EXECUTIVE SUMMARY

The Eleco group develops software solutions and services for the architectural, engineering and construction
industries. Asta Powerproject is part of the Eleco Groups offerings.
Used globally, Asta Powerproject leads the market in project management software as case studies and
testimonials within this report will prove.
Asta Powerprojects features include flexible license options which save costs in comparison with P6, in
addition to innovative features not found in other project management software.
The report concludes with references and contact details of International and Australian users of Asta
Powerproject.

Page 3 of 21

INDEX

Executive Summary ............................................................................................................................................ 2


Index ................................................................................................................................................................... 3
Introduction ........................................................................................................................................................ 4
Introduction to Asta Powerproject ................................................................................................................. 5
Where is Asta used Globally? ............................................................................................................................. 5
Solid Support ...................................................................................................................................................... 6
Banora Point Case Study - Introduction ............................................................................................................. 7
Licensing Options ................................................................................................................................................ 8
Summary of Licensing Costs in comparison with P6*:.................................................................................. 10
Asta Powerproject 4d bim ............................................................................................................................ 11
Activity Scheduling........................................................................................................................................ 12
Progress Reporting ....................................................................................................................................... 13
Custom Automation ..................................................................................................................................... 14
Risk/Issue Management ............................................................................................................................... 15
Easy site-to-office project progress reporting via your mobile devices ....................................................... 17
Summary ........................................................................................................................................................... 19
References and Contacts .................................................................................................................................. 20
Multiplex : ..................................................................................................................................................... 20
Westfield :..................................................................................................................................................... 20
Hansen Yuncken ........................................................................................................................................... 20
Probuild ........................................................................................................................................................ 20
Australand .................................................................................................................................................... 20
Paul Harris..................................................................................................................................................... 20
Appendix 1 : Asta Powerproject System Requirements ................................................................................... 21

Page 4 of 21

INTRODUCTION
SOFTWARE DEVELOPMENT AND SERVICES FOR THE ARCHITECTURAL, ENGINEERING AND CONSTRUCTION
INDUSTRIES

In 1901, ELECO designed and supplied the electric light lanterns that now grace the Victoria Embankment in
London and has provided innovative technical solutions to the UK construction industry for more than 100
years. ELECO has now emerged as a leading supplier of innovative technology led software applications and
training for project management, estimation, visualisation and Building Information Modelling disciplines to
construction industries worldwide.
ELECO group currently comprises nine companies which market and sell software applications directly to many
leading construction companies primarily in the UK, Sweden, Germany and Benelux but also through dealer
and channel partner networks in other international markets in Eastern Europe, the US, Australia and New
Zealand.
In 1939, ELECO was listed on the London Stock Exchange. It is now listed on the AIM market (AIM:ELCO).
Asta Development, part of Eleco, is a leading international developer of project, portfolio and resource
management software.
Since its launch in 1988, Asta Powerproject has evolved and improved driven by regular feedback from global
users and using the latest technologies available. We listen carefully to our customers and their feedback plays
a key role in shaping how we continuously develop and improve our products and services.

Page 5 of 21

INTRODUCTION TO ASTA POWERPROJECT

Asta Powerproject, is a class-leading project, portfolio and resource management solution used successfully
throughout the world on projects of all sizes and by all industry sectors. The software is suitable for use by
anyone involved in the delivery of a project.
Asta Powerproject at a glance:

Quickly create and update precise project schedules


Produce high quality standard and custom reports
Reduce costs with flexible licensing and deployment options
Enter task updates directly with laptop or mobile device
Show, analyze and compare progress against unlimited baseline plans
Easily manage resources, costs and third-party participants with drag and drop functionality
Integrate with MS Outlook, accounting, BIM and ERP systems such as SAP
Easily import and export data from Primavera and MS Project
Provide view and print access with our Free Project Viewer

WHERE IS ASTA USED GLOBALLY?

Asta Development works with a wide range of customers, large and small across a wide variety of industry
sectors throughout the world. Our project, portfolio and resource management software is used by them to
support activity on simple through to complex business activity.
Asta Powerproject is a valued tool for Project & Portfolio Management read why in our customer case
studies : http://www.astadev.com/customers/

Page 6 of 21

SOLID SUPPORT

Solid Supports national coverage ensures consistency of service and support for Asta Powerproject users
across Australia, and with our partners in New Zealand. Our strategic relationships with Australian Universities
ensures that the next generation of construction professionals are familiar with the fundamentals of planning
using Asta Powerproject. These Universities include:
The University of Technology Sydney, New South Wales
Bond University, Queensland.
Royal Melbourne Institute of Technology, Victoria.
Curtin University Perth, Western Australia.
Solid Support has delivered 20 years of planning and scheduling expertise to the Australian market. The
addition of Asta Powerproject to the suite of services in 2008 reaffirms Solid Supports commitment to making
global best practice planning tools available in Australia.
As the exclusive distributor in Australia, Solid Support delivers helpdesk services to over 1000 licensed Asta
Powerproject users nationally. With proven consultancy expertise in planning, training, delay analysis and now
3D and 4D planning technology, Solid Support is the perfect partner in time management.

Page 7 of 21

BANORA POINT CASE STUDY - INTRODUCTION

The Banora Point Upgrade Alliance is responsible for upgrading 2.5 kilometres of highway near the New South
Wales and Queensland border in Australia; part of a major programme to transform the Pacific Highway which
runs along the New South Wales coast. The Banora Point project will ultimately create a six-lane divided
carriageway with numerous points of access, a land-bridge and a 300 metre long viaduct. It is being
constructed in close proximity to heritage wetlands, endangered ecological communities, protected snails and
recreational lakes and local communities, under the close scrutiny of local government, community and
environmental groups.
While construction is under way it must be ensured that traffic flow is not interrupted at any of the seven
interchanges/ramps along this length. Such a complex project requires tight overall and daily programme
management, and after early attempts with Primavera P6, Microsoft Project and other tools, this team turned
to Asta Powerproject to create a more consolidated and controllable way of working.

We discovered that it was more user-friendly than P6 and it could perform with higher
functionality if we needed it.
-

Steve Allan, Project Manager: Banora Point

See Appendix for the full Case Study.

Page 8 of 21

LICENSING OPTIONS
There are two main license types available for you to choose from, with the option to share licenses between
team members for increased cost-efficiency.
1.

Asta Powerproject Named User License

Simplest license where the software can be accessed on a specific machine only. However, the license can
periodically be transferred to another machine if required. The project data is stored as a single file which can
be saved on a local memory disk or a shared location.

2.

