DOCUMENT NO :
FLEXIBLE PAVEMENT
JSSB/QAP/MS/PAV
Reference :
1.0 SCOPE OF WORKS
1.1
Contract document
Sect.4/PAV
JKR/SPJ/2005
To determine existing and to fix pavement level, cross fall and alignment
shall be carried out.
2.2
Setting out and control pegs shall be installed on site to control :2.2.1
2.2.2
2.2.3
2.2.4
2.2.5
2.2.6
2.2.7
3.1
3.2
3.3
The speed limit for the traffic along the diversion shall be as requirement.
3.4
The diversion shall be well sealed with premix and to be maintained regularly.
3.5
Page 1 of 59
DOCUMENT NO :
FLEXIBLE PAVEMENT
JSSB/QAP/MS/PAV
Reference :
4.0 SURFACE DRAINAGE
4.1
Prior to any pavement work, all drainage system shall be present and
functional.
4.2
Contract document
Sect.4/PAV
JKR/SPJ/2005
5.2
5.3
The compaction shall be checked by the Field Density Test 95% the
Relative Compaction.
5.4
5.5
Subgrade shall be developed along the full width of the carriage way and
compacted in longitudinal direction from the outer edge to the inner edge
and shall be from the lower end to the higher end in the super-elevated
areas.
5.6
5.7
The line and level shall be control by dipping pegs, which indicated the
offsets and levels.
SUB BASE
6.1.1
Prior to laying any sub base material, the under laying
subgrade shall have been shaped and compacted as per
requirements.
Page 2 of 59
FLEXIBLE PAVEMENT
DOCUMENT NO :
JSSB/QAP/MS/PAV
Reference :
6.1.2
6.1.3
6.1.4
6.1.5
6.1.6
6.1.7
Compaction requirement
6.1.7.1
Compaction is not less 95% of the maximum
dry density as determined by BS 1377 test
(4.5 kg rammer method )
6.1.8
Field Control
6.1.8.1
6.2
ROAD BASE
6.2.1
6.2.2
6.2.3
Page 3 of 59
Contract document
Sect.4/PAV
JKR/SPJ/2005
6.2.4
FLEXIBLE PAVEMENT
Reference :
Cleanliness, uniformity or moisture and prevention of physical
segregation of the material shall always be ensured and
Contract document
compaction shall be provided using a suitable compacting
Sect.4/PAV
plant and tested.
JKR/SPJ/2005
6.2.5
6.2.6
Compaction requirement
6.2.6.1
6.3
6.2.6.2
6.2.6.3
BITUMINOUS COATING
6.3.1
6.3.2
DOCUMENT NO :
JSSB/QAP/MS/PAV
Prime coat.
6.3.2.1
6.3.2.2
6.3.2.3
Page 4 of 59
FLEXIBLE PAVEMENT
DOCUMENT NO :
JSSB/QAP/MS/PAV
Reference :
6.3.2.4
6.3.3
6.3.4
Tack Coat
6.3.3.1
6.3.3.2
6.3.3.3
6.3.3.4
Field Control
These shall be carried out to assess and determine the rate
of spread. A tray will be weighed, measured and will be put at
the middle of area to be sprayed. Hence, the rate of the
spread will be determine as follows :
Rate of spread :
7.2
The surface to receive the asphaltic concrete binder course shall be free
of all dirt, loose material and water ponding.
7.3
The approved mix shall be delivered to site by tipper trucks covered with
tarpaulin to prevent heat lost.
7.4
The asphaltic concrete shall be laid using Vogele Super 1502 paver or
equivalent in single layer.
Page 5 of 59
Contract document
Sect.4/PAV
JKR/SPJ/2005
7.5
7.6
FLEXIBLE PAVEMENT
DOCUMENT NO :
JSSB/QAP/MS/PAV
Reference :
If the laid surface in open-textured, back casting shall be carried out and
the bigger size of aggregates shall be removed before rolling.
