Академический Документы
Профессиональный Документы
Культура Документы
So you can easily see that being "mathematically ready" for your PMP Exam means
more than simply knowing your Earned Value formulas. Yes, you'll definitely see at least
one EV question on your exam but that's simply not all there is.
Many PMP aspirants find the concepts behind Earned Value Management (EVM) hard
to understand and the formula even harder, so that's where we are going to start.
First, let's define the term:
Earned Value (EV). The measure of work performed expressed in terms of the
budget authorized for that work.
PMBOK Guide
The thing that complicates it for many people is the question: "What on earth is value?"
For the Earned Value calculations you just have to remember that value equals money.
The total value of a project (in EVM terms) is equal to the budget of the project. As you
work through the project you spend the budget in order to achieve the project's
objectives, which in turn deliver business value. You can assess how much value you
have 'earned' (read: 'achieved') by knowing how far through the project you are and
how much you have spent.
The earned value management formulas are simply the calculations that give you the
data to work out the EV position on your project. There are 12 earned value
calculations in total.
Still not clear? You'll see what I mean with an example.
$60,000.
Plug those figures into the formula and we get 33% * $60,000 = $20,000. The earned
value of the project is $20,000.
There is no formula for PV. It's simply the approved budget for a task. You can use PV
for the budget of a phase, stage or work package. It's normally measured over a
particular time period.
One argument that I often get from my students is something along the lines of "I don't
see how SV is possible! I mean we are using numbers from the budget and you expect
me to believe that they help predict how I'm doing on the schedule??" It's not an
unreasonable argument. But it is indeed possible. For now I'm going to ask you to take
a leap of faith (I did when I originally came across SV) and I'll explain how it all works.
Let us begin with the formula:
The formula:
SV = EV - PV
just finished the 2nd month in the project and while the total project duration is 6
months; therefore consumed 33.33% of the time.
It seems that we are on track!
But wait a minute, what if the project was front-loaded? A front-loaded project requires
more resources and work at the front of the project in comparison to the end. In this
project we planned to complete 66.67% of the work in the first two months and very
few resources are involved in the last three months of the project. Although we have
consumed 33.33% of the time and the project is 33.33% complete, this is not good
since we should have completed 66.67% of the project according to our plan.
The EV of our fantastic new app development project is $20,000, as we saw earlier.
However, the Planed Value (PV) is $40,000 (66.67% of $60,000). In other words this
means according to our plan we should have completed $40,000 worth of work. Using
those numbers in the schedule variance formula we get $20,000 - $40,000 = -$20,000.
These are really simplified figures to help you understand the math more easily and
you can clearly see that this is bad news. Now we are starting to dig into the numbers
we can see that the project is running behind.
example, anyway...)
So what do we know about the project so far? It's not over budget or under budget,
but it is running behind. We thought we would have completed more activities as per
the plan by now so this is an early warning sign that the timescales for the project
might slip.
It's important to consider the context behind the numbers. Our company has never
delivered this kind of smartwatch app before, so we're learning as we go. Maybe that's
why we aren't making the progress we expected. Maybe one of the big mobile
platforms has taken longer than expected to get back to us about how to get our
product in their store. There could be lots of reasons that explain the numbers, so
when you're reporting the project's status to the sponsor, don't just rely on the
numbers to tell the story.
on the right things, but there's still more to uncover about how this project is
performing.
Challenge Yourself With a Really Hard CPI Sample PMP Exam Question
Click the image below to watch a video with a really hard CPI question. This one not
only requires you to identify the correct formula, but then you also have to adjust the
formula or you'll get the wrong result - tell us in the comments if you got it right or
wrong:
Youch. We are working at half the speed that we planned. This is where the project is
struggling! We had better stop doing project management formulas and start helping
our team get the work done! But before we leap into the To Do list, let's just check a
couple of other formulae.
Now you know that there is a CPI and an SPI. But what exactly is the difference? Find
the answer here...
helps you look forward and anticipate the difference between your original BAC and
the newly calculated EAC. In other words, it's the total cost we originally planned minus
the total cost that we now expect.
The formula:
VAC = BAC - EAC
That tells us there will be a negative variance of $10,000 by the time this smartwatch
app is developed. Our sponsor is going to want to know about that too.
The last bit of PMP mathematics we are going to do is to work out the TCPI. It's worth a
mention because it's one of the PMP exam formulas that people find most difficult.
TCPI is used to calculate the cost performance that must be achieved to hit your
budget (either BAC or EAC).
You can work out TCPI against your BAC or EAC. We know that the smartphone project
has already had the budget re-estimated once so it's best to use the latest figures.
We're going to use the EAC to work it out.
The formula:
TCPI = (BAC - EV) / (EAC - AC)
TCPI on our development project is 0.8. In order to get the intuition behind TCPI, let's
break the formula in two parts. The first part, BAC EV, indicates how much project
work is remaining, i.e., how much value remains that need to be achieved. The second
part, EAC AC, indicates the money available to finish the project. Hence, the TCPI
gives you the ratio of work that needs to be completed and the money available to
complete the project.
The smartwatch app project started off looking quite good but we had to re-estimate
the budget and we uncovered that we aren't getting through the tasks as quickly as we
need to. In fact, the amount of work to do is unlikely to get done in time if we only
apply the same amount of effort as we are now.
Thanks to the PMP cost management formulas we know a lot more about our project
now.
Phew! We made it through all the earned value management formulas. Here's a table
that summarizes all of that.
If you're creating a PMP formula sheet for your exam revision, there are a few more
calculations that you'll want to include.
= (Pessimistic - Optimistic) / 6
The larger the standard deviation, the greater the risk. The risk level on this task seems
OK but we can always take it to our sponsor for a second opinion.
understand.
Download our free PMP Formulas PDF Guide so that you've got all the data and
formulae to hand.
Another great way to practice is to do sample exam questions. This free batch of
sample PMP math questions will help you see where you need to build your skills.