Вы находитесь на странице: 1из 16

V.A.

C WORKS
TECHNICAL SPECIFICATIONS

Rev : 0
Date : 17 Oct 2008

Division No. 2, 1

KAJIMA DESIGN ASIA PTE. LTD


SENAYAN SQUARE - JAKARTA
Office Tower 3 & Annex Carpark 2

SECTION 15010 : VENTILATION AND AIR CONDITIONING GENERAL PROVISIONS


PART 1 - GENERAL
1.0. GENERAL CONDITIONS
A.

All sections under this Division shall be subject to the requirements of the
Conditions of Contract for VAC Works and Section 15010 of these Specifications.

B.

The term Contractor" shall mean the VAC Works Contractor who shall enter into a
contract with the Owner in respect of the VAC Contract Works.

C.

The term Engineer" shall mean the Engineering Design / Consulting firm hired for
the project, which is, Design Site Office.

1.1. GENERAL DESCRIPTION


A.

The work to be done under this Division of the Specifications consist of the
fabrication, complete in all details, of the VAC Works, at the subject premises and all
work and materials incidental to the proper completion of the installations, except
those portions of the work which are expressly stated to be done by others. All work
shall be in accordance with the governing Codes and Regulations and with the
Specifications, except where same shall conflict with such codes, etc., which, latter
shall then govern. The requirements in regard to materials and workmanship specify
the required standards for the furnishing of all labor, materials and appliances
necessary for the complete installation of the work specified herein and indicated on
the drawings. These specifications are intended to provide a broad outline of the
required installation, but not intended to include all detail design and construction.

B.

The Contractor before submitting his proposal shall examine all drawings relating to
his work and verify all governing conditions at site and shall become fully informed
as to the extent and character of the work required. No consideration will be granted
for any alleged misunderstanding of the materials to be furnished or work to be
done, it shall be understood that the submission of a proposal is an agreement to all
items and conditions referred to herein or indicated on the accompanying drawings
and actual site conditions. If specified equipment/instruments are not locally
available, Contractor must immediately place an order as soon as project is
awarded. Any exceptions, omission or substitutions shall be presented in writing
with the Contractor's bid.

C. The Contractor, before commencing work shall examine all adjoining areas on which
this work is in these established lines and levels. Verify all measurements at site and
check the correctness of same as related to the work. Should the Contractor
discover any discrepancy between actual measurements and those indicated, which
prevents following good practice or intent of the drawings and specifications, he
15010 - 1

V.A.C WORKS
TECHNICAL SPECIFICATIONS

Rev : 0
Date : 17 Oct 2008

Division No. 2, 1

KAJIMA DESIGN ASIA PTE. LTD


SENAYAN SQUARE - JAKARTA
Office Tower 3 & Annex Carpark 2

shall notify the Owner/Engineer and shall not proceed with his work, until he has
received instructions from the Owner/Engineer.
D. It is of the intention of these Specifications and drawings to call for furnished work
tested and ready for operation. Whenever the word provide" is used, it shall mean
furnish and install, complete and ready to use". Certain terms such as "shall,
provide, install, complete, start-up" are occasionally not used in some parts of these
specifications. This does not indicate that the items shall be less than completely
installed or that systems shall be less than complete. Minor details not usually
shown or specified, but necessary for the proper installation and operation, shall be
included in the work, the same as if herein specified or shown.
1.2. REFERENCE
A.

The work under this contract is to be installed according to the latest requirements
of the following;
1. Departemen Pekerjaan Umum (DPU)
Nothing contained in these Specifications or shown on the drawings shall be
construed as to conflict with National and Local Ordinances or Laws governing
the installation of VAC Work and all such laws and ordinances are hereby
made part of the specifications. The Contractor is required to meet the
requirements thereof.

B.

