RANCANGAN TEBATAN BANJIR

LEMBAH BERTAM, CAMERON HIGHLANDS, PAHANG


PROJEK MELEBAR DAN MENDALAMKAN SUNGAI BERTAM
DAN KERJA - KERJA BERKAITAN
METHOD STATEMENT
( INTERIM )

DOCUMENT NO :

FLEXIBLE PAVEMENT

JSSB/QAP/MS/PAV

Reference :
1.0 SCOPE OF WORKS
1.1

The structural elements that are covered by this method statement s


be include;

Contract document
Sect.4/PAV
JKR/SPJ/2005

1.1.1 Non Bituminous Courses.


1.1.1.1
Sub Grade
1.1.1.2
Sub Base
1.1.1.3
Road Base/ Base Course
1.1.1.4
Dense Bituminous Macadam (DBM)
1.1.2 Bituminous Courses.
1.1.2.1
Asphaltic Concrete Binder Course
1.1.2.2
Asphaltic Concrete Wearing Course
2.0 SURVEY AND SETTING OUT
2.1

To determine existing and to fix pavement level, cross fall and alignment
shall be carried out.

2.2

Setting out and control pegs shall be installed on site to control :2.2.1
2.2.2
2.2.3
2.2.4
2.2.5
2.2.6
2.2.7

Required design level.


Alignment of road and lanes.
Width of road and lanes.
Junction and road connection.
Dipping measurement
Automatic paving string line.
Cross fall and super elevation

3.0 TEMPORARY TRAFFIC DIVERSION AND CONTROL.

3.1

Traffic Management Plan shall be submitted for approval to ensure


traffic flow is not much disrupted.

3.2

Diversion of road shall be constructed to the most suitable angle of


entry, adequate width, horizontal curvature and level that would
constitute a safe flow.

3.3

The speed limit for the traffic along the diversion shall be as requirement.

3.4

The diversion shall be well sealed with premix and to be maintained regularly.

3.5

All diversion shall be adequately furnished with the necessary signages,


barriers, reflective strings, barricades, night illumination blinker, beacons,
markers and traffic controller as and when necessary. The diversion and
approach road shall also be provided with proper road marking in
accordance to Arahan Teknik ( Jalan ) 2C/ 85 .

Page 1 of 59

RANCANGAN TEBATAN BANJIR


LEMBAH BERTAM, CAMERON HIGHLANDS, PAHANG
PROJEK MELEBAR DAN MENDALAMKAN SUNGAI BERTAM
DAN KERJA - KERJA BERKAITAN
METHOD STATEMENT
( INTERIM )

DOCUMENT NO :

FLEXIBLE PAVEMENT

JSSB/QAP/MS/PAV

Reference :
4.0 SURFACE DRAINAGE
4.1

Prior to any pavement work, all drainage system shall be present and
functional.

4.2

Permanent subsoil drains, ( if any ) must have already been installed to


ensure firm foundation and any localized soft spot shall be identified and
rectified in advance.

Contract document
Sect.4/PAV
JKR/SPJ/2005

5.0 PREPARATION OF FORMATION


5.1

Prior to preparation of formation or subgrade, all foundation and


earthwork must have been completed up to the level of tolerance as
specified in the specification. Filling or cutting is normally done up to +/ 300 mm from the formation level, after which it is considered as
formation of subgrade level.

5.2

Excess material shall be removed to facilitate the works. The material


shall be imported from approved source of borrowed pit and shall satisfy
all suitability requirement as well as the CBR > 5%.

5.3

The compaction shall be checked by the Field Density Test 95% the
Relative Compaction.

5.4

No heavy vehicles shall be allowed over the prepared subgrade. Where


necessary, a protective layer shall be placed over the subgrade and to
be removed when no longer needed.

5.5

Subgrade shall be developed along the full width of the carriage way and
compacted in longitudinal direction from the outer edge to the inner edge
and shall be from the lower end to the higher end in the super-elevated
areas.

5.6

Any material that found unsuitable, to be removed and replaced with


imported material.

5.7

The line and level shall be control by dipping pegs, which indicated the
offsets and levels.

6.0 PLACING OF SUB-BASE AND ROAD BASE


6.1

SUB BASE
6.1.1
Prior to laying any sub base material, the under laying
subgrade shall have been shaped and compacted as per
requirements.

Page 2 of 59

RANCANGAN TEBATAN BANJIR


LEMBAH BERTAM, CAMERON HIGHLANDS, PAHANG
PROJEK MELEBAR DAN MENDALAMKAN SUNGAI BERTAM
DAN KERJA - KERJA BERKAITAN
METHOD STATEMENT
( INTERIM )

FLEXIBLE PAVEMENT

DOCUMENT NO :
JSSB/QAP/MS/PAV

Reference :
6.1.2

Material specification requirement for lower sub base ( CBR


Value > 30 and gradation Limit, table 4.1 ). Random sampl
shall be taken from site to comply with the specification.

6.1.3

Suitable spreading plant such as motor grader and


backpusher and compaction shall be carried out using suitable
compacting plant.

6.1.4

Cleanliness and uniformity of moisture and prevention of


physical segregation of the material laid shall always be
ensured through the used of a box spreader or prudent used
of the motor grader, water tanker, compactor combination.

6.1.5

The material shall be done in a single lift. If the required


thickness is more 200mm, the placing, spreading and
compacting of material shall be done in two layers.

6.1.6

Once the required 95% Relative Density is achieved, the level


shall be checked using dipping pegs at 12.5 m interval to
ensure the correct cross fall and adequacy thickness is
achieved with the tolerance + 10mm / - 20mm.

6.1.7

Compaction requirement
6.1.7.1
Compaction is not less 95% of the maximum
dry density as determined by BS 1377 test
(4.5 kg rammer method )

6.1.8

Field Control
6.1.8.1

6.2

Trial compaction shall be carried out to excess


the suitability of the compaction plant and to
establish the rolling pattern required to
achieved the specified compaction
requirement.

ROAD BASE
6.2.1

Prior to placing the road base material, the underlying


subgrade or sub base shall have been shaped and
compacted.

6.2.2

Upon approval of the preceding sub base layer, the road


base shall be in layers having compacted thickness not less
than 100mm and not exceeding 200mm.

6.2.3

Suitable spreading plant such as motorgrade or backpusher


shall be used and as well as for compaction activity.

Page 3 of 59

Contract document
Sect.4/PAV
JKR/SPJ/2005

RANCANGAN TEBATAN BANJIR


LEMBAH BERTAM, CAMERON HIGHLANDS, PAHANG
PROJEK MELEBAR DAN MENDALAMKAN SUNGAI BERTAM
DAN KERJA - KERJA BERKAITAN
METHOD STATEMENT
( INTERIM )

6.2.4

FLEXIBLE PAVEMENT

Reference :
Cleanliness, uniformity or moisture and prevention of physical
segregation of the material shall always be ensured and
Contract document
compaction shall be provided using a suitable compacting
Sect.4/PAV
plant and tested.
JKR/SPJ/2005

6.2.5

Check the dipping at 12.5m intervals, shall be carried out to


ensure that the correct cross fall within the tolerance after the
required 95% relative density is achieved.

6.2.6

Compaction requirement
6.2.6.1

Method of compaction shall achieved not less


than 95% of the dry density as determined
by BS 1377 ( 4.5 kg rammer method )

6.3

6.2.6.2

Trial compaction shall be carried out to assess


the suitability of the compaction plant and
establish the rolling pattern required.

6.2.6.3

The material shall conform the requirement


( CBR Value > 30 and gradation limit, table 4.2 )

BITUMINOUS COATING
6.3.1

Plant and Equipment


6.3.1.1

6.3.2

DOCUMENT NO :
JSSB/QAP/MS/PAV

Bitumen Emulsion using Self-Propelled Hand


Operated Distributor.

Prime coat.
6.3.2.1

Clean the surface of compacted Road base


from loose sand, clay or silt using a tractor
attached with power broom.

6.3.2.2

The resulting surface shall reveal an intact but


rough and irregular surface finish, with enough
voids to allow the sprayed prime coat achieve
good penetration in the road base.

6.3.2.3

The rates of application shall be agreed upon


the spray trial ( within the range of 0.5 to 1.0
litre/ sq. m at the temperature range of the
between 25 c and 45 c.

Page 4 of 59

RANCANGAN TEBATAN BANJIR


LEMBAH BERTAM, CAMERON HIGHLANDS, PAHANG
PROJEK MELEBAR DAN MENDALAMKAN SUNGAI BERTAM
DAN KERJA - KERJA BERKAITAN
METHOD STATEMENT
( INTERIM )

FLEXIBLE PAVEMENT

DOCUMENT NO :
JSSB/QAP/MS/PAV

Reference :
6.3.2.4

6.3.3

6.3.4

The application shall be distributed uniformly


over the surface having deviation not more
than 10% from those prescribed and shall b
normally be left undisturbed for at least 24

Tack Coat
6.3.3.1

Works shall commence on site upon approval


and acceptance of the previous bituminous
layer.

6.3.3.2

Bituminous tack coat materials shall be rapid


setting bitumen of grade K140, RS-1 or RS-1K
conforming to MS 161.

6.3.3.3

The surface to receive tack coat shall free


from all loose material, standing water and
any damage or deterioration of it shall be
make good prior to application.

6.3.3.4

The rate of tack coat application shall be 0.25


to 0.55 litres/ sq m. at temperature range
between 25 c and 45c.

Field Control
These shall be carried out to assess and determine the rate
of spread. A tray will be weighed, measured and will be put at
the middle of area to be sprayed. Hence, the rate of the
spread will be determine as follows :
Rate of spread :

( tack coat + tray ) - ( tray )


( density of tack coat ) ( area of tray )

7.0 ASPHALTIC CONCRETE BINDER COURSE


7.1

Works shall commence on site upon approval of design mix and


acceptance of previous prime layer.

7.2

The surface to receive the asphaltic concrete binder course shall be free
of all dirt, loose material and water ponding.

7.3

The approved mix shall be delivered to site by tipper trucks covered with
tarpaulin to prevent heat lost.

7.4

The asphaltic concrete shall be laid using Vogele Super 1502 paver or
equivalent in single layer.

Page 5 of 59

Contract document
Sect.4/PAV
JKR/SPJ/2005

RANCANGAN TEBATAN BANJIR


LEMBAH BERTAM, CAMERON HIGHLANDS, PAHANG
PROJEK MELEBAR DAN MENDALAMKAN SUNGAI BERTAM
DAN KERJA - KERJA BERKAITAN
METHOD STATEMENT
( INTERIM )

7.5

7.6

FLEXIBLE PAVEMENT

DOCUMENT NO :
JSSB/QAP/MS/PAV

Reference :
If the laid surface in open-textured, back casting shall be carried out and
the bigger size of aggregates shall be removed before rolling.
Contract document
Sect.4/PAV
The transverse joint shall be feathered down, at the end of the pavin
JKR/SPJ/2005
operation on ( and vertical joint shall be provided ). Tack coat shall be
uniformly applied evenly over the vertically cut joint 15 minutes before
jointing.

7.7

Compaction shall be carried out using specified or equivalent type of


compactors and the rolling pattern shall be as per established during trial
lay from the lower to the higher side of the carriage way. The minimum
rolling temperature is 110C.

7.8

The surface shall be finished to the grade and line as required. Dipping at
12.5m intervals shall be carried out and to check that the tolerance of
5mm is achieved.

