,304
153,740
91,380
61,688
80,995
64,929
76,869
45,691
30,845
40,498
32,464
512,465
304,602
205,629
269,983
216,430
743,074
441,673
298,161
391,476
313,824
5,867,720
3,487,691
2,354,449
3,091,311
2,478,128
586,772
348,769
235,445
309,131
247,813
6,454,492
3,836,460
2,589,894
3,400,442
2,725,941
PEMBULATAN
6,454,000
3,836,000
2,590,000
3,400,000
2,726,000
: SULAWESI UTARA
KABUPATEN MINAHASA
:
SELATAN
ELEMEN BANGUNAN
RUMAH
GEDUNG
BERTINGKAT
MENENGAH
MEWAH
MENENGAH
SEDERHANA
Spek 2 (dua)
lantai
Rp. / m
Rp. / m
Rp. / m
Rp. / m
GUDANG
Rp. / m
A. BIAYA LANGSUNG
Pondasi
712,754
543,483
319,406
551,986
387,037
Struktur
1,425,509
1,086,966
638,810
1,103,972
774,073
Rangka Atap
237,585
181,161
106,469
183,995
129,012
Penutup Atap
276,275
238,837
190,331
148,213
186,881
Plafon
387,393
104,010
89,779
229,658
Dinding
892,196
464,589
412,369
216,802
306,454
382,371
199,110
176,730
92,915
131,338
Lantai
567,301
257,687
136,471
97,458
302,223
Utilitas
629,738
199,890
140,998
278,442
110,507
5,511,122
3,275,734
2,211,363
2,903,443
2,327,525
165,334
98,272
66,340
87,104
69,826
82,666
49,136
33,171
43,552
34,912
Keuntungan Kontraktor
551,112
327,574
221,136
290,344
232,752
799,113
474,982
320,647
421,000
337,491
6,310,235
3,750,715
2,532,010
3,324,442
2,665,016
631,023
375,072
253,201
332,444
266,502
6,941,258
4,125,787
2,785,211
3,656,887
2,931,518
PEMBULATAN
6,941,000
4,126,000
2,785,000
3,657,000
2,932,000
Provinsi
Kota /
Kabupaten
ELEMEN BANGUNAN
RUMAH
GEDUNG
BERTINGKAT
MENENGAH
MEWAH
MENENGAH
SEDERHANA
Spek 2 (dua)
lantai
Rp. / m
Rp. / m
Rp. / m
Rp. / m
GUDANG
Rp. / m
A. BIAYA LANGSUNG
Pondasi
729,794
556,476
327,042
565,182
396,289
Struktur
1,459,588
1,112,952
654,082
1,130,365
792,579
Rangka Atap
243,265
185,492
109,014
188,394
132,096
Penutup Atap
282,880
244,547
194,882
151,757
191,349
Plafon
396,654
106,497
91,925
235,148
Dinding
913,526
475,696
422,227
221,985
313,780
391,512
203,870
180,955
95,136
134,478
Lantai
580,864
263,847
139,734
99,788
309,448
Utilitas
644,793
204,669
144,369
285,099
113,149
5,642,875
3,354,046
2,264,230
2,972,855
2,383,169
169,287
100,621
67,926
89,186
71,495
84,643
50,311
33,964
44,593
35,747
564,287
335,405
226,423
297,285
238,316
818,217
486,337
328,313
431,064
345,559
6,461,092
3,840,383
2,592,542
3,403,919
2,728,728
646,109
384,038
259,254
340,392
272,873
7,107,201
4,224,421
2,851,797
3,744,311
3,001,601
PEMBULATAN
7,107,000
4,224,000
2,852,000
3,744,000
3,002,000
Umur Ekonomis
1.
Umur ekonomis ialah : Suatu periode waktu dimana aset (bangunan) diharapkan dapat digunakan/dimanfaatkan secara ekonomis
sesuai fungsinya.
2.
3.