Codes and standards of the following organizations other than mentioned above are
referenced in this Division. The Contractor shall comply with these codes without
additional cost or compensation;
1. Safety Provisions and Regulations by Local Labor Codes
2. Regulations issued by Ditjen Bina Lindung (Depnaker)
3. Pedoman Plumbing Indonesia etc
4. Regulations issued by PAM & PLN
5. PUIL 2000 etc
6. National Fire Protection Association (NFPA)
7. Fire Offices Committee ( FOC )
8. Air moving and Conditioning Association, Inc. (AMCA)
9. American National Standards Institute (ANSI)
10. American Refrigeration Institute (ARI)
11. American Society of Heating, refrigerating and Air Conditioning Engineers
(ASHRAE)
12. American Society for Testing materials (ASTM)
13. American Welding Society (AWS)
14. American Water Works Association (AWWA)
15. Factory Mutual (FM)
16. British Standard (BS)
17. Japan Industrial Standards (JIS)

15010 - 2

V.A.C WORKS
TECHNICAL SPECIFICATIONS

Rev : 0
Date : 17 Oct 2008

Division No. 2, 1

KAJIMA DESIGN ASIA PTE. LTD


SENAYAN SQUARE - JAKARTA
Office Tower 3 & Annex Carpark 2

1.3. QUALITY ASSURANCE


A.

Surveys and Measurements


The Contractor shall be measured, both horizontal and vertical, from established
bench marks. All work shall agree with these established lines and levels. Verify all
measurements at site and check the correctness of related to the work.
Should the Contractor discover any discrepancy between actual measurements
and those indicated, which prevents following good practice or intent of the
drawings and specifications, he shall notify the Owner/Engineer's and shall not
proceed with his work until he has received instructions from the Owner/Engineer.

B.

Drawings and Minor Modification


Drawings are diagrammatic and indicate the general arrangement of the systems
and work included in the contract. Drawings are not to be scaled. The drawings
and details shall be examined for exact location of fixtures and equipment by
verifying actual site conditions.
The Contractor shall follow drawings in laying out work and check drawings of
other trades to verify spaces in which work will be installed. Maintain maximum
headroom and space conditions at all points. Where headroom or space
conditions appear inadequate, the Owner/Engineer's shall be notified to change
and/or modify before proceeding with installation, fabrication or purchase of
materials and equipment.
If directed by the Owner/Engineer, the Contractor shall change and/or modify at no
extra cost. In the event of changes and/or modification, the contractor shall prevent
confliction with other trade of works.

C. Security and Safety


The Contractor shall protect all works and materials from damage by his work,
workmen, Subcontractor's work or Subcontractor's workmen and shall be liable for
all damaged caused.
The Contractor shall be responsible for work and equipment until finally inspected,
tested, and accepted. He shall protect work against theft, injury or damage and
shall carefully store material and equipment received on sites which are not
immediately installed. He shall seal temporary covers or plugs during storage and
construction to prevent entry of foreign material from open end.
The Contractor shall take adequate prevention against fire by observing the
following measures;
15010 - 3

V.A.C WORKS
TECHNICAL SPECIFICATIONS

Rev : 0
Date : 17 Oct 2008

Division No. 2, 1

KAJIMA DESIGN ASIA PTE. LTD


SENAYAN SQUARE - JAKARTA
Office Tower 3 & Annex Carpark 2

1. Provide fire protection equipment in his field office, warehouse and where
actual work is being undertaken.
2. Refrain from smoking in the construction premises and area. Smoking shall
only be allowed in areas designated by the Owner/Engineer.
3. Cooking, if allowed, only in areas designated by the Owner/Engineer.
4. Maintain construction premises and areas in neat and orderly condition by
disposing all waste materials and trash from work area at the end of the day.
The Contractor shall also make available first-aid facilities during all hours that
work is in progress. Such basic first-aid kit and equipment must be adequate
to treat minor injuries.
D. Cleaning and Sanitation During Construction Period
1. The Contractor shall maintain the construction premises and area in a
reasonably neat and orderly condition, free from accumulation of waste
materials and rubbish during the entire construction period. He shall remove
crates, cartons and other flammable waste materials and trash from the work
areas at the end of each day.
2.

The Contractor shall clean and leave free from rubbish such as, loose
plaster, mortar drippings, extraneous materials, dirt and dust in electrical
closets, pipe and duct shafts, furred spaces and similar spaces where
generally unfinished.

3. The Contractor shall clear rubbish, trash and debris designated area or outside
building. He shall not throw or drop such waste and rubbish from one level to
another within or outside the buildings.
4.

The Contractor shall not mark soil or deface finished surfaces and restore
such defaced surfaces to their original finished conditions.

5.

The Contractor shall clean the areas where painting and finishing are to be
performed prior to starting said activities. This includes cleaning of exposed
structural steel, miscellaneous metals, woodworks, plaster, and masonry,
concrete, mechanical and electrical equipment, piping, ductworks, conduit and
also surfaces visible after permanent fixtures, grilles, registers and devices
have been installed in place.