7.9

COMPACTION REQUIREMENT
7.9.1

The compacted Asphaltic Concrete Binder Course shall


achieved 95% - 100% of Marshall Density.

7.9.2

Coring shall be carried out to determine Marshall Stability Test


and the compaction, 24 hours after laying.

7.10 FIELD CONTROL


7.10.1

Trial Mix and Trial Lay


7.10.1.1

These shall be carried out to access the


suitability of the mixing, laying and compacting
plant and to establish the sequence of the
laying operation.

7.10.1.2

Compaction shall be carried out using


rollers as given below:-

Vibratory Tandem Roller


Operating weight, total
Drum width
Speed
Pneumatic Tyre Roller
Operating weight, total
Drum width
Speed

: Model - Dynapac CC21


or equivalent
: 6800 kg
: 1,450 mm
: 3 - 5 km/h
: Model - Pynapac WP20
or equivalent
: 13,760 kg
: 2,100 mm
: 3 - 5 km/h

Page 6 of 59

RANCANGAN TEBATAN BANJIR


LEMBAH BERTAM, CAMERON HIGHLANDS, PAHANG
PROJEK MELEBAR DAN MENDALAMKAN SUNGAI BERTAM
DAN KERJA - KERJA BERKAITAN
METHOD STATEMENT
( INTERIM )

FLEXIBLE PAVEMENT

DOCUMENT NO :
JSSB/QAP/MS/PAV

Reference :
7.10.1.3

The proposed rolling pattern applied shall be


as follows:-

Breakdown Rolling

Intermediate Rolling

Final Rolling

2 passes with vibration


using Dynapac CC21 or
equivalent
8 passes with WP20
pneumatic tyre roller or
equivalent
2 passes with Dynapac
CC21 or equivalent

8.0 ASPHALTIC CONCRETE WEARING COURSE


8.1

Works shall commence on site upon approval and acceptance of the


asphaltic concrete binder course.

8.2

Apply tack coat on the prepared surface. The full width of surface to the
treated shall be swept using a power broom followed by a compressed
air blower to remove all dirt, dust and loose material.

8.3

Tack coat of approval bitumen emulsion ( MS 161 ) shall be applied as


per procedure on the prepared surface prior to laying the wearing
course.

8.4

The asphaltic concrete wearing course shall be laid using paver in single
layer and the temperature of mix shall not less than 125C prior to
unloading from truck into the paver.

8.5

Backcasting shall be carried out if the laid surface is open-textured and


uneven size of aggregates removed before rolling.

8.6

Construction joints in a layer of bituminous mix shall be offset from those


in any immediately underlying bituminous layer at least 100mm for
longitudinal joints and at least 0.5m for transverse joints.

8.7

Compaction shall be carried out using specified compactor and rolling


pattern shall be as establish during trial lay from the lower to the higher
side of the carriage way with 120C rolling temperature.

8.8

The finished surface shall be to grade and line as required. Dipping at


12.5m intervals shall be carried out to check that the tolerance of
5mm is achieved.

Page 7 of 59

Contract document
Sect.4/PAV
JKR/SPJ/2005

RANCANGAN TEBATAN BANJIR


LEMBAH BERTAM, CAMERON HIGHLANDS, PAHANG
PROJEK MELEBAR DAN MENDALAMKAN SUNGAI BERTAM
DAN KERJA - KERJA BERKAITAN
METHOD STATEMENT
( INTERIM )

FLEXIBLE PAVEMENT

DOCUMENT NO :
JSSB/QAP/MS/PAV

Reference :
8.9

COMPACTION REQUIREMENT
8.9.1

The compacted Asphaltic Concrete Wearing Course shall


achieved 98% - 100% of Marshall Density.

8.9.2

Coring shall be carried out to determine Marshall Stability Test


and the compaction, 24 hours after laying.

8.10 FIELD CONTROL


8.10.1

Trial Mix and Trial Lay


8.10.1.1

These shall be carried out to assess the


suitability of the mixing, laying and compacting
plant and to establish the sequence of the
laying operation.

8.10.1.2

Compaction shall be carried out using rollers as


given below:-

Vibratory Tandem Roller


Operating weight, total
Drum width
Speed
Pneumatic Tyre Roller
Operating weight, total
Drum width
Speed
8.10.1.3

: Model - Pynapac WP20


or equivalent
: 13,760 kg
: 2,100 mm
: 3 - 5 km/h

The proposed rolling pattern applied shall be


as follows:-

Breakdown Rolling

Intermediate Rolling

Final Rolling

: Model - Dynapac CC21


or equivalent
: 6800 kg
: 1,450 mm
: 3 - 5 km/h

2 passes with vibration


using Dynapac CC21 or
equivalent
12 passes with WP20
pneumatic tyre roller or
equivalent
2 passes with Dynapac
CC21 or equivalent

Page 8 of 59

Contract document
Sect.4/PAV
JKR/SPJ/2005

RANCANGAN TEBATAN BANJIR


LEMBAH BERTAM, CAMERON HIGHLANDS, PAHANG
PROJEK MELEBAR DAN MENDALAMKAN SUNGAI BERTAM
DAN KERJA - KERJA BERKAITAN
METHOD STATEMENT
( INTERIM )

FLEXIBLE PAVEMENT

DOCUMENT NO :
JSSB/QAP/MS/PAV

Reference :
EQUIPMENT/ MANPOWER/ TEST

a)

PLANT AND EQUIPMENT


Compactor Roller
Proof Roller
Backpusher
Motor Grader
Paving Set
Dumptrucks
Water Browser
Sprayer

b)

no
no
no
nos
nos
nos
no
no

MANPOWER
Supervisor
Machine operator
General Worker

c)

1
1
1
2
1
3
1
1

1 nos
10 nos
6 nos

TEST
Refer to Inspection & Test Plan (ITP)

Page 9 of 59

PROJEK MENAIKTARAF LEBUHRAYA JOHOR BAHRU - PASIR GUDANG


DARI 4 LORONG KE 6 LORONG, JOHOR

TEMPORARY WORK FOR BORED PILING


WORK FOR BRIDGE OVER SUNGAI MASAI B8

METHOD STATEMENT
( INTERIM )

1.0 INTRODUCTION
1.1 The purpose of this method statement is to describe the activities an
documentation required to commence the temporary work for bridge
2.0 SCOPE OF WORKS
2.1 Preparation of access road
2.2 Preparation of temporary platform
2.3 Installation of sheet pile
3.0 WORK SEQUENCE FLOW
START
Setting out

Site clearing &


preparing access road
Preparation of
temporary platform
Installation of
sheet pile
Additional site investigation
(S.I)
Bored piling work
commence
Construction of
column
Backfilling
work
Removal of
sheet pile
END

Page 10 of 59

DOCUMENT NO :
IDX/QAP/MS/TWB8

PROJEK MENAIKTARAF LEBUHRAYA JOHOR BAHRU - PASIR GUDANG


DARI 4 LORONG KE 6 LORONG, JOHOR

METHOD STATEMENT
( INTERIM )

DOCUMENT NO :

TEMPORARY WORK FOR BORED PILING


WORK FOR BRIDGE OVER SUNGAI MASAI B8

IDX/QAP/MS/TMB8

4.0 METHOD STATEMENT


4.1 SETTING OUT
4.1.1 The land surveyor will identify the Right of Way boundary and location
of the piling point.
4.1.2 Offset for the piling point, finished road level, cut off level will be
provided at the peg allocated for the piling point.
4.2 SITE CLEARING
4.2.1 The site clearing will be performed at the allocated location.

IDX/QAP/MS/SC

4.2.2 The opening as a mean of access to the location will be constructed


and filling and cutting of the OGL are required until the difference in
ground level is appropriate for machineries and transportation
4.2.3 The location of machineries, the opening, the material will be arrang
based on the suitability of site condition
4.3 CONSTRUCTION OF THE WORKING PLATFORM
4.3.1 The working platform is prepared as per cut off level reference.
The excavation will take place and the leveling of the area is performed
until it reaches a satisfactory perimeter for the bored piling machine
maneuver.
4.4 INSTALLATION OF SHEET PILE
4.4.1 The access and platform for vibro hammer will be prepared by means
of leveling and cut and fill method
4.4.2 The vibro hammer will install the sheet pile as per diagram

TEMP/CROSS-SECT-B8-S1

4.4.3 Previously the design calculation for sheet piling had been worked ou
as a reference for the installation of sheet pile work

Attachment 1

4.5 COMMENCEMENT OF BORED PILING & SUB STRUCTURE WORK


4.5.1 Once the sheet pile has been installed, the leveling work continues
until it is appropriate for bored piling machine to operate on the platform
4.5.2 The bored piling work commence

IDX/QAP/MS/BPW

4.5.3 The column will be constructed and once the base is backfilled
as per construction drawing and under permission by S.O
the sheet pile will be removed from the base

IDX/QAP/MS/SSW
IDX/QAP/MS/CPC

Page 11 of 59

PROJEK MENAIKTARAF LEBUHRAYA JOHOR BAHRU - PASIR GUDANG


DARI 4 LORONG KE 6 LORONG, JOHOR

TEMPORARY WORK FOR BORED PILING


WORK FOR BRIDGE OVER SUNGAI MASAI B8

METHOD STATEMENT
( INTERIM )

DOCUMENT NO :
IDX/QAP/MS/TMB8

4.5.4 The sheet pile will be transferred to the another working platform and
installed there as per diagram
4.6 SHEET PILE & STEEL PLATE DESCRIPTION
4.6.1 The sheet pile to be used is Type SP 3A (refer to the attachment)
4.7 TIDE LEVEL
4.7.1 The highest tide level and lowest tide level is
recorded as per table below:

4.7.2 For detail references on the tide level, the full table can be obtained
from Jabatan Meteorologi Malaysia and Jabatan Pengairan dan
Saliran Malaysia. The record shown in table is based on actual level
measured on the site in respect to sea water level.
4.8 SEQUENCES OF WORK
4.8.1 The working platform will be prepared as per this sequence:

Abutment A

Abutment B

Abutment B-1

Abutment A-1
4.8.2 The sequence for piling work as per diagram attached.

Page 12 of 59

TEMP/SEQ-B8-S1

PROJEK MENAIKTARAF LEBUHRAYA JOHOR BAHRU - PASIR GUDANG


DARI 4 LORONG KE 6 LORONG, JOHOR

METHOD STATEMENT
( INTERIM )

TEMPORARY WORK FOR BORED PILING


WORK FOR BRIDGE OVER SUNGAI MASAI B8

5.0 SAFETY REQUIREMENT


5.1 The existing traffic flow will be monitored by traffic supervision team
and mobilization and demobilization of machineries are not allowed
if the traffic supervision team is not available.
5.2 Only experienced personnel are allowed at working area.
5.3 Site personnel must be briefed and be well versed with all site safety
measures.
5.4 Site personnel must be in proper safety working attire e.g. Safety boots
and helmets must be worn at all times.
5.5 Site safety member should be available at all times and must be able to
respond correctly to emergency
5.6 Proper and adequate provisions of Temporary Signage and Barricades
at diversions and haul road as necessary.
6.0 AUTHORITY REQUIREMENT
6.1

The contractor will issue to the local authority involved such as JPS a
liability letter that will transfer the responbility of damage to the
surrounding area due to the work at site to the contractor.

