Академический Документы
Профессиональный Документы
Культура Документы
Economic Operation
There are many factors involved in the successful operation of a power system.
Next to security, economy is the most important.
Economic load dispatch concerns with the optimum load scheduling of the
different generating plants in the system and it involves 2 different problems.
1. Economic Dispatch an on-line problem to optimally distribute the load
1
among the generating units to minimise the total cost of supply while the total
demand and the losses at any instant is met by the total generation.
2. Unit Commitment a predispatch problem to select optimally out of the
available generating units to meet the expected load and provide a specified
margin of operating reserve over a specified period of time.
Economic Load Dispatch only deals with the problem of minimum cost of power
production. Other economic operation aspects such as minimum-loss delivery
of the generated power to the loads are beyond the scope of this topic.
Economic Dispatch
The sole focus of economic dispatch is the minimisation of the thermal fuel costs,
even though there are other factors such as labour, supplies and maintenance in
dealing with the total costs of producing electrical energy.
There are 2 important cases of optimal economic dispatch to be analysed.
1. Economic Dispatch Neglecting Losses
2
KWCn v3.1
Economic Operation
The fuel cost is meaningful in case of thermal stations, but for hydro stations where
the energy storage is apparently free, the operating fuel cost as such is not
meaningful. This is the reason why only thermal plants are considered in the
following sections.
Ci is constructed of
$/h
Piecewise
Non-linear
Characteristics
dCi
dPi
i
The slope of the cost curve, i.e. dC
dPi , is called the
incremental fuel cost (ICi ). If the cost is approximated
KWCn v3.1
Pi,max
MW
Unit output, Pi
+ B1 Pi + B0 $/h
where B0 ,
Pi,min
Cost-Output Curve
$/MWh
Ci =
B2 Pi2
Polynomial
Approximation
Linear
Approximation
Unit output, Pi
MW
Economic Operation
C1 =
C2 =
C =
PD =
Then
C1 + C2
total load demand = P1 + P2 = constant
total fuel cost
C
P1
=
=
and
PD
P1
C1
P1
C1
P1
= 1+
+
+
P2
P1
C
P1
C2
P1
C2
P2
P2
P1
=0
=0
P2
P1
C1
P1
= 1
=
C2
P2
= (say)
i.e. the basic criterion for economical division of load between units is that
both the units must operate at the same incremental fuel cost .
2.4 Example 1
The total amount output of a 2-generator station is P MW and the cost curves of
Determine how this load should be shared to give the most economical distribution.
The incremental costs of the generators are:
6
IC1 = 2B2 P1 + B1
IC2 = 2B2 P2 + B1
For optimum division of load, the two incremental costs should be equal, i.e.
2B2 P1 + B1 = 2B2 P2 + B1
(E1.1)
B2
B1 B1
P1 =
P+
B2 + B2
2(B2 + B2 )
B1 B1
B2
P+
P2 =
B2 + B2
2(B2 + B2 )
KWCn v3.1
Economic Operation
2.5 Example 2
Determine the most economical load distribution and the total minimum cost
of operation at this load as described in Example 1. Given that:
P = 450 MW
B1 = 4.0 $/MWh
B2 = 0.02 $/MW 2 h
B1 = 3.4 $/MWh
B2 = 0.01 $/MW 2 h
From the results obtained in Example 1, the optimium load of generator 1 and 2 are:
7
B1 B1
B2
P
+
B2 + B2
2(B2 + B2 )
3.4 4.0
0.01
450 +
= 140 MW
=
0.02 + 0.01
2(0.02 + 0.01)
P2 = P P1 = 450 140
= 310 MW
P1 =
C = C1 + C2 = B2 P12 + B1 P1 + B0 + B2 P22 + B1 P2 + B0
= 0.02(140)2 + 4(140) + B0 + 0.01(310)2 + 3.4(310) + B0
= 2967 + B0 + B0 $/h
C is the total fuel cost of the entire system and PD is the total load demand.
