Академический Документы
Профессиональный Документы
Культура Документы
TECHNICAL SPECIFICATIONS
This Section contains the references to the Standard Specifications and
supplementary information (Special Provisions) that describes the Works
to be
procured.
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX
Table of Contents
of
SPL
SPL
SPL
SPL
SPL
SPL
SPL
SPL
SPL
SPL
SPL
SPL
SPL
F5
F6
F7
F8
F9
F10
F11
F12
F13
F14
F15
F16
F17
IX
PART G
DRAINAGE AND SLOPE PROTECTION STRUCTURES...............170
ITEM 500 SP Pipe Culverts and Storm Drains.................................170
ITEM 501 SP Underdrains..................................................................172
ITEM 502 SP Inlet/Outlet Headwalls, Manhole, Inlets and Catch Basins 175
ITEM 504 SP Cleaning and Reconditioning Existing Drainage Structures 176
ITEM 505 SP Riprap and Grouted Riprap.........................................177
ITEM 506 SP Stone Masonry............................................................177
SPL G1 Slope Remediation Measures................................................178
SPL G2 Composite Turf Reinforcement Matting.................................182
SPL G3 Micropiling..............................................................................184
SPL G4 Ground Anchor......................................................................192
SPL G5 Soil Nailing............................................................................202
PART H
MISCELLANEOUS STRUCTURES.............................................210
ITEM 601 SP Sidewalk.......................................................................210
ITEM 602 SP Monuments, Markers and Guide Posts.......................210
ITEM 603 SP Guardrail......................................................................210
ITEM 612 SP Reflective Thermoplastic Stripping Materials (Solid Form). 211
SPL H1 Landscaping...........................................................................214
SPL H2 Seeding..................................................................................216
SPL H3 Street Lighting (Electrical Works)..........................................217
SPL H4
Contract Information Signs..................................................226
PART J
PROVISIONAL SUMS..................................................................229
SPL J1 Relocation of Affected Electric Power Utilities.......................229
SPL J2 Removal and Relocation of Existing Barangay Markers........229
SPL J3 Provisional Sum.......................................................................230
PART K
DAYWORKS..............................................................................231
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
SPL K1
IX
Dayworks...............................................................................231
APPENDIX A
SUPPLEMENTAL TESTING REQUIREMENTS
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 1
TECHNICAL SPECIFICATIONS
INTRODUCTION
Technical Specifications for this project are comprised of the
DPWH Standard Specifications and these Special Provisions and
Supplemental Specifications. The Supplemental Specifications are for
items not covered by the DPWH Standard Specifications while the
Special Provisions are specific clauses setting forth the conditions or
requirements applicable to this particular project.
The Technical Specifications consists of two (2) Sections:
SECTION I: - DPWH Standard Specifications for Public Works and
Highways, 2004 Edition: Volume II, Highways, Bridges and Airports,
including all Department Orders and Circulars.
SECTION II: - Special Provisions and Supplemental Specifications.
Special Provisions (SP) of this Project shall consist of modifications on
the
general
conditions or requirements of the DPWH Standard Specifications defined as
follows:
Modifications
of
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 2
SECTION I -
DPWH Standard Specifications for Public Works and
Highway, 2004 Edition: Volume II, Highways, Bridges and
Airports including all Department Orders and Circulars.
These standard specifications have not been included in these Technical
Specifications but can be obtained from the Republic of the Philippines
Department of Public Works and Highways.
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 3
SPECIAL PROVISIONS
Delete Part A FACILITIES
replace with the following:
PART A SP
FOR
THE
ENGINEER
in
its
entirety
and
A.1 SP
Requirements
A.1.1(a) SP
Temporary Facilities
Laboratory
Quarters Building)
for
the
Engineer (Field
and
Office,
The Contractor shall furnish and maintain one (1) combined field
office/laboratory testing facility and one (1) living quarters facility
while the permanent Engineers Facilities are being constructed.
The Contractor shall secure land to construct Temporary Facilities (office,
laborartory & living quarters) or may lease an existing structure(s)
meeting the approval of the Engineer and the following requirements:
Field Office and Laboratory
Floor space of not less than 168 square
meters Three (3) management offices
One (1) general staff office
area One (1) laboratory
area
Two (2) bathrooms
Living Quarters
Floor space of not less than 168 square
meters Kitchen/Dinning area
Living room area
Eight (8) bedrooms
Two (2) bathrooms with showers
The Contractor shall provide
electricity, telephone, internet, air
conditioning, potable water, and sanitary facilities for the Engineer and his
staff.
Temporary Facilities shall be sited no more than 10 Km from the project
area
and
shall
be sited no closer than 50 meters to a residence and/or school unless
approved
by
the
Engineer.
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 4
A.1.1(a-1) SP
and
securing
the
Environmental
Compliance
Certificate (when
applicable)
along
with
all
Government/local
permits,
licenses,
fees
required
to
construct
Engineers Facilities structures and related site features.
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 5
All structures shall be constructed meeting all Government and local building codes
and
requirements.
Engineers Facilities shall be fenced with at least3-m high inter-link wire with
necessary gates as approved by the Engineer.
Driveways, parking areas, sidewalk, curb and gutters shall be constructed
from Class A concrete. Disturbed areas within the fence line shall be
seeded.
Exterior lighting shall be furnished and installed around the Engineers
Facilities with a minimum of 10 lux (ft) candles
The Contractor shall provide
electricity, telephone, internet, air
conditioning, potable water, and sanitary facilities for the Engineer and staff.
In the absence of sufficient sewage disposal system, a septic tank shall
be constructed conforming to the details shown on the Drawings
and the requirements of the Department of Health for septic vaults
including drain outlets.
In the event that adequate municipal electric power is not available at the
location of the Engineers Facilities the Contractor shall furnish and
install
a
generator
cabable
of furnishing electrical power to the
Engineers Facilities at full load.
The Contractor shall furnish and install a backup generator of
sufficient capacity capable of furnishing electrical power to the Engineers
Facilities at full load.
The generator(s) shall be positioned remotely on the site
surrounded by
CMU block walls to minimize noise as approved by the Engineer.
The
of
IX - 6
2 - Utility person
4 - Security
Guard
4 - Laboratory Aides
1 - Utility person
For Quarters:
1 - Cook/Maid
2 - Laundry person
The Conractor is shall be responsible for making minor repairs to both
temporary and constructed
office/laborartory/quarters
space due to
normal use.
This Contractor shall be responsible for all monthly costs associated
with providing potable water, sanitary, electric, telephone and internet
services.
The Contractor shall provide adequate stock of all expendable items, such
as
laboratory
equipment accessories, light bulbs, light tubes, floor wax, brooms,
floor
mats,
insect
sprays, tissue paper and other building maintenance accessories and
supplies,
etc.,
at
all
times to ensure proper and continuous functioning of all the Engineers
Facilities.
The Contractor shall provide adequate firefighting equipment in
Engineers Facilities buildings meeting all Government and local fire safety
regulations.
The Contractor shall provide within forty five (45) days after receipt
of Notice to Proceed (NTP) a sufficient supply of all normal stationary
printing papers, laboratory and testing materials and consumable items, as
required and at the discretion of the Engineer. If the Contractor cannot
provide the articles as described or intends to supply unacceptable
substitutes, the Engineer may secure the specified articles from available
sources. The Contractor shall be duty bound to pay the expenses
incurred in the purchase of the articles or the Engineer shall have the right
to deduct the sums from any money due or which will become due to the
Contractor.
All testing and quality control works shall be done by the Contractors
Materials
Testing
and Laboratory Staff under the direct supervision of the Engineer. The
Contractor
shall
also provide qualified and experienced laboratory staff, to carry out all
materials
quality
control and all the tests specified in the Contract or as required by the
Engineer.
The
person so appointed by the Contractor to manage the laboratory
shall
be
well
experienced in the type of work to be undertaken and shall be subject to
the
approval
of
the Engineer.
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 7
Equipment and
Supplies
Furniture
UNIT
for
the
QTY.
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
Each
16
Set
Each
IX - 8
Set
Each 2
16
Each
Set3
Each 1
3
Set1
1
1
Set1
1
2
1
Publications (AASHTO)
1. Standard Specification for Transportation Material and
Method of Sampling and Testing Part I
Specification (Original)
2. Standard Specification for Transportation Materials and
Method of Sampling and Testing Part II (Original)
Each 1
Each 1
of
Furnitures,
Appliances
and
Supplies
for
Living Room
UNIT QTY.
1. Sofa chair, 730 x 900 x 2100 mm all padded with dark Each 2
brown synthetic leather upholstery
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 9
2. Lounge Chairs, 635 x 840 mm all padded with dark brown Each2
synthetic leather upholstery
3. Center Table, 430 x 584 x 1150 mm tanguile, non-gloss
Each2
varnish
1.
2.
3.
4.
5.
6.
7.
8. Kettles, Aluminum
Set
1
Each 10
1
1
1
1
1
2
Each
Each
Each
Each
Units
14
28
28
28
3
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 10
Office
Bond Paper, A4
UNIT
Ream
QTY.
50
2.
Bond Paper, A3
Ream
50
3.
Ream
20
4.
Pad
100
5.
Each
180
6.
Each
180
7.
Box
10
Box
10
9.
Each
20
Each
12
Each
60
Roll
100
Roll
60
Roll
60
Each
40
Box
30
Each
30
Each
200
Box
40
20. Fastener
Box
40
10
Each
20
Each
Each
12
Each
27. Puncher
Each
28. Scissors
Each
Set
Each
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
50
Office
31. Technical Pen (Pt. 0.8 to 1.0 & 1.2)
IX - 11
UNIT
Each
QTY.
40
Pair
12
Each
Each
Each
Box
Box
20
Bottle
10
Each
Each
60
Each
60
Each
20
Pad
50
Each
15
Each
20
Each
Each
30
Each
10
49. CD Rewritable
Each
150
Rolls
Each
25
Each
Each
Set
Each
60
15
6
8
Each
60
Other Consumables
52.
53.
54.
55.
Insect Spray
Heavy Duty Flashlights
Floor Mop (Set Handle with Mophead)
Broom
All un-used office supplies and related materials listed in Schedule E is the
property
of
the Contractor shall be returned to the Contractor upon completion of the
Project.
A.1.1(e) SP
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 12
UNIT QTY.
Each
Each
3. 2
Each
Each
5. 1
Each
6.
Each
7. "
Each
8. 3/8
Each
9. #4
Each
10. #8
Each
11. #10
Each
12. #12
Each
13. #16
Each
14. #20
Each
15. #30
Each
16. #40
Each
17. #50
Each
Each
Each
Each1
Each
Each
Each
Each
Each
Each
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 13
Each
Each 2
Each
Each
Bottl
e
10
Box
10
Bottl
e
Box
Bottl
e
Laboratory
31. Sodium Hydroxide Solution
32. Capping Compound
33. Sodium Sulfate
34. Calcium Carbide Reagent
35. Sand Equivalent Stock Solution
36. Color Standard Chart
Set
10
Gal
10
II
III
Each
1200
Atterberg Limits
31. Liquid Limit Set
Set
Set
Each1
Each
Each
Set
Each
38. Spatula
Each
Each
Each
Each
Each
Each
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IV
IX - 14
Each
Bottl
e
Each
Each
Each
Each
Each
Each
Each
Doze
n
Moisture Density
Each
Each
Each
Each
Each
Each
Each
Each
Each
Each
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
Each1
Set
reading
Irrigator
of
IX - 15
Measuring
graduated
cylinder Siphon assembly
Measuring tin 90ml, 60mm
dia.
Funnel
Bottle, 4 liter Enamel Tray, 345mm x 265mm x 60mm
68. Sieve 4.75 (No. 4)
Each
Reagents
VII
VIII
Each
Each
70. Glycerin
Each
71. Formaldehyde
Each
Set 1
Each6
Each
Each
12
Each
Each
Each
Each
Each
Each
Each
Each
Each
Each
Each
Each
Each
Each
Each
Each
Each
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX
XI
IX - 16
1
T
e
e
1
R
o
Each
1
Technical
Specifications: Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
1
1
1
1
1
1
1
1
1
10
1
1
16
4
2
1 (min.) or
as necessary
1 (min.) or
as necessary
1 (min.) or
IX - 17
as necessary
Each
115. *Data logger with humidity and temperature sensors for Each 3
initial cure
XII
XIII
Each1
Each
Each
Set
Each
Each
Each
Each
Each
Slump
119. Slump
Slump
120. Mixing
XIV
Miscellaneous Equipments
125. Laboratory Oven, Double Wall Gravity connection, 220 / 60 Each1
cy.
A.C. Cap 1 cu.m.
126. Hot Plate, 12 x 12, 220 volts
Each
Each
Set
each
The Contractor shall furnish and deliver to the Engineer cellular phone,
Nokia brand (open line) or its equivalent within forty five (45) days
from the notice to Proceed (NTP) and prior to Commencement of the
Works.
Technical
Specifications:
Rehabilitation/Construction
of
IX - 18
All expenses relative to the supply, delivery and use of cellular phones
shall be borne by the Contractor until the completion of the Contract.
All cell phones are the property of the Contractor and
returned to the Contractor at the completion of the Project.
A.1.2(a) SP
shall
be
The Contractor shall provide and maintain brand new 4 x 4 - 4 door Pick-
up Crew Cab Type, 4 cylinder with engine displacement of not less than 2500
cc, diesel powered, air- conditioned, 4-wheel drive or equivalent.
The Contractor shall provide comprehensive insurance for the
vehicles to cover accident, loss or damage of the vehicle, Third
Party Liability (TPL) coverage, duly registered and complying in all
aspects to other legal requirements. The documents evidencing
registration and insurance initially and succeeding years, as they
become due and renewable shall be handed over to the Engineer.
Vehicle(s) shall be delivered within forty five (45) days from the Notice
to Proceed (NTP) and prior to the commencement of the Works.
All vehicles shall be turned over to the Philippine Government and shall
become the property of the Philippine Government at the completion of
the Project. Vehicles shall be delivered to the DPWH Regional Office.
A.1.2(b) SP
A.1.3(a) SP
Assistance to the Engineer - Provision of Survey
Equipment, Schedule G
Add the following at the end of this Subsection:
The Contractor shall provide the following survey
exclusive use of the Engineer and his representatives.
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
equipment
of
for
the
IX - 19
The surveying instruments shall be brand new, of the latest design and
manufactured
by
a reputable manufacturer acceptable to the Engineer. The Contractor shall
submit
to
the
Engineer for approval the proposed manufacturer, type and models
with
parts
performance catalogues and manufacturers warranty prior to
purchase of the
instruments.
Schedule G - Provision of Survey Equipment
Electronic Total Station, complete set
(w/ tripod,
2 prism), 30X2Each
telescope magnification with 2x plug-in camcorder NIMH GEB
111, GKL 111 charger, RS232 interface cable for date
transfer, GDF 111 Tribrach, laser plummet incorporation
Automatic level complete with tripod 3x magnification, +/-0.80 mm 2Each
standard deviation, erect image telescope, 0.50 m
shortest focusing distance, with built-in compensator of less
than
0.3
setting
accuracy, fully waterproof and dust
resistant with a horizontal circle that can be in grads or
degrees and aluminum tripod.
Leveling rod (5 m. ht.) aluminum
Each
50 m Fiberglass tape
Each
5 m Carpenters Tape
Each
Survey Umbrellas
Each
Range Pole
Each
This item shall also include the required periodic maintenance of provided
survey
instruments.
The survey equipment listed in Schedule G shall be turned over to
the
Philippine
Government and shall become the property of the Philippine
Government
at
the
completion of the Project. Survey equipment shall be delivered to the
DPWH
Regional
Office.
A.1.3(b) SP
of
IX - 20
2 - Levelman
1 - CADD Operator
8 - Survey Aides
The Contractor shall provide his separate team to assist his own operation.
A.1.4 SP
Progress Photographs
Contractor
shall
apply also
and
miscellaneous items.
to
Bridges,
Culverts,
Protection
other
Works
5. The Engineer shall designate the points where the photographs are to be taken.
6. The before, during and after photographs shall be properly labeled and
arranged
in
a
page for ready comparison.
A.2 SP
Method of Measurement
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 21
Laboratory
and
Laboratory
and
Operate and Maintain Facilities for the Engineer (Field Office, Laboratory
and Quarters Building) shall be measured per Month.
Provision of Furniture, Fixtures, Office Equipment and Appliances for
the
Office,
Laboratory and Quarters for the Engineer, Schedules C and D shall be
measured
per
Month.
Provision of Office Supplies and Consumable Stores for the Engineer,
Schedule E shall be measured per Month.
Provide Laboratory Equipment and Apparatus, Schedule F
measured as a Lump Sum.
shall be
up
for
the
Engineer
Survey
Personnel
Provision
of
Survey
shall
be
Equipment
shall
be
Basis of Payment
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
Pay Item
Description
A.1.1(a) SP
(Field
IX - 22
Unit
of
Measurement
Month
Lump Sum
Month
A.1.1(b) SP
A.1.1(c) SP
A.1.1(d) SP
A.1.1(e) SP
A.1.1(f) SP
A.1.2(a) SP
A.1.2(b) SP
A.1.3(a) SP
of
A.1.3(b) SP
of
A.1.4 SP
Photographs
Month
Month
Lump Sum
Unit Month
Each
Vehicle Month
Lump Sum
Month
Month
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
PART B
IX - 23
SPECIAL PROVISIONS
B1 SP
B.1 SP
Contractors Facilities
B.1.1 SP
General
The Contractor shall provide and maintain at his own expense living
accommodation and amenities for all staff and labour employed by
him directly or indirectly in connection with the project, except for
those recruited from the immediate vicinity of the works. Each structure
for living accommodation shall be provided with lights, potable
water, efficient sanitation and refuse disposal system, cooking areas
and equipment, and appropriate furnishings. All living accommodation
shall be maintained in a clean and sanitary condition at all times.
B.1.3 SP
of
B.1.4 SP
IX - 24
All
structures
temporary
and/or
permanent
shall
Government and local building codes and/or requirements.
B.1.5 SP
meet
all
Storage of Materials
and
sloped
to
the
Working Areas
The Contractor shall select, arrange for and, if necessary, pay for use
of
sites
for
all
mixing plants for Portland cement concrete, for bituminous concrete, for
the
storage
of
equipment, materials for office buildings, or other uses necessary for the
execution
of
the Works.
B.1.8 SP
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 25
The Contractor shall locate plants and stock yard away from
residential
and environmentally sensitive areas. Provide adequate
pollution control devices, air filters, etc. and the equipment shall be
operated during daytime only.
Before any land belonging to the Government or to a private landowner
is used for any purpose in connection with the prosecution of the Works,
the Engineers approval shall be obtained.
B.1.10 SP
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 26
SUPPLEMENTAL SPECIFICATIONS
SPL B.5
4. If during construction of the Works, there should exist variations from the
data
contained in the Contract Documents, it shall be the Contractors
responsibility
to
forthwith notify the Engineer in writing of such variations, who in turn
shall
issue
also in writing appropriate instructions. Unless evidenced by a written
instruction,
the Employer will not entertain any claims by the Contractor
arising
from
such
variations.
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 27
SPL B.5.2.1
Removal,
and Site Facilities
Relocation
and
Inclusion
of
Public
Utilities
of
IX - 28
Approval of Materials
Notice of Operations
obtained
or
fabricated.
No element of the Permanent Works shall be undertaken without
the Engineers approval. Full and complete written notice shall be given
to the Engineer in advance of the operation early enough for the
Engineer to make such arrangements as he may deem necessary for
inspection of the work.
SPL B.5.2.6
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
SPL B.5.2.7
IX - 29
Standard of Workmanship
All workmanship shall meet the requirements of the Contract, and shall
be carried out to the satisfaction of the Engineer.
SPL B.5.2.8
The Contractor shall, at his own expense, carefully protect all work and
materials from damage by the weather.
SPL B.5.2.9
SPL B.5.2.10
Sufficient metal templates shall be supplied by the Contractor for his own
use
and
to
the
Engineer to check the finished surfaces of the pavement structures.
These
templates
shall be submitted to the Engineer for his approval. The templates used
to
control
the
work shall be maintained at all times in a condition to produce
the
correct
cross
sections, profile and shall be checked regularly and, if necessary, repaired
or adjusted.
The Contractor shall furnish sufficient straight edges, as may
specified by the Engineer, to check the surface of the pavement.
SPL B.5.2.11
be
Construction Procedures
Prior to the commencement of any work item the Contractor shall inform
the
Engineer
as to the starting date, work schedule and general procedures for this
operation.
The
Engineer shall, in turn, issue the necessary certification that permission is
granted
and
work can proceed as requested. Any variation in the sequence of work
as
proposed
in
the work programme required by the Conditions of Contract must be
called
to
the
attention of the Engineer. Contractor shall notify Engineer a minimum of
two
(2)
days
prior to any additional subsurface investigation or adjustment in design.
SPL B.5.2.12
At the
Statistical Report
end of
each month,
the
Contractor,
at no
additional
cost,
shall
furnish
the Engineer the following information in a form and
number of copies to be determined by the Engineer:
1. Physical Progress Reports for the month or period and estimated
progress
for
the
succeeding month or period.