7.0 PLANT AND EQUIPMENT

Excavator
Roller compactor
Backpusher
Tipper
Vibro Hammer

2
2
1
1
1

nos
nos
nos
nos
nos

8.0 MANPOWER

Supervisor
Machine operator
General Worker

1 person
7 persons
4 persons

Page 13 of 59

DOCUMENT NO :
IDX/QAP/MS/TMB8

PROJEK MENAIKTARAF LEBUHRAYA JOHOR BAHRU - PASIR GUDANG


DARI 4 LORONG KE 6 LORONG, JOHOR

METHOD STATEMENT
( INTERIM )

TEMPORARY WORK FOR CONSTRUCTION


OF PILE CAP FOR BRIDGE OVER SUNGAI
MASAI - B8

1.0 INTRODUCTION
1.1 The purpose of this method statement is to describe the activities an
documentation required to commence the temporary work during
construction of pile cap for Bridge 8.
2.0 SCOPE OF WORKS
2.1 Preparation of cofferdam
2.2 Excavation to the cut-off level
2.3 Commencement of pile cap construction
3.0 WORK SEQUENCE FLOW
START
Setting out

Preparation of
platform for
excavation
Installation of sheet
pile & permanent
steel plate

Excavation
work to the
cut-off level
Pile cap
construction

Backfilling
work
Removal of
sheet pile
END

Page 14 of 59

DOCUMENT NO :
IDX/QAP/MS/TW2B8

PROJEK MENAIKTARAF LEBUHRAYA JOHOR BAHRU - PASIR GUDANG


DARI 4 LORONG KE 6 LORONG, JOHOR

METHOD STATEMENT
( INTERIM )

DOCUMENT NO :

TEMPORARY WORK FOR CONSTRUCTION


OF PILE CAP FOR BRIDGE OVER SUNGAI
MASAI - B8

IDX/QAP/MS/TW2B8

4.0 METHOD STATEMENT


4.1 SETTING OUT
4.1.1 The land surveyor will take the as-built data of the bored pile level
and platform level before excavation wor
4.1.2 The perimeter of the pile cap will be determined at site based on the
piling location and construction drawing.
4.2 SITE CLEARING
4.2.1 The site clearing will be performed at the allocated location.

IDX/QAP/MS/SC

4.2.2 The opening as a mean of access to the location will be constructed


and filling and cutting of the OGL are required until the difference in
ground level is appropriate for machineries and transportation
4.2.3 The location of machineries, the opening, the material will be arrang
based on the suitability of site condition
4.3 CONSTRUCTION OF THE WORKING PLATFORM
4.3.1 The working platform is prepared as per cut off level reference.
The excavation will take place and the leveling of the area is performed
until it reaches a satisfactory perimeter for the bored piling machine
maneuver.
4.4 INSTALLATION OF SHEET PILE
4.4.1 The access and platform for vibro hammer will be prepared by means
of leveling and cut and fill method
4.4.2 The vibro hammer will install the sheet pile as per diagram

TEMP/CROSS-SECT-B8-S1

4.4.3 Previously the design calculation for sheet piling had been worked ou
as a reference for the installation of sheet pile work

Attachment 1

4.5 COMMENCEMENT OF BORED PILING & SUB STRUCTURE WORK


4.5.1 Once the sheet pile has been installed, the leveling work continues
until it is appropriate for bored piling machine to operate on the platform
4.5.2 The bored piling work commence

IDX/QAP/MS/BPW

4.5.3 The pile cap and pier will be constructed and once the base is backfil
as per construction drawing and under permission by S.O
the sheet pile will be removed from the base

IDX/QAP/MS/SSW
IDX/QAP/MS/CPC

Page 15 of 59

PROJEK MENAIKTARAF LEBUHRAYA JOHOR BAHRU - PASIR GUDANG


DARI 4 LORONG KE 6 LORONG, JOHOR

TEMPORARY WORK FOR CONSTRUCTION


OF PILE CAP FOR BRIDGE OVER SUNGAI
MASAI - B8

METHOD STATEMENT
( INTERIM )

DOCUMENT NO :
IDX/QAP/MS/TW2B8

4.5.4 The sheet pile will be transferred to the another working platform and
installed there as per diagram
4.6 SHEET PILE & STEEL PLATE DESCRIPTION
4.6.1 The sheet pile to be used is Type IIIA (refer to the attachment)
4.7 TIDE LEVEL
4.7.1 The highest tide level and lowest tide level is
recorded as per table below:

4.7.2 For detail references on the tide level, the full table can be obtained
from Jabatan Meteorologi Malaysia and Jabatan Pengairan dan
Saliran Malaysia. The record shown in table is based on actual level
measured on the site in respect to sea water level.
4.8 SEQUENCES OF WORK
4.8.1 The working platform will be prepared as per this sequence:

Abutment A

Abutment B

Abutment B-1

Abutment A-1
4.8.2 The sequence for piling work as per diagram attached.

Page 16 of 59

TEMP/SEQ-B8-S1

PROJEK MENAIKTARAF LEBUHRAYA JOHOR BAHRU - PASIR GUDANG


DARI 4 LORONG KE 6 LORONG, JOHOR

TEMPORARY WORK FOR CONSTRUCTION


OF PILE CAP FOR BRIDGE OVER SUNGAI
MASAI - B8

METHOD STATEMENT
( INTERIM )

5.0 SAFETY REQUIREMENT


5.1 The existing traffic flow will be monitored by traffic supervision team
and mobilization and demobilization of machineries are not allowed
if the traffic supervision team is not available.
5.2 Only experienced personnel are allowed at working area.
5.3 Site personnel must be briefed and be well versed with all site safety
measures.
5.4 Site personnel must be in proper safety working attire e.g. Safety boots
and helmets must be worn at all times.
5.5 Site safety member should be available at all times and must be able to
respond correctly to emergency
5.6 Proper and adequate provisions of Temporary Signage and Barricades
at diversions and haul road as necessary.
6.0 AUTHORITY REQUIREMENT
6.1

The contractor will issue to the local authority involved such as JPS a

liability letter that will transfer the responbility of damage to the


surrounding area due to the work at site to the contractor.
7.0 PLANT AND EQUIPMENT
Excavator
Roller compactor
Backpusher
Tipper

2
2
1
1

nos
nos
nos
nos

Vibro Hammer

1 nos

8.0 MANPOWER
Supervisor
Machine operator
General Worker

1 person
7 persons
4 persons

Page 17 of 59

DOCUMENT NO :
IDX/QAP/MS/TW2B8

PROJEK MENAIKTARAF LEBUHRAYA JOHOR BAHRU - PASIR GUDANG


DARI 4 LORONG KE 6 LORONG, JOHOR

METHOD STATEMENT
( INTERIM )

CONSTRUCTION OF PILE CAP

1.0 INTRODUCTION
1.1 The purpose of this method statement is to describe the activities an
documentation required to commence the construction of pile cap
2.0 SCOPE OF WORKS
2.1 Setting Out
2.2 Reinforcement work for the pile cap
2.3 Concreting work of the pile cap
3.0 WORK SEQUENCE FLOW
START
Setting out

Preparing the base &


lean concreting
Installation of
formwork
Installation of
reinforcement
steel
Concreting
work
Bitumen layering
surrounding the
buried surface

Backfilling
work

END

Page 18 of 59

DOCUMENT NO :
IDX/QAP/MS/CPC

PROJEK MENAIKTARAF LEBUHRAYA JOHOR BAHRU - PASIR GUDANG


DARI 4 LORONG KE 6 LORONG, JOHOR

METHOD STATEMENT
( INTERIM )

DOCUMENT NO :

CONSTRUCTION OF PILE CAP

IDX/QAP/MS/CPC

4.0 METHOD STATEMENT


4.1 SETTING OUT
4.1.1 The land surveyor will identify the exact location of pile cap and mark
the edge of the pile cap
4.1.2 Offset for the piling point, finished road level, cut off level will be
recorded for reference
4.2 PREPARING THE BASE & LEAN CONCRETE
4.2.1 The surface of the base will be cleared from any debris and levelled
to ensure the flat and conceivable surface for lean concreting.
4.2.2 Before the lean concrete is poured, the inspection will take place
to ensure the base is ready for such work.

Request for Inspection Form

4.2.3 Lean concreting work will commence once the inspection has been d
and agreeable quality is achieved
4.3 REBAR & FORMWORK INSTALLATION
4.3.1 Upon completion of bored piling the depth of excavation from ground
level to lean concrete i.e. : 50mm below pile cap soffit determine by the
surveyor.
4.3.2 Preparation of pile head by hacking to the required level for starter bar
extended into pile cap.
4.3.3 Prior to lean concrete, the pile cap dimension and soffit level shall be
marked by the surveyor.
4.3.4 The lean concrete preferably be 100-150mm larger then the size of p
cap and mark pile cap dimension prior to install rebars and formwork.
4.3.5 The bar bending schedule will be submitted in advance to the consul
for approval, where some of the rebars are custom cut. The size type
member, spacing and lap length shall be accordance to the drawing.
4.3.6 Concrete spacer shall be provided for adequate spacing and cover the
rebars are free from dirt or grease and in a proper storage.
4.3.7 All starter bar member, size, type and lap length are installed according
to the drawings.
4.3.8 The formwork are cut in size and dimension using waterproof plywoo
and shall be applied with mould oil to enhance the finish surface and to
prevent adhension of concrete.

Page 19 of 59

PROJEK MENAIKTARAF LEBUHRAYA JOHOR BAHRU - PASIR GUDANG


DARI 4 LORONG KE 6 LORONG, JOHOR

METHOD STATEMENT
( INTERIM )

CONSTRUCTION OF PILE CAP

DOCUMENT NO :
IDX/QAP/MS/CPC

4.3.9 The formwork shall be so erected to comply with the following


requirement ;
4.3.10 a) Conformity of dimension within allowable tolerance.
b) Strength and rigidity of formwork
c) Sufficient propping and bracing to the formwork support.
d) Tightness and sealing of joint from loss of grout.
4.3.11 Place the rebars in position according to size and spacing and properly
tied with wire.
4.3.12The process of formwork dismantling will be done soon after the curing
period has achieved without shock, disturbance and damage to the
structures.
4.4 CASTING
4.4.1 The qualities of cement, fine aggregates and coarse aggregates as
defined from the approved sources and the consultant shall be afforded
all reasonable opportunity to do the inspection and to carry out relevant
test comply to the specification.
4.4.2 Design mix and trial mix to the appropriated grade of concrete shall be
submitted for approval prior to commencement of concreting activity.
4.4.3 Prior to the commencement of work, the following item shall be carried
out:
a) All plant and equipment are adequate in place.
b) Proper access to point of discharge
c) Arrangement for protection against rain and water.
d) Compliance to the safety requirement.
e) Finished levels are clearly marked for reference.
4.4.4 Concrete shall be deposited in horizontal layer to a compacted depth not
exceeding 450mm by using vibrating poker, Until expulsion of air has
practically caused but would not cause over vibration that will lead to mix
segregation.
4.4.5 Concrete shall not be dropped from height exceeding 1.5m unless tremie
pipe or chute are used.
4.4.6 Curing shall be carried out after the compaction to the exposed surfaces
to keep the concrete continuously damped. Methods of curing may vary
subject to the practicality.

