Академический Документы
Профессиональный Документы
Культура Документы
This paper givm an overview of the study performed and will present the laboratory test results for 84 030 cases. These tests were
conducted on a modem real time power system simulator. The
study began in April 1989 and finished in December 1990.
: ZH
: PC
: CD
: ZM
: SD
In the results tables and figures, the different relays are referred
to by their protection principle, followed by a serial number if there
were more than one of the same type.
COMMISSIONINGASPECTS EVALUATION
The relays were commissioned according to the manufacturers
recommendations. However, due to various problems experienced
during commissioning, it was decided to include this aspect in the
evaluation. Six different points were covered and each was evaluated on a scale of 1to 5, the perfect score being a 5.The qualitative evaluations associated with the marks assigned are described
below and the results are summarized in Table I.
Settings
5 :Settings are easy to calculate and to apply. No significantchange
was needed for the complete duration of the study.
4 : Settings are more complicated to achieve.
3 : Settings are relatively complicated and not all accessible on the
front panel of the relay. Therefore, for some relays, changes to the
settings anger programmable links have to be done directly on the
printed circuit boards.
2:Changes in the settings, using the power system simulator,were
needed to get a good performance of the relay.
1800
the evaluation was made in terms of marks from 1to 5 and the
qualitative evaluations for the marks assigned are given below.
Characteristic
Signalling
Testing
equipment
67
67 90
77
90
evaluation in % 63
67 68
Logic checking
2:Part of the relay is microprocessor based with continuous supervision, but no other facilities for logic checking are available.
Hardware
5 : New technology using integrated circuits and microprocessors.
Good quality for the printed circuit boards.
4 : Older technology.
-2 :Aging product for which it may be difficult to obtain spare parts.
Defective parts
5 : Relay was received in perfect operating condition.
4 :Relay was not fully operational due to either :problem of overheating components, problem with radio interference tests, wrong
resistors for a polarization circuit, different programming for 2
identical relays.
3 : Relay was not fully operational due to either :module out of
acceptable tolerance, defective component (integrated circuit,
diode, etc.), problem of duty cycle for some auxiliary relays, modules with wrong nominal current or basic frequency, errors in wiring, problems with crimped terminals inside the relay, diode matrix
different from the one given in the documentation.
Troubleshooting
4 :Error codes are given by the manufacturer to rapidly find and
replace a defective card or module. Difficult to replace a component due to a lack of documentation. Troubleshooting is possible
through buttons which allow a check of a part of or the entire logic
of the relay.
3 :No facilitiesavailable to perform troubleshooting. Information
is incomplete and/or contains errors.
2 :No facilitiesavailableto perform troubleshooting.Information
is incomplete, contains errors and is not fully applicable to the relays being tested.
Documentation
-5 :Documentation is clear, complete,and easily availablefrom the
manufacturer.
4 :Software documentation is incomplete, not always up to date,
contains errors, or is not compatible w$h the relay being tested.
3 : Information on wiring between cards and external connectors
is missing, electronicschematicsdo not correspond to the relay being tested.
2 : Major lack of documentation, not easily understandable, and
contains errors.
d a : Documentation was in preparation at the time the relay was
being tested.
Table 11. Manufacturingquality evaluation
1801
SIMULATION ASPECTS
Approach
Using a fully automatic test control procedure, supported by a highly specialized softwarepackage, it was possible to perform an average of 250 tests per hour, including all on-line data processing and
statistical analysis.
The power system simulation could have been done using off-line
digital transient simulation programs such as EMTP [9] or MOR- Network description
GAT [ 101. In such a case, the voltages and currents seen by the relayswould have been recorded and replayed at a speed correspond- The study was carried out using a model of the future series coming to real time. The waveforms would have been applied to the pensated Hydro-QuCbec system. The network included all 735 kV
relays using appropriate WA interfaces and power amplifiers lines and part of the 315 kV system. Equivalents were used for volt[ 10,11,12,13,14,15].The simulation time, however, would have age levels below 315 kV. Electromechanical oscillations were not
been relatively long. For example, a 6 cycle fault on the modeled represented for this study.
Hydro-QuCbec power system (Figure 1)using EMTP on a SPARC
The simulated network included :
station 1took roughly 30 minutes of CPU time.
Furthermore, based on IREQs past experience,performance evaluation of protection systemshas proved to be best achieved using
a statistical approach. The choice of lines studied, fault inception
angles, fault positions, types of switching operations, network parameters and configurations are all parameters that can influence
significantly the performance of some relays. The need to perform
a great number of network disturbances in order to obtain the best
possible sampling virtually imposes the need for the use of a fully
automated modem real time power system simulator. Of course,
the statistical approach does not eliminate the need for engineering judgement in choosing the tests to be performed.