Asta Powerproject Concurrent User License

The software can be installed on any number of machines which all point to a central machine on the internal
company network where the Asta license server is installed. The license server counts how many people are
using the software and ensures that this number does not exceed the licensed quantity at any one time. A
concurrent license allows multiple people to work on the same project file if that file was saved into a shared
location (such as a network drive or cloud storage) but only one person would be able to edit it at any one
time. Concurrent licenses can also be temporarily loaned for a predetermined time to a designated machine,
allowing Asta Powerproject to be used when offline from the company network.
Asta Powerproject Enterprise
With Asta Powerproject Enterprise, both license options are available with fully collaborative access to a
shared database of project data. This provides all users with shared real-time access to projects, sharing of
project resources, integration with other business critical systems and visibility of all projects.

All projects are stored on a central server


More than one person can work on the same project at the same time
Changes are propagated in real time to all users
Locks data at task level to prevent conflicts

Page 9 of 21
Asta License Manager (ALM)
The concurrent licensing model is extremely flexible in that licenses can be loaned to remote users for periods
of time if required using Asta License Manager.
Asta License Manager (ALM) allows you to streamline the management and distribution of your Asta
Powerproject network licenses from one easy-to-use application. ALM is free with the purchase of one
concurrent license.
Designed to help you manage multiple concurrent licenses across your network, it provides your office-based
staff, mobile and home-based staff with a flexible way of accessing Asta Powerproject wherever they are.
Asta Project Viewer is FREE
Provide everyone involved in your projects with the ability to view, navigate and print out project plans for
free. All you need is Asta Project Viewer 12. Use it to view projects created in Asta Powerproject as well as
Microsoft Project and Primavera.
Supported file formats are:
Asta Powerproject versions 5, 6, 7, 8, 9, 10, 11 and 12 standalone and network editions. Asta
Powerproject multi-user is not supported.
Microsoft Project XML
Oracles Primavera XER (compatible with P3e versions 4.1, P5 and P6)
Oracles Primavera P3 batch format (compatible with Primavera P3)
Choose what information is visible
Users of Asta Powerproject version 10, 11 or 12 can choose exactly which views and charts to show or hide in
Asta Project Viewer. This ensures that users of Asta Project Viewer only see the information that is relevant to
them.

Page 10 of 21

SUMMARY OF LICENSING COSTS IN COMPARISON WITH P6*:

Asta PP Standalone

$ 1,495.00

$ 2,700.00

Primavera P6 PPM

Asta PP Standalone BIM License

2,345.00

NA

TBC

Asta PP Concurrent License

$ 1,995.00

NA

TBC

Asta PP Concurrent Enterprise

$ 2,595.00

NA

TBC

Asta PP Concurrent BIM License

NA

TBC

Asta PP Risk Analysis Network

$ 1,605.00

$ 10,260.00

Primavera Risk Analysis (per user)

NA

No Comparison (Full License cost


required to view a P6 Program)

Asta PP Free Viewer

3,345.00

FREE

*Primavera cost source : https://shop.oracle.com/pls/ostore/f?p=dstore:6:3611154657642::::: Australian pricing. While the website pricing
is accurate at time of writing, we suggest making contact with Oracle directly to confirm.

Sample Project license Configurations and Costs:


Small Project with three fulltime planners, and 15 onsite users requiring infrequent access to a networked
version of the software.
Option 1 -Asta Powerproject with full editing capability for all users:
Stand Alone Licenses : 3 x 1495 = $4485
Concurrent Network Licenses for onsite users: 3 x 1995 = $5985
Unlimited Free Viewer Licenses : FREE

Total : $10,470
Option 2 - Primavera:
3 x Primavera P6 PPM : 3 x 2700 = $8100
15 x Primavera P6 Enterprise Licenses = $44,550

Total : $52,650

Page 11 of 21

ASTA POWERPROJECT 4D BIM


ASTA POWERPROJECT BIM IS 4D ENABLED - LINK YOUR PROJECT PLAN AND MODEL TOGETHER IN ONE
APPLICATION
Quickly create your project plan directly from your IFC4* model file by:
o Dragging and dropping objects between the 3D view and tasks
o Using structured templates with predefined searches to automatically link to the IFC model
objects
Compare `planned and `actual schedule plans with full 3D visual impact
Manage large projects with the ability to save snapshot positions to enable quick navigation
Save images to standard graphical formats to use for reporting or site recording of project status
Create and play a time-line of your project linked to milestones and baselines to simulate subsections
or whole projects
A plugin/upgrade to your existing licence of Asta Powerproject
Full property controls for visual impact and ability to hide and view objects
Manage your 4D planning at an affordable cost
Ideal for tendering and progress monitoring in 3D
Import costs from estimating applications supporting the IFC4 file format

About IFC format


The Industry Foundation Classes (IFC) data model is an open, international and standardized specification for
Building Information Modelling (BIM) data that is exchanged and shared among software applications used by
the various participants in a building, construction or facilities management projects.
IFC can be used to exchange and share BIM data between applications developed by different software
vendors without the software having to support numerous native formats. As an open format, IFC does not
belong to a single software vendor; it is neutral and independent of a particular vendors plans for software
development.

Page 12 of 21

ACTIVITY SCHEDULING

The powerful Gantt chart is at the heart of Asta Powerproject and the ease of use is often quoted as the most
important differentiator. Tasks, summaries, and projects can be drawn directly onto the timeline and modified
via simple mouse interactions. Multiple tasks can be drawn on one line and links between activities also
manipulated via mouse clicks. Asta Powerproject supports multiple links between activities meaning
schedules more accurately reflect the real-world dependencies within a business.

Page 13 of 21

PROGRESS REPORTING

To many, project management software becomes no more than a presentation or drawing tool. The key to
successful project management is accurate tracking of project activity, ensuring that early warning signs are
highlighted and corrective action taken. Asta Powerproject provides unrivalled functionality for running live
projects including:
Unlimited number of baselines, to capture project status at a point in time
Actual progress captured against defined progress periods
Mobile applications and web interfaces for inputting data
Extensive Earned Value Analysis performance monitoring
Business Intelligence reports to propagate key performance indicators

Page 14 of 21

CUSTOM AUTOMATION

Asta Powerproject includes a built-in VBA Macro Editor. This allows custom defined routines to be developed
by either Asta or the user following documented procedures. Macros are ideal for bespoke enhancements
within the software, as opposed to integration with other systems which typically require the use of the full
API.