Contract document
Sect.4/PAV
The transverse joint shall be feathered down, at the end of the pavin
JKR/SPJ/2005
operation on ( and vertical joint shall be provided ). Tack coat shall be
uniformly applied evenly over the vertically cut joint 15 minutes before
jointing.
7.7
7.8
The surface shall be finished to the grade and line as required. Dipping at
12.5m intervals shall be carried out and to check that the tolerance of
5mm is achieved.
7.9
COMPACTION REQUIREMENT
7.9.1
7.9.2
7.10.1.2
Page 6 of 59
FLEXIBLE PAVEMENT
DOCUMENT NO :
JSSB/QAP/MS/PAV
Reference :
7.10.1.3
Breakdown Rolling
Intermediate Rolling
Final Rolling
8.2
Apply tack coat on the prepared surface. The full width of surface to the
treated shall be swept using a power broom followed by a compressed
air blower to remove all dirt, dust and loose material.
8.3
8.4
The asphaltic concrete wearing course shall be laid using paver in single
layer and the temperature of mix shall not less than 125C prior to
unloading from truck into the paver.
8.5
8.6
8.7
8.8
Page 7 of 59
Contract document
Sect.4/PAV
JKR/SPJ/2005
FLEXIBLE PAVEMENT
DOCUMENT NO :
JSSB/QAP/MS/PAV
Reference :
8.9
COMPACTION REQUIREMENT
8.9.1
8.9.2
8.10.1.2
Breakdown Rolling
Intermediate Rolling
Final Rolling
Page 8 of 59
Contract document
Sect.4/PAV
JKR/SPJ/2005
FLEXIBLE PAVEMENT
DOCUMENT NO :
JSSB/QAP/MS/PAV
Reference :
EQUIPMENT/ MANPOWER/ TEST
a)
b)
no
no
no
nos
nos
nos
no
no
MANPOWER
Supervisor
Machine operator
General Worker
c)
1
1
1
2
1
3
1
1
1 nos
10 nos
6 nos
TEST
Refer to Inspection & Test Plan (ITP)
Page 9 of 59
METHOD STATEMENT
( INTERIM )
1.0 INTRODUCTION
1.1 The purpose of this method statement is to describe the activities an
documentation required to commence the temporary work for bridge
2.0 SCOPE OF WORKS
2.1 Preparation of access road
2.2 Preparation of temporary platform
2.3 Installation of sheet pile
3.0 WORK SEQUENCE FLOW
START
Setting out
Page 10 of 59
DOCUMENT NO :
IDX/QAP/MS/TWB8
METHOD STATEMENT
( INTERIM )
DOCUMENT NO :
IDX/QAP/MS/TMB8
IDX/QAP/MS/SC
TEMP/CROSS-SECT-B8-S1
4.4.3 Previously the design calculation for sheet piling had been worked ou
as a reference for the installation of sheet pile work
Attachment 1
IDX/QAP/MS/BPW
4.5.3 The column will be constructed and once the base is backfilled
as per construction drawing and under permission by S.O
the sheet pile will be removed from the base
IDX/QAP/MS/SSW
IDX/QAP/MS/CPC
Page 11 of 59
METHOD STATEMENT
( INTERIM )
DOCUMENT NO :
IDX/QAP/MS/TMB8
4.5.4 The sheet pile will be transferred to the another working platform and
installed there as per diagram
4.6 SHEET PILE & STEEL PLATE DESCRIPTION
4.6.1 The sheet pile to be used is Type SP 3A (refer to the attachment)
4.7 TIDE LEVEL
4.7.1 The highest tide level and lowest tide level is
recorded as per table below:
4.7.2 For detail references on the tide level, the full table can be obtained
from Jabatan Meteorologi Malaysia and Jabatan Pengairan dan
Saliran Malaysia. The record shown in table is based on actual level
measured on the site in respect to sea water level.