The use of real time power system simulation for protective relay
testing has been discussed in [16,17,18,19,20],among others. The
IREQ digitally controlled real time power system simulator was
used to perform the present study. The hardware has been extensively described in [21]. System voltage levels are scaled down to
a nominal 100 V phase-to-phase on the simulator and an impedance scaling factor is selected to keep the fault current below 5 A.
*
*
*
&
. . .7
~~~
LEGEND
CHU7
~~
MTG7
ARN7
1802
The recorded lines (total of 7) are those for which tests were performed, but without the relays being evaluated. This was done to
record voltage and current waveforms which could be replayed for
additional testing in the future.
The network simulation included transformer saturation, mutual
coupling between lines, varistor models, spark gap and bypass
breaker models, line breakers, and other system components. Lines
were represented by IT sections,approximatelyone for every 50 km.
The voltage signals were measured on the bus side of the series capacitor banks, as will be the case in the real network.
Extemal faults had a duration of 20 cycles and the fault was eliminated by the fault breaker, without line opening. These tests also
comprised 50 switching operations and the same 4 types of fault.
The simulated network was validated using EMTP for the frequen- The fault impedance was again close to 0 ohms. Typically, 10 to 20
cy responses and fault currents. All networkequivalents,forvoltage different fault positionswereused for every line studied. Gap flashlevels below 315 kV, were validated up to 450 Hz. Load flows ob- ing for extemal faults was addressed in the same manner as for intained on the simulator were regularlyvalidated against numerical temal faults.
load flows to ensure a precision greater than 1% for the voltage
amplitudesand 1degree for the voltage angles. More than 70 mea- Specific and pammetric tests
surement points were monitored daily to validate the network.
These tests were performed mainly on one line which proved to
Relay testing procedure
be particularlyproblematical for the studied relays during the basic
tests. This line was the Abitibi - La Vkrendiye series compensated
Since 8 different line protection systems were tested simultaneous- line (see ABI7-LvD7 in Figure 1).The following tests were perly, open-loop testing was performed. The relays were connected to formed using the latter as the protected line :
the simulator, one at each end of the protected line, using high fidelity current and voltage power amplifiers.For every switching op- SDecific tests :
eration, an automaticprocedure compared the waveforms seen by
the relays with those measured on the simulator to detect any malLine switching without faults
function or unacceptableperformance of the amplifiers.No signifiLine switching onto load
cant problem was encountered regarding this aspect.
Series capacitor bank switching
To test the relays, a variable parameter line model (VPLM) was
Line switching onto faults
used. Thisline was composed of an increased number of IT sections,
one for every 12.5km, thus giving a frequency response valid up to
Shunt inductance switching
2OOO Hz in positive sequence for lines averaging 250 km. The
Power transformer energization
VPLM was composed of a double circuit mutually coupled line,
Gap firing for extemal faults
with variable series compensation. Gap models were triggered on
apre-defined time basis and not from an on-line measurement sysFaults on parallel line with delayed breaker opening,
tem; the reason being that the varistor energy levels for gap triggerincluding current reversals
ing were not known at that time. Telecommunication between the
Evolving faults
relays was simulated through a direct link with a rise time delay of
25 ms and a drop-out time delay of 100 ms.
Fault clearing
Faults with system frequency at 58.5 and 61.5 Hz
A fully automatictesting procedure allowed the execution of a wide
range of tests and statistical analysis. The test control program
Effect of a sudden increase in the load current
made it possible to automatically vary the fault position, the network configuration, inception angle, fault type, gap triggering time, Parametric tests :
fault duration, and other sequenceparameters. It automaticallyrecorded and stored in the result data base (see RDB in the DataproI) Intemal and extemal faults at every 25 km with gap flashing
cessing section) all waveforms and relay signals corresponding to
at 10 and 25 ms
worst case operations. Afterwards, it was always possible to repeat
I)
Increase
of series compensation from 30 % to 70 %
the problematic tests with exactly the same conditions for fine tun# Reductionof the short-circuit level using different network
ing of the settings and in depth study of the relay behavior.
configurations and resistive faults of 10 SZ
Tests description
This protection study was divided into 2 parts. First, basic tests were The last 2parametric tests (increase of series compensation and reperformed on 13 carefully selected lines of the 735 kV Hydro- duction of the short-circuit level) were also conducted on the MonQukbec 1993network, winter configuration (Figure 1).The second tagnuis - Amaud 735 kV line (see MTG7-ARN7 in Figure 1). In
part comprised specific andparametric tests [22] on the same net- addition, tests were conducted with resistivefaults of 75 SZ in order
to evaluate the sensitivity limit of each protection scheme. These
work with some variation in configuration.
results are not included in the paper.
