Академический Документы
Профессиональный Документы
Культура Документы
Title
Management
Process
Number
5020
Written by
Approved by
Issue Number
Issue Date
Chris Clifford
Tim Lansdell
L
25/11/2013
1. The following is detailed guidance applicable to each stage refer to Process map O 9180.
1. Requests for product change via this process are only considered when submitted via the *Tracker process, the CQT
or by limited verbal communication and also have minimal design planned undertakings, all other product changes
will be required to pass through the controls of the NP&SI process (SM 3005) and will be deemed a **project.
* Tracker is a tool within engineerings Teamcentre management software which enables the registering of requests for product change.
**A project intends to yield a very specific set of results through a documented and ordered set of time sensitive activities and actions that are dependent on
many associated elements of design/development.
Individuals within Quality, Manufacturing, Purchase and Engineering have been trained on how to log tracker
requests. Individuals who have not been trained should seek the assistance of a trained person if they wish to
request a product change.
2.
3. Accepted requests are allocated to the engineering resource that will complete the work. Trackers relating to a CQT
issue may have problem solving tools initiated and managed as part of the change procedure. Appropriate
verification activity will also be identified and planned.
Each ECR / ECO will be subject to a review against the Matrix attached in Appendix A by engineering before
release. Cross functional or supplier involvement within the ECO design or Risk Assessment process will be
arranged by engineering as appropriate. FMEAs must be linked as an attachment to the ORACLE ECO.
Representatives from Warrantee, CQT, Manufacturing and Service must be consulted when allocating an ECO
grade as below. Quotations for external supply to be established when possible before implementation on Oracle.
1 Of 4
eng_5020_ecr_eco_process_iss L.docx
Textron Ipswich
Title
Management
Process
Number
5020
Written by
Approved by
Issue Number
Issue Date
Chris Clifford
Tim Lansdell
L
25/11/2013
4. The completed ECO is issued to the Programme Manager and the Implementation team who have responsibility for
the effective implementation and validation of the change. The Implementation team consists of representatives
from.
a.
b.
c.
d.
e.
f.
g.
Quality
Engineering
Manufacturing
Finance
Service parts
Supply
Service
Each of the above functions must be represented at each meeting. The functional head of that person must be
responsible for deputising.
The programme manager works with the team to compile an implementation plan appropriate to the ECO grade for each ECO, this is
normally in the form of the standard plan shown against each ECO in the managed list. The team to meet weekly to progress each ECO.
Grade 1. All parts in Company inventory plus all machines in dealers stock and with customers SLT to determine if shipments should
be held until rectification work has been completed, with the exception of Safety related issues which should be immediate.
Grade 2. All parts on production line and in spares stock. Also any machines in the Warehouse reworked - SLT to determine if shipments
should be held until rectification work has been completed, with the exception of Safety related issues which should be immediate.
The machine serial number at the point of introduction must be recorded, unless an unspecialised accessory.
Grade 3. Introduces new parts, includes instruction to modify or scrap stock. Machine serial no. at the point of introduction is required.
Grade 4. Introduces no new parts, does not involve scrapping or modifying parts, makes no changes to purchased parts, and does not
affect safety or warranty. For Grade 4 ECOs the effectively date is immediate.
NOTE: Consideration and guidance must be given on how to action stock at Jacobsen Charlotte.
2 Of 4
eng_5020_ecr_eco_process_iss L.docx
Textron Ipswich
Title
Number
Management
Process
5020
Written by
Approved by
Issue Number
Issue Date
Chris Clifford
Tim Lansdell
L
25/11/2013
Risk
Assessment
Not required
Prototype
Specification
Not required
Designers
Discretion
Not required
Certificate of
Conformity
Use existing
Technical File
Update
Not required
Designers
discretion
Not required
Not required
Not required
Use existing
Not required
Designers
Discretion
Not required
Not required
Not required
Not required
Use existing
Not required
Yes Manager
to sign off
Yes
Yes
Not required
Test to relevant
standards
Record results
Yes
Yes
Designers
Discretion
3 Of 4
Review impact
Change to be
of change to
detailed, test
noise levels &
reports filed.
required
amendment or
issue of new
Compliance
Certificate.
Supplier
Use existing
Change to be
approval
unless change
detailed, test
Results in Tech impacts on
reports filed.
File
noise level.
eng_5020_ecr_eco_process_iss L.docx
Description of Change
Hydraulic Pump, Motor,
Valve, Filter or Cooler
change.
CQT related change
Development of Customer
option
Non Standard Product Form
Engine option, changes to
cutting config. Intro of ROPS
or Cab
Serial Prefix Change
Textron Ipswich
Title
Management
Process
Risk
Assessment
Yes Manager
to sign off
Prototype
Specification
Yes
Yes
Designers
Discretion
Yes Manager
to sign-off
Yes
Number
5020
Written by
Approved by
Issue Number
Issue Date
Chris Clifford
Tim Lansdell
L
25/11/2013
Certificate of
Conformity
As above
Technical File
Update
As above.
Designers
Discretion
Designers
discretion
Yes
As above
Yes
Designers
Discretion
Yes
Yes Manager
to sign-off
Yes
Yes
Yes
Marketing
approval
Sign-off against
spec
As above
New Cab or
Rops require
Certificates of
Incorporation
As above
Designers
Discretion
Designers
Discretion
No
No
No
No
No
New Certificate
4 Of 4
Change to be
detailed, test
reports filed.
As above.
eng_5020_ecr_eco_process_iss L.docx