2. Completion schedule (target/actual) based on approved construction programme.
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 30
Equipment
all
necessary
equipment
required,
failure
of
thereof
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 31
The Contractor shall be solely responsible for ensuring that the quality of
materials and workmanship is in accordance with the requirements of
this specification and the Contract Documents. The Contractor shall
carry out his own inspection of materials and workmanship and satisfy
himself that they meet the Specifications before submitting them to
the Engineer for acceptance of payment.
The Contractor shall prepare and submit to the Engineer within 30 days
of Notice to Proceed (NTP) a written Quality Assurance Management
System Manual in accordance with ISO 9000 series of standards which
shall include the following:
Project organization chart with roles, duties
responsibilities. Schedule
Equipment
selection
process
Local
staff
selection process Project
submittals
Project documentation
Manufactured
Materials
Quality
Control
Quality
Control
Plan/Procedures
Purchased materials Quality Control Plan
Procedures Field Inspections
Environmental
Conditions
Monitoring
Programmes Project produced (Manufactured
Materials)
and
This shall show the Contractors site organization with respect to quality
assurance
and
shall demonstrate the Contractors commitment to checking and
reporting
on
the
quality of materials and workmanship. It shall also show how the
system
will
be
extended to suppliers and sub-Contractors and how all elements of the
system
will
be
documented.
The Contractor shall, before placing any order for materials for incorporation in
the
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 32
Works, submit for the information of the Engineer names of the firms
from whom he proposes to obtain such materials. He shall give
descriptions, manufacturers specifications, quality, weight, strength and
origin of the materials, as applicable, and confirm the quantities to be
procured. The Contractor shall provide the Engineer with samples of
materials when requested, details of the suppliers quality assurance
system and, where appropriate, manufacturers certificates of recent
tests carried out on similar materials. In accordance with the Conditions
of the Contract the Engineer may require visits to the facilities of any
manufacturer or supplier.
The Contractor shall carry out trials of all concrete mixes,
bituminous mixes and mixtures of others materials to demonstrate
that,
not
only
are
the
constituents
in compliance with the
specifications, but that the resultant mixtures also comply. He shall show
as part of the Quality Assurance system the relationship between trials
and job mixes and his proposals for maintaining the quality of all mixes on
site.
SPL B.5.2.17
After
Engineer
of
IX - 33
for
SPL B.5.2.19
Record Documents
The Contractor shall maintain in a safe place at the site one record copy of
all Drawings, Specifications, Addenda, Written Amendments, Change
Orders, Work Directive Changes, Field
Orders
and
written
interpretations/clarifications and submittals/shop drawings in good order.
Upon completion of the Project, these record documents shall be
delivered to the Engineer.
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
SPL B.5.2.20
IX - 34
a)
borrow pits and quarries, whether pre-existing or opened-up
specifically
for
the
road contract;
b) other sites where spoil disposal will not result in a potential
safety
hazard,
instability, erosion, or water management problems.
Preference shall be given to the backfilling of borrow pits and quarries as
an aid to site restoration.
Local communities must give their consent before any spoil disposal
site
shall
be
permitted.
2.
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 35
load
slope
the
spoil disposal proposals if, in the Engineers
likely to cause environmental damage.
opinion,
they
are
a) marking the boundaries of the site with white paint so that the
perimeter
is
clearly visible;
b) erecting a sign at the entrance to the site with the words Road
Project
Disposal
Area;
c) carrying out appropriate and effective drainage works to the
satisfaction
of
the
Engineer;
d) constructing spoil retention structures around the perimeter as approved by
the
Engineer.
6. The Contractor should ensure that no drainage or concentrated runoff occurs
down
the face of any spoil disposal site.
7. Spoil shall be placed in shallow layers and compacted to 90% relative density
or as
otherwise directed by the Engineer.
8. The Contractor shall monitor the condition of each disposal site and shall
submit a
report to the Engineer at least monthly and after any precipitation
event exceeding 100mm in 24 hours to include:
a) volume of materials disposed at site;
b) any signs of movement or instability;
c) any movement of spoil beyond the perimeter of the site;
d) any erosion and sediment deposition caused by runoff from the site.
works
to prevent
10. When
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 36
The work associated with SPL B.5 Supplemental General Requirements shall
not be
measured and paid for separately and is considered subsidiary and included
in other
pay items in the Contract listed in the Bill of Quantities.
SPL B.6
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
SPL B.6.1
IX - 37
General Provisions
This section
shall
contain
the Employers Environmental
& Social
Management Plan to allow Bidders to understand what will be involved
in implementing the environmental and social mitigation measures
associated with the project. This is not to substitute for the Contractors
Environmental & Social Management Plan (CESMP) that the winning
Bidder will need to draft based on the Employers ESMP, any relevant
environmental Specifications found in the Technical Specifications, Bill of
Quantities, Drawings and relevant partner country laws and regulations.
The Contractor is required to prepare and submit a Contractors
Environmental and Social Management Plan (CESMP with operational
details for review and approval by the Engineer not later than 30 days
after the receipt of the Notice to Proceed.
The ESMP shall be organized in four sections as follows:
SPL B.6.2.1
Management Acknowledgements
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 38
highest
- All current environmental laws and regulations - be they national or local related but not necessarily limited to:
Noise;
Air pollution;
Water contamination;
Solid waste disposal;
Liquid waste disposal;
Sanitary conditions (water supply, sewerage, etc.);
Use of explosives; and
Protection of public traffic.
The Contractor shall restore areas citing temporary plants to their original
condition on completion of Project Works. This shall include the clean-
up of spillage and debris before leaving any temporary construction site.
c) Availability of Documents
The Plan shall state where copies of safety and industrial health
regulations and documents will be available on the construction site
and verify that all regulations and documents have been or will be
available and displayed or kept.
d) Management of Sub-Contractors
The Plan shall provide a commitment that the Contractor for the work shall:
Provide subcontractors with copies of the ESMP and the ECC
and incorporate provisions of the ESMP and ECC into all sub-contract
documentation to ensure the compliance with the Plan at all tiers of the
sub-contracting.
Require all subcontractors to appoint a safety representative who shall
be
available
on the Site throughout the operational period of the respective
subcontract;
and
Ensure, as far as is practically possible, that employees of
subcontractors
of
all
tiers
are conversant with appropriate parts of the ESMP, ECC and
the
statutory
regulations.
SPL B.6.2.2
Organization Chart.
The Plan shall include an organization chart identifying (by job title and
by
the
name
of
the individual) the personnel to be engaged solely for environmental
protection and
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 39
safety. The chart and the supporting text shall identify the designated
Environmental Manager and /Health and Safety Manager and identify
other participants and their areas of responsibility.
Identification of Responsibilities.
The Plan shall provide a description of the responsibilities of the
Environmental, Health and Safety staff appearing on the Organization
Chart.
Nomination
Safety
of
proposed
Manager. The
Environmental
Plan
shall
Manager
indicate
the
and
name
Health
of
&
theses
proposed personnel.
Certification related to the Environmental Manager and /Health & Safety
Manager. The Plan shall certify that:
- These managers will be appointed and assigned duties throughout the period
of
the Contract entirely connected with the environmental and safety
activities on the Site.
- The proposed managers shall be bilingual (Tagalog/English) and suitably
qualified and experienced to supervise and monitor compliance with
the
ESMP
and will, in particular but without limitation, carry out auditing of
the
operation
of the ESMP to be submitted, from time to time, to the Engineer for
his consent.
- These managers shall not be removed from the Site without the express,
prior
written permission of the Engineer. Within fourteen (14) days
of any such removal or notice of intent of removal, replacement
staff shall be nominated for the Engineers approval.
- These managers shall be provided with supporting staff in accordance with
the
staffing levels set out in the Plan.
- These managers will be empowered to instruct all employees of the
Contractor
or Subcontractors at any level to cease operations and take
urgent and appropriate action to make safe the Site and prevent
unsafe working practices or other infringements of the Plan or the
statutory regulations.
- These managers shall maintain a daily Site Diary in order to
comprehensively
record all relevant matters concerning Site environmental
management and safety, inspections and audits, related incidents
and the like. The Site Diary shall be available at all times for
inspection by the Engineer.
Contact Information.
Contact information for all Environmental and Health & Safety staff shall
be provided in the Plan.
SPL B.6.2.3
of
IX - 40
Provisions:
SPL B.6.3.1
of
IX - 41
areas
SPL B.6.3.3
The Contractor shall ensure that his activities do not result in any
contamination
of
land
or water by polluting substances. He shall implement physical and
operational
measures such as earth bunds of adequate capacity around fuel, oil and
solvent
storage
tanks and stores, oil and greases traps in drainage systems from
workshops,
vehicle
and
plant washing facilities and service and fuelling areas and kitchens, the
establishment of
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 42
any
Unless
The Contractor shall not use, or permit to be used, wood as fuel for the
execution of any part of the Works including, but not necessarily limited
to, the heating of bitumen and bitumen mixtures, and to the extent
practicable shall ensure that fuels other than wood are used for cooking,
space and water heating in all camps and living accommodations. Any
wood so used must be harvested legally, and the Contractor shall
provide the Engineer with copies of the relevant permits if required.
SPL B.6.3.6
Fire Prevention
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 43
In undertaking the Works, the Contractor shall be aware that the Engineer
may prohibit or
restrict
the
Contractors
activities
in
other
ecologically, culturally or historically sensitive areas which become
known to him during the course of the project. The location of any
such areas shall be notified to the Contractor by the Engineer at the
earliest opportunity.
SPL B.6.3.8
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 44
be
removed
or
given to local residents. All temporary structures including office building,
shelters
and
latrines shall be removed to prevent encroachment within the road right-
of-way.
The
site shall be restored to near natural or stable conditions, including any
access
roads
and infrastructure established for the camps. The Engineer shall report in
writing that
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 45
the camp has been vacated and restored to pre-project conditions before
acceptance of the works.
SPL B.6.3.14 Borrow Pits and Quarries
The Contractor shall make his own arrangements for the supply of
any necessary aggregates including compensation for landowners and
others, the acquisition of the Environmental Compliance Certificate and
any necessary permits from the competent authorities, access, and site
clearance and restoration, subject to the provisions of these Specifications
and the Conditions of Contract. No borrow pits or quarries will be
established in the Samar Island Natural Park or other protected areas.
In
making
his
of
IX - 46
Where the Contractor obtains his construction materials from borrow pits
and
quarries
operated by others, the Engineer reserves the right to disallow such
materials
where
the borrow pits or quarries in question are unlicensed or fall under 3 (i), (ii),
(iii)
or
(iv)
above.
The Contractor should note that all borrow pits, quarries, and associated
access
tracks
and stockpile areas shall be restored and re-vegetated, unless otherwise
directed
by
the
Engineer.
The Engineer may direct that materials be selected in borrow pits which
may include double handling, stockpiling and excavation in particular areas of
a borrow pit.
The
worked-out
borrow
pits
or
to
used
any
the
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 47
The Engineers approval of any spoil disposal site shall not in any
way relieve the Contractor of his responsibility, inter alia, for land
acquisition, provision of temporary access, works preparatory to spoiling,
management
of
the
spoiling
operation,
and making good after
completion of spoiling.
Where the alignment traverses side-long ground and spoil volumes are
low,
or where existing environmental damage is so great that the
additional impact from soil disposal would be insignificant, the Engineer
may permit limited side-casting. Permission will be granted in writing for
specific sections of roadway not exceeding 25 m in length. Where side-
casting is permitted, the volume of material side-cast shall be limited to the
surplus from the adjacent earthwork.
Unless exempted by the Engineer, in all locations where side-cast material
exceeds 250 mm average depth, the surface will be re-vegetated in
accordance with Clause B.3.5. The Engineer may direct that additional
vegetation and stabilization measures be applied to side-cast slopes.
1.
for
of
IX - 48
Under the Mobility and Access Facilitation Plan (MAFP) the Contractor
shall ensure mitigation of negative impacts of construction related works
on the project population is planned in advance.
The Contractors MAFP shall include the items in Section XI ESMP:
SPL B.6.4.2
Under the Social and Gender Plan the Contractor shall to perform
the work in accordance with the Section XI ESMP, and the following:
The Contractor is required to provide periodic training and basic
facilities to communities to develop school zone crossing safety
procedures, including the use of trained volunteer adult crossing guards
to assist children in crossing the road. This will include at a minimum:
Contractor will hire a traffic engineer with appropriate national
certifications to oversee and manage the road safety training
process.
Contractor will prepare a road safety training program, syllabus for
the training, and training materials. These will be submitted to the
Engineer for review and approval prior to start of work.
Training classes will be required at each school/barangay.
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 49
Under the Trafficking in Persons (TIP) Plan, the Contractor shall complete
the work in accordance with the Section XI ESMP:
SPL B.6.4.4
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 50
Technical
Specifications:
Rehabilitation/Construction
of
IX - 51
Monitoring Location
Soil erosion.
Soil contamination.
Monitoring
Method
Monitoring
Frequency
At
beginning
of
Site inspection
sites
intended
use; as
necessary
during
Cut and fill areas,
Site
inspection construction
retaining
walls, and
As
necessary
test during
bridges,
and soil
information
construction
earthwork
Plant and
inspection
equipment operation Site
and
areas; oil and
test
hazardous materials soil
information
Water pollution
(Turbidity,
DO, storage areas
Suspended solids, Oil Streams and rivers
Site
inspection
and grease,
and analysis of
Total dissolved solids.)
water samples
Ground
water
pollution (Suspended Wells adjacent to
Groundwater
solids, Oil and grease, road in RROW
sample
and
Total dissolved
laboratory
solids).
analysis
As
necessary
during
construction
Before construction
at river crossings
for
establishing
baseline;
as
necessary
during
construction
Before
construction
to
establish
a
baseline; as needed
during
construction
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
Monitoring
IX - 52
Monitoring Location
Air
pollution/dust Work sites
(PM10, NOx, SOx CO).
Noise (Leq)
Work sites
Work
sites
storage areas
Quarry site
Vehicle
pedestrian
and access
of
Roadwork site
and
safety
Each barangay/
town
Posted
information
on
project
schedule,
notices,
and
endangered species
information
Technical
Specifications:
Monitoring Method
Air sample and
laboratory analysis
of samples in an
approved
laboratory
Inspection
and
noise levels (dB);
measurement
and
Site
inspection
and
accident
reports
Site
inspection
Monitoring
Frequency
Before construction
near barangays/
towns
for baseline; as
needed
during construction
Before construction
near barangays/
towns
for baseline; as
needed
during construction
When accident
occurs
Completion of
construction or end
Inspection on
of
visibility,
supervised/
compliance
with
protected
traffic and
site
pedestrian
At
each
management
activity
plans
Site
requiring
inspection
traffic
control
Quarterly
Rehabilitation/Construction
of
IX - 53
Monitoring
Monitoring Location
Monitoring Method
Number
of
road
safety
training
sessions
Each school
Training report,
agenda, number
of
participants, and
Number
of
TIP
training sessions
attendance
At the camp site sheet
where
training signed by
takes place
participants
Training Report,
agenda, number
Number of HIV/
At the camp site of
Aids
prevention
where
training participants, and
takes place
training sessions
attendance
sheet
signed
by
Worker safety and
participants
compliance with
Roadwork site
Training Report,
health and safety
agenda, number
plan
of
participants, and
Unresolved grievances Along entire project
attendance
or complaints
sheet
signed
by
participants
Inspection
Public consultation
Monitoring
Frequency
Quarterly
Quarterly
Quarterly
Safety
audits
during
construction
After construction
completion, during
defect
liability
period
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
IX - 54
of
SPL B.6.7
IX - 55
SPL B.7
Description
Compliance with
Management Plan
Unit of Measurement
Environmental
and
Social
Month
Traffic Management
Traffic
(NTP)
and
to the
affected by
from
his
3. The Contractor shall keep the length of the construction areas in such
condition that
traffic will be accommodated safely. Traffic control devices and
services shall be
provided and maintained both inside and outside the Project work
limits as needed
to facilitate traffic guidance.
4. Prior to the start of construction operations, the Contractor shall erect
such signs,
barricades, and other traffic control devices as may be required or
directed by the
Engineer.
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 56
shall
be
system
requirements. The
Contractor shall be solely responsible for meeting the requirements
of the RAP
Program related to the additional properties/structures impacted by
their proposed
temporary detour.
2. The Contractor may at their convenience construct temporary detour
roads outside
the limits of the Right-of-Way as approved by the Engineer. The
Contractor shall be
responsible for all costs associated with acquiring and/or leasing
additional lands.
All additional impacted properties/structures which have not
already been
identified in the Projects RAP Program will be subject to the
Project RAP
requirements. The Contractor shall be solely responsible for
meeting the
requirements of the RAP Program related to the additional
properties/structures for
their proposed temporary detour.
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 57
3. The Contractor shall furnish and maintain all temporary road works
such as sleeper
tracks and temporary crossings over streams or unstable ground. Such
temporary
road works shall be constructed to the satisfaction of the Engineer.
Such approval
shall not relieve the Contractor of their responsibilities under the Contract.
4. The Contractor shall submit drawings of temporary roads
detailing alignment,
profile, pavement construction, signing, lighting and the duration of
the temporary
road for the Engineers approval.
5. Any temporary roads, staging/service areas shall be immediately
removed after they
are no longer required and restored to pre-project conditions meeting
the approval
of the Engineer.
SPL B.7.2.2
Traffic Control
The Contractor shall ensure all work areas are adequately sign posted
(see
Table
B.7)
especially where width restrictions are imposed due to construction
works.
The
Contractor shall provide details in writing to the Engineer for his approval at
least seven
(7) days in advance of the works. On receipt of the Engineers
approval,
advance
warning signs (reflectorized), coning and bunding, stop and give way
(yield)
signs,
Giveway signs, other appropriate signing and lighting shall be provided
and
maintained
by the Contractor in accordance with his approved Traffic Management
Plan
and
the
effectiveness of this signing and lighting shall be constantly
monitored
by
the
Contractor.
All full and partial/temporary road closures shall be properly staffed
24 hours/7 days/week by the Contractor. All operatives shall be trained
and fully briefed by the Contractor on their responsibilities.
The Contractor shall utilize flagmen when necessary to direct the flow of
traffic for any restriction to traffic (reduction to one-lane) 24 hours/7
days/week.
Where appropriate the traffic controllers
provided with communication equipment.
SPL B.7.2.3
Table B.7
or
flagmen
shall
be
Item
Specification
1. General
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
Item
IX - 58
Specification
4.
Square plywood of the dimensions, colors,
legend,
and spacing indicated on the drawing
details shall be installed in advance of the works.
The signs shall be placed on the edge of pavement
facing the traffic flow.
2. Signs
3. Delineators
4. Warning - Lights
All barricades fences and such other aids that maybe required shall be
reflectorized and shall conform to the regulations of the DPWH and shall be
illuminated at night.
The Contractor shall appoint a representative, subject to the approval of
the Engineer who will be responsible for daily inspection of all traffic
aids within the site and to arrange such cleaning and repair as the
Engineer considers necessary to maintain the proper effectiveness of these
traffic aids at all times.
SPL B.7.2.4
The Contractor shall be fully liable for traffic control, safety and any
damage caused to or by vehicles directly caused by the temporary
road/and or feature.
Approval by the Engineer of the Contractors traffic control and signing
proposals
in
no
way will be construed as relieving the Contractor of any of his obligations
or
liabilities.
If in the opinion of the Engineer the Contractor does not fulfill
his
duties
and
responsibilities under these Specifications, the Engineer will be forced to
carry
out
such
works as he deems to be necessary and to charge the Contractor with
the
full
cost
thereof plus fifteen (15%) percent of such cost, which sum will be
deducted
from
any
money due or which may become due to the Contractor under the Contract.
SPL B.7.3
Method of Measurement
Basis of Payment
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 59
Technical
Description
Unit of Measurement
Traffic Management
Specifications:
Rehabilitation/Construction
Month
of
SPL B.8
IX - 60
The OHSP shall follow the current Philippine DPWH Department Order
Series
2005
Guidelines for Implementation of DOLE D.O. No. 13 Series 1998,
Governing
Occupational Safety and Health in the Construction Industry.
SPL B.8.1
of
IX - 61
of noise,
manual
minimize
footwear,
addition
The Contractor shall provide a designated, full time on-site safety officer
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 62
The Contractor shall provide and maintain throughout the duration of the
Contract, a weather tight medical examining room and sick bay together
with all necessary supplies and
equipment
to
be sited
in
the
Contractors main camp. The rooms shall be used exclusively for medical
purposes and shall be of good quality construction with electric lighting
and otherwise suitable for their purpose. The sick bay shall have at least
two beds, and shall be provided with adjacent washing and
sanitation facilities. The Contractor shall have means (which may
include designated emergency evacuation vehicles) to transport injured
workers to nearby hospitals.
The Contractor shall provide at least one fully trained medical aide, nurse
or paramedic who shall be on-site full time engaged solely for medical
duties.
The Contractor shall provide first aid equipment at all camps and work
sites to the satisfaction of the Engineer, and shall ensure that at all
camps and work sites where forty (40) or more persons are engaged on
the Works there shall at all times be a person qualified in first-aid with
access to appropriate first-aid equipment.
The location of the medical room and other medical and first-aid facilities
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 63
adequate
together
Engineer.
trenches
Description
SPL B.8
SPL B.9
SPL B.9.1
Description
Unit of Measurement
Month
Mobilization
without prior
written approval by the Engineer.