Basic tests
Using the digital playback system and the waveform data base
Intemal faults had a duration of 20 cycles, with the opening of the created during this study (see WDB in the following section), the
line between the 18th and 19th cycles. Since 8 line protection sys- impact of measuring elements such as capacitive voltage transtems were tested simultaneously, the trip commands from the re- formers was also evaluated for the selected relays [23,24,25]. This
lays were not used to open the line breakers, but were all recorded. is part of the second phase of the study, which ended in 1992.The
For every fault position, 50 tests were repeated for different values corresponding test descriptions and results are not presented in
of the initial point-on-wave from Oo to 360' in steps of 7.2' for this paper.
1803
Data processing
A total of 128 recording channels were used during the full duration of this study. The sampling rate was 5000 samples per second
per channel and the acquisition period was 500 ms. On-line data
processing and statistical analysis software performed the following calculations :
Protection system results
AI (kA)
change
vaGstors
tots;
Montagnais
' I U
-400
-200
250
AV (kv)
Figure 3. Fault trajectory in the (AI) YS (AV) plane
for superimposed directional relay
Immediately following each test, the acquired data was processed
to decide if any of the chosen criteria were met. If so, the voltage
and current waveforms, the relay signals along with the calculated
results were stored. This selectivityensured that only critical cases
were kept for further analysis.These selected cases were automatically documented and stored in a result data base (RDB), which
allowed for easy access and display.
During this study, another goal was to create a waveform data base
(WDB) for series compensated networks. Consequently, all voltage and current waveforms were recorded on optical disks for all
network disturbances performed. For every test, 15 signals were
stored in the WDB :the fault application time signal, and the current and voltage waveforms at both ends of the line, including the
neutral currents. A total of 115 000 network disturbances were recorded on 20 different 735 kV lines of the simulated HydroQuCbec network.
The RDB and WDB represent a total of 40 Gbytes of valuable information stored on optical disks. Of this 40 Gbytes, 17 Gbytes are
used for the voltage and current waveforms of the WDB and the
remaining 23 Gbytes contain the processed data, selected waveforms, and relay signals of the RDB.
$ . I
The functional tests results presented in this paper cover the 8 preselected high performance line protection systems analyzed during
the study. The tabulated cases do not take into account the tests
performed in order to fine-tune the relay settings and study in
depth specific cases of relay malfunctions or particular behavior.
Evaluation of the 735 kV line protection systemswas based on Hydro-QuCbec's new design criteria which can be summarized as follows :
50
R (ohms)--,
100
I) The two main criteria for protection systems are always&pendability and security. For Hydro-QuCbec,due to its network topology, securitv is the most critical design factor.
1804
I) Maximum fault clearance time is typically 5 cycles for the
line end near the fault and 6 cycles for the far end. For lines
near the generating stations, a maximum of 4 cycles is allowed to clear the end near the station if a heavy close-in
fault should occur during periods of peak load.
r) Phase selectivityis needed for reclosingpurposes only. All
tripping initiated by the line protection relays will be threephase, and a reclosing order will be transmitted to the line
breakers only when a single-phase fault is detected.
With respect to the analysis regarding the dependability of relay
performance, it is important to note that phase selectivitywas not
considered, and that only relav omrati~lgtimes under 4 cvcles
were tabulated as correct operation.
CONCLUSIONS
Relay performance
In order to draw conclusions regarding the test results, the focus
is placed on the relay protection principles and not on the discrepancies between the manufacturers. By combining Table III and
N,the final evaluation for the tested relay is obtained. These results, summarizedin Figures 8 and 9, give the global relay performance for the 84 030 cases performed. Refemng to these figures, the
following conclusion can be made:
Without taking into account telecommunication requirements or
other external constraints, the laboratorytest results show that the
two best protection principles to be applied on the Hydro-Qukbec
series eompensated network are :
Current differential
Based on CD2 results :
Dependability on 24 200 cases : 100.0 %
Security on 59 830 cases
: 100.0 %
r) Segregated phase comparison
Based on PC results :
Dependability on 24 200 cases
Security on 59 830 cases
: 99.30 %
: 99.96 %
Commissioning
With regard to the relay commissioningaspects,the main concem
is the qGality and availability of the documentation.Complete documentation is essential in order to successfullyperform calculation
and implementationof relay settings, logic checking, characteristic
validation, and relay troubleshooting.