Pn
C = C1 + C2 + . . . + Cn = i=1 Ci
Pn
PD = P1 + P2 + . . . + Pn = i=1 Pi = constant
= 0, i.e.
C
C
C
dP1 +
dP2 + . . . +
dPn = 0
P1
P2
Pn
For the total load demand PD to remain constant, dPD = 0, i.e.
dC =
(1)
(2)
C
C
C
dP1 +
dP2 + . . . +
dPn = 0 (3)
P1
P2
Pn
KWCn v3.1
Economic Operation
C
C
C
=
= ... =
=
P1
P2
Pn
dC
dC
dC
=
= ... =
=
dP1
dP2
dPn
Or
coordination equations
Ci
dCi
=
Pi
dPi
This shows that the criterion for most economical division of load between units
within a plant is that all the units must operate at the same incremental fuel cost .
This is known as the principle of equal criterion for economic operation.
The method used above is called the method of Lagrangian multipliers.
Pn
C
(
i
i=1 Pi PD )
i=1
dCi
L
=0
=
Minimization is achieved by the condition:
Pi
dPi
The Lagrangian is defined as:
L=
Pn
2.7 Example 3
The power needs of a large plant are served by three generating unit, which have
the following incremental cost functions:
PD = 800 MW and the cost in cents per kWh at this operating condition.
The required optimal condition is when = IC1 = IC2 = IC3 hence
P1 =
P2 =
P3 =
8.8
0.01
10.2
0.015
12.1
0.02
= 100( 8.8)
= 66.67( 10.2)
= 50( 12.1)
P3
i=1
Pi = PD yields
KWCn v3.1
Hence,
2.8
Economic Operation
It is not uncommon for the solution in the lossless case to be determined easily.
However, analytical solutions are often difficult to obtain when losses in the
11
transmission network must be considered and efforts are better served by resorting
to an iteration solution using computer as follows:
(a) Express each generator power in terms of the Lagrangian multiplier
(b) Pick a suitable initial value of
(c) Find the corresponding real powers P1 , P2 . . . Pn
P
Pi PD = 0, the optimal solution is reached
P
If
Pi PD < 0, increase and goto (c)
P
If
Pi PD > 0, decrease and goto (c)
(d) If
dC1
dP1
dC2
dP2
dC3
dP3
P1
P2
12
Compared to Pd
dC1
dP1
dC2
dP2
P3
dC3
dP3
dCi
dPi
G1
Range 2
G2
P1
KWCn v3.1
P2
Range 3
Range 1
P3
P
Graphical Representation
Economic Operation
2.9 Example 4
The following are the fuel-cost curves for the 3 generating units of a power plant.
2200 MW)
when the generators are sharing the load optimally, and hence find the incremental
cost for the load PD
= 1800 MW.
Incremental Cost
($/MWh)
Generator
7.6
50+50+50 = 150
50+150+325 = 525
9.2
G3
G2 , G3
G1 , G2 , G3
G1 , G3
G3
9.5
400+800+1000 = 2200
8.05
8.15
8.8
50+50+275 = 375
266.67+800+650 = 1716.67
400+800+850 = 2050
14
KWCn v3.1
Economic Operation
When transmission losses are included in the economic dispatch problem, the total
load demand equation becomes:
n
X
Pi PL = PD
i=1
where PL is the total transmission loss. In general, PL is not constant but depends
15
L=C
"
n
X
Pi PL PD
i=1
L
Minimum of C is attained when P
"
n
X
Pi PL PD
Pi
Pi
or
16
i=1
=0
PL
dCi
1
=0
dPi
Pi
"
or
dCi
dPi
or
dCi
Li = for all values of i
dPi
where Li
PL
Pi
(4)
1
is known as the penalty factor for plant i.
L
1 P
Pi
Thus the optimum fuel economy is achieved when the product of the incremental
L
is known as the
fuel times the penalty factor is the same for all plants. P
P
i
dC1
dC2
dCn
L1 =
L2 = . . . =
Ln =
dP1
dP2
dPn
The above equations are known as the exact coordination equations because both
incremental fuel cost and incremental transmission loss are coordinated for best
economy.