4.8 SEQUENCES OF WORK
4.8.1 The working platform will be prepared as per this sequence:
Abutment A
Abutment B
Abutment B-1
Abutment A-1
4.8.2 The sequence for piling work as per diagram attached.
Page 12 of 59
TEMP/SEQ-B8-S1
METHOD STATEMENT
( INTERIM )
The contractor will issue to the local authority involved such as JPS a
liability letter that will transfer the responbility of damage to the
surrounding area due to the work at site to the contractor.
Excavator
Roller compactor
Backpusher
Tipper
Vibro Hammer
2
2
1
1
1
nos
nos
nos
nos
nos
8.0 MANPOWER
Supervisor
Machine operator
General Worker
1 person
7 persons
4 persons
Page 13 of 59
DOCUMENT NO :
IDX/QAP/MS/TMB8
METHOD STATEMENT
( INTERIM )
1.0 INTRODUCTION
1.1 The purpose of this method statement is to describe the activities an
documentation required to commence the temporary work during
construction of pile cap for Bridge 8.
2.0 SCOPE OF WORKS
2.1 Preparation of cofferdam
2.2 Excavation to the cut-off level
2.3 Commencement of pile cap construction
3.0 WORK SEQUENCE FLOW
START
Setting out
Preparation of
platform for
excavation
Installation of sheet
pile & permanent
steel plate
Excavation
work to the
cut-off level
Pile cap
construction
Backfilling
work
Removal of
sheet pile
END
Page 14 of 59
DOCUMENT NO :
IDX/QAP/MS/TW2B8
METHOD STATEMENT
( INTERIM )
DOCUMENT NO :
IDX/QAP/MS/TW2B8
IDX/QAP/MS/SC
TEMP/CROSS-SECT-B8-S1
4.4.3 Previously the design calculation for sheet piling had been worked ou
as a reference for the installation of sheet pile work
Attachment 1
IDX/QAP/MS/BPW
4.5.3 The pile cap and pier will be constructed and once the base is backfil
as per construction drawing and under permission by S.O
the sheet pile will be removed from the base
IDX/QAP/MS/SSW
IDX/QAP/MS/CPC
Page 15 of 59
METHOD STATEMENT
( INTERIM )
DOCUMENT NO :
IDX/QAP/MS/TW2B8
4.5.4 The sheet pile will be transferred to the another working platform and
installed there as per diagram
4.6 SHEET PILE & STEEL PLATE DESCRIPTION
4.6.1 The sheet pile to be used is Type IIIA (refer to the attachment)
4.7 TIDE LEVEL
4.7.1 The highest tide level and lowest tide level is
recorded as per table below:
4.7.2 For detail references on the tide level, the full table can be obtained
from Jabatan Meteorologi Malaysia and Jabatan Pengairan dan
Saliran Malaysia. The record shown in table is based on actual level
measured on the site in respect to sea water level.
4.8 SEQUENCES OF WORK
4.8.1 The working platform will be prepared as per this sequence:
Abutment A
Abutment B
Abutment B-1
Abutment A-1
4.8.2 The sequence for piling work as per diagram attached.
Page 16 of 59
TEMP/SEQ-B8-S1
METHOD STATEMENT
( INTERIM )
The contractor will issue to the local authority involved such as JPS a
2
2
1
1
nos
nos
nos
nos
Vibro Hammer
1 nos
8.0 MANPOWER
Supervisor
Machine operator
General Worker
1 person
7 persons
4 persons
Page 17 of 59
DOCUMENT NO :
IDX/QAP/MS/TW2B8
METHOD STATEMENT
( INTERIM )
1.0 INTRODUCTION
1.1 The purpose of this method statement is to describe the activities an
documentation required to commence the construction of pile cap
2.0 SCOPE OF WORKS
2.1 Setting Out
2.2 Reinforcement work for the pile cap
2.3 Concreting work of the pile cap
3.0 WORK SEQUENCE FLOW
START
Setting out
Backfilling
work
END
Page 18 of 59
DOCUMENT NO :
IDX/QAP/MS/CPC
METHOD STATEMENT
( INTERIM )
DOCUMENT NO :
IDX/QAP/MS/CPC
4.2.3 Lean concreting work will commence once the inspection has been d
and agreeable quality is achieved
4.3 REBAR & FORMWORK INSTALLATION
4.3.1 Upon completion of bored piling the depth of excavation from ground
level to lean concrete i.e. : 50mm below pile cap soffit determine by the
surveyor.