6. The Contractor shall only use designated sanitary facilities constructed solely
for their use. Such facilities shall be completed and in good working order
before any work is commenced or the construction camp is occupied.
15010 - 4

V.A.C WORKS
TECHNICAL SPECIFICATIONS

Rev : 0
Date : 17 Oct 2008

Division No. 2, 1

KAJIMA DESIGN ASIA PTE. LTD


SENAYAN SQUARE - JAKARTA
Office Tower 3 & Annex Carpark 2

7. The Contractor shall be responsible for and shall exercise all sanitary
precautions and control at the jobsite to safeguard the public health and the
living conditions of his laborers.
E.

Material and Workmanship:


1. The works shall be executed in the best and most thorough manner to the
satisfaction by the Owner/Engineer's, who will jointly interpret the meaning of
the Drawings and Specifications and shall have power to reject any work and
materials which, in their judgment, is not in full accordance therewith.
2. The Contractor shall take responsibility to provide the service of a qualified
Engineer to supervise the installations of systems and who shall have
capability of conducting the final acceptance tests.
3.

All materials, equipment and apparatus required for the work shall be new
and first class quality, furnished, delivered, erected, connected and finished in
every detail and shall be so selected and arranged as to fit properly into the
building spaces. Where no specific kind or quality of material is first class
article shall be furnished.

4. The Contractor shall furnish the services of a full time, experienced


superintendent, who shall available supervised and coordinate the installation
of the work, with skilled workmen, fitters, metal workers, welders, helpers and
laborers required to unload, transfer, erect, connect-up, adjust, start, operate,
and test on each system.
1.4. SUBMITTALS
A.

The Contractor shall submit to the Engineer for approval, detailed shop drawings of
all equipment and all materials required to complete the project. No material or
equipment may be delivered to the jobsite or installed until the Contractor has
obtained the approved shop drawings of all materials or equipment. The shop
drawings shall be complete as described herein.
The Contractor shall furnish five (5) copies of the submittals as required by the
Contract.

B.

Submit materials and equipment informations such as manufacturer, trade name


and model number including copies of applicable brochure or catalog material. Do
not assume applicable catalog are available in the Engineers office. Maintenance
and operating manuals are not suitable substitutes for shop drawings.

C. Identify each sheet of printed submittal pages (using arrows, underlining or circling)
to show applicable sizes, types model numbers, ratings, capacities and options
15010 - 5

V.A.C WORKS
TECHNICAL SPECIFICATIONS

Rev : 0
Date : 17 Oct 2008

Division No. 2, 1

KAJIMA DESIGN ASIA PTE. LTD


SENAYAN SQUARE - JAKARTA
Office Tower 3 & Annex Carpark 2

actually being proposed. Cross out non-applicable information. Note specified


features such as special tank linings, pump seals, materials or painting.
D.

Include dimensional data for roughing in and installation, technical data sufficient to
verify that equipment meet requirements of drawings and specifications. Include
wiring, piping and service connection data, motor sizes complete with voltage
ratings and schedules.

E.

Installed materials and equipment shall meet specified requirements.

F.

Furnish a complete set of reviewed and stamped shop drawings and product data
on site.

G. Prepare and submit detailed shop drawings for piping work and other distribution
services, including locations and sizes of openings in floor decks, walls and roofs.
H.

The work described in shop drawing submission shall be carefully checked for
clearances (including those required for maintenance of equipment and proper
coordination with other trades on the job site. Each submitted shop drawing to
include a certification that related job conditions have been checked and that
confliction do not exist.

I.

Shop drawings shall be submitted in advance of field requirements to allow for


ample time for checking. Submittals shall be completed and contain required
detailed information. Shop drawings with multiple parts shall be submitted as a
package.

J.

Submit scaled shop drawings request by the Owner/Engineer's for approval. The
Contractor shall submit general layout and details of these works within one (1)
month prior to actual installation Construction Managements approval.

K.

If submittals differ from the Contract Document, to state such difference in a written
transmittal, with request for substitution, together with reasons.

L.

Approved data or shop drawings for materials, equipment, apparatus, devices,


arrangement and layouts shall not relieve the Contractor from responsibility of
furnishing dimensions and weight, capacities, sizes, quantity, quality and installation
details to perform the requirements and intent of the Contract. Approval shall not
relieve the Contractor from responsibility for errors, omissions or inadequacies of
submitted data or shop drawings.