KWCn v3.1
Economic Operation
Pi = PD + PL
The loss penalty factor for this generator can be rewritten as:
17
Li =
Pi
Pi
1
1
=
1
=
PL
L
P
P
P
1
1 P
i
L
D
Pi
Pi
dCi
dCi Pi
dCi
incremental cost of
Li =
=
= received power for unit i
dPi
dPi PD
dPD
or
18
G1
V1
pf1
G2
R1
R2
I1
I2
R3
Load
V2
pf2
KWCn v3.1
Economic Operation
Based on the experience with the simple case in last section, a general expression
for the total system losses can be written, with several approximations, as:
PL =
n X
n
X
Pi Bij Pj
and
i=1 j=1
X
PL
=
2Bij Pj
Pj
i=1
where Bij is the loss coefficients which are constants unders certain assumed
operating conditions and Bij
19
= 2B2i Pi + B1i
dCi
L
Substituting P
Pj and dPi from the above coordination equation (4) an collecting all
P
Bi
terms of Pi :
1 1
2Bij Pj
j6=i
Pi =
2B2i
+ 2Bii
For any particular value of , Pi can be solved iteratively by assuming initial values
of P i. A convenient choice is Pi
= 0.
3.4 Example 5
Generator 1 is remotely located and generator 2 is at the load centre.
When 100 MW is dispatched from generator 1, the transmission loss is 10%.
When the system is optimally dispatched at a certain time the system
is found to be $25 per MWh.
Determine the power output of each generator and the power taken by the load.
20
0.015P 2 + 17P + 14
0.030P 2 + 19P + 16
PL
P12
Incremental cost :
KWCn v3.1
$/h
PL = B11 P12
B11 =
$/h
10010%
1002
= 103 MW1
IC1 = 0.03P1 + 17
IC2 = 0.06P2 + 19
10
Economic Operation
L1 = ?
L2 = 1
= 25
where
Hence,
IC1 L1 = IC2 L2 =
(no loss)
(given)
0.06P2 + 19 = 25
P2 = 100 MW
21
Penalty factor :
L1 =
1
1
=
PL
1 2B11 P1
1 P1
P1 =
Load, PD
3.5 Example 6
22
2
+ 60PG1 + 15
C1 = 0.25PG1
2
+ 70PG2 + 13
C2 = 0.25PG2
2
+ 75PG3 + 12
C3 = 0.25PG3
$/h
$/h
$/h
The transmission losses are given by a loss formula whose only non-zero coefficient
is B33 = 0.0005 MW1 .
Assuming that G1s power output is fixed at 140MW, calculate to an accuracy of
2MW per generator the optimal dispatch of a system demand of 550MW and
obtain the corresponding average system electricity production cost in cents/kWh.
Determine also the marginal cost of supplying an additional kWh of electricity to the
KWCn v3.1
11
Solution:
IC1 = 0.5P1 + 60
IC2 = 0.5P2 + 70
IC3 = 0.5P3 + 75
Economic Operation
PD = 550 MW =
PL = B33 P32
PL
= 2B33 P3
P3
Pi
Li =
1
1
PL
Pi
P1 = 140 MW , L1 = L2 = 1 & L3 = ?
1st iteration :
L3 = 1 PL = 0 (lossless)
P2 + P3 = PD P1 + PL = 410 MW
IC2 L2 = IC3 L3 0.5P2 + 70 = 0.5P3 + 75
23
2nd iteration :
set
P2 = 210 MW
P3 = 200 MW
L3 =
1
12(0.0005)(200)
2
= 1.25
PL = (0.0005)(200 ) = 20
3rd iteration :
P2 = 260 MW
P3 = 170 MW
L3 =
1
12(0.0005)(170)
2
= 1.2048
PL = (0.0005)(170 ) = 14.45
P2 + P3 = 424.45 MW
0.5P2 + 70 = 1.2048(0.5P3 + 75)
24
4th iteration :
P2 = 250.4 MW
P3 = 174 MW
L3 = 1.2107
P2
PL = 15.14 MW P3
= 251.82 MW
= 173.63 MW
= (C1 + C2 + C3 )/550
= 122.5 $/MWh = 12.25 cents/kWh
KWCn v3.1
12
Economic Operation
Power plants are connected together through tie-line (transmission line) to form a
large interconnected system due to the following advantages.