Another important area of concern is the correction of problems
and implementationof new developments for microprocessorbased
d a y s through new softwm versions. This gives rise to new concerns
regarding relay validation before field operation. It is the authors'
opinion that comprehensive testing will be needed before a relay software venion is changed in the field.
Manufacturing quality
Regarding the relay manufacturing quality, four major observations are made. First, the hardware ranges from good to excellent.
Second, troubleshooting facilities are not always available for the
user. Third, it is still possible to have defective components even
if the relay has been through the manufacturer's quality control.
Finally,the documentation is not always complete or easy to obtain
from the manufacturers.
General conclusion
Real time power system simulation proved to be an efficient technique to evaluate protection relay performance. The importance
of performing a great number of tests is demonstrated by the test
results presented in Tables I11 and IV. In many instances, problems
with dependability and security of the relays occurred in only a
small percentage of cases for each type of test performed. As aconsequence, if the scope of the study and the number of tests performed had been reduced, many or even most of the problems encountered might well have been missed. It should be pointed out
that the relays being tested in this study were all recommended by
the manufacturers as their best protection systems for the HydroQuCbec series compensated network.
Finally, a waveform data base (WDB) containing 115 000 network
disturbanceswas created.'This WDB, in conjunction with a digital
playback system, has already proved to be very useful in evaluating
the impact of instrument transformers, relay modifications, software upgrades, and new relays on the market.
1805
BIOGRAPHIES
Charles Gapnon was born in Montreal, Canada and graduated in
electrical engineering (B.Sc.) from Sherbrooke University. In 1985,
he joined the Research Institute of Hydro-Qutbec (IREQ) as a research engineer in the Network Analysis Software Department
where he performed software development mainly for short-circuit calculation,power line fault probability, and harmonic analysis
programs. In 1987,he worked for BBC in the Power System Protection Department. In 1988, he returned to IREQ in the Network
Simulation Department to perform network and protection studies. From 1989to 1990,he was responsible for network simulation
and relay performance tests for the evaluation of protection systems for the Hydro-Qutbec series compensated network. Since
1990, he has been responsible for the AC & DC Network Study
Group in the Network Simulation Department.
Pierre Gravel was born in Thetford Mines, Canada in 1948.He received his technician degree from Institut de Technologiede TroisRivikres in 1968. From 1968 to 1971, he worked with Northern
Electric on communication hardware. Since then, he has worked
with Hydro-Qutbec on validation and approval of protection systems. From 1989 to 1992, he was responsible for the technical aspects of the protection systems under test for the Hydro-Qutbec
series compensated network.
ACKNOWLEDGMENT
This study was made possible through a strong team effort. The
authors gratefully acknowledge the contributions of Gilbert Sybille, Jean Lemay, and Jean-Claude Soumagne from the Network
Simulation Department (IREQ) and Clermont Gagnon, JeanPierre Benoit, Jean-Louis Rousseau, Rent Lord, and the late Raymond Reed from the Protection Department (Hydro-Qutbec).
REFERENCES
[ 11 L. Champagne, J.-P Benoit, Protection of Hydro-Qutbecs
Series Compensated Lines, CEA Conference, May 1991.
[19]G. Nimmersjo,B. Hillstrom, 0.Werner-Ericlisen, G.D. Rockefeller, A Digitally-Controlled, Real Time Analog Power System
Simulator for Closed Loop Protective Relaying Testing, ZEEE
Emis. Power Delivery, Vol. 3, No. 1, January 1988, pp. 138-152.
[3] A. Newbould, I.A. Taylor, Series Compensated Line Protection :System Modelling &Relay Testing,IEE Conference Publication on Developments in Power System Protection, No. 302, Edinburgh, 11-13 April 1989, pp. 182-186.
