Вы находитесь на странице: 1из 21

Ref.

: SRTS-1:KNL:SS-XIX:KNL-TVM-1:2014:

Date: 09.05.14

To
The Superintending Engineer
TL & SS Circle, APTRANSCO
Kurnool
Dear sir,
Sub: Construction of 765 KV D/C Kurnool-Tiruvelam Transmission line
EHV Power Line crossings Request for shut down - Reg.
Your kind self is well aware that stringing work of 765 KV D/C Kurnool-Tiruvelam
Transmission line is under progress. The subject line is crossing 132 KV S/C NandyalaBanaganapalle near Banaganapalle. Shut down (LC) is needed on above line for stringing
works of 765 KV line. The details of crossing & requirement of LC are furnished below.
Sl.
No.
1

Name of HV Line of
APTRANSCO
132 KV S/C NandyalBanaganapalle near
Muthapalle vill

APTRANSCO
Tower Nos./
crossing span
6A 6B

POWERGRID
Tower Nos./
crossing span
Tower no. 27/0
(DD+9) &
28/0 (DD+6)

Proposed dates & time


for LC (shutdown)
09.05.2014 (08.00 Hrs)
To
10.05.2014(18.00 Hrs)

Because of Double circuit & Hexa conductor configuration shut down is needed for
two consecutive days to complete the entire stringing work in the crossing span.
In view of the above it is requested to kindly approve the revised shutdown proposal
as per the dates proposed. An early communication is requested in this regard for necessary
mobilization of men, material and T&P for smooth completion of work.
Your kind consideration in this regard is highly solicited.
Thanking you,
Yours faithfully,
(N. Harshavarthan)
Engineer
Copy to:
1. Divisional Engineer, TL & SS Division, APTRANSCO/Kurnool for kind information please.
2. Divisional Engineer, TL & SS Division, APTRANSCO/Nandyal for kind information please

Ref.: SRTS-1:KNL:SS-XIX:KNL-TVM-1:2014:

Date: 15.04.14

To
The Superintending Engineer
TL & SS Circle, APTRANSCO
Kurnool
Dear sir,
Sub: Construction of 765 KV D/C Kurnool-Tiruvelam Transmission line
EHV Power Line crossings Request for shut down - Reg.
Kindly refer our earlier letter dtd 24.01.2014 & 06.02.14 vide which, it was requested
for LC on following lines. Considering the readiness of towers & crossing condition, the
following revised schedule is being submitted here with for your kind consideration and
consent please.
Sl.
No.
1

Name of HV Line of
APTRANSCO
220 KV (D/C tower)
SomayajulapalliNannur(Kurnool) near
Chinnamsettipalle vill.

APTRANSCO
Tower Nos./
crossing span
61-A &
60-B

POWERGRID
Tower Nos./
crossing span
Tower no.
5/3 (DD+9) &
6/0 (DD+25)

Proposed dates & time


for LC (shutdown)
22.04.2014 (08.00 Hrs)
To
23.02.2014(18.00 Hrs)

Because of Double circuit & Hexa conductor configuration we need shut down for
two consecutive days to complete the entire stringing work in the crossing span.
In view of the above it is requested to kindly approve the revised shutdown proposal
as per the dates proposed. An early communication is requested in this regard for necessary
mobilization of men, material and T&P for smooth completion of work.
Your kind consideration in this regard is highly solicited.
Thanking you,
Yours faithfully,
(TRC Murty)
Chief Manager
Copy to:
1. Divisional Engineer, TL & SS Division, APTRANSCO/Kurnool for kind information please.
2. Divisional Engineer, TL & SS Division, APTRANSCO/Nannur for kind information please.