1. Increased Reliability - extra spining reserve and redundant power paths
25
Power is bought from the lower cost generator and hence the cost of
generation is reduced.
Changes of load can be catered by all generating units within the whole
Consider two power systems operating with different incremental costs (IC).
KWCn v3.1
13
Economic Operation
4.2 Example 7
Consider the following interconnected areas:
4
1
27
Area 2
Load 1100MW
Area 1
Load 700MW
Ci = fi (ai + bi Pi + ci Pi2 )
Unit
1
2
3
4
5
6
Pimin Pi Pimax
fi
ai
bi
ci
Pimin (MW)
Pimax (MW)
2.0
2.0
2.0
1.9
1.9
1.9
561
310
78
500
295
295
7.92
7.85
7.97
7.06
7.46
7.46
0.001562
0.00194
0.00482
0.00139
0.00184
0.00184
150
100
50
140
110
110
600
400
200
590
440
440
28
Area 1
Area 2
P1 = 322.7MW, P2 = 277.9MW
P3 = 99.4MW, PArea1 = 700MW
1 = 17.856 $/MWhr
C1 = 13,677.21 $/hr
P4 = 524.7MW, P5 = 287.7MW
P6 = 287.7MW, PArea2 = 1100MW
2 = 16.185 $/MWhr
C2 = 18,569.23 $/hr
= C1 + C2 = 32,246.4 $/hr
Area 2
P1 = 184MW, P2 = 166.2MW
= 404.6MW
P3 = 54.4MW, PArea1
P4 = 590MW, P5 = 402.7MW
= 1395.4MW
P6 = 402.7MW, PArea2
= 16.99 $/MWhr
C1 = 8,530.93 $/hr
= 16.99 $/MWhr
C2 = 23,453.89 $/hr
KWCn v3.1
= C1 + C2 = 31,984.82 $/hr
14
Economic Operation
PI = PArea2
PArea2 = 1395.4 1100 = 295.4MW
CP = C1 C1 0.5CS
= 13, 677.21 8, 530.93 130.81 = 5, 015.47$/hr
29
Each area would have $130.81 reduction in operating cost per hour.
Alternatively, perform economic dispatch for separate areas with:
Unit Commitment
To commit a generating unit is to turn it on; that is, to bring the unit up to
speed, synchronize it to the system, and connect it so it can deliver power
to the network.
The problem with commit enough units and leave them on line is one of
30
Since the load varies continuously with time, the optimum combination of units
may alter during any period. To determine which units of a plant should operate
for a given load is the problem of unit commitment (plant ordering).
KWCn v3.1
15
Economic Operation
5.1 Example 8
Suppose the following 3 units are available:
Unit 1:
Unit 2:
31
Unit 3:
Min
150 MW
C1
Min
100 MW
C2
Min
50 MW
C3
Max
Max
Max
600 MW
400 MW
200 MW
To solve this problem, simply try all combinations of the 3 units (23
feasible combination, the units will be dispatched using the techniques outlined in
previous sections on economics dispatch.
Unit
32
Max
Min
P1
P2
P3
F1
F2
F3
Total
MW
MW
MW
MW
MW
cost
200
50
400
100
600
150
400
150
3760
1658
5418
600
150
550
5389
5389
800
200
500
50
4911
586
5497
1000
250
295
255
3030
2440
5471
1200
300
267
233
50
2787
2244
586
5617
KWCn v3.1
16
Economic Operation
Many constraints can be placed on the unit commitment problem. Each individual
power system, power pool, reliability council and so forth may impose different rules
on the scheduling of units, depending on the generation makeup, load-curve
characteristics and such.