4.3.2 Preparation of pile head by hacking to the required level for starter bar
extended into pile cap.
4.3.3 Prior to lean concrete, the pile cap dimension and soffit level shall be
marked by the surveyor.
4.3.4 The lean concrete preferably be 100-150mm larger then the size of p
cap and mark pile cap dimension prior to install rebars and formwork.
4.3.5 The bar bending schedule will be submitted in advance to the consul
for approval, where some of the rebars are custom cut. The size type
member, spacing and lap length shall be accordance to the drawing.
4.3.6 Concrete spacer shall be provided for adequate spacing and cover the
rebars are free from dirt or grease and in a proper storage.
4.3.7 All starter bar member, size, type and lap length are installed according
to the drawings.
4.3.8 The formwork are cut in size and dimension using waterproof plywoo
and shall be applied with mould oil to enhance the finish surface and to
prevent adhension of concrete.
Page 19 of 59
METHOD STATEMENT
( INTERIM )
DOCUMENT NO :
IDX/QAP/MS/CPC
Page 20 of 59
METHOD STATEMENT
( INTERIM )
Crane
Ready mixed truck
Vibrator Poker
1 nos
4 nos
1 nos
7.0 MANPOWER
Supervisor
Machine operator
General Worker
1
5
Page 21 of 59
DOCUMENT NO :
IDX/QAP/MS/CPC
METHOD STATEMENT
( INTERIM )
VIBRATION MONITORING
DOCUMENT NO :
IDX/QAP/MS/VM
1.0 Introduction
Vibration monitoring shall be carried out at all such locations where it is
required to access the effect of induced vibrations due to any dynamic
loading. A standard vibration monitoring system shall carry out this
assessment of vibration. This equipment should be able to evaluate the
parameters of vibrations in all three planes i.e. Longitudinal, Transverse and
vertical. Construction process like pile driving, blasting, soil compaction
induces vibrations that are at times above permissible limits. Permissible
limits of vibrations shall be as defined by relevant compliance code.
The method adopted shall measure peak pulse velocity, peak acceleration and
peak displacement in transverse, longitudinal and vertical direction for a
particular frequency. Every structure has its own frequency and unless the
induced vibration frequency does not match with this resonance frequency the
structure can sustain vibration safely. However vibrator forces above limits
specified in compliance code are detrimental to the health of the structure
and action contributory to such vibration should be immediately stopped.
Appendix B
Page 22 of 59
Appendix C
METHOD STATEMENT
( INTERIM )
VIBRATION MONITORING
DOCUMENT NO :
IDX/QAP/MS/VM
4.0 Methodology
a) Conduct sensor check using internal check facilities prior to measurement. Set
up the Vibration Meter by mounting the tri-axial sensors in the soil, pointing to
the sources of vibration.
b) The location of the sensor should be installed near the bridge structure. There
should be no obstacles along side the perimeter involved. The radius shall not
beyond 200 meter from the sensor's location and point of observation.
Page 23 of 59
Appendix A
METHOD STATEMENT
( INTERIM )
VIBRATION MONITORING
IDX/QAP/MS/VM
7.0 Limitations
The test cannot provide data about the maximum vibration that can occur as
the test provides result for the loading imposed on the location during testing
procedure. This test enables evaluation of more specific strength parameters
only when used in conjunction with other tests. Location and time specific
damping can affect the results of the test. Displacement evaluated and
maximum frequencies are evaluated during separate tests and if the loading
is not same the result could vary.