Page 15 of 21

RISK/ISSUE MANAGEMENT
Asta Powerproject allows for the comprehensive management and tracking of risk/issues, along with a
statistical analysis tool to understand the effects of project uncertainty. Risks can be better assessed,
proactively managed and effectively communicated all directly within Asta:

At a project management layer, risks can be noted against specific tasks, with details added such as impact,
mitigation and current status. A task can be given 3 durations minimum time forecast to take, most likely
duration and maximum predicted time; alternatively, each task can be assigned a category in terms of the
chances of it running late. This allows a Monte Carlo simulation to be run across the project, evaluating the
probability of finishing on time and on budget by applying the uncertainty added to the task durations. The
result is a series of reliable possible outcomes that remove the guesswork for an informed understanding of
the risks faced.

Page 16 of 21

At a programme and portfolio level, risks from across multiple projects can be pulled into a single view to form
an overall risk register. This allows decisions to be taken on the risks which are likely to pose the greatest risk
and the status of risks can be tracked as projects progress.

Page 17 of 21

EASY SITE-TO-OFFICE PROJECT PROGRESS REPORTING VIA YOUR MOBILE DEVICES

Site Progress Mobile is a free downloadable app which enables mobile users to record the progress of tasks
and repetitive events from a remote location against their work as scheduled in an Asta Powerproject project
plan. Each user sees only the relevant tasks and progress check lists for which they have responsibility.
Log in to Site Progress Mobile and the projects assigned to you are downloaded automatically from
the Cloud.
Select your project that you want to update and browse through the project hierarchy to locate the
tasks against which you want to report progress.
Update your individual tasks and tick-off the sections of repetitive events that have been
completed.
Save your updates. Once you have downloaded a project to your mobile device, you can save your
updates to the project even if you do not have a phone or Wi-Fi signal, which may be the case if you
are working onsite in a remote location, or in a basement.
Submit your changes and they are then uploaded to the Cloud as soon as your phone or Wi-Fi signal
is restored.
Site Progress Mobile enables you to:
Record project progress quickly and easily via mobile devices
Update progress at any time, from any location. No signal needed to record progress values, only
when submitting updates
Improve data accuracy by removing need for any re-keying of progress updates from paper notes or
emails
Record actual dates for events, not just the percentage complete
Take photographs and record notes which can be associated with particular tasks or build stages

Page 18 of 21

Download the app for free for Android, Apple, or Windows device.
The Site Progress Mobile app is free to install, with the use of the service charged according to the number of
active jobs exported to the secure cloud storage area.

Page 19 of 21

SUMMARY

Asta Powerproject is world class project management software. Used in Australia over the last 10 years, Asta
has become a highly regarded alternative to Primavera P6 and Microsoft Project.
Asta is easy to get started with which means the barriers for end user uptake are minimal. The added
functionality like intuitive drag and drop resourcing and flexible licensing options catering for power-users
through to basic reviewers is why companies are taking up Asta Powerproject.

Page 20 of 21

REFERENCES AND CONTACTS


MULTIPLEX :
Simon Rhys-Maitland
T : +61 8 9428 6813
E : Simon.Rhys-Maitland@brookfieldmultiplex.com

WESTFIELD :
Angus Davis
T : +61 2 9028 8145
E : adavis@scentregroup.com

HANSEN YUNCKEN
David Hughes
T : +61 8 8229 7333
E : dhughes@hansenyuncken.com.au

PROBUILD
Peter Gallagher
T : +61 3 9693 8222
E : peterg@probuild.com.au

AUSTRALAND
Gary Clark
T : +61 2 9767 2109
E : gclark@australand.com.au

PAUL HARRIS
Paul Harris
T : +61 411 187 701
E : harrispe@eh.com.au

Page 21 of 21

APPENDIX 1 : ASTA POWERPROJECT SYSTEM REQUIREMENTS

Minimum

Recommended

Processor

Intel compatible 400 MHz

Intel compatible 1 GHz or greater

Operating
System

Windows XP, Windows Vista, Windows 7,


Windows 8

Windows Vista, Windows 7,

Memory

1 gigabyte (GB) RAM (32-bit) or 2 GB RAM


(64-bit)

1.5 gigabyte (GB) RAM (32-bit) or 2.5 GB RAM


(64-bit)

Hard Disk

150 Mb disk space

250 Mb disk space

Windows 8

Important Information:
Note that Asta Powerproject only runs on Microsoft Windows operating systems.
Microsoft Windows 64-bit:
Asta Powerproject is approved for use with 64-bit operating systems and is compatible with Asta
Powerdraw (supplied free of charge with Asta Powerproject).
Microsoft Office 2010:
Asta Powerproject Version 12.5.00 will work with Microsoft Office 2010.
Microsoft Windows 2008 R2 Server:
Asta Powerproject Version 12.5.00 is approved for use with Microsoft Windows 2008 R2 Server and
Windows Server 2012 with a GUI (please note non GUI versions are not supported).
Virtual Environments:
Asta Powerproject Version 12.5.00 is supported on VMWare ESX, VMWare ESXi and when using
VMWare Workstation. Other virtual environments are not currently supported. Please contact our
Technical Support team for information on licensing in a VMWare environment.

Asta Powerproject Case Study: Banora Point


ASTA POWERPROJECT HELPS THE EARTH MOVE
FOR BANORA POINT

Steve Allan is Project Manager for


Earthworks for the Banora Point project,
formed between the Roads and Maritime
Services, Abigroup Contractors, Seymour
Whyte Constructions and SMEC. He
explains the scope of the project: We have
about a 7500-task programme broken
down into approximately 70 work areas,
with 12 earthworks and structural
engineers needing to feed constant
updates into the master programme.
We used Primavera P6 for about a year for
the master programme, with our
earthworks engineers using MS Project
and structural engineers utilising MS Excel.
They would send in their updates to a
programmer in Sydney to update the
master plan. We switched about half way
through the programme before that it
was a nightmare.

www.astadev.com

This hybrid was used because each


product had its own strength and each was
required for various parts of the project, but
when Seymour Whyte undertook extensive
reviews and selected Asta Powerproject as
its preferred product, we realised that this
one product could be used instead and we
implemented it on the Alliance. We
discovered that it was more user-friendly
than P6 and it could perform with higher
functionality if we needed it.
The switch to Asta Powerproject allowed
them to maintain an up-to-date view of the
programme for the first time ever, because it
enables multiple users to keep the
information absolutely fresh and current:
We have 12 engineers using the

We discovered that
it was more user-friendly
than P6 and it could
perform with higher
functionality if we
needed it.