Ref.: SRTS-1:KNL:LILO:2014:

Date: 19.03.14

To
The Superintending Engineer
TL & SS Circle, APTRANSCO
Kurnool
Dear sir,
Sub: Construction of LILO of Nagarjunasagar-Gooty line at Kurnool Transmission
line EHV Power Line crossings Request for shut down - Reg.
Kindly refer our earlier letter dtd 14.02.2014 vide which, it was requested for LC on
following lines. Considering the readiness of towers & crossing condition, the following
revised schedule is being submitted here with for your kind consideration and consent please.
Sl.
No.
1

Name of HV Line of
APTRANSCO
220 KV D/C Somayajulapalle
-Nannur near Nannur village

APTRANSCO
Tower Nos./
crossing span

POWERGRID
Tower Nos./
crossing span

Proposed dates & time


for LC (shutdown)

9 & 10

Tower no. 19/0


(DD+6)
& 20/0 (DD+25)

21.03.2014
(07.00 Hrs to 18.00 Hrs)

In view of the above, it is requested to kindly approve the shutdown(LC) on above


line as per the dates proposed. An early communication is requested in this regard for
necessary mobilization of men, material and T&P for smooth completion of work.
Your kind consideration in this regard is highly solicited.
Thanking you,
Yours faithfully,
(TRC
Murty)
Manager
CC: 1. Divisional Engineer, TL & SS Division, APTRANSCO/Kurnool
- for kind information & needful please.
2. Divisional Engineer, TL & SS Division, APTRANSCO/Nannur
- for kind information & needful please.

Ref.: SRTS-1:KNL:KNL-KNL:2014:

Date: 18.02.14

To
The Divisional Engineer
TL & SS Division, APTRANSCO
400 KV Substation, Nannur
Dear sir,
Sub: Construction of 400 KV D/C Kurnool(APTRANSCO)-Kurnool(POWERGRID)
Transmission line EHV Power Line crossings Request for shut down - Reg.

Kindly refer our earlier letter dtd 31.01.2014 & 17.02.14 vide which, it was requested
for LC on following line. In view of the Bandh call given by Samykhya Andhra agitating
people the it is requested consider our revised LC schedule on 20.02.2014 on the following
line.
Sl.
No.
1

Name of HV Line of
APTRANSCO

APTRANSCO
Tower Nos./
crossing span

220 KV (D/C tower)


Kurnool(Nannur)
Brahmanakotkuru near
Nannur village

Tower no.
9 & 10

POWERGRID
Tower Nos./
crossing span
Tower no. 4/0
(DD+25)
& 5/0 (DD+6)

Proposed dates & time


for LC (shutdown)
20.02.2014
From 07.00 Hrs
To 18.00 Hrs

It is requested to kindly permit LC on above line on 20.02.14 from 07.00 hrs to 18.00 hrs.
Your kind consideration in this regard is highly solicited.
Thanking you,
Yours faithfully,

(TRC
Murty)
Manager
CC: The A.D.E., TL, APTRANSCO, Nannur : for kind information & needful please.

Ref.: SRTS-1:KNL:KNL-KNL:2014:

Date: 17.02.14

To
The Divisional Engineer
TL & SS Division, APTRANSCO
400 KV Substation, Nannur
Dear sir,
Sub: Construction of 400 KV D/C Kurnool(APTRANSCO)-Kurnool(POWERGRID)
Transmission line EHV Power Line crossings Request for shut down - Reg.

Kindly refer our earlier letter dtd 31.01.2014 vide which, it was requested for LC on
following line. Considering the readiness of towers & crossing condition, the following
revised schedule is being submitted here with for your kind consideration and consent please.
Sl.
No.
1

Name of HV Line of
APTRANSCO

APTRANSCO
Tower Nos./
crossing span

220 KV (D/C tower)


Kurnool(Nannur)
Brahmanakotkuru near
Nannur village

Tower no.
9 & 10

POWERGRID
Tower Nos./
crossing span
Tower no. 4/0
(DD+25)
& 5/0 (DD+6)

Proposed dates & time


for LC (shutdown)
19.02.2014
From 07.00 Hrs
To 18.00 Hrs

It is requested to kindly permit LC on above line on 19.02.14 from 07.00 hrs to 18.00 hrs.
Your kind consideration in this regard is highly solicited.
Thanking you,
Yours faithfully,

(TRC
Murty)
Manager
CC: The Superintending Engineer, TL & SS Circle, APTRANSCO, Kurnool :-

for kind information please.

