Вы находитесь на странице: 1из 6

Empowering Maintenance & Reliability Decision Makers

Estimating Failure Parameters


Mick Drew ARMS Reliability Engineers

How important is it to use Failure Parameters in Reliability Analysis and RAMS for
major projects?

Answer: There are different types of Failure Parameters that can be used. There are failure parameters that
are used to assess the reliability of a component or system, and there are failure parameters used to predict
reliability of components or systems.

Assessment: One of the most common parameters used to assess reliability is MTBF. Comparing the MTBF is an
indicator of the time between failures and can also be used to calculate system Availability.
The Mean Time Between Failures is calculated by:- Total Operating hours/No of Failures
The MTBF can be used at equipment level or at System level. The inverse of the MTBF is the Failure rate. For
new projects failure rates can be determined from existing plant, similar plant or there may be published data
availability from various industry bodies. OREDA is often referred to for offshore oil industry, and the GADS
database for more than 6,500 electric generating units. Other published data is available from Reliability Analysis
Centre such as the NPRD handbook for non electronic parts.
Of course the best data is from your own plant or similar plant. In the following I describe the analysis of failure
data for four cases.

2009 ARMS Reliability Engineers

Empowering Maintenance & Reliability Decision Makers

Case 1
Up

Down
15

30

45

60

In case a system has four failures over the first 70 days of operation. The timeline is shown above. From the
event log the following data is assembled and the MTBF is calculated from 44 operating days divided by 4
failures gives an mtbf of 11 days. Similarly the MTTR the plant is 6.5 days.

In service

TTF

Perform
Maintenance

Duration

11

10

21

26

12

38

45

15

60

10

Total

44

26

Mean

11

6.5

A maintenance analysis finds the first failure was due to severe aging mechanism, whereby it was decided to
perform a PM task every 15 days.
The resulting timeline is shown in (Case 2) and the timeline shows the first failure eliminated.

2009 ARMS Reliability Engineers

Empowering Maintenance & Reliability Decision Makers

Case 2
Up

Down
15

30

45

60

In this case the MTBF has increased from 11 days to 18 days. A dramatic improvement. Or is it?
When we include the planned outages in the calculation as shown in Case 3, the Mean Time Between Outages
has reduced to only 6.7 days. So whilst the failures have reduced the downtime has actually increased.

Case 3

Up

Mtbo=47/7=6.7days

Down
15

In
service

30

45

Perform
Maintenance

TTF

60

75

Duration

15

15

PM

17

21

Repair

26

30

PM

32

38

Repair

45

45

PM

47

13

60

10

Repair+PM

70

75

PM

Total

47

30

6.7

4.3

Mean

2009 ARMS Reliability Engineers

Empowering Maintenance & Reliability Decision Makers

Investigation work by the Engineering group finds a way to eliminate the Regular PMS and design out two of the
failures, but the repair time is now greatly increased. But the MTBF increases significantly to 18 days.

Case 4.
Up

Mtbf=36/2=18days

Down
15

30

45

60

In
service

TTF

Perform
Maintenance

Downtime

21

21

24

45

15

60

26

Total

36

50

Mean

18

25.0

75

2009 ARMS Reliability Engineers

Empowering Maintenance & Reliability Decision Makers

Discussion of Results
Comparison on the MTBF could indicate that the MTBF of case 4 means that Case 4 is the best case.

MTBF (Days)

Case 1

Case 2

Case 3

Case 4

11

16

6.7

18

This is clearly not the case if one was at all concerned about the amount of downtime.
In order to consider the downtime it is necessary to factor in the MTTR and calculate Availability for each case
which is shown below.

Availability = MTBF/(MTBF+MTTR)
Case 1

Case 2

Case 3

Case 4

MTBF

11

16

6.7

18

Failure Rate

0.09

0.06

0.15

0.06

MTTR

6.5

7.3

4.3

25

Availability

62.9%

68.6%

61.0%

41.9%

From this of course we see that Case 1 is actually better than Case 3 and Case 4 and Case 2 is invalid because the
planned downtime was not taken into account.

Conclusions

If you are concerned about number of unplanned outages- MTBF can be used as a guide.
If you are concerned about number of outages- MTBO can be used as a guide.
If you are concerned about minimising Downtime then Availability can be used as a guide.
It is very important to consider both planned and unplanned outages when assessing and comparing
systems.
The use of a fixed time maintenance regime without consideration of operating time is far too
conservative.
Major projects may start off with maintenance outage data from vendors but the actual outage times
must be determined through maintainability studies that take into account logistics delays, sparing
levels, diagnostic times.
What about Predicting performance? For the answer to that question we need to go to Reliability
Parameters.

2009 ARMS Reliability Engineers

Empowering Maintenance & Reliability Decision Makers

2009 ARMS Reliability Engineers

Вам также может понравиться