Page 20 of 59

PROJEK MENAIKTARAF LEBUHRAYA JOHOR BAHRU - PASIR GUDANG


DARI 4 LORONG KE 6 LORONG, JOHOR

METHOD STATEMENT
( INTERIM )

CONSTRUCTION OF PILE CAP

5.0 SAFETY REQUIREMENT


5.1 The existing traffic flow will be monitored by traffic supervision team
and mobilization and demobilization of machineries are not allowed
if the traffic supervision team is not available.
5.2 Only experienced personnel are allowed at working area.
5.3 Site personnel must be briefed and be well versed with all site safety
measures.
5.4 Site personnel must be in proper safety working attire e.g. Safety boots
and helmets must be worn at all times.
5.5 Site safety member should be available at all times and must be able to
respond correctly to emergency
5.6 Proper and adequate provisions of Temporary Signage and Barricades
at diversions and haul road as necessary.
6.0 PLANT AND EQUIPMENT

Crane
Ready mixed truck
Vibrator Poker

1 nos
4 nos
1 nos

7.0 MANPOWER
Supervisor
Machine operator
General Worker

1
5

Page 21 of 59

DOCUMENT NO :
IDX/QAP/MS/CPC

PROJEK MENAIKTARAF LEBUHRAYA JOHOR BAHRU - PASIR GUDANG


DARI 4 LORONG KE 6 LORONG, JOHOR

METHOD STATEMENT
( INTERIM )

VIBRATION MONITORING

DOCUMENT NO :
IDX/QAP/MS/VM

1.0 Introduction
Vibration monitoring shall be carried out at all such locations where it is
required to access the effect of induced vibrations due to any dynamic
loading. A standard vibration monitoring system shall carry out this
assessment of vibration. This equipment should be able to evaluate the
parameters of vibrations in all three planes i.e. Longitudinal, Transverse and
vertical. Construction process like pile driving, blasting, soil compaction
induces vibrations that are at times above permissible limits. Permissible
limits of vibrations shall be as defined by relevant compliance code.

The method adopted shall measure peak pulse velocity, peak acceleration and
peak displacement in transverse, longitudinal and vertical direction for a
particular frequency. Every structure has its own frequency and unless the
induced vibration frequency does not match with this resonance frequency the
structure can sustain vibration safely. However vibrator forces above limits
specified in compliance code are detrimental to the health of the structure
and action contributory to such vibration should be immediately stopped.

2.0 Scope of Works


The vibration monitoring will be conducted for 8 selected locations at the
project site, Lebuhraya Pasir Gudang - Johor Bahru
The objective of this monitoring is to measure the induced vibrations for use
in vibration impact assessment and/or for compliancee verification during
construction stage of the proposed project based on the Department of
Environment guidelines.
The sampling points will be taken at the nearest constructed bridge and the
selections will be agreed by client. The vibration level readings were taken for
a consultant/S.O's decided duration at each selected location during piling and
these readings will provide data of the vibration level generated from the
surrounding of the selected points.

Appendix B

3.0 Test Equipment


The instrumentation used was the Instantel Model Minimate Plus. The
instrument captures the required data and stores in the memory for later
retrieval via computer software or direct print out. Monitoring data was taken
on the ground or structure of the locations. For ground vibrations, the
instrument measures the vibrations in three orthogonal axes, namely
transverse, vertical and longitudinal vibrations. transverse ground vibrations
agitate particles in a side to side motion. Vertical ground vibrations agitate
particles in an up and down motion. Longitudinal ground vibrations agitate
particles in a forward and back motion progressing outward from the source of
vibration

Page 22 of 59

Appendix C

PROJEK MENAIKTARAF LEBUHRAYA JOHOR BAHRU - PASIR GUDANG


DARI 4 LORONG KE 6 LORONG, JOHOR

METHOD STATEMENT
( INTERIM )

VIBRATION MONITORING

DOCUMENT NO :
IDX/QAP/MS/VM

The parameter that is used in the assessment of vibration is based on the


vectorial sum of vibration in the three orthogonal axes, termed peak particle
velocity (mm/s ppv)

4.0 Methodology
a) Conduct sensor check using internal check facilities prior to measurement. Set
up the Vibration Meter by mounting the tri-axial sensors in the soil, pointing to
the sources of vibration.
b) The location of the sensor should be installed near the bridge structure. There
should be no obstacles along side the perimeter involved. The radius shall not
beyond 200 meter from the sensor's location and point of observation.

c) Three vibration readings will be taken simultaneous which is vertical,


transverse and longitudinal.
d) After certain predetermined duration the vibration readings will be stored in
the memory of the vibration meter which can be retrieved for data processing
using vibration software.
5.0 Data Processing
The test report shall consist of
i) Site name, client and test agency
ii) Distance from activity.
iii) Location of monitoring.
iv) Peak particle velocity, peak acceleration, and peak displacement in all
three planes.
Specific job objectives need to be addressed during the interpretation and
result evaluation. Any peculiar findings shall be highlighted and reported
during the study. Clear statement of limitation and difficulties faced during
various stages of testing shall also be reported.
6.0 Reporting
The test report shall consists on:
6.1 A brief description about the location where maximum displacement is
evaluated.
6.2 An interpretation of all tests done and locations where the displacement is
beyond acceptable limits.
6.3 Specific job objectives need to be addressed during the interpretation and
results evaluation.

Page 23 of 59

Appendix A

PROJEK MENAIKTARAF LEBUHRAYA JOHOR BAHRU - PASIR GUDANG


DARI 4 LORONG KE 6 LORONG, JOHOR

METHOD STATEMENT
( INTERIM )

VIBRATION MONITORING

IDX/QAP/MS/VM

7.0 Limitations
The test cannot provide data about the maximum vibration that can occur as
the test provides result for the loading imposed on the location during testing
procedure. This test enables evaluation of more specific strength parameters
only when used in conjunction with other tests. Location and time specific
damping can affect the results of the test. Displacement evaluated and
maximum frequencies are evaluated during separate tests and if the loading
is not same the result could vary.

8.0 Acceptance Criteria


MS codal provision provides for acceptance criteria for bridge and its
dependant on the use of the bridge. This should be kept in mind when
evaluating the results of the test.
9.0 Safety Requirement
The existing traffic flow will be monitored by traffic supervision team
and mobilization and demobilization of machineries are not allowed
if the traffic supervision team is not available.
Only experienced personnel are allowed at working area.
Site personnel must be briefed and be well versed with all site safety
measures.
Site personnel must be in proper safety working attire e.g. Safety boots
and helmets must be worn at all times.
Site safety member should be available at all times and must be able to
respond correctly to emergency
Proper and adequate provisions of Temporary Signage and Barricades
at diversions and haul road as necessary.
10.0 Plant and Equipment

Vibration Monitoring Equipment 1 nos


11.0 ManPower

Supervisor
Assistant Supervisor

DOCUMENT NO :

1
1

Page 24 of 59

PROJEK MENAIKTARAF LEBUHRAYA JOHOR BAHRU - PASIR GUDANG


DARI 4 LORONG KE 6 LORONG, JOHOR

METHOD STATEMENT
( INTERIM )

DISPLACEMENT MONITORING

DOCUMENT NO :
IDX/QAP/MS/DM

1.0 GENERAL
Structures such as bridges and tunnels may be required to be
monitored for horizontal and vertical displacement. It is important
to be able to accurately measure the amount of displacement at
predetermined locations over a period of time.
All survey work associated and undertaken for the monitoring of
structures must be sufficiently accurate to detect horizontal and
vertical movement of + or - 2mm
2.0 SURVEY DATUM
All co-ordinates supplied shall be as per setting out drawings
provided at the latest unless otherwise specified.
3.0 SURVEY CONTROL
Survey control for the monitoring of structures should be
established so that the integrity of the monitoring data can be
guaranteed. 4 points on each structure will be taken into
consideration. The actual co-ordinates and level will be recorded.

APPENDIX A

4.0 SURVEY EQUIPMENT


All instrumentation shall be calibrated on any certified baselines
prior to the commencement of work and be checked and adjusted
for horizontal and vertical collimation.
The instrument will have been serviced by an authorised agent for
that make of instrument within the last 12 months.
5.0 METHOD OF SURVEY
Times of extreme weather (heat and wind) should be avoided. Care
should be taken to avoid monitoring during periods of high traffic
volumes as this may affect the survey results
All targets are interchanged and tribrachs must remain fixed during
observations (forced centering), thus minimizing plumbing erros.
All results should be recorded electronically in the correct format to
allow the reduction of angle sets and distances.
Horizontal Survey
The coordinates for each eight points will be compared weekly and
the differences will be recorded as the horizontal displacement.

Page 25 of 59

APPENDIX A

PROJEK MENAIKTARAF LEBUHRAYA JOHOR BAHRU - PASIR GUDANG


DARI 4 LORONG KE 6 LORONG, JOHOR

METHOD STATEMENT
( INTERIM )

DISPLACEMENT MONITORING

DOCUMENT NO :
IDX/QAP/MS/DM

Vertical Survey
The existing level will be recorded weekly and any reduction will be
recorded as vertical displacement
6.0 RECORDING AND PRESENTATION OF DATA
Survey control points shall be recorded in spreadsheet. Point
identification, easting, northing, elevation and a description of the
point shall be recorded as a minimum. Any subsequent changes in
elevation shall also be recorded. Differences in easting, northing
and RL should be compared to the initial observations and
tabulated. Any movement of 4mm or greater in horizontal position
and 2mm in vertical position should be flagged for further scrutiny.
Digital and hard copies of survey control data shall be provided to
client/S.O following initial and subsequent surveys.
An example of the required format for recording of monitoring
results for structures is included in Appendix B
7.0 SAFETY REQUIREMENT
Only experienced personnel are allowed at working area.
Site personnel must be briefed and be well versed with all site safety
measures.
Site personnel must be in proper safety working attire e.g. Safety boots
and safety vest and helmets must be worn at all times.
Site safety member should be available at all times and must be able to
respond correctly to emergency
Flagman will be provided during the monitoring work conducted

to ensure the safety of the person-in-charge from the heavy traffic


8.0 PLANT & EQUIPMENT

Survey Equipment

9.0 MANPOWER
Land Surveyor
Chainmen

Page 26 of 59

APPENDIX B

PROJEK MENAIKTARAF LEBUHRAYA JOHOR BAHRU - PASIR GUDANG


DARI 4 LORONG KE 6 LORONG, JOHOR

METHOD STATEMENT
( INTERIM )

CONSTRUCTION OF BORED PILE

1.0 INTRODUCTION
1.1 Bore cast-in-situ piles are piles formed by excavating a hole, of the
specified size (diameter), to the required depth and casting the
excavated hole with concrete of specified strength after the
reinforcement is lowered into the holes.
1.1 The purpose of this method statement is to describe the activities and
documentation required to commence the construction of bored pile.
2.0 SCOPE OF WORKS
2.1
2.2
2.2
2.3

Setting Out
Excavation of hole (Boring work)
Reinforcement work
Concreting work

3.0 WORK SEQUENCE FLOW

Site Preparation

Setting Out

Boring Work

Installation of
Casing

Reinforcement
Work

Concreting Work

Testing and
commisioning

END

Page 27 of 59

DOCUMENT NO :
IDX/QAP/MS/BP

Page 28 of 59

PROJEK MENAIKTARAF LEBUHRAYA JOHOR BAHRU - PASIR GUDANG


DARI 4 LORONG KE 6 LORONG, JOHOR

METHOD STATEMENT
( INTERIM )