Supervisor
Assistant Supervisor
DOCUMENT NO :
1
1
Page 24 of 59
METHOD STATEMENT
( INTERIM )
DISPLACEMENT MONITORING
DOCUMENT NO :
IDX/QAP/MS/DM
1.0 GENERAL
Structures such as bridges and tunnels may be required to be
monitored for horizontal and vertical displacement. It is important
to be able to accurately measure the amount of displacement at
predetermined locations over a period of time.
All survey work associated and undertaken for the monitoring of
structures must be sufficiently accurate to detect horizontal and
vertical movement of + or - 2mm
2.0 SURVEY DATUM
All co-ordinates supplied shall be as per setting out drawings
provided at the latest unless otherwise specified.
3.0 SURVEY CONTROL
Survey control for the monitoring of structures should be
established so that the integrity of the monitoring data can be
guaranteed. 4 points on each structure will be taken into
consideration. The actual co-ordinates and level will be recorded.
APPENDIX A
Page 25 of 59
APPENDIX A
METHOD STATEMENT
( INTERIM )
DISPLACEMENT MONITORING
DOCUMENT NO :
IDX/QAP/MS/DM
Vertical Survey
The existing level will be recorded weekly and any reduction will be
recorded as vertical displacement
6.0 RECORDING AND PRESENTATION OF DATA
Survey control points shall be recorded in spreadsheet. Point
identification, easting, northing, elevation and a description of the
point shall be recorded as a minimum. Any subsequent changes in
elevation shall also be recorded. Differences in easting, northing
and RL should be compared to the initial observations and
tabulated. Any movement of 4mm or greater in horizontal position
and 2mm in vertical position should be flagged for further scrutiny.
Digital and hard copies of survey control data shall be provided to
client/S.O following initial and subsequent surveys.
An example of the required format for recording of monitoring
results for structures is included in Appendix B
7.0 SAFETY REQUIREMENT
Only experienced personnel are allowed at working area.
Site personnel must be briefed and be well versed with all site safety
measures.
Site personnel must be in proper safety working attire e.g. Safety boots
and safety vest and helmets must be worn at all times.
Site safety member should be available at all times and must be able to
respond correctly to emergency
Flagman will be provided during the monitoring work conducted
Survey Equipment
9.0 MANPOWER
Land Surveyor
Chainmen
Page 26 of 59
APPENDIX B
METHOD STATEMENT
( INTERIM )
1.0 INTRODUCTION
1.1 Bore cast-in-situ piles are piles formed by excavating a hole, of the
specified size (diameter), to the required depth and casting the
excavated hole with concrete of specified strength after the
reinforcement is lowered into the holes.
1.1 The purpose of this method statement is to describe the activities and
documentation required to commence the construction of bored pile.
2.0 SCOPE OF WORKS
2.1
2.2
2.2
2.3
Setting Out
Excavation of hole (Boring work)
Reinforcement work
Concreting work
Site Preparation
Setting Out
Boring Work
Installation of
Casing
Reinforcement
Work
Concreting Work
Testing and
commisioning
END
Page 27 of 59
DOCUMENT NO :
IDX/QAP/MS/BP
Page 28 of 59
METHOD STATEMENT
( INTERIM )
DOCUMENT NO :
IDX/QAP/MS/BP
METHOD STATEMENT
( INTERIM )
4.6 BORING
Boring commence after the position of the boring plant is checked.
Usually, an auger of the required size is used to excavate the hole.
During excavation, the hole shall be observed for its stability. If the
excavated hole is collapsible, a temporary casing of the same size
shall be installed using a vibro-hammer, to prevent collapse.
Excavation of the hole then continues until the required depth.
When rock is encountered during the excavation (usually observed
by the difficulty in advancing the excavation) other drilling tools
may be utilised. A rock auger, coring bucket, chisel or a
combination of these tools may be used to break up the rock.
