Академический Документы
Профессиональный Документы
Культура Документы
1. Introduction
Via the IBP supply planning lot size policy the user controls if and how dependent
demands of several subsequent periods are bundled and satisfied by one
transportation or production receipts. In order to minimize or to limit the number of
transports and production events a lot size policy enforces the system to produce or
transport the demands of the current and n subsequent periods already in the current
period. The intention is to satisfy the demand of the current and of n subsequent
periods with the inventory built in the current period so that the next production event
or transport has to be planned in period (n+1) or later.
In addition to the lot size policy there are lot size parameters which impact how the lot
size is determined in IBP supply planning. Lot size parameters determine the range
in which a lot size can be chosen, i.e. the lower and upper bound (minimum and
maximum lot size) and whether a lot size quantity has to be a multiple of a given
increment (rounding value). Lot size parameters are defined on the level of
production or transportation sourcing rule.
Page 2
D:
PS:
I:
N:
R:
S:
00
00
00
00
00
10
10
10
Static Periods
of Supply:
D:
PS:
I:
N:
R:
S:
00
02
20
20
20
00
10
02
10
00
00
10
Static Periods
of Supply:
D:
PS:
I:
N:
R:
S:
00
02
20
20
20
00
10 10 00
02
10 00 10
00 00 10
00 00 10
10 10 00
DC1 P1 S1
00 10 10 00 00 10 10 10
00
10
10
10
00
00
00
00
00
00
00
00
00
10
10
10
00
10
10
10
00
10
10
10
00
02
20
10
10
00
10
02
20
10
10
10
10
02
10
00
00
10
10
02
00
00
00
10
00 10 10
02
10 00 10
00 00 20
00 00 20
00 10 10
10
100%
P:
DC1 P1
10
02
00
00
00
10
00
02
10
10
10
00
DC1 P1 S1
100%
P:
DC1 P1
D:
I:
N:
S:
Dependent Demand
Projected Inventory
Net Demand
Supply
00
00
00
10
00 10 10 00 00 10 10 10
20 00 00 10 10 10 00 00
DC1 P1 S1
100%
R:
Total Receipts
CD: Constrained Demand
PS: Periods of Supply (SUBPERIODSOFSUPPLY)
SN: Number of sub-periods (SUBPERIODNUM)
P:
20 00 00 10 00 00 20 00
P: Production
IT: Inventory Target
The plan in the middle was computed (again by the heuristic) with parameter n set in
key figure SUBPERIODSOFSUPPLY (Periods of Supply) equal to two (n = 2) in
each period. Hence the heuristic plans production receipts so that the resulting
projected inventory in each period covers the dependent demand of the current
period and the next two periods. For that reason the projected inventory of period 1
covers the demand of the dependent demand of periods 2 and 3 which is in total 20.
The projected inventory of period 2 covers the dependent demand of periods 3 and
4, which is 10 and so forth.
This example was slightly modified in the lower area of figure 1. The difference to the
example in the middle is that key figure PS (SUBPERIODSOFSUPPLY) is equal to
two only in the first and fourth period so that only in these two periods the projected
inventory should cover the demand of the next two periods. Therefore, the projected
inventory in period 6 is zero and does not cover the demand of periods 7 and 8. In
the example shown in the middle, the projected inventory of period 6 was 20. The
reason is that in the lower example input key PS (SUBPERIODSOFSUPPLY) stores
no value (which is equivalent to zero) for period 6 whereas in the example in the
middle the user entered a two in for that period. In periods where input key figure
Page 3
SUBPERIODSOFSUPPLY does not contain a value (greater than zero) the lot for lot
policy is applied.
