Академический Документы
Профессиональный Документы
Культура Документы
well bore, having lost their supports, and cause the well to sand up.
Several remedial operations that have been used in eliminating or
significantly reducing the sand problems in this area are discussed.
Plastics,
plastic coated walnut shells and Ottawa sands, of various grades, were used
in these operations.
CASE 4F1
Prior to undertaking this operation the well was producing 102 BID net of
24 gravity oil.
top perforations for purposes of cementing and plasticizing the blank liner
annulus to the shoe of the water string.
duced satisfactorily, but with increasing sand problems, from March 1959 to
July 1961, when remedial operations were started.
operation prior to remedial work, investigation showed that the tubing had
been sand blasted, thus indicating the point of sand entry_
-2A production rig was moved over the well, the oil in the hole was
displaced with oil base fluid, and the hole cleaned out to bottom.
A 6-5/8" straddle tool with a four foot net span and a plug ca.tcher
above one joint of tubing was run in the hole on 2-1/2" tubing to approximately ten feet above the perforations.
tested with 1200 psi pressure.
C.P. holes and closed.
pulled up three feet, and an additional three or four cubic feet of displacing
fluid was pumped in to clear the tool of plastic.
slowly. to prevent swabbing of the hole.
run on tubing and the excess pI a.stic cleaned out of the liner.
A straddle
tool was rerun on tubing and the C.P. holes tested with pressures ranging
from 500 psi to 1000 psi.
The straddle tool was pulled out and the hole was
-3CASE 112
Ntll!e!'.
These were pump-packed with 720 sacks of 6-9 gravel and 20-40
problems from November 1958 until May 1959 when remedial operations took
place.
A production rig was set over the well and the liner was backscuttled to bottom and the tubing was pulled out.
A 6-5/8" retrievomatic
cementing tool was run in on tubing and set in the liner at a point halfway
between the top and bottom of the perforations.
Dis-
Again
-4Fourteen sacks of plastic coated walnut shells were pumped down the tubing.
In both stages of this operation, rubber balls were intermittently inserted
to obtain a more uniform distribution of the sand.
taken to allow the pressure to equalize before releasing the tool and pulling
out.
A 5-5/8" roller bit was run on tubing and excess sand and gravel
were cleaned out of the liner.
This well was producing 28 B/D net of 22.9 gravity oil, cutting
88.3% water.
increasing sand problems since March 1960 and in November 1961 remedial
operations were started.
A bailer was run through the tubing and the liner cleaned out
to bottom.
The oil in the hole was displaced with oil base drilling fluid
pulling up of the straddle tool, five practice runs were made prior to the
actual ope ration.
The tubing pump and rods were rerun and the well returned
to production.
Since that time, November 1961, the well has produced satisfactorily
and at present is producing 37 BID net of 23.7 gravity oil.
The average cost of these remedial operations was $8600.00.
Since being returned to production each has produced sufficiently to
recover these remedial costs.
It should be noted that there was a production loss, ranging from
25 to 50%.
remedial operations with plastic, because the oil sands in the interval
treated become plugged with plastic.