M.

Each shop drawing shall contain job title and reference to the Applicable drawing
and specification article.

N. Within three (3) weeks after award of Contract, submit a complete list of shop
drawings which will be submitted in the course of the project.
15010 - 6

V.A.C WORKS
TECHNICAL SPECIFICATIONS

Rev : 0
Date : 17 Oct 2008

Division No. 2, 1

KAJIMA DESIGN ASIA PTE. LTD


SENAYAN SQUARE - JAKARTA
Office Tower 3 & Annex Carpark 2

O. Submit shop drawings and manufacturer's data for the following items in
accordance with the Contract Documents;
1. Coordinated, detailed layout drawings of mechanical rooms, services and
distribution systems, including plans, profiles and sections.
2. Details of piping supports, seismic bracing, elbows, anchors and miscellaneous
appurtenances.
3. Hangers, supports, insert anchors and guides.
4. Valves.
5. Pressure gauges and thermometers.
6. Ductwork and piping layout at requested scale by the Owner/Engineers for the
building.
7. Location and sizes of sleeves for openings in floors and walls.
8. Certified equipment performance curves for pumps.
9. F a n s.
10. Schedule of pipe and fittings, materials and application, valves, escutcheons,
Air vents, valve tags and schedules, strainers, and water specialties.
11. Pumps and Tanks.
12. Access doors, dampers, fire dampers, smoke dampers, combination fire and
smoke dampers.
13. Air distribution devices.
14. Sound insulation, thermal insulation, sound traps, and vibration isolation.
15. Flushing.
16. Motors.
17. Equipment identification.
18. Water coils.
19. Refrigeration machines and cooling towers.
15010 - 7

V.A.C WORKS
TECHNICAL SPECIFICATIONS

Rev : 0
Date : 17 Oct 2008

Division No. 2, 1

KAJIMA DESIGN ASIA PTE. LTD


SENAYAN SQUARE - JAKARTA
Office Tower 3 & Annex Carpark 2

20. Air filters including media, frames and cabinet construction.


21. Ducting specialties, dampers, turning vanes, flexible duct and flexible
connections.
22. Sheet metal shop details.
23. Water treatment.
24. Automatic control system.
25. Other shop drawings and submittals within the specifications and as requested
by the Engineer.
P.

Upon completion of the portion of work and the Contractor obtained final
acceptance, to submit five (5) copies of approved operation and maintenance
manuals and As-built drawings, and other documents as specified in Section 15015
to the Owner/Engineer.

1.5. COORDINATION
A.

The VAC drawings show the general arrangement of equipment, ductwork, piping
and accessories. Follow these drawings as closely as the actual construction and
the work of other trade will permit. Provide offsets, fittings and accessories which
may be required but not shown on the drawings. Investigate the site, structural and
finish ground conditions affecting the work and arrange the work accordingly.
Provide such work and accessories as may be required to meet such conditions.

B.

Certain materials will be provided by other trades. Examine the Contract Documents
to ascertain these requirements.

C.

Carefully check space requirements with other trades to insure that materials can
be installed in the spaces allotted including finished suspended ceilings

D.

Wherever this work interconnects with work of other trades, coordinate with other
trades to insure that they have the information necessary so that they may properly
install the necessary connections and equipment. Identify items (valves, dampers,
coils, etc.) requiring access in order that the Ceiling Works Contractor will know
where to install access doors and panels.

E.

Consult with other trades regarding equipment so that, wherever possible, motors,
motor controls, pumps and valves are of the same manufacturer.
Furnish and set sleeves for passage of pipes, ducts and conduits through structural
masonry and concrete walls and floors and elsewhere as required for the proper
protection of each pipe and duct passing through building surfaces.

F.

15010 - 8

V.A.C WORKS
TECHNICAL SPECIFICATIONS

Rev : 0
Date : 17 Oct 2008

Division No. 2, 1

KAJIMA DESIGN ASIA PTE. LTD


SENAYAN SQUARE - JAKARTA
Office Tower 3 & Annex Carpark 2

G. Provide required supports and hangers for piping and equipment, designed so as
not to exceed allowable loading of structures.
H.

Examine and compare the contract drawings and specifications with the drawings
and specifications of other trades and report any discrepancies between them to the
Engineer and obtain from him written instructions for changes necessary in the VAC
Work in cooperation with other related trades. Before installation, make proper
provisions to avoid interferences.