After reaching the required depth, a cleaning bucket shall be used
to clean up the bottom of the borehole. A joint measurement of the
depth shall be made before lowering of the reinforcement and
concreting.
4.7 REINFORCEMENT
Reinforcement for the bored piles shall be pre-fabricated in the
reinforcement yard (near the piling platform) and lifted to the
borehole for placing, using a service crane. After fabrication by the
bar benders, the helical links will be tack welded to the main
reinforcement. Laps are also to be welded sufficiently so that they
remain intact during transportation and handling. 100mm diameter
round spacers will be welded to the reinforcement to provide the
cover to ther reinforcement against the soil during concreting.
4 numbers of sonic logging pipes with 50mm diameter and 6 meter
length will be tack welded to the main reinforcement. Each length
will be jointed by another 6 meter length sonic logging pipes until it
reaches the bottom of the hole. The opening of sonic logging pipe
must be located exactly above the cut-off level (on the same level
as platform level) and be cleared from any debris or blockage by
any means necessary.
The reinforcement will be lowered into the completed borehole,
prior to concreting, by means of a service crane and to be adjusted
to the correct level.
4.8 CONCRETING
Concreting shall commence immediately after the reinforcement is
placed.
Concrete shall be supplied by ready-mixed truck to the pile
positions. The concrete slump to be used shall depend on the
method of concreting, as below.
The tremie pipe shall be extended to the bottom of the excavation.
The tremie pipe shall at all times be embedded in the concrete and
shall be withdrawn after completion of the concreting process. No
direct discharge method shall be used be the borehole is dry or
underwater to avoid segregation.
Page 30 of 59
DOCUMENT NO :
IDX/QAP/MS/BP
METHOD STATEMENT
( INTERIM )
DOCUMENT NO :
IDX/QAP/MS/BP
Diagram
4.11 RECORDS
All bore piling records are to be recorded in the Bore Log provided.
A copy is enclosed for reference
5.0 MATERIAL
Concrete Grade 40/20 Tremie
Reinforcement Steel
Bentonite (If any)
Bar Schedule
6.0 MACHINERY
Vibro hammer
Excavator
Boring Plant
Mobile Crane
Generator Set
1
1
1
1
2
7.0 MANPOWER
Site supervisor
Machine Operator
General Worker
1
4
10
8.0 PRODUCTIVITY
3 days for each point from setting out until cut-off level
Page 31 of 59
METHOD STATEMENT
( INTERIM )
Page 32 of 59
DOCUMENT NO :
IDX/QAP/MS/BP
Page 33 of 59
METHOD STATEMENT
( INTERIM )
STRUCTURAL CONCRETING
1.0 INTRODUCTION
1.1 The purpose of this method statement is to describe the activities and
documentation required for structural concreting for pile cap,
column/abutment wall, deck slab and parapet wall.
2.0 SCOPE OF WORKS
2.1
2.2
2.3
2.4
END
Reinforcement - Placement
START
Checking on concrete cover
Intersecting bars and links - tied together
with binding wire
Lay the reinforcement according to
specification and construction
drawing
Install spacers
Welded if necessary as per instruction (if
any)
Pre-concreting Inspection
END
Page 34 of 59
DOCUMENT NO :
IDX/QAP/MS/STC
END
Page 35 of 59
METHOD STATEMENT
( INTERIM )
STRUCTURAL CONCRETING
Concrete Placement
START
Preliminary Inspection on
Structure
Placing order for concrete
supply
Standby all workmen necessary for
concrete placement work
Arrange rotation of supervisory
staff (if necessary)
Installation of formwork
Placing of concrete
END
Page 36 of 59
DOCUMENT NO :
IDX/QAP/MS/STC
METHOD STATEMENT
( INTERIM )
STRUCTURAL CONCRETING
Grade
15/20
40/20
40/20
40/20
40/20
50/20
40/20
50/20
40/20
40/20
40/20
DOCUMENT NO :
IDX/QAP/MS/STC
METHOD STATEMENT
( INTERIM )
STRUCTURAL CONCRETING
Cover to
Reinforcement
75mm
75mm for *BF
45mm for *OF
45mm
45mm
45mm
30mm
45mm
30mm
45mm
45mm
75mm for *BF
45mm for *OF
45mm
ends of the wire shall be turned into the main body to concrete.
e) Links shall be securely fixed with binding wire to the longitudinal
reinforcement.
f) The reinforcement shall be laid out in accordance with the
specified.
