Вы находитесь на странице: 1из 21

Monthly Lookahead Plan for 400 KV Switchyard (Package Owner - Mr.

MLN Reddy) for the Mo


Sub Package : 400KV SWITCHYARD
Sr. No.

Key Activity

TOWER STR. ERECTION

Tower Type 4TA

II

Tower Type 4TB

III

Tower Type 4TC

IV

Tower Type 4TD

Tower Type 4TE

GANTRY STR. ERECTION

Gantry Type 4GA

II

Gantry Type 4GB

III

Gantry Type 4GC

EQUIPMENT STR. ERECTION

LA

II

CVT

III

WT

IV

BPI

ISOLATOR (42 SET,1 Set=6 No.)

VI

CB (12 SET,1Set=3 No.)

VII

CT

VII

KIOSK

EQUIPMENT ERECTION

LA

II

CVT

III

WT

IV

BPI

ISOLATOR (42 SET,1 set=3 No.)

VI

CB (12 SET,1 set=3 No.)

VII

CT

VII

KIOSK

VIII

ERECTION OF CR PANEL

STRINGING WORK

STRINGING OF MAIN BUS - A

II

STRINGING OF MAIN BUS - B

III

STRINGING OF AUX. BUS - A

IV

STRINGING OF AUX. BUS - B

STRINGING(Betn 4TA & 4TE Tower) 27 mtr


span(GT-1 BAY)

VI

STRINGING(Betn 4TA & 4TE Tower) 27 mtr


span(ST-1 Bay)

VII

STRINGING(Betn 4TA & 4TD Tower) 27 mtr


span(LINE-1 BAY)

VIII

STRINGING(Betn 4TA & 4TD Tower) 27 mtr


span(LINE-2 BAY)

IX

STRINGING(Betn 4TA & 4TE Tower) 27 mtr


span(GT-2 BAY)

STRINGING(Betn 4TA & 4TE Tower) 27 mtr


span(ST-2 Bay)

XI

STRINGING(Betn 4TA & 4TD Tower) 27 mtr


span(LINE-3 BAY)

XII

STRINGING(Betn 4TA & 4TD Tower) 27 mtr


span(LINE-4 BAY)

XIII

STRINGING(Betn 4TD & 4TE Tower) 86 mtr


span(ST-1 Bay)

XIV

STRINGING(Betn 4TC & 4TE Tower) 86 mtr


span(GT-1 Bay)

XV

STRINGING(Betn 4TC & 4TE Tower) 86 mtr


span(GT-2 Bay)

XVI

All JUMPERING WORKS

XVII

4" IPS AL. TUBE WORK

ERECTION WORK AT CONTROL


ROOM

ERECTION OF 220 V BATTERY

II

ERECTION OF 48 V BATTERY

III

ERECTION OF 220 V BATTERY CHARGER

IV

ERECTION OF 48 V BATTERY CHARGER

ERECTION OF 1000 KVA TRAFO

VI

ERECTION OF PMCC

VII

ERECTION OF BUS DUCT

VIII

ERECTION DCDB, LDB

ERECTION OF CABLE TRAY


SUPPORT & CABLE TRAY

SEC : 1 - 1 (600 :_____MTR)

II

SEC : 2 - 2 (600 :_____MTR.

III

SEC : 3 - 3 (600 :_____MTR.)

IV

SEC : 4 - 4 ( 150 & 300: MTR)

CONTROL ROOM BULIDING

EARTHING WORKS (Entire


switchyard)

Main Grid, Earthing at 400 KV S/Y

II

Auxiliary Grid, Earthing at 400 KV S/Y

IV

Raiser, For Tower & Equipment Structure at


400 KV S/Y

Equipment Earthing at 400 KV S/Y with GI


Flat.

III

Auxilary Earth Mat

VIII

Non Treated Earth Pit

IX

Non Treated Earth Pit for LA CVT & C/R LP

Shield wire

CABLE LAYING

CONTROL

II

POWER CABLE LAYING

10

TERMINATION

a.

Bay-401 (GT-1 )

b.