Within thirty (30) days from the Notice to Proceed (NTP), the Contractor
shall
prepare
the initial listing of the items specified in this Specification together with
his assessment
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 64
Demobilization Phase
Method of Measurement
Basis of Payment
shall
percent
be
of
Pay Item
SPL B.9
Description
IX - 65
Unit of Measurement
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
Lump Sum
of
PART C
IX - 66
EARTHWORK
SPECIAL PROVISIONS
ITEM 100 SP
100.2.1
Construction Requirements
100.2.2
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
100.4
IX - 67
Basis of Payment
Description
Unit of Measurement
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
Hectare
Each
of
ITEM 101 SP
101.1.1
IX - 68
Description
addition
Construction Requirements
101.2.1
General
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 69
shall
be
material
shall
be
dismantled
approved places.
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
Partial
IX - 70
or
Method of Measurement
101.4
Basis of Payment
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 71
Description
Unit of
Measurement
Removal of Existing Cansolabao Bridge
Lump Sum
Removal of Existing Binaloan Bridge
Lump Sum
Removal of Existing Bayo Bridge
Lump Sum
Removal of Existing Burak Bridge
Lump Sum
Removal of Existing Lumatod Bridge
Lump Sum
Removal of Existing Kilometer Post (for Replacement)
Each
Removal of Existing Chevron Signs
Each
Removal of Existing Miscellaneous Road Signs
Each
Removal of Existing Asphalt Concrete Pavement
Square Meter
Breaking/Removal of Existing PCC Pavement
Square Meter
Breaking/Removal of Existing Concrete Sidewalk
Square Meter
Removal of Existing Grouted Riprap
Square Meter
Cutting/Breaking/Removal of Existing PCCP for
Square Meter
RCPC/RCBC Road Crossing
Removal of Existing Reinforced Concrete Pipe Culvert Linear Meter
610mm dia.
Removal of Existing Reinforced Concrete Pipe Culvert Linear Meter
910mm dia.
Removal of Existing Reinforced Concrete Pipe Culvert Linear Meter
1070mm dia.
Removal of Existing Reinforced Concrete Pipe Culvert Linear Meter
1220mm dia.
Removal of Existing Reinforced Concrete Pipe Culvert Linear Meter
1520mm dia.
Removal of Existing Metal Guardrail
(Metal Beam) Linear
including Posts
101(4)g Removal of Existing Concrete Guardrail including Posts Linear Meter
101(4)h Removal of Existing Reinforced Concrete Box Culvert, Linear Meter
1-0.80m x 0.80m
101(4)i Removal of Existing Reinforced Concrete Box Culvert, Linear Meter
1-1.25m x 1.00m
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
101(4)j
101(5)
ITEM 102 SP
102.1
IX - 72
Excavation
Description
Roadway Excavation
of
the
Standard
of
IX - 73
Borrow Excavation
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 74
will decide the angles of the slope of cuts and fills as the
proceeds
of his evaluation of the soil characteristics. The actual lines
the
cuts
and
will be duly measured and recorded by the Contractor. The
will
records and will approve the measurements, if correct,
a
basis
for
Excavation and filling beyond the neat lines shown on the Drawings or
specified by the Engineer shall not be paid for.
Excess of excavation shall be backfilled, as directed by the Engineer,
with approved materials without extra payment to the Contractor.
102.2.8 Borrow Areas
Add the following:
Materials from borrow area shall normally be used for the construction of
embankment or for backfill when there is no suitable materials available
from roadway excavation, ditches and water courses, or structure
excavation. Permission to use materials from borrow areas shall first be
obtained in writing from the Engineer. Nevertheless, the total amount of
materials from roadway excavation, ditch and water course excavation
and structure excavations after deduction of the materials declared
unsuitable by the Engineer shall be considered available for use in the
work regardless of haul distances and any surplus material resulting
from the Contractor having used materials from borrow areas in its
place shall not be measured for payment.
102.2.9 Removal of Unsuitable Material
Add the following:
In general, whenever material of doubtful characteristics are discovered
in
any
area
where excavation is being performed or at places where embankment
will
be
formed
which, in the opinion of the Engineer, constitutes materials unsuitable for
use
as
backfill
or embankment, such material so discovered, shall not be used in the
works
until
the
Contractor has shown by laboratory tests, with the approval of the Engineer,
that they
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 75
Basis of Payment
Description
Unsuitable Excavation
Surplus Common Excavation
ITEM 103 SP
103.1
Structure Excavation
Construction Requirements
Excavation
Unit of Measurement
Cubic Meter
Cubic Meter
of
IX - 76
sufficient working space on each side of the pipe for jointing and the
convenience in the compaction of backfill. For box culverts, 450 mm on
each side of the wall shall be excavated to allow sufficient working
space for the installation of steel bars and formworks. Sides of
excavation serving as formworks during the construction of box culverts
shall not be permitted.
The sides of pits, trenches and other excavations shall, where required,
be adequately timbered and supported to the satisfaction of the
Engineer, and all such excavations shall be of sufficient size to enable
the pipes and concrete to be laid accurately and proper refilling and
compaction to be carried out.
The Contractor shall take every precaution, and use the most
appropriate method of excavation, to avoid the loosening of materials or
the breaking of rock beyond the lines and grades shown on the
Drawings.
Should excavations be effected to a greater depth or width than is
necessary; then the Contractor shall at his own expense backfill the
excess excavation with approved materials, compacted to the density of
the adjacent ground, to the correct levels and dimension to the approval
of the Engineer.
Trenches shall be kept clean and free from water during excavation,
concreting, laying of pipes and backfilling, and the Contractor shall
dig diversion channels, erect cofferdams or otherwise de-water the trench.
Where, in the opinion of the Engineer, any invert has become soft or
unsuitable
to
receive the culvert or concrete bed due to the Contractors method of
working,
the
Contractor shall remove and replace the materials with non-structural
concrete
or
other
approved materials at his own expense, as instructed by the Engineer.
Where
concrete
is specified; the mix shall consist of ordinary Portland cement and
aggregate,
both
complying with the Specifications, Item 405. The weight of cement mixed
with
0.3
m3
of
aggregate shall not be less than 50 kg. The quantity of water shall
not
exceed
that
required to produce a smooth cement paste which coat evenly the
whole
of
the
aggregate.
For
culverts
density of the adjacent ground, whichever is the greater, such that the
foundation
of
the
culvert or bedding is true to grade and of uniform density over the
whole
length
of
the
culvert.
The Engineers approval of all excavation for bridges, structures and
culverts shall be obtained prior to commencing any bedding for the
bridges, structure or culvert foundation or for installation of the culvert
itself.
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 77
Basis of Payment
Method
necessary,
materials, labour, tools and
work
following Items.
incidentals
under
necessary
all
to complete
the
the
Description
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
Unit of Measurement
of
Pay Item
Description
IX - 78
Unit of Measurement
103(1)a
103(2)a
Structure Excavation
Bridge Excavation (AOWL)
Cubic Meter
103(2)b
Cubic Meter
103(2)c
Riverbed/Riverbank Excavation
103(3)
103(6)
Cubic Meter
Cubic Meter
ITEM 104 SP
104.2
Embankment
Cubic Meter
Material Requirements
Cubic Meter
104.3
Construction Requirements
104.3.2
Methods of Construction
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 79
When fill is placed against a channel slope, vertical surfaces shall not
exceed one (1) meter in height.
104.3.3
Compaction
When
on Steep Slopes.
Stone Fill at Abutment Slopes
Size of Stone
150 mm
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
Size of Stone
100 mm
60 mm
25 mm
IX - 80
fill
Method of Measurement
Basis of Payment
Description
Unit
of
Measurement
Cubic
Meter
Cubic
Meter
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
Cubic Meter
of
ITEM 105 SP
105.3.3
IX - 81
Subgrade Preparation
Method of Measurement
Delete this Section in its entirety and replace with the following:
The work associated with the following items shall be measured as
specified
below
completed in accordance with the Drawings, Specifications and as
accepted
by
the
Engineer.
Replacement of the
150mm materials
removed under Section
105.2, Material
Requirements, is to be watered, shaped and compacted with material
approved by the Engineer and which has CBR value not less than 7%.
Should a leveling course be necessary to correct the irregularities of the
prepared sub- grade or for non-compliance to the maximum allowable
tolerances prescribed in Section 105.3.2, such course shall not be
measured separately but deemed to have been included the item for
Sub-grade Preparation.
Subgrade Preparation (Common Material)
Square Meter complete in place.
shall
be
measured
per
shall
be
measured
per
105.5
Basis of Payment
Description
105(1)
105(2)
Unit of Measurement
Square Meter
Square Meter
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
PART D
IX - 82
SPECIAL PROVISIONS
ITEM 200 SP
200.2
Material Requirements
Delete this section in its entirety and replace with the following:
Aggregate subbase course shall consist of natural or processed
aggregates such as gravel, sand, stone fragments, or crushed (partly or
totally) stone which shall conform to the following requirements.
Sieve Designation
Standard,
mm
50.0
37.5
25.0
9.50
4.75
2.00
0.425
0.075
Alternate US
Standard
2
1 -
1
3/8
No. 04
No. 10
No. 40
No. 200
Percent
Passing by
Wt.
Grading A
100
80 - 100
55 - 85
40 - 75
35 - 60
25 - 45
10 - 30
0 - 12
The portion passing the 0.425 mm (No. 40) sieve shall have a liquid
limit not greater than 35 and a plasticity index not greater than 12 as
determined by AASHTO T89 AND T90, respectively. The soaked CBR value
shall not be less than 30% at 100% MDD as determined by AASHTO T193.
Sieve analysis testing shall be performed in accordance with AASHTO T27
and
T11.
At
least 35% by weight of the aggregate retained on and above the 4.75
MM
(No.4)
sieve
shall have at least one fractured face. The coarse aggregate portion of
the
sample
when
tested in accordance with AASHTO T 96 shall have a percent loss no greater
than 50%.
If fillers, in addition to that naturally present in the aggregate subbase
material, are necessary for meeting the grading requirements and/or for
satisfactory bonding of the material, it shall be uniformly blended with
the subbase course material on the road. The material for such purpose
shall be obtained from sources approved by the Engineer, shall be free
from hard lumps and shall not contain more than 15 percent of material
retained on the No. 4 sieve.
When additional fillers, approved by the Engineer, are to be blended
with
subbase
material, this is to be blended off the road, the blending material shall
be spread in a
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 83
uniform
manner
over
the
loosely
spread
subbase
layer
in
quantities previously determined in order to satisfy the specified
grading and quality requirements in all respects and then brought to
the road and laid.
After each layer of subbase course material has been placed with or
without blending material added, it shall be thoroughly wetted, mixed to
the full depth of the required layer by scarifying and blending. When
and if directed by the Engineer, the materials shall be watered to
prevent segregation of particle sizes and to obtain the moisture content
required for compaction. When uniformly mixed, the mixture shall be
spread smoothly to the cross-section shown on the plans.
200.4
Method of Measurement
Basis of Payment
for
shall
be
following
made
under
Unit
Item:
Description
200
ITEM 202 SP
Course
of
Measurement
Pay Item
202.2
the
Cubic
Meter
Material Requirements
Alternate US
Standard
Percent
Passing by
Wt.
Grading A
37.5
1 -
100
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
25.0
19.00
4.75
0.425
0.075
IX - 84
1
3/4
No. 04
No. 40
No. 200
-
60 - 85
30 - 55
8 - 25
2 - 14
The portion passing the 0.425 mm (No. 40) sieve shall have a liquid
limit not greater than 25 and a plasticity index not greater than 6 as
determined by AASHTO T89 AND T90, respectively. The soaked CBR value
shall not be less than 80% at 100% MDD as determined by AASHTO T193.
Sieve analysis testing shall be performed in accordance with AASHTO T27
and
T11.
At
least 50% by weight of the aggregate retained on and above the 4.75
MM
(No.4)
sieve
shall have at least one fractured face. The coarse aggregate portion of
the
sample
when
tested in accordance with AASHTO T 96 shall have a percent loss no greater
than 40%.
202.5
Basis of Payment
Description
202
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
Unit of Measurement
Cubic Meter
of
PART E
IX - 85
SURFACE COURSES
SPECIAL PROVISIONS
ITEM 300 SP
300.2 SP
Materials Requirements
ITEM 311 SP
311.2.2
be used
Fine Aggregate
Coarse Aggregate
Delete the second paragraph in its entirety and substitute with the following;
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 86
Construction Requirements
Equipment
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 87
quality
Basis of Payment
Description
Unit of Measurement
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
Square Meter
of
311(1)b
Meter
IX - 88
Square
Square Meter
SUPPLEMENTAL SPECIFICATIONS
SPL E1
SPL E1.1
Description
Material Requirements
Material
All material shall be in accordance with Section 311 unless otherwise specified.
SPL E1.2.2
Patching Material
Other than specified in SPL 3.3.1, patching material for use in the
repair of surface defects less than 50 mm wide and 25mm deep prior
to the overlay shall consist of bituminous material, cementitious
material, or other equivalent material meeting the approval of the
Engineer.
SPL E1.2.3
Concrete
the
unbonded
overlay
Dowel Bars
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
shall
be
in
IX - 89
Construction Requirements
Surface Preparation
All holes greater than 50mm wide and 25mm deep in the surface of
the
traffic
lanes
shall be filled with Crushed Aggregate Base Course material meeting
Item
202
SP
gradation and shall be compacted to a minimum of at least 100 percent of
the
maximum
dry density as determined in accordance with AASHTO T-180, Method D
and
to
a
flat,
tight surface.
At locations with rocking or unstable existing concrete slabs with high
deflection
or
pumping problems, remove slab and repair subbase/subgrade where
soft
spots
or
if
excessive loss of support exists with properly compacted Crushed
Aggregate
Base.
At
locations of badly shattered slabs with working cracks, punchouts or
blowups,
remove
and replace concrete pavement with properly compacted full-depth
crushed
aggregate
subbase meeting Item 202 requirements, repair subbase/subgrade where
soft
spots
or
if excessive loss of support exists. Repair area should extend at least
475mm
beyond
the
area of distress. In repair areas, excavate to a depth of 150mm below
any
exposed
subgrade; remove and replace the excavated subgrade with additional
subbase
material
(as above).
SPL E1.3.2
Expansion Joints
existing
pavement
shall
be
The Crushed Aggregate Base interlayer shall comply with the requirements
of Item 202 SP. and will be placed with a minimum thickness of 75 mm.
SPL E1.3.4
Concrete Pavement
degrees F. The newly placed concrete shall have a traverse tining finish.
The concrete shall be cured with white pigment curing compound.
The
of
SPL E1.3.5
IX - 90
Surface Treatment
Dowel Bars
Tie Bars
the
Method of Measurement
Unbonded
Concrete
Overlay
Pavement
shall
be
measured
2% of
of the
per
the
with
Basis of Payment
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
the
Drawings,
IX - 91
Description
Unit of Measurement
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
Square Meter
of
SPL E2
Woven Geotextile
SPL E2.1
Description
IX - 92
This work shall consist of furnishing and installing woven geotextile, prior
to placement of pavement layers or embankment materials. The woven
geotextile shall be installed as indicated on the drawings and these
specifications or as directed by the Engineer.
SPL E2.2
Composite:
Material Requirements
The
woven
Test Methods
Mechanical Properties ASTM
ISO
Tensile Strength
D 4595 10319
Elongation
D 4595 10319
Units
US Units
SI Units
Lbs / ft
kN/m
%
%
CBR Puncture
UV resistance after
500 hours
D 6241 12236
D 4355 11341
lbs
%
kN
%
1,124
90
5
90
D 4751 12956
Inches
ft
ft
mm
m
m
0.0118
328
14.76
0.30
100
4.50
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
SPL E2.3
IX - 93
Method of Measurement
Basis of Payment
Description
Woven Geotextile
Unit of Measurement
Square Meter
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
PART F
IX - 94
BRIDGE CONSTRUCTION
SPECIAL PROVISIONS
ITEM 400 SP
Piling
Delete Section 400.3.7 in its entirety and replace with the following:
400.3.7 SP
400.3.7.1 SP Description
This item consists of construction of bored piles in drilled holes through
surface gravel and underlying silty clay strata drilled with the use of
specialized equipment and water as soil surface stabilizer. It shall include
the excavation and drilling of holes, furnishing and placing steel casing
for the top zone of the pile and incidentals necessary for the execution
of the work. Pile construction shall be at locations, dimensions and
lengths indicated in the drawings and in accordance with this specification.
400.3.7.2 SP Working Drawings
The Contractor shall submit to the Engineer for review and approval, an
installation plan for the construction of bored piles. The submittal shall
include the following:
1. List of proposed equipment to be used including cranes, drills,
augers, bailing
buckets, final cleaning equipment, desanding equipment, slurry
pumps, sampling
equipment, tremies or concrete pumps, etc.
2. Details of overall construction operation sequence and the sequence
of
bored
pile
construction in bents or groups.
3. Details of pile excavation methods.
4. For
is
required,
to
details
of
the method
mix,
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 95
of
the
Silt Curtain
The silt curtain fabric shall consist of high tenacity and high quality
polyester yarn. The manufacturing process shall consist of a weaving
technique to form a dimensional
stable fabric providing significant tensile reinforcement capacity in the
warp and weft direction. The manufacture shall certify compliance with
this requirement.
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 96
piles
are
to
be
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 97
following
construction
construction
tolerances
of
shall
be
maintained
bored
in
piles:
The bored pile shall be within 75 mm of the plan position in the
horizontal plane at the plan elevation for the top of the shaft.
The vertical alignment of the drilled hole shall not vary from the plan
alignment by more than 20 mm per meter.
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 98
After all the pile concrete is placed, the top of the reinforcing steel
cage shall be no more than 150 mm above and no more than 75 mm
below plan position.
The top elevation of the pile shall be within 25 mm of the plan top of
pile elevation. The bottom of the shaft excavation shall be normal to
the axis of the pile within 60 mm per meter of pile diameter.
Sloughing and Caving
Correct any sloughing or caving of the shaft excavation sidewalls.
Remove all sloughed material and smooth the caved area surface and
edges to facilitate the flow of concrete into the caved space. Ensure
complete filling of the shaft. If caving occurs during placement of
drilled shaft concrete, immediately stop the flow of concrete and
undertake corrective measures to completely remove the sloughed
materials from the shaft. If necessary to facilitate material removal,
remove the concrete and reinforcing steel already placed in the shaft.
Permanent Casing
Furnish and install permanent casing as specified. Permanent casing may
be oversized up to 75mm if necessary to facilitate temporary casing
installation. Install permanent casing to the plan elevation, or elevation
established by the DPWH Engineer.
Temporary Casing
Furnish temporary casing extending to the bottom of the drilled shaft
excavation
to
prevent material from entering the shaft excavation. Be prepared to
provide
up
to
3
m
of additional temporary casing in the event the shaft bottom elevation is
lowered
during
construction. Use casing with an outside diameter no less than the
specified
diameter
of
the shaft. Advance the casing prior to or concurrently with the
excavation.
Limit
the
excavation in advance of the casing tip to 3 meters. Withdraw the
temporary
casing
while placing the drilled shaft concrete. During casing extraction, maintain
a
level
of
fresh concrete in the casing a minimum of 1.5 meters above the
hydrostatic
water
or
drilling fluid level outside the casing, or a minimum of 1.5 meters above
the
bottom
of
the casing, whichever is higher. Maintain an adequate level of concrete
within
the
casing
so fluid trapped behind the casing is displaced upward and discharged
at
the
ground
surface without contaminating or displacing the shaft concrete. Temporary
casings
that
have become bound or fouled during shaft construction and cannot be
removed
are
considered to be a defect in the drilled shaft. Correct defective shafts
using
approved
methods at no cost to the DPWH. Corrective action may consist of, but is
not
limited
to,
the following:
1. Removing the drilled shaft concrete and extending the drilled shaft deeper
to
compensate for the loss of frictional capacity to the cased zone.
2. Providing straddle drilled shafts to compensate for capacity loss.
3. Providing a replacement drilled shaft.
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 99
Obstructions
An obstruction is considered a specific object exceeding 50% of the shaft
diameter that cannot be removed from the drilled shaft excavation using
conventional augers or core barrel
tools.
If
an
obstruction
is
encountered, promptly notify the Project Engineer. Submit four copies of
a proposed obstruction removal method to the Project Engineer for
approval within two calendar days of encountering the obstruction
Excavated materials which are removed from the hole excavation and
any drilled fluid used shall be disposed of and measure of environmental
protection due to discharge is needed in accordance with the special
provisions or as directed by the Engineer.
Slurry
Slurry used in drilling process shall be mineral slurry. The slurry shall
have
both
a
mineral grain size that will remain in suspension and sufficient
viscosity
and
gel
characteristics to transport excavated material to a suitable screening
system.
The
percentage and specific gravity of the material used to make the
suspension
shall
be
sufficient to maintain the stability of the excavation and to allow
proper
concrete
placement. The level of the slurry shall be maintained at a height
sufficient
to
prevent
caving of the hole.