I.

Wherever the work is of sufficient complexity, prepare additional detail drawings to


scale similar to that of the design drawings, prepared on tracing medium of the
same size as contract drawings. With these layouts, coordinate the work with the
work of other trades. Such detailed work to be clearly identified on the drawings as
to the area to which it applies. Submit these drawings to the Engineer for approval.
At completion, include a set of such drawings with each set of as-built drawings.

J.

Slots, chases, openings and recesses through floors, walls, ceilings and roofs shall
be provided by the various trades in their respective materials. Properly locate such
openings and be responsible for cutting and patching.

K.

Adjust location of pipes, equipment, etc., to accommodate the work to prevent


interferences, both anticipated and encountered. Determine the exact route and
location of each piping and equipment prior to fabrication.
1. Right-of-Way: Lines which pitch have the right-of-way over those which do not
pitch (e.g. Plumbing drains normally have right-of-way). Lines whose
elevations cannot be changed have right-of-way over lines whose
elevations can be changed.
2. Make offsets, transitions and changes in direction in pipes and ducts as
required maintaining proper head room and pitching on sloping lines. Furnish
and install air vents, drains, etc., as required to affect these offsets, transitions
and changes in direction.

L.

Install the VAC Works to permit removal (without damage to other parts) of coils,
chiller tube bundles, fan shafts and wheels, filters, belt guards, sheaves and drives,
and other parts requiring periodic replacement or maintenance. Arrange pipes and
equipment to permit access to valves, gauges, starters, motors and control
components, and to clear the opening of swinging doors and access panels.

M.

Change in the cross-sectional dimensions of ductwork is permissible when


required to meet job conditions. Maintain at least the same equivalent crosssectional duct area in accordance with the latest edition of ASHRAE Guide. To
obtain approval from the Engineer prior to fabrication of ductwork requiring such
changes.
15010 - 9

V.A.C WORKS
TECHNICAL SPECIFICATIONS

Rev : 0
Date : 17 Oct 2008

Division No. 2, 1

N.

KAJIMA DESIGN ASIA PTE. LTD


SENAYAN SQUARE - JAKARTA
Office Tower 3 & Annex Carpark 2

Provide access panels in equipment, duct, as required for inspection and


maintenance of internal equipment.

1.6. GUARANTEE
A.

The Contractor shall guarantee that the VAC System is free from all defective
workmanship and materials and will remain so for a period of One (1) year from date
of final acceptance as certified by the Owner/Engineer.

B.

Any defects, appearing within the aforesaid period shall be promptly remedied by
the Contractor at his own expense.

C.

The Contractor shall indemnify and save harmless the Owner and the Engineer
from and against all liability for damages arising from injuries or disabilities to
persons or damage to property occasioned by any act or omissions of the
Contractor or any of his Subcontractors, including any and all expenses, legal or
otherwise which may be incurred by the Owner or the Engineer, in defense of any
claim, action or suit.

PART 2 - PRODUCTS
2.1. EQUIPMENT AND MATERIALS
A.

The Contractor shall fully protect finished parts of the materials and equipment
against damage from whatever cause during duration of the work until final
acceptance. Materials and equipment in storage and during construction shall be
covered in such a manner that no finished surfaces will be damaged or marred and
moving parts shall be kept clean and dry.

B.

If products and materials are specified or indicated on the drawings for a specific
item or system, the Contractor shall use those products or materials. If products and
materials are not listed in either of the above, use first class product and materials,
subject to approval of shop drawings.

C. Products and materials shall be new, clean, free of defects, damage and corrosion.
D. Ship and store products and materials in a manner which will protect them from
damage, weather and entry of debris. If items are damaged, do not install, but take
immediate steps to obtain replacement or repair.
E.
F.

Replace materials with less than specified quality or as designated by Engineer


and relocate work incorrectly installed as determined by Engineer.
Materials and equipment installed shall be new, of the quality specified. Statically
15010 - 10

V.A.C WORKS
TECHNICAL SPECIFICATIONS

Rev : 0
Date : 17 Oct 2008

Division No. 2, 1

KAJIMA DESIGN ASIA PTE. LTD


SENAYAN SQUARE - JAKARTA
Office Tower 3 & Annex Carpark 2

and dynamically balance rotating equipment shall be of minimum vibration and low
operating noise level.
G. Provide name/data plates on major components of equipment with manufacturer's
name, model number, serial number, capacity data and electrical characteristics
attached in a conspicuous place.
H. Install materials and equipment by qualified trades people.
I.