The Banora Point Upgrade Alliance is


responsible for upgrading 2.5 kilometres of
highway near the New South Wales and
Queensland border in Australia; part of a
major programme to transform the Pacific
Highway which runs along the New South
Wales coast. The Banora Point project will
ultimately create a six-lane divided
carriageway with numerous points of
access, a land-bridge and a 300 metrelong viaduct. It is being constructed in
close proximity to heritage wetlands,
endangered ecological communities,
protected snails and recreational lakes and
local communities, under the close scrutiny
of local government, community and
environmental groups. While construction
is under way it must be ensured that traffic
flow is not interrupted at any of the seven
interchanges/ramps along this length.
Such a complex project requires tight
overall and daily programme management,
and after early attempts with Primavera P6,
Microsoft Project and other tools, this team
turned to Asta Powerproject to create a
more consolidated and controllable
way of working.

application, and they can all update the


programme at once. They are all working
independently on different aspects within
the same master programme, and our
software now supports that. It has speeded
up the process immensely when we were
using P6 there was a big time-lag. We never
really had an up-to-date programme
because the information was always based
on engineer updates from a week or even
up to a month before. Any issues arising
could add a few days more delay. The
information was never accurate but now,
the master programme effectively updates
itself. I would never know what the status of
the whole job was when I needed it, I would
always be a few days behind waiting for
multiple people to update now, I have the
right information at my fingertips.
With disparate tools in use, inaccurate
information about work schedules between
different trades was a particular issue. Steve
explains: There were clear interfacing risks
between trades, because the earthworks
and structural engineers were using
different programmes that never met in the
middle. We were always having clashes
between activities simply because they

ASTA POWERPROJECT HELPS THE EARTH MOVE


FOR BANORA POINT

The acceptance of the tool has been strong,


with particular appreciation from the
earthworks engineers The earthworks
engineers simply love Asta Powerproject,
and could immediately see how the
software worked when they switched over
from MS Project.
The appreciation of the earthworks team is
perhaps understandable, when you

I roll all the


application information up
into summaries whenever
I need to, such as a
high-level programme
update for the board of
directors. Now it reflects
the detail of the programme
perfectly, because its
based on the actual
information.

www.astadev.com

consider just how complicated the


earthworks challenge is for this project. The
team must move half a million cubic metres
of excavated material and place 350,000
cubic metres of material and soil in the
process of creating the infrastructure and
at the same time, keep the traffic flowing.
We need to do all the earthworks and
construction while maintaining the ability for
traffic to flow through 7 entry and exit points
along the length of the site. There are more
than 70 individual work zones that we have
defined, within which we have to coordinate
work to happen at exactly the right time and
move a lot of earth.
Protecting both the local environment and
local community from the potential impact
of earthworks is essential. Sediment
control is our main concern, because
earthworks create a lot of dirty water. We
must control the runoff from the works
whenever there is rain, and ensure that dirty
water never reaches the public or protected
wildlife areas. We must be really careful as
to how we organise sediment control, so
that we dont flood either highways or
homes and that no untreated water affects
local flora and fauna. It involves a lot of
temporary pipe work and drainage which
must all be planned, constructed and
managed with the help of our planning
software. The team, evidently, has done an
excellent job it has been awarded the
prestigious International Erosion Control
Association (IECA) premier award.
Managing a huge array of different types of
activity would be complex without the right
tools, especially when they touch on key
control conditions which the local
government has mandated about, like noise

and vibration levels. We use the code


library within Asta Powerproject to classify
and tag different activities by factors such as
how noisy they are or the community impact
they might have, and create filters that let us
focus on those activities. Each week we can
meet with the community team and easily
show on screen any community-sensitive
activities like blasting, for instance. This has
been a powerful tool for being able to easily
communicate about all types of activity.
The pinpoint accuracy of time planning and
resource allocation within Asta
Powerproject adds a further level of clarity
to their community and stakeholder
communications both in advance and in
retrospect, since the solution allows for a
clear audit trail as well as forward planning:
We are limited on some activities in terms
of timing, such as not working late and
creating noise too late into the evening. At
any point we can look at the plan and say
that there will be blasting in a particular
place, with a particular noise level, at a
specific time. It also helps us to respond to
questions - if a local resident complains
about an activity and they want answers on
our previous works programme, we can
respond quickly, even though there are
7500 lines of activity. It is easy for us now
to look back to the date of a complaint and
know exactly what we were doing and what
resources were involved. If someone
enquires about when something is going to
be completed, such as a noise-wall,
we can look ahead in Asta Powerproject
and give them a clear date for exactly when
it will be installed.

I love the way you


can move around quickly.
Whereas in MS Project you
must create summary bars
to group activities, in Asta
Powerproject it lifts them
all into a single window so
you can see exactly what
you need.

The team makes good use of all the features


that enable them to test their planning, and
run what if and risk management
scenarios. Asta Powerproject allows us to
look at the critical path from a master point
of view, focus in on critical tasks and ensure
that the duration allowed for each is right,
running risk/opportunity analysis on each
and discussing with key people. We can run
scenarios a lot quicker than before, and they
are more accurate too. We review the
current programme and find risks and
opportunities with respect to the current
programme. We baseline this then make
changes to reflect the realisation of various
risks and opportunities and compare to the
baseline. If we like a scenario Asta
Powerproject allows us to select that option
and convert it from a baseline back into the
actual programme.

The earthworks
engineers simply love
Asta Powerproject, and
could immediately see
how the software worked
when they switched over
from MS Project.

werent visible in the same programme.


Having Asta Powerproject eliminated the
risk of conflicting and mutually exclusive
activities being planned in for the same
timeframe. This improved conflict planning
and general site safety.

ASTA POWERPROJECT HELPS THE EARTH MOVE


FOR BANORA POINT

There are many stakeholders in any


government-backed project, and Steve
values the reporting capability that Asta
Powerproject delivers. I roll all the
application information up into summaries
whenever I need to, such as a high-level
programme update for the board of
directors. Now it reflects the detail of the
programme perfectly, because its based on
the actual information.

www.astadev.com

To have all this capability, enabling


everyone to work concurrently, the
investment was well worth it. They just
asked me to renew my maintenance licence
and I didnt even have to think about it. A
senior manager asked me what I thought of
Asta Powerproject, and whether I would
take it on to future jobs. I replied
Absolutely!

ABOUT ASTA
DEVELOPMENT

Asta Development is a leading


international developer of project,
portfolio and resource management
software which provides solutions
for managing any size and any type
of project.
Since its launch in 1988, the companys
core solution suite, Asta Powerproject,
has evolved and improved driven by
regular feedback from users and using
the latest technologies available. It has
proved its capabilities over the years on

high profile projects throughout the world


and is now used by thousands of
planners in a wide variety of industry
sectors in the UK, Europe, Asia Pacific
and the USA. Asta Development
supports customers directly from its
offices in Oxfordshire and Shropshire.
Outside of the UK, Asta Development
has a network of distributors who supply,
train and support customers, with the
software available in up to seven
different languages. Asta Development is
a part of Eleco plc, a holding company
focusing on software and advanced offsite building systems for the construction
industry. The company is listed on the
London Stock Exchange's Alternative
Investment Market (AIM). More
information about Asta Development and
its products can be found at
www.astadev.com and information about
Eleco plc can be found at
www.eleco.com.