The polymer slurry shall be premixed thoroughly with clean fresh water
and adequate time allotted for hydration prior to introduction into the
drilled hole. Adequate slurry tanks will be required when specified. No
excavated slurry pits will be allowed without written permission of the
Engineer when slurry tanks are required on the project. Adequate
desanding equipment will be required when specified. Steps shall be
taken as necessary to prevent the slurry from setting up in the
shaft
excavation,
such
as, agitation, circulation and adjusting the
properties of the slurry.
Control tests using suitable apparatus shall be carried out by the
Contractor on the polymer slurry to determine density, viscosity and pH.
An acceptable range of values for those physical properties is shown in
the following table:
Range of Values (at 68F)
Property (units)
Density (pcf)
64.3 to 75.0
Density
Balance
28 to 45
Marsh Cone
Ph
8 to 11
pH paper or
8 to 11
meter
Notes:
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 100
Silt Curtain
Installation of the fabric (silt curtain) shall be in accordance with the
manufactures
instructions. The supplier shall provide a method statement detailing
installation
procedure.
Reinforcing Steel Cage Construction and Placement
The reinforcing steel cage consisting of the steel shown on the Plans plus
cage
stiffener
bars, spacers, centralizers and other necessary appurtenance shall
be
completely
assembled and placed as a unit immediately after the shaft excavation is
inspected
and
accepted and prior to shaft concrete placement. Support the steel cage
from
the
top
so
that racking and distortion are prevented. Remove internal stiffeners as
necessary
as
the steel cage is placed in the borehole to prevent interference with the
placement
of
concrete.
Where the reinforcing steel cage length is too long for the placement as a
single unit, the cage may be placed in separate units such that
appropriate means of splicing the longitudinal steel is provided for such
of
IX - 101
48.0
hours
after
pile concrete
operations
has
been
placed,
no
that would cause soil movement adjacent to the shaft, other than mild
vibration,
shall
be
conducted.
Portion of bored piles exposed to a body of water shall be protected by
form in place for a minimum of seven (7) days after concrete placement.
400.5 SP
Basis of Payment
of
IX - 102
Unit of Measurement
Linear Meter
Linear Meter
ITEM 404 SP
404.4
Reinforcing Steel
Method of Measurement
Designatio
n
#2
#3
#4
#5
#6
Unit
Weight
Designation
(kg/m)
Size
(mm
)
6
10
12
16
20
0.222
0.616
0.888
1.579
2.466
404.5
Basis of Payment
Technical
Specifications:
#8
#9
#10
#11
Size
(mm)
25
28
32
36
Rehabilitation/Construction
Unit
Weight
(kg/m)
3.854
4.833
6.313
7.991
of
IX - 103
Description
Unit of Measurement
ITEM 405 SP
Kilogram
Kilogram
Structural Concrete
Delete Section 405.1.2 in its entirety and replace with the following:
405.1.2
Seven classes of concrete are provided for this Item, namely: A (Mod), A,
AA, B, C, D, P and Lean Concrete. Each class shall be used in that part
of Bridge Construction as called for on the plans.
The classes of concrete for bridge structures are used as follows:
Class A (Mod) -
Class A
Class AA
Class B
Class C
Class D
Bored Piles
Class P
Pre-stressed concrete
Lean Concrete -
Cement for all piles and abutments of bridges and Box Culverts shall be
Type
II
Sulfate
Resistant, in accordance with AASHTO M85, the rest shall be Type I,
Portland cement.
405.2.2
Fine Aggregates
of
IX - 104
The fine aggregate shall not contain deleterious materials in such a form
or in sufficient quantity to affect adversely the strength at any age or
the durability of concrete. Any effect shall be determined by comparing
the strength of concrete cylinders made with the aggregate in question
with that of concrete made with acceptable aggregates. The details of
this concrete test, including mix proportions, type of cement, type of
grading of reference aggregates, age at test and criterion for acceptance,
shall be approved by the Engineer prior to the test.
405.2.3
Coarse Aggregate
Delete this Sub-section in its entirety and replace with the following:
1. Premolded Expansion Joint Filler
2. Joint Filler (Sealant)
Poured Joint Filler material shall be mixed with asphalt and mineral or
rubber filler conforming to the applicable requirements of Item 705 Joint
Materials.
3. Polystyrene
Expanded polystyrene and hard board shall be commercially available
polystyrene
board. Expanded polystyrene shall have a flexural strength of 0.24
MPa
(35
psi,
minimum, determined in accordance with ASTM Designation: C203, and a
compressive
yield strength of between 0.11 MPa and 0.28 MPa (16 and 40 psi),
at
5%
percent
compression. When shown on the plans, surfaces of expanded
polystyrene
shall
be
faced with hardboard of minimum thickness of 3.2 mm (1/8 inch). All
boards
shall
be
held in place by nails, waterproof adhesive or other means as approved by the
Engineer.
405.4.1
Proportioning and Strength of Structural Concrete
Add the following paragraph:
To prevent harmful alkali-silica reaction, the Portland cement shall have a
total alkali content not exceeding 0.60 percent expressed as sodium oxide
(Na2O) equivalent.
The total alkali content of the concrete mixture shall be less than 3.0
kg/m3 regardless of the rock type of aggregate used.
Delete Table 405.2 and replace with the following:
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 105
Table 405.2 Composition and Strength of Concrete for Use in Bridge Structure
Class of
Concrete
A(Mod)
Minimum
Cement
Content per
cu.m.
kg (bag**)
360
(9)
Maximum
Water/Cement
Ratio
kg/kg
0.53
360
(9)
AA
360
(9)
B
320
(8)
C
380
(9.5)
D
400
(10)
P
440
(11)
Lean
240
(6)
**Based on 40 kg. bag
405.5
Consistency
Range in
Slump mm
(inch)
50 - 100
(2 - 4)
0.53
50 - 100
(2 - 4)
0.53
50 - 100
(2 - 4)
50 - 100
(2 - 4)
50 - 100
(2 - 4)
50 - 100
(4 max)
100 (max)
(4 max)
120 - 200
(5 max)
0.58
0.53
0.53
0.49
0.62
Minimum
Compressive
Strength of
150x300 mm
Designated Size
concrete
of Coarse
cylinder
Aggregates
specimen at 28
Square Opening days MN/sq.m.
std. mm.
(psi)
19 - 4.75
20.7
(3/4 - No.4)
(3,000)
37.5- 4.75
(1 - No.4)
19 - 4.75
(3/4 - No.4)
50.0- 4.75
(2 - No.4)
12 - 4.75
(1/2 - No.4)
19.0- 4.75
(3/4 - No.4)
19.0- 4.75
(3/4 - No.4)
50.0- 4.75
(2 - No.4)
20.7
(3,000)
27.6
(4,000)
16.5
(2,400)
20.7
(3,000)
27.6
(4,000)
37.7
(5,000)
9.9
(1450)
Method of Measurement
Basis of Payment
of
Pay Item
Description
405(1)a
Measurement
Meter
405(1)b
MPa
405(1)c
MPa
Cubic
Cubic Meter
Cubic Meter
Technical
Specifications:
Rehabilitation/Construction
of
Pay Item
Description
407(1)
Lean Concrete
ITEM 406 SP
406.1
IX - 106
Unit of Measurement
Cubic Meter
Description
herein
refer
to
DPWH
Standard
Details of Design
When the design for the prestressing work is not fully detailed on
the
plans,
the Contractor shall determine the details or type of
prestressing system for use and select materials and details conforming
to these specifications as needed to satisfy the prestressing
requirements specified. The system selected shall provide the
magnitude and distribution of prestressing force and ultimate strength
required by the plans without exceeding allowable temporary stresses.
Unless otherwise shown on the plans, all design procedures, coefficient
and allowable stresses, friction and prestress losses as well as tendon
spacing and clearances shall be in accordance with the Division I, Design
AASHTO Standard Specifications for Highway Bridges.
The prestressing may be performed by either pretensioning or post-
tensioning methods unless the plans show only pretensioning details.
When
of
IX - 107
of the
Material Requirement
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
406.2.1
IX - 108
The materials for concrete and grout shall conform to Section 405,
Structural Concrete. The concrete shall be Class P or as shown on the
Plans. The proportions of the grout will be as set out in Subsection 406.3.7,
Grout and Grouting 2.3(4) below.
406.2.2
Reinforcing steel shall conform to Item 710, Reinforcing Steel and Wire Rope.
406.2.3
Prestressing Steel
Strand
Uncoated seven-wire strand shall conform to the requirements of
AASHTO M203 (ASTM A416). Supplement S1 (Low-Relaxation) shall apply
when specified.
b. Wire
Uncoated stress-relieved steel wire shall conform to the requirements
of AASHTO M204 (ASTM A421)
c.
Bars
Uncoated
the
minimum
specified ultimate strength of the prestressing steel, when tested in
an unbounded
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 109
Ab
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 110
As used in the above equation fcp is the average bearing stress, P/A, in the
concrete
computed by dividing the force P of the prestressing steel by the net projected
area, Ab'
between the concrete and the bearing plate or other structural
element of the anchorage which has the function of transferring the
force to the concrete.
(iii)
Supplemental Reinforcement
of
IX - 111
The actual strength of the prestressing steel shall not be less than
specified by the applicable ASTM Standard, and shall be determined by
tests of representative samples of the tendon materials in conformance
with ASTM Standard.
All of the materials specified for testing shall be furnished free of cost
and shall be delivered in time for tests to be made well in advance of
anticipated time of use.
(i) Pretensioning Method Tendons
For pretensioned strands, one sample at least 2.0 meter long shall
be furnished in accordance with the requirements of paragraph 9.1 of
AASHTO M203.
(ii)
bars
to be
between
furnished
with
threaded ends
threads
and
nuts
1.5
at
meter
ends.
(iii) Anchorage Assemblies and Couplers
Except for anchorage devices without distribution plates (See AASHTO
requirements), the Contractor shall furnish for testing, one specimen
of each size of prestressing tendon, including coupling, of the
selected type, with end fittings and anchorage assembly attached for
strength test only. These specimens shall be 1.5 meter in clear length,
measured between ends of fittings. If the results of the test indicate the
necessity of check tests, additional specimens shall be furnished without
cost.
When dynamic testing is required, the Contractor shall perform the
testing and shall furnish certified copies of test results which indicate
conformance
with
the
specified requirements prior to installation of
anchorages or couplers.
For prestressing systems previously tested and approved on projects
having the same tendon configuration, the Engineer may not require
complete tendon samples provided there
is
no
change
in
the
material, design, or details previously approved. Shop drawings or
prestressing details shall identify the project on which approval was
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 112
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 113
and
sealing
leakage of grout.
to
prevent
Grout
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 114
b.
Expansion ratio shall not exceed 10%. However, the ration shall
be always less
than the bleeding ratio immediately after the injection until the
bleeding is
maximum.
c.
d.
Water-to-Cement ratio shall not exceed 45%. A process whereby
thin grout is
used initially to wet the ducts, and is subsequently thickened to
the specified
ratio may be considered where long ducts result in grout drying
out and zero
flow before the end of the duct is reached.
e.
Portland Cement
Portland Cement shall conform to one of the following:
Specifications for Portland Cement - ASSHTO M85. Types I, II or
III. Cement used for grouting shall be fresh and shall not
contain any lumps or other indication of hydration or pack
set.
(ii) Water
The water used in the grout shall be potable, clean and free
of injurious quantities of substances known to be harmful
to Portland Cement or prestressing steel.
(iii) Admixtures
Admixtures, if used, shall impart the properties of low-water
content, good flowability, minimum bleed, and expansion if
desired. They shall contain no chemicals in quantities that may
have harmful effect on the prestressing steel or cement.
Admixtures which, at the dosage used, contain chlorides in
excess of 0.005 percent of the weight of the cement used or
contain any fluorides, sulphites, and nitrates shall not be used.
Whenever
grout
the
expanding
admixture
is
required, or
Contractors
is
used
at
option, it shall be well dispersed through the other admixtures and shall
produce a 2 to
6 percent unrestrained expansion of the grout.
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 115
Water
Enclosures
Construction Requirement
406.3.1
General
Technical
Specifications:
Rehabilitation/Construction
of
IX - 116
Combined Method; in which part of the reinforcement is pretensioned and part post-
tensioned. Under this method all applicable requirements for
pretensioning
and
for
post-tensioning shall apply to the respective reinforcing elements
using
these
methods.
During stressing of strand, individual wire failures may be accepted by the
Engineer,
provided not more than one wire in any strand is broken and the
area
of
broken
wires does not exceed 2 percent of the total area of the prestressing
steel
in
the
member.
B. Concrete Strength
Prestressing forces shall not be applied or transferred to the concrete until
the
concrete
has attained the strength specified for initial stressing. In addition,
cast-in-place
concrete for other than segmentally constructed bridges shall not be post-
tensioned.
C. Prestressing Equipment
Hydraulic jacks used to stress tendons shall be capable of providing and
sustaining
the
necessary forces and shall be equipped with either a pressure gauge or a
load cell for
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 117
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 118
Prestressing Method
with
the
Casting Yard
Placing Enclosures
shall
at
be
b.
Placement of Ducts
Ducts
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 119
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 120
15 days
20 days
After tendons are placed in ducts, the opening at the ends of the ducts
shall be sealed to prevent entry of moisture.
When steam curing is used, steel for post-tensioning
installed until the stream curing is complete.
shall
not
be
Placing Steel
Steel units shall be accurately placed at the position shown on the Plans
and firmly held during the placing and setting of the concrete.
Ducts
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 121
406.3.7
Post Tensioning
a.
Tensioning of the prestressing reinforcement shall not be commenced
until tests on
concrete cylinders, manufactured of the same concrete and cured
under the same
conditions, indicate that the concrete of the particular member to be
prestressed has
attained 85 % compressive strength of at least 40 MPa unless
otherwise specified.
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 122
b. After all concrete has attained the required strength, the prestressing
reinforcement
shall be stressed by means of jacks to the desired tension and the
stress transferred to the end anchorage.
c. Cast-in-place concrete shall not be post-tensioned until at least ten (10) days after
the last concrete has been placed in the member to be post-tensioned
and until the compressive strength of said placed concrete has
reached the strength specified for the concrete at the time of stressing.
d. All side forms for girders shall be removed before post-tensioning. The
falsework
under the bottom slab supporting the superstructure shall not be
released
until
a
minimum of 48 hours had elapsed after grouting of the post-tension
tendons
nor
until all other conditions of the Specifications have been met.
The
supporting
falsework shall be constructed in such a manner that the
superstructure
will
be
free
to lift off the falsework and shorten during post-tensioning. Formwork
left
inside
box girders to support the roadway slab shall be detailed in such a
manner
so
as
to
offer minimum resistance to girder shortening due to shrinkage and
post-tensioning.
e. The tensioning process shall be so conducted that the tension being applied
and
elongation of the prestressing elements may be measured at all times.
The friction loss in the a element, i.e., the difference between the
tension at the jack and the minimum tension, shall be determined in
accordance with Article 1.6.7 of AASHTO Standard Specification for
Highway Bridges.
f. Suitable shims or other approved devices shall be used to insure that the
specified
anchor set loss is attained.
g. A record shall be kept of gauge pressure and elongation at all times and
submitted to
the Engineer for his approval.
h. Prior to post-tensioning of any member, the Contractor shall demonstrate
to the
satisfaction of the Engineer that the prestressing steel is free and unbounded in
the
duct.
i. All strands in each tendon, except for those in flat ducts with not more than
four
strands, shall be stressed simultaneously with a multi-strand jack.
j. Tensioning shall be accomplished so as to provide the forces and
elongations
specified in Sub-section 406.3.10 of DPWH Specification.
k. Except as provided herein or when shown on the plans or on the approved
working
drawings, tendons in continuous post-tensioned members shall be
tensioned by jacking at each end of the tendon. For straight tendons
and when one end stressing is shown on the plans, tensioning may be
performed by jacking from one end or both ends of the tendon at the
option of the Contractor.
406.3.8
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 123
a. Prestressing steel shall be bonded to the concrete by filling the void space
between
the duct and the tendon with grout.
b. Grout shall consist of Portland Cement, water and an expansive admixture
approved
by the Engineer.
c. Water shall be potable.
d. No admixture containing chlorides or nitrates shall be used.
e. Water shall first be added to the mixer followed by cement and admixture.
f. The grout shall be mixed in mechanical mixing equipment of a type that will
produce
uniform and thoroughly mixed grout with the ingredients accurately
measured. The water content shall be not more than 19 litres (5
gallons) per sack of cement. Retempering of grout will not be
permitted. Grout shall be continuously agitated until it is pumped.
g. Grouting equipment shall be capable of grouting at a pressure of at least 1.0 Mpa.
h. Grouting equipment shall be furnished with a pressure gauge having a full-
scale
reading of not more than 2.07 Mpa (300 psi).
i. Standby flushing equipment capable of developing a pumping pressure of
1.72MPa
(250 psi) and of sufficient capacity to flush out any partially grouted
ducts shall be provided.
j. All ducts shall be clean and free of deleterious materials that would impair
bonding
of the grout or interfere with grouting procedures.
k. All grout shall pass through a screen with a 2 mm (0.0787 inch) maximum
clear
openings prior to being introduced into the grout pump.
l. Grout injection pipes shall be fitted with positive mechanical shutoff valves.
Vents
and ejection pipes shall be fitted with valves, caps or other
devices capable of withstanding the pumping pressures. Valves and
caps shall not be removed or opened until the grout has set.
m. Post-tensioned steel shall be bonded to the concrete. All prestressing
steel to be
bonded to the concrete shall be free of dirt, loose rust, grease or
other deleterious
substances.
n. Prior to placing forms for roadway slabs of box girder structures, the
Contractor
shall demonstrate to the satisfaction of the Engineer that all ducts are
unobstructed and if the prestressing reinforcement has been placed,
that the steel is free and unbonded in the duct.
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 124
o. After the tendons have been stressed to the required tension, each conduit
encasing
the prestressing steel shall be blown out with compressed oil-free air.
p. The conduit shall then be completely filled from the low end with grout
under
pressure. Grout shall be pumped through the duct and continuously
wasted at the outlet until no visible slugs of water or air are ejected
and the efflux time of ejected grout is not less than 11 seconds. All
vents and openings shall then be closed and the grouting pressure at
the injection end shall be raised to a minimum of 0.6894 Mpa (100
psi) and held for a minimum of 10 seconds.
q. If aluminum powder is used to expand the grout it shall be added as follows:
From 2 to 4 grams of the unpolished variety (about 1 to 2 teaspoons)
shall
be
added
for each sack of cement used in the grout. The exact amount of
aluminum
powder
will be designated by the Engineer. The dosage per batch of grout
shall
be
carefully
weighed. A number of weighing may be made in the laboratory and
doses
placed
in
glass vials for convenient use in the mix. The aluminum powder shall
be
blended
with pumicite or other inert powder in the proportion of 1 part powder
to
50
parts
pumicite (or other inert powder) by weight. The blend shall be
thoroughly
mixed
with the cement. The amount of the blend used should vary from 120g
(4
ounces)
per sack of cement for concrete having a temperature of 21.1C to
190
g
(7
ounces)
for a temperature of 4.44C after all ingredients are added, the batch
shall
be
mixed
for 3 minutes. Batches of grout shall be placed within 45 minutes after
mixing.
406.3.9
Temperature Considerations
Unbounded Steel
of
ASTM
416 (AASHTO M
Handling
care
of
IX - 125
store precast units in other than this position, it shall be done at his
own risk after notifying the Engineer of his intention to do so.
Prestressed concrete girders shall not be shipped until tests on
concrete cylinders, manufactured of the same concrete and cured under
the same conditions as the girders, indicate that the concrete of the
particular girder has attained a compressive strength equal to the specified
design compressive strength of the concrete in the girder and has
attained a minimum age of 14 days.
406.3.10
The
Method of Measurement
Basis of Payment
Description
Prestressed Concrete Girder
(AASHTO Type IV-A) L = 28.05m
Unit of Measurement
Each
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
ITEM 411 SP
IX - 126
Paint
411.3
Construction Requirements
411.3.6
Painting
411.4
Delete this sub-section in its entirety and replace with the following:
For new bridge structures painting shall not be measured and paid for
separately, but the cost thereof shall be considered as included in
the pay items under Bridge Construction indicated in the Bill of
Quantities.
Payment shall be full compensation for furnishing and installing all
materials including labour, tools, equipment and incidentals necessary
to complete the work under this Item. The work associated with
surface preparation of steel member s by means of sandblasting is
also included in this work Item
Payment will be made under the following Item:
Pay Item
Description
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
Unit of Measurement
of
411(1)
Painting
ITEM 412 SP
412.1
IX - 127
Square Meter
Scope
Material Requirement
Elastomer:
The elastomer compound to be used in the construction of the
bearing
pads
shall contain only 100% virgin chloroprene (neoprene) as the raw
polymer. All
materials shall be new with no reclaimed materials incorporated in the
finished bearing. The elastomer compound shall conform to the
requirements of Table 1 and as prescribed in the DPWH Department
Order #25, Series of 1997, dated 29 January 1997, Revised DPWH
Standard Specification for Elastomeric Bearing Pads.