Spinning reserve (SR) is the term used to describe system reserved generation
capacity, i.e. it is the amount of generation available from all units synchronized
(i.e. spinning) on the system minus the present load and losses being supplied.
Reserve allocation to various units has to obey certain rules, usually set by the
Examples:
1. A generating plant has a policy to keep a 15% reserve for its peak demand.
If a forecast peak demand is 2200MW, the required spinning reserve would
be 2200MW x 0.15 = 330MW.
34
Reserves should also be spread around the power system so as not to bottled
into a particular region due to transmission limitations if a large set is lost in the
another area bottling of reserves. Under severe condition, reserves can run
KWCn v3.1
17
Economic Operation
Region 1
Interchange, PT
Region 2
SR1
(Transmission limit, P
Tmax)
SR2
SR1 + SR2 may be globally adequate but if largest set in one region is lost, the
spare transmission available (i.e. 550MW - interchange) cannot meet the
reserve tranfser from the other region.
35
Beyond spinning reserve, the unit commitment problem may involve various
classes of scheduled reserves or off-line reserves such as diesel or
gas-turbine units, hydro-units and pumped-storage hydro-units.
It should also be noted that rules for spining reserve differs from one power
Thermal generator usually requires an up time of several hours to bring the boiler
temperature and turbine speed up to the full operational conditions before it can be
synchronized and bring on-line.
1. Minimum up time once the unit is running, it should not be turned off
immediately.
36
2. Minimum down time once the unit is decommitted, there is a minimum time
before it can be recommitted.
3. Crew constraints if a plant consists of two or more units, they cannot both be
turned on at the same time since there are not enough crew members at attend
both units while starting up.
4. Start-up cost it is the cost required to bring a thermal unit on-line. The start-up
cost can vary from a maxium cold-start value to a much smaller value if the unit
KWCn v3.1
18
Economic Operation
5. Cooling and banking there are 2 approaches to treating a thermal unit during
its down period. The first is referred as cooling. It allows the units boiler to cool
down and then heat back up when recommitted. The second called banking
requires that sufficient energy be input to the boiler to just maintain operating
temperature. The costs for the two can be formulated as:
t
Start-up
cost
37
Cooling
where
Cf
Cc
Ct
time of cooling
fixed cost
cold-start cost
Banking
tc
Time-dependent start-up costs
Note: up to certain hours, the cost of banking will be less than the cost of
Some units are given a must-run status for stability or security reasons or for such
purpose as supply of steam for uses (e.g. heating) outside the plant itself.
specified amount of fuel in a given time (for example due to contractual reasons).
KWCn v3.1
19
Economic Operation
39
A shut-
Load
Unit 1
Unit 2
Unit 3
1200
1150
1100
1050
1000
950
800
Total load
1200
MW
750
Unit 2
700
Unit 3
Unit 3
load-curve
650
Unit 2
600
600
MW
550
Unit 1
4 PM
4 AM
500
4PM
Time of day
The shut-down rule is quite simple: When load is above 1000 MW, run all 3 units;
between 1000 MW and 600 MW, run units 1 and 2; below 600 MW, run only unit 1.
Alternatively, this rule can be expressed as a priority list of units: 1, 2, 3. It shows
that unit 1 has the top priority to be committed while unit 3 has the lowest priority.
As the above priority list is derived by brute-force, it is very time consumming for a
large system. Simpler methods for the production of approximate priority lists have
40
been used by utilities. For the above example a simpler scheme is outlined below:
First derive the full load average production cost (FLAPC) table for all units as
follows and then a commitment scheme based on FLAPC can be drawn.
Unit
FLAPC ($/MWh)
Combination
Min MW
Max MW
9.79
2+1+3
300
1200
9.40
2+1
250
1000
11.19
150
400
KWCn v3.1
20
Economic Operation
41
b) Determine when the unit will be needed next (when load rises),
say H hours later.
c) If this is less than the minimum shut down time, keep the unit on-line,
if not goto (d).
d) Calculate two costs. First is cost for next H hours with unit on-line; second is
without unit (to choose between banking and cooling depending on cost).