CONSTRUCTION OF BORED PILE

4.0 METHOD STATEMENT


4.1 SITE PREPARATION
The platform shall be prepared to the required platform level and it
shall be reasonably firm, flat and accessible. Proper drainage
systems shall be provided and a pump sump shall be constructed, if
necessary. A proper access road shall be established prior to the
construction works to allow un-obstructed flow of traffic for
concrete trucks during bore pile casting and for exporting of bore
pile spoil (excavated earth). During the commencement of work, a
steel plate will be placed over the platform to ensure the stability of
the boring plant of top of the platform.
4.2 ADDITIONAL S.I
Before commencement of any boring works, the S.I data must be
obtained for each point involved to determine the hard layer
(N>50). This data will be required to ensure the drilling progress
works well without any obstruction. Modification to the drilling
procedure will be decided once the hard layer is determined.
4.3 SETTING OUT
The contractor shall provide a surveyor for setting out of the pile
points. 2 offset peg will be prepared for each pile points. The pile
points should be set-out as shown in the Construction Drawings.
Attention shall be paid for raking piles and shall be set-out in
accordance to the inclination required in the Construction
Drawings.
4.4 BORING PLANT
The boring plant intended to be used for the site is a Mechanical
Boring Rig Model CMV TRM 35/21 mounted on a 38RB base crane or
equivalent. A telescopic kelly bar of external dimension 400mm
diameter and 4 x 12 metre length is mounted on the boring plant.
The lower end of this Kelly bar is adaptable to other drilling tools,
e.g augers, coring buckets, cleaning buckets, etc.
Before any commencement of work, documentation such as boring
plant catalogue, PMA and operator certificate will be submitted to
client for approval.
4.5 POSITIONING OF BORING PLANT
The boring plant will be moved to the pile point intended for
excavation. The kelly bar mounted with an auger is placed just
above the pile point. The verticality of the kelly bar shall be
checked by means of a spirit level. Adjustment should be made so
as to enable the kelly bar to be as vertical as possible. Then the
position of the auger is checked against the pile point. Adjustment
shall be made so that the centre of the auger is nearest to the pile
point. The auger is then lowered and boring operation commences.
Reasonable care shall be taken so that the pile position and
verticality are constructed within the specified tolerance. The
maximum permitted tolerance shall be 75 mm from the pile
position and the verticality shall not exceed 1 in 75.
Page 29 of 59

DOCUMENT NO :
IDX/QAP/MS/BP

Reasonable care shall be taken so that the pile position and


verticality are constructed within the specified tolerance. The
maximum permitted tolerance shall be 75 mm from the pile
position and the verticality shall not exceed 1 in 75.
PROJEK MENAIKTARAF LEBUHRAYA JOHOR BAHRU - PASIR GUDANG
DARI 4 LORONG KE 6 LORONG, JOHOR

METHOD STATEMENT
( INTERIM )

CONSTRUCTION OF BORED PILE

4.6 BORING
Boring commence after the position of the boring plant is checked.
Usually, an auger of the required size is used to excavate the hole.
During excavation, the hole shall be observed for its stability. If the
excavated hole is collapsible, a temporary casing of the same size
shall be installed using a vibro-hammer, to prevent collapse.
Excavation of the hole then continues until the required depth.
When rock is encountered during the excavation (usually observed
by the difficulty in advancing the excavation) other drilling tools
may be utilised. A rock auger, coring bucket, chisel or a
combination of these tools may be used to break up the rock.
After reaching the required depth, a cleaning bucket shall be used
to clean up the bottom of the borehole. A joint measurement of the
depth shall be made before lowering of the reinforcement and
concreting.
4.7 REINFORCEMENT
Reinforcement for the bored piles shall be pre-fabricated in the
reinforcement yard (near the piling platform) and lifted to the
borehole for placing, using a service crane. After fabrication by the
bar benders, the helical links will be tack welded to the main
reinforcement. Laps are also to be welded sufficiently so that they
remain intact during transportation and handling. 100mm diameter
round spacers will be welded to the reinforcement to provide the
cover to ther reinforcement against the soil during concreting.
4 numbers of sonic logging pipes with 50mm diameter and 6 meter
length will be tack welded to the main reinforcement. Each length
will be jointed by another 6 meter length sonic logging pipes until it
reaches the bottom of the hole. The opening of sonic logging pipe
must be located exactly above the cut-off level (on the same level
as platform level) and be cleared from any debris or blockage by
any means necessary.
The reinforcement will be lowered into the completed borehole,
prior to concreting, by means of a service crane and to be adjusted
to the correct level.
4.8 CONCRETING
Concreting shall commence immediately after the reinforcement is
placed.
Concrete shall be supplied by ready-mixed truck to the pile
positions. The concrete slump to be used shall depend on the
method of concreting, as below.
The tremie pipe shall be extended to the bottom of the excavation.
The tremie pipe shall at all times be embedded in the concrete and
shall be withdrawn after completion of the concreting process. No
direct discharge method shall be used be the borehole is dry or
underwater to avoid segregation.
Page 30 of 59

DOCUMENT NO :
IDX/QAP/MS/BP

The tremie pipe shall be extended to the bottom of the excavation.


The tremie pipe shall at all times be embedded in the concrete and
shall be withdrawn after completion of the concreting process. No
direct discharge method shall be used be the borehole is dry or
underwater to avoid segregation.

PROJEK MENAIKTARAF LEBUHRAYA JOHOR BAHRU - PASIR GUDANG


DARI 4 LORONG KE 6 LORONG, JOHOR

METHOD STATEMENT
( INTERIM )

CONSTRUCTION OF BORED PILE

DOCUMENT NO :
IDX/QAP/MS/BP

4.9 PERMANENT CASING


Permanent casings are to be installed using a vibro-hammer.
Permanent casing shall be driven to a depth that is sufficient to
prevent any collapse of the borehole during the whole installation
process.

Diagram

However, the permanent casing shall be installed after excavation


of hole for 3 meters deep only.
4.10 SEQUENCE OF PILING WORK
The sequence of piling work can be referred to Method Statement
for Temporary Work at Bridge for each bridge involved.

Method Statement for


Temporary Work at Bridge

4.11 RECORDS
All bore piling records are to be recorded in the Bore Log provided.
A copy is enclosed for reference

Bore Log Record

5.0 MATERIAL
Concrete Grade 40/20 Tremie
Reinforcement Steel
Bentonite (If any)

Bar Schedule

6.0 MACHINERY
Vibro hammer
Excavator
Boring Plant
Mobile Crane
Generator Set

1
1
1
1
2

7.0 MANPOWER
Site supervisor
Machine Operator
General Worker

1
4
10

8.0 PRODUCTIVITY
3 days for each point from setting out until cut-off level

Page 31 of 59

PROJEK MENAIKTARAF LEBUHRAYA JOHOR BAHRU - PASIR GUDANG


DARI 4 LORONG KE 6 LORONG, JOHOR

METHOD STATEMENT
( INTERIM )

CONSTRUCTION OF BORED PILE

9.0 SAFETY & ENVIRONMENT REQUIREMENT


9.1 Only experienced personnel are allowed at working area.
9.2 Site personnel must be briefed and be well versed with all site safety
measures.
9.3 Site personnel must be in proper safety working attire e.g. Safety boots
and helmets must be worn at all times.
9.4 Site safety member should be available at all times and must be able to
respond correctly to emergency
9.5 Proper and adequate provisions of Temporary Signage and Barricades at
diversions and haul road as necessary.
9.6 Sludge tank (if any) must be prepared nearby excavation area and
protected from spillage into the nearby river/body water
10.0 INSPECTION AND TEST PLAN/FORMS
As per attached
11.0 Diagram & Drawings
As per attached

Page 32 of 59

DOCUMENT NO :
IDX/QAP/MS/BP

Page 33 of 59

PROJEK MENAIKTARAF LEBUHRAYA JOHOR BAHRU - PASIR GUDANG


DARI 4 LORONG KE 6 LORONG, JOHOR

METHOD STATEMENT
( INTERIM )

STRUCTURAL CONCRETING

1.0 INTRODUCTION
1.1 The purpose of this method statement is to describe the activities and
documentation required for structural concreting for pile cap,
column/abutment wall, deck slab and parapet wall.
2.0 SCOPE OF WORKS
2.1
2.2
2.3
2.4

Reinforcement Work - Handling, Storage, Placement


Formwork - Fabrication, fixing & striking
Concreting - Testing & Placement
Remedial Measures

3.0 WORK SEQUENCE FLOW


Reinforcement - Handling & Storage
START
Delivery of Reinforcement steel
bars
Checking on the Mill Certificate
Identify if the bars free from surface
rust/scale dirt
Unloaded and
stacked in bundles

END

Reinforcement - Placement
START
Checking on concrete cover
Intersecting bars and links - tied together
with binding wire
Lay the reinforcement according to
specification and construction
drawing
Install spacers
Welded if necessary as per instruction (if
any)
Pre-concreting Inspection
END
Page 34 of 59

DOCUMENT NO :
IDX/QAP/MS/STC

END

Page 35 of 59

PROJEK MENAIKTARAF LEBUHRAYA JOHOR BAHRU - PASIR GUDANG


DARI 4 LORONG KE 6 LORONG, JOHOR

METHOD STATEMENT
( INTERIM )

STRUCTURAL CONCRETING

On Site Fabrication & Fixing of Formwork


START
Setting out the reference
line
Setting out the side line of the
structure based on reference
line
Determine the level of the lean
concrete
Clean the base and check the
level
Installation of formwork
Placement of rebar
Checking on any
unwanted opening and
block it
Concreting Work
Striking of formwork
END

Concrete Placement

START
Preliminary Inspection on
Structure
Placing order for concrete
supply
Standby all workmen necessary for
concrete placement work
Arrange rotation of supervisory
staff (if necessary)
Installation of formwork
Placing of concrete
END

Page 36 of 59

DOCUMENT NO :
IDX/QAP/MS/STC

PROJEK MENAIKTARAF LEBUHRAYA JOHOR BAHRU - PASIR GUDANG


DARI 4 LORONG KE 6 LORONG, JOHOR

METHOD STATEMENT
( INTERIM )

STRUCTURAL CONCRETING

4.0 METHOD STATEMENT


4.1 MANUFACTURES AND SUPPLIERS
a) Steel Bars Manufacturers
Steel bars of Grade 500 to be used in the works shall comply with
M.S 146:1988 or BS 4449. These shall be obtained from MaSteel or
any approved manufacturer. Mill Certificate shall be submitted to
S.O.'s Representative for every batch of steel bars delivered to
project sites.
b) Cement
The cement be used in this work shall be complying with
construction drawing provided for this project.
c) Concrete Quality
Element
Blinding Concrete
Cast In-Situ Bored Piles
Pile Cap
Piers & Crossheads
Abutments & Wingwall
Prestressed Concrete
Deck Slab & Diaphragm
Bearing Plinth & Upstand
Bridge Parapets
Retaining Wall
Approach Slab

Grade
15/20
40/20
40/20
40/20
40/20
50/20
40/20
50/20
40/20
40/20
40/20

4.2 MIX DESIGN


Details on every concrete ready mix supplier selected shall be
submitted to the Engineer for approval, which shall include, but not
limited to:
i. Name of Supplier
ii. Design Mix
iii. Grade of Concrete Supplied
iv. Location of Plant
v. Type of Plant (Wet/Dry Mix)
vi. Calibration Certificate of Plant
vii. Source of Aggregate, Cement, Sand, Water and Test Results
viii. Cube Test Results for Trial Mixes
4.3 REINFORCEMENT - HANDLING & STORAGE
a) Reinforcement steel bars shall be delivered at site progressively
b) The supplier or manufacturer shall submit the Mill Certificate before

or during delivery of the steel bars. The Mill Certificates shall


clearly state the grade, quantity, chemical composition, test
results, size, truck registration number and the date of delivery.
Page 37 of 59

DOCUMENT NO :
IDX/QAP/MS/STC

The supplier or manufacturer shall submit the Mill Certificate before


or during delivery of the steel bars. The Mill Certificates shall
clearly state the grade, quantity, chemical composition, test
results, size, truck registration number and the date of delivery.
c) All bars shall be free from surface rust, scale dirt etc.