Page 38 of 59
DOCUMENT NO :
IDX/QAP/MS/STC
METHOD STATEMENT
( INTERIM )
STRUCTURAL CONCRETING
of the lean concrete and the Engineer shall ensure that the base is
clean and level.
d) For horizontal structures, one side of the form shall be erected
initially along the stringed side line. Temporary strutts and shores
are placed to hold the form in position.
After the placement of rebar, the other side of the form shall be
e) erected. Straightness and verticality check executed and strutts
secured in placed together with horizontal braces to maintain the
required width throughout.
DOCUMENT NO :
IDX/QAP/MS/STC
METHOD STATEMENT
( INTERIM )
STRUCTURAL CONCRETING
DOCUMENT NO :
IDX/QAP/MS/STC
METHOD STATEMENT
( INTERIM )
STRUCTURAL CONCRETING
Page 41 of 59
DOCUMENT NO :
IDX/QAP/MS/STC
c)
However, for designed mix, at least four samples (12 cubes) shall
be taken of concrete on the first day of concreting for each grade of
concrete to be used in the Work, irrespective of the volume of
concrete produced or the sampling rate. Subsequent rate of
sampling shall be at least one sample from each source of
production on each day that concrete of any particular grade is
used.
METHOD STATEMENT
( INTERIM )
STRUCTURAL CONCRETING
5
1
1
1
2
1
1
1
7.0 MANPOWER
Site supervisor
Machine Operator
General Worker
1
2
10
Page 42 of 59
DOCUMENT NO :
IDX/QAP/MS/STC
METHOD STATEMENT
( INTERIM )
STRUCTURAL CONCRETING
Page 43 of 59
DOCUMENT NO :
IDX/QAP/MS/STC
Page 44 of 59
METHOD STATEMENT
( INTERIM )
STRUCTURAL CONCRETING
1.0 INTRODUCTION
1.1
END
Reinforcement - Placement
START
Checking on concrete cover
Intersecting bars and links - tied together
with binding wire
Lay the reinforcement according to
specification and construction
drawing
Install spacers
Welded if necessary as per instruction (if
any)
Pre-concreting Inspection
Page 45 of 59
DOCUMENT NO :
IDX/QAP/MS/STC
END
Page 46 of 59
METHOD STATEMENT
( INTERIM )
STRUCTURAL CONCRETING
Concrete Placement
START
Preliminary Inspection on
Structure
Placing order for concrete
supply
Standby all workmen necessary for
concrete placement work
Arrange rotation of supervisory
staff (if necessary)
Installation of formwork
Placing of concrete
END
Page 47 of 59
DOCUMENT NO :
IDX/QAP/MS/STC
METHOD STATEMENT
( INTERIM )
STRUCTURAL CONCRETING
Grade
15/20
40/20
40/20
40/20
40/20
50/20
40/20
50/20
40/20
40/20
40/20
DOCUMENT NO :
IDX/QAP/MS/STC
METHOD STATEMENT
( INTERIM )
STRUCTURAL CONCRETING
Cover to
Reinforcement
75mm
75mm for *BF
45mm for *OF
45mm
45mm
45mm
30mm
45mm
30mm
45mm
45mm
75mm for *BF
45mm for *OF
45mm
ends of the wire shall be turned into the main body to concrete.
e) Links shall be securely fixed with binding wire to the longitudinal
reinforcement.
f) The reinforcement shall be laid out in accordance with the
specified.