If there is a saving, shut down the unit; otherwise, operate as at present.
e) Repeat this entire procedure for the each unit on the priority list.
7.3 Example 9
A supply system consists of four generators, each of which has a rating of 500MW
and a minimum permitted output of 100MW. The operating costs of the units are
given by the quadratic formula:
C = a + bP + cP 2
where C is in $/h and P in MW. The coefficient values are tabulated below:
42
Unit
500
0.02
1000
0.03
500
0.03
500
0.05
KWCn v3.1
21
Economic Operation
MW
1600
1200
800
400
43
1
hr
Ct t k$
where Ct = 0.8
starting cost when cooling : Cc (1 et/d ) k$ where Cc = 5 & d = 3
Unit
1 2 3 4
Hours 4 4 2 2
Determine a full unit commitment schedule for this system.
Solution:
i) G1: FLAPC =
G2: FLAPC =
G3: FLAPC =
44
G4: FLAPC =
ii)
C1 (500)
500
C2 (500)
500
C3 (500)
500
C4 (500)
500
=
=
=
=
Priority list:
= 18 $/MWh
= 26 $/MWh
= 22 $/MWh
= 30 $/MWh
Unit
FLAPC ($/MWh)
Priority
Combination
Min MW
Max MW
18
1+3+2+4
400
2000
26
1+3+2
300
1500
22
1+3
200
1000
30
100
500
KWCn v3.1
22
Economic Operation
Load
Load+SR
1600
1760
1+3+2+4
1400
1540
1+3+2+4
1200
1320
1+3+2
800
880
1+3+2
800
880
1+3+2
1200
1320
1+3+2
1400
1540
1+3+2+4
1400
1540
1+3+2+4
45
Unit Schedule
Remark
= (0.8)(4)
= 3.2 k$
Cooling cost = 5(1 e4/3 ) = 3.68 k$
Banking cost
cheaper option
G4 should be banked.
The systems treated so far have included only fossil-fuel generating units. In
practice, however, systems have a mix of different types of units including fossil-fuel,
nuclear, pumped-storage hydro, hydro and other types such as wind generators,
diesel and gas-turbine units, etc.
46
Although the fixed costs of a nuclear unit may be high, their operating cost are
low due to inexpensive nuclear fuel.
As such, nuclear units are normally base-loaded at their rated outputs. That is,
the reference power settings of turbine-governors for nuclear units are held
constant at rated output.
Nuclear units, therefore, become large in size and they are committed to supply
only base loads and do not normally participate in economic diapatch.
KWCn v3.1
23
Economic Operation
During off-peak hours these units are operated as sychronous motors to pump
water to a higher elevation. Then during peak-load hours the water is released
and the units are operated as synchronous generators to supply power.
47
The input-output relation of a hydro unit is a function of both discharge rate and
effective head.
The last two features make hydro plants specially suitable for cold reserve and
for working as peaking and regulating plants.
However, while the fuel-supply is not a limiting factor in the operation of thermal
plants, the operation of hydro-electric plants is dependent on the availability of
water flow.
In other words, energy output (MWh) is fixed and the MW dispatch is regulated
KWCn v3.1
24
The fuel-cost curves for three generating units are given as follows :
$/h
10 P1 120 MW
$/h
10 P2 100 MW
$/h
10 P3 80
MW
where P1, P2 and P3 are in MW. Neglecting transmission losses, the three generators are
being dispatched economically.
a) Obtain by calculation the dispatch of a load of 220MW.
b) Plot the graph of incremental cost versus load from 30MW to 300MW and hence
determine the incremental cost for a load of 250MW.
2.
A two-bus system which has a total load of 400MW and no generator limits is shown in
Fig.1. The incremental fuel cost functions of the generators and the loss formula of the
transmission link are given below:
IC1 = 0.015P1 + 50
IC2 = 0.015P2 + 50
$/MWh
$/MWh
PL = 0.0008( P2 100) 2
MW
where IC1 and IC2 are the incremental costs of generator 1 and 2 when their outputs are
P1 and P2, respectively. PL is the power loss in the transmission link.
a) Neglecting transmission losses, find the optimal generation for each plant and the
system .
b) Using the solution of (a) as a starting point, find the optimal generation for each
plant and the transmission loss.
c) If the transmission loss is included but not coordinated,
i. how much will the total generation cost increase?
ii. what will be the transmission losses?
