SAUDI ARAMCO ID/PID - REV 1 - 5/18/05 (Standards Cutoff - August 2004)

SATIP No.

SAUDI ARAMCO TYPICAL INSPECTION PLAN


SHOP FABRICATION - PIPING & MISCELLANEOUS STEEL STRUCTURES

APPROVED DATE

SATIP-L-350-08

PROJECT TITLE:

ITEM
NO.

1.0

PROJECT PHASE
& Activity Code

DISCIPLINE:

25-May-05

MECHANICAL

CONTRACTOR/SUBCONTRACTOR

TASK / ACTIVITY

QUALITY
PROCEDURE

QUALITY
RECORD

INSPECTION RESPONSIBILITY
ASSIGNMENTS
CNTRCTR

SAUDI
ARAMCO

H1

H1

REMARKS

DOCUMENT REVIEW

SAIC-L-2031
(HOLD)

Fabrication Shop - any fabrication facility outside or


within the project site subject to controlled conditions
and approval by Saudi Aramco Inspection (PID or
VID) per SAES-W-011, 17.6.1.3.1.

1.1

Fabrication Shop Qualification & Approval

1.2

NDE Procedure

1.3

Positive Material Identification (PMI)


Procedure

SAIC-L-2004

HR1

R1

1.4

Pipe Bending Procedure (if required)

SAIC-L-2033

H1

R1

2.1

Verification of Pipe and Fittings (Visual


Inspection & Document verification)

SAIC-L-2005

SAIC-L-2005

W1

W2

SA to witness the initial delivery and perform random


inspection thereafter.

2.2

Structural Steel & Plates

SAIC-M-2003

SAIC-M-2003

W1

W2

SA to witness the initial delivery and perform random


inspection thereafter.

2.3

Material Storage & Handling

SAIC-L-2034

SAIC-L-2034

W1

2.4

Positive Material Identification of Alloyed


Materials

SAIC-L-2010

SAIC-L-2010
SATR-A-2012
SATR-A-2013

H1

W2

3.1

Cutting & Assembly fit-up

SAIC-L-2035

SAIC-L-2035

W1

3.2

Welding Inspection

2.0

3.0

Refer to the applicable SATIP for NDE; SATIP-NDELPT-01, NDE-MPT-01, NDE-RT-01, NDE-UT-01

MATERIAL RECEIVING

See Note 1 and will perform random inspection


thereafter.

FABRICATION
NOTE: Depending on the QC Organization, this is
usually assigned to the Piping Inspector, should there
be a division of responsibility between a Piping
inspector and a Welding inspector.
Refer to the applicable SATIP for welding: SATIP-W011-01, W-012-01, W-016-01, W-014-01, & M-00104

Page 1 of 2

APPROVED DATE

SATIP No.

SAUDI ARAMCO TYPICAL INSPECTION PLAN


SHOP FABRICATION - PIPING & MISCELLANEOUS STEEL STRUCTURES

SATIP-L-350-08

PROJECT TITLE:

ITEM
NO.

DISCIPLINE:

25-May-05

MECHANICAL

CONTRACTOR/SUBCONTRACTOR

PROJECT PHASE
& Activity Code

TASK / ACTIVITY

QUALITY
PROCEDURE

QUALITY
RECORD

INSPECTION RESPONSIBILITY
ASSIGNMENTS
CNTRCTR

SAUDI
ARAMCO

REMARKS

3.3

Cold Bending

SAIC-L-2036

SAIC-L-2036

H1

W1

3.4

Hot bending

SAIC-L-2037

SAIC-L-2037

H1

W1

3.5

NDE Performance Verification

Refer to the applicable SATIP for NDE; SATIP-NDELPT-01, NDE-MPI-01, NDE-RT-01, NDE-UT-01.

3.6

Pressure Testing (when required)

Refer to SATIP-A-004-02 or A-004-01 whichever is


applicable.

3.7

Painting (when required)

Refer to the applicable Painting SATIP:


SATIP-H-100-01

4.0

RELEASE FOR
SHIPMENT

4.1

Visual inspection of completed pipe


spools or assembly

SAIC-L-2038

SAIC-L-2038

H1

W1

4.2

Visual inspection of completed structural


components or assembly

SAIC-M-2021

SAIC-M-2021

H1

GENERAL NOTES
1

The first three incidents of each Inspection or testing activity listed require 100 % participation by Saudi Aramco Site Inspection Personnel. After this period, Saudi Aramco Inspection may adjust the
levels of Saudi Aramco participation based upon the Contractors performance.

Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization

Witness:
QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC organization representative
is not present.

Hold:

If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Saudi Aramco.

QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization representative in attendance.

LEGEND
W1

100% Witness Inspection/Test

H2

Sample Hold Point for QC Inspection or Test

RH1 100% Review and Approval of Documents

W2

Sample Witness Inspection/Test

R1

100% Review of Documents

RH2 Sample Review and Approval of Documents

H1

100% Hold Point for QC Inspection or Test

R2

sample Review of Documents

Page 2 of 2