Ref.: SRTS-1:KNL:SS-XIX:KNL-TVM-1:2014:

Date: 06.02.14

To
The Superintending Engineer
TL & SS Circle, APTRANSCO
Kurnool
Dear sir,
Sub: Construction of 765 KV D/C Kurnool-Tiruvelam Transmission line
EHV Power Line crossings Request for shut down - Reg.
Kindly refer our earlier letter dtd 24.01.2014 vide which, it was requested for LC on
following lines. Considering the readiness of towers & crossing condition, the following
revised schedule is being submitted here with for your kind consideration and consent please.
Sl.
No.
1

Name of HV Line of
APTRANSCO
220 KV (D/C tower)
SomayajulapalliDhone(Gooty) near
Chinnamshettipalli village
220 KV (D/C tower)
SomayajulapalliNannur(Kurnool) near
Chinnamshettipalli vill.

APTRANSCO
Tower Nos./
crossing span
226-A &
225-A

POWERGRID
Tower Nos./
crossing span
Tower no.
7/0 (DD+6) &
8/0 (DD+18)

Proposed dates & time


for LC (shutdown)
12.02.2014 (08.00 Hrs)
To
13.02.2014(18.00 Hrs)

61-A &
60-B

Tower no.
5/3 (DD+9) &
6/0 (DD+25)

19.02.2014 (08.00 Hrs)


To
20.02.2014(18.00 Hrs)

Because of Double circuit & Hexa conductor configuration we need shut down for
two consecutive days to complete the entire stringing work in the crossing span.
In view of the above it is requested to kindly approve the revised shutdown proposal
as per the dates proposed or dates suitable within 1 or 2 days closer to proposed dates as per
your convenience. An early communication is requested in this regard for necessary
mobilization of men, material and T&P for smooth completion of work.
Your kind consideration in this regard is highly solicited.
Thanking you,
Yours faithfully,
(TRC
Murty)
Manager

CC: Divisional Engineer, TL & SS Division, APTRANSCO/Kurnool for kind information


please.

Ref.: SRTS-1:KNL:KNL-KNL:2014:

Date: 31.01.14

To
The Superintending Engineer
TL & SS Circle, APTRANSCO
Kurnool
Dear sir,
Sub: Construction of 400 KV D/C Kurnool(APTRANSCO)-Kurnool(POWERGRID)
Transmission line EHV Power Line crossings Request for shut down - Reg.

In continuation our earlier letter ref. no. SRTS-1: KNL: 400KV (QUAD): 2013
dtd.14.12.13 vide which the crossing details of EHV lines come across the 400 KV D/C
(QUAD) Kurnool(APTRANSCO)-Kurnool(POWERGRID) line under construction are
furnished.
We are pleased to inform that tower erection has been completed at the following
crossing towers and we are planning for stringing work at theses crossings for which
shutdown schedule is being proposed as under:
Sl.
No.
1

Name of HV Line of
APTRANSCO
220 KV (D/C tower)
Kurnool(Nannur)
Brahmanakotkuru near
Nannur village

APTRANSCO
Tower Nos./
crossing span
Tower no.
9 & 10

POWERGRID
Tower Nos./
crossing span
Tower no. 4/0
(DD+25)
& 5/0 (DD+6)

Proposed dates & time


for LC (shutdown)
15.02.2014
From 07.00 Hrs
To
18.00 Hrs

In view of the above, it is requested to kindly approve the shutdown proposal as per
the date proposed or dates suitable within 1 or 2 days closer to proposed dates as per your
convenience. An early communication is requested in this regard for necessary mobilization
of men, material and T&P for smooth completion of work.
Your kind consideration in this regard is highly solicited.
Thanking you,
Yours faithfully,
(TRC
Murty)
Manager
CC: Divisional Engineer, 400KV SS, APTRANSCO/Nannur for kind information please.