The visual
navigation capability of
Asta Powerproject is
one of its very best
features.

The team has experienced a very smooth


ride in getting up and running with Asta
Powerproject: I have only ever had to call
on Asta Development to help me with one
thing and that was a feature that didnt
really exist involving a custom calculation
around quantity and productivity. The
support was brilliant the support guy
went away and figured it all out, and sent
me an email with every single step
outlined and screen-grabs to show me
what I should be seeing. He gave me
exactly what I needed.

The powerful navigation features of Asta


Powerproject are much appreciated: I love
the way you can move around quickly.
Whereas in MS Project you must create
summary bars to group activities, in Asta
Powerproject it lifts them all into a single
window so you can see exactly what you
need. It makes it really easy to break the job
into different areas, and you never have to
scroll through page after page of activities to
find something. If you have two areas you
want to compare and see how they
interface, you just click Control at the
same time and they both appear side by
side. The visual navigation capability
of Asta Powerproject is one of its very
best features.

To have all this


capability, enabling
everyone to work
concurrently, the
investment was well
worth it.

The ability to tag, classify, colour code and


report on activities feeds directly into
resource planning We use the code library
to manage our hours, and tag all the
nightshift activities carefully; we look at it
every three weeks to ensure we have the
right resources on at night, and tag and run
reports for different trades and
subcontractor types, such as drainage
subcontractors. Because we can easily
run a report filtered only to show drainage
activities; they see exactly whats
relevant to them.

ABOUT BANORA POINT


UPGRADE ALLIANCE

The Banora Point upgrade includes


2.5 km of the Pacific Highway near the
NSW / Queensland border from the
northern end of the Barneys Point
bridge to the southern end of the
completed Tweed Heads bypass.
Roads and Maritime Services (formerly
Roads and Traffic Authority) has formed
an alliance with Abigroup Contractors,
Seymour Whyte Constructions and
SMEC. The alliance project team will
design and construct the Banora Point
upgrade. The Banora Point upgrade is
jointly funded by the Australian and
NSW governments.
For more information visit
http://www.rta.nsw.gov.au/roadprojects/p
rojects/pac_hwy/ballina_tweed_heads/b
anora_point/project_overview.html

Asta Powerproject Case Study: Skanska


The highway to programme management ef ciency at Skanska

Skanska, established in 1887, is one of


the worlds leading project development
and construction groups. The UK
operation is one of the countrys top
contractors, employing over 5200
people and with revenues well over
1billion annually.
Within its diverse business, Skanska
delivers infrastructure services which
span civils and public realm, rail, street
lighting and highways maintenance.
It has a long track record of building,
maintaining and operating highways,
and today delivers round-the-clock
maintenance for roads, tunnels, and
bridges, plus a comprehensive range
of exterior and street lighting services,
to county councils and the Highways
Agency, amongst others.
Graham Roebuck, chief planner within
Skanskas infrastructure services division in
the UK, talks about how he and his team use
Asta Powerproject Enterprise.
The business of highways maintenance
and street lighting management requires
its planners to keep a very tight handle on
all the different jobs that may be running
simultaneously but it also involves a
high degree of repetitive work. To support
this, Grahams team utilises the multiuser and multi-project functionality of Asta
Powerproject Enterprise.

u Planning high volume activity


Graham explains: Highways maintenance
involves planning, processing and managing
a high volume of work. At any time we
might have anywhere between 80 and 200
individual projects underway, starting and
ending at different times. Projects can range
from resurfacing a road to replacement of a
bridge or major road improvement schemes.
We use Asta to manage the whole life-cycle
of all these different projects.
Because many of the projects have common
elements, Skanska has developed a template
approach. All the jobs have some degree of
standardisation so, using Asta Powerproject

www.astadev.com

Enterprise, we have created a series of


templates and then adapt them to individual
jobs. We needed the Enterprise version
because, unlike a typical single project, we
may have 200 different critical paths which
dont interact at all, yet we need to monitor
and track resources and cash-ow within the
whole contract.

We needed the
Enterprise version
because, unlike in a
typical single project, we
may have 200 different
critical paths which
dont interact at all, yet
we need to monitor and
track resources and
cash-ow within the
whole contract.
u Templated approach

He continues: On each type of job well have


an Asta template for work on structures, one
for work on resurfacing, and so on, each
one preloaded with the typical cost-loaded
resources. We can then do things like track
our design, estimating and project
management resources across schemes,

and track each one against its budget. As


we move through our various predened
gateways (such as design, pricing,
governance and mobilisation) we can see
how things are changing. We can keep track
of an enormous number of tasks overall if
there are 200 jobs underway, each one might
have up to 100 separate tasks.
The division uses Asta Powerproject
Enterprise to enable and empower staff at
different levels and with different specialisms:
Weve got 20 concurrent licenses at present,
but we must have over 100 potential users in
all. The software is mostly used by designers
and project managers, each of whom update
progress on their own programmes. It has
changed the culture and driven greater
engagement and accountability which is
helping us monitor progress and thats why
its been so successful. I will visit one of our
project ofces and often see 5 or 6 project
managers with Asta open on their screens.

u Maintaining a clear view


When describing how the software supports
their ability to communicate and report,
Graham explains: We collect the information
from Asta, and then manage it visually in our
project management and design meetings.
In the project ofce we often map out the
overall programme on the wall, using visual
management techniques. When we hold
weekly meetings to discuss progress, the
attendees know exactly what is going on in
their own programme but only if theyve

The highway to programme management ef ciency at Skanska


curve is quick and people nd it simple to
use. One big advantage with Asta is the
helpdesk. I know that if ever I get stuck I can
just phone them, and theyll help me out.
We put our guys through training with Asta
and the costs are much cheaper than other
routes. Because of its cost effectiveness, I
would be happy to send a keen site manager
on an Asta training course, and know that
they would be able to produce a programme
quickly.

ABOUT ASTA DEVELOPMENT

Asta Development is a leading


international developer of project, and
resource management software which
provides solutions for managing any
size and any type of project.

taken the responsibility on board, and


ensured that they have updated it in the
software.

u Bespoke solutions to specic


challenges

Asta has created bespoke software to


support various street lighting and highways
maintenance contracts. Street lighting
presents different challenges. Before
instigating Asta Powerproject Enterprise we
used many different spreadsheets to juggle
all the information we needed. The numbers
of tasks involved can be huge, for example,
we might have to replace 40,000 street lights
on a single project and each one involves
7 or 8 tasks, so that could be more than
300,000 tasks.

