Академический Документы
Профессиональный Документы
Культура Документы
http : //www.cigre.org
B1-211
CIGRE 2012
SUMMARY
This paper includes a description of the development and experiences of the 400kV XLPE
cable and accessories. Type test and PQ test carried out with conductor cross section of
2500mm2. Applying for the electrical stress analysis, we can optimize insulation design of the
cable and accessories up to 500kV including safety factor.
The type test was started on January 2009 with cable bending test and successfully completed
on September 2009. To verify and to evaluate the long-term reliability and stability, we
continuously installed and tested 400kV cable system with accessories at KEMA test site. In
accordance with IEC 62067, PQ Test was completed satisfactorily at the renowned
independent third party certification authority (KEMA, Netherlands) on January 2011 without
encountering any problems. In addition, after completion of the 400kV test at the rated
lightning impulse test voltage, an additional lightning impulse test of 1550kV,
corresponding 500kV class, was executed and satisfied.
As we successfully completed the Type test and PQ test of the 400kV cable as well as
accessories, we are able to design more optimized 500kV cable and accessories with this
accumulated knowledge and experiences.
KEYWORDS
400kV - XLPE cable - Accessory - EHV cable systems - IEC 62067 - 2500mm2
Youngbum.Kim@iljin.co.kr
1. INTRODUCTION
Nowadays, the EHV cable systems for the underground have been developed up to the rated
voltages of 500kV and cross section up to 2500mm2. In order to keep up with the trend of the
power cable market, we have designed the 400kV cable system (cables and accessories), and
carried out the type test and prequalification test at KEMA laboratory in accordance with the
IEC 62067 specification.
After the type test completed successfully by the end of 2009, the prequalification test was
started from the December of 2009. The PQ test of the cable system that had undergone one
year (8,760 hours) heating cycle voltage test is comprised one porcelain outdoor termination
which is designed and optimized for the use of installation on site, one insulation joint for
tunnel which is protected with copper box, one insulation joint for direct buried, two GIS
terminations (back to back configuration) and one composite outdoor termination.
Throughout improved well-controlled manufacturing process and quality control, we
previously assured the test specimens for successful certification.
This paper shows the process of the test, characteristics of the test objects and the results of
the cable and accessories.
2. DESCRIPTION OF THE TEST OBJECT
2.1 Single-core Power Cable
* 220/400 (420) kV 1x2500 mm2 CU/XLPE/Corrugated AL/PE single core power cable
- Conductor :
copper, 1x2500 mm2 , Milliken construction
- Conductor Screen :
semi-conducting compound and tapes
- Insulation :
cross-linked polyethylene (XLPE)
- Insulation screen :
semi-conducting compound and semi-conducting swellable tape(s)
- Metallic screen :
corrugated aluminium
- Filling :
blown asphalt
- Oversheath :
polyethylene (PE ST7) with graphite coating
No.
Description
1
2
3
4
5
6
7
8
Conductor
Conductor screen
Insulation
Insulation screen
Watertightness
Metallic sheath
Bitumen layer
Oversheath
Thickness
(Nom.mm)
2.0
27.0
1.5
3.0
3.2
0.1
6.0
Diameter
(Nom.mm)
61.4
66.6
120.6
123.6
130.0
149.2
149.4
161.4
The type of the outdoor termination is the self-pressurized slip-on type stress relief cone
made from silicone rubber, so that it is no need extra compression devices for electrical
control. To cope with the global market competitively, we were successfully designed and
applied a compacted insulator after verifying the mechanical forces and electrical advantages
of it. The design processes is based on the mechanical and electrical calculations to meet the
demands of the site environmental basis. During designing, the electrical stress analysis is the
priority step for it. It means that a safety factor should be considering on designing process.
After manufacturing the insulator core with defined shape, the outer sheds are added a variety
of shapes and then finally fitting metallic flange are combined both top and bottom positions.
Therefore, new shape of insulator was chosen for its benefits regarding low weight, less
insulation filling compounds, smaller top and bottom flanges.
Figure 8. 400kV type test - Insulation joints for Annex D & main loop
Cross bonding system with an epoxy insulating barrier
Electrical control: stress relief cone made from silicone rubber
Compressing type connection
The joint consists of an one piece pre-moulded type insulation body made of silicone rubber
with an integrated field control electrode and two deflectors, protection box made from
copper alloy and insulating barrier made of epoxy resin for cross bonding system. The
insulating barrier is connected with protection box and this enables a cross bonding
arrangement of the cable screens to reduce induced screen currents and losses of the AC cable
system.