PROJEK MENAIKTARAF LEBUHRAYA JOHOR BAHRU - PASIR GUDANG


DARI 4 LORONG KE 6 LORONG, JOHOR

METHOD STATEMENT
( INTERIM )

STRUCTURAL CONCRETING

d) Materials so accepted shall be unloaded from the truck by a mobile


crane and stacked in bundles at the fabrication yard according to
their sizes.
e) The rebar shall be stacked at least 6 inches above the ground level.
4.4 REINFORCEMENT - PLACEMENT
a) The engineer shall direct and supervise the personnel responsible
for the placement of rebar in accordance with all related designs,
specifications, conditions of contract and associated procedures.
b) All reinforcement shall be securely placed to ensure against
displacement during the placement of concrete. Provide the
following clear cover to all reinforcement unless otherwise noted on
the drawings.
Element
Cast-Insitu Bored Piles
Pile Caps
Piers & Crossheads
Abutments & Wingwall
Bearing Plinth Upstand
Prestressed Concrete
Bridge Parapets
Pretensioned Beam
Deck Slab and Diaphragm
Retaining Wall Stem
Retaining Wall Base
Approach Slab

Cover to
Reinforcement
75mm
75mm for *BF
45mm for *OF
45mm
45mm
45mm
30mm
45mm
30mm
45mm
45mm
75mm for *BF
45mm for *OF
45mm

Notes: *BF denotes Bottom Face Reinforcement


*OF denotes Other Face Reinforcement
c) Tolerance on nominal cover shall be 5mm.
d) All intersecting bars shall be tied together with binding wire and the

ends of the wire shall be turned into the main body to concrete.
e) Links shall be securely fixed with binding wire to the longitudinal

reinforcement.
f) The reinforcement shall be laid out in accordance with the

approved drawings and schedules. The reinforcement shall be


suspended by annealed wire, supported on concrete spacers to
prevent displacement during the placing and compacting of
concrete.
Spacers, where used to maintain concrete cover to reinforcement,

g) may be either concrete or plastic construction unless otherwise

specified.
Page 38 of 59

DOCUMENT NO :
IDX/QAP/MS/STC

h) Minimum lap length should be referred to construction drawing provided.


i) Unless otherwise shown on the drawing, splices in adjacent bars
shall be staggered.

PROJEK MENAIKTARAF LEBUHRAYA JOHOR BAHRU - PASIR GUDANG


DARI 4 LORONG KE 6 LORONG, JOHOR

METHOD STATEMENT
( INTERIM )

STRUCTURAL CONCRETING

j) On no account shall reinforcement be heated to facilitate bending.


Reinforcement shall not be re-bent unless approved by the
Engineer.
k) Reinforcement in structures shall not be welded without the
approval of the Engineer.
l) The supervisor shall also ensure that all required builder's work in
connection with M&E requirements including openings, conduits,
block outs, puddle flanges etc. are installed before placement of
the top bars.
m) Carry out inspection on reinforcement placed as per Pre-Concreting
Checklist. Bar bending schedule shall be submitted before
concreting.
4.5 ON SITE FABRICATION & FIXING OF FORMWORK
a) The surveyor will first set up a reference line offset from the
nearest TBM or from a previously constructed structure with
established survey data.
b) The subcontractors shall determine the side line of the structure of

offsetting from the reference points, established by the surveyor


using string lines and measuring tapes.
c) Before installation of formwork, the surveyor shall survey the level

of the lean concrete and the Engineer shall ensure that the base is
clean and level.
d) For horizontal structures, one side of the form shall be erected
initially along the stringed side line. Temporary strutts and shores
are placed to hold the form in position.
After the placement of rebar, the other side of the form shall be
e) erected. Straightness and verticality check executed and strutts
secured in placed together with horizontal braces to maintain the
required width throughout.

f) Where holes are needed in formwork to accommodate projecting


reinforcement starters, services of fixing devices, care shall be
taken to ensure that all holes or openings are plugged or blocked to
prevent the loss of grout when concreting or damage to the
concrete surface when removing forms.
g) Before concreting, the Site Supervisor shall ensure that all forms
are thoroughly cleaned out, free from sawdust shavings, dust, mud
or other debris and deleterious matter by using appropriate tools
and equipments as follows:
i) Mud deposits on or in formwork shall be removed by brushing or
Page 39 of 59

DOCUMENT NO :
IDX/QAP/MS/STC

water jet as required.


ii) Sawdust shavings, dust or loose particles and matters can be moved
to a corner using a compressor. These can be removed by sweeping
into a bin if a hatch opening is provided for.
h) The formwork face in contact with the concrete shall be coated with

a suitable mould oil or approved release agent. Such oils or release


agents shall not come into contact with the reinforcement.
PROJEK MENAIKTARAF LEBUHRAYA JOHOR BAHRU - PASIR GUDANG
DARI 4 LORONG KE 6 LORONG, JOHOR

METHOD STATEMENT
( INTERIM )

STRUCTURAL CONCRETING

i) All forms shall be formally inspected by the Engineer after


preparation and prior to placing of concrete as per Pre-Concreting
Checklist. No placing of concrete shall be commenced until the
formwork has been approved.
4.6 STRIKING OF FORMWORK
a) The Sub-contactors shall liase with the Engineer to obtain approval
before striking any formwork and to conduct inspection after
striking of forms as per Post Concreting Checklist.
b) The removal shall be done in such a manner as not to damage the
concrete and shall take place at times to suit the requirements for
its curing.
c) Where it is intended that forms are to be reused, it shall be cleaned
and made good to the approval of the S.O's representative.
4.7 PREPARATION FOR CONCRETING
Upon completion of the formwork, reinforcement and all associated
a) builder's works in connection with the Mechanical, Electrical and
other related services the Supervisor shall undertake a preliminary
inspection to ensure that such items are complete and in
accordance with all controlling relevant construction drawings and
pre concreting checklists.
b) Following this preliminary inspection the Site Supervisor shall
advise the Project Manager who shall ensure that the following
arrangements have been or being made prior to placement.
c) Place an order for the supply of concrete on a scheduled date.
d) Standby all workmen necessary to carry out the works till
completion. For long hours (more than 16 hours), shift may be
required and night lighting a must.
e) Arrange the rotation of supervisory staff.
4.8 PLACING OF CONCRETE
a) For lean concreting, a minimum of 50mm thickness blinding layer
shall be laid on well prepared firm ground after or before formwork
is placed in position.
b) Concrete shall be placed into the forms or excavations using the
appropriate plant and equipment for the purpose including direct
chute discharge from concrete mixer trucks, concrete pumps or
crane assisted concrete bucket.
Page 40 of 59

DOCUMENT NO :
IDX/QAP/MS/STC

Concrete shall be placed into the forms or excavations using the


appropriate plant and equipment for the purpose including direct
chute discharge from concrete mixer trucks, concrete pumps or
crane assisted concrete bucket.
c) Concreting shall start fresh or from a predetermined construction

joint and shall continue uninterrupted up to the next predetermined


construction joint or completion.
d) If concreting is to commence from a construction joint, the said

joint shall be roughened before receiving fresh concrete and mortar


water must also be poured over this area.
PROJEK MENAIKTARAF LEBUHRAYA JOHOR BAHRU - PASIR GUDANG
DARI 4 LORONG KE 6 LORONG, JOHOR

METHOD STATEMENT
( INTERIM )

STRUCTURAL CONCRETING

e) Placement of concrete shall be in horizontal layers and to a


compact depth not exceeding 450mm. The rate of discharge shall
be such that the concrete placement is uniform across the section
and increasing at a rate to prevent segregation of the bottom
layers.
f) Compaction shall be carried out by both hand tamping and
mechanical vibrator and shall be thoroughly worked into corners.
g) To avoid a vertical drop of concrete greater than 1.5 metres,
trunking and chutes shall be used.
h) Fresh concrete shall not be placed against in-situ concrete during
the pouring sequence within certain time limits based upon the
design mix of the concrete. No pouring of water into semi-hardness
concrete in the truck is allowed.
i) Concreting operation shall cease immediately if leaks occurs in the

formwork and shall be rectified on the spot.


j) All concrete, after it has set shall be kept continuously damp by
placing wet jute sack on top of the surface.
k) The use of any curing compound shall be subjected to the approval
of the Engineer.
4.9 CONSTRUCTION JOINTS
a) Construction joints shall be located in the positions as shown on
drawings or as required.
b) The joints shall be at right angles to the general direction of the
member and shall take due account of shear and other stresses.
c) Concrete shall not be allowed to run to a feather edge and vertical
joints shall be formed against a stop board.
4.10 TESTING OF CONCRETE WORKS
a) The indicative sampling rate shall be as follows:
- One sample per 10.0 m3 or every group of 10 batches for critical
structures such as columns, pile caps and abutment wall.
- One sample per 20.0 m3 or every group of 20 batches for slabs.

Page 41 of 59

DOCUMENT NO :
IDX/QAP/MS/STC

c)

However, for designed mix, at least four samples (12 cubes) shall
be taken of concrete on the first day of concreting for each grade of
concrete to be used in the Work, irrespective of the volume of
concrete produced or the sampling rate. Subsequent rate of
sampling shall be at least one sample from each source of
production on each day that concrete of any particular grade is
used.