1806
Lines Studied
Criteria
L44MAN7-LEv7
Dependability
security
LA2MAN7-MIc7
Dependability
SecUrity
L39 CHU7-MTG7
Dependability
security
MTG7--7
Dependability
Security
LA1 MIC7-ARN7
Dependability
Security
L3 NEM7-ABI7
Dependability
L14ABI7-cHI7
Dependability
Security
L27 JAC7-CH07
Dependability
Security
(","','
1 I
I 1
1 93x3;: I
CD1
%
CD2
%
ZM1
%
ZM2
Dependability
Security
SD1
%
SD2
%
Number
ofcases
91.50
100.0
100.0
100.0
100.0
100.0
100.0
100.0
100.0
100.0
98.50
100.0
97.50
100.0
99.00
88.00
800
800
91.00
100.0
100.0
100.0
100.0
100.0
100.0
100.0
100.0
97.95
100.0
100.0
100.0
100.0
100.0
100.0
800
4200
100.0
100.0
85.00
100.0
100.0
100.0
96.00
98.73
94.00
96.00
95.88
99.86
100.0
100.0
1600
2200
I I
100.0
100.0
90.00
100.0
93.50
82.50
99.81
100.0
1 I
99.75
100.0
1600
2600
99.94
100.0
100.0
100.0
100.0
100.0
99.88
99.50
99.94
100.0
I I
99.69
100.0
1600
2400
99.94
100.0
100.0
100.0
83 19
100.0
88.44
99.70
100.0
100.0
I I
99.94
99.83
1600
3000
100.0
99.75
100.0
100.0
100.0
100.0
99.83
99.57
99.17
99.75
99.50
99.84
400
4600
I I
100.0
100.0
100.0
100.0
99.81
97.37
100.0
100.0
95.50
92.84
95.21
98.20
99.75
99.95
96.38
100.0
99.94
100.0
99.75
100.0
98.50
100.0
I 1
1 I
I I
98.94
100.0
80 46
.lOb.O
LMo7-ALB7
~~
I I
100.0
100.0
100.0
100.0
1 1 1
99.38
91.04
100.0
100.0
I I I
100.0
100.0
100.0
100.0
I ii::1 I
92.69
98.80
I I 1
100.0
100.0
100.0
100.0
I I I
100.0
100.0
99.94
100.0
1::!i I 1
I I
I I
I I
99.88
99.95
1600
3 800
I I
99.92
99.93
2400
4400
I 1
99.00
100.0
1600
2 200
600
4 600
L13 NEM7-ALB7
Dependability
Security
GLOBAL
Dependability
EVALUATION
I ;I; I
1600
3000
600
100.0
100.0
100.0
5 200
90.24
100.0
100.0
100.0
97.72
98.11
96.95
97.82
99.35
99.96
99.76
17000
99.73
42 800
1807
Test description
Criteria
%
-
Security
55.00
100.0
100.0
100.0
100.0
100.0
100.0
100.0
80
Security
100.0
100.0
100.0
100.0
100.0
100.0
96.25
52.50
80
Security
100.0
100.0
100.0
100.0
100.0
100.0
100.0
100.0
800
Line switching
onto faults
Dependability
Security
88.06
100.0
98.89
100.0
360
480
100.0
100.0
180
100.0
100.0
150
96.52
100.0
100.0
100.0
94.13
88.91
99.57
95.22
460
99.38
100.0
100.0
100.0
99.90
97.50
100.0
99.38
960
78.60
98.40
99.20
100.0
67.20
99.10
100.0
100.0
90.50
89.40
77.10
93.00
76.00
96.00
93.60
95.20
1000
1000
98.82
170
99.69
99.48
640
960
99.53
98.44
640
960
99.41
510
PC
CD1
CD2
ZM2
%
SDI
Number
of cases
ZM1
%
Line switching
without faults
Line switching
onto load
ZH
SD2
%
%
I
Shunt inductance
switchine
Power transformer
energization
Security
Security
Security
Evolving faults
Dependability
Security
Fault clearing
Security
83.53
100.0
100.0
Dependability
Security
100.0
97.81
100.0
100.0
81.88
99.27
Dependability
Security
85.62
97.81
100.0
99.90
82.50
99.06
Sudden increase
in the load current
Security
100.0
100.0
100.0
Dependability
Security
100.0
99.11
100.0
100.0
1920
3 040
Increase of series
compensation
from 30 % to 70 %
Dependability
Security
83.75
97.65
93.12
99.56
960
2 720
Dependability
Security
Security
100.0
100.0
100.0
GLOBAL
EVALUATION
Dependability
Security
I
85.40
99.16
t
89.38
96.81
98.60
99.92
81.02
99.46
100.0
98.82
93.12
96.25
90.94
87.71
99.53
99.06
1 1 I I :1 I
100.0
100.0
83.59
80.00
100.0
99.81
99.98
91.18
I I I I 1
I
90.59
99.36
92.97
94.58
100.0
I
I
100.0
I
I
100.0
I I I 1 I
I I I I 1
100.0
100.0
83.59
96.47
78.07
98.42
97.03
99.64
97.32
97.97
1680
4 480
100.0
88.70
95.51
85.71
97.46
95.84
99.40
97.58
96.77
7 200
17 030
100.0
1808
I
S D2
I
99.73 %
SD2
SD1
ZM2
ZM1
CD2
CD1
PC
ZH
90
92
94
96
98
lO%
100%
SD2
97.58 %
SD2
66.77%
ZM2
ZM1
CD2
CD1
PC
ZH
94
I
98 67 %
S D2
I
7
Z M2 h
91.33%
95
96
97
98
0%
99
SD1
ZM2
ZM3
CD2
CD1
ZH
80
85
90
95
100%
99.96%
IJ
98.22 %
95
96
97
98
99
100%
1809
DISCUSSION
WALTER L. HINMAN, RFL Electronics Inc., Boonton Twp, NJ:
The authors, and all those involved in this extensive study and report, are to be commended. This report serves a very useful purpose to the electric power industry. Several questions arise :