The objective of the lot size policy static periods of supply is to build up a safety
inventory which depends on the dependent demand of n subsequent periods. The
inventory should be high enough to cover the dependent demand of some future
periods. In contrast, via input key figure inventory target a user can specify a safety
stock which is independent of the dependent demand of future periods. Compared to
the Periods of Demand approach the disadvantages of inventory target are:
(i) if the sub-sequent periods do have no demand or less than expected the safety
stock would be built up unnecessarily or unnecessarily high
(ii) if the future demand is higher than expected the target stock might be too small to
cover the entire future demand.
The lot size policy static periods of supply is respected by the heuristic and the
optimizer.
In the upper area of Figure 2 we again see as a starting point the same example of
Figure 1, computed according to the lot for lot policy. The lower area of Figure 2
depicts a supply plan which was computed based on the dynamic periods of supply
Page 4
policy. Again, via input key figure PS (SUBPERIODSOFSUPPLY) the user has
specified that the projected inventory should cover the demand of the next two
periods, however, this condition should be fulfilled only for periods in which receipts
are required to satisfy its dependent demand. For that reason, the projected inventory
of period 1 is zero (in period 1 there is no dependent demand at all). The same holds
for periods 4 and 5.
D:
PS:
I:
N:
R:
S:
00 10 10 00 00 10 10 10
00
00
00
00
00
10
10
10
00
10
10
10
00
00
00
00
00
00
00
00
00
10
10
10
00
10
10
10
00
10
10
10
00
02
00
00
00
00
10
02
20
30
30
10
10
02
10
00
00
10
10
02
00
00
00
10
100%
P:
DC1 P1
Dynamic Periods
of Supply:
D:
I:
N:
S:
Dependent Demand
Projected Inventory
Net Demand
Supply
D:
PS:
I:
N:
R:
S:
00
02
00
00
00
00
10
02
10
20
20
10
10
02
00
00
00
10
00
02
00
00
00
00
00 10 10 00 00 10 10 10
DC1 P1 S1
100%
R:
Total Receipts
CD: Constrained Demand
PS: Periods of Supply (SUBPERIODSOFSUPPLY)
SN: Number of sub-periods (SUBPERIODNUM)
P:
00 20 00 00 00 30 00 00
P: Production
IT: Inventory Target
As period 2 has a dependent demand of 10 units the heuristic ensures that the
resulting projected inventory of period 2 covers the demand of periods 3 and 4, which
is 10 + 0 = 10 units. The projected inventory of period 6 covers the demand of
periods 7 and 8, i.e. 20 units.
The supply plan of Figure 2 has two periods (2 and 6) with production receipts
greater than zero, the comparable example of Figure 1 (middle area) has four.
The objective of lot size policy dynamic periods of supply is to minimize the number
of periods with a production or transportation event. The strategy is to produce or
transport only in periods with a demand and to produce or transport the demand of
Page 5
the current and n subsequent periods, in order to avoid the need to produce or
transport the same product in too many periods again and again.
Only the heuristic of IBP supply planning considers the dynamic periods of supply
policy explicitly. The optimizer, in contrast, minimizes the sum of set up and inventory
holding costs to find a cost optimal plan with a reasonable number of lots.
Page 6
DC1 P1
D:
SN:
PS:
I:
N:
R:
S:
D:
I:
N:
S:
00
30
15
00
00
00
00
10
30
15
05
15
15
10
Dependent Demand
Projected Inventory
Net Demand
Supply
10
30
30
00
05
05
10
00
30
30
00
00
00
00
00
30
30
00
00
00
00
10
30
45
15
25
25
10
10
30
30
05
00
00
10
10
30
30
00
05
05
10
DC1 P1 S1
100%
P:
00 15 05 00 00 25 00 05
R:
Total Receipts
CD: Constrained Demand
PS: Periods of Supply (SUBPERIODSOFSUPPLY)
SN: Number of sub-periods (SUBPERIODNUM)
P: Production
IT: Inventory Target
In periods 3, 4 and 5 the coverage period is set to 30 sub-periods which means that
the Projected Inventory of these three periods should cover exactly one planning
period but only if Receipts are greater than zero which is not the case for any of
these three periods.