TABLE 1
Elastomer Properties
Grade (Durometer)
60
Original Physical Properties
Hardness ASTM, D2240
60+5
Tensile Strength, minimum
MPA (psi) ASTM 412
17.2(2,500)
Elongation of break, minimum
Percent
425%
Accelerated
Tests
to
Determine
Long Term Aging
Characteristics Over Aged 70 hrs/100+C ASTM D 573
Hardness, points change, maximum
Tensile Strength, % change,
Maximum
+15
Elongation at break, % change,
maximum
-40
Ozone - 1 PPM in Air by Volume
-20% Strain -100+1.1+C(2+F)
ASTM D 1149 100 hrs
no cracks
Compression
Set-22
hrs
70+C
ASTM D 395 - Method B:
70
70+5
17.2(2,500)
300
0 to +15 0 to 15
+15
-40
no cracks
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
% maximum
IX - 128
25
25
68.9(10,000) 68.9(10,000)
43.75(250)
412.2.1
39.28(225)
Fabrication
Bearings shall be cast as a unit in a mold. The mold shall have standard
shop practice mold finish. Bearing shall be built to the design dimensions
and this Specifications with the following tolerances as listed in Table 2.
TABLE 2
Overall Vertical Dimensions
Design Thickness
32mm (1-1/4) or less
Design Thickness over
32mm (1-1/4)
Overall Horizontal Dimensions
0.914 m and less (36)
Over 0.914 (36)
Thickness of individual layers
of elastomer (laminated bearings
value only) but any point within
the bearing
Variations from a plane parallel to the
Theoretical surface (as determined
measurements
at
the
edge
of the bearings)
Top
Sides
Position of exposed Connection
Member
Edge Cover embedded laminates
of connection members
Tolerances
(mm)
(in)
-0+3
-0+1/8
-0+6
-0+1/4
-0+6
-0+1/4
-0+12
-0+1/2
+20 percent of design
no more than +3mm
(+1/8)
by
1/8
-0+3
0+1/8
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 129
+3
+3
+1/8
+1/8
The manufacturer shall certify that each bearing satisfies the design
specification and supply a certified copy test results. Each bearing shall
be marked in indelible ink or flexible paint. The marking shall consist
of the order number, lot number, bearing identification number and
elastomer type. The marking shall be on a face, which is visible after
erection of the bridge.
A lot of pads shall be considered to be a group of 100 or fewer pads, which are
manufactured from the same batch of elastomer, cured under the same
conditions, and are all the same size and type.
412.2.3
Shear Modulus
Nominal hardness
Shear Modulus at 73
F(psi)
Shear Modulus at 73
F(Mpa)
1.84)
50
60
85-110
120-155
(0.60-0.77)
(0.85-1.10)
70
160-260
(1.13-
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 130
(3) Load Test: Each bearing shall be proof loaded with a compression load 1.5
times
the maximum design load. If there are three separate surface
cracks, which are greater than 2 mm wide and 2 mm deep, the
bearings shall be rejected.
In addition to the certified copies of test results from the manufacturer,
the
Engineer
shall obtain samples from each lot of same size and type of pads
delivered
to
be
tested
for materials property as specified in Table 1 and to be load tested as
specified
in
(3)
above. Testing may require destruction to one or more bearings from a
lot.
Therefore
provisions shall be made to provide additional bearings for testing
purposes.
Only
after
the satisfactory results of these confirming tests shall the bearing pads be
installed.
412.3
Method of Measurement
Basis of Payment
Description
Unit of Measurement
412(1)
Each
SUPPLEMENTAL SPECIFICATIONS
SPL F1
SPL F1.1
Description
SPL F1.2
General
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 131
Test Procedures
Method of Measurement
Pile Integrity Tests shall be measured by the test per Each completed
in accordance with the Drawings, Specifications and as accepted by the
Engineer.
SPL F1.7
Basis of Payment
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 132
Description
Pile Integrity Test
SPL F2
SPL F2.1
Description
Unit of Measurement
Each
General
The steel or concrete weight for testing the bored pile shall have a weight of at
least
1.5% to 2% of the required ultimate pile capacity. A 10 cm to 15 cm
wooden material shall be placed on top of the pile to serve as a pile
cushion. A steel cap cover shall be placed on top of the pile cushion for
uniform impact distribution and to hold the pile cushion in place during
testing. The size of the pile cushion should be roughly the same, as the
diameter of the pile while the steel cap cover should snugly fit the pile top.
At the time of the testing, the bored piles shall have attained their
28-days compressive strength. Waiting period is likewise essential to
allow the previously disturbed soil to set-up and develop a natural bonding
with the pile.
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
SPL F2.3
IX - 133
Test Procedures
Method of Measurement
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 134
Pile Dynamic Tests shall be measured by the test per Each completed
in accordance with the Drawings, Specifications and accepted by the
Engineer.
SPL F2.7
Basis of Payment
Description
Unit of Measurement
Each
SPL F3
SPL F3.1
Description
Materials Requirements
Materials shall conform to the requirements for each and every item of work
specified
to complete this item:
1.
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 135
2.
Coconut logs
3.
Timber
4.
Reinforced concrete
pipe
culverts
5.
Detour road
SPL F3.3
Construction Requirements
Method of Measurement
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 136
Basis of Payment
the
the
Description
SPL F4
Pipe
GI Drain
Unit
of
Measurement
Lump Sum
Lump Sum
Lump
Sum
Lump
Sum
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
Lump Sum
of
SPL F4.1
IX - 137
Description
The work related to this item shall consist of the construction of GI drain
pipe on bridge and shall conform to the applicable requirements of Item
517, Drain Pipe.
SPL F4.2
Material Requirements
Method of Measurement
G.I. Drain Pipe shall be measured per Each complete in place installed
in accordance with the Drawings, Specifications and as accepted by the
Engineer.
SPL F4.4
Basis of Payment
Description
Unit of Measurement
Each
SPL F5
SPL F5.1
Description
The work related to this item shall consist of the construction of concrete
stair with G.I. pipe railings to the lines and grades as shown on the
Drawings.
SPL F4.2
Material Requirements
to
the
requirements
Technical
Specifications:
Rehabilitation/Construction
of
of
Item
SPL F4.3
IX - 138
Method of Measurement
Concrete Stair with G.I. Pipe Railings shall be measured per Linear
Meter
complete
in
place installed in accordance with the Drawings, Specifications and as
accepted
by
the
Engineer.
SPL F4.4
Basis of Payment
Description
Concrete Stair with G.I. Pipe
Railings
SPL F6
SPL F6.1
Description
Unit
of
Measurement
Linear Meter
with
a
variable
dispense pressure of 0-15 MPa. When the epoxy comes out on the adjacent
port
and
the
material injected has reached the full depth of the concrete fissures, the
injection port is
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 139
plugged and the injection is resumed at the next port. These steps are
to be followed until all ports are similarly injected.
SPL F6.3
Curing time
Test Reports shall include the following:
a.
b.
c.
d.
e.
f.
Viscosity
Consistency
Gel time
Absorption
Shrinkage
Thermal compatibility
of
a.
b.
c.
d.
IX - 140
Epoxy number
Consistency
Compressive single shear strength
Pot life
in
FOR
with the
of concrete used
before the grout or
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 141
any damage to the structure beyond the removal area caused by the
removal operation to the satisfaction of the Engineer.
Steel reinforcement exposed during the removal operation shall be blast
cleaned and shall be free from dirt, oil, paint, grease, loose or thick
rust and other deleterious substances which could impair bond of steel
with the concrete.
Additional steel reinforcement where shown on the Drawing or as
directed by the Engineer shall be furnished and installed to the
requirements of Item 404(60) SP, Reinforcing Steel.
Epoxy Bonding Compound shall be furnished in accordance with Item
719,
EPOXY
RESIN-BASE BONDING SYSTEMS FOR CONCRETE. Concrete shall be
furnished, placed and cured in accordance with applicable requirements
of Item 405, STRUCTURAL CONCRETE. Before depositing new concrete
on or against existing concrete, the surface of the existing concrete
shall be thoroughly cleaned of dust, laitance and foreign matters.
The surfaces of the existing concrete which will come in contact with
the new concrete shall be flushed, with water and allowed to dry
to a surface condition immediately prior to placing concrete.
SPL F6.6
Pier Scour Protection shall include furnishing and placing rock and wire
mesh baskets (gabions/mattresses) at the locations shown on the Plans or
designated by the Engineer in conformity with the lines, grades,
dimensions
and
arrangements
shown
on
the Drawings and in
accordance with Item 511, Gabions and Mattresses.
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 142
Poured joint filler shall be mixed asphalt and mineral or rubber filler
conforming to the applicable requirements of Item 705, Joint Materials.
SPL F6.11
Replacement of Superstructure
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 143
steel
bars
shall
be
be blast
thick rust
the steel
on the
to
the
installed
as
Concrete shall be Class A (Mod) and shall be furnished, placed and cured
in
accordance
with the applicable requirements of Item 405 SP, Structural
Concrete,
Item
407,
Concrete Structures and this Specification. Forms shall be built and
set
in
place
as
tightly as possible that can be rigidly held in line and grade, and removed
without
injury
to concrete. Before depositing new concrete on or against existing
concrete,
the
surface
of the existing concrete shall be thoroughly cleaned of dust, laitance and
foreign
matter.
The surfaces of the existing concrete which will come in contact with the
new
concrete
shall be flushed with water and allowed to dry to a surface condition
immediately
prior
to placing of concrete.
Rebuild reinforced concrete deck slab and/ or girder shall be measured
per
cubic
meter
of structural concrete and per kilogram of reinforcing steel in placed and
accepted
by
the Engineer. The price shall be full compensation for the furnishing
and
placing
concrete and reinforcing steel including all labor, equipment, tools
and
incidentals
necessary to complete the works. Shoring where necessary shall not
be
paid
for
separately but its deemed to be included in the payment per cubic
meter
of
concrete
in
place.
SPL F6.12
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 144
Backwall/Wingwall Reconstruction
Specifications.
Materials shall conform to the requirements for each and every item of
work specified to complete this item:
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 145
with
applicable
provisions
of
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 146
Method of Measurement
of
of grouted
IX - 147
of
in
Expansion
Joint
place.
shall
be
measured
per
Linear
Meter
complete in place.
Replacement of Superstructure shall be measured perCubic Meter
of Structural Concrete Class A (Mod),-20.7 MPa, per Kilogram of
Reinforcing Steel Bars, Grade 60, per Each of Elastomeric bearing Pad,
per Each of G.I. Drain Pipe - 150mm dia., per Lump Sum of
falsework and per Lump Sum of Demolition/Removal of Existing
Structure, per each of Mechanical Coupler and per Linear Meter
of Temporary Concrete Barrier complete in place.
Replacement of Approach Sidewalk and Railing shall be measured per
Cubic Meter of Structural Concrete Class A (Mod), - 20.7 MPa, per
Kilogram of Reinforcing Steel Bars, Grade 60,
per Each of Drill and
Bond (Dowel Bar, __mm x __mm) and per Cubic Meter of Selected
Borrow complete in place.
Backwall/Wingwall Reconstruction shall be measured per Lump Sum of
Demolition
of
Existing Backwall/Wingwall, per Cubic Meter of Structural Concrete Class
A (Mod), -
20.7 MPa, per Kilogram of Reinforcing Steel Bars, Grade 60,
per Each
of Drill and Bond (Dowel Bar, __mm x __mm
Restoration of Girder End shall be measured per Cubic Meter of
Structural Concrete Class A (Mod),-20.7Mpa and per Kilogram of Reinforcing
Steel Bars,Grade 60.
SPL F6.16
Basis of Payment
Items.
Payment shall be made under the following Items:
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 148
Pay Item
Description
SPL
SPL
SPL
SPL
SPl
SPl
F6(1)
F6(2)
F6(3)
F6(4)
F6(4)a
F6(4)b
Unit of
Measurement
SPL F6(5)
SPL F6(5)a Abutment Slope Protection
SPL F6(5)b Grouted Riprap Class A
Gabions
SPL F6(6)
SPL F6(6)a Repair of Abutment Slope Protection
Grouted Riprap Class A
Cubic Meter
Cubic Meter
Cubic Meter
SPL F6(7)
SPL F6(7)a Pier Scour Protection
SPL F6(7)b Gabions
Mattress
SPL F6(8)
Painting of Steel Components (Bearing)
SPL F6(9)
Provision of Asphalt Overlay
SPL F6(10)
Repair of Expansion Joint
SPL
SPL
SPL
SPL
SPL
SPL
SPL
SPL
SPL
SPL
SPL
SPL
SPL
SPL
SPL
SPL
Cubic Meter
Cubic Meter
Square Meter
Square Meter
Linear Meter
F6(11)
F6(11)aReplacement of Superstructure
F6(11)bStructural Concrete Class A(Mod),-20.70 MPa
Cubic Meter
F6(11)c Reinforcing Steel Bars, Grade 60
Kilogram
F6(11)dElastomeric Bearing Pad ___mm x ____mm x __mm
Each
F6(11)eG.I. Drain Pipe - 150mm dia.
Each
F6(11)f Falsework
Lump Sum
F6(11)gDemolition/Removal of Existing Structure
Lump Sum
F6(11)hMechanical Coupler 12 mm dia.
Each
F6(11)i Mechanical Coupler 16 mm dia.
Each
F6(11)j Mechanical Coupler 28 mm dia.
Each
Temporary Concrete Barriers
Linear Meter
F6(12)
F6(12)aReplacement of Approach Sidewalk and Railing
F6(12)bStructural Concrete Class A,-20.70 MPa
Cubic Meter
F6(12)c Reinforcing Steel Bars, Grade 60
Kilogram
F6(12)dDrill and Bond (Dowel Bar, __mm dia. x ___mm)
Each
Selected Borrow
Cubic Meter
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
SPL
SPL
SPL
SPL
SPL
F6(13)
F6(13)aBackwall/Wingwall Reconstruction
F6(13)bRemoval of Existing Backwall/Wingwall
F6(13)c Structural Concrete Class A,-20.70 MPa
F6(13)dReinforcing Steel Bars, Grade 60
Drill and Bond (Dowel Bar, __mm dia. x ___mm)
SPL F6(14)
SPL F6(14)aRestoration of Girder End
SPL F6(14)bStructural Concrete Class A(Mod),-20.70 MPa
Reinforcing Steel Bars, Grade 60
IX - 149
Lump Sum
Cubic Meter
Kilogram
Each
Cubic Meter
Kilogram
SPL F7
SPL F7.1
Description
The work related to this item shall include constructing shear keys for
existing bridges as shown on the Drawings and in accordance with these
Specifications.
SPL F7.2
Material Requirements
Materials shall conform to the requirements for each and every item of
work specified to complete this item:
1.
2.
Reinforcing Steel Bars - Shall be in accordance with the applicable
provisions
of
Item
404SP.
3. Formworks - Shall be used to form shear block, and shall conform to
the
applicable
requirements of Item 414, Form and Falseworks
4.
Epoxy
SPL F7.3
Method of Measurement
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 150
Basis of Payment
Description
SPL F7(1)
SPL F7(2)
SPL F7(3)
Unit of
Measurement
Cubic Meter
Kilogram
Each
SPL F8
SPL F8.1
Description
The work related to this item shall include constructing shear keys at
bridge piers as shown on the Drawings and in accordance with these
Specifications.
SPL F8.2
Material Requirements
Materials shall conform to the requirements for each and every item of work
specified
to complete this item:
1. Class A Concrete shall be in accordance with applicable provision of Item
405SP.
2. Reinforcing Steel Bars shall be in accordance with the applicable
provisions
of
Item 404(60).
3. Formworks
and
of Item 414,
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 151
Method of Measurement
Basis of Payment
Description
SPL F8(1)
SPL F8(2)
SPL F8(3)
SPL F8(4)
Falsework
SPL F9
Slab Strengthening
SPL F9.1
Description
Unit of Measurement
Cubic Meter
Kilogram
Each
Lump Sum
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
SPL F9.2
IX - 152
Materials Requirements
Table SPL
1.0% 0.85%
11.9 x 106 psi
(82 GPa)
15,000 psi
(104.8 MPa)
384,000 psi
(2.65 GPa)
42,500 psi
(293 MPa)
1.0%
0.85%
3.6ppm./F
20.3 ppm./F
1.0mm
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
1.0 mm
of
IX - 153
Method of Measurement
Basis of Payment
Description
SPL F9(1)
SPL F9(2)
Asphalt Overlay
Carbon Fiber Reinforced Polymer
SPL F10
SPL F10.1
Description
Unit of Measurement
Square Meter
Square Meter
The work related to this item shall consist of furnishing and istalling bridge rod
restrainers of the type and size as shown on the Drawings
and in
accordance with the requirements of these Specifications.
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
SPL F10.2
IX - 154
Material Requirements
Construction Requirements
Method of Measurement
Basis of Payment
Description
SPL F10
Rod Restrainer
SPL F11
SPL F11.1
Description
Unit of Measurement
Set
The work related to this item shall consist of the modifying existing
columns to the alignment, grades, design, dimensions and details as
shown on the Drawings and in accordance with this Specification for
reinforcing steel, structural concrete and other items which constitute
the completed structure.
SPL F11.2
Material Requirements
Materials shall conform to the requirements for each and every item of
work specified to complete this item:
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 155
be used
and
as
grout
of Item 414,
for dowels
should
and
D3410
D3410
Specifications:
ASTM Method
1.0% 0.85%
11.9 x 106 psi
(82 GPa)
15,000 psi
(104.8 MPa)
384,000 psi
(2.65 GPa)
42,500 psi
(293 MPa)
Rehabilitation/Construction
of
Flexural Failure
D790
Strain
Longitudinal
D696
Coefficient of
Thermal Expansion
Coefficient of
D696
Thermal Expansion
Nominal Laminate
Thickness
IX - 156
1.0%
0.85%
3.6ppm./F
20.3 ppm./F
1.0mm
1.0 mm
Construction Requirements
Method of Measurement
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 157
SPL F11.5
Basis of Payment
Description
SPL F11(1)
Structural Concrete Class A(Mod),-
20.70 MPa SPL F11(2)
Reinforcing Steel Bars,
Grade 60
SPL F11(3) Falsework
SPL F11(4) Drill and Bond (Dowel Bar, __mm
x __mm) SPL F11(5)
Carbon Fiber Reinforced
Polymer
SPL F12
Retrofit
SPL F12.1
Description
Unit of Measurement
Cubic Meter
Kilogram
Lump Sum
Each
Square Meter
The work related to this item shall consist of furnishing and installing of
carbon fiber reinforced polymer to existing concrete girders to the lines
and grades as shown on the Drawings and in accordance with these
Specifications.
Girder Strengthening shall be measured per square meter of carbon
fiber reinforced polymer in placed and accepted by the Engineer. The
price shall be full compensation for the furnishing and placing carbon
fiber reinforced polymer including all labor, equipment, tools and
incidentals necessary to complete the works.
SPL F12.2
1.
Materials Requirements
of
F12.1 and SPL F12.2
Table
SPL F9.3 below.
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
SPL
of
IX - 158
Laminate Properties
Typical Test Value Design Value
143,000 psi (986 121,000 psi (834
MPa)
MPa)
D3039
13.9 x 106 psi
(95.8 GPa)
17,900 psi
(123.4 MPa)
452,000 psi
(3.12 GPa)
50,000 psi
(344.8 MPa)
1.0% 0.85%
11.9 x 106 psi
(82 GPa)
15,000 psi
(104.8 MPa)
384,000 psi
(2.65 GPa)
42,500 psi
(293 MPa)
1.0%
0.85%
3.6ppm./F
20.3 ppm./F
1.0mm
1.0 mm
of
Elongation Percent
Flexural Strength
Flexural Modulus
D638 Type 1
D790
D790
IX - 159
5%
17,900 psi (123.4 MPa)
452,000 psi (3.12 GPa)
.2. Formworks
shall be used to form shear block, to be good quality and
shall
conform to the requirements of Item 414, Form and Falseworks.
SPL F12.3
Method of Measurement
Basis of Payment
Pay Item
Description
SPL F12(1)
SPL F12(2)
Falsework
Carbon Fiber Reinforced Polymer
SPL F13
SPL F13.1
Description
The
Unit of Measurement
Lump Sum
Square Meter
Specifications.
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
SPL F13.2
IX - 160
Material Requirements
Materials shall conform to the requirements for each and every item of
work specified to complete this item:
1.
2.
Reinforcing Steel Bars shall be in accordance with the applicable
provisions
of
Item
404 SP, Reinforcing Steel.
3.
4.
5.
Selected Borrow shall conform to the requirement of Item 104 SP, Embankment
6.
SPL F13.3
Construction Requirements
Materials shall conform to the requirements for each and every item of
work specified to complete this item:
1. Demolition of Existing Pavement and Approach Slabs: The Contractor
shall outline
the limits of the existing pavement and approach slabs to be removed,
with 19mm
deep saw cut. Demolition and removal shall be in accordance with
the applicable
provisions of Item 101, Removal of Structures and Obstructions.
2. Ground Preparation: After removal of existing pavement and
approach slabs, the
ground shall be trimmed to the required elevation shown on the
Drawings. If
additional fill material is needed, the material shall conform to the
requirement of
Item 104, SP Embankment.