Ref.: SRTS-1:KNL:SS-XIX:KNL-TVM-1:2014:

Date: 24.01.14

To
The Superintending Engineer
TL & SS Circle, APTRANSCO
Kurnool
Dear sir,
Sub: Construction of 765 KV D/C Kurnool-Tiruvelam Transmission line
EHV Power Line crossings Request for shut down - Reg.
In continuation our earlier letter ref. no. SRTS-1:KNL:SS-XIX:KNL-TVM1:2013:3367 dtd. 23.04.13 vide which the crossing details of EHV lines come across the 765
KV D/C (Hexa) Kurnool-Tiruvelam line under construction.
We are pleased to inform that tower erection has been completed at the following
crossing towers and we are planning for stringing work at theses crossings for which
shutdown schedule is being proposed as under:
Sl.
No.
1
2

Name of HV Line of
APTRANSCO
220 KV (D/C tower)
Somayajulapalli-Kurnool
near Chinnamshettipalli vill.
220 KV (D/C tower)
Somayajulapalli-Gooty near
Chinnamshettipalli village

APTRANSCO
Tower Nos./
crossing span
61-A &
60-B
226-A &
225-A

POWERGRID
Tower Nos./
crossing span
Tower no.
5/3 (DD+9) &
6/0 (DD+25)
Tower no.
7/0 (DD+6) &
8/0 (DD+18)

Proposed dates & time


for LC (shutdown)
12.02.2014 (08.00 Hrs)
To
13.02.2014(18.00 Hrs)
19.02.2014 (08.00 Hrs)
To
20.02.2014(18.00 Hrs)

Because of Double circuit & Hexa conductor configuration we need shut down for
two consecutive days to complete the entire stringing work in the crossing span.
In view of the above it is requested to kindly approve the shutdown proposal as per
the dates proposed or dates suitable within 1 or 2 days closer to proposed dates as per your
convenience. An early communication is requested in this regard for necessary mobilization
of men, material and T&P for smooth completion of work.
Your kind consideration in this regard is highly solicited.
Thanking you,
Yours faithfully,
(TRC
Murty)

Manager
CC: Divisional Engineer, TL & SS Division, APTRANSCO/Kurnool for kind information
please.

Ref.: SRTS-1: KNL: SS-XIX: KNL-TVM-1:2014:

Date: 21.01.14

The Superintending Engineer


TLC Circle
APTRANSCO, Kurnool
Sir,
Sub:

Construction of 765 KV D/C Kurnool-Tiruvalam Transmission line Over head crossing


of 220kV and 132kV APTRANSCO lines Concurrence of APTRNSCO-Reg.

Kindly refer our earlier letter dated 23.04.13 vide which it was brought to your kind notice
about the construction of 765 KV D/C Kurnool-Tiruvelam line by POWERGRID & Power lines crosses
en-route. Further our Regional Engineering has communicated about the crossing lines and sought
concurrence from Chief Engineer, Construction-II, APTRANSCO vide letter dtd. 30.08.13.
We are thankful for the inspection report forwarded by your good office to C.E.(ConstructionII)APTRANSCO, Hydrabad vide letter reference no. SE/TLC Circle/KNL/F.765KV/D No. 1837/13 dtd.
18.11.13 for the following lines:
Sl.
No.
1
2

3
4

Name of HV Line of APTRANSCO


220 KV (D/C tower) SomayajulapalliKurnool near Chinnamshettipalli village
220 KV (D/C tower) Somayajulapalli-Gooty
near Chinnamshettipalli village

APTRANSCO Tower
Nos./crossing span
61-A & 60-B
226-A & 225-A

The following lines are yet to be inspected:


132 KV S/C Kurnool- Cement Nagar
near Bugganipalli village
132 KV S/C Nandyal-Banaganapalle near
Muthapalle vill

122 & 123


6A 6B

POWERGRID Tower
Nos./crossing span
Tower no. 5/3 (DD+9) & 6/0
(DD+25)
Tower no. 7/0 (DD+6) & 8/0
(DD+18)
Tower no. 11/0 (DD+6) &
12/0 (DD+18)
Tower no. 27/0 (DD+9) &
28/0 (DD+6)

In this regard we are submitting here with the revised profile of crossing no. - 4 above for your
kind perusal.
Required Electrical clearances (7.94 m) are being maintained at the above line crossings. It is
requested to kindly communicate the concurrence for said over head line crossings please. So that
POWERGRID can carry out the stringing works.
Thanking you,
Yours faithfully,
Enclrs. : As above.
(T.R.C.Murty)
Manager (TLC)

Copy to : Divisional Engineer(TLC), APTRANSCO, Kurnool:- for kind information pl.