One big advantage


with Asta is the
helpdesk. I know that if
ever I get stuck I can just
phone them, and theyll
help me out.

www.astadev.com

We were really happy with the service


we got from Asta. They took the time to
understand our business and helped us to
develop the macros we needed. I can rely
on Asta to make something bespoke and
know they wont ever leave you in the lurch or
charge through the nose for bug-xing.
Graham explains how Asta Powerproject
is used to better manage resourcing and
reporting: We use the software to manage
our design and project management
resources. Most schemes within a highway
maintenance contract needs design. Asta
Business Intelligence has helped us see the
peaks and troughs of design needs, and
know where we can redeploy resources
across the contracts. Business Intelligence
also generates two other key reports; one, a
trafc-light report so that we can see our key
gateways status; and the other one a report
to track expenditure.
Is Asta Powerproject something that Graham
values? His answer is unequivocal: Asta
is my preference for project and programme
management. I have been using it for over
15 years, and I nd it easier to use than
alternatives. Also, if I want to cascade a bit of
software down to site managers I will always
recommend Asta, because the learning

Since its launch in 1988, the


companys core solution suite, Asta
Powerproject, has evolved and
improved driven by regular feedback
from users and using the latest
technologies available. It has proved
its capabilities over the years on
high prole projects throughout the
world and is now used by thousands
of planners in a wide variety of
industry sectors in the UK, Europe,
Asia Pacic and the USA. Asta
Development supports customers
directly from its ofces in Oxfordshire
and Shropshire. Outside of the UK,
Asta Development has a network
of distributors who supply, train and
support customers, with the software
available in up to seven different
languages. Asta Development is a
part of Eleco plc, a holding company
focused on software development and
services for architectural, engineering
and construction industries. The
company is listed on the London Stock
Exchanges Alternative Investment
Market (AIM).
More information about Asta
Development and its products can
be found at www.astadev.com and
information about Eleco plc can be
found at www.eleco.com.

Case study: Saunders Construction


Saunders Construction professionalizes scheduling company-wide with Asta
Powerproject

Asta Powerproject has helped the rapidly growing construction firm adopt standardized scheduling practices and apply those to
every job, regardless of size. The softwares ease of use, affordability, and robust feature-set designed for construction made it the
logical choice to extend Saunders competitive advantage.

Saunders Construction is ranked by


ENR Magazine as one of the largest
general contractors in Colorado with
440 staffers and annual billings
topping $450 million. The company has
steadily grown and taken on projects of
increasing complexity since its founding
in 1972. Their clients come from a
diverse mix of industries including
healthcare, retail, manufacturing,
religious, governmental, and K-12 and
higher education.
With an increasing number of complex
projects running simultaneously, a
better, more systematic approach
to scheduling was needed. The
professionalizing of project scheduling

With Asta
Powerproject, we now
have a very effective and
efficient tool that
is helping us achieve
ALL of our goals of
improved scheduling
and planning
throughout Saunders.

initial tasks was to find and standardize


on a new scheduling system. Saunders
staffers were so frustrated with the
outdated Suretrak system that many
simply didnt build formal project
schedules. Those that did use it,
needed the companys IT staff to
downgrade their computers operating
system to Windows XP in order to allow
Suretrak to run. A couple of copies of
Primavera P6, purchased for one RFP
requirement, sat unused due to its
excessive complexity.

at Saunders sought to reduce risk while


increasing management visibility. In
2013, the company hired a seasoned
scheduling manager to oversee the
transition.

After a competitive search, the company


chose to adopt Asta Powerproject
enterprise-wide, providing shared
licenses for all its superintendents,
project managers, and project
engineers.

Colorados top commercial


builder makes plans to stay
that way

One of the new scheduling managers

astapowerproject.com

Asta Powerproject: The power behind successful projects

Case study: Saunders Construction

Making the switch to Asta


Powerproject
Saunders recognized that senior
management buy-in and proper training
would be critical if the new system were
to be fully adopted.
Company owners and senior
management were heavily involved
in the ultimate selection process and
in setting up guidelines for its use.
With Asta Powerproject we now have
a very effective and efficient tool that
is helping us achieve all of our goals
of improved scheduling and planning
throughout Saunders, said company
president Greg Schmidt.
Initial training on Asta Powerproject
was conducted by regional Elecosoft
resellers Project Integration. The system
was so intuitive to use, most Saunders
staffers in the training sessions were
making schedules within a couple of
hours. Daniel was also able to then train
future sets of users internally.
The transition from Suretrak (or no
scheduling at all) to Asta Powerproject
on every job was completed in 2013.

The Saunders team finds


plenty to love about Asta
Powerproject
Impacts of the adopting Asta
Powerproject were evident throughout
the organization quickly. Saunders
accounting and financial team
appreciated the cost savings over
other systems. Thanks to concurrent
licensing, the scheduling software runs

I thought this was


going to be hard. Why
does P6 make this so
difficult?

The software is now used for every


job regardless of project size, says
Bill Jack Daniel, scheduling manager
at Saunders. Its a corporate initiative
and it truly helps us better manage and
track all jobs.

on 200 computers with only 30 licenses


a savings of more than $400,000
compared to Oracle Primavera, which
does not offer concurrent licensing.
Additionally, because it is intuitive to
use, less time is spent training staff.
And, theres less IT department time
needed for maintaining the system and
the machines needed to run it.
Project engineers and managers also
reported high satisfaction with Asta
Powerproject for its simplicity but
powerful functionality. As one project
superintendent said, The tool is so
easy, I actually use it!
Custom templates have allowed
Saunders schedulers to reduce the
time spent entering tasks on common
projects. Robust reporting and the
ability to easily share project files have
also led to the softwares successful
adoption.
Finally, Saunders is able to deliver more
accurate and real-time information
to clients because they can build
schedules much further in advance.
Asta Powerprojects robust reporting
tools paint a clear picture of the
progress and remaining steps. Earlier
communication helps avoid costly
surprises late in the construction
process.
Saunders has a goal to go paperless
and will adopt Powerprojects new Site
Progress Mobile app when it launches
this summer. The app will allow for easy
progress reporting from the jobsite.