3. Dowelling: When new concrete is shown on the Drawings to be
joined to existing
concrete by means of bar reinforcing steel dowels grouted into holes
drilled in the
existing concrete, the holes shall be drilled by methods that will
not shatter or
damage the concrete adjacent to the holes. Holes in which longitudinal
or transverse
reinforcement is encountered during drilling before the specified depth
is attained
shall be rejected. A new hole which does not strike reinforcement
shall be drilled
adjacent to the rejected hole to the depth shown on Drawings. The
diameters of the
drilled holes shall be 6mm larger than the nominal diameter of the
dowels unless
shown otherwise on the Drawings. The grout shall be neat epoxy
made up of resin
and hardener without the addition of sand and shall be in accordance
with Item 719,
Epoxy-Resin-Base Bonding Systems for Concrete. Drilled holes shall be
cleaned of
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 161
dust, oil, grease and other deleterious materials before the epoxy is
deposited in the hole, after which the dowel is inserted. Any dowels or
grout which fail to bond or are damaged before the new concrete is
placed shall be removed and replaced.
4. Mechanical coupler
specified
Drawings
for
reinforcing
5. Pavement:
steel
on
bars
shall
be
installed
the
requirements
Portland
of
as
item
Method of Measurement
Basis of Payment
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 162
Description
SPL F13(1)
Pavement
SPL F13(2)
Grade 60
SPL F13(3)
SPL F13(4)
__ mm)
SPL F13(5)
SPL F13(6)
dia
SPL F13(7)
dia
SPL F14
Unit of Measurement
Removal of Existing
Square
Meter
Kilogram
Cubic Meter
Each
Cubic Meter
Selected Borrow
Mechanical Coupler 16mm
Each
Each
SPL F14.1
Description
The work related to this item shall consist of cutting and removal of
existing concrete structure as shown in the Drawings and in accordance with
these Specifications.
SPL F14.2
Construction Requirements
Method of Measurement
of Exisitng
Meter
Concrete
place.
SPL F14.4
Basis of Payment
Piles
shall
complete
be
measured
per
in
Cubic
of
IX - 163
Description
SPL F14
SPL F15
SPL F15.1
Unit of Measurement
Cubic Meter
The work related to this item shall conist of furnishing and installing
bridge bearing pads. Jacking up of the superstructure is required when
replacing existing bearings. The load from the superstructure must be
relieved from the bearings and methods must be provided to temporarily
carry the loads while the bearings are removed.
This Item therefore shall consist of jacking -up the superstructure
including the construction of the jacking frame and temporary supports,
cutting of existing dowels where applicable, removal of existing
bearings, installation of new bearings and the removal of jacking frame.
SPL F15.2
Working Drawings
The Contractor shall submit to the Engineer for review and approval a
detailed plan and methodology for the replacement of the bearings.
The Contractor shall provide sufficient time for the Engineer to
complete
the
review.
Such
time
shall
be proportionate to the
complexity of the design and in no case shall be less than two (2)
weeks. The submittal shall include the following:
a. Details of the jacks to be used.
b. Shop drawings for the jacking frame and temporary supports.
c. Design calculations for the jacking frame and temporary
supports including
assumptions used for the soil bearing capacity and the maximum
loadings and
deflections for jacks, brackets, columns and beams.
d. Step by step jacking up operation sequence from the construction
of the jacking
frame until installation of new bearings and the subsequent removal
of the jacking
frame.
e. Other information requested by the Engineer.
Construction for which working drawings are required shall not start
drawings have
not relieve the
until
been
approved
by
the
Engineer.
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
such
Such approval
of
will
IX - 164
Materials Requirements
Construction Requirements
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 165
Method of Measurement
Each
number
of
Basis of Payment
included
Quantities.
in
the
Bill
of
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 166
Description
Jacking of Superstructure
Elastometric Bearing Pad ( __mm x
___mm x ___mm)
SPL F16
Footing Retrofit
SPL F16.1
Description
Unit of Measurement
Each
Each
Material Requirements
Construction Requirements
not shatter or
damage the concrete adjacent to the holes. Holes in which longitudinal
or transverse
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 167
Method of Measurement
Bored pile shall be measured and paid for as provided in Item 400 SP, Piling.
Steel Reinforcement including the dowels shall be measured and paid for
as provided in Item 404 SP, Reinforcing Steel.
Concrete
Class
shall
be
measured
per
Cubic
Meter
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 168
Grout for dowels shall not be measured for direct payment and is
considered incidental to other various related item
SPL F16.5
Basis of Payment
Description
SPL
SPL
SPL
SPL
SPL
F16(1)
F16(2)
F16(3)
F16(4)
F16(5)
SPL F17
SPL F17.1
Description
Unit of Measurement
Cubic Meter
Kilogram
Linear Meter
Lump Sum
Each
This item shall conist of furnishing and installing steel shoe bumpers
for
the
girders
conforming to the alignment, grades, design, dimension and details as
shown
on
the
Drawings.
SPL F17.2
Material Requirements
Method of Measurement
of
IX - 169
shoe
Basis of Payment
Description
SPL F17
Unit of Measurement
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
Set
of
PART G
IX - 170
SPECIAL PROVSIONS
ITEM 500 SP
500.1 Description
Add the following after the last paragraph.
This shall also include the provision of Pipe Sleeves in accordance with
the line, grades and location as shown in the drawing or as instructed by
the Engineer.
500.2
Material Requirements
comply
with
the
Construction Requirements
General
station
type of drainage structure (RCPC, RCBC, other)
size
whether to be extended, replaced, or newly constructed
headwalls/wingwalls
Technical
Specifications:
Rehabilitation/Construction
of
500.3.2
IX - 171
Bedding
Delete the second sentence of the first paragraph and substitute with the following:
Unless shown or directed otherwise, bedding for pipe culverts shall be Class B
bedding.
500.3.6
Backfilling
Delete the second sentence of the third paragraph and substitute with the
following:
The width of the backfill on each side of the conduit for the portion above
the
top
of
the
trench shall be equal to 3 times the pipe diameter or 3 meters whichever is
greater.
Add the following paragraph;
When damaged sections of existing reinforced concrete pipe culvert are
to
be
replaced,
the Contractor shall first remove the fill material covering the section to
be
replaced;
then the damaged section shall be removed and disposed. Bedding shall
be
prepared
and compacted in accordance with the provisions of Section 500.3.2,
Bedding.
The
new
pipe section shall be placed and the joint with the adjoining existing pipe
shall
be
sealed
with cement mortar. Backfilling shall be made in accordance with the
provisions
of
Section 500.3.6, Bedding.
Compaction equipment or methods that may cause excessive
displacement or may cause damage to structures shall not be used.
500.4
Method of Measurement
Delete Section 500.4 in its entirety and replace with the following:
Reinforced concrete pipe culvert sizes and classes are specified on the
drawings shall be measured per Linear Meter of pipe of the several
classes and sizes, measured along the pipe complete in place as and
accepted by the Engineer.
500.5 Basis of Payment
Add the following:
The quantities, measured as provided in Section 500.4, Method of
Measurement, shall be paid at the contract price per unit of measurement of
each of the particular pay items listed below, that is shown in the Bill of
of
for
all
the
paid
IX - 172
Payment for pipe sleeves shall be full compensation for furnishing and
installation of pipe sleeves including encasement and end structure and
all labour, equipment, tools and incidentals necessary to complete the work.
Payment shall be made under the following Items:
Pay Item
Unit
Description
Measurement
Linear Meter
Linear Meter
Linear Meter
Linear Meter
Linear Meter
Pipe Sleeves
ITEM 501 SP
501.1
of
Underdrains
Description
Delete this Subsection in its entirety and replace with the following:
This Item shall consist of constructing underdrains, using slotted
Polyvinyl Chloride (PVC) pipe and rounded or crushed aggregate for filter
materials, Non-woven geotextile, underdrain pipe outlets, and blind drains
using aggregate material in accordance with this specification and in
conformity with the lines and grades as shown in the drawings or as
directed by the Engineer.
501.2
Material Requirements
Technical
Specifications:
Rehabilitation/Construction
of
IX - 173
and
MIN VALUE
REQT
TEST
METHOD
Vicat Softening
77
76 min
ISO 2507
Temp (C min)
5 max
ISO 2505
40
40 max
ISO 2508
PROPERTIES
Longitudinal
Reversion (% max)
Water Absorption(g/m2 max)
Resistance to Acetone Passed
Resistance to
Acid Passed
Sulfuric
No
delamination/
Disintegration
Max Wt Inc
gm
Max Wt Dec
gm
ISO 3472
0.316
ISO 3473
0.013
Passed
40 min
ASTM D 2729
Resistance
to
External
Blows (TIR max)
10%
10% max
ISO 3127
39.9
Max Tensile
ISO 3504
42.2 min
Strength (MPa)
Max Elongation
501.2.2
80+
80 min
Non-woven Geotextile
Polyester or Polypropelene
Mechanically or Thermally bonded
Non-woven and needle punched
Effective Opening Size
5.
100%
110
microns
(max)
0.60 mm (min.)
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
6.
7.
IX - 174
200g/sq.m.
tensile
Strength,
12 - 13 KN/m
8.
650 n (min)
1900 - 2100 N
80 I/sq.m./sec or
0.06 cm/sec
50% (min)
Pipe Installation
Method of Measurement
Delete this subsection in its entirety and replace with the following:
Under-drains shall be measured per Linear Meter for pipe of the
type and size specified which includes non-woven geotextile, required
as shown on the drawings or as directed by the Engineer.
Blind drain shall be measured by the Linear Meter which includes
excavation and required backfill materials.
Granular Backfill Filter Materials for Under-drains shall be measured per
cubic meter complete in place. Cross-sectional measurements shall not
exceed the net dimensions shown on the drawings or as directed by the
Engineer.
Excavation for under-drain pipe will be measured and paid for as provided in
Item 103, Structure Excavation.
501.5
Basis of Payment
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 175
Delete this section in its entirety and replace with the following:
The accepted quantities measured as specified in Method of Measurement
shall
be
paid
for at the Contract unit price at the Pay Item listed below that is
included
in
the
Bill
of
Quantities.
Payment shall be full compensation for furnishing
Granular Backfill including all labour, equipment, tools
necessary to complete the work under Item 501(1).
and installing
and incidentals
and
paid
for
as
Description
Underdrain 150 dia. Perforated
Pipe
Granular Backfill Filter Materials
for Underdrains
ITEM 502 SP
502.1
Unit of Measurement
Linear Meter
Cubic Meter
Description
Method of Measurement
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 176
Basis of Payment
Delete this Section in its entirety and replace with the following:
The accepted RCPC and RCBC headwall structures, as provided in Section
502.4, Method of Measurement of the Pay Items in Bill of Quantities,
shall be paid for at the Contract unit prices, which shall constitute full
compensation for furnishing and placing all materials complete in
place including all labour, equipment, tools and incidentals necessary
to complete the item.
Excavation and backfill will be measured and paid for under Item 103
SP, Structure Excavation.
Payment shall be made under the following Items:
Pay Item
Description
405(1)b
404(40)
407(1)
103(1)a
Excavation
Cubic Meter
Kilogram
Cubic Meter
Cubic Meter
ITEM 504 SP
504.3
Unit of Measurement
Construction Requirements
Basis of Payment
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
Pay Item
Description
504(3)a
504(3)b
ITEM 505 SP
IX - 177
Unit
of
Measurement
Linear Meter
Linear Meter
505.2
Material Requirements
505.2.1
Stones
Basis of Payment
Description
505(5)
ITEM 506 SP
Unit of Measurement
Cubic Meter
Stone Masonry
506.2
Material Requirements
506.2.1
Stone
Delete the first sentence of the second paragraph and substitute with the following:
Sizes and Shape - Boulders shall range in size from 250 mm to 350
mm in its longest dimension with roughly similar blunted ends.
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 178
SUPPLEMENTAL SPECIFICATIONS
SPL G1
SPL G1.1
Description
The slope remediation measures covered under this item are classified as follows;
1. Geogrid Soil Reinforcement, Drainage Blanket
2. Trimming, Coconet and Vegetative Cover on Slope
3. Reinforced Concrete Retaining Wall, Tie Back Anchor, Rockbolts and Reno
Mattress
4. Micropiles with Reinforced Concrete Cap, Gabions, Drainage Blanket
and
Geogrid
Reinforced Soil on Slope
5. Geogrid Soil Reinforcement, Gabions, Coconet and Vegetative Cover on Slope
6. Trimming, Turf Reinforcement Matting and Catchment Barrier
7. Wire Mesh, Matting and Catchment Barrier
8. Gabions and Reno Matteress
9. Reno Mattress, Riprap Class A
10. Ground Anchor with Pre-Cast Concrete Thrust Block
11. Reinforced Concrete Retaining Wall Matting
12. Trimming, Rockbolts
13. Micropiles with Reinforced Concrete Pile Cap and Gabions
14. Trimming Rocknails, Wire Mesh and Rockfall Barrier
15. Trimming, Wire Mesh, Matting and Catchment Barrier
16. Geogrid Soil Reinforcement, Erosion Control Fabric
SPL G1.3
Material Requirements
The
different
slope
remediation
measures
shall
meet
the
following material requirements:
1. Geotextile Fabric: Shall have a tensile strength of 11kN/m
2. Gabions: Shall conform to the requirements of Item 511, Gaboins and
Mattresses.
3. Coconet: Shall conform to the requirements of Item 518 SP Coconet
Bio-Engineering
Solutions
4. Erosion Control Fabric
5. Jute Bags : Coco Sack or equivalent
6. Micropiles: Shall conform to the requirements of Item SPL G3,
Micropiling,
Item
405
SP, Structural Concrete, Item 404 SP, Reinforcing Steel
7. Geogrid Reinforcement: Shall have a tensile strength of 840kN/m
8. Turf Reinforcement Matting: Shall be high strength erosion control
matting and shall
conform to the requirements of Item SPL G2, Composite Turf
Reinforcement
Matting.
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 179
requirements: Bar for expansion shell type bolts ASTM A 306 Grade
80, plain
Bar
for
bolts
resin
type
Expansion
shell
ASTM
615
Grade
80,
Bearing
plate
B ASTM A 563
Nut
ASTM A 220
Washer
After fabrication, bolts have the following mechanical properties:
Min. yield load
15,000 kg
of
IX - 180
16. Soil Nails: Shall conform to the requirements of Item SPL G5, Soil Nailing
17. Gravel Fill: Shall conform to the requirements of Item 200 SP, Aggregate
Subbase
18. Native Fill: Shall conform to the requirement of Item 104 SP, Embankment
19. Fertile Soil: Shall conform to the requirement of Item 608, Top Soil
20. Compacted Fill: Shall conform to the requirements of Item 104 SP,
Embankment
21. Stone Masonry: Shall meet the requirements of Item 506 SP, Stone Masonry
22. Weepholes: Shall be PVC Sch. 40
23. Rockfall Barrier: The cable net and wiremesh system and all
hardware shall be
protected from corrosion, Structural steel components, including
cable anchor,
bolts, post foundation bolts, detachable base plates, clamps and
clips, shall be
galvanized.
Cable net to be used in the installation shall be galvanized
coated with polyvinyl chloride.
Wiremesh fabric to be used in the installation shall be zinc
coated and polyvinyl chloride coated.
Post for net supporting shall be painted with one
protective primer and with one additional coat of paint.
26. Tieback Anchor: Shall
SPL G1.4
coat
of
Construction Requirements
Trimming
slope where needed to effect required H:V ratio. Shear
(500mm vertical and varied horizontal slope trimmings) may
be provided (but not necessary) for increased contact between
of
IX - 181
fill
material
then
wrap
around
SPL G1.5
Method of Measurement
SPL G1.6
Basis of Payment
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 182
Description
Unit of
Measurement
SPL
SPL
SPL
SPL
G1(1)
G1(2)
G1(3)
G1(4)
Stone Masonry
Gabions
Mattress
Coconets
Cubic
Cubic
Cubic
Square
SPL
SPL
SPL
SPL
SPL
SPL
SPL
SPL
SPL
SPL
SPL
SPL
SPL
SPL
SPL
SPL
G1(5)
G1(6)
G1(7)
G1(8)
G1(9)
G1(10)
G1(11)
G1(12)
G1(13)
G1(14)
G1(15)
G1(16)
G1(17)
G1(18)
G1(19)
G1(20)
Cubic Meter
Square Meter
Each
Square Meter
Linear meter
Liner Meter
Cubic Meter
Cubic Meter
Square Meter
Cubic Meter
Square Meter
Linear Meter
Kilogram
Cubic Meter
Linear Meter
Linear Meter
SPL G2
SPL G2.1
General
The
work
Meter
Meter
Meter
Meter
of
IX - 183
which
The
Requirements
Black in color;
Minimum mat thickness of 13mm, measured under ASTM D1777;
Minimum tensile strength of 1,370 x 790 N/M measured under ASTM D 1682;
Maximum elongation of 75 by 75 percent measured under ASTM D 1682;
Minimum calculated porosity of 90 percent;
Resiliency of 80 percent, measured under ASTM D 1777; and
Ultraviolet stability, measured under ASTM D 4355.
SPL G2.3
Construciton Requirements
Prepare fertilize and seed the erosion control blanket area before placing
the blanket. Handle and place it following the manufacturers
recommendations.
If recommendations are not provided, install as
follows.
1. In ditches, unroll the blanket downstream and lap 105mm over
the
adjoining
blanket. Bury the edges to prevent water and wind undercutting.
2. On slopes, the blanket may be unrolled horizontally or vertically to
Method of Measurement
Retention
of
IX - 184
Engineer.
SPL G2.5
Basis of Payment
Description
SPL G2
SPL G3
Micropiling
SPL G3.1
General
Unit of Measurement
Square Meter
on
the
The
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 185
2. Tolerances Position
The pile heads shall be positioned as shown on the Drawings within
a maximum deviation of 40mm in either direction from correct centre
point. Vertically For bored cast-in-situ piles, the maximum permitted
deviation of the finished pile from the vertical at any level is 1 in
150. The Contractor shall demonstrate to the satisfaction of Engineer
the pile vertically is within the allowable tolerance. Should piles
be installed outside these tolerances affecting the design and
appearance of the structure, the Contractor shall propose and carry
out immediate remedial measure to the approval of the Engineer.
3. Person in Charge
The piling work is to be carried out by full time operators and
supervisory staff who must be experienced in the installation of the
proposed type of piles. The Contractor shall submit to the Engineer for
approval, written evidence to show that the persons who will be
engaged in the works have had such experience.
4. Piling Equipment and Accessories
The equipment and accessories must be capable of safely, speedily
and
efficiently
installing piles to the design requirements at the project site.
Sufficient
units
of
equipment and accessories must be provided to keep to the
agreed
construction
schedule.
5. Scope of Work
The contract comprises the provision of all
tools, plant etc necessary for the following work:
labor,
materials,
the
piles
to cut
of
off
levels
specified
the
and
Material Requirements
Reinforcement
The type of reinforcement to be used, the diameter and/or thickness,
grade, yield strength and stress shall be as specified or as shown on the
Drawings.
2. Grout
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 186
Site
and
Adjacent
soil
for
the
the
to
Site Visit
The
Contractor shall visit the site to acquaint himself with the site
conditions
and
no
claims for inadequate information regarding site conditions will be
entertained
at
a
later date. The system or systems put forward by the Contractor shall be
well
known.
The adequacy of any system and its approval shall be at the discretion of the
Engineer
Underground Services And Adjacent Property
The Contractor shall take care to ensure the safety of underground
services and adjacent properties during the installation of micropiles. The
contractor will be liable lo any claims of damage to the piling operations.
SPL G3.3
Drilling Operations
1.
Diameter of Piles
The diameter of piles shall not he less than the specified/designed
diameter at any level throughout its length.
2.
Drilling
The Contractor shall submit to the Engineer details of drilling
equipment and drilling procedure for approval before commencement
of works. Drilling operations shall be earned out in accordance with
the relevant requirements as follows:
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 187
Execution
Phases
Phase
1-
Drilling
The drilling is performed by rotation with direct circulation of the
drilling fluid. Phase 2 - Annular Grouting
At completion of drilling, a single packer is lowered to the bottom of the
drill string- reinforcing steel pipe, in order to inject from the bottom the
cement grout that will form the annular around the reinforcing steel pipe.
The purpose of this annular grout is to provide sufficient cover for the
reinforcing steel pipe, and to permit the subsequent pressure grouting of
each valve.
The bottom non-return valve, positioned at the base of the drag bit
prevents the flowback of the annular grout, inside the string-reinforcing
steel pipe.
Phase 3 - Active Bond Grouting
After setting of the annular grout has taken place, the pressure grouting
of each valve is performed by isolating each valve with a double
packer. Sufficient grout pressure is applied in order to break the annular
grout in correspondence with the valve, and to permit the injected mixture
to penetrate into the surrounding soil.
Should the grout absorption be very high, the grouting of each valve can
be repeated at later dates until the refusal pressure, defined at the design
stage have been reached.
After grouting at the active bond length is completed the inner part of
the reinforcing steel pipe is filled with the same grout mixture utilized for the
bond grouting.
c) Rock Coring
Rock coring shall means coring of sound bedrock. Coring of rock other
than two items specified below shall not be considered as coring in rock,
and will only be considered as boring in soil.
(i)
Rock
length
(ii)
roof
socket
Cavity
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 188
and
SPL G3.4
SPL G3.4.1
Grouting Operations
Mixing and Placing Grout
The Contractor shall provide details of the method and equipment used in
grout
mixing.
Further information such as grouting pressure, grouting procedure, grouting
equipment
and technique employed in grouting underwater shall also be furnished
for
approval.
