SAB1023
KURSUS
(COURSE)
UKUR KEJURUTERAAN
(ENGINEERING SURVEY)
PROGRAM
(PROGRAMME)
SAW
MASA
(DURATION)
2 JAM
(2 HOURS)
TARIKH
(DATE)
APRIL 2009
2.
Amaran!
Pelajar-pelajar yang didapati meniru semasa peperiksaan, boleh
dikenakan tindakan tatatertib dan Fakulti boleh mencadangkan supaya
di buang pengajian.
SAB 1023
-1Q1.
(a)
(b)
Table Q1(a)
Staff Readings
Level Position
1.283
0.860
1.612
1.219
(c)
If the level was then used to determine the reduced level of a TBM,
determine the corrected staff readings and the reduced level of the
TBM based on the data given in Table Q1(b). Unequal sight distances
were unavoidable and assume that accuracy check is not required.
Table Q1(b)
Backsight (BS)
Foresight (FS)
1.428
1.119
Distance (m)
45(BS)
2.214
3.387
35(BS)
Remarks
BM (23.478)
20(FS)
CP
45(FS)
TBM
(8 marks)
SAB 1023
-2Q2.
(a)
(b)
(13 marks)
(c)
Figure Q2
(c)
SAB 1023
-3Q3.
(a)
(b)
i.
ii.
Table Q3
Instrument Station:P
Instrument Height :1.44 m
Horiz. Angle
Vert. Angle
'
"
"
'
340
356
15
33
52
70
82
89
45
29
42
24
10
58
42
47
37
10
43
48
54
56
45
28
92
91
93
94
93
95
96
97
35
9
12
35
24
5
5
21
40
8
55
6
42
44
3
15
Height of
prism/reflector
1.65
1.65
1.65
1.33
1.82
1.58
1.58
1.58
Slope
Distance
32.837
33.282
32.388
32.251
33.564
43.150
51.403
55.899
Remarks
Centreline Point 1
Centreline Point 2
Centreline Point 3
Centreline Point 4
Centreline Point 5
Centreline Point 6
Centreline Point 7
Centreline Point 8
SAB 1023
-4Q4.
(a)
(b)
As the site engineer for a housing project, you were asked to set-out
the centreline of a circular curve that connects two straights within the
housing area. If the data is as follows:-
Degree of a curve
= 30o
Chord interval
= 10 meter
= 3221.62 m
Coordinate of stations :
a
1304.345 N , 4987.562 E
1983.703 N , 5496.254 E
1876.497 N , 6003.650 E
1891.566 N , 6026.224 E
Calculate:i)
ii)
Intersection angle.
(5 marks)
iii)
SAB 1023
-5Q5.
(a)
(b)
C:
ii)
(20 marks)
SAB 1023
-6Q6.
((a)
(b)
1 cm = 25 m
Vertical scale:
1 cm = 200 m3
i.)
Haul
ii.)
Overhaul
iii.)
(20 marks)
TABLE Q6
Chainage
Cut Volume
Fill Volume
0
0
50
270
100
750
150
2010
200
580
250
140
300
325
400
450
500
550
600
650
36
73
373
582
664
627
373
118