Bay-402 (Tie b/w GT-1 & ST-1)

c.

Bay-403 (ST-1 )

d.

Bay-404 (Line-1 )

e.

Bay-405(Tie b/w Line-1 & Line-2)

f.

Bay-406(Line-2 )

g.

Bay-407(GT-2)

h.

Bay-408 (Tie b/w GT-2 & ST-2)

Bay-409 (ST-2 )

j.

Bay-410(Line-3)

k.

Bay-411(Tie b/w Line-3& Line-4)

l.

Bay-412 (Line-4)

11
a.

SITE EQUIPMENT TESTING


Bay-401 (GT-1 )

b.

Bay-402 (Tie b/w GT-1 & ST-1)

c.

Bay-403 (ST-1 )

d.

Bay-404 (Line-1 )

e.

Bay-405(Tie b/w Line-1 & Line-2)

f.

Bay-406(Line-2 )

g.

Bay-407(GT-2)

h.

Bay-408 (Tie b/w GT-2 & ST-2)

i.

Bay-409 (ST-2 )

j.

Bay-410 (Line-3)

k.

Bay-411(Tie b/w Line-3& Line-4)

l.

Bay-412 (Line-4)

12

PRECOMMISSIONING

13

INSPECTION BY CEI

14

COMMISSIONING & CHARGING

L & T POWER

ahead Plan for 400 KV Switchyard (Package Owner - Mr. MLN Reddy) for the Month of FEB'2013
Sub Package : 400KV SWITCHYARD
UOM

Scope

Cumulative
Planned till
31th JAN'2013

Cumulative
Achieved till
31th JAN
-2013

Target for Achieved


FEB'2013 FEB'2013

Week 1
(1 - 3th Feb)
P

Week 2
(4 - 10th Feb)
P

Week 3
(11- 17th FEb)
P

Nos

69

68

67

Nos

26

26

26

TARGET COMPLETED

Nos

15

15

15

TARGET COMPLETED

Nos

Nos

12

11

11

Week 4
(18 - 24th Feb)
P

TARGET COMPLETED

Nos

Nos

48

47

45

Nos

10

Nos

32

32

32

Nos

Nos

598

577

577

Nos

24

15

15

Nos

34

34

34

TARGET COMPLETED

1
TARGET COMPLETED

Nos

12

NOT STARTED & CRITICAL for CHARGING

Nos

176

176

176

TARGET COMPLETED

Nos

252

252

252

TARGET COMPLETED

SET

36

36

36

TARGET COMPLETED

Nos

60

60

60

TARGET COMPLETED

TARGET COMPLETED

SET

Nos

472

451

451

Nos

24

15

15

Nos

34

34

34

TARGET COMPLETED

Nos

12

NOT STARTED & CRITICAL for CHARGING

Nos

176

176

176

TARGET COMPLETED

Nos

126

126

126

TARGET COMPLETED

Nos

36

36

36

TARGET COMPLETED

Nos

60

60

60

TARGET COMPLETED

SET

TARGET COMPLETED

All CRP panel erected except metering panel.


Metering panel is not available in site.
12267.6

12927.6

12497.6

Mtrs

3194.4

3194.4

3194.4

TARGET COMPLETED

Mtrs

3194.4

3194.4

3194.4

TARGET COMPLETED

Mtrs

2380.8

2380.8

2380.8

TARGET COMPLETED

Mtrs

1194.0

1194

1194

TARGET COMPLETED

Mtrs

102.0

102

102

TARGET COMPLETED

Mtrs

102.0

102

102

TARGET COMPLETED

Mtrs

204.0

204

204

TARGET COMPLETED

Mtrs

204.0

204

204

COMPLETED

MTRS

TARGET COMPLETED

COMPLETE
Mtrs

102.0

102

102

TARGET COMPLETED

Mtrs

102.0

102

102

TARGET COMPLETED

Mtrs

204.0

204

204

TARGET COMPLETED

Mtrs

204.0

204

204

TARGET COMPLETED

Mtrs

420.0

420

420

TARGET COMPLETED

Mtrs

660.0

660.0

660.0

TARGET COMPLETED

Mtrs

660.0

660.0

230

Mtr

LS

Mtrs

3370

3370

3168

16

14

12

Set

TARGET COMPLETED

Set

TARGET COMPLETED

Nos

TARGET COMPLETED

Nos

TARGET COMPLETED

Nos

TARGET COMPLETED

Set

TARGET COMPLETED

Set

NSPBD material is not available in site.