Grout shall be mixed on Site and shall be free from segregation,
clumping
and
bleeding.
Grout shall be pumped into its final position in one continuous operation
as
soon
as
possible and in no case more than half an hour after mixing. Micropile
shall
be
grouted
in one continuous process. If there is significant loss of grout, the
Contractor
may
choose to carry out pre-grouting in stages as necessary to prevent
further
loss
of
grout
for the construction of micropile. Method statement of pre-grouting
including
details
of
equipment, materials and procedures have to be reviewed and
approved
by
the
Engineer. If after the process of pre-grouting and re-drilling of the hole is
required.
The
Contractor has to bear the cost and time of the pre-grouting and re-drilling.
SPL G3.4.2
Grout Falls
The lost of flushing mediums of either water or drilling mud drilling will
demonstrate potential excessive grout loss or falls. Depending on its
seriousness, the Contractor can decide to carry out a water tightness test
to decide whether pregrouting is required. The cost and time of the test
will be borne by the Contractor. Pregrouting an re-drilling shall be earned out
if results of the test shown that leakage exceeds 5L/min at an excess head
of 0.1 Mpa, measured over a period of 10 minutes.
SPL G3.5
SPL G3.5.1
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 189
Standards
All materials shall be of the best quality and new. All piling work shall
be executed in accordance with the approved designs prepared by the
Contractor and to the approval of the Engineer.
1. Standard Load Tests
Load test of two (2) times the working loads shall be carried out on
piles designated by the Engineers. The number and location of test
piles shall be at the discretion of the Engineer. The Contractor shall
submit a detailed proposal of the load tests to the Engineer and shall
obtain his approval in writing before carrying them out. On
completion of the test, the Contractor shall submit to the
Engineer the results including graphs showing load and settlement
versus time and settlement versus load. The test procedure shall be
as specified in Specification. Failure to standard load test shall be as
specified in Specification.
SPL G3.7
Test Report
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 190
SPL G3.9
Piling Records
As-Built Drawings
After completion of the piling the Contractor shall submit as-built drawings.
Those
drawings should include the following:
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 191
Method of Measurement
Basis of Payment
The Contract Unit Price for Micropiles shall include the Standard load
test, drilling, furnishing, and placing the reinforcing steel and casing,
grouting, and pile top attachments. The Contractor is also responsible
for estimating the grout take. There will be no extra payment for grout
overruns.
Payment for the work items listed below shall be full compensation for
furnishing and installing
all materials, including all labour, equipment,
tools and incidentals necessary to complete the work under this Item.
Payment shall be made under the following Item:
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
Item Number
Description
SPL G3
SPL G4
SPL G4.1
IX - 192
Unit of Measurement
Linear Meter
Ground Anchor
Description
Material Requirements
from
steel
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 193
SPL G4.3
Tendon Fabrication
The tendons can be either shop or field fabricated from prestressing steel
of
IX - 194
Total Anchor Length: The total anchor length shall not be less than that
indicated on the Contract Drawings.
Anchorage and Trumpet: Nonrestressable anchorage devices can be used
except where indicated on the Contract Drawings.
Restressable anchorage shall be provided on those ground anchors
designated
as
restressable on the Contract Drawings. The post-tensioning supplier
shall
provide
a
restressable anchorage compatible with the post-tensioning system
provided.
The
supplier shall also provide written recommendations concerning the
restressing
of
the
tendons.
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 195
The trumpet shall be welded to the bearing plate. The trumpet shall
have
an
inside
diameter equal to or larger than the hole in the bearing plate. The trumpet
shall
be
long
enough to accommodate movements of the structure during testing and
stressing.
SPL G4.4
Installation
be
drilled
in
a
location that requires the tendon to be bent in order to enable the
bearing
plate
to
be
connected to the supported structure. At the point of entry the ground
anchor
shall
be
0
installed within plus/minus three degrees (3 ) of the inclination from
the
horizontal
shown in the Contract Drawings. At the point of entry the horizontal angle
made
by
the
ground anchor and the structure shall be within plus/minus three degrees
(30)
of
a
line
drawn perpendicular to the plane of the structure unless otherwise
shown
on
the
Contract Drawings. The ground anchors shall not extend beyond the
right-of-way
or
easement limits shown on the Contract Drawings.
Tendon Insertion: The tendon shall be inserted into the drill hole to the
desired
depth
without difficulty. When the tendon cannot be completely inserted, the
Contractor shall
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 196
remove the tendon from the drill hole and clean or redrill the hole to
permit insertion. Partially inserted tendons shall nor be driven or forced into
the hole.
Grouting: The Contractor shall use a neat cement grout or a sand-
cement grout. The cement shall not contain lumps or other indications of
hydration. Admixtures, if used, shall be mixed in accordance with the
manufacturers recommendations.
The grouting equipment shall produce a grout free of lumps and
undispersed cement. A positive displacement grout pump shall be used.
The pump shall be equipped with a pressure gauge to monitor grout
pressures. The pressure gauge shall be capable of measuring pressures
of at least 150 psi or twice the actual grout pressures used by the
Contractor whichever is greater. The grouting equipment shall be sized to
enable the grout to be pumped in one continuous operation. The
mixer should be capable of continuously agitating the grout.
The grout shall be injected from the lowest point of the drill hole. The
grout maybe pumped through grout tubes, casing, hollow-stem-augers or drill
rods. The grout can be placed before or after insertion of the tendon. The
quantity of the grout and the grout pressures shall be recorded. The
grout pressures and grout takes shall be controlled to prevent excessive
heave or fracturing.
Except where indicated below, the grout above the top of the bond length
may
be
placed
at the same time as the bond length grout but it shall not be placed under
pressure.
The
grout at the top of the drill hole shall not contact the back of the structure
or
the
bottom
of the trumpet.
If the ground anchor is installed in a fine-grained soil using drill holes
larger
than
150mm in diameter, then the grout above the top of the bond length
shall
be
placed
after the ground anchor has been tested and stressed. The Engineer
will
allow
the
Contractor to grout the entire drill hole at the same time if the
Contractor
can
demonstrate that his particular ground anchor system does not
derive
a
significant
portion of its load-carrying capacity from the soil above the bond length
portion
of
the
ground anchor.
Upon completion of grouting, the grout tube may remain in the hole but it
shall be filled with grout.
After grouting, the tendons shall not be loaded for a minimum of three (3) days.
Installation
of
Trumpet and
surrounding
Anchorage:
The
corrosion
the
protection
unbonded length of the tendon shall extend up beyond the bottom seal of
the
trumpet.
If
the protection does not extend beyond the seal or sufficiently far
enough
into
the
trumpet, the Contractor shall extend the corrosion protection to prevent
contact.
The
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
the
and
IX - 197
Contractor
shall
trim
the
corrosion
The bearing plate and anchor head shall be placed so the axis of
the tendon is perpendicular to the bearing plate within plus/minus three
degrees (30) and the axis of the tendon shall pass through the center of
the bearing plate.
The trumpet shall be completely filled with corrosion inhibiting
grease or grout. Trumpet grease can be placed any time during
construction. Trumpet grout shall be placed after the ground anchor
has been tested and stressed. The Contractor shall demonstrate to
the Engineer that the procedures selected by the Contractor for
placement of either grease or grout will produce a completely filled
trumpet.
All
Each ground anchor shall be tested. No load greater than ten percent of
the design load can be applied to the ground anchor prior to testing.
The maximum test load shall not exceed 80 percent of the minimum
specified ultimate tensile strength of the tendon. The test load shall be
simultaneously applied to the entire tendon. Stressing of single
elements of multi-element tendons shall not be permitted.
The testing equipment shall consist of:
1. A dial gauge or vernier scale capable of measuring to 0.25 mm shall be
used
to
measure the ground anchor movement. The movement-measuring
device shall have a minimum travel equal to the theoretical elastic
elongation of the total anchor length at the maximum test load
and it shall have adequate travel so the ground anchor movement can
be measured without resetting the device.
2. A hydraulic jack and pump shall be used to apply the test load. The
jack and pressure
gauge shall be used to measure the applied load. The jack and
pressure gauge shall
be calibrated by an independent firm as a unit. The calibration
shall have been
performed within forty-five (45) working days of the date submitted.
Testing cannot
commence until the Engineer has approved the calibration. The
pressure gauge shall
be graduated in 100-psi increments or less. The ram travel of the jack hall
not be less
than the theoretical elastic elongation of the total anchor length at the
maximum test
load.
3. A calibrated reference pressure gauge shall also be kept at the site.
The
reference
gauge shall be calibrated with the test jack and pressure gauge.
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 198
Load
AL
0.25DL*
AL
0.25DL
0.50DL*
AL
0.25DL
0.50DL
0.75DL*
AL
Load
AL
0.25DL
0.50DL
0.75DL
1.00DL
1.20DL*
AL
0.25DL
0.50DL
0.75DL
0.25DL
0.50DL
0.75DL
1.00DL*
1.00DL
1.20DL
1.33DL*
Reduce to lock-off load
of
IX - 199
0.75DL
of
IX - 200
The creep test shall be made by incrementally loading and unloading the
ground
anchor
in accordance with the performance test schedule given above. At
the
end
of
each
loading cycle, the load shall be held constant for the observation period,
the
load
shall
be held constant for the observation period indicated in the creep test
schedule
below.
The times for reading and recording the ground anchor movement
during
each
observation period shall be 1 minute, 2, 3, 4, 5, 6, 10, 15, 20, 25, 39, 45,
60,
75,
90,
100,
120, 150, 180, 210, 240, 270 and 300 minutes as appropriate. Each
load-hold
period
shall start as soon
as the test load is applied. In a creep test, the
pressure
gauge
and
reference pressure gauge will be used to measure the applied load and
the
load
cell
will
be used to monitor small changes in load during a constant load-hold
period.
The
jack
shall be repumped as necessary in order to maintain a constant load.
The
exceed
2.0mm/log cycle of time; and
2. Total movement at the maximum test load exceeds 80 percent of
the
theoretical
elastic elongation of the unbonded length.
If the total movement of the ground anchors at the maximum test load does not
exceed
80 percent of the theoretical elastic elongation of the unbonded length,
the Contractor shall replace the ground anchor at no additional cost to the
Owner.
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 201
Method of Measurement
Basis of Payment
of
IX - 202
Description
SPL G4
Ground Anchor
SPL G5
Soil Nailing
SPL G5.1
Description
Unit of Measurement
Set
The work related to this item shall consist of furnishing, installing and
testing the soil nailing in accordance with details shown in the Drawings
and these Specifications or as directed by the Engineer.
The Contractor shall inspect the site, study soil investigation results and
design details before preparation and submission of the method statement
to
the
Engineer
for
prior approval (at least 7 days) before the
commencement of works.
The Contractor shall be fully responsible to provide all necessary and
suitable resources and materials to complete all the soil nails strictly
according to this specification. The Contractor shall install the trial or
preliminary soils nails and carry out the verification pull-out test at
locations selected by the Engineer.
SPL G5.2
SPL G5.2.1
General Requirements
Setting Out
Position
The maximum allowable deviation for drill hole entry point shall not
exceed 75 mm in any direction.
SPL G5.2.3
Alignment of Nail
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 203
Submittals
The Contractor shall keep records for each soil nail installation and shall
submit
one
signed copy to the Engineer not later than noon of the next working day
after
the
soil
nails have been installed. The record for each soil nail shall include soil
nail
reference
number, date/time of commencement and completion of drilling and
grouting,
names
of
supervisor and operators, plus the necessary drilling and grouting details,
etc.
Format and details of record and layout of nail shall be approved by the Engineer.
SPL G5.3
SPL G5.3.1
Material Requirements
Reinforcement
Reinforcement for soil nails shall be high yield steel reinforcing bars
threaded and hot- dip galvanized with minimum coat thickness of 85
microns or 610 gm per meter square surface and or the reinforcement
bars shall be pre-grouted as shown on drawings. The nail bars shall be
threaded at the ends for a sufficient length (minimum 150 mm long) to
facilitate fixing of galvanized washer, overlap locking washer and nut at
the exposed end and fixing of galvanized coupler at the other end, if
required.
The tensile strength and galvanized rebar quality of the coupled nail bar
shall be not less than 410 N/mm2 or specified on drawings.
Only soil nails of more than 12 m long shall have rebars spliced or
coupled.
The
tensile
strength of the coupler shall be capable to develop at least 95 % of the
tensile
strength
of the rebar as tested and certified by the manufacturer. Test certificates
from
reputable
laboratory or accredited laboratory approved by the Engineer to show
compliance
of
the specification shall be submitted to the Engineer for verification and
approval.
SPL G5.3.2
Cement Grout
MPa
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
through a 5 mm sieve to
attached with paddle agitator.
IX - 204
remove
lumps
into
storage
tank
If any of the above results falls below the acceptable limits, at least
one or 1 % of grouted working nails whichever is greater shall be
subject to pull-out test
at the Contractor own cost.SPL G6.3.3
Centralizers
Centralizers shall be tightly fixed to the rebar at the spacing as shown
on
the
drawings.
The centralizers shall be firm and as small as possible (not more than 50
%
of
the
nail
section) so blockage of grout flow is kept to a minimum. Centralizers
shall
be
fixed
inside and outside of the protective sheath, if applicable, and shall be spaced
at
not
more
than 2m. Centralizers shall be sized to position the rebar within 25 mm
of
the
center
of
the drill holes; sized to allow tremie pipe (about 30 mm diameter)
insertion
to
the
bottom of the drill hole.
SPL G5.3.4
The size, shape and length of the sheath to protect the rebar shall be as
shown on the drawings or as directed by the Engineer. The sheath shall
consist of HDPE (high density polyethylene) with a wall thickness not less
than 1.0 mm and shall provide at least 5 mm of grout cover over the
nail rebar within the sheath. The thickness of grout between the HDPE
sheath and the sides of drill hole shall be not less than 25 mm.
SPL G5.3.5
be
cause
for
rejection. Rebars shall be protected from dirt, rust and other
deleterious
substances
prior to installation. Heavy corrosion or pitting of rebars shall be cause
for
rejection.
Anchorage end of rebars to which bearing plate and nuts will be
attached
shall
be
protected by some protective wrap during handling, installation, grouting and
guniting.
Pregrouted rebars in HDPE sheaths shall not be moved or transported
until
the
grout
has reached sufficient strength to resist damage during handling. The
pregrouted
rebars
shall be handled with care and with sufficient supports to prevent
large deflections,
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 205
Drilling
The Contractor shall deploy suitable drilling machine and tools plus
skilled operator and supervisor that have adequate capacity and
experience to produce the drill hole according to the size, length and
accuracy as shown in the drawings and as specified in this specification.
Unless
for
Inserting Reinforcement
After inserting about 75 % of the total design length, the rebar shall be
withdrawn to check the conditions of the centralizers and contamination of
rebar. Such pull-out check shall be carried out on at least 1 % of the
nails especially for those drill holes that have been left for more than 2
hours after completion of drilling. If collapse of drill hole is suspected,
redrilling and flushing shall be carried out as directed by Engineer.
Damaged centralizers shall be replaced immediately and rechecked.
SPL G5.3.8
Grouting
Grout
of
IX - 206
the
All the disturbed, loose or soft soil around nail head shall be removed
and replaced by non-shrink mortar of grade 30 strength or approved
equivalent by the Engineer.
Nail head with steel plate shall be in a plane normal to the nail axis
clamped down with galvanized nut and washers to a minimum clamping
force of 5 kN or as shown in the Drawings, using a calibrated torque
wrench. Clamping shall be carried out with a thin layer (< 25 mm) of
fresh non shrink mortar (grade 30) behind the steel plate to ensure
proper seating. Nail head construction shall only be carried out after the
grout and the mortar have reached at least 7-days strength (> 20 MPa).
SPL G5.3.10 Pull-out Tests
The
Purpose
of
IX - 207
from sunlight and rain. The complete jacking system including hydraulic
jack,
pump,
and pressure gauge should be calibrated as a single unit before use to an
accuracy
of
not
less than 5 % of the applied load. The center and bearing plates of the
jack
system
shall
be properly arranged so that the test nail will not carry the weight
of
the
testing
equipment. The gauge used to measure the nail head movement shall be
aligned
parallel
with the axis of the nail and the support of the gauges shall be
independent
from
the
jack and the reaction frame. Load cell is important to maintain
constant
load
hold
during the creep test load hold increment. The jack and pressure gauges
shall
have
a
pressure range not exceeding twice the anticipated maximum test
pressure.
Jack
ram
travel shall be sufficient to allow the test to be done without resetting the
equipment.
At least 2 preliminary pull-out tests or verification or sacrificial tests up to
2.0 times the design pull-out resistance, Qd or as specified on
drawing shall be carried out for different soil/rock unit or for
different drilling/grouting method for each nailed slope/hill or as
specified and directed by the Engineer.
For the soil nails selected for pull-out test, the temporary unbonded
length
(Lu)
of
the
test nail shall be at least 1 m, i.e. the bonded length (Lb) of the soil nail
selected
for
pull-
out test shall be Lb = L - Lu, where L = total soil nail length. To prevent
collapse
of
the
unbonded drill hole during the test, a temporary GI pipe of about 1 m
long
near
the
slope surface shall be installed. In case the drill hole is fully grouted, a GI
pipe
of
about
at least 600 mm long and slightly larger than the grouted hole shall be
driven
to
ensure
the reaction force is not transmitting to the grouted hole near the slope
surface.
Lb
shall
be at least 3 m.
Table G5.3.11 - loading schedule for verification test
Load
(5%
0.25
0.50
0.75
1.00
1.25
1.50
1.75
1 minutes
10 minutes
10 minutes
10 minutes
10 minutes
10 minutes
60 minutes
10 minutes
10 minutes
DTL
= Design Test Load (kN) = Lb
x Qd
Lb = Pull-out test bonded length.
Lb = design nail length - unbonded
length
Lb shall not exceed 0.9fy As / 2.0 Qd, where fy and As are yield stress and area of
rebar
respectively. Qd = /a x pd
= Design allowable pull-out resistance (kN/m) specified in the
Drawing or by the Designer. /a = design allowable bond stress (kN/m2), d
= diameter of nail in m.
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 208
The alignment load shall be the minimum load required to align the
alignment
load
has
been applied. At least 2 calibrated dial gauges of 0.025 mm accuracy
shall
be
used
to
measure nail head movement. Each load increment shall be held for at
least
10
minutes.
Nail movement at creep test (1.50 DTL) shall be taken at 1, 2, 3, 5, 6, 10,
20, 30, 50 and
60 minutes. The load during the creep test shall be maintained
within 2 % of the intended load by use of a calibrated load cell.
For working pull-out tests or proof tests, the testing procedure including
creep test is similar to verification test except that the max test load (MTL) =
1.5 x DTL.
A pull-out test is deemed satisfactory
following
criteria
met :
1. For verification tests, a total creep movement less than 2 mm between the 6
and 60
minute readings measured during the creep test and the creep
rate is linear or decreasing throughout the creep test load hold
period.
2. For proof tests, total creep movement less than 1 mm is measured
between the 1
and 10 minute readings or creep movement less than 2 mm during
the 60 minute
readings and the creep rate is linear or decreasing throughout the
creep test load
hold period.
3. The total measured movement at the maximum test load (MTL)
exceeds 80% of
theoretical elastic elongation (le) of the test nail unbounded length (le
= 0.8P (Lu)
(106)/ As E, where P = max applied load (kN), Lu = length from the
back of nail to
jack connection to the top of the bond (m), As = rebar cross-sectional
area (mm2)
and E = rebar's modulus =200,000 MPa).
4. A pull-out failure does not occur at the maximum test load. Pull-out
failure is defined
as the load at which attempts to further increase the test load
simply result in
continued pull-out movement of the test nail.
The Contractor shall submit the results of pull-out tests to the
Engineer
for
final interpretation
and
necessary
design
review
immediately after the test. Full formal report of pull-out test including
all plotting, method statement, test length, photos, test certificates, etc.
shall be submitted to the Engineer within 1 week after the test.
For
verification
test
nails,
the
Engineer
shall
evaluate
the
results and
Method of Measurement
Soil Nailing
accordance
Engineer.
SPL G5.5
shall
with
Basis of Payment
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 209
shall
Item.
Payment shall be made under the following Item:
Pay Item
SPL G5
Description
Unit of Measurement
Soil Nailing
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
Linear Meter
of
PART H
IX - 210
MISCELLANEOUS STRUCTURES
SPECIAL PROVISIONS
ITEM 601 SP
601.5
Sidewalk
Basis of Payment
Description
601(1)a
ITEM 602 SP
602.5
Unit of Measure
Square Meter
Basis of Payment
Description
602(2)
602(3)
ITEM 603 SP
Guardrail
Unit of Measurement
Each
Each
Description
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
603.4
IX - 211
Basis of Payment
Delete the table under the second paragraph and replace with the following:
Payment will be made under the following Items:
Pay Item
Description
603(3)a
603(3)b
603(5)
ITEM 612 SP
Form)
612.1
Unit of Measurement
Linear Meter
Each
Linear Meter
Description
yellow
Thermoplastic
Material Requirements
the
following
at
the
end
of
this
Subsection Characteristics:
1. Appearance in Container - in powder or blocks.
Condition
of
10
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
degrees
IX - 212
tolerance
of
9.5
White
Yellow
Binder, %
Glass Bead, %
Titanium Dioxide, %
Calcium Carbonate and
Inert Filler, %
15.0 min.