3. TYPE TEST
3.1 Type Test Arrangement
400kV cable and their systems is type tested according to the IEC 62067 standard in 2009.
The test has been carried out with conductor cross section of 2500 mm2.
The test loop consist of;
One porcelain outdoor termination, one composite outdoor termination, two SF6 Gas
Immersed Sealing Ends (in a back to back configuration) and one premoulded insulation joint.
4
The reference cable (so-called dummy loop) was cut from the total cable and was installed
close to the main loop in order to create the same environmental conditions as for the test loop.
Figure 9 shows the type test whole loop of the cable system and Figure 10. shows the
thermocouples connection of KEMA laboratory.
3.1.2 Conductor Temperature Measuring
During the heat cycling test, it is very important process how to determine the conductor
temperature which can affect the test process. To check the temperature, we usually ready for
a reference loop, separately. And then, drilling a hole through the insulation layer and be
contacted the thermocouple on the conductor. This contact should be maintained throughout
the whole test period. To make sure of this, we followed the KEMAs new method for the
conductor temperature measuring, see Figure 10. In short, to reach the conductor of a
reference loop, a small part of the outer sheath is taken out in order. After the conductor is
exposed, the thermocouples are fixed between the wires of the conductor. This method was
more recommended and confidence way than the previously one.
3.1.3 The Results of Type Test
400kV XLPE cable system including the Annex D of IEC 62067, test of outer protection for
buried joints, both electrical and non-electrical type tests were carried out successfully in
accordance with IEC 62067 specification at KEMA laboratory in 2009.
4. PREQUALIFICATION TEST
4.1 PQ Test Arrangement
The 400kV cable system of prequalification test was installed and arranged sequentially in an
outdoor test field at KEMA after all type tests successfully carried out. The metallic structures
were fixed on H-beam or conformable firm ground for use of the supporting the porcelain and
composite outdoor terminations.
The total cable length of the PQ was approximately 200m. The SF6 gas immersed sealing end
was installed back to back configuration in a ventilated steel-plate above the ground. Two
types of insulation joints were installed. One was installed in a ventilated underground
concrete tunnel and another was buried in ground. From efficiency viewpoint, the tunnel joint
was better to install and suitable to work.
5
Figure 15. shows the whole loop and arrangement of the PQ test cable system. The test
carried out in accordance with IEC 62067, clause 13;
After checking on the insulation thickness of cable for electrical prequalification test (clause
13.2.1 & 12.4.1), the PQ test consists of a heating cycle voltage test (clause 13.2.3), lightning
impulse voltage test on the cable sample (clause 13.2.4) and an examination of the complete
cable system (clause 13.2.5) was carried out in order of precedence.
4.2 The Results of Prequalification Test
4.2.1 Heating Cycle Voltage Test
The heating cycle voltage test was carried out from on December of 2009 to on December of
2010. In accordance with IEC 60060-1, clause 16.1.2, the required tolerance of the test
voltage is 3%, but it was well controlled by means of a computer application, which kept the
required test voltage within 374 5kV.
The duration of each heating cycle was 48 h and consisted of 16 h of heating with induced
current in the conductor, followed by 32 h of natural cooling. During each heating period, the
conductor at the hot-spot location reached a temperature of 92 within 14 h of heating.
ITEM
Value
374
Tolerance (kV)
5kV
Frequency (Hz)
50
Total duration of
voltage application
8,760 h
ITEM
Value
0 3700
16
32
at hot-spot location ()
92 (requirement:
90 95)
Duration of stabilizing
2 at 92 (h)
180
IEC 62067 Standard Power cables with extruded insulation and their accessories for rated
voltages above 150kV (Um=170kV) up to 500kV (Um=500kV) Test methods and
requirements 2006
AS 4436 Standard Guide for the selection of insulators in respect of polluted conditions
Edwin PULTRUM et al., New approach to measure conductor temperature during type test
Jicable (2007), paper A103
Jerome MATALLANA et al., 400kV 2500 mm2 XLPE Cable system prequalification and type
test for middle east evvironment Jicable (2007), paper A16