Nos

TARGET COMPLETED

Mtr

3642

3642

3642

Mtr

200

200

200

TARGET COMPLETED

Mtr

628

628

628

TARGET COMPLETED

Mtr

2514

2514

2514

TARGET COMPLETED

Mtr

160

160

160

TARGET COMPLETED

Mtr

140

140

140

TARGET COMPLETED

MTRS

29250

29250

28799

Mtr

9150
13250

12815

Mtr

4100

Mtr

7350

7350

7350

Mtr

8650

8650

8634

Nos

258

258

258

Nos

73

73

67

Nos

64

64

56

mtrs

5400

5400

4584

MTRS

104789

104789

81228

Mtr

75469

75469

51985

Mtr

29320

29320

29243

435

218

218

218

TARGET COMPLETED
16

16

0
TARGET COMPLETED

Work Completed
Work Completed
Work Completed
Work Completed
Work Completed
Work Completed
Work Completed

Work Completed

Work Completed

Work Completed

Work Completed

Work Completed

Testing Completed

Testing Completed
Testing Completed
Testing Completed
Testing Completed
Testing Completed
Only 2 set ISO tested below Main - Buses & Other Equipment Testing Not started

Only 2 set ISO tested Below Main - Buses & Other Equipment Testing Not started
Only 2 set ISO tested Below Main - Buses & Other Equipment Testing Not started

Only 2 set ISO tested Below Main - Buses & Other Equipment Testing Not started

Work in Progress

L & T (PT & D)

DB POWER LIMITED

2013
Week 4
(18 - 24th Feb)
A

or CHARGING

Week 5
(25 - 28th Feb)
P

Remarks / Compliances

Tower erection is pending due to nonavailability of CIVIL front in transformeryard. Still foundation is not ready.

Related tower erection pending due to the reason


mentioned above.

Gantry erection is pending due to nonavailability of front in transformer-yard

Front not available for unit 2


Material not available at site

Front not available for unit 2

or CHARGING

metering panel.
able in site.

PANEL IS NOT DELIVERED DUE TO SOME


COMMERCIAL ISSUE BETWEEN DBPL &
LNT POWER.

Related Equipment is not erected for jumpring

1. The above balance Al tube work for Line-1, Line-2 ,Liine -3 &, Line
-4 is pending due to WAVE TRAP.

able in site.

pending flat earthing will be completed after


wave trap erection.
target achived.

work is pending ,due to non-availability of


front in trasformer yard .
switchyard control cable laying is completed only
23.5 km control cable laying is pendind in
between switchyard to Xmer yard & TG Building

Target achieved .
Target achieved .
Target achieved .
Target achieved .
Target achieved .
Target achieved .

Target achieved .

Target achieved .
Target achieved .

Target achieved .

Target achieved .

PRIORITY BAY
IN AC-Kiosk 3 - Relay testing completed in
all the CR Panel. Relay Testing is in Bay
Control Unit Relay has completed Periferal
Unit Relay testing has completed .

PRIORITY BAY
IN AC-Kiosk 3 - Relay testing completed in
all the CR Panel. Relay Testing is in Bay
Control Unit Relay has completed Periferal
Unit Relay testing has completed .
PRIORITY BAY
IN AC-Kiosk 1 - Relay testing completed in
all the CR Panel. Relay Testing is in Bay
Control Unit Relay has completed Periferal
Unit Relay testing has completed .

Unit 2 all related testing will be start


from 2nd week of FEB

Unit 2 all related testing will be start


from 2nd week of FEB

Вам также может понравиться