15.0 min.
8.0 min.
15.0 min.
15.0 min.
-
55.0-75.0**
Basis of Payment
Description
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
Unit of Measurement
of
612(1)
612(2)
IX - 213
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
Square Meter
Square Meter
of
IX - 214
SUPPLEMENTAL SPECIFICATIONS
SPL H1
Landscaping
SPL H1.1
Description
The work related to this item shall consist of furnishing landscaping, sod,
plants and concrete marker with brass plate as shown in the drawings as
required by the Engineer. This also includes the furnishing and
planting deciduous shade, flowering trees, ornamental plants in pots
and in the arrangements approved by the Engineer.
SPL H1.2
Material Requirements
Construction Requirements
Maintenance
Method of Measurement
Basis of Payment
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
IX - 215
of
IX - 216
Description
SPL H1
Landscaping
SPL H2
Seeding
SPL H2.1
Description
Unit of Measurement
Lump Sum
The work related to this item shall consist of seeding disturbed areas
along
the
roadway
shoulders and/or embankments as indicated on the drawings or as
directed
by
the
Engineer.
SPL H2.2
Material Requirements
Seed
Mixture:
Shall
be
fast
growing
native
legominous
creeping/twining grass cover free from weeds and invasive species.
Fertilizer: Commercial grade 10-10-10 fertilizer
Ground Limestone: Ground limestone shall contain not less than 85
percent of calcium and magnesium caronates and shall be of such
fineness that 100 percent shall pass through a 2.00 mm sieve and not
less than 35 percent through a 0.150 mm sieve.
SPL H2.3
Preparation of Topsoil
foreign materials,
roots.
contaminated soil.
weeds
and
undesirable
Remove
plants
and
in
accordance
with
the
1. Apply
fertilizer
Manufacturers
recommendations.
and
limestone
use of a
approved
Engineer.
hydroseeder
with
hydromulch
by
may
be
permitted
the
as
SPL H2.5
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 217
Method of Measurement
Basis of Payment
Description
SPL H2
Seeding
SPL H3
SPL H3.1
Description
Unit of Measurement
Square Meter
The work related to this item shall consist of furnishing and installing
the electrical system as required by the Drawings and in accordance
with these Specifications. The work shall include the following:
1.
Electrical services including all conduits, junction boxes, fittings, and
wiring
from
the
Local Electric Cooperative supply and meter to the lighting panel
boards.
Lighting and contactor panel
Complete street lighting
luminaires Steel poles and
foundations
Timer Switch
Grounding system
SPL H3.2
SPL H3.2.1
Material Requirements
General Material Requirements
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 218
SPL H3.2.2
the
Lighting
loadside
of
of
have
IX - 219
silver
Poles:
Provide steel poles designed for wind loading of 145 kilometers
per hour while supporting luminaires having effective projected areas
indicated. Poles shall be anchor- based type designed for use with
underground supply conductors.
Brackets and Supports:
NEMA SH 5 - Pole brackets shall be not less
than 50 mm steel secured to pole. Slip-fitter or pipe-threaded brackets may
be used, but brackets shall be coordinated to the luminaires provided,
and all brackets for use with one type of luminaire shall be
identical. Brackets for pole-mounted street lights shall correctly
position the luminaire not lower than the mounting height indicated.
Special mountings or brackets shall be as indicated and shall be of metal
which will not promote galvanic reaction with the luminaire head.
Anchor Base Assemblies: Anchor bolts
yield strength of 345 MPa; the top
galvanized per ASTM A 153. Anchor
structural quality hot rolled carbon
strength of 248 MPa.
indicated otherwise.
Fluorescent Lamp Electronic Ballast:
The electronic
minimum meet the following characteristics.
ballast
1. Ballast
shall
as a
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 220
Lamp Holder: Lamp holder shall be UL listed and shall be rated 600 volts.
Housing shall be polycarbonate and shall have a temperature index of 115
degree C.
Enclosure: Fluorescent lighting fixture enclosure shall be 22 gauge sheet
steel,
formed,
screwed with machine or stove bolt and/or welded. Finish shall be two (2)
coat
primer,
and baked white acrylic paint. Knockouts for starters shall be provided if
required.
Diffuser:
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
SPL H3.2.4
IX - 221
Conduit
Outlet Bodies
Outlet
Type
THWN
conforming to UL 83. Type THWN wires and cables shall be suitable for
the type of
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 222
Tape
Pull Rope
Pull rope shall be plastic or flat pull line (bull line) having a minimum tensile
strength of 890 N (200 pounds).
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
SPL H3.2.9
IX - 223
Grounding Installation
Constuction Requirements
Codes and Regulations
All work shall be done in accordance with the requirements of the latest
edition of the PHILIPPINE
ELECTRICAL
CODE
and
the
NATIONAL
SAFETYCODE, with the applicable ordinances of the local government,
and with the requirements of the local power company that will
eventually furnish the service. Nothing contained herein or shown on the
Plans shall be construed as to conflict with the requirements of these
codes which are hereby made part of the work of the item.
SPL H3.3.2
Contractor Submittals
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 224
2. Street lightings, including light poles, bracket and slip fittings for
attachment
of
bracket to light poles.
3. Timer switch
4. Manufacturers Data. When data that described more than one type,
size, model, or
items is submitted, clearly mark the data to indicate which type, size,
model, or item
is being provided. Data shall be sufficient to show conformance
to specified
requirements.
a.
b.
c.
d.
e.
Luminaires
Poles and Brackets
Timer Switch
Ballast
Shop Drawings
Luminaires.
On completion the Contractor shall perform all required tests at his own
expense. The Contractor shall give the Engineer at least twenty-four (24)
hours notice of any test. The Engineer will be present for all tests.
The Contractor shall repair all defects and replace any part of the work
not meeting the requirements of the contract at no additional cost.
All apparatus, materials and labour required for making the tests shall be
supplied by the Contractor.
The Contractor shall furnish a guarantee covering all labour and
for a period of one year from the date of final acceptance of his
he shall agree to repair and make good at his expense any
defects which may develop during that time, if such defects shall
defective workmanship or materials.
SPL H3.3.4
Service Entrance
materials
work and
and all
arise from
The
of
IX - 225
run down the utility line and into the box. Electrical components shall be
mounted
to
the black panels or control panels with machine screw and wired as
shown
on
the
plans
or as directed. Forms for the footings shall not be removed until
the
concrete
has
hardened properly and not less than 24 hours after the concrete had
been placed.
SPL H3.3.5
Installations
surfaces
shall
be
terminated
with
control
boxes.
board
Conduit under Roadway: Installation shall avoid pocket in the conduit run.
All run shall be straight as possible and shall be installed in a neat
and workmanlike manner. Conduit under roadway shall be encased in
reinforced concrete.
Electrical
of
IX - 226
Contractor shall install electrical conductors and shall make all required
connections as shown on wiring diagrams to be furnished or as
directed by the Engineer. The conductors shall be installed so that
there will be no cuts or abrasions in the insulation or protective covering
of the conductor. No splices shall be made in conductors, except at
boxes, outlets or cabinets.
SPL H3.4
Method of Measurement
Basis of Payment
Description
Street Lighting
SPL H4
SPL H4.1
Description
Unit of Measurement
Each
The work related to this item shall consist of furnishing and installing
and
illuminating
project information signs of the types specified in accordance with these
Specifications
and to the detail and locations shown on the Drawings or as required by the
Engineer.
Contract information signs shall be the project signs prescribed
separately by Department of Public Works and Highways (DPWH) and
Commission on Audit (COA) for Government infrastructure projects, to
inform the public of implementation of the project and to advise the
road-users of on-going construction. COA should be consulted regarding
whether project cost should be displayed in some sensitive regions within
the Republic of the Philippines.
SPL H4.2
SPL H4.2.1
Material Requirements
Sign Panels
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 227
Hardware
All hardware shall be of the kind and size specified on the drawings or
as approved by the Engineer.
SPL H4.2.4
Paints
Paints for the background and legend shall be approved by the Engineer.
SPL H4.3
SPL H4.3.1
Contract
Construction Requirement
Location
be installed
at or
end
Project.
SPL H4.3.2
Erection of Posts
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
SPL H4.3.5
IX - 228
Illumination
Method of Measurement
The DPWH and COA project signs shall be measured per Each of the
specified sizes including their posts and illumination, complete in place
installed in accordance with the drawings, specifications and accepted by the
Engineer.
SPL H4.5
Basis of Payment
Description
SPL H4(a)
SPL H4(b)
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
Unit of Measurement
Each
Each
of
IX - 229
PART J
PROVISIONAL SUMS
SPL J1
SPL J1.1
Description
Method of Measurement
The work will be measured as established in the order authorizing the work.
SPL J1.3
Basis of Payment
Description
Unit of Measurement
Provisional Sum
SPL J2
SPL J2.1
Description
Method of Measurement
The work will be measured as established in the order authorizing the work.
SPL J2.3
Basis of Payment
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 230
Description
Removal and Relocation of Barangay
Markers
SPL J3
Provisional Sum
SPL J3.1
Description
Unit of Measurement
Provisional Sum
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
Pay Item
SPL J3
PART K
Description
Provisional Sum
IX - 231
Unit of Measurement
Provisional Sum
DAYWORKS
SPL K1
Dayworks
SPL K1.1
Description
This item shall consist of labor, materials, plant and equipment rates,
and
shall
be
subjected to the provisions of Clause 29 of the General Conditions of
Contract.
For minor or incidental works, the Engineer may, if in his opinion it is
necessary or desirable, instruct that a variation shall be executed on
a dayworks basis. These dayworks may include unforeseen works
necessary in the prosecution of the project, not captured in the detailed
engineering design and not described as specific items in the bill of
quantities, like:
Emergency works as a result of calamity such as landslide, flooding
and typhoons; Urgent works brought by road accidents which affect
the project;
Removal of temporary obstructions; and,
Other similar unforeseen works as determined by the Engineer.
The works shall then be valued in accordance with the Daywork
Schedule included in the Contract, plus a percentage to be entered by
the bidder representing contractors profit, overhead/contingencies, supervision
cost and other charges.
The following procedure shall then apply:
a. Before ordering goods for the works, the Contractor shall request
for
quotations
from at least 3 suppliers and submit the same to the Engineer.
b. Involves, vouchers and accounts or receipts shall be kept by the
Contractor
for
submission prior to payment.
SPL K1.2
The Contractor will be paid for dayworks carried out during the course of
the contract at the rates entered in the priced Bill of Quantities.
Daywork rates quoted for labor shall be the amounts payable, and shall include
allowances for complying with the labor law, for use and waste of hand
tools and for all ordinary non-mechanical plant including stagings,
scaffoldings, etc., where not erected especially for the execution of a
daywork item, use of electric light and all special
of
IX - 232
The rates of material used on dayworks shall include for delivery to the immediate
working area and for unloading. Should any material be required for use
on dayworks
that are not included in Section VIII, Bill of Quantities, the lowest current
net market
price shall apply, plus the cost of loading and unloading and 15%
allowance for
overhead and profit. Should the Engineer instruct that materials be
ordered from
outside the country, then the lowest current net manufacturers CIF price
shall apply,
plus the cost of customs and handling charges and transporting to the
immediate
working area and unloading and 15% allowance for overhead and profit.
All rates shall
include for adequately storing and additional handling costs and taxes if
applicable.
Plant and equipment shall include the wages of drivers, attendants and operators,
maintenance in proper working order at all times, attendance in starting up and
shutting down, all fuel and power, oils, greases and cleaning materials.
Replace and/or sharpening of tools and provision of tools, charges for
depreciation insurance, taxes and the like and all other ancillary items
including consumable stores.
Payment shall be made under the following Item:
Pay Item
K1
Description
Dayworks
Unit of Measurement
Provisionsal Sum
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 233
Appendix A
SUPPLEMENTAL
TESTING REQUIREMENTS
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
IX - 234
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
Item No.
102
103
Description
Excavation
Structure
Excavation
Item
1. Gradation
Test of Control
AASHTO T88
-OR- AASHTO T27
and AASHTO T11
2. Atterberg
Limits
AASHTO T89
AASHTO T90
3. CBR Test
AASHTO T193
4. Laboratory
Compaction
1. Gradation
AASHTO T99
2. Atterberg
Limits
3. CBR Test
104
Embankment
Materials
IX - 235
4. Laboratory
Compaction
1. Gradation
2. Atterberg
Limits
3. CBR Test
4. Laboratory
Compaction
5. Field Density
Frequency
Remarks
1 complete test per Test results must be
1500 cubic meter or submitted before
fraction thereof or excavated materials
every change in soil are incorporated into
properties.
the work as fill.
[1 complete test is
defined as
acceptable test
results for items 1
thru 4]
AASHTO T88
1 complete test per Test results will be
-OR- AASHTO T27 1500 cubic Meter or submitted before
and AASHTO T11
fraction thereof or excavated materials
every change in soil are incorporated into
AASHTO T89
properties.
the work as fill.
AASHTO T90
[1 complete test is
defined as test
AASHTO T193
results for items 1
thru 4]
AASHTO T99
AASHTO T88
1 complete test per Test results will be
-OR- AASHTO T27 1500 cubic Meter or submitted before
and AASHTO T11
fraction thereof or excavated materials
every change in soil are incorporated into
AASHTO T89
properties.
the work as fill.
AASHTO T90
[1 complete test is
defined as test
AASHTO T193
results for items 1
thru 4]
AASHTO T99
AASHTO T 191
Minimum of 3 per
every 500 sq.
meters of fraction
thereof per layer
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
A layer is considered
20cm of uncompacted
thickness. An
acceptable test is one
which meets the
stated
moisture
and compaction
requirements the
identified item no.
Item No.
Description
Item
Compacti
on
6. Shrinkage/
7. CBR Test
Swell
Factor
1. Gradation
105
Sub Grade
Preparatio
n
IX - 236
Test of Control
ASTM D4546
AASHTO T88
-OR- AASHTO T27
and AASHTO T11
AASHTO T89
2.
Atterberg
Limits
Frequency
AASHTO T90
AASHTO T193
1
complete test per
1500
cubic Meter or
fraction
thereof
or
every
change
in
soil
properties.
[1 complete test is defined
as test
results for items 1 thru 4]
3. CBR Test
4.
Laboratory
AASHTO T99
Compaction
Minimum
of
3
per
every
500
square
meters
or
fraction
thereof per layer
AASHTO T191
1
test per source or
for
every
1500
cubic
meters
or
fraction
thereof
5. Field Density
ASTM D4546
106
Aggregate
Subbase
Course
6. Shrinkage/
Swell
Factor
AASHTO T88
AASHTO T89
1. Gradation
AASHTO T90
2.
Atterberg
Limits
AASHTO T96
AASHTO T180
3. Abrasion
4.
Laboratory
202
Crushed
Aggregate
Base Course
AASHTO T193
Compaction
AASHTO T191
5. CBR Test
AASHTO T88
AASHTO T89
6. Field Density
AASHTO T90
1. Gradation
AASHTO T96
2.
Atterberg
Limits
3. Abrasion
AASHTO T104
ASTM D-5821
4. Soundness
5.
Fractured
Face
(one)
6.
Laboratory
AASHTO T180
AASHTO T193
Every
meter
thereof
1500
cubic
or
fraction
Remarks
1 test per
source or
for every
1500
cubic
meters or
fraction
thereof
Test
res
ults
will
be
sub
mitt
ed
bef
ore
exc
ava
ted
materials
are
incorporate
d into the
work as fill.
A
layer
is 20cm
of
uncomp
acted
thickness. An
acceptab
le
test
is
one
which
meets
the
stated
moistur
e
and
compac
tion
requi
reme
nts
the
identifi
ed
item
numb
er.
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of
of
of
Item No.
Description
Item
8.
Density
Tests
Aggregate
Surface
Course
300
Gravel
Surfacing
IX - 237
Test of Control
Field
AASHTO T-191
conformance to
project
specifications
minimum of 5
samples per lot.
Frequency
3 tests per every
500 square meters
or
fraction thereof
AASHTO T88
1. Gradation
2.
Atterberg
Limits
3. Abrasion
AASHTO
T89
AASHTO
T90
AASHTO T96
4. Soundness
5. CBR Test
6.
Fractured
Face
(one)
7.
Laboratory
Compaction
8. CBR Test
AASHTO
T104
AASHTO
Every
cubic
meter
fraction
thereof
1500
or
T193
ASTM D-5821
AASHTO T180
AASHTO T193
AASHTO T-191
Field
Acceptanc
e Testing
311
PCCP Overlay
1st
3
delivery
vehicles
and any time there
is
a question of being
1.
Slump of
Plastic Concrete
AASHTO
T119
AASHTO
T141
2. Air Entrainment
AASHTO
T152
AASHTO
T141
At the fabrication
of
the
flexural
strength
test specimens or
if
any question of
Remarks
For every layer 15 to
20 cm of compacted depth
based on
results
of
compaction
trials.
For
every
layer or 15
to 20cm of
compacted
depth
based on
results of
compactio
n trials.
1st 3
vehicles
should
meet
project
specifica
tions. If
the
concrete
slump
does
not
meet
spec
ificat
ions,
Proje
ct
Engi
neer
shall be
contact
ed and
shall
determin
e if
additiona
l samples
shall be
tested.
Project
Engin
eer
shall
deter
mine
if
paving
shall
progress
based on
consisten
cy of the
concrete
slump or
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
if additional
adjustments to the
mix
should
be
made
prior to proceeding
with paving
operations.
Prior to the start
of paving air
entrainment
shall
be tested in one of
the first 3 delivery
vehicles (in addition
to 5 other sampling
events
for
fabrication
of flexural strength
specimens).
of
Item No.
Description
Item
3. Temperature
4. Unit Weight
IX - 238
Test of Control
ASTM C 1064
AASHTO
T121
AASHTO
T141
Frequency
At the fabrication
of
flexural
strength
specimens.
5
samples per lot.
At
the
same
frequency
as
fabrication
of
flexural
strength
specimens.
5 samples per lot.
5. Flexural Strength
AASHTO T97
AASHTO T23
AASHTO
T141
Minimum of 5
samples
for
single
lot
6. Thickness
Determinatio
n
AASHTO T148
7. IRI
311, 405
Cement
Quality
Quality
1. Grading
311, 405
2. Wash Loss
3. Bulk Specific
Gravity
AASHTO M85
AASHTO T27
AASHTO T11
4. Absorption
AASHTO T84
Fine Aggregate 5.
Mortar
Strength source not yet
tested
6. Soundness
5
cores
for
every
kilometer
for
one
lane or 5 cores
for
every 500 m when
2
lanes
are
poured
concurrently.
AASHTO T84
AASHTO
7. Organic Impurities
T106M
8. Unit Weight
AASHTO T104
9. % Clay Lumps
AASHTO T21
10. % Shale
AASHTO T19
311, 405
Fine Aggregate
Quality
AASHTO T112
AASHTO T113
Every
cubic
meters
fraction
thereof
1,500
or
Remarks
Temperature should be monitored
throughout the delivery.
Unit
weight
should
be
determined
from
the same sample
obtained for strength specimens.
3
(minimum)
beam
2
specimens
broken
at
28
days
and one
hold
specime
n shall
be
consider
ed at
sample.
A lot
shall be
consider
ed to
for
definition of partial
lots]
be one
shifts
productio
n;
however
a new
lot
shall
begin
when
the
mix
design is
changed.
[See SPs
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
IRI shall be
determined
both
directions.
of
for
travel
Item No.
Description
Item
Previously
1. Grading
Tested and
Passed Sources 2. Wash Loss
IX - 239
Test of Control
AASHTO T27
Frequency
meters or fraction
thereof
Remarks
AASHTO T11
AASHTO T84
5. Mortar Strength
311, 405
Coarse
Aggregate
source not yet
tested
Quality
1. Grading
AASHTO T27
311, 405
3. Absorption
AASHTO T85
4. Abrasion
AASHTO T96
5. Soundness
AASHTO T104
6. Unit Weight
AASHTO T19
Coarse
Quality
Aggregate
1. Grading
AASHTO T27
Previously
Tested and
2. Bulk Specific GravityAASHTO T85
Passed Sources
3. Absorption
AASHTO T85
4. Abrasion
515
Mechanically
Stabilized
Earth Walls
1. Excavation
Elevation and
dimensions specified
Laboratory
2. Backfill
Compaction
Field Density
3. Wall Face
Line and grade
400
AASHTO T96
Concrete
Structural Piles
Micropiles
Field measured
Each foundation
AASHTO T99
stakes.
AASHTO
T180
AASHTO T191
Field measured
Not to exceed 30
mm
Horz and 30 mm
Vert. from reference
Lift
size
greater than
mm
loose
thickness.
soil
no
200
lift
Not to exceed 75
mm
Horiz. and 75 mm
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
1 laboratory
compaction
curve per
type.
of
Item No.
406
Description
Item
Concrete
Reinforcing
Steel Wire
Strand
Item
Same
IX - 240
Test of Control
Test
as
Frequency
Remarks
for
405
Same Test as for Item
404
1-Q, for every 20 tons
or fration thereof
Technical
Specifications:
Rehabilitation/Construction
Samar Road Ref 330200 - CP2 Package
of