Maintain uniformity of manufacturer for equipment used in similar applications and


sizes.

J.

Applicable equipment and materials to be manufactured in accordance with ASME,


ANSI or JIS standards, or as approved by local code enforcement authorities having
jurisdiction.

K.

Fully lubricate equipment when installed.

L.

Do not operate water systems until piping has been cleaned and strainers are in
place.

M. Secure equipment with bolts, washers and locknuts of ample size to support
equipment. Embedded anchor bolts to have bottom plate and pipe sleeves. Grout all
machinery set in concrete under the entire bearing surface. After grout has set,
remove all wedges, shims and jack bolts and fill space with grout.
N. Valves, actuators and access doors, shall be easily accessible, either in mechanical
spaces or through access panels specified.
O. Follow manufacturers' instructions for installing, connecting, and adjusting
equipment. Provide a copy of such instructions at the equipment during work on the
equipment.
P.

Pressure vessels and relief valves shall be selected, built and labeled in accordance
with ASME or JIS. Obtain necessary certificates from the Code Enforcement
Authority (Depnaker) showing such acceptance.

Q. General test shall be carried out for all VAC systems prior to the handover.
R. All cost relating to the test and certificate from the Authority shall be Contractors
scope of work.
2.2. ALTERNATIVE MATERIALS AND EQUIPMENT
A.

Materials and equipment are based on Contract documents. Approval by the


15010 - 11

V.A.C WORKS
TECHNICAL SPECIFICATIONS

Rev : 0
Date : 17 Oct 2008

Division No. 2, 1

KAJIMA DESIGN ASIA PTE. LTD


SENAYAN SQUARE - JAKARTA
Office Tower 3 & Annex Carpark 2

Engineer of equipment submitted by the Contractor as equal to that specified does


not relieve the Contractor of any responsibility for contract compliance.
B.

Equipment manufacturers listed in individual sections are approved for this project,
subject to requirements of contract documents.

C. Submit proposals for alternative materials or equipment, in writing, to the Engineer


at least Seven (7) days prior to closing date of tender for VAC Work.
D.

Revisions required to adapt to the proposed alternatives shall be included in such


proposals. No increase in the contract price will be considered to accommodate the
use of equipment other than specified.

E.

Wherever operating results such as quantity delivered, pressure obtained, or


similar results are specified or a definite manufacturer and size of apparatus is
specified, for which such quantities are readily determinable, the manufacturer and
size of apparatus that the Contractor has proposed to use must conform
substantially (in regard to the operating results) to the quantities specified or
implied. This requirement shall also apply to important dimensions relating to
operation of apparatus in coordination with the rest of the system and to properly
locating the apparatus in available space conditions.

F.

Acceptance of substitutions for equipment specified shall be given only after


receipt of complete and satisfactory performance data covering the complete range
of operating conditions in tabular and graphical form. Furnish complete and
satisfactory information relative to equipment dimensions, weight, etc. Acceptance
of equipment specified or shown on the drawings or substitutions submitted for that
specified or shown on the drawings, will be granted if such equipment, in the opinion
of the Engineer, conforms to the performance requirements, space conditions,
weight requirements and quality requirements. Any additional construction and
design costs incurred as a result of any accepted substitution shall be borne by the
Contractor.

2.3. SUBCONTRACTS, ETC


The Contractor shall be fully responsible for the work of any Subcontractor or
manufacturer performing work for or supplying materials from, as it is intended that the
entire VAC Work, when finally delivered to the Owner shall be ready in every respect for
satisfactory and efficient operation.
2.4. DESIGN CONDITIONS
A.

Outdoor Design Conditions.


Maximum Outdoor Condition

Outdoor Temperature : 33.3oC DB

Relative Humidity
: 68 %
15010 - 12

V.A.C WORKS
TECHNICAL SPECIFICATIONS

Rev : 0
Date : 17 Oct 2008

Division No. 2, 1

Wind Velocity

Minimum Outdoor Condition

Outdoor Temperature

Relative Humidity

Wind Velocity
B.