1. The relay systems with the best performance are PC (segregated phase comparison) and CD2 (one of the two currentdifferential schemes). CD2 out-performs the other current differential
scheme (CD1) by a wide margin with regard to dependability. Was
CD2 a segregated phase system and CD1 a composite quantity system?
2. If the answer to the previous question is yes, do the authors
believe that the main reason for the superiority of CD2 over CD1
is the possibilityof severe seriesphase impedanceunbalance on series compensated lines? (An example would be an internal
3-phase fault with unequal gap flashing causing significant circulating zero-sequence and negative-sequence currents creating restraint on composite quantity schemes).
3. If the answer to question 1is yes, was the ability of the CD2
scheme to correctly target all fault types considered significant?
If the CD2 schemedid not include a G (i.e., 3 IO) target, was this
considered a disadvantage?
4. The two highest rated systemsare current-only schemes, and are
1810
0
Figure 1. Differentially protected line
CHARLES GAGNON, IREQ, Institut de recherche dHydroQukbec, Varennes, Canada, and PIERRE GRAVEL, HydroQukbec, Montrkal, Canada :
The authors would like to thank Messrs.Hinman, Adamiak and
Alexander for the interest they have shown in the paper and for
their insightful comments and questions which have surely contributed to the enhancement of the paper.
2. Within the test program performed, it was observed that asymmetrical faults near the series capacitorline side,without gap flashing, caused serious lackof dependability for the compositequantity
system CD1. Cases of severe series phase impedance unbalance,
for security performance evaluation, such as gap misfiring on one
phase of the protected line during external faults, were also performed. Table IV presents the corresponding results under Gap
firingfor extemal faults. Neither the CD 1nor the CD2system had
problems for the simulated cases.To sum up, the superiority of the
CD2 system over the composite quantity system CD1 is due to a
number of reasons, which are not related to cases of severe series
phase impedance unbalance. For example, casesof evolving faults
and asymmetricalfaults near the series capacitor line side, without
gap flashing, proved to be most problematical to the CD1 system
(seeTable III and IV for more details).
3. On its 735 kV system, Hydro-Qu6bec allows only three-pole
tripping and reclosing. However, reclosing is permitted only for
single-phm faults. Consequently, relay phase selectivityis a very
important aspect for Hydro-Qu6bec Regarding phase selectivity,
the CD2system exhibitedexcellentbehavior. The fact that forphase-to-ground and phase-phase-to-ground faults, the CD2 system
did not include a ground target, was not considered a disadvantage
for Hydro-Qu6bec
4. It was indeed observed that the two highest rated systems,based
on the laboratory test results presented in this paper, are current
only schemes.It is a fact that these systems are not affected byvoltage reversals, subsynchronous resonances appearing on the voltage waveforms and also capacitive voltage transformer response.
These are certainly significant factors which contribute to their favorable rating. However, it shouldbe noted that the superimposed
directional schemes (SO),which use voltages and currents, also
performed quite effectively as shown in figures 4 to 9.
1811
an important point, but for Hydro-Qukbecs needs, Security is the
key factor. For equal security performance, the fastest relays have
indeed received some rating credit in the final analysis.
REFERENCES
[XI A. Sauve, M. Le-Quang, A. Lavallte, Testingof Series-Compensated Line Protection System with Telecommunications,CEA
Conference, April 1992.
Manuscript received May 2, 1994.