Fig.1
3.
A small power system with total load of 800MW is served by three generating units
which have the following cost characteristics.
C1 = 5.0 + 7.0 P1 + 0.004 P12 $/h
C2 = 6.0 + 8.0 P2 + 0.006 P22 $/h
a) Determine the optimal economic dispatch of generation and the marginal cost of
supplying an additional kWh of electricity.
b) If the transmission loss associated with generation is given by
PL = 0.005P32 MW
Using the results obtained in (i) as the initial estimates, determine the optimal
economic dispatch and hence obtain the corresponding transmission loss and the
average system electricity production cost in $/kWh.
4.
A supply system consists of four generators. The operating costs of the units are given by
the following quadratic formula :
C = a + bP + cP 2
where a, b and c are constants whilst C and P are in $/hr and MW, respectively. The
coefficient values and loading limits are tabulated below.
_
Unit
1
2
3
4
Loading Limits
Minimum
Maximum
(MW)
(MW)
125
550
100
450
75
500
75
400
___
a) Determine the full load average production cost (FLAPC) of each generator.
b) Determine the priority order for the generators based on the FLAPC, and hence
prepare a merit order loading scheme with information on both the unit combination
and load MW range.
c) Comment on the optimality of this scheme and suggest a better approach to the
problem.
5.
A power system consists of four generators with the characteristics tabulated below.
Unit Merit
Order
1
2
3
4
Loading Limits
Minimum
Maximum
(MW)
(MW)
100
500
150
600
100
500
150
600
($/hr)
($)
( hr)
1100
5500
5
1300
5000
4
1200
5500
3
1300
6000
4
_
The units are scheduled according to a strict merit order with the following system and
operation constraints:
a) The spinning reserve requirement is 10% of the system loading MW capacity.
b) The restarting cost after banking and cooling for all generators are given by Cb t
and Cc (1 e t / ) , respectively, in dollars, where t is the time of cooling in hours.
c) The minimum down time for a generator taken off-line is 2 hours for all units.
The system demand over a ten hours period is given in the table below with the
assumption that the load demand remains constant for each hour.
Hour
Load (MW)
1
1100
2
800
3
1050
4
1200
5
1500
6
900
7
900
8
1200
9
1700
10
1800
Determine a full unit commitment schedule for the above system including specification
of which generator, if any, should be banked or cooled, when taken off.
6.
A supply system consists of four generators, each of which has a rating of 500MWand a
minimum permitted output of 50MW. The operating costs Co and the restarting cost Cr
after banking and cooling of the units are given by the following formulas.
Co = a + bP + cP 2
banking
C t
Cr = b
t /
CC (1 e ) cooling
where Co, Cr, P and t are in $/hr, $,MW, and hr, respectively, and the coefficient values
are tabulated below.
Unit
1
2
3
4
a
500
1000
600
700
b
7
9
6
4
c
0.02
0.03
0.03
0.05
Cb
1100
1300
1200
1300
5
3
2
4
Cc
5500
6000
5500
5000
1
1300
2
800
3
950
4
1800
5
1700
6
850
7
800
8
950
9
1300
a) IC1 = 12 + 0.05P1
IC2 = 17 + 0.10P2
IC3 = 15 + 0.02P3
10 <= P3 <= 80 MW
P1 + P2 + P3 = 220
=>
0.02 P3 + 3 0.02 P3 2
+
+ P3 = 220
0.05
0.1
P3 = 112.5 MW
i.e.
=>
P1 +
0.05P1 5
= 140
0.1
P1 = 126.7 MW
IC1
IC2
IC3
P1
P2
P3
PD
12.5
15.2
16.6
18
-
18
28
15.2
16.6
-
10
64
92
120
120
10
10
10
10
100
10
10
80
80
80
30
84
182
210
300
2.
a) As generator 1 and 2 has the same incremental cost function with no transmission
losses, generator 1 and 2 share the load equally, i.e.