Page 49 of 59
DOCUMENT NO :
IDX/QAP/MS/STC
METHOD STATEMENT
( INTERIM )
STRUCTURAL CONCRETING
of the lean concrete and the Engineer shall ensure that the base is
clean and level.
d) For horizontal structures, one side of the form shall be erected
initially along the stringed side line. Temporary strutts and shores
are placed to hold the form in position.
After the placement of rebar, the other side of the form shall be
e) erected. Straightness and verticality check executed and strutts
secured in placed together with horizontal braces to maintain the
required width throughout.
DOCUMENT NO :
IDX/QAP/MS/STC
METHOD STATEMENT
( INTERIM )
STRUCTURAL CONCRETING
DOCUMENT NO :
IDX/QAP/MS/STC
METHOD STATEMENT
( INTERIM )
STRUCTURAL CONCRETING
Page 52 of 59
DOCUMENT NO :
IDX/QAP/MS/STC
c)
However, for designed mix, at least four samples (12 cubes) shall
be taken of concrete on the first day of concreting for each grade of
concrete to be used in the Work, irrespective of the volume of
concrete produced or the sampling rate. Subsequent rate of
sampling shall be at least one sample from each source of
production on each day that concrete of any particular grade is
used.
METHOD STATEMENT
( INTERIM )
STRUCTURAL CONCRETING
5
1
1
1
2
1
1
1
7.0 MANPOWER
Site supervisor
Machine Operator
General Worker
1
2
10
Page 53 of 59
DOCUMENT NO :
IDX/QAP/MS/STC
METHOD STATEMENT
( INTERIM )
STRUCTURAL CONCRETING
Page 54 of 59
DOCUMENT NO :
IDX/QAP/MS/STC
Page 55 of 59
METHOD STATEMENT
( INTERIM )
1.0 INTRODUCTION
1.1 The purpose of this method statement is to describe the activities an
documentation required to commence the temporary work for bridge
2.0 SCOPE OF WORKS
2.1 Preparation of access road
2.2 Preparation of temporary platform
2.3 Installation of sheet pile
3.0 WORK SEQUENCE FLOW
START
Setting out
Page 56 of 59
DOCUMENT NO :
IDX/QAP/MS/TWB5
METHOD STATEMENT
( INTERIM )
DOCUMENT NO :
IDX/QAP/MS/TWB5
IDX/QAP/MS/SC
TEMP/CROSS-SECT-B8-S1
4.4.3 Previously the design calculation for sheet piling had been worked ou
as a reference for the installation of sheet pile work
Attachment 1
IDX/QAP/MS/BPW
4.5.3 The pile cap and pier will be constructed and once the base is backfil
as per construction drawing and under permission by S.O
the sheet pile will be removed from the base
IDX/QAP/MS/SSW
IDX/QAP/MS/CPC
Page 57 of 59
METHOD STATEMENT
( INTERIM )
DOCUMENT NO :
IDX/QAP/MS/TWB5
4.5.4 The sheet pile will be transferred to the another working platform and
installed there as per diagram
4.6 SHEET PILE & STEEL PLATE DESCRIPTION
4.6.1 The sheet pile to be used is Type IIIA (refer to the attachment)
4.7 SEQUENCES OF WORK
4.7.1 The working platform will be prepared as per this sequence:
Pier 2-1
Pier 3 - 1
Pier 1-2
Pier 2
Pier 3
Pier 1
Abutment A
Abutment B
Abutment B-1
TEMP/SEQ-B8-S1
Abutment A - 1
Page 58 of 59
METHOD STATEMENT
( INTERIM )
Excavator
Roller compactor
Backpusher
Tipper
Vibro Hammer
2
2
1
1
1
nos
nos
nos
nos
nos
7.0 MANPOWER
Supervisor
Machine operator
General Worker
1 person
7 persons
4 persons
Page 59 of 59
DOCUMENT NO :
IDX/QAP/MS/TWB5