Вы находитесь на странице: 1из 7

Bill of Engineering Measurements

Item
Description

Unit

Quantity

Rate (N)

Amount (N)

1.1 Excavate vegetable top soil to length


of
16.8m, width of 11.25m to an a.v.
depth of 150mm

m3

45.36

200.00

9,072.00

1.2 Excavate treench to receive


foundation
from strip level not exceeding 1.2m
deep

m3

152.9

700.00

107,030.00

1.3 Excavate column bases

m3

18.7

700.00

13,090.00

1.4 Level and compact bottom of


excavation to receive concrete

m2

186.03

150.00

27,904.50

1.5 Backfill and consolidate excavated


material around foundation

m3

100.34

250.00

25,085.00

1.6 Spread and level surplus excavated


material on site

m3

52.56

200.00

10,512.00

1.7 Laterite earth filling in making up


level

m3

218.77

1,800.00

393,786.00

Bill 1: Excavation and Earth Work

To summary

586,479.50

Bill 2: Block work


2.1 225mm thick sandcrete solid block
in
cement and sand mortar (1:6) mix

m2

275.62

2,400.00

To summary

661,488.00

661,488.00

Bill 3: Concrete work


Plain in-situ concrete (1:3:6) - 38mm
aggregate in

3.1 Blinding concrete 50mm thick

m3

9.31

20,000.00

186,200.00

3.2 150mm bed over ground floor

m3

39.06

20,000.00

781,200.00

3.3 Concrete facial roof

m3

8.22

20,000.00

164,400.00

3.4 Column base 350mm thick

m3

18.7

25,000.00

467,500.00

3.5 Vertical column 225 x 225mm

m3

14.11

25,000.00

352,750.00

3.6 Beams 225 x 450mm

m3

10.08

25,000.00

252,000.00

3.7 Lintel 225 x 225mm

m3

5.89

25,000.00

147,250.00

3.8 Floor slab 150mm thick

m3

30.06

25,000.00

751,500.00

3.9 Stair case

m3

6.72

25,000.00

168,000.00

Plain in-situ concrete (1:2:4) - 20mm


aggregate in

To summary

3,270,800.00

Bill 4: Reinforcement
4.1 10mm diameter

kg

2924.94

260.00

760,484.40

4.2 12mm diameter

kg

3880.05

260.00

1,008,813.00

4.3 16mm diameter

kg

1592.7

260.00

414,102.00

To summary

2,183,399.40

Bill 5: Form work


5.1 Sawn form work to column 225 x
225mm

1113.6

5.2 Side and soffit of beam

m2

5.3 Horizontal soffit of floor slab


5.4 Edges of floor slab

300.00

334,080.00

89.6

1,200.00

107,520.00

m2

260.38

1,200.00

312,456.00

83.55

200.00

16,710.00

5.5 Horizontal soffit of land slab of stairs

m2

11.52

1,200.00

13,824.00

5.6 Soffit of sloping stair

m2

22.42

1,200.00

26,904.00

5.7 Edge of sloping slab (waist 150mm)

29.89

350.00

10,461.50

5.8 Edge of riser 150mm thick

72.96

350.00

25,536.00

To summary

847,491.50

Bill 6: Roofing
6.1 Roof trusses and aluminium roofing
sheets fixed to roof trusses with all
accessories

P.S

5,280,000.00

To summary

5,280,000.00

5,280,000.00

Bill 7:Carpentry and Joinery


7.1 50 x 175mm door frame

197.76

7.2 900 x 2100mm door

No

7.3 750 x 2100mm door


7.4 1350 x 2100mm door

700.00

138,432.00

12

7,000.00

84,000.00

No

6,000.00

24,000.00

No

10,000.00

30,000.00

To summary

276,432.00

Bill 8: Iron Mongery


8.1 Pair of 100mm steel butt hinges

No

67

200.00

13,400.00

8.2 Mortice lock with lever handel

No

32

200.00

6,400.00

To summary

19,800.00

Bill 9: Electrical Installation


9.1 Provide a sum for electrical
installation
including piping, wiring, fitting,
lighting, etc
To summary

P.S

128,000.00

128,000.00

128,000.00

Bill 10: Metal work/ Glazing


GNP Anodized Aluminium sliding
fixed to block work in
10.1 1200 x 1200mm window

No

33

25,000.00

825,000.00

10.1 600 x 600mm window

No

7,500.00

7,500.00

10.2 1350 x 3550mm window

No

130,000.00

130,000.00

To summary

962,500.00

Bill 11: Plumbling and Sanitary


Installations
11.1 Provide sum for plumbing and
sanitary
installation including piping, fitting
and accessories

P.S

880,000.00

To summary

880,000.00

880,000.00

Bill 12: Finishing


12.1 Floor tiles bedded in cement sand
mortar (1:3) mix

m2

155.52

3,000.00

466,560.00

12.2 13mm cement sand (1:4) mix


rendering to soffit of floor
slabs/beam
and stairs

m2

260.38

700.00

182,266.00

12.3 13mm cement and sand (1:4) mix


rendering to block wall internally
and
externally

m2

1950.46

600.00

1,170,276.00

12.4 150 x 150mm ceramic wall tiles


bedded in cement mortar (1:3) mix

m2

171.3

2,200.00

376,860.00

To summary
Bill 13: External works

2,195,962.00

13.1 Excavate and construct septic tank


and
soak away pit as directed, connect to
building to receive waste

L.S

1,920,000.00

To summary

1,920,000.00

1,920,000.00

Bill 14: Painting and Decoration


14.1 Prepare and apply one under coat
and
two finishing coats of emulsion paint
on rendered walls - internally and
externally

14.2 Ditto on soffit of floor slabs and


stairs/
ceiling
To summary

m2

1950.46

550.00

1,072,753.00

m2

5577.38

600.00

3,346,428.00

4,419,181.00

SUMMARY
S/N
DESCRIPTION
1 BILL 1: EXCAVATION AND EARTH WORK

AMOUNT (N)
586,479.50

BILL 2: BLOCK WORK

BILL 3: CONCRETE WORK

3,270,800.00

BILL 4: REINFORCEMENT

2,183,399.40

BILL 5: FORM WORK

BILL 6: ROOFING

BILL 7: CARPENTRY AND JOINERY

BILL 8: IRON MONGERY

BILL 9: ELECTRICAL INSTALLATION

128,000.00

10

BILL 10: METAL WORK/ GLAZING

962,500.00

11

BILL 11: PLUMBING AND SANITARY INSTALLATIONS

880,000.00

12

BILL 12: FINISHING

2,195,962.00

13

BILL 13: EXTERNAL WORKS

1,920,000.00

14

BILL 14: PAINTING AND DECORATION

4,419,181.00

SUB - TOTAL
Allow 10% of sub - total for contigencies

661,488.00

847,491.50
5,280,000.00
276,432.00
19,800.00

23,631,533.40
2,363,153.34

GRAND TOTAL

25,994,686.74

Вам также может понравиться