About Saunders
Construction
Saunders Construction is one of
the largest and most respected
commercial builders in the Rocky
Mountain region. Since 1972, the
company has built some of the
areas most notable landmarks
while establishing a reputation
for quality and on-time delivery.
The companys 440 employees
specialize in construction for
a wide range of industries
including healthcare, industrial,
retail, religious, education and
government.
The University of Colorado
Boulders Center for Community
(seen on pg. 1) and the Adams
County Government Center in
Brighton, Colorado (above) are just
two examples of the companys
vast and lasting legacy.
For more information about
Saunders, please visit
www.saundersci.com.

astapowerproject.com

Asta Powerproject: The power behind successful projects

15 reasons to use Asta Powerproject for managing


construction projects
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.

Easier to use
Superior presentation of project plans and simpler printing
More precise scheduling for greater accuracy
Share plans with anyone with a free Asta Project Viewer
Cost effective licensing
Collect and update progress easily on mobile devices
Plan and manage repeated tasks on one row of the plan
Easy integration with other software
Link projects plans to 3D models within a single application
Filtering for easier managing of sub-contractors
Enterprise version for collaboration across programme plans
Better protection against litigation caused by delay
Construction specic training courses and expert support
Used by leading contractors and many smaller companies
Price

When it comes to managing construction projects you need software you can rely on.
If you use the wrong software in a project where there is a contractual arrangement
and it is necessary to show cause and effect as well as the impact of progress on the
works, you are probably getting the wrong answer - and that could cost you a lot of
money!
Asta Powerproject was designed to support the way construction planners work and
has evolved with their input to meet the requirements of the industry.

Asta Powerproject: The power behind successful projects

Easier to use

Construction-specic project templates are provided with pre-set reporting codes, calendars,
resources, standard reports etc. so you can get up and running quickly
Draw in tasks quickly and easily using the mouse
Perform unlimited undos, even after a save or reschedule
Intuitive drag and drop assignment of resources, codes etc.

I love the way you can move around quickly. Whereas in MS Project you
must create summary bars to group activities, in Asta Powerproject it lifts
them all into a single window so you can see exactly what you need.
Steve Allan, Project Manager for Earthworks, Banora Point Upgrade Alliance

Superior presentation of project plans and simpler printing

Customise the borders around your plan with exible header and footer page surrounds, including
your own logos and references
Show only those parts of the plan that are relevant by turning different aspects of the bar chart on
and off, e.g. oat, critical path, holidays, links, etc.
Highlight important information by adding annotations such as text, pictures, colour shading JPG and
GIF graphics
Gain total control over printouts: you dene where you want the page to break; what you see on
screen is what is printed; and there is no white space on printouts

Asta Powerproject has a drag and drop functionality that makes it much
easier to use than P6.

Bill Jack Daniel, Saunders Construction

More precise scheduling for greater accuracy

Create and edit links both by typing in the spreadsheet and by drawing in the bar chart
Create links by drawing without having to specify the link type (SS, FF, etc.). This makes it much
faster to link tasks
Links are clearly displayed between tasks, allowing you to evaluate the importance of each link by
sight
Create any type and number of links between two tasks. It is often important to set a link not just at
the start of a task, but also at the end. So if a task is extended, or partially progressed, any knock-on
impact is shown. Software that does not have this facility (such as Microsoft Project) does not show
the true knock-on impact of changes and progress edits to the schedule
Produce an accurate Critical Path Analysis every time with just one click
Navigate the logic and edit existing links quickly and easily
Avoid problems from using different calendars. Asta Powerproject always uses the correct calendar
when two activities with different calendars are linked together, giving you accurate results that you
can rely on. It uses the predecessor calendar for Start-Start links and the successor calendar for
Finish-Finish links. Software that does not have this facility will return an inaccurate project end date
The critical path is outlined in red

4
5

Share plans with anyone with a free Asta Project Viewer

You dont have to pay anything to look at Asta Powerproject les. The free Asta Project Viewer
enables anyone to open and print Asta Powerproject plans at no cost
Use Asta Project Viewer to read Microsoft Project les and Oracle Primavera les for free too!

Cost effective licensing

If you have multiple users, you can purchase a concurrent licence. This means that users can
access the same licence across the network at different times. A 10-user concurrent licence could
be used by 30+ people, so you only need to buy 10 licences not 30. This makes Asta Powerproject
very cost effective

We were looking to move away from MS Project as it was proving too


expensive and found the exibility of Astas approach much more suited to
our ways of collaborative working.
Clive Bassett, Beard

Collect and update progress easily on mobile devices

Record project progress quickly and easily via mobile devices


Update progress at any time, from any location. No signal needed to record progress values, only
when submitting updates
Improve accuracy by removing need for re-keying of progress updates from paper notes or emails
Record actual dates for events, not just the percentage complete
Take photographs and record notes which can be associated with particular tasks or build stages

Plan and manage repeated tasks on one row of the plan

Save time and space on the Gantt chart by displaying overlapping repeated tasks on the same bar
line. This avoids the need to laboriously create tasks on dozens of different rows when planning
repeated tasks
Information is presented in a very compact form use a single sheet rather than multiple pages
For house building each row can represent a house (or at) and the tasks represent the stages of
construction. This approach is also highly-effective for the nishing stages of t-out work or multistorey construction
The procurement stages for each work package in a plan can be detailed as events on one row and
linked in to the rst construction event. This technique unies the procurement and construction
phases and provides realistic information about required dates for the design team
The build stages for a house can be shown on one line

With Asta Powerproject having multiple activities on the same line makes it
easy to see what is going on and easy to produce summary print outs. On
large complex projects like I work on to do the same in Primavera without
this would be complex and take lots of pages to print.
Michael Powell-Brett, Powell Brett Associates

Easy integration with other software

Open les from other software systems (Microsoft Project, Oracle Primavera P3 & P6 and SureTrak)
Save Asta Powerproject les into formats that can be opened in such systems
Easily exchange data with people working on different software if you need to
Templates are provided for opening les from other formats, so as to give the user a more familiar
presentation of their project data
Easy integration with estimating, accounting, enterprise resource planning (ERP) systems and BIM
tools
Save Asta Powerproject les in
Microsoft Project format

Link projects plans to 3D models within a single application

Asta Powerproject BIM enables you to create a 4D planning environment by reviewing the 3D model
across time, all within a professional project management system in one application
The combined IFC le and schedule interact smoothly and effectively, removing the risk of human
error and speeding up the linking process
Drag and drop objects between the 3D view and Gantt chart
Compare `planned and `actual schedule plans with full 3D visual impact
View dynamic schedule updates in 3D window

10

Filtering for easier managing of sub-contractors

Highlight the work of different trade contractors with colour codes. The colour codes are shown as a
legend on the output and allow specic task lists for each subcontractor to be created quickly
Trade contractors do not need Asta Powerproject to read their task lists you can email them the
Asta Powerproject le which they can open using the free Asta Project Viewer
Ask trade contractors to update the plan in either Asta Powerproject or Asta Easyplan, the entrylevel sister product. You can then automatically update their changes in your main Asta Powerproject
plan without any data re-entry

Asta Powerproject is also particularly good at modularising projects. The


master programme can be broken down into work packages, and they can
be ltered. This is obviously useful for subcontractors who do not need to
see everyone elses tasks, but can be provided with a succinct programme
of their own works.