PROJEK MENAIKTARAF LEBUHRAYA JOHOR BAHRU - PASIR GUDANG


DARI 4 LORONG KE 6 LORONG, JOHOR

METHOD STATEMENT
( INTERIM )

STRUCTURAL CONCRETING

d) The actual rate of sampling may be increased in appropriate


circumstances e.g. for critical elements, when required by the S.O.
For each sampling, three cubes shall be made from a single sample
e) taken from a randomly selected bacth of concrete. The sample shall
be taken at the point of discharge from the mixer or, in the case of
ready mixed concrete, at the point of discharge from the delivery
vehicle.
f) All cubes shall be clearly marked with undeletable paint with the
date of casting and serial number.
A record shall be clearly kept to identify each cube by date and by
g) serial number relating to the part of the work from which they are
taken.
h) One cube from each sample batch shall be tested for the 7-day
compressive strength. The remaining two cubes from the sample
batch shall be tested for the 28-day compressive strength.
5.0 MATERIAL
Concrete Grade 40/50/55
Reinforcement Steel
Formwork (Steel/Wood)
Scaffolding
6.0 MACHINERY
Concrete Lorry
Excavator
Mechanical Vibrator
Mobile Crane
Generator Set
Air compressor
Water pump
Concrete mixer

5
1
1
1
2
1
1
1

7.0 MANPOWER
Site supervisor
Machine Operator
General Worker

1
2
10

Page 42 of 59

DOCUMENT NO :
IDX/QAP/MS/STC

8.0 SAFETY & ENVIRONMENT REQUIREMENT


8.1 Only experienced personnel are allowed at working area.
8.2 Site personnel must be briefed and be well versed with all site safety
measures.
8.3 Site personnel must be in proper safety working attire e.g. Safety boots
and helmets must be worn at all times.
8.4 Site safety member should be available at all times and must be able to
respond correctly to emergency
8.4 Proper and adequate provisions of Temporary Signage and Barricades at
diversions and haul road as necessary.
PROJEK MENAIKTARAF LEBUHRAYA JOHOR BAHRU - PASIR GUDANG
DARI 4 LORONG KE 6 LORONG, JOHOR

METHOD STATEMENT
( INTERIM )

STRUCTURAL CONCRETING

8.5 All the leftover/debris shall be removed and collected at one


specific location before being carried away from site in accordance
with environment protection specification.
9.0 INSPECTION AND TEST PLAN/FORMS
As per attached
10.0 PRODUCTIVITY RATE

Page 43 of 59

DOCUMENT NO :
IDX/QAP/MS/STC

Page 44 of 59

PROJEK MENAIKTARAF LEBUHRAYA JOHOR BAHRU - PASIR GUDANG


DARI 4 LORONG KE 6 LORONG, JOHOR

METHOD STATEMENT
( INTERIM )

STRUCTURAL CONCRETING

1.0 INTRODUCTION
1.1

This work shall consists of AnchorSOL retaining wall constructed in


accordance witht these specifications and in reasonably close
conformity with the lines, grades, design and dimensions shown on
the drawing or established by the Superintendent Officer (S.O)

2.0 SCOPE OF WORKS


2.1
2.2
2.3
2.4

Reinforcement Work - Handling, Storage, Placement


Formwork - Fabrication, fixing & striking
Concreting - Testing & Placement
Remedial Measures

3.0 WORK SEQUENCE FLOW


Reinforcement - Handling & Storage
START
Delivery of Reinforcement steel
bars
Checking on the Mill Certificate
Identify if the bars free from surface
rust/scale dirt
Unloaded and
stacked in bundles

END

Reinforcement - Placement
START
Checking on concrete cover
Intersecting bars and links - tied together
with binding wire
Lay the reinforcement according to
specification and construction
drawing
Install spacers
Welded if necessary as per instruction (if
any)
Pre-concreting Inspection

Page 45 of 59

DOCUMENT NO :
IDX/QAP/MS/STC

END

Page 46 of 59

PROJEK MENAIKTARAF LEBUHRAYA JOHOR BAHRU - PASIR GUDANG


DARI 4 LORONG KE 6 LORONG, JOHOR

METHOD STATEMENT
( INTERIM )

STRUCTURAL CONCRETING

On Site Fabrication & Fixing of Formwork


START
Setting out the reference
line
Setting out the side line of the
structure based on reference
line
Determine the level of the lean
concrete
Clean the base and check the
level
Installation of formwork
Placement of rebar
Checking on any
unwanted opening and
block it
Concreting Work
Striking of formwork
END

Concrete Placement

START
Preliminary Inspection on
Structure
Placing order for concrete
supply
Standby all workmen necessary for
concrete placement work
Arrange rotation of supervisory
staff (if necessary)
Installation of formwork
Placing of concrete
END

Page 47 of 59

DOCUMENT NO :
IDX/QAP/MS/STC

PROJEK MENAIKTARAF LEBUHRAYA JOHOR BAHRU - PASIR GUDANG


DARI 4 LORONG KE 6 LORONG, JOHOR

METHOD STATEMENT
( INTERIM )

STRUCTURAL CONCRETING

4.0 METHOD STATEMENT


4.1 MANUFACTURES AND SUPPLIERS
a) Steel Bars Manufacturers
Steel bars of Grade 500 to be used in the works shall comply with
M.S 146:1988 or BS 4449. These shall be obtained from MaSteel or
any approved manufacturer. Mill Certificate shall be submitted to
S.O.'s Representative for every batch of steel bars delivered to
project sites.
b) Cement
The cement be used in this work shall be complying with
construction drawing provided for this project.
c) Concrete Quality
Element
Blinding Concrete
Cast In-Situ Bored Piles
Pile Cap
Piers & Crossheads
Abutments & Wingwall
Prestressed Concrete
Deck Slab & Diaphragm
Bearing Plinth & Upstand
Bridge Parapets
Retaining Wall
Approach Slab

Grade
15/20
40/20
40/20
40/20
40/20
50/20
40/20
50/20
40/20
40/20
40/20

4.2 MIX DESIGN


Details on every concrete ready mix supplier selected shall be
submitted to the Engineer for approval, which shall include, but not
limited to:
i. Name of Supplier
ii. Design Mix
iii. Grade of Concrete Supplied
iv. Location of Plant
v. Type of Plant (Wet/Dry Mix)
vi. Calibration Certificate of Plant
vii. Source of Aggregate, Cement, Sand, Water and Test Results
viii. Cube Test Results for Trial Mixes
4.3 REINFORCEMENT - HANDLING & STORAGE
a) Reinforcement steel bars shall be delivered at site progressively
b) The supplier or manufacturer shall submit the Mill Certificate before

or during delivery of the steel bars. The Mill Certificates shall


clearly state the grade, quantity, chemical composition, test
results, size, truck registration number and the date of delivery.
Page 48 of 59

DOCUMENT NO :
IDX/QAP/MS/STC

The supplier or manufacturer shall submit the Mill Certificate before


or during delivery of the steel bars. The Mill Certificates shall
clearly state the grade, quantity, chemical composition, test
results, size, truck registration number and the date of delivery.
c) All bars shall be free from surface rust, scale dirt etc.

PROJEK MENAIKTARAF LEBUHRAYA JOHOR BAHRU - PASIR GUDANG


DARI 4 LORONG KE 6 LORONG, JOHOR

METHOD STATEMENT
( INTERIM )

STRUCTURAL CONCRETING

d) Materials so accepted shall be unloaded from the truck by a mobile


crane and stacked in bundles at the fabrication yard according to
their sizes.
e) The rebar shall be stacked at least 6 inches above the ground level.
4.4 REINFORCEMENT - PLACEMENT
a) The engineer shall direct and supervise the personnel responsible
for the placement of rebar in accordance with all related designs,
specifications, conditions of contract and associated procedures.
b) All reinforcement shall be securely placed to ensure against
displacement during the placement of concrete. Provide the
following clear cover to all reinforcement unless otherwise noted on
the drawings.
Element
Cast-Insitu Bored Piles
Pile Caps
Piers & Crossheads
Abutments & Wingwall
Bearing Plinth Upstand
Prestressed Concrete
Bridge Parapets
Pretensioned Beam
Deck Slab and Diaphragm
Retaining Wall Stem
Retaining Wall Base
Approach Slab

Cover to
Reinforcement
75mm
75mm for *BF
45mm for *OF
45mm
45mm
45mm
30mm
45mm
30mm
45mm
45mm
75mm for *BF
45mm for *OF
45mm

Notes: *BF denotes Bottom Face Reinforcement


*OF denotes Other Face Reinforcement
c) Tolerance on nominal cover shall be 5mm.
d) All intersecting bars shall be tied together with binding wire and the

ends of the wire shall be turned into the main body to concrete.
e) Links shall be securely fixed with binding wire to the longitudinal

reinforcement.
f) The reinforcement shall be laid out in accordance with the

approved drawings and schedules. The reinforcement shall be


suspended by annealed wire, supported on concrete spacers to
prevent displacement during the placing and compacting of
concrete.
Spacers, where used to maintain concrete cover to reinforcement,

g) may be either concrete or plastic construction unless otherwise

specified.
Page 49 of 59

DOCUMENT NO :
IDX/QAP/MS/STC

h) Minimum lap length should be referred to construction drawing provided.


i) Unless otherwise shown on the drawing, splices in adjacent bars
shall be staggered.

PROJEK MENAIKTARAF LEBUHRAYA JOHOR BAHRU - PASIR GUDANG


DARI 4 LORONG KE 6 LORONG, JOHOR

METHOD STATEMENT
( INTERIM )

STRUCTURAL CONCRETING

j) On no account shall reinforcement be heated to facilitate bending.


Reinforcement shall not be re-bent unless approved by the
Engineer.
k) Reinforcement in structures shall not be welded without the
approval of the Engineer.
l) The supervisor shall also ensure that all required builder's work in
connection with M&E requirements including openings, conduits,
block outs, puddle flanges etc. are installed before placement of
the top bars.
m) Carry out inspection on reinforcement placed as per Pre-Concreting
Checklist. Bar bending schedule shall be submitted before
concreting.
4.5 ON SITE FABRICATION & FIXING OF FORMWORK
a) The surveyor will first set up a reference line offset from the
nearest TBM or from a previously constructed structure with
established survey data.
b) The subcontractors shall determine the side line of the structure of

offsetting from the reference points, established by the surveyor


using string lines and measuring tapes.
c) Before installation of formwork, the surveyor shall survey the level

of the lean concrete and the Engineer shall ensure that the base is
clean and level.
d) For horizontal structures, one side of the form shall be erected
initially along the stringed side line. Temporary strutts and shores
are placed to hold the form in position.
After the placement of rebar, the other side of the form shall be
e) erected. Straightness and verticality check executed and strutts
secured in placed together with horizontal braces to maintain the
required width throughout.

f) Where holes are needed in formwork to accommodate projecting


reinforcement starters, services of fixing devices, care shall be
taken to ensure that all holes or openings are plugged or blocked to
prevent the loss of grout when concreting or damage to the
concrete surface when removing forms.
g) Before concreting, the Site Supervisor shall ensure that all forms
are thoroughly cleaned out, free from sawdust shavings, dust, mud
or other debris and deleterious matter by using appropriate tools
and equipments as follows:
i) Mud deposits on or in formwork shall be removed by brushing or
Page 50 of 59

DOCUMENT NO :
IDX/QAP/MS/STC

water jet as required.


ii) Sawdust shavings, dust or loose particles and matters can be moved
to a corner using a compressor. These can be removed by sweeping
into a bin if a hatch opening is provided for.
h) The formwork face in contact with the concrete shall be coated with

a suitable mould oil or approved release agent. Such oils or release


agents shall not come into contact with the reinforcement.
PROJEK MENAIKTARAF LEBUHRAYA JOHOR BAHRU - PASIR GUDANG
DARI 4 LORONG KE 6 LORONG, JOHOR

METHOD STATEMENT
( INTERIM )

STRUCTURAL CONCRETING

i) All forms shall be formally inspected by the Engineer after


preparation and prior to placing of concrete as per Pre-Concreting
Checklist. No placing of concrete shall be commenced until the
formwork has been approved.
4.6 STRIKING OF FORMWORK
a) The Sub-contactors shall liase with the Engineer to obtain approval
before striking any formwork and to conduct inspection after
striking of forms as per Post Concreting Checklist.
b) The removal shall be done in such a manner as not to damage the
concrete and shall take place at times to suit the requirements for
its curing.
c) Where it is intended that forms are to be reused, it shall be cleaned
and made good to the approval of the S.O's representative.
4.7 PREPARATION FOR CONCRETING
Upon completion of the formwork, reinforcement and all associated
a) builder's works in connection with the Mechanical, Electrical and
other related services the Supervisor shall undertake a preliminary
inspection to ensure that such items are complete and in
accordance with all controlling relevant construction drawings and
pre concreting checklists.
b) Following this preliminary inspection the Site Supervisor shall
advise the Project Manager who shall ensure that the following
arrangements have been or being made prior to placement.
c) Place an order for the supply of concrete on a scheduled date.
d) Standby all workmen necessary to carry out the works till
completion. For long hours (more than 16 hours), shift may be
required and night lighting a must.
e) Arrange the rotation of supervisory staff.
4.8 PLACING OF CONCRETE
a) For lean concreting, a minimum of 50mm thickness blinding layer
shall be laid on well prepared firm ground after or before formwork
is placed in position.
b) Concrete shall be placed into the forms or excavations using the
appropriate plant and equipment for the purpose including direct
chute discharge from concrete mixer trucks, concrete pumps or
crane assisted concrete bucket.
Page 51 of 59