For period 6 the heuristic had to plan Receipts greater than zero so that the dynamic
Periods of Supply should apply. For that reason the Projected Inventory should cover
45 days and hence the demand of the next 1.5 planning periods which means that
the Projected Inventory of period 6 should be equal or greater than the entire
demand of period 7 plus 50% of the demand of period 8 which is 10 + 5 = 15 units.
in all periods, each period has 30 sub-periods and the number of sub-periods to be
covered by the Projected Stock is 60 in all periods, which means that the Projected
Stock of each period should cover the Dependent Demand of the next two periods.
The coverage time span of a planning period includes this period itself, i.e. the
current (planning) period and the sub-sequent planning periods which should be
covered by the Projected Stock of the current period. In the example of Figure 4 the
coverage time span of all periods has the same lengths of three (planning) periods as
key figure Periods of Supply (PS) contains the value 60 (sub-periods) for all planning
periods and as all planning periods consist of 30 sub-periods the number of subsequent periods to be covered is 60 / 30 = 2. So, the coverage time span (of each
period) includes the current period and the next two periods. The background of this
definition is that the Net Demand of a period is computed so that it covers (together
with the Stock-on hand, i.e. the Projected Stock of the previous period) the
-
DC1 P1
Period 1
D:
10
SN:
30
PS:
60
I:
60
IT:
20
N:
70
R:
70
S:
10
D:
I:
N:
S:
Dependent Demand
Projected Inventory
Net Demand
Supply
2
10
30
60
50
20
00
00
10
3
10
30
60
40
40
00
00
10
4
10
30
60
40
20
10
10
10
5
10
30
60
30
20
00
00
10
6
10
30
60
20
20
00
00
10
R:
Total Receipts
CD: Constrained Demand
PS: Periods of Supply (SUBPERIODSOFSUPPLY)
SN: Number of sub-periods (SUBPERIODNUM)
P: Production
IT: Inventory Target
Page 8
The Net Demand of period 1 is computed so that the Dependent Demand of period 1
(which is 10) plus the Dependent Demands of periods 2 and 3 (which is 10 + 10 = 20)
are met and it has to be ensured that the Target Stock in each period of the coverage
time span is met which means that the Projected Stock of each period has to be
equal or greater than the Inventory Target. As the maximum Inventory Target of
periods 1, 2 and 3 is 40 the Net Demand of period 1 is: 10 + 20 + 40 = 70 units.
The Net Demand of period 4 is 10 because the Net Demand of that period has to
cover the Dependent Demand of period 4 (which is 10), the Dependent Demands of
period 5 and 6 (10 + 10 = 20) and the Projected Stock of period 4, 5 and 6 has to be
equal or greater than the corresponding Inventory Target which is 20 in all periods.
Based on a Projected Stock in period 3 of 40 units, the Net Demand in period 4 is
computed as follows: Net Demand (4) = 10 + 20 + 20 40 = 10.
Page 9
DC1 P1
Period 1
D:
10
SN:
30
PS:
45
I:
35
IT:
20
N:
45
R:
45
S:
10
D:
I:
N:
S:
Dependent Demand
Projected Inventory
Net Demand
Supply
2
10
30
45
55
20
30
30
10
3
10
30
45
45
40
00
00
10
4
10
30
45
35
20
00
00
10
5
10
30
45
30
20
05
05
10
6
10
30
45
20
20
00
00
10
R:
Total Receipts
CD: Constrained Demand
PS: Periods of Supply (SUBPERIODSOFSUPPLY)
SN: Number of sub-periods (SUBPERIODNUM)
P: Production
IT: Inventory Target
Figure 5: Static PoS with Inventory Target and partial coverage time span
rounding value is 20, the heuristic will plan production receipts of 100 or 120 or 140
and so forth, depending on the production demand in the considered period.
Page 12