Aims and Objectives of the Assignment

The main aim of this assignment is to widen the degree of accessibility and scope of services provided by
the Nigerian Civil Aviation Technology. This is achievable through the proposed construction of the
NCAT Flying School Minna Campus. As a result, the objectives of the assignment include the following:

To ensure that the project is completed on time and to the required quality and within the

approved budgetary limit.


To ensure that the Clients needs and core values are well captured throughout the project

development, completion and lifecycle.


To ensure that the project when finished is structurally sound and stable and can last

throughout its lifespan without any major defects.


To ensure the proper provision of durable and sustainable lighting fittings and connections,
power fittings and connections, communication and security connections. All in accordance

with approved standards of quality and safety.


To ensure the provision of durable and sustainable sanitary installations in accordance with

approved standards of practice and quality.


To ensure that only approved materials and equipment are used on the project.
To ensure all relevant Health and Fire safety standards are implemented on the project.
To ensure that the project does not exceed the set budget limit of the client.
To ensure proper coordination of activities and compliance with prepared schedules.
To ensure smooth project delivery without conflicts and injuries.

Possible Challenges Affecting this Assignment


In order to achieve the objectives of this assignment as listed above, it is necessary to highlight the
possible problems which could prevent the successful attainment of the project objectives. They include
the following:

Delays
Budget overruns
Incompetent Contractors
Poor quality of Construction and materials
Poor communication among stakeholders
Conflicts between stakeholders
Poor designs ETC

The epi-center or crux of these challenges lies in inadequate consultation, and coordination between
project strategic partners. In carrying out our assignment for the provision of Consultancy services our
methodology and work plans are itemized and shown below.
Methodology for Performing This Assignment
In preferring our methodology in carrying out the assignment, we have adopted certain aspects of the
RIBA plan of work and added some elements we have utilized in all our projects in order to prevent the
challenges highlighted above. A typical RIBA plan of work conntains the following key stages
i)
ii)
iii)
iv)
v)

Inception (A, B),


Design (C, D,)
Pre-construction (F, G, H)
Project planning & site operation (J, K, L)
Construction Stage.

vi)

The four (4) initial key stages are further broken down into 11 sub-processes; Inception (A),
Feasibility (B), Outline Proposals (C), Scheme Design (D), Detail Design (E), Tender
Documentation (G), Tender Action (H), Project Planning (J), Operations on site (K) and
Completion (L).

WORK
STAGES
1. Pre-design
2. Design
3. Pre const.

ACTIVITIES

+C

+D

4.Construction

F+

Post Const.

+ J

L
M

Here, the project begins with Inception and the development of the project brief. The feasibility studies
and Site/soil investigations are completed next. The outline proposals (C) and Scheme Design (D) stages
are initiated next and after this there will be a Strategic Value Management Session This session will
enable the project team to gainfully assess outline proposals and determine if such captures the core values
of the Client at a minimum cost. Furthermore, it will also provide the opportunity for other team members
2

to get a full grasp of the Clients needs and values on the project. As a result during this stage, the initial
project estimates will be produced in order to provide the means for checking the actual value of the
outline proposals.
The development of the design is completed during the Detail Architectural Designs (E) and other Design
information will be completed. This will lead to the preparation of Bill of quantities. The use of BIM
software or Autocad 2013 will enable ease in transferring copies of the drawings among team member and
also to provide the means of producing accurate Bill of Quantities.
The preparation of invitation of Contractors for prequalification will take place and suitable tenderers will
be invited to participate in the Tendering process. Careful analysis of submitted bids will be done and
recommendations made to the Client on suitable Contractors for the works will also be submitted to the
Client. Concurrently, a new Planning phase will take place (J) along with the production of Value/Risk
management plans will be produced. This will enable the stakeholders to monitor the project core values
and risks inherent on the project.

FORM4A5: WORKPLAN FOR THE DESIGN AND SUPERVISION OF THE PROPOSED CONSTRUCTION OF N.C.A.T FLYING SCHOOL CAMPUSES (LO
ID Task Name
1 Inception and Development of Project Brief

Duration
1 day

Start
December 8, 2014

Finish
4th Quarter 1st Quarter 2nd Quarter 3rd Q
December 8, 2014

Feasibility Studies

3 days

December 10, 2014

December 12, 2014

Site/Soil Investigation

5 days

December 10, 2014

December 16, 2014

Outline Proposal

5 days

December 17, 2014

December 23, 2014

Initial Project Cost Estimation

1 day

December 24, 2014

December 24, 2014

Strategic Value Management Analysis

2 days

December 25, 2014

December 26, 2014

Scheme Designs

5 days

December 29, 2014

January 2, 2015

Approximate Estimation of Project costs

1 day

January 5, 2015

January 5, 2015

Detailed Designs

7 days

January 6, 2015

January 14, 2015

10 Preparation of Detailed Structural/Mech/Elect 7 days


Designs

January 15, 2015

January 23, 2015

7 days

January 26, 2015

February 3, 2015

12 Tender Action, Documentation, Analysis and 21 days


Report

February 4, 2015

March 4, 2015

11 Preparation of Bill of Quantities

13 Project Planning
14 Value/Risk Management Plans
15 Site Handing Over/Ground Breaking
Ceremony
16 Pre-Mobilization
17 Setting Out
18 Project Supervision and Inspection
19 Monthly Progress reports and Payment
Certificates
20 Site Meetings
21 Practical Completion

1 day

March 5, 2015

March 5, 2015

2 days

March 4, 2015

March 5, 2015

1 day

March 9, 2015

March 9, 2015

1 day

March 10, 2015

March 10, 2015

1 day

March 24, 2015

March 24, 2015

170 days

March 24, 2015

November 16, 2015

147 days

April 24, 2015

November 16, 2015

147 days

April 24, 2015

November 16, 2015

1 day

November 16, 2015

November 16, 2015

3 days

November 16, 2015

November 18, 2015

23 Preparation of Final Certificate

3 days

May 18, 2016

May 20, 2016

24 Final Handing Over/Commissioning

1 day?

May 18, 2016

May 18, 2016

22 Preparation of Penultimate Certificate

Project: NCAT Flying School Campus


Minna
Date: November 30, 2014

Task

Milestone

External Tasks

Split

Summary

External Milestone

Progress

Project Summary

Deadline