DOCUMENT NO :
IDX/QAP/MS/STC

Concrete shall be placed into the forms or excavations using the


appropriate plant and equipment for the purpose including direct
chute discharge from concrete mixer trucks, concrete pumps or
crane assisted concrete bucket.
c) Concreting shall start fresh or from a predetermined construction

joint and shall continue uninterrupted up to the next predetermined


construction joint or completion.
d) If concreting is to commence from a construction joint, the said

joint shall be roughened before receiving fresh concrete and mortar


water must also be poured over this area.
PROJEK MENAIKTARAF LEBUHRAYA JOHOR BAHRU - PASIR GUDANG
DARI 4 LORONG KE 6 LORONG, JOHOR

METHOD STATEMENT
( INTERIM )

STRUCTURAL CONCRETING

e) Placement of concrete shall be in horizontal layers and to a


compact depth not exceeding 450mm. The rate of discharge shall
be such that the concrete placement is uniform across the section
and increasing at a rate to prevent segregation of the bottom
layers.
f) Compaction shall be carried out by both hand tamping and
mechanical vibrator and shall be thoroughly worked into corners.
g) To avoid a vertical drop of concrete greater than 1.5 metres,
trunking and chutes shall be used.
h) Fresh concrete shall not be placed against in-situ concrete during
the pouring sequence within certain time limits based upon the
design mix of the concrete. No pouring of water into semi-hardness
concrete in the truck is allowed.
i) Concreting operation shall cease immediately if leaks occurs in the

formwork and shall be rectified on the spot.


j) All concrete, after it has set shall be kept continuously damp by
placing wet jute sack on top of the surface.
k) The use of any curing compound shall be subjected to the approval
of the Engineer.
4.9 CONSTRUCTION JOINTS
a) Construction joints shall be located in the positions as shown on
drawings or as required.
b) The joints shall be at right angles to the general direction of the
member and shall take due account of shear and other stresses.
c) Concrete shall not be allowed to run to a feather edge and vertical
joints shall be formed against a stop board.
4.10 TESTING OF CONCRETE WORKS
a) The indicative sampling rate shall be as follows:
- One sample per 10.0 m3 or every group of 10 batches for critical
structures such as columns, pile caps and abutment wall.
- One sample per 20.0 m3 or every group of 20 batches for slabs.

Page 52 of 59

DOCUMENT NO :
IDX/QAP/MS/STC

c)

However, for designed mix, at least four samples (12 cubes) shall
be taken of concrete on the first day of concreting for each grade of
concrete to be used in the Work, irrespective of the volume of
concrete produced or the sampling rate. Subsequent rate of
sampling shall be at least one sample from each source of
production on each day that concrete of any particular grade is
used.

PROJEK MENAIKTARAF LEBUHRAYA JOHOR BAHRU - PASIR GUDANG


DARI 4 LORONG KE 6 LORONG, JOHOR

METHOD STATEMENT
( INTERIM )

STRUCTURAL CONCRETING

d) The actual rate of sampling may be increased in appropriate


circumstances e.g. for critical elements, when required by the S.O.
For each sampling, three cubes shall be made from a single sample
e) taken from a randomly selected bacth of concrete. The sample shall
be taken at the point of discharge from the mixer or, in the case of
ready mixed concrete, at the point of discharge from the delivery
vehicle.
f) All cubes shall be clearly marked with undeletable paint with the
date of casting and serial number.
A record shall be clearly kept to identify each cube by date and by
g) serial number relating to the part of the work from which they are
taken.
h) One cube from each sample batch shall be tested for the 7-day
compressive strength. The remaining two cubes from the sample
batch shall be tested for the 28-day compressive strength.
5.0 MATERIAL
Concrete Grade 40/50/55
Reinforcement Steel
Formwork (Steel/Wood)
Scaffolding
6.0 MACHINERY
Concrete Lorry
Excavator
Mechanical Vibrator
Mobile Crane
Generator Set
Air compressor
Water pump
Concrete mixer

5
1
1
1
2
1
1
1

7.0 MANPOWER
Site supervisor
Machine Operator
General Worker

1
2
10

Page 53 of 59

DOCUMENT NO :
IDX/QAP/MS/STC

8.0 SAFETY & ENVIRONMENT REQUIREMENT


8.1 Only experienced personnel are allowed at working area.
8.2 Site personnel must be briefed and be well versed with all site safety
measures.
8.3 Site personnel must be in proper safety working attire e.g. Safety boots
and helmets must be worn at all times.
8.4 Site safety member should be available at all times and must be able to
respond correctly to emergency
8.4 Proper and adequate provisions of Temporary Signage and Barricades at
diversions and haul road as necessary.
PROJEK MENAIKTARAF LEBUHRAYA JOHOR BAHRU - PASIR GUDANG
DARI 4 LORONG KE 6 LORONG, JOHOR

METHOD STATEMENT
( INTERIM )

STRUCTURAL CONCRETING

8.5 All the leftover/debris shall be removed and collected at one


specific location before being carried away from site in accordance
with environment protection specification.
9.0 INSPECTION AND TEST PLAN/FORMS
As per attached
10.0 PRODUCTIVITY RATE

Page 54 of 59

DOCUMENT NO :
IDX/QAP/MS/STC

Page 55 of 59

PROJEK MENAIKTARAF LEBUHRAYA JOHOR BAHRU - PASIR GUDANG


DARI 4 LORONG KE 6 LORONG, JOHOR

TEMPORARY WORK FOR BORED PILING


WORK FOR BRIDGE OVER PLENTONG
INTERSECTION - B5

METHOD STATEMENT
( INTERIM )

1.0 INTRODUCTION
1.1 The purpose of this method statement is to describe the activities an
documentation required to commence the temporary work for bridge
2.0 SCOPE OF WORKS
2.1 Preparation of access road
2.2 Preparation of temporary platform
2.3 Installation of sheet pile
3.0 WORK SEQUENCE FLOW
START
Setting out

Site clearing &


preparing access road
Preparation of
temporary platform
Installation of
sheet pile
Bored piling
work
commence
Construction of pile
cap and half of pier
Backfilling
work
Removal of
sheet pile
END

Page 56 of 59

DOCUMENT NO :
IDX/QAP/MS/TWB5

PROJEK MENAIKTARAF LEBUHRAYA JOHOR BAHRU - PASIR GUDANG


DARI 4 LORONG KE 6 LORONG, JOHOR

METHOD STATEMENT
( INTERIM )

DOCUMENT NO :

TEMPORARY WORK FOR BORED PILING


WORK FOR BRIDGE OVER PLENTONG
INTERSECTION - B5

IDX/QAP/MS/TWB5

4.0 METHOD STATEMENT


4.1 SETTING OUT
4.1.1 The land surveyor will identify the Right of Way boundary and location
of the piling point.
4.1.2 Offset for the piling point, finished road level, cut off level will be
provided at the peg allocated for the piling point.
4.2 SITE CLEARING
4.2.1 The site clearing will be performed at the allocated location.

IDX/QAP/MS/SC

4.2.2 The opening as a mean of access to the location will be constructed


and filling and cutting of the OGL are required until the difference in
ground level is appropriate for machineries and transportation
4.2.3 The location of machineries, the opening, the material will be arrang
based on the suitability of site condition
4.3 CONSTRUCTION OF THE WORKING PLATFORM
4.3.1 The working platform is prepared as per cut off level reference.
The excavation will take place and the leveling of the area is performed
until it reaches a satisfactory perimeter for the bored piling machine
maneuver.
4.4 INSTALLATION OF SHEET PILE
4.4.1 The access and platform for vibro hammer will be prepared by means
of leveling and cut and fill method
4.4.2 The vibro hammer will install the sheet pile as per diagram

TEMP/CROSS-SECT-B8-S1

4.4.3 Previously the design calculation for sheet piling had been worked ou
as a reference for the installation of sheet pile work

Attachment 1

4.5 COMMENCEMENT OF BORED PILING & SUB STRUCTURE WORK


4.5.1 Once the sheet pile has been installed, the leveling work continues
until it is appropriate for bored piling machine to operate on the platform
4.5.2 The bored piling work commence

IDX/QAP/MS/BPW

4.5.3 The pile cap and pier will be constructed and once the base is backfil
as per construction drawing and under permission by S.O
the sheet pile will be removed from the base

IDX/QAP/MS/SSW
IDX/QAP/MS/CPC

Page 57 of 59

PROJEK MENAIKTARAF LEBUHRAYA JOHOR BAHRU - PASIR GUDANG


DARI 4 LORONG KE 6 LORONG, JOHOR

TEMPORARY WORK FOR BORED PILING


WORK FOR BRIDGE OVER PLENTONG
INTERSECTION - B5

METHOD STATEMENT
( INTERIM )

DOCUMENT NO :
IDX/QAP/MS/TWB5

4.5.4 The sheet pile will be transferred to the another working platform and
installed there as per diagram
4.6 SHEET PILE & STEEL PLATE DESCRIPTION
4.6.1 The sheet pile to be used is Type IIIA (refer to the attachment)
4.7 SEQUENCES OF WORK
4.7.1 The working platform will be prepared as per this sequence:
Pier 2-1

Pier 3 - 1

Pier 1-2

Pier 2

Pier 3

Pier 1

Abutment A

Abutment B

Abutment B-1

TEMP/SEQ-B8-S1

Abutment A - 1

Page 58 of 59

PROJEK MENAIKTARAF LEBUHRAYA JOHOR BAHRU - PASIR GUDANG


DARI 4 LORONG KE 6 LORONG, JOHOR

TEMPORARY WORK FOR BORED PILING


WORK FOR BRIDGE OVER PLENTONG
INTERSECTION - B5

METHOD STATEMENT
( INTERIM )

5.0 SAFETY REQUIREMENT


5.1 The existing traffic flow will be monitored by traffic supervision team
and mobilization and demobilization of machineries are not allowed
if the traffic supervision team is not available.
5.2 Only experienced personnel are allowed at working area.
5.3 Site personnel must be briefed and be well versed with all site safety
measures.
5.4 Site personnel must be in proper safety working attire e.g. Safety boots
and helmets must be worn at all times.
5.5 Site safety member should be available at all times and must be able to
respond correctly to emergency
5.6 Proper and adequate provisions of Temporary Signage and Barricades
at diversions and haul road as necessary.

6.0 PLANT AND EQUIPMENT

Excavator
Roller compactor
Backpusher
Tipper
Vibro Hammer

2
2
1
1
1

nos
nos
nos
nos
nos

7.0 MANPOWER

Supervisor
Machine operator
General Worker

1 person
7 persons
4 persons

Page 59 of 59

DOCUMENT NO :
IDX/QAP/MS/TWB5