Ref.: SRTS-1:KNL:SS-XIX:KNL-TVM-1:2013:

Date: 23.04.13

To
The Superintending Engineer
TL & SS Circle
APTRANSCO
Kurnool
Dear sir,
Sub: Construction of 765 KV D/C Kurnool-Tiruvelam Transmission line
Details of HV Power Line crossings Reg.

Please refer our earlier letter no. SRTS-1:KNL:SS-XIX:KNL-TVM-1:2013 dtd.


23.04.13 intimating about the crossing of various power lines of APTRANSCO by our new
765 KV D/C Kurnool-Tiruvelam line being constructed under System Strengthening XIX of
Southern Region as per the direction of Ministry of Power, Govt. of India vide Letter Ref No.
15/8/2011-Trans dtd. 18.01.2012.
The foundation & tower erection works of said line were completed at the crossing
towers of following lines and we are planning to carry out the stringing works at these
crossings as per the schedule given below:
Sl.
No.
1
2

Name of HV Line of
APTRANSCO
220 KV (D/C tower)
Somayajulapalli-Kurnool(Nannur)
near Chinnamshettipalli village
220 KV (D/C tower)
Somayajulapalli-Gooty near
Chinnamshettipalli village

APTRANSCO
Tower Nos.at
crossing span
61-A &
60-B
226-A &
225-A

POWERGRID
Tower Nos./
crossing span
Tower no. 5/3
(DD+9) &
6/0 (DD+25)
Tower no. 7/0
(DD+6) &
8/0 (DD+18)

Proposed dates of
stringing/
L.C. required

It is requested to kindly permit the stringing work at above crossings as per the
schedule given and issue necessary L.C. please.
Your kind consideration in this regard is highly solicited.
Thanking you,
Yours faithfully,
(TRC
Murty)
Manager

CC:
Divisional Engineer, TL & SS Division, APTRANSCO/Kurnool for kind information
please.

Ref.: SRTS-1: KNL: 400KV (LILO):2013:

Date: 14.12.13

The Superintending Engineer


TLC Circle
APTRANSCO, Kurnool
Sir,
Sub: Construction of LILO of 400 KV S/C Nagarjunasagar-Gooty Transmission line
at Kurnool Over head crossing of APTRANSCO EHV lines -Reg.
Power Grid Corporation of India Ltd (A Govt. of India Enterprise) and the Central
Transmission utility is entrusted to construct LILO of 400 KV S/C Nagarjunasagar-Gooty
Transmission line at Kurnool as a part of transmission System associated with Krishnapatnam UMPP
Part C1 as per the direction of Ministry of Power, Govt. of India vide Letter Ref No. 15/8/2011-Trans
dtd. 18.01.2012.
On completion of Detailed Survey of above line it is observed that the subject line crosses the
following EHV lines of APTRANSCO.
Sl.
No.
1
2
3

Name of HV Line of APTRANSCO


132 KV S/C Kurnool- Done line near
Lakshmipuram village
132 KV S/C Carbide Factory- Cement
Nagar near Nannur village
220 KV D/C Somayajulapalle -Nannur near
Nannur village

APTRANSCO Tower
Nos./crossing span
255 & 256
55 & 56
Tower no. 9 & 10

POWERGRID Tower
Nos./crossing span
Tower no. 5/5(DA+9) &
5/6 (DD+0)
Tower no. 16/0 (DD+18) &
16/1 (DA+9)
Tower no. 4/0 (DD+25
& 5/0 (DD+6)

Required Electrical clearances (>5.64 m) are being maintained while crossing the above lines
by our 400 KV line. Now the construction works are in progress and foundation works of said LILO
of 400 KV S/C Nagarjunasagar-Gooty Transmission line at Kurnool are commencing at crossings of
above APTRANSCO lines. This is for your kind information please.
Yours faithfully,
(T.R.C.Murty)
Manager (TLC),
Kurnool

Copy to :1).The Superintending Engineer, TL&SS Circle, APTRANSCO, Kurnool:- for kind
information pl.
2). Executive Engineer(TLC), APTRANSCO, Kurnool:- for kind information pl.
3). Divisional Engineer(TL&SS), APTRANSCO, Kurnool:- for kind information pl.
4). Divisional Engineer(O&M), APTRANSCO, Nannur:- for kind information pl.