P1 = 200 MW
P2 = 200 MW
= 0.015(200)+50 = 53 $/MWh
b) L1 = 1.0,
L2 =
1 =
1
PL 1.16 0.0016 P2
1
P2
L1 IC1 = 0.015P1 + 50 =
P1 = 50
0.015
P2 = 1.16 50
0.015 + 0.0016
0.015P2 + 50
=
1.16 0.0016 P2
P1 + P2 = (300 + 100) + PL
L2 IC2 =
)
(
0.015
0.0016
+
+
1.16 50 100
50 + 1.16 50 = 400 + 0.0008
0.015 0.015 + 0.0016
0.015 + 0.0016
125.8
IC1dP1 +
204.36
ii.
3.
a)
IC2dP2 = $371.2/h
204.36
PD = P1 + P2 + P3 = 800MW
b) L1 = 1.0,
P1 = 479.81 MW
P2 = 236.54 MW
P3 = 83.65 MW
L2 = 1.0,
and
1 =
1
PL 1 0.01P3
1
P3
P1 = 7.0
0.008
P2 = 8.0
0.012
L3 =
L2 IC2 =
9.5 + 0.016 P3
=
1 0.01P3
P1 + P2 + P3 = 800 + PL where
P3 =
9.5
0.016 + 0.01
PL = 0.005P32
9.5
9.5
7.0 + 8.0 +
= 800 + 0.005
0.008
0.012 0.016 + 0.01
0.016 + 0.01
9.5
= 800 + 0.005
0.016
+ 0.01
Use = 108.38 $/MWh as the initial estimate and iterate: 0 = 10.84 $/MWh
hence,
P1 = 522.63 MW
1 = 11.19
P2 = 265.08 MW
2 = 11.18
P3 = 13.15 MW
3 = 11.18
PL = 0.86 MW
Total production cost = C1 + C2 + C3 = 7,437.53 $/h
average production cost = 0.93 c/kWh
4.
a)
b) Generator
G1
G2
G3
G4
Priority order
1
3
2
4
Loading units
G1+G3+G2+G4
G1+G3+G2
G1+G3
G1
c)
Loading limits
Min
Max
375
1900
300
1500
200
1050
125
550
Scheme based on the priority ordering is not optimum as only average costs are
considered. A better approach would be one based on dynamic programming (DP)
using detailed production cost and economic dispatch analysis.
5.
6.
Hour
1
2
3
4
5
6
7
8
9
10
Load
1100
800
1050
1200
1500
900
900
1200
1700
1800
Load+SR
1210
880
1155
1320
1650
990
990
1320
1870
1980
Banking
Cooling
= $12002 = $2400
= $5500(1 e-2/3) = $2676.2
Banking
Cooling
= $13003 = $3900
= $6000(1 e-3/4) = $3165.8
a) Unit
1
2
3
4
Unit Schedule
1+2+3
1+2+3
1+2+3
1+2+3
1+2+3+4
1+2
1+2
1+2+3
1+2+3+4
1+2+3+4
Cheaper
Cheaper
FLAPC($/MWh)
18
26
22.2
30.4
b) The FLAPC based priority order for the these units is as follows:
Unit
$/MWh
Min MW
Max MW
1
18
50
500
3
22.2
100
1000
2
26
150
1500
4
30.4
200
2000
c) Hour
1
2
3
4
5
6
7
8
9
Load
1300
800
950
1800
1700
850
800
950
1300
Load+SR
1430
880
1045
1980
1870
935
880
1045
1430
Unit Schedule
1+3+2
1+3+2
Unit 2: On (min 2 hrs down time)
1+3+2
1+3+2+4
1+3+2+4
1+3
Unit 2: Off for 2 hrs Banking
1+3
Unit 4: Off for 4 hrs Cooling
1+3+2
1+3+2
cheaper choice
cheaper choice