KAJIMA DESIGN ASIA PTE. LTD


SENAYAN SQUARE - JAKARTA
Office Tower 3 & Annex Carpark 2

8 m/s

: 21.5oC DB
: 91%
: 1 m/s

Indoor Design Conditions


Temperature

Offices
Meeting Areas
Lobbies
Lounge
BAS/PABX Room
Computer Rooms

Relative Humidity
(oC) DB
% RH
24 1oC
24 1oC
N.A.
24 1oC
N.A.
:
24 1oC
:
22 1oC
o
22 1 C
N.A.

:
:
:

N.A.

N.A.
N.A.

C. Noise Criteria
NC

Offices
Meeting Areas
Lobbies
Lounge
Clinic
Computer Rooms

:
:

35 - 40

35 - 40
:
:

35 - 40
35 - 40
:

35 - 40

40 - 45

PART 3 - EXECUTION
3.1. SUBSTANTIAL COMPLETION INSPECTION
A.

Prior to this inspection, confirm in writing, that the following work is completed;
1. Ventilation and air conditioning systems are capable of operation with alarm
controls functional and automatic controls in operation, generally.
2. Tests performed on equipment including those required by authorities and
approval certificates obtained.
3. Rough balance of air and water systems are complete.
4. Valve tagging is completed, equipment is identified and escutcheons installed.
15010 - 13

V.A.C WORKS
TECHNICAL SPECIFICATIONS

Rev : 0
Date : 17 Oct 2008

Division No. 2, 1

KAJIMA DESIGN ASIA PTE. LTD


SENAYAN SQUARE - JAKARTA
Office Tower 3 & Annex Carpark 2

Equipment and piping are painted.


5. Equipment is lubricated per manufacturer's instructions.
6. Systems are chemically cleaned, flushed, strainers are cleaned and water
treatment initiated. Obtain report from Manufacturer's Representative to
confirm acceptability of treatment provided.
7. Samples of Operating or Maintenance Manuals submitted. Arrange Operating
and Maintenance Instruction Seminar and submit schedule for approval.
8. Ensure electrical connections to VAC equipment are complete.
9. Noise and vibration control devices including flexible connections and written
report submitted.
10. Equipment aligned by qualified millwright and certified report submitted.
11. Air handling units and ductwork plenums cleaned, permanent filters installed.
B.

Prior to the inspection, provide complete list of items which are not finished or
deficient at the time of the scheduled inspection.

C. Prior to the final inspection, provide in writing that previously identified deficiencies
and the following items have been completed.
1. Equipment cleaned inside, outside and lubricated.
2. Final balancing completed and balance reports submitted.
3. Final calibration of controls completed and control system report submitted.
4. Written report of flushing to be submitted
3.2. START-UP
A.

Properly lubricate to equipment.

B.

Check and clean ducts of dirt and debris.

C. Install filters in air handling systems and strainers on pumps.


D. Prepare each piece of equipment in accordance with manufacturers installation
instructions and have a copy at the equipment.
E.

Fill and vent water systems.


15010 - 14

V.A.C WORKS
TECHNICAL SPECIFICATIONS

Rev : 0
Date : 17 Oct 2008

Division No. 2, 1

F.

KAJIMA DESIGN ASIA PTE. LTD


SENAYAN SQUARE - JAKARTA
Office Tower 3 & Annex Carpark 2

Check rotation on each motor.

G. Have representatives of each manufacturer present when here in after specified, so


that equipment will be started up by manufacturer.
H. Test requirements under section on Tests shall be performed prior to approval of the
work.
3.3. FEES
A.

Printing of plans and specifications required shall be obtained by and at the expense
of the Contractor. The Contractor shall furnish the Owner/Engineers final certificates
of inspection and approval from the proper government authorities after the
completion of the work. The Contractor shall prepare all As-built plans and all other
paperwork required by the approving authorities.

B.

Contractor permits and fees will be covered by the Contractor.

C. Approval from authorities of all documents plans and specifications for construction
and permit shall be secured by the Contractor.
D. Pay required fees for testing and inspection to ensure code compliances.
E.

Pay royalties or fees required in connection with the use of patented devices and
systems, if any.
END OF SECTION

15010 - 15

V.A.C WORKS
TECHNICAL SPECIFICATIONS

Rev : 0
Date : 17 Oct 2008

Division No. 2, 1

15010 - 16

KAJIMA DESIGN ASIA PTE. LTD


SENAYAN SQUARE - JAKARTA
Office Tower 3 & Annex Carpark 2

Вам также может понравиться