Ref.: SRTS-1: KNL: 400KV (QUAD):2013:

Date: 14.12.13

The Superintending Engineer


TLC Circle
APTRANSCO, Kurnool
Sir,
Sub: Construction of 400 KV D/C (QUAD) Kurnool-Kurnool(APTRANSCO)
Transmission line Over head crossing of 220kV APTRANSCO line -Reg.

Power Grid Corporation of India Ltd (A Govt. of India Enterprise) and the Central
Transmission utility is entrusted to construct 400 KV D/C (QUAD) Kurnool (APTRANSCO)
Kurnool(POWERGRID) Transmission line as a part of transmission System associated with
Krishnapatnam UMPP Part C1 as per the direction of Ministry of Power, Govt. of India vide
Letter Ref No. 15/8/2011-Trans dtd. 18.01.2012.
On completion of Detailed Survey of above line it is observed that the subject line
crosses the following HV lines of APTRANSCO.
Sl.
No.

Name of HV Line of APTRANSCO

APTRANSCO Tower
Nos./crossing span

POWERGRID Tower
Nos./crossing span

220 KV (D/C tower) Kurnool(Nannur)


Brahmanakotkuru near Nannur village

Tower no. 9 & 10

Tower no. 4/0 (DD+25


& 5/0 (DD+6)

Required Electrical clearances (>5.64 m) are being maintained while crossing the
above lines by our 400 KV line. Now the construction works are in progress and foundation
works of said 400 KV D/C (QUAD) Kurnool (APTRANSCO) Kurnool (POWERGRID)
line are commencing at crossings of above APTRANSCO line. This is for your kind
information please.
Yours faithfully,
(T.R.C.Murty)
Manager (TLC)
Kurnool
Copy to :1).The Superintending Engineer, TL&SS Circle, APTRANSCO, Kurnool:- for kind
information pl.
2). Executive Engineer(TLC), APTRANSCO, Kurnool:- for kind information pl.

3). Divisional Engineer(O&M), APTRANSCO, Nannur:- for kind information pl.

Ref.: SRTS-1: KNL: SS-XIX: KNL-TVM-1:2013:


18.09.13

Date:

The Superintending Engineer


TLC Circle
APTRANSCO, Kurnool
Sir,
Sub: Construction of 765 KV D/C Kurnool-Tiruvalam Transmission line Over head
crossing of 220kV and 132kV APTRANSCO lines Concurrence of
APTRNSCO-Reg.
Kindly refer our earlier letter dated 23.04.13 vide which it was brought to your kind
notice about the construction of 765 KV D/C Kurnool-Tiruvelam line by POWERGRID &
Power lines crosses en-route. Further our Regional Engineering has communicated about the
crossing lines and sought concurrence from Chief Engineer, Construction-II, APTRANSCO
vide letter dtd. 30.08.13.
In this regard we are submitting here with the profiles of following line crossings for
your kind perusal.
Sl.
No.
Name of HV Line of APTRANSCO
1 220 KV (D/C tower) SomayajulapalliKurnool near Chinnamshettipalli village
2 220 KV (D/C tower) SomayajulapalliGooty near Chinnamshettipalli village
3 132 KV S/C Kurnool- Cement Nagar
near Bugganipalli village
4 220 KV S/C Dhone-Krishnagiri
near Mutthapalli village

APTRANSCO Tower
Nos./crossing span
61-A & 60-B
226-A & 225-A
122 & 123
6-A & 6-B

POWERGRID Tower
Nos./crossing span
Tower no. 5/3 (DD+9) &
6/0 (DD+25)
Tower no. 7/0 (DD+6) &
8/0 (DD+18)
Tower no. 11/0 (DD+6) &
12/0 (DD+18)
Tower no. 27/0 (DD+9) &
28/0 (DD+6)

Required Electrical clearances (7.94 m) are being maintained at the above line
crossings. It is requested to kindly communicate the concurrence for said over head line
crossings please. So that POWERGRID can carry out the stringing works.
Thanking you,
Yours faithfully,
Enclrs. : As bove.
(T.R.C.Murty)
Manager (TLC)

Copy to : Divisional Engineer(TLC), APTRANSCO, Kurnool:- for kind information pl.