Ray Ferguson, GRAHAM Construction

11

Enterprise version for collaboration across programme plans

Centrally manage all your projects for optimum efciency


Empowering collaboration by enabling a number of people to access and work on the same project
plan at the same time
Allocate and track resources across multiple projects for enhanced productivity & utilisation
Control project costs, income and cash ow across your portfolio
Provide clients and senior management with vital management information via automated reports
and dashboard views based on accurate, up-to-date data

Asta Powerproject Enterprise is really powerful in comparison to some


other systems, and it is very scalable so you can grow it as large as
required.

Brandon Taggart, Resource Planner & Programmer, FM Conway

12

Better protection against litigation caused by delay

Progress in each Progress Period is displayed in a separate colour. You decide the lengths of the
Progress Periods: weeks, months etc.
Information on how much progress was recorded in a specic Progress Period is kept, even when
the task is completed
Create an unlimited number of baselines as a snapshot of the project, so you can compare the
evolving plan against any previous version
The baselines are a copy of the whole project and not just key data, so changes to logic or calendar
working time can be demonstrated and not lost

Forecast

Baseline

13

15

Asta Powerproject provides us with a documented story of how the project


is performing and acts as a delay management tool.
Kevin Taylor, Senior Contracts Manager, J Breheny

Construction specic training courses and expert support

14

Actual progress in week 4

Training courses are designed specically for the construction industry, with practical examples
A wide range of courses are available to suit all users, from beginners to advanced users
Helpdesk support is tailored to the needs of construction customers, with a dedicated team providing
Asta Powerproject support by phone, email or on the web
Expert consultants available for specialist support if required

Used by leading contractors and many smaller companies

Over 80,000 construction users worldwide


Used to deliver some of the worlds most complex construction projects such as Europes tallest
building, The London Shard; Jumeirah Park, Dubai; The Reichstag, Berlin; Petronas Towers,
Malaysia; and Durban International Airport and for house building projects of all sizes.

Price

Standalone License: $1495 + Annual Maintenance & Helpdesk: $299


Concurrent Network License: $1995 + Annual Maintenance & Helpdesk: $399

4D BIM Standalone License: $2345 + Annual Maintenance & Helpdesk: $469


4D BIM Concurrent Network License: $3345 + Annual Maintenance & Helpdesk: $669

Asta Powerproject BIM


BRINGING 4D PLANNING WITHIN AFFORDABLE REACH
BY COMBINING 3D PLANNING AND SCHEDULING

ASTA POWERPROJECT BIM IS 4D ENABLED - LINK YOUR PROJECT PLAN AND MODEL TOGETHER
IN ONE APPLICATION
Quickly create your project plan directly from your IFC4*
model file by:
Dragging and dropping objects between the 3D view
and tasks
Using structured templates with predefined searches
to automatically link to the IFC model objects
Compare `planned and `actual schedule plans with full
3D visual impact

Create and play a time-line of your project linked to


milestones and baselines to simulate subsections or
whole projects
A plugin/upgrade to your existing licence of Asta
Powerproject
Full property controls for visual impact and ability to hide
and view objects
Manage your 4D planning at an affordable cost

Manage large projects with the ability to save snapshot


positions to enable quick navigation

Ideal for tendering and progress monitoring in 3D

Save images to standard graphical formats to use for


reporting or site recording of project status

Import costs from estimating applications supporting the


IFC4 file format

*About IFC format


The Industry Foundation Classes (IFC) data model is an open, international and standardized specification for Building Information
Modelling (BIM) data that is exchanged and shared among software applications used by the various participants in a building,
construction or facilities management projects.
IFC can be used to exchange and share BIM data between applications developed by different software vendors without the software
having to support numerous native formats. As an open format, IFC does not belong to a single software vendor; it is neutral and
independent of a particular vendors plans for software development.

www.astadev.com

Asta Powerproject BIM


BRINGING 4D PLANNING WITHIN AFFORDABLE REACH
BY COMBINING 3D PLANNING AND SCHEDULING

View your structure externally and internally with easy


to use navigation controls
Simulate the build process while walking or positioning
yourself within the structure
User definable interface to ease control of model
objects
Perspective mode settings to give realistic views
around and inside the structure
DirectX graphical interface used to increase
performance and enhance model look and feel

EASY NAVIGATION AND FLEXIBLE VIEWS

SAVE TIME AND INCREASE EFFICIENCY BY


USING ONE APPLICATION
Visually review your 4D planning and the 3D impact all
within a professional project management system in one
application, from one company
With the IFC file and schedule all located within the same
software you can interact smoothly and effectively, removing
the risk of human error and speeding up the process
Quick and easy to learn as fully integrated with
Powerproject existing feature sets
As you update the schedule, you can see the impact
transferred across to the other view
Removes problems with failed attempts to email large
BIM models as entire model is stored in the cloud

INTRODUCING THE ELECO BIMCLOUD

Asta Powerproject BIM extends the functionality of Asta


Powerproject, enabling you to create a flexible, 4D planning
platform that uses the ELECO BIMCloud. The ELECO
BIMCloud shares information and supports improved
cross-functional collaboration for all those involved in BIM
as it stores all data in the industry common IFC4 format.
It is this capability which enables you to open a 3D model
which has been created from 3rd party applications
within Asta Powerproject.
From within the application users are not only able to
access the core project management, scheduling and
resource management capabilities but also draw on the
functionality of other products from the ELECO group, of
which Asta is a part, allowing sharing of data from
visualisation, design and cost estimation tools such as
Arcon and Bidcon.

HOW TO ACCESS ASTA POWERPROJECT BIM


AND THE ELECO BIMCLOUD

An Asta Powerproject BIM licence is required. If you are an


Asta Powerproject supported licenced user you just need to
upgrade your existing licence. New users can purchase a
combined Asta Powerproject and Asta Powerproject BIM
licence. For information on licensing terms and a quote to
match your requirements, please contact us on 01844
261700 or via enquiries@astadev.com.

2014 Asta Development plc

www.astadev.com

You will also need a subscription to the ELECO


BIMCloud. This is free for the first 12 months for all Asta
Powerproject BIM licensed users, allowing storage of up
to 5GB. Any additional storage requirements can be
quoted upon request.