Ref.: SRTS-1:KNL:SS-XIX:KNL-TVM-1:2013:

Date: 23.04.13

To
The Superintending Engineer
TL & SS Circle
APTRANSCO
Kurnool
Dear sir,
Sub: Construction of 765 KV D/C Kurnool-Tiruvelam Transmission line
Details of HV Power Line crossings Reg.
Power Grid Corporation of India Ltd (A Govt. of India Enterprise) and the Central
Transmission utility is entrusted to construct 765 KV D/C Kurnool -Tiruvelam Transmission
line under System Strengthening XIX of Southern Region as per the direction of Ministry of
Power, Govt. of India vide Letter Ref No. 15/8/2011-Trans dtd. 18.01.2012 (copy enclosed).
On completion of Detailed Survey of above line it is observed that the subject line
crosses the following HV lines of APTRANSCO.
Sl.
Name of HV Line of APTRANSCO
No.
1 220 KV (D/C tower) SomayajulapalliKurnool near Chinnamshettipalli village
2 220 KV (D/C tower) SomayajulapalliGooty near Chinnamshettipalli village
3 132 KV S/C Kurnool- Cement Nagar
near Bugganipalli village
4 220 KV S/C Dhone-Krishnagiri
near Mutthapalli village

APTRANSCO Tower
Nos./crossing span
61-A & 60-B
226-A & 225-A
122 & 123
6-A & 6-B

POWERGRID Tower
Nos./crossing span
Tower no. 5/3 (DD+9) &
6/0 (DD+25)
Tower no. 7/0 (DD+6) &
8/0 (DD+18)
Tower no. 11/0 (DD+6) &
12/0 (DD+18)
Tower no. 27/0 (DD+9) &
28/0 (DD+6)

Required Electrical clearances (7.94 m) are being maintained while crossing the
above lines by our 765KV line. Now the construction works are in progress and foundation
works of said 765 KV D/C Kurnool - Tiruvelam line are commencing at crossings of above
APTRANSCO lines. This is for your kind information please.
Thanking you,
Yours faithfully,
(TRC
Murty)
Manager
CC:
Divisional Engineer, TL & SS Division, APTRANSCO/Kurnool for kind information
please.

Ref.: SRTS-1:KNL:SS-XIX:KNL-TVM-1:2013:

Date: 23.04.13

To
The Superintending Engineer
TL & SS Circle
APTRANSCO
Kadapa
Dear sir,
Sub: Construction of 765 KV D/C Kurnool-Tiruvelam Transmission line
Details of HV Power Line crossings Reg.
Power Grid Corporation of India Ltd (A Govt. of India Enterprise) and the Central
Transmission utility is entrusted to construct 765 KV D/C Kurnool -Tiruvelam Transmission
line under System Strengthening XIX of Southern Region as per the direction of Ministry of
Power, Govt. of India vide Letter Ref No. 15/8/2011-Trans dtd. 18.01.2012 (copy enclosed).
On completion of Detailed Survey of above line it is observed that the subject line
crosses the following HV lines of APTRANSCO.
Sl.
Name of HT Line of APTRANSCO
No.
1 132 KV D/C RameswaramJammalamadugu near Kakarenipalli vill
2 220 KV D/C RTPP - Chinnakampalli
near Kalamalla village
3 220 KV D/C RTPP Yerraguntla
near Kalamalla village

APTRANSCO Tower
Nos./crossing span
42 & 43

POWERGRID Tower
Nos./crossing span
Tower no. 37/0 (DD+9) &
38/0 (DD+9)

8&9
9 & 10

Tower no. 44/5 (DD+25) &


45/0 (DD+25)

Required Electrical clearances (7.94 m) are being maintained while crossing the
above lines by our 765KV line. Now the construction works are in progress and foundation
works of said 765 KV D/C Kurnool - Tiruvelam line are commencing at crossings of above
APTRANSCO lines. This is for your kind information please.
Thanking you,
Yours faithfully,
(TRC Murty)
Manag
er

CC:
Divisional Engineer, TL & SS Division, APTRANSCO/Kadapa for